54
February 4, 2007 Global Design Effort 1

ILC Interaction Region and Machine Detector Interface

  • Upload
    manchu

  • View
    32

  • Download
    1

Embed Size (px)

DESCRIPTION

ILC Interaction Region and Machine Detector Interface. Andrei Seryi, SLAC. representing BDS Area leaders Deepa Angal-Kalinin, Andrei Seryi, Hitoshi Yamamoto MDI panel and BDS team. Contents. - PowerPoint PPT Presentation

Citation preview

Page 1: ILC Interaction Region and  Machine Detector Interface

February 4, 2007 Global Design Effort 1

Page 2: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 2

Contents

• Will describe design of Beam Delivery System, focusing in particular on Machine Detector Interface aspects– IR hall and surface buildings– Detector assembly– Machine background– Design of IR and detector – IR arrangements for two detectors

Page 3: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 3

BDS layout

Page 4: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 4

IR hall region

Page 5: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 5

BDS beam-line layout

14mr IR

FF

E-collimator

-collim.

Diagnostics

Tune-up dump

BSY

Sacrificial collimators

Extraction

service tunnel

Muon wall

-2.2km

5m

Polarimeter

E-spectrometer

Page 6: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 6

BDS optics

Upstream polarimeter; & E –collimation ; Energy spectrometersare of particular MDI interest

IRlinac

Page 7: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 7

BDS parameters

Page 8: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 8

CMS assembly approach:• Assembled on the surface in parallel with underground work• Allows pre-commissioning before lowering• Lowering using dedicated heavy lifting equipment• Potential for big time saving• Reduces size of required underground hall

On-surface assembly of ILC detectorsCMS approach

Page 9: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 9

ILC Underground schedule

Earlier version of layout

Page 10: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 10

On-surface assembly of ILC detectors

• Adopted CMS on-surface assembly approach for ILC detector – This allows saving more than two years and

fitting into the goal of “7years until first beam” and “8years until physics run”

• CMS assembly and lowering the detectors parts in the hall is presently ongoing, according to the plan– Information and images on next pages are

courtesy of CERN colleagues Alain Herve, Martin Gastal, et al.

Page 11: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 11

CMS Assembly

Page 12: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 12

CMS Assembly

Page 13: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 13

CMS Assembly

Page 14: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 14

CMS Assembly

Page 15: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 15

CMS Assembly

Page 16: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 16

CMS Assembly

Page 17: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 17

CMS Assembly

Page 18: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 18

CMS Assembly

Page 19: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 19

CMS Assembly

February 1. Lowering down a 1200 ton barrel ring. Photo and info courtesy Alain Herve

Page 20: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 20

CMS Assembly

CMS is at half process. Next -- lowering 2kt central barrel by the end of February. Alain Herve

Lowering down a 1200 ton barrel ring

Page 21: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 21

Optimization of IR hall and assembly procedure

• For RDR, discussing possible variations of assembly procedure– pure and modified CMS assembly (configs. A and B

in the table on next slide)• Difference being how large pieces are assembled on surface

• Present RDR does not intend to finalize all the details for the schedule, hall sizes, capacity of cranes, etc.

• Optimization will be done in details by BDS, CF&S and Detector concept groups in EDR phase

Page 22: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 22

Table of IR assumptions

continued …

Page 23: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 23

… continued …

Page 24: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 24

Included in IR hall and surface buildings:

• IR hall: – detectors hall of 120x25x39m– service cavern 40x15x10m– finished civil engineering works, plus– movable concrete shielding wall in two parts (on air pads)– steel platforms with staircases and all fittings– two 1.6t elevators between steel platforms plus two 2.8t in shafts,– steel plates on the floor of the Hall– one 400t and two 20t overhead cranes in Hall– etc…

• Included in surface assembly building:– two assembly buildings 100x25x25m – 400t and 20t overhead cranes

• This choice can suite some detectors better than other (one size does not fit all) and may cause some concerns

• Further adjustments of IR hall and surface buildings will be done, in close connection with detector colleagues, during EDR phase

Page 25: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 25

IR surface area

Page 26: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 26

Next slides

• Will discuss– Machine background

• muons• Synchrotron Radiation• Beam-gas• Extraction line losses

– IR design • Detector Integrated Dipole (DID)• Antisolenoids

Page 27: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 27

polarimeterskew correction /emittance diagnostic

MPScoll

betatroncollimation

fastsweepers

tuneupdump

septa

fastkickers

energycollimation

betamatch

energyspectrometer

final focus

finaldoublet

IP

energyspectrometer

polarimeter

fastsweepers

primarydump

muon wall

BDS layout & possible sources of muons

clean-upcollimators

SP2 SP4

SPEX

Page 28: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 28

• Muon flux in BDS & IR with and without 5m muon wall

• Allows reducing flux in TPC to a few per ~100 bunches

5m wall

100

1

N.Mokhov et al., FNAL

Muon reduction

Page 29: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 29

Muon walls

5m muon wall installed initially

If muon background measured too high, the 5m wall can be lengthened to 18m and additional 9m wall installed(Local toroids could be used also)

• Purpose:– Personnel Protection: Limit

dose rates in IR when beam sent to the tune-up beam dump

– Physics: Reduce the muon background in the detectors

Page 30: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 30

Beam gas & SR in IR

• Beam gas– is minimized by controlling the

pressure near IP within 1nTorr level, 10nTorr in 200-800m from IP and ~50nTorr in the rest of the system

• SR in IR – due to upstream collimation is

contained within a defined cone which is extracted away

Example of SR rays from beam halo in IR aperturesF.Jackson, et al

Page 31: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 31

Extraction Lines

optionalhigh L parameters(500 GeV CM)

• Losses for the nominal case are negligible (~1W for 200m from IP)• Even for High L parameters is within acceptable levels• Small losses in extraction and separation from dump are important to keep the back-shine low

nominal parameters(500 GeV CM)

Y.Nosochkov, et al

Page 32: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 32

Anti-DID coils

-5 -3 -1 1 3 5m

Two overlapping Detector Integrated Dipole coils create field flattened in the IR region

Application of anti-DID to guide pairs to the exit hole

B.Parker, et al, BNL

Page 33: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 33

Antisolenoids

• Antisolenoids for local compensation of beam coupling

• Depend on all parameters (L*, field, sizes, etc) and is a delicate MDI issue

SiD with L*=4.5mLDC with

L*=4.5m

B.Parker, BNL

QD0

Example of optimal field for local compensation of coupling (SiD, L*=3.5m)

Page 34: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 34

Arrangements for two detectors

• IR design• Shielding• Moving the detectors• Services• Opening• Connections• etc

Page 35: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 35

IR conceptual design

Move with detector

Stay fixedWarm space

for vacuum valves for disconnect

Detector

B.Parker, et al, BNL

Page 36: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 36

Shield ONShield ON Shield OFFShield OFF

Intensity of color represent value of magnetic field.

Active shielding demonstration

IR magnet design

Actively shielded QD0

Page 37: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 37

Steel Yoke(no yoke for 4th)

Solenoid

HCal ECal

TPC orSi Tracker

Antisolenoid

Low ZMask

Vertex Detector IP Chamber

BeamCal

FD Cryostats

LumiCalDetectors

Generic Detector - IR Details

Working progressJohn Amann, et al

Page 38: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 38

Vertex Detector

IP Chamber

LumiCal Detectors

Beam Cal

Warm Beam Pipes

FD CryostatGroup 1

QD0

OC0

SD0

Valves for Push Pull

QDEX1

Space forFeedback Kicker

FD CryostatGroup 2

QFEX2

QF1

SF1OC1

Mask

Generic IR layout

Page 39: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 39

IR forward region and chambers

• Watch in study & design: – integration; support; assembly; wake-fields and EMI;

location of BPMs; vacuum & pumping; cold-warm transitions; etc.

Page 40: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 40

250mSv/h

Shielding the IR hall

Self-shielding of GLD Shielding the “4th“ with walls

Page 41: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 41

Working progress on IR design…

John Amann

3m Thickness

9m Base25m Height

Structural Rib

Overlapping Rib

Illustration of ongoing work… Designs are tentative & evolving

Mobile Shield Wall

Mobile Platform20m x 30m

Electronics/Cryo Shack1m Shielded

Page 42: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 42

Beamline shielding

Illustration of ongoing work… Designs are tentative & evolving

John Amann

Recessed Niche

Pac Man Open

Pac Man Closed

Beam Line Support Here

Page 43: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 43

Beamline shielding

Looking into experience of existing machines…

CMS shield openedCMS shield opened

pacman closedpacman closed

pacman openedpacman openedSLD pacman closedSLD pacman closed door tunneldoor tunnel pacman openedpacman opened

Page 44: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 44

Air-pads at CMS

Photo from the talk by Y.Sugimoto, http://ilcphys.kek.jp/meeting/lcdds/archives/2006-10-03/

• Single air-pad capacity ~385tons• Air-pads equipped with hydraulic jack for height adjustment & service• Lift is ~8mm for 385t units • Steel plates (~4cm) on the floor (compressed air 50bars)• Inclination of ~1% of LHC hall floor is not a problem • Last 10cm of motion on grease pads

[Alain Herve, et al.] 14kton ILC detector would require ~36 such air-pads

Page 45: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 45

Displacement, modeling

Idealized models

Short range deformation (~0.1mm) is very similar in both models.

Long range (1/r) deformation (~0.3mm) is not seen in ANSYS because too thin slab in the model

More details (3d shape of the hall, steel plates on the floor, etc.) to be included.

Long term settlement, inelastic motion, etc., are to be considered.

Parameters: M=14000 ton; R=0.75m (radius of air-pad); E=3e9 kg/m^2, n=0.15 (as for concrete); Number of air-pads=36

J.Amann, http://ilcagenda.cern.ch/conferenceDisplay.py?confId=1225

Analytic model, half-space

ANSYS model

Page 46: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 46

Hilman rollers is also a possibility

• For pre-determined path of motion for detector exchange, Hilman rollers may be suitable

• Standard capacity to 1kton• While not standard items, the 5kton capacity rollers have

been manufactured• Durability is important and to be studied

Contact Roll

Roller Chain Links5000 ton module will have 51 contact rolls in 3 rows of 17

Page 47: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 47

Other considerations

• Hydraulic jacks for adjustment• Drive systems• Guiding mechanism• Alignment, etc

Hydraulic Jacks/Shims

Screw type drive system

Page 48: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 48

Detector support

• Detector may have a supporting platform– size of IR hall increased to allow for this

Page 49: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 49

detectorB

may be accessible during run

accessible during run Platform for electronic and

services (~10*8*8m). Shielded (~0.5m of concrete) from five sides. Moves with detector. Also provide vibration isolation.

Concept of IR hall with two detectors

The concept is evolving and details being worked out

detectorA

Page 50: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 50

Concept of detector connections

fixed connections

long flexible connections

detectordetector service platform or mounted on detector

high V AC

high P room T Hesupply & return

chilled water for electronics

low V DC forelectronics

4K LHe for solenoids

2K LHe for FD

high I DC forsolenoids

high I DC for FD

gas for TPCfiber data I/O

electronics I/O

low V PShigh I PSelectronic racks4K cryo-system2K cryo-systemgas system

sub-detectorssolenoidantisolenoidFD

move together

Page 51: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 51

QD0 part QF1 part

doorcentral part

Need to be optimized for fast switch of detectors in push-pull and fast opening on beamline

This scheme may require lengthening L* to 4.5m and increase of the inner FD drift

Opening of detectors on the beamline (for quick fixes) may need to be limited to a smaller opening (MDI negotiation issue!) than what could be done in off-beamline position

Concept of cryo configuration

Page 52: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 52

Finishing up…

• Machine Detector Interface issues which require careful balance of very different constrains from Detectors and Machine– IR design, FD, support, connections, alignment– Detector design, opening, movements– Backgrounds, machine and beam related– Conventional facilities– Stability– Services– Radiation safety– etc

Page 53: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 53

Summary

• Interaction Region is a machine area where balance of design constraint from many groups is especially important

• The Beam Delivery Design group is looking forward to work on IR design together with Detector colleagues in the EDR phase of ILC

Page 54: ILC Interaction Region and  Machine Detector Interface

February 4, 07 Global Design Effort IR&MDI: 54

Thanks

• BDS design team• MDI panel• Detector colleagues• Push-Pull evaluation task-force• Colleagues from LHC, CERN• All colleagues involved in BDS & MDI work