    PROYEK AKHIR PU

    Perencanaan Pelaksanaan ProyekPengaspalan Jalan Bungadidi Poreang

    STA0+000 - STA1+500 Kab. Luwu Utara

    Prov. Sulawesi Selatan

    Pembimbing :

    Ir. Sulchan Arifin, M.Eng.

    Andi Bangsawang.L

    Dipresentasikan Oleh :

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    2/42

    Perencanaan Pelaksanaan Proyek Pengaspalan JalanBungadidi Poreang STA0+000 - STA1+500

    Kab. Luwu Utara Prov. Sulawesi Selatan

    BAB I PENDAHULUAN

    BAB II TINJAUAN PUSTAKA

    BAB III METODOLOGI

    BAB IV JENIS, VOLUME & METODE PELAKSANAAN PEKERJAAN

    BAB V RENCANA ANGGARAN BIAYA (RAB)

    BAB VI PERENC. & JADWAL KEGIATAN & SUMBER DAYA PROYEK

    BAB VII KESIMPULAN

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    3/42

    BAB I

    PENDAHULUAN

    LATAR BELAKANG

    Proyek pengaspalan jalan Bungadidi - PoreangKab.Luwu Utara Prov. Sulawesi Selatan dilaksanakan untukmeningkatkan mutu pelayanan jalan dengan merubah kondisijalan yang ada menjadi kondisi jalan yang mantap.

    Sebelum pelaksanaan pekerjaan dimulai, dibutuhkansuatu perencanaan yang betul-betul terencana dan matang agarmenghasilkanproyek yang efektif dan efisien.

    Sehubungan dengan hal tersebut maka kami mencobamemberikan alternatif perencanaan pelaksanaan proyektersebutdiatas dalamproyek akhir ini.

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    4/42

    PERUMUSAN MASALAH

    Permasalahanyang timbul dari latarbelakang di atas adalah :

    1. Bagaimana memperhitungkan Rencana Anggaran Biaya(RAB) yang dibutuhkan untuk penyelesaian proyek ?

    2. Bagaimana merencanakan kebutuhan bahan, peralatan

    dan tenaga kerja yang efektif dan efisien berdasarkankondisi dilapangan ?

    3. Bagaimana merencanakan jadwal pelaksanaan & sumberdaya proyek yang efektif dan efisien berdasarkan metode

    PDM ? ?

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    5/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    TUJUAN PENULISAN

    Dengan berlandaskan pada perumusan masalah, makatujuandari penulisan proyekakhir ini adalahsebagai berikut :

    1. Dapat mengetahui Rencana Anggaran Biaya (RAB) yangdibutuhkanuntukpenyelesaianproyek

    2. Dapat mengetahui kebutuhan bahan, peralatan dantenaga kerja yang efektif dan efisien berdasarkan kondisilapangan

    3. Dapat mengetahui penjadwalan kegiatan & sumber dayaproyek yang efektifdan efisien berdasarkanmetode PDM

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    6/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    BATASAN MASALAH

    Batasanmasalahdalampenulisan Proyek akhir ini adalah:

    1. Pengadaan material /bahanproyeksudahditerima diBase camp

    2. Mengingatketerbatasan waktu maka pada perencanaanini tidak membahas drainase dan gorong-gorong.

    3. kebutuhan tenaga kerja mengacu kepada PanduanAnalisa Harga Satuan Kementrian PU

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    7/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    TUJUAN

    Dengan adanya penulisan proyek akhir ini diharapkan dapat

    melatih mahasiswa untuk dapat mengerti dan mengatasipermasalahanyang timbul dalampelaksanaansuatu proyek..

    MANFAAT

    Dengan adanya penulisan proyek akhir ini diharapkan dapatmemberi manfaat kepada mahasiswa tentang prosesperhitungan RAB, kebutuhan bahan, peralatan, tenaga kerja,,dan penjadwalan kegiatan dan sumber daya proyek padasuatu proyek pengaspalan jalan.0

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    8/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    DATA PROYEK

    Adapun data proyek tersebut adalah :

    1. Nama Proyek : Pengaspalan J alan Bungadidi Poreang

    2. No. Kontrak : 043/17/22/SPP KONT/BM/DPU

    3. Volume : 1.500 m x 3,50 m

    4. Lokasi Proyek : Bungadidi Poreang Kec.Bone - BoneKab.Luwu Utara Prov. Sulawesi Selatan

    5. Kontraktor : PT. Kilat Karya Konstruksi

    6. Nilai Kontrak : Rp.783.637.000,-

    7. Sumber Dana : DAK dan APBD Kab.Luwu Utara

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    9/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    LOKASI PROYEK

    Lokasi proyek berada di ruas Bungadidi - Poreang Kecamatan

    Bone-bone Kabupaten Luwu Utara Provinsi Sulawesi Selatanseperti terlihat pada peta dibawah ini

    Lokasi Proyek

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    10/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    DETAIL LOKASI PROYEK

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    11/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    BAB II

    TINJAUAN PUSTAKA

    BIAYA PEMAKAIAN PERALATAN

    Biaya Pemakaian Peralatan terdiri dari :

    - Biaya Pemilikan (Biaya Pasti)Yaitu biaya penyusutan dan biaya pembayaran bunga atas nilai

    modal peralatan serta asuransi dan pajak

    - Biaya Operasi & Pemeliharaaan , terdiri dari : Biaya Bahan Bakar Biaya Pelumas Biaya Perbaikan & Perawatan Biaya Operator

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    12/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    PRODUKTIVITAS ALAT BERAT

    Produktivitas Alat adalah besarnya keluaran volume pekerjaantertentu yang dihasilkan alat per satuan waktu.

    Secara Umum Perhitungan Produktivitas alat Sebagai berikut :

    Q = q x N x E

    Dimana :Q = Produksi per jam dari alatq = Produksi dalam satu siklus

    N = J umlah siklus dalam satu jamN = 60Cm

    E = Efisiensi kerjaCm = Waktu Siklus dalam menit

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    13/42

    Adapun metode penyelesaian masalah dalamProyek akhir ini adalah :

    1. Pengumpulan DataData yang dikumpulkan terbagi atas dua bagian yaitua. Data Primer

    Data Primer berupa teknis pelaksanaan pekerjaan yang didapatkandari hasil pengamatandilapangan.

    b. Data Sekunder Peta Lokasi

    Gambar Cross Section Data J enis Pekerjaan Data Harga bahan, peralatan, dantenaga kerja.

    2. PerhitunganVolume PekerjaanTerdiri dari Perhitungan Volume pekerjaan Badan J alan, LPB Kelas C, LPAKelas B, Prime Coat dan Laston

    BAB III

    METODOLOGI

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    14/42

    3. Perhitungan Rencana Anggaran Biaya, dimulai dari :

    I. Harga satuan DasarII. Analisa Harga SatuanIII. Harga Satuan PekerjaanIV. Harga PekerjaanV. Estimasi Biaya proyek (OE/EE)

    4. Perencanaan dan Penjadwalan Kegiatan & Sumber Daya Proyek

    Perecanaan Kebutuhan Bahan Perencanaan Kebutuhan Tenaga Kerja

    Perencanaan Kebutuhan Peralatan J aringan Kerja (Network Planning) PDM Diagram Batang & Kurva S J adwal Kebutuhan Bahan J adwal Kebutuhan Tenaga Kerja J adwal Kebutuhan Peralatan

    1 T j P li1 T j P li

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    15/42

    1.Tujuan Penulisan1.Tujuan Penulisan

    DIAGRAM ALIR METODOLOGI

    Pengumpulan Data

    Data Primer Data Sekunder

    Volume Pekerjaan

    Perhitungan Rencana Anggaran Biaya

    Perhitungan dan Penjadwalan Kegiatan & Sumber Daya Proyek

    Kesimpulan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    16/42

    BAB IV

    JENIS, VOLUME & METODE PELAKSANAAN PEKERJAAN

    J enis Pekerjaan :1. Pekerjaan Persiapan

    Terdiri dari Mobilisasi dan Demobilisasi serta pengaturan Lalu-Lintas selama proyek berlangsung.

    2. Pekerjaan Penyiapan Badan J alanPekerjaan ini berupa penyiapan permukaan tanah dasar denganpemerataan dan pembentukan kemiringan untuk penyiapanmaterial perkerasan diatasnya.

    3. Pekerjaan Lapis Pondasi Bawah Kelas CLapis pondasi bawah adalah lapis konstruksi pembagi bebankedua yang diletakkan diatas lapisan tanah dasar yang dibentukdan dipadatkan. Agregat yang digunakan adalah agregat kelas Cyang terdiri dari kerikil danbatu pecahhalus.

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    17/42

    4. Pekerjaan Lapis PondasiAtas Kelas BLapis Pondasi atas adalah bagian dari konstruksi jalan yang

    terletak antara lapis pondasi bawah dan lapis permukaan jalan.Agregat yang digunakan adalah agregat kelas B yang terdiri daribatu kali danbatu pecahhalus.

    5. Pekerjaan Lapis Resap PengikatPrime Coat merupakan lapisan aspal yang digunakan pada

    lapisan permukaan yang belum beraspal dengan komposisicampuranterdiri dari 56 % aspal dan44 % minyak tanah.Lapisan ini bertujuan memberi daya ikat antara lapis pondasiagregatdengan campuranberaspal

    6. Pekerjaan LapisAspal Beton (Laston)Laston merupakan lapisan pada permukaan jalan yang terdiri darisejumlah agregat kasar, agregat halus, filler dan aspal semenyang dihasilkan dari instalasiAspaltMixing Plant (AMP).

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    18/42

    Volume Pekerjaan :

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    19/42

    VOLUME PEKERJAAN PENYIAPAN BADAN JALAN

    PANJ ANG LEBAR LUAS

    (m) (m) (m)

    STA

    0+000 - 1+500 1500 4,5 6750

    CL

    L = P X L

    L

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    20/42

    VOLUME PEKERJAAN LPB KELAS C

    PANJ ANG LEBAR TEBAL LUAS VOLUME

    (m) (m) (m) (m) (m)

    0+000 - 1+500 1500 4,50 0,10 6750 675

    V = P x L x T

    STA

    T

    L

    CL

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    21/42

    VOLUME PEKERJAAN LPA KELAS B

    PANJ ANG LEBAR TEBAL LUAS VOLUM E

    (m) (m) (m) (m) (m)

    0+000 - 1+500 1500 4,50 0,10 6750 675

    V = P x L x T

    STA

    T

    L

    CL

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    22/42

    VOLUME PEKERJAAN LAPIS RESAP PENGIKAT

    PANJ ANG LEBAR LUAS VOLUME(m) (m) (m) (Liter)

    0+000 - 1+500 1500 3,50 5250 0,50 2625

    STA LITER/M

    CL

    L

    V = P x L x LITER

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    23/42

    VOLUME PEKERJAAN LAPIS ASPAL BETON

    L = P x L

    PANJ ANG LEBAR LUAS

    (m) (m) (m)

    0+000 - 1+500 1500 3,50 5250

    STA

    L

    CL

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    24/42

    METODE PELAKSANAAN PEKERJAAN

    PENYIAPAN BADAN JALAN

    1. Motor Grader meratakan dan membentuk kemiringan melintangjalan sebesar 2 %

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    25/42

    PENYIAPAN BADAN JALAN

    2. Water Tank Truck menyiramkan air sejumlah 0,07 Liter/m padalokasi pekerjaan. Kemudian dilakukan pemadatan menggunakanVibrator Roller sampai didapatkepadatan CBR >5 %.

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    26/42

    METODE PELAKSANAAN PEKERJAAN

    PEKERJAAN LPB KELAS C

    1. Whell Loader memuat agregat ke dalam Dump Truck di Base

    Camp dan selanjutnya diangkut ke lokasi pekerjaan.

    Lokasi Pekerjaan

    Base Camp

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    27/42

    PEKERJAAN LPB KELAS C

    2. Agregat kemudian dihamparkan dan dibentuk kemiringannya(2 %) menggunakan Motor Grader

    Lokasi Pekerjaan

    3. Hamparan agregat kemudian dipadatkan dengan menggunakanVibrator Roller dan PTR hingga dihasilkan 100 % kepadatankering maksimum sambil disiram air sejumlah 0.07 Liter/mdengan menggunakan WaterTanker

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    28/42

    METODE PELAKSANAAN PEKERJAAN

    PEKERJAAN LPA KELAS B

    1. Whell Loader memuat agregat ke dalam Dump Truck di BaseCamp dan selanjutnya diangkut ke lokasi pekerjaan.

    Lokasi Pekerjaan

    Base Camp

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    29/42

    PEKERJAAN LPA KELAS B

    2. Agregat kemudian dihamparkan dan dibentuk kemiringannya(2%)dengan Motor Grader

    Lokasi Pekerjaan

    3. Hamparan agregat kemudian dipadatkan dengan menggunakanVibrator Roller dan PTR hingga dihasilkan 100 % kepadatankering maksimum sambil disiram air sejumlah 0.07 Liter/mdengan menggunakan WaterTanker

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    30/42

    METODE PELAKSANAAN PEKERJAAN

    PEKERJAAN LAPIS RESAP PENGIKAT

    1. Terlebih dahulu Permukaan dibersihkan dari debu dan kotorandengan Air Compressor

    Compressor

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    31/42

    PEKERJAAN LAPIS RESAP PENGIKAT

    2. Selama dalampekerjaan pembersihan berlangsung, aspal dan minyak tanah

    dicampur (perbandingan 56:44) dan dipanaskan dalam Aspal Sprayersehingga menjadi campuran aspal cair. Setelah mencapai temperatur 38 C- 93 C, campuran aspal cair disemprotkan dengan AsphaltSprayer ke ataspermukaanyang akandilapis.

    Asphalt Sprayer

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    32/42

    METODE PELAKSANAAN PEKERJAAN

    PEKERJAAN LAPIS ASPAL BETON

    1. Agregat dan aspal dicampur dan dipanaskan dalam AMP. Kemudian dimuatlangsung ke dalam Dump Truck dan diangkut ke lokasi pekerjaan

    Base Camp

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    33/42

    PEKERJAAN LAPIS ASPAL BETON

    2. Dump Truck kemudian menuangkan material Aspal ke dalamAsphalt

    Finisher lalu kemudian dihampar dan diratakan. Setelahpenghamparan kemudian dilakukan pemadatan awal denganTandemRoller sebanyak 1-3 Lintasan

    Material AsphalAsphal FinisherTandem Roller

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    34/42

    PEKERJAAN LAPIS ASPAL BETON

    3. Selanjutnya pemadatan antara dengan rentang waktu sekitar 5 -15

    menit setelah pemadatan awal dengan menggunakan PTRsebanyak 10 16 Lintasan. Kemudian Pemadatan akhir denganTandem Roller sebanyak 1 2 Lintasan dengan rentang waktu tidaklebih dari 45 menit sesudah penghamparan. Pemadatan inidilakukan untuk meningkatkanpenampakanpermukaan

    Pneumatic Tyre RollerTandem Roller

    Lokasi Pekerjaan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    35/42

    BAB IV

    RENCANA ANGGGARAN BIAYA

    Perhitungan anggaran biaya merupakan salah satu daribagian perencanaan proyek sehingga dapat diketahuialokasi biaya yang diperlukan untuk menyelesaikansuatu proyek.

    HARGA SATUAN DASAR ALAT

    Harga satuan dasar alat adalah keluaran dari analisa alatyang meliputi biaya pemilikan (biaya pasti) serta biaya

    operasi dan pemeliharaan.

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    36/42

    ANALISA HARGA SATUAN

    Didalam analisa harga satuan ini dilakukan perhitungan

    untuk menentukan koefisien bahan, upah tenaga kerja,dan peralatan setelah terlebih dahulu menentukanasumsi-asumsi dan faktor faktor serta prosedurkerjanya.

    Terdiri dari :1. Analisa Harga Satuan Penyiapan Badan J alan2. Analisa Harga Satuan LPB kelas C3. Analisa Harga Satuan LPA kelas B4. Analisa Harga Satuan Prime Coat5. Analisa Harga Satuan Laston.

    http://bab%20iv%20rab%20oke%21/Analisa%20Harga%20Satuan%20&%20Harga%20Satuan%20Pekerjaanhttp://bab%20iv%20rab%20oke%21/Analisa%20Harga%20Satuan%20&%20Harga%20Satuan%20Pekerjaanhttp://bab%20iv%20rab%20oke%21/Analisa%20Harga%20Satuan%20&%20Harga%20Satuan%20Pekerjaanhttp://bab%20iv%20rab%20oke%21/Analisa%20Harga%20Satuan%20&%20Harga%20Satuan%20Pekerjaanhttp://bab%20iv%20rab%20oke%21/Analisa%20Harga%20Satuan%20&%20Harga%20Satuan%20Pekerjaan
  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    37/42

    HARGA SATUAN PEKERJAAN

    Harga Satuan adalah harga suatu jenis pekerjaan tertentu persatuan tertentu berdasarkan rincian metode pelaksanaan yangmemuat jenis, kuantitas (koefisien) dan harga satuan dasar darikomponen bahan, peralatan dan tenaga kerja yang diperlukan dandidalamnya sudah termasuk biaya umum (Over Head) dan

    keuntungan.

    Terdiri dari :1. Harga Satuan Pekerjaan Penyiapan Badan J alan2. Harga Satuan Pekerjaan LPB kelas C3. Harga Satuan Pekerjaan LPA kelas B

    4. Harga Satuan Pekerjaan Prime Coat5. Harga Satuan Pekerjaan Laston.

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    38/42

    HARGA PEKERJAAN

    Harga pekerjaan tercantum dalam DaftarKuantitas dan Harga (BOQ) yang merupakanhasil perkalian dari Volume Pekerjaan denganHarga Satuan pekerjaan.

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    39/42

    ESTIMASI BIAYA PROYEK (OE/EE)

    Harga Total Pekerjaan diperoleh dari jumlahdari total harga pekerjaan ditambah dengan

    Pajak pertambahan nilai (PPN).

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    40/42

    BAB VI

    PERENCANAAN DAN PENJADWALAN

    KEGIATAN DAN SUMBER DAYA PROYEK

    Perencanaan Sumber Daya Proyek Perencanaan Bahan

    Perencanaan Tenaga Kerja Perencanaan Peralatan

    Penjadwalan Kegiatan & Sumber Daya Proyek PDM

    Diagram Batang J adwal Kebutuhan Bahan J adwal Kebutuhan Tenaga Kerja J adwal Kebutuhan Peralatan

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    41/42

    BAB VII

    KESIMPULAN

    Dengan terselesaikannya penulisan Tugas Akhir ini makaPenulis dapatmenyimpulkanbeberapa hal sebagai berikut :

    1. Rencana anggaran biaya yang diperlukan dalam proyekpengaspalan jalan ruas Bungadidi Poreang STA 0+000 s/d

    STA 1+500 Kab. Luwu Utara Prov. Sulawesi Selatan adalahsebesar Rp. 689.255.000,-

    2. Kebutuhan sumber daya proyek harus direncanakan denganmatang dan terencana agar didapatkan suatu proyek yang efektif

    danefisien

    3. J adwal kegiatan dan sumber daya proyek mengikuti waktupelaksanaan pekerjaan yang direncanakan yaitu selama 26 harikerja

  • 7/29/2019 ITS NonDegree 17136 3108038727 Presentation

    42/42

    Sekian dan Terimakasih