Upload
hector-perkins
View
215
Download
2
Embed Size (px)
Citation preview
IE450Models Relating Cycle-time, Throughput, WIP and Batch
Sizes
Planning manufacturing capacity
Dr. R. A. Wysk
Learning Objectives• To be able to name the most important factors that
contribute to the increase in the cycle time of a production system.
• To be able to explain the Little’s Law and its application to the operations of a production system.
• To be able to explain the fundamental relationship between resource utilization, cycle time and process and arrival variability in a production system.
Any Production System
Input Output
WIP
Resources
Any Production System
Input Output
WIP
Input = Output [– defects] (1st Law of Factory Physics)
WIP - Work-In-Process
Idle time - % of time a resource is not working
Any Production System
Input Output
Throughput – the average output per unit time (a rate)
Lead time – the time needed to process a part through a facility
Cycle time, flow time or sojourn time – the average time from release of a job to completion
Relating Throughput and WIP
One unit in WIP
Lead time ?
Idle time ?
Throughput?Assuming each process takes 1 minute.
Lead time ?
Idle time ?
Throughput?
More WIP (everything else the same) ...
More WIP - “keep all machines busy” ...
Lead time ?
Idle time ?
Throughput?
More WIP - diminishing returns ...
Lead time ?
Idle time ?
Throughput?
Active Exercise: Diminishing return?
At some point more WIP does not achieve anything except for longer lead times
Take 3 minutes to complete the following task.
Draw graphs relating WIP to throughput.
Relating WIP and ThroughputT
hrou
ghpu
t
WIP
100%
What is the limiting throughput?
A very useful relationship
• Little’s Law is a fundamental law of system dynamics
• Gives good results for a variety of scenarios
• Throughput (Units/time).
Example: A facility can produce 200 units per week, and the average lead time is 2 weeks. According to Little’s law the average WIP = 200 x 2 = 400 units.
Little’s Law:WIP = (Throughput) x (Lead Time)
Scenario 1: No Variability (Ideal World)Data and Calculations
Planning Horizon 30 hoursProcessing time 8 hour/unitInter-arrival time 10 hoursUtilization 80%Average queue time 0 hoursAverage lead time 8 hours
0 10 20 30
1st part processing
2nd part processing
3rd part processing
1st part arrives
2nd part arrives
3rd part arrives
1st part departs
3rd part departs
2nd part departs
8 18 28
Scenario 2: Processing VariabilitySCENARIO 1 2Planning Horizon 30 hours sameProcessing time 8 hour/unit 12, 9, 3Inter-arrival time 10 hours sameUtilization 80% sameAverage queue time 0 hours 1 hourAverage lead time 8 hours 9 hours
0 10 30
1st part processing2nd part
processing3
1st part arrives
2nd part arrives
1st part departs
3rd part departs
2nd part departs
12 21 2420
3rd part arrives
Parts waiting in queue
Same average !!!Same average !!!
Same utilization but . . .• More queue time
• More lead time
Scenario 3: Arrival VariabilitySCENARIO 1 2 3Planning Horizon 30 hours same as 1 same as 1Processing time 8 hour/unit 12, 9, 3 same as 1Inter-arrival time 10 hours same 13.5, 6.5Utilization 80% same as 1 same as 1Average queue time 0 hours 1 hours 0.5 hoursAverage lead time 8 hours 9 hours 8.5 hours
0 10
1st part processing
2nd part processing
3rd part processing
1st part arrives
2nd part arrives
1st part departs
3rd part departs
2nd part departs
8 21.5 29.520
3rd part arrives
Part 3 waiting in queue
Same average !!!Same average !!!
Again, same utilization but . . .
• More queue time
• More lead time
13.5
13.5 hours 6.5 hours
Scenario 4: Increased utilizationSCENARIO 1 2 3 4Planning Horizon 30 hours same as 1 same as 1 same as 1Processing time 8 hour/unit 12, 9, 3 same as 1 (2) + 1 hourInter-arrival time 10 hours same as 1 13.5, 6.5 same as 1Utilization 80% same as 1 same as 1 90%Average queue time 0 hours 1 hours 0.5 hours 2 hoursAverage lead time 8 hours 9 hours 8.5 hours 11 hours
0 10
1st part processing 2nd part processing 3
1st part arrives
2nd part arrives
1st part departs
3rd part departs
2nd part departs
13 23 2720
3rd part arrives
Parts waiting in queue
30
Increased utilization but …
• more queue time
• longer lead times
What would happen What would happen if the processing if the processing time variability is time variability is eliminated?eliminated?
Larger Batch Sizes
Example Summary
• Utilization alone is not sufficient to estimate the lead-time performance
• One must also consider the products arrival and processing variability.
• A mathematical model is needed to study the system.
SCENARIO 1 2 3 4Planning Horizon 30 hours same as 1 same as 1 same as 1Processing time 8 hour/unit 12, 9, 3 same as 1 (2) + 1 hourInter-arrival time 10 hours same as 1 13.5, 6.5 same as 1Utilization 80% same as 1 same as 1 90%Average queue time 0 hours 1 hours 0.5 hours 2 hoursAverage lead time 8 hours 9 hours 8.5 hours 11 hours
Questions??