Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Annals of the „Constantin Brancusi” University of Targu Jiu, Engineering Series, No. 3/2018
13
GROUNDING RESISTANCE MEASURMENTS AND CONTROL FOR WIND
GENERATORS
Georgi Tsonev Velev, Technical University of Gabrovo, Gabrovo, BULGARIA
Krasimir Marinov Ivanov, Technical University of Gabrovo, Gabrovo, BULGARIA
Petar Kolev Petrov, Technical University of Gabrovo, Gabrovo, BULGARIA
Adriana Foanene, University „Constantin Brȃncuşi” in Targu Jiu, ROMANIA
ABSTRACT: The paper inhere describes the measuring procedure and results for grounding
resistance audit and control in regard with wind generators having EMC problems, working at the
locality of “Buzludzha” in the “Stara Planina” mountain, owned by “VETROKOM” LTD.
KEY WORDS: wind generator, grounding (earth) resistance, grounding (earthing) system,
electromagnetic compatibility (EMC).
INTRODUCTION Until 2011 “Vetrokom” LTD, has installed
in the locality of “Buzludzha” in the “Stara
Planina” mountain 29 wind generators with
total installed capacity of 72,5 MW at an
altitude of 1490 m. The single aggregates are
with rated capacity of 2,5 MW each, having
their own step-up transformers in the gondola
with secondary rated voltage of 20 kV. Wind
aggregates have locally their own grounding
installations, around their foundations and are
connected electrically in groups of 4(or 5)
units by loop cable power line 20kV with
main step-up substation 20/110 kV. The
interconnection between the wind power
station and the transmission power grid has
been established by 9 km cable power line at
110 kV.
In 2017 “Vetrokom” LTD turned to the
Technical University of Gabrovo with a
request for support about EMC problems with
5 of their generators. Most of the problems
were related to frequent cases of damaged
power-electronic blocks, situated in the wind
turbine gondolas, after intensive lightning
activity. The first approach in the study was to
check grounding efficiency, having in mind
that the problem exists only with 5 of the
wind generators.
CHOOSING THE CORRECT
METHOD TO MEASURE
GROUNDING RESISTANCE OF
WIND TURBINES. The problematic wind turbines, intended
for the measurement procedure were with
numbers №725, №789, №797, №731 and
№736.
FL 725R1
R2
R3
R4
Power Cable 20 kV
Figure 1. Reinforced concrete foundation of
wind generators
Annals of the „Constantin Brancusi” University of Targu Jiu, Engineering Series, No. 3/2018
14
Each wind generator has four grounding
electrodes, connected in parallel (Fig. 1) with
earth resistances 1 2 3 4, , and R R R R .
Having in mind the large size of the wind
turbine steel-concrete foundation (a square
with side edge of 40 meters) and the lack of
any engineering plans of the wind turbines
grounding installation, the grounding
installation size was assumed to be treated as
an large-scale [2].
For large-scale grounding installations, the
generally used in practice “Fall of potentials
method” is not applicable, because it requires
extremely long cable leads covering the
required extended distance from the ground
electrode center to the current probe(200-
500m)[1,3-6,8].
Long distances to current probe results in
limiting the current injected through the earth,
and respectively to week voltage signal on the
potential probe. All that, combined with the
extremely high soil resistivity on site (around
2800Ω/m) leads to insufficient instrument
sensitivity.
In order to obtain accurate measurement
results the “Slope” method was chosen.
“SLOPE” METHOD BASICS
“Slope” method has been shown to give
reliable results, even when the soil is
nonhomogeneous.
It has been designed to eliminate the need
for impractically long leads by the ability to
interpolate the correct distance along the
combined resistance curve, i.e. the curve of
the current probe’s resistance superimposed
upon that of the tested grid, without sufficient
spacing to produce the characteristic “flat
portion” between [5, 6].
CD
0,2 CD 0,4 CD 0,6 CD
Potential electrocde
Current electrode
Grounding grid
PD
Figure 2. Set-up for the “Slope” method,
where PD - distance from grounding grid to
potential probe; CD - distance from grounding
grid to current probe;
Procedure consists of the following steps:
1. Earth tester is connected to the grounding
grid on convenient place;
2. Current probe is inserted at distance CD
from the grounding grid (normally 2 to 3
times the maximum dimension of the
system);
3. Potential probe are located consequently at
distances equal to 20% of CD , 40% of CD
and 60% of CD and measurements are
performed for every one of the cases. The
obtained resistances are RE1, RE2 and RE3
respectively.
4. The coefficient µ is calculated. It represents
the change of slope in the
resistance/distance curve.
3 2
2 1
E E
E E
R R
R R
(1)
5. From appendix 1, the respective value of
P
C
D
D is taken in regard with µ.
7. Since the distance to the current probe CD
is already known, a new value for
PD (distance to the potential probe) is
calculated.
PP C
C
DD D
D
(2)
Potential probe is relocated to its new
“Actual” position.
6. The actual grounding resistance is
measured for the new set-up, placing the
potential probe at its new distance PD .
7. Measurement procedure is recommended to
be repeated for other current probe distances
(larger values for CD ). Measurements are
assumed with sufficient accuracy when for
the different current probe distances the
results for earth resistance are stable.
MEASURMENT RESULTS FOR
WIND GENERATORS EARTH
RESISTANCE
The procedure described in the previous
chapter is used to calculate earth resistance
Annals of the „Constantin Brancusi” University of Targu Jiu, Engineering Series, No. 3/2018
15
for all of the wind generators that have been
under test. In details the intermediate
calculations are displayed only for Generator
№731 (table 1).
Table 1
Cu
rren
t p
rob
e d
ista
nce
DC
R1
( D
P =
0,2
.DC
)
R2
( D
P =
0,4
.DC
)
R3
(
DP
=
0,6
.DC
)
µ P
C
D
D
DP
_R
EA
L
RGR
m - - m 80 6,2 10,2 15,8 1,4 0,43 34,4 11,7
All results are summarized in Table 2, where
the real measured value for earth resistance of
each wind generator GRR is corrected by the
season coefficient , which takes an account
of the season in which the measurement is
performed (wet/dry) and the dimensions and
geometry of grounding electrodes used. For
each wind generator a comparison is made
between the measured earth resistance and the
norm regulated value by Bulgarian legislation
[3, 7].
Table 2
Win
d g
ener
ato
r №
:
RG
R
S
easo
n c
oef
fici
ent
RC
OR
=
φ
. R
GR
NORMR
Gro
un
din
g E
ffic
ien
cy
- - FL-725 28,9 1,3 37,5 30 NO
FL-789 21,3 1,3 27,6 30 YES
FL-797 - 1,3 - 30 NO
FL-731 11,7 1,3 15,2 30 YES
FL-736 5,35 1,3 6,96 30 YES
Protective earth resistance of wind turbine
№ 725 in wind farm “Vetrokom” does not
comply with standards [3] and [7]. The
single earth electrode 1R does not have an
electrical connection with the grounding
contour. The connecting bus-bar is probably
interrupted at the point of interconnection
with the grounding system, inside the
reinforced concrete foundation;
Protective earth resistance of wind turbine
№ 797 does not comply with standards [3]
and [7]. Single earth electrodes
1 2 3 4, , ,R R R R does not have an electrical
connection with the grounding contour. The
measured resistances for each of the earth
electrodes is in the order of kΩ -s. Wind
generator FL 797 is actually grounded only
via the lightning bus-bar and the grounded
armor of the power cable, through which the
machine is partially grounded to the earth
contours of the neighboring wind turbines in
series in the group.
ADDITIONAL STUDIES AND
RECOMMENDATIONS
For the period of audit and control, also
measurements in regard with soil resistivity
were made for the locality adjacent to wind
turbine FL 725 using Wener’s method.
In the surface soil layer with a depth of up
to 5 meters soil resistivity varies in the range
1500 – 5000Ω.m , which means that surface
soil layer is very inhomogeneous. For deep
soil layers (depth 10 m and more) soil
resistivity decreases and falls below
1000Ω.m . Measurements results were
processed in specialized software, and an
average soil resistivity of 2800 Ω.m was
obtained. Average soil resistivity was used for
further engineering calculations.
If an additional grounding system is
designed and built, which consists of
horizontal galvanized flat grounding bars with
standard dimensions of 40/4 mm, buried in
trenches at a depth of 1.5 m, according to the
diagram below (Fig. 3), grounding resistance
will comply with the prescriptions in
standards [3] and [7] about resistance to
ground in regard with the wind generators
with EMC problems ( 29,5 GRR ).
If the horizontal grounding bus-bar is
covered with a layer of loamy soil, earth
resistance will be further reduced to a value
of 23 GRR . Using a layer of loamy soil
will also enhance electrical contact of the
grounding bus-bar with surrounding soil.
Annals of the „Constantin Brancusi” University of Targu Jiu, Engineering Series, No. 3/2018
16
If horizontal bus-bar width is
increased 2 times, earth resistance will
become 9,8 GRR
tower
foundation
Grounding bus-bars
Grounding bus-bars
50 m 50 m
50
m5
0 m
Two layers of loamy soil
Soil from the site
Grounding electrode
Section of the earth conductor trench
1,5
m0
,25
m
0,2
5 m
0,5 m
Figure 3. Additional grounding system in
order to reduce grounding resistance
According to Fig. 3 the following procedure
must be followed:
1. Trenches with a depth of 1.5 m and a
width of 0.5 m are pre-excavated;
2. A layer of clay soil at the bottom of the
trench with a thickness of 25 cm is placed
and trampled;
3. Zinc-coated horizontal bus-bar is laid
down on it and a second layer of clay soil
with a thickness of 25 cm is placed,
which is also tramped.
4. The rest of the trench is filled with the
dredged soil and compacted.
The application of deep vertical
earthing electrodes by pre-drilling holes in the
soil will be difficult because of the stony
nature of the soil layer. In this case it will be
necessary to use additional low resistivity
materials to improve the soil resistance, which
in liquid form have to be poured into the
drilled hole after the vertical earth electrode is
placed in it in order to seal and improve the
contact of the electrode with surrounding soil.
Construction of vertical earth electrodes of
this kind would require large investments and
the results are not guaranteed;
Realization of additional grounding
systems will require more thorough
engineering calculations and design, as well
as additional field measurements of soil
resistivity at various locations at the region of
the “Vetrocom” wind farm.
CONCLUSIONS Wind turbines are connected by loop
power cable 20 kV in groups of 4 (5) power
unit. The metal screen of the power cable
connects electrically the metal towers of the
machines in the group to each other and to the
substation grounding system. Separately, the
power cable is protected from lightning by a
steel reinforcement along its length, which is
attached to the reinforced concrete structure
of the foundation of each machine at an
unknown point. These facts explain why the
most distant machines in the group have the
highest earth resistance, which is exceeding
the requirements. In fact, the nearby machines
to the substation and those along the power
cable line between two neighboring
generators are additionally partially grounded
by the grounding systems of neighboring
machines and the substation earthing system.
The last wind generators in the group due to
their high distance from the power substation
are only partially grounded only to the
previous machine;
In some wind turbines it was found
that bus-bars connecting the tower of the unit
with the local lightning protection grounding
electrodes are interrupted somewhere in the
machine steel-concrete foundation (for FL
797 the four connecting bus-bars do not make
a connection with the grounding system, thus
the machine is grounded only through the
earth systems of neighboring wind turbines
trough the lightning protection conductor of
the cable and its grounded screen. For FL 797
one of the connecting bus-bars has been
disconnected in the foundation). We assume
that the same problem may exist for other
wind generators also;
Since soil resistivity in the region as a
result of the rocky soil type is very high (with
average of 2800 Ω.m ), the local lightning
protection grounding resistance for some of
the aggregates do not comply with the 30
limit, as stated in Bulgarian standards [3, 7],
which seem to be the most liberal, compared
to other standards. For example in IEC
Annals of the „Constantin Brancusi” University of Targu Jiu, Engineering Series, No. 3/2018
17
61400-24 [4], earth resistance limit for
lightning protection of wind turbines is 10 ;
A reason for the high grounding
resistance measurement results in some of the
wind generators can also be found in the
imprecise dimensioning and technical
construction of wind generators’ grounding
systems and their elements and the reinforced
concrete foundation, since the grounding
system is built simultaneously with the
reinforced concrete foundation.
REFERENCES 1. IEEE Std 81-1983, “IEEE Guide for
Measuring Earth Resistivity, Ground
Impedance, and Earth Surface Potentials of a
ground system”, American National Standards
Institute, September 1984;
2. IEEE Std 80-2000, “IEEE Guide for Safety in
AC Substation Grounding”, IEEE-SA
Standards Board, January 2000;
3. Ordinance No 3 from 9 June 2004 for the
design of electrical systems and power
lines(Bulgarian standard);
4. IEC 61400-24:2010, Wind turbines - Part 24:
Lightning protection;
5. Megger, Getting Down to Earth - A practical
guide to earth resistance testing, 2010
6. Whitham D. Reeve, Principles and Practice of
Earth Electrode Measurements, Reeve
Engineers, 2008
7. Ordinance No 16-116 from 8 February 2008
for the Technical Operation of the Electrical
Energy Equipment (Bulgarian standard).
8. L.M. Cîrţînă, C. Militaru, C. Rădulescu, Study
of compensation errors due to temperatures, as
elements that are component of the chains of
dimensions formed at assembly,7th Youth
Symposium on Experimental Solid, Jurnal
Mechanics, 2008/5/14,Wojcieszyce, Poland
.
APPENDICES
Appendix A1. Dependence of the ratio P
C
D
D
on the coefficient µ