Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
July 2009
© Commonwealth of Australia 2010.
This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no part may be reproduced by any process without prior written permission from the Commonwealth.
Defence Publishing Service, Corporate Graphics – DEC009/09
Contents
Terminology & AbbreviATions ii
PrefAce & inTroducTion To The mAnuAl iii Objectives of the Manual III
What is Petroleum Hydrocarbon Contamination? III
Who Should Use the Manual? IV
What Information is in this Manual? IV
How to Use the Manual IV
Other Defence Guideline Documents IV
1. bAckground informATion & drivers 1 1.1 Defence Waste Management Hierarchy 1
1.2 Situations Where Soil Remediation or Management May Be Required 2
1.3 Status of Current Approaches to Remediation and Management 2
1.4 Regulatory Framework and Legislation 2
1.5 External Technical Support 2
1.6 Drivers for Remediation and Management Projects (Checklist 1) 3
2. consTrAinTs, endPoinT selecTion & soil/sedimenT chArAcTerisATion 4
2.1 Constraints 4
2.2 Endpoint Selection 6
2.3 Soil & Sediment Characterisation/Waste Classification 6
2.4 Soil / Sediment Remediation (Treatment) Requirements 9
3. AssessmenT & selecTion of remediATion or mAnAgemenT oPTions 10
3.1 Overview of Available Remedial Technologies 10
3.2 Remedial Options Screening Matrix 11
3.3 General Guidelines for Remediation and Management Options 13
3.4 Field Trials 14
4. vAlidATion And endPoinT 15 4.1 How do I validate and document that an endpoint has been reached? 15
4.2 What if the option selected does not achieve the desired end-point? 16
5. oTher informATion & key conTAcTs 17 Evaluation/Selection of Technologies 17
Other Relevant Information 17
figure index figure 1 summary of the remediation and management options decision Process iv
figure 2 remediation & management options decision Process v
figure 3 distribution of Acid sulfate soils Across Australia 8
figure 4 ex-site and in-situ remediation / management Approach 10
figure 5 health and environment risk Assessment model 14
APPendices A summary of state & Territory requirements 18
b remediation options facts sheets 21
c further references 29
d case studies & examples 31
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and SedimentsII
Section Title to go here
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments III
Terminology & Abbreviations
Terminology
Contamination – alteration of a natural matrices
(soil, sediment, surface water, groundwater or air)
so that the quality of the matrix, for human and
environmental ecologies, is decreased.
Petroleum Hydrocarbons – chemicals that
are made up of a series of carbon atoms and
can occur naturally or can be man-made.
Remediation – the treatment of a
contaminated material via physical, biological
or chemical processes.
AbbreviATions
ANZECC Australian and New Zealand Environment and Conservation Council
BTEX Benzene, Toluene, Ethyl-benzene and Xylene
CSR Contaminated Sites Register
DQO Data Quality Objective Defence Department of Defence
EO Exploded Ordinance
EPA Environment Protection Authority.
EPBC Act Environmental Protection and Biodiversity Conservation Act
LOR Limit of Reporting
NATA National Association of Testing Authority
NAPL Non-Aqueous Phase Liquid
NEPM National Environment Protection (Assessment of Site Contamination) Measure, 1999
NEPC National Environment Protection Council
PAHs Polycyclic Aromatic Hydrocarbons
PSH Phase Separated Hydrocarbon
QA/QC Quality Assurance/Quality Control
TPHs Total Petroleum Hydrocarbons
UST Underground Storage Tank
UXO Unexploded Ordnance
VOCs Volatile Organic Compounds
Preface & Introduction to the Manual
The Australian Department of Defence (Defence) National Contamination Team has developed this Manual for the Management and Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediment at Defence Sites. This Manual has been generated to provide Defence regional personnel and Defence maintenance contractors with practical information about the management and remediation (treatment) of petroleum hydrocarbon contaminated soil and sediment at Defence facilities.
The Manual has been developed to provide
general information and an overview of the
process used to select a management and/
or remediation option for contaminated soil/
sediment. For example you need to consider
the possible presence of other types of
contamination such as weeds, heavy
metals, other chemicals etc.
This manual is designed to assist in
determining the most appropriate management
of hydrocarbon contaminated soil and sediments
in line with industry practice and legislation. It is
a tool to support existing Regional and facility
based Defence Environmental Management
System processes.
It is designed to assist in determining the
most appropriate management of hydrocarbon
contaminated soil and sediments in line with
industry practice and legislation. It is a tool
to support existing Defence Environmental
Management System processes.
Before starting the process of assessing,
selecting and implementing a remedial/
management option for hydrocarbon
contaminated soil, users of the Manual must
consider the contaminated sediment or soil
in the wider environmental impact and safety
context. For example, petroleum, hydrocarbon
contaminated soil may also contain noxious
weeds, high levels of heavy metals or other
chemicals. Contact the Regional Environment
Officer to assist in undertaking a risk assessment
to determine the full range of Aspects and
Impacts under the applicable Regional or
Base Environmental Management Program.
The findings from this risk assessment will
provide a broader perspective on whether
the petroleum hydrocarbon contaminated soil/
sediment can remain on-site or be managed/
disposed of off-site.
objectives of the manual
The Manual aims to provide practical information
to manage petroleum hydrocarbon impacted
soil and sediment at Defence Base/Facilities so
that Defence capability can be maintained and
associated impacts to the environment mitigated.
What is Petroleum hydrocarbon contamination?
Petroleum hydrocarbons are chemicals made
up of a series of carbon atoms that can occur
naturally (e.g. coal and oil reserves) or can be
man-made (e.g. unleaded petrol or diesel).
When man-made petroleum hydrocarbons enter
the environment (e.g. from a tank leak or spill)
they can cause contamination that can pose a
risk to human health and the environment.
Although soil/sediment can be impacted by
a number of potential sources of petroleum
hydrocarbons, the petroleum hydrocarbons
addressed in this Manual are likely to be
associated with:
Fuel for ground-based vehicles, boats or •
aircraft (e.g. diesel, leaded and unleaded
petrol and aviation fuel); and
Oils, such as lubricants and degreasers, •
used in workshops or stored at facilities.
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and SedimentsIV Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments V
Who should use the manual?
The Manual was generated for use by Defence
relevant personnel and maintenance contractors
who require a practical reference point to assess,
select and implement a management and/or
remediation strategy for petroleum hydrocarbon
contaminated soil and/or sediment.
What information is in this manual?
The information provided in this manual includes:
The potential drivers and key considerations •
associated with the remediation (treatment)
and management options;
A process for assessing and selecting a •
remediation and/or management option;
General guidance for the construction •
and operation of four (4) remediation/
management options. General construction
and operational information is provided so
that specifications for the construction and
operation requirements for the remediation
and/or management option can be developed
once an option is selected; and
General guidance for the validation of the •
soil/sediment at the endpoint following
implementation of the remedial or
management strategies presented.
Soil Remediation & Management Drivers
Constraints (Logistics, Financial, Time)
Endpoint Selection
Soil Characterisation/Classification
Remedial/Management
Options Screening Matrix
EX-SITU REMEDIATION
1) DISPOSAL OFF-SITE
2) MANAGEMENT EX-SITU
4) MANAGEMENT IN-SITU
3) REUSE ONSITE
IN-SITU REMEDIATION
Section 1 – Background Information & Drivers
Section 4 – Validation & Endpoint
Section 2 – Constraints Endpoint Selection & Soil/Sediment
Characterisation
Section 3 – Assessment & Selection of Remediation &
Management Option Assessment
Figure 1 – Summary of the Remediation and Management Options Decision Process
how to use the manual
Figure 1 presents a summary of the processes to
follow in selecting a remediation or management
option and provides cross-references to the
appropriate sections in this Manual.
You are also referred to Figure 2, which
presents the full process required for selecting
a remediation and/or management option for
the site. Figure 2 presents the four stages of the
Remediation and Management Options Decision
Process, namely:
• Stage 1 – Background Information
& Project Drivers.
Stage 2• – Constraints, Endpoint Selection
and Soil/Sediment Characterisation.
• Stage 3 – Assessment & Selection of
Remediation & Management Options.
Stage 4• – Validation and Endpoint.
As represented in Figure 2, each section of
the Manual is aligned with one of these four
stages so that you have a reference point for
where you can locate the information required
to assess, select and implement a remediation
and/or management option.
other defence guideline documents
Defence has a number of other guideline
documents that may be of relevance to you which
are available form the EM webpage, including:
Defence (2004) • Underground Petroleum
Storage Systems, Management Guidelines for
Regional Environmental Officers;
Defence (2004) • Thin Guide:
Re-use of Contaminated Materials
for Environmental Officers;
Defence (2007) • Contamination Management
Strategy. Advancing Defence’s Contamination
Management Capability;
Defence (2007) • Pollution Prevention Strategy.
Advancing Defence’s Pollution Prevention
Capability; and
Defence (2007) • Contamination Risk
Assessment Tool
• Defence (2009) Management of Biosecurity
and Overabundant Native Species Risks on
the Defence Estate – National guidelines
• Defence (2009) Wash Down Facility
Design Features – Pamphlet
Defence (2009) Managing Weeds – Pamphlet•
Figure 2 - Remediation & Management Options Decision Process
sTA
ge
1 –
b
Ac
kg
ro
un
d &
d
riv
er
s
sTA
ge
2 –
c
on
sTr
Ain
Ts, e
nd
Po
inT
se
lec
Tio
n
& s
oil
se
dim
en
T c
hA
rA
cTe
ris
ATio
n
sTA
ge
3 –
A
ss
es
sm
en
T &
s
ele
cTi
on
of
re
me
diA
Tio
n &
m
An
Ag
em
en
T o
TPio
n
sTA
ge
4 –
vA
lid
ATio
n &
en
dP
oin
T
Drivers for Soil/Sediment Management & RemediationWhat are the Drivers for Soil/Sediment Manageent/Remediation?
Refer to Checklist 1
Has the contaminated soil/sediment been adequately characterised to progress to Stage 3 or Stage 4?
Refer to Checklist 3
Is soil/sediment treatment (remediation) required?
Refer to Checklist 3
Soil Characterisation/Classification– Chemical Composition– Physical Composition– Volume Estimation
Refer to Section 2.3
Validation– Waste Classification– Human Health & Ecological Assesment
Risk AssessmentHuman Health & Ecological Risk Assesment
Remediation Options Screening Matrix (ROSM)
4) MANAGEMENT IN-SITU
1) DISPOSAL OFF-SITE
2) MANAGEMENT EX-SITU
3) RE-USE ONSITE
Consider Project & Site Constraints– Logistics– Financial– Time– Sustainability
Refer to Checklist 2
Select Desired Endpoint– Disposal Off-site– Management Ex-situ– Re-use On-site– Management In-situ
Refer to Section 2.2
EX-SITU REMEDIATION IN-SITU REMEDIATION
Hold point 2
a) Landing Farming* b) Biopiling c) Containment d) In-situ Treatment e) No Action
Hold point 3
Table Notes * Depending on the type of contamination land farming may not be an option in some states.
Hold point 1
Hold point 1 + Hold point 2 Does the soil meet the appropriate waste classification (wast disposal) and/or HIL & EIL for reuse?
Hold point 3 Are the risks to human health and the environment acceptable for management in-situ?
Content • Exit • Print
2.
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments
Section Title to go here
1 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 2
Background Information & DriversSection Title to go here
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments1
1.
Background Information & Drivers
1.1 defence WAsTe mAnAgemenT hierArchy
With regard to waste management
Defence adopts the following strategy
to the management of waste:
Avoid; •
Reduce; •
Reuse; •
Recycle; and •
Dispose. •
Aligned with this waste management strategy,
Defence has a preference for the management
of impacted soil/sediment present at its facilities
in accordance with the following hierarchy:
Reuse On-site; •
Remediation On-site; and •
Disposal Off-site. •
With this strategy in mind, before starting the
process of assessing, selecting and implementing
a remediation/management option, users of the
Manual should consider:
• What activity or incident generated the
contaminated soil/sediment containing
petroleum hydrocarbons in the first instance?
Is there a measure that can be undertaken •
to avoid or minimise, the generation of the
contaminated soil/sediment?
This section is to present background information and outlines drivers for initiating a soil/sediment remediation/management project. This section is linked to Stage 1 (Background & Drivers) of Figure 2.
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 2
1.2 siTuATions Where soil remediATion or mAnAgemenT mAy be required
There are numerous sources and activities on
Defence facilities in which petroleum hydrocarbon
contaminated soil/sediment may have been
generated. Typically, petroleum hydrocarbon
contamination at Defence sites is associated
with man-made products such as:
Fuel for ground-based vehicles, boats or •
aircraft (e.g. diesel, leaded and unleaded
petrol and aviation fuel); and
Oils, such as lubricants and degreasers, •
used in workshops or stored at facilities.
Examples of activities and sources of
contaminated soil/sediment include:
Leaks and spills of fuels, or other products, •
from Underground and Above Ground
Storage Tanks (USTs and ASTs);
Leaks and spills during bulk transfer of •
fuels or other products;
General use and engine maintenance •
of vehicles, boats or aircraft;
Fire Training Activities or burning exercises; •
Disposal of waste fuels or fuel oils •
to landfills or other;
Sediment from wash down bay facilities; •
Sediment from clean out of stormwater drains;•
Soil excavated from removal of a leaking •
UST; and
Soil stockpiles from redevelopment •
of former industrial or road areas.
1.3 sTATus of currenT APProAches To remediATion And mAnAgemenT
The current approach to remediation and
management of petroleum hydrocarbon impacted
soil/sediment varies greatly across the Defence
regions and facilities. Limitations such as locality,
type and level of base activity and availability of
space and resources (or information) appear to be
the primary causes for the variations in approach.
Some of the current approaches include:
Excavation of soil/sediment and storage •
on site;
Excavation, characterisation/waste •
classification and disposal to landfill; and
Contaminated soil/sediment remains in-situ. •
A number of facilities have undertaken some
innovative and successful remediation and
management approaches. Contact the National
Contamination Remediation Program team for
a list of regional environment staff who have
undertaken these types of remediation projects.
1.4 regulATory frAmeWork And legislATion
The National Environment Protection Council
(NEPC) formulated the National Environment
Protection (Assessment of Site Contamination)
Measure (NEPM) in December 1999. The NEPM
provides a national risk-based framework with
human health and ecological investigation levels
for a set of defined land uses. The NEPM is the
primary document referred to by Defence.
There are no overarching federal guidelines for the
remediation of contaminated land. The States and
Territories of Australia have different requirements
and guidelines for the management and disposal
of contaminated soil/sediment.
Defence seeks to meet the “spirit and intent”
of the regulations and legislation of each State
and Territory in which it operates. Some States/
Territories have extensive regulatory requirements
(i.e. NSW and VIC), while other States/Territories
have relatively limited requirements and default
to other State regulations for guidance
(i.e. NT and QLD).
Although Defence is governed by
Commonwealth legislation and regulations,
the state regulatory framework becomes
particularly important with regards to:
Off-site Disposal – waste generated by
Defence is transported, treated, managed
or disposed of off-site. Any off-site activities
(including those of contractors engaged by
Defence to transport waste off its sites) must
comply with State legislative and regulatory
requirements. It is noted that these requirements
may vary between states; and
Off-site Migration – pending the regulatory •
framework of the state or territory, off-site
migration of contamination may trigger an
assessment of contamination, including a
health risk assessment.
A summary of the contaminated soil
management requirements of each State and
Territory is provided in Appendix A. Defence also
maintains a Legal Obligations Register (LOR)
which contains reference to relevant legislation
and regulations relevant to Defence. The reader is
encouraged to access the LOR to keep updated
with regard to the state regulatory framework for
remediation/waste disposal.
1.5 exTernAl TechnicAl suPPorT
As you work though the remediation and
management options decision process, presented
in this Manual and in Figure 2, there may be points
at which you require external technical support. To
assist you with the technical aspects of assessing,
selecting and implementing a remediation or
management option you may wish to contact:
The Defence National Contamination Team •
located in Canberra; and/or
A Defence regional personnel with experience •
in undertaking a remediation or management
project; and/or
A contaminated land consultant. •
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments3 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 4
Background Information & Drivers
Checklist 1 – Potential drivers for remediation and management Projects
drivers for remediation / management Projects Yes No Don’t Know
unacceptable risk to human health or the environment
1. Is the soil / sediment currently managed in a way that may pose an unacceptable risk to the health of human receptors a or a sensitive environmental receptor? b
For example if the soil / sediment is odorous, or corrosive, and is located within proximity to human and environmental receptors?□ □ □
2. Are there any cases of illness or health impairment among people who have had exposure to the contaminated soil / sediment? □ □ □
3. Is there the potential for contaminated soil / sediment to be acting as a source of contamination to the surrounding environment on-site? □ □ □
4. Is there the potential for, or any evidence of, migration of contaminants off-site to human receptors or the nearby environment? c □ □ □
5. Did an external consultant’s report identify the requirement to remediate or manage the contaminated soil/sediment? □ □ □
operational drivers
6. Has a FACOPS Risk Assessment been undertaken? (If yes go to Question 7). □ □ □
7. Did the FACOPS risk rating identify the contaminated soil / sediment as being a HIGH risk or above? □ □ □
8. Do you want to dispose of the contaminated soil/sediment off-site as part of base maintenance activities? d, e □ □ □
9. Do you want to reuse the contaminated soil/sediment on-site or elsewhere? f □ □ □
current management Approach to the storage of contaminated material
10. If the soil / sediment is ex-situ, is it currently stored (e.g. stockpiled) on an impermeable surface and with appropriate environmental controls? g □ □ □
11. If the soil / sediment is ex-situ, is it currently stored (e.g. stockpiled) in an area that is protected from large rainfall events or wind? □ □ □
Following the completion of Checklist 1 the drivers and key objective for commencing a management/remediation project should have been identified.
1.6 drivers for remediATion And mAnAgemenT ProjecTs (checklisT 1)
It is important to understand the drivers behind
why a soil/sediment management or remediation
project needs to be implemented. There are
many possible reasons for wanting to undertake
a soil/sediment management or remediation
projects including potential risk to human or
environmental receptors or operational reasons
(base housekeeping or environmental policy).
Checklist 1 is provided as a framework
to allow you to:
Identify the drivers for initiating the •
remediation and/or management project
in order to communicate them to your
stakeholders (for example in a business
case); and
Scope the objective of the project in •
order to communicate them to your
stakeholders (for example inclusion in a
remediation contractors scope of work).
There may be questions in the checklist
that require further information to answer.
You may wish to seek external technical
support (refer to Section 1.5).
Note Checklist 1 is not comprehensive and should be used as a guide only.
Table Notes a. Human receptors include Defence Personnel, contractors or visitors that may be located in buildings (residential, administration, workshops) or working out doors in areas adjacent
to the contaminated soil/sediment. b. Sensitive environmental receptors include creeks, rivers, ocean, wetlands or groundwater. c. Migration may occur via surface water run-off, groundwater or vapour.
d. Please note that waste classification will be required prior to disposal off-site. e. Please note that waste treatment may be required prior to disposal off-site. f. Please note that treatment may be required
prior to re-use. g. Environmental controls include, bunding and overhead protection if in a large rainfall region.
2.
Constraints, Endpoint Selection & Soil/Sediment Characterisation
The first part of Section 2 outlines the key initial considerations in selecting the remediation/management option, including the:
Potential project constraints; and •
Desired endpoint. •
Prior to the selection of a management or
remediation option it is important to consider
the desired end-points for the soil/sediment.
For example Do you wish to dispose of the soil/
sediment off-site or do you wish to manage the
material in-situ? These endpoint considerations
will set the context for the option you select.
The second part of Section 2 presents the
possible scenarios where soil sampling may be
required and an overview of the soil/sediment
characterisation and waste classification process.
This section is linked to Stage 2 (Constraints,
Endpoint Selection and Soil/Sediment
Characterisation) of Figure 2.
2.1 consTrAinTs
When selecting the most suitable remediation
or management option the following factors may
be considered:
Time• – the potential duration of time
associated with the implementation of
each option;
• Financial (Costs) – the potential costs
associated with the implementation of
each option;
• Logistical – the potential site specific
logistical constraints associated with the
implementation of each option;
• Regulatory – the relevant State and
Commonwealth requirements for the
possible management and remediation
options being considered;
Reputation• – the public perception/scrutiny
and media implications; and
• Sustainability Elements – the core elements
of sustainability.
Checklist 2 is provided to assist you in the
consideration of the potential constraints
associated with remediation / management
projects. You need to consider the likelihood
of factors such as time, financial (cost),
logistical and sustainability elements acting
as a project constraint. Potential constraint
factors should be revisited later in the options
assessment and selection process.
Note Checklist 2 is not comprehensive and is provided as a guide only.
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments5 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 6
Constraints, Endpoint Selection & Soil/Sediment Characterisation
Checklist 2 – Potential constraining factors for management / remediation Projects
factorlikelihood of constraint comment/mitigation measure
unlikely Possible likely
Time
Site permitting, regulatory requirements, stakeholder consultation □ □ □ Time Estimation
Preparation of tender documents (if subcontracted) □ □ □
Implementation of physical works □ □ □
Requirement for a small field scale trial a □ □ □
On-going management / monitoring and liability following implementation of physical □ □ □
Supervision of contractors and contract administration □ □ □
financial (cost)
Funding cycle
Purchase of capital infrastructure for remedial works □ □ □ Cost Estimation
Implementation of the option; consider the volume of soil requiring excavation, treatment, off-site disposal □ □ □
On-going operation b and monitoring c requirements □ □ □
logistical
Potential impact of physical works to Defence capability □ □ □ Time & Cost Implications
Accessibility of the site for plant and equipment □ □ □
Availability of resources to implement physical works □ □ □
Site suitability considerations (weather / seasonal conditions) □ □ □
Site suitability considerations (other)
For Example: a) Suitable geological conditions (soil –permeability and groundwater depth), b) Distance from sensitive receptors (air emissions, dust, noise and water discharge) c) Space to construct appropriate environmental controls d) Bio-security considerations e) Site Master Planning.
□
□
□
□
□
□
Distance of the site for to an appropriately licensed landfill □ □ □
Volume of soil/sediment (selection of an option commensurate with the volume of material) □ □ □
State or Commonwealth regulatory requirements (refer to Appendix A) □ □ □
reputation
Public perception / scrutiny □ □ □
Media implications □ □ □
sustainability elements d
Energy requirements □ □ □ High, Medium, Low
Air emissions (remedial equipment and treatment process) □ □ □
Water requirements and potential for impact on water resources □ □ □
Land and ecosystem impacts (e.g. soil and habitat disturbance) □ □ □
Material consumption and waste generation □ □ □
Long-term stewardship (e.g. intra and inter-generational equity) □ □ □
Following the completion of Checklist 2 you should have identified the possible factors that may constrain your proposed remediation/management
project and the mitigation measures for overcoming these constraints.
Table Notes a. Field Scale Trial – large volumes of waste soil/sediment or high degree of technical difficulty. b. On-going operational costs include the costs associated with operating soil treatment equipment, labour hours, and the cost of treatment reagents. c. On-going monitoring requirements are likely to be required if management in-situ is pursued as an end-point. Monitoring requirements may include groundwater, surface water, soil and vapour monitoring. d. The core sustainability elements are derived from the US EPA (2008) document titled Green Remediation: Incorporating Sustainable Practices
into Remediation of Contaminated Sites document released by the US EPA.
Constraints, Endpoint Selection & Soil/Sediment Characterisation
2.2 endPoinT selecTion
Once you have worked through Checklist 1
and 2 the desired project endpoint should be
considered. Examples of possible project end-
points are presented below:
1. Disposal Off-Site – disposal of the
contaminated soil/sediment off-site to an
appropriately licensed waste disposal facility.
Depending on the waste characterisation of
the soil/sediment, waste may be disposed
of off-site pre or post treatment. If treatment
of waste soil/sediment is required,
treatment may occur on-site or off-site at an
appropriately licensed premises, pending
approvals or other requirements by State
authorities. An example of an off-site disposal
project is presented in Appendix D;
2. Management Ex-situ (Storage) – the
storage of contaminated soil, once
excavated, in a dedicated long-term or
short-term storage area on or off-site in
a manner consistent with local regulatory
requirements. Storage may be a short-term
option or an option to be considered if a) the
soil/sediment treatment technology selected
is unsuccessful or b) immediate funding to
treat the soil/sediment is not initially available.
Having the available space and resources
to ensure waste segregation is achieved is
an important consideration when evaluating
this endpoint;
3. Reuse of Soil/Sediment On-site – re-use of
soil/sediment either at the site or elsewhere,
pending approval by the regulatory authority
(if required) and the suitability of materials
based on an assessment against human
health and ecological criteria (e.g. NEPM). If
treatment of contaminated soil is required it
may occur on or off-site at an appropriately
licensed premise. This end-point assumes
that the soil/sediment can be treated to a
quality (i.e. chemical and physical) suitable
for reuse in accordance with Defence and
State and Territory regulatory requirements.
An example of a soil/sediment re-use project
is presented in Appendix D; and
4. Management In-situ – the management
of impacted soil/sediment in-situ without
extensive excavation to remove the source.
This endpoint may be achieved via the
a) installation of a containment wall, b)
use of in-situ remedial techniques such
as bio-venting or c) if a risk assessment
finds the environmental and human health
risks acceptable. Management of residual
impacted soil in-situ may need to be
approved by the appropriate regulatory
authority and would require a site-specific
management plan.
The endpoint selected determines the scale
and duration of the project as the time, cost
and logistical implications, and regulatory
constraints, associated with each of these
endpoints varies greatly.
2.3 soil & sedimenT chArAcTerisATion/WAsTe clAssificATion
Once you have considered the possible end
points you should assess whether you have
adequate information and data to progress to
the next stage of the management or remediation
process (as presented in Figure 2).
Often further sampling is required. Further
sampling to characterise, or provide a waste
classification, for the soil/sediment should include
sampling and analysis for chemical and physical
parameters and an estimate of the volume of
material for management or remediation.
Due to the inherent uncertainty associated
with the subsurface (i.e. level and extent of
contamination) many remediation projects
run over budget and are delivered out of the
scheduled time frame. An inadequate intrusive
investigation is a common cause of budget and
schedule over-run in remediation projects. In order
to reduce uncertainty and control project costs
in remediation projects, a robust Stage 1 and
2 Investigation, where adequate contamination
characterisation and delineation has been
implemented is essential (refer to Appendix D
for a relevant case study).
Following the soil/sediment characterisation,
and/or waste classification, you should be in
a position to assess whether soil/sediment
remediation (treatment) is required.
2.3.1 do you have Adequate data?
Once you have considered the possible
end points you should assess whether you
have adequate data to progress to the next
stage of the management or remediation project
(as presented in Figure 2). Checklist 3 provides
prompts for assessing whether adequate soil/
sediment sampling and analysis has previously
undertaken to facilitate:
Selection of a treatment technology •
(refer to Stage 3 of Figure 2); or
Progression to an end-point, for example •
off-site disposal (refer to Stage 4 of Figure 2).
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments7 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 8
Constraints, Endpoint Selection & Soil/Sediment Characterisation
Checklist 3 is not comprehensive and is provided as a guide only.
checklist 3 – soil / sediment classification & characterisation indicators for soil / sediment classification & characterisation yes no
1. Visual Evidence of Contamination – are there any visual indications of chemical contamination on or in the soil/sediment and has adequate sampling/analysis been undertaken
to determine the cause of the visual impact? a □ □
2. Odours – are there any odours emanating from the soil/sediment and has adequate sampling/analysis been undertaken to determine the cause of the olfactory impact? b □ □
3. Potentially Contaminating Activities – what type of activity has caused the generation of the soil/sediment, and does the activity have the potential to have contaminated
the soil/sediment?
For example if the soil/sediment has been:
Generated from the removal of a UST, a vehicle wash down bay or a drain near a mechanical workshop, then there is a high likelihood that the soil/sediment •is contaminated; whereas
Excavated on a Greenfield site, or a site where little historic activity has occurred, then there may be a low probability that the soil/sediment is contaminated. •
□ □
4. Waste Soil from an Unknown Source – is the source of the soil / sediment known?
If the source of the soil / sediment is unknown then sampling and analysis of the material is advisable in order to assess the most appropriate option for the material. □ □
5. Waste Classification – has adequate sampling and laboratory analysis been undertaken of the soil/sediment to assess the chemical composition, and determine a
waste classification of the material?
The sampling and analysis requirements, in addition to the categories of waste, vary between the States/Territories. The State/Territory requirements are summarised in
Appendix A.
□ □
6. Reuse of Material – has adequate sampling and laboratory analysis been undertaken of the soil/sediment to assess the chemical composition to determine whether
the material is suitable for reuse on or off-site? (Refer to Section 4.1)
The land-use criteria (for human health and ecological protection) are provided in the National Environment Protection (Assessment of Contamination) Measure 1999.
□ □
7. If ex-situ remediation (i.e. excavation) is proposed, is there the potential for the soil/sediment to be Acid Sulfate Soils (ASS)?
Has any sampling been undertaken to confirm the absence or presence of ASS? (Refer to Section 2.3.3). □ □
8. Remediation/Management Parameters – has adequate sampling and laboratory analysis been undertaken to characterise the key chemical and physical parameters
of the soil/sediment to:
Assess whether specific soil/sediment remediation methods are appropriate; and •
Assess the suitability of the available management options (Monitored Natural Attenuation).•
□ □
A “No” response to the questions in Checklist 3
may indicate that further soil/sediment sampling
is required to characterise, or provide a waste
classification, for the material. Section 2.3.2
provides background information on what the
soil/sediment characterisation/classification step
generally involves.
2.3.2 chemical & Physical Parameters & volume estimation
It is important to assess the chemical and
physical characteristics of the soil/sediment,
and estimate its volume, to determine the
remediation or management option(s) available.
Soil/sediment characterisation and classification
typically involves:
Collecting a representative sample(s) •
of the soil/sediment;
Submitting the samples to an analytical •
laboratory for a suite of selected
chemicals; and
Comparison of the analytical results to •
the appropriate State or Federal waste
disposal regulations (refer to Appendix A)
and environmental/human health criteria
to determine whether treatment of the
soil/sediment is required to achieve the
endpoint selected.
The following national guideline documents
provide further information on the technical
requirements for soil/sediment sampling
and analysis:
National Environmental Protection •
(Contaminated Land) Measure (1999),
Guideline on Data Collection, Sample Design
and Reporting of Data;
National Environmental Protection •
(Contaminated Land) Measure (1999),
Guideline on Laboratory Analysis of Potentially
Contaminated Soils; and Standard (AS)
4482.1 (2005), Guide to the Investigation
and Sampling of Sites with Potentially
Contaminated Soil.
Chemical Composition
Sampling for chemical characterisation may
be undertaken to achieve three objectives,
namely to assess:
• Waste Classification – a waste classification
of the soil to facilitate off-site disposal;
Treatment Suitability• – information to assist
with an assessment of the potential for the soil
to be successfully remediate to achieve the
desired end-point; and
Table Notes a. Visual indications may include surface staining, vegetation dieback, sheen or product floating on surface or groundwater. b. Typical hydrocarbon odours include the smell of fuel,
oil and grease. Volatile chemicals can be dangerous to humans health and the environment and may require measurement and assessment by a qualified occupational health professional.
Constraints, Endpoint Selection & Soil/Sediment Characterisation
• Suitability for Re-use – assessment of the
soil/ sediment for reuse following excavation
and treatment. Further information on the
sampling and analysis requirements are
provided in Section 4.1.1.
Typically sampling and analysis for chemical
composition involves:
Collection of representative samples for •
the waste soil/sediment; and
Analysis for total concentrations (reported •
in mg/kg) and Australian Standard Leaching
Procedure (acetate buffer) (ASLP) analysis to
allow a waste classification to be generated.
Where petroleum hydrocarbons are the
contaminant of concern the following chemicals
are typically selected for laboratory analysis:
Total Petroleum Hydrocarbons (TPHs)• 1
fractions C6 – C9, C10 – C36;
Benzene, Toluene, Ethyl-benzene, •
Xylene (BTEX);
Polycyclic Aromatic Hydrocarbons (PAHs); •
Phenols; and •
Lead. •
A broader of sampling suite of potential
contaminants may be required to characterise
the soil/sediment if:
Little is known about the origin of the •
contaminated material;
The material appears to be mixed with •
other waste; or
The material appears to be comprised •
of multiple soil/sediment types.
The presence of other contaminants is an
important consideration as other contaminants
such as heavy metals, impact the effectiveness
some remediation options. A matrix of common
contaminating activities at Defence sites, and a
corresponding list of the typical contaminants
of concern (CoC), are included the report in the
Defence report titled Review of Environmental
Investigations2.
Physical Composition
Physical characterisation of the material is
particularly important for the evaluation of
remediation options. Generally sampling and
analysis for physical parameters includes:
Bulk density; •
Plasticity; •
Spadeablility (to identify material •
handling requirements if soil/sediment
is to be excavated); and
Composition (silt, clay, sand and gravel •
components) and consistency of the soil/fill.
Other parameters may be required for specific
remediation (e.g. bioremediation).
Volume Estimation
The quantity of contaminated soil/sediment
requiring remediation or management can have
significant cost and time implications. As part of
the soil/sediment characterisation process an
estimate of the soil volume should be undertaken.
For an accurate estimation of soil volumes you
may consider engaging a licensed surveyor.
The user of this manual may wish to seek
external support in order to undertake the soil/
sediment characterisation/classification works
(refer to Section 1.5).
2.3.3 Acid sulfate soils
Acid sulfate soils (ASS) are soils, sediments or
rocks that contain elevated levels of metal sulfides.
In an undisturbed and waterlogged state, these
soils are relatively harmless, but when disturbed
and exposed to oxygen (through excavation
or drainage), these soils can generate sulfuric
acid in large quantities. Runoff and leachate
from acid sulfate soils can adversely impact
aquatic communities, agricultural practices
and engineering works.
Acid sulfate soils are found along the
coastline throughout much of Australia.
It is estimated that there is approximately
40,000 km2 of coastal ASS.
Acid sulfate soils can be separated
into two categories:
Actual acid sulfate soils (AASS): Soil/sediment •
that has been oxidised and is generating
acid; and
Potential acid sulfate soils (PASS): Soil/•
sediment that contains metal sulfides, but
has not been exposed to oxygen (oxidised).
If acid sulfate soils are found to be present
(see table below), they should be managed
in accordance with Vic EPA publication 655,
Acid Sulfate Soil and Rock (1999), and Vic EPA
publication 680, Managing Waste Acid Sulfate
Soils (2000). Other references are provided
in Appendix D.
Further detail with regard to sampling, analysis
and classification of actual and potential acid
sulfate soils is provided in the references
presented in Appendix C.
1 If impacted soils are to be considered for re-use on or off the site, TPH speciation will be required in order to undertake an assessment for suitability for human health. Information with regard to TPH speciation is provided in Section 4.1.1.
2 A copy of the report Review of Environmental Investigations (Defence / SMEC 2007) is available at by contacting the National Defence Contamination Team-based in Canberra.3 Source National Strategy for the Management of Coastal Acid Sulfate Soils, January 2000.
Figure 3 – Distribution of ASS Across Australia 3
AUSTRALIA
Darwin
Perth
Adelaide
Proposed pyotic sediments
Melbourne
Hobart
Canberra
Sydney
Brisbane
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments9 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 10
Constraints, Endpoint Selection & Soil/Sediment Characterisation
2.4 soil/sedimenT remediATion (TreATmenT) requiremenTs
Treatment (remediation) of the soil/sediment
may be required based on the results of
the chemical and physical characterisation/
classification undertaken.
checklist 4 – Assessment of the requirement for soil / sediment Treatment soil / sediment Treatment requirements yes no 1. Waste Classification – if off-site disposal is your desired endpoint, does the material meet the appropriate waste classification to facilitate off-site disposal to an appropriately
licensed waste disposal facility? Note that disposal fee will vary with waste classification.
Refer to Appendix A – Summary of State & Territory Regulatory Requirements.
□ □
2. Reuse of Material – if re-use of material is the desired end-point, does the material meet the human health and ecological criteria.
Refer to Appendix A – Summary of State & Territory Regulatory Requirements. □ □
3. Management ex-situ – if management ex-situ (long-term storage / containment) is the desired end-point, does the physical and chemical composition of the soil / sediment make the material suitable for ex-situ containment options. □ □
4. Management in-situ – if management in-situ is the desired end-point, does the material meet the human health and ecological criteria for that land-due and are the risks associated with management in-situ considered acceptable.
Refer to Appendix A – Summary of State & Territory Regulatory Requirements.
□ □
A “No” response to the questions in Checklist 4 may indicate that soil/sediment treatment is required to achieve
the desired endpoint. If, based on the soil/sediment characterisation/classification, the material does not meet
the initially desired endpoint you should consider:
What remediation options are available to assist you in achieving your endpoint (refer to Section 3); and •
Other endpoints (refer to Section 2.2) that may be more suitable given the type and concentration •
of the contamination.
Checklist 4 is provided to facilitate
an assessment of whether treatment
(remediation) of soil/sediment may be
required to reach the desired end-point.
Please note that Checklist 4 is not
comprehensive and is provided as a
guide only. 3.
Assessment & Selection of Remediation or Management Options
The objective of Section 3 is to provide you with general guidance about the available remediation an/or management options and assist in the selection of the possible options using a screening matrix. Section 3 also provides general guidelines and indicative diagrams for the option selected.
This section is linked to Stage 3 (Assessment and
Selection of Remediation & Management Option)
of Figure 2.
3.1 overvieW of AvAilAble remediAl Technologies
Although there are many remediation
options/techniques available for the treatment
of hydrocarbon contaminated soils, for the
purposes of the Manual, five (5) remediation
options have been selected. The five options
include (but not limited to):
1. Land farming4;
2. Bio-piling;
3. Containment;
4. In-situ Treatment; and
5. No Action.
These five (5) options have been identified as most
appropriate for inclusion in this Manual based on
the following factors:
The type of chemicals expected to be •
associated with soil/sediment contaminated
with petroleum hydrocarbons at Defence sites;
Ease of implementation, proven effectiveness •
and track record of success on Defence sites;
System reliability and degree of operation •
and maintainability; and
Cost, time, logistical, regulatory, sustainability •
and community acceptance.
General information about the construction,
operation and maintenance of the five (5) options
for the remediation/management of petroleum
hydrocarbon contaminated soil/sediment is
provided in Section 3.3.
The five (5) options identified can be
broadly divided into options that require
excavation (ex-situ) and options that do not
require excavation (in-situ).
As illustrated in Figure 2, the three in-situ
approaches may need to be complemented with
a Human Health and Ecological Risk Assessment.
IN-SITU REMEDIATIONEX-SITU REMEDIATION
1) Landing Farming 3) Containment 4) In-situ Treatment2) Biopiling 5) No Action (Risk Assessment)
Figure 4 – Ex-situ and In-situ Remediation/Management Approach
4 Depending on the type of contamination land farming may not be an option in some states.
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments11 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 12
Assessment & Selection of Remediation or Management Options
3.2
re
me
diA
l o
PTi
on
s s
cr
ee
nin
g m
ATr
ix
The
Rem
edia
l Opt
ions
Scr
eeni
ng M
atrix
(RO
SM
) is
prov
ided
as
a to
ol to
ass
ist y
ou in
con
side
ring
the
stre
ngth
s an
d
wea
knes
ses
of th
e fiv
e op
tions
in th
e co
ntex
t of t
heir
site
-spe
cific
sce
nario
. The
RO
SM
has
the
follo
win
g fe
atur
es to
assi
st y
ou in
iden
tifyi
ng th
e m
ost s
uita
ble
optio
n:
Key
adv
anta
ges
and
disa
dvan
tage
s as
soci
ated
with
eac
h re
med
iatio
n/m
anag
emen
t opt
ion
for
you
to c
onsi
der;
•
Eig
ht c
riter
ia fo
r as
sess
ing
each
rem
edia
tion/
man
agem
ent o
ptio
n; a
nd
•
A r
atin
g fo
r ea
ch re
med
iatio
n/m
anag
emen
t opt
ion
agai
nst t
he c
riter
ia.
•
It is
not
ed th
at th
e cr
iteria
are
bas
ed a
roun
d th
e co
nstr
aini
ng fa
ctor
s se
t out
in C
heck
list 2
pre
sent
ed in
Sec
tion
2.1.
rem
edia
tion
op
tions
scr
eeni
ng m
atrix
(Ada
pted
from
the
US
EPA
(200
6) T
echn
olog
y S
cree
ning
Mat
rix)
re
me
diA
Tio
n /
m
An
Ag
em
en
T o
PTi
on
ke
y A
dvA
nTA
ge
sk
ey
d
isA
dvA
nTA
ge
s
Proven remediation / management method
degree of Technical difficulty
Time (relative)
cost (relative)
capital / infrastructure intensive
operation & maintenance
long-Term management requirements & liabilities
sus
tain
abili
ty
ele
men
ts
ex-siTu APProAch
1) L
and
Farm
ing1
E
ase
of im
plem
enta
tion
•
Rel
iabl
e an
d pr
oven
rem
edia
tion
optio
n •
Low
cos
t (re
lativ
e) to
und
erta
ke
•re
med
ial w
orks
Red
uctio
n in
on-
goin
g lia
bilit
y an
d •
futu
re m
anag
emen
t req
uire
men
ts re
lativ
e to
oth
er o
ptio
ns
Mai
nten
ance
of D
efen
ce c
apab
ility
•
in th
e lo
ng-t
erm
Gen
erat
ion
of w
aste
soi
l •
Def
ence
cap
abilit
y m
ay b
e im
pact
ed in
the
•sh
ort-
term
due
to la
rge
scal
e in
trus
ive
wor
ks
and
requ
irem
ent f
or la
rge
rem
edia
tion
area
for
cons
truc
tion
of li
ned
beds
/row
s
Em
issi
on o
f vap
our/
vola
tile
off-
gase
s•
Ene
rgy
Air
Em
issi
ons
Land
& E
cosy
stem
Mat
eria
l Con
sum
ptio
n
Was
te G
ener
atio
n
Long
-ter
m S
tew
ards
hip
2) B
io-p
iling
Rel
iabl
e an
d pr
oven
rem
edia
tion
optio
n •
Con
trol
of v
apou
r/vo
latil
e of
f-ga
ses
•
Rem
edia
tion
para
met
ers
(e.g
. moi
stur
e,
•nu
trie
nts,
and
tem
pera
ture
) can
be
cont
rolle
d
Red
uctio
n in
on-
goin
g lia
bilit
y an
d fu
ture
•
man
agem
ent r
equi
rem
ents
rela
tive
to
othe
r op
tions
Mai
nten
ance
of D
efen
ce c
apab
ility
•
in th
e lo
ng-t
erm
Mor
e in
frast
ruct
ure
and
cons
truc
tion
•re
quire
men
ts th
an la
nd fa
rmin
g
Mor
e ex
pens
ive
com
pare
d to
land
farm
ing
•
Gen
erat
ion
of w
aste
incl
udin
g so
il/se
dim
ent
•an
d va
pour
Pot
entia
l to
impa
ct o
n D
efen
ce c
apab
ility
•in
the
shor
t-te
rm d
ue to
larg
e sc
ale
intr
usiv
e w
orks
Ene
rgy
Air
Em
issi
ons
Land
& E
cosy
stem
Mat
eria
l Con
sum
ptio
n
Was
te G
ener
atio
n
Long
-ter
m S
tew
ards
hip
Assessment & Selection of Remediation or Management Options
in-siTu APProAch
3) C
onta
inm
ent
Lim
ited
gene
ratio
n of
was
te a
nd a
void
s w
aste
•
regu
lato
ry fr
amew
ork
for
off-
site
dis
posa
l
Rel
ativ
ely
shor
t dur
atio
n of
tim
e to
und
erta
ke
•ph
ysic
al w
orks
Red
uces
acc
essi
bilit
y to
con
tam
inat
ion
by
•hu
man
rece
ptor
s
On-
goin
g lia
bilit
y, m
onito
ring
and
•m
anag
emen
t req
uire
men
ts. R
isks
ass
ocia
ted
with
mai
ntai
ning
the
inte
grity
of t
he p
hysi
cal
cont
ainm
ent s
yste
m
Hig
h co
st o
f im
plem
enta
tion
rela
tive
•
to o
ther
opt
ions
May
requ
ire a
Hum
an H
ealth
and
•
Eco
logi
cal R
isk
Ass
essm
ent
May
impa
ct o
n D
efen
ce c
apab
ility
•
in th
e lo
ng-t
erm
Ene
rgy
Air
Em
issi
ons
Land
& E
cosy
stem
Mat
eria
l Con
sum
ptio
n
Was
te G
ener
atio
n
Long
-ter
m S
tew
ards
hip
4) In
-situ
Tre
atm
ent
Lim
ited
gene
ratio
n of
was
te a
nd a
void
s w
aste
•
regu
lato
ry fr
amew
ork
for
off-
site
dis
posa
l
Lim
ited
impa
ct to
Def
ence
cap
abilit
y
•in
the
shor
t-te
rm
Sys
tem
can
be
cont
rolle
d to
sui
t cha
ngin
g •
cond
ition
s an
d st
ages
of r
emed
iatio
n
On-
goin
g lia
bilit
y, m
onito
ring
and
•
man
agem
ent r
equi
rem
ents
Mos
t tec
hnic
ally
diffi
cult
optio
n to
•
impl
emen
t/in
stal
l
May
requ
ire a
Hum
an H
ealth
and
•
Eco
logi
cal R
isk
Ass
essm
ent
Ene
rgy
Air
Em
issi
ons
Land
& E
cosy
stem
Mat
eria
l Con
sum
ptio
n
Was
te G
ener
atio
n
Long
-ter
m S
tew
ards
hip
5) N
o A
ctio
n
(Ris
k A
sses
smen
t) N
o ge
nera
tion
of w
aste
and
avo
ids
was
te
•re
gula
tory
fram
ewor
k fo
r of
f-si
te d
ispo
sal
Lim
ited
impa
ct to
Def
ence
cap
abilit
y in
•
the
shor
t-te
rm a
s no
requ
irem
ent f
or
phys
ical
wor
ks
No
sign
ifica
nt p
hysi
cal w
orks
requ
ired
•
(i.e.
low
cos
ts)
Opt
ion
will
requ
ire a
det
aile
d H
uman
•
Hea
lth R
isk
Ass
essm
ent
On-
goin
g lia
bilit
y, m
onito
ring
and
•
man
agem
ent r
equi
rem
ents
May
impa
ct o
n D
efen
ce c
apab
ility
in th
e
•lo
ng-t
erm
term
as
cont
amin
ated
soi
l rem
ains
Ene
rgy
Air
Em
issi
ons
Land
& E
cosy
stem
Mat
eria
l Con
sum
ptio
n
Was
te G
ener
atio
n
Long
-ter
m S
tew
ards
hip
defi
nitio
n of
sym
bol
s an
d c
riter
ia in
the
rem
edia
tion/
man
agem
ent
op
tions
mat
rix
fAc
Tor
Ab
ove
Ave
rage
Ave
rage
bel
ow A
vera
ge
Pro
ven
Tech
nolo
gy /
Met
hod
Rem
edia
tion
optio
n is
est
ablis
hed
and
wid
ely
used
for
the
rem
edia
tion
of s
oil/s
edim
ent i
mpa
cted
with
pet
role
um h
ydro
carb
ons.
Rem
edia
tion
optio
n ha
s be
en im
plem
ente
d at
the
field
sca
le b
ut
has
varia
ble
succ
ess
in re
med
iatio
n so
il/se
dim
ent i
mpa
cted
with
pe
trol
eum
hyd
roca
rbon
s.
Rem
edia
tion
optio
n is
hig
hly
varia
ble
in th
e re
med
iatio
n of
soi
l /
sedi
men
t im
pact
ed w
ith p
etro
leum
hyd
roca
rbon
s.
Deg
ree
of T
echn
ical
Diffi
culty
Low
leve
l of t
echn
ical
diffi
culty
, with
rega
rd to
impl
emen
tatio
n, re
lativ
e to
oth
er o
ptio
ns.
Ave
rage
leve
l of t
echn
ical
diffi
culty
, with
rega
rd to
impl
emen
tatio
n,
rela
tive
to o
ther
pre
sent
ed.
Hig
h le
vel o
f tec
hnic
al d
ifficu
lty, w
ith re
gard
to im
plem
enta
tion,
rela
tive
to o
ther
pre
sent
ed.
Cos
tLo
w d
egre
e of
gen
eral
cos
ts re
lativ
e to
oth
er o
ptio
ns.
Ave
rage
deg
ree
of g
ener
al c
osts
rela
tive
to o
ther
opt
ions
.H
igh
degr
ee o
f gen
eral
cos
ts re
lativ
e to
oth
er o
ptio
ns.
Tim
e0.
5 –
2 ye
ars.
Tim
e to
impl
emen
t the
met
hodo
logy
and
rem
edia
te th
e so
il/se
dim
ent.
2 –
5 ye
ars.
Tim
e to
impl
emen
t the
met
hodo
logy
and
rem
edia
te th
e so
il/se
dim
ent.
Mor
e th
an 5
yea
rs. T
ime
to im
plem
ent t
he m
etho
dolo
gy a
nd
rem
edia
te th
e so
il /
sedi
men
t.
Cap
ital /
Infra
stru
ctur
e In
tens
ive
Low
deg
ree
of c
apita
l inv
estm
ent r
elat
ive
to o
ther
opt
ions
.A
vera
ge d
egre
e of
cap
ital i
nves
tmen
t rel
ativ
e to
oth
er o
ptio
ns.
Hig
h de
gree
of c
apita
l inv
estm
ent r
elat
ive
to o
ther
opt
ions
.
Ope
ratio
n &
Mai
nten
ance
Inte
nsiv
eLo
w d
egre
e of
ope
ratio
nal a
nd m
aint
enan
ce re
quire
men
ts re
lativ
e to
ot
her
optio
ns.
Ave
rage
deg
ree
of o
pera
tiona
l and
mai
nten
ance
requ
irem
ents
rela
tive
to o
ther
opt
ions
.H
igh
degr
ee o
f ope
ratio
nal a
nd m
aint
enan
ce re
quire
men
ts re
lativ
e to
ot
her
optio
ns.
Long
-Ter
m M
anag
emen
t R
equi
rem
ents
and
Lia
bilit
ies
Low
leve
l of o
ngoi
ng m
anag
emen
t req
uire
men
ts a
nd o
n-go
ing
liabi
lity
rela
tive
to o
ther
opt
ions
.M
ediu
m le
vel o
f ong
oing
man
agem
ent r
equi
rem
ents
and
on-
goin
g lia
bilit
y re
lativ
e to
oth
er o
ptio
ns.
Hig
h le
vel o
f ong
oing
man
agem
ent r
equi
rem
ents
and
on-
goin
g lia
bilit
y re
lativ
e to
oth
er o
ptio
ns.
Sus
tain
abilit
y E
lem
ents
Low
leve
l of 1
) ene
rgy
use,
2) a
ir em
issi
ons,
3) i
mpa
ct to
land
and
ec
osys
tem
s, 4
) mat
eria
l con
sum
ptio
n, 5
) was
te g
ener
atio
n or
6)
long
-ter
m s
tew
ards
hip
(i.e.
inte
r/in
tra-
gene
ratio
nal e
quity
) is
sues
rela
tive
to o
ther
opt
ions
.
Ave
rage
leve
l of 1
) ene
rgy
use,
2) a
ir em
issi
ons,
3)
impa
ct to
land
and
eco
syst
ems,
4) m
ater
ial c
onsu
mpt
ion,
5)
was
te g
ener
atio
n or
6) l
ong-
term
ste
war
dshi
p (i.
e. in
ter/
intr
a-ge
nera
tiona
l equ
ity) i
ssue
s re
lativ
e to
oth
er o
ptio
ns.
Hig
h le
vel o
f 1) e
nerg
y us
e, 2
) air
emis
sion
s, 3
) im
pact
to la
nd a
nd
ecos
yste
ms,
4) m
ater
ial c
onsu
mpt
ion,
5) w
aste
gen
erat
ion
or 6
) lon
g-te
rm s
tew
ards
hip
(i.e.
inte
r/in
tra-
gene
ratio
nal e
quity
) iss
ues
rela
tive
to
othe
r op
tions
.
Mat
rix
Sym
bols
A
bove
Ave
rage
A
vera
ge
Bel
ow A
vera
ge
N
ot a
pplic
able
.
Con
ten
t •
Ex
it •
Pri
nt
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments13 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 14
Assessment & Selection of Remediation or Management Options
3.3 generAl guidelines for remediATion And mAnAgemenT oPTions
This section provides general information
once you have considered your site in the
context of the information presented in the
ROSM and identified which option(s) may be
applicable. For each remediation/management
option where physical works are required,
general information is provided:
General construction considerations; •
Operational considerations including; •
General maintenance and performance –monitoring considerations;
Environmental management and –occupational health and safety considerations; and
End point parameters. For the No Action (Risk
Assessment) option, general information with
regard to the risk assessment process is provided.
The information presented in this section
is aims to:
Give the users of this manual general •
information with regard to the construction
and operation requirements of the options
available; and
Act as a generalised template to be used •
as a basis for Defence regional personnel
in developing site-specific requirements for
Defence CMC contracts for implementation
of the option.
3.3.1 land farming
Land farming involves the application of
excavated contaminated soil or sediment in a
thin layer across the ground. Minerals, nutrients,
moisture and air are then added to the thin
layer of contaminated soil (usually via tilling or
ploughing) to stimulate microorganisms, which
use hydrocarbons as a food source and convert
them to carbon dioxide and water. For further
information on land farming as a remedial
technique, refer to the Land Farming Remediation
Factsheet in Appendix B. It is important to note
that land farming may not be applicable in certain
case (e.g. close to residential area) and that it is
not acceptable by some EPAs in Australia
(e.g. NSW, Vic).
3.3.2 biopiling
Biopiling involves the placement of contaminated
soil or sediment into a stockpile, which has
parameters such as moisture, nutrients and
oxygen controlled to stimulate microorganisms,
which use hydrocarbons as a food source and
convert them to carbon dioxide and water.
For further information on biopiling as a remedial
technique, refer to the Biopiling Remediation
Factsheet in Appendix B.
3.3.3 containment
Containment involves the construction of a
physical barrier in the ground to prevent the
migration of contaminated soil, sediment and
groundwater away from the source zone.
Containment is generally used as a short
term measure while remedial techniques are
being considered or as a long term measure in
combination with other remedial techniques. For
further information on containment as a remedial
technique, refer to the Containment Remediation
Factsheet in Appendix B.
3.3.4 in-situ Treatment – bioventing
Bioventing is a mechanical means of remediation
in which oxygen is delivered to contaminated,
unsaturated soils by forced air movement (through
injection of air) to increase oxygen concentrations
and stimulate biodegradation of contaminants
in the subsurface. For further information on
bioventing as an in-situ remedial technique,
refer to the Bioventing Remediation Factsheet
in Appendix B.
3.3.5 no Action (risk Assessment)
The no action (or risk assessment) option
may be an appropriate in-situ management
method no unacceptable risk to human heath
and the environment is determined following
a risk assessment.
What is Risk Assessment?
A risk assessment is an appraisal of
the nature and magnitude of the human
health and/or ecological risks associated
with chemical contamination at a site.
A risk assessment considers:
Site-specific factors such as the existing/•
proposed land use and on-site/off-site
occupants;
Physico-chemical and bioavailability •
characteristics of particular contaminants;
Depth and distribution of the chemical •
contamination; and
Potential exposure setting for the possible •
human and ecological receptors.
What Does a Risk Assessment Involve?
Typically, a risk assessment is undertaken by an
external technical consultant who is a specialist
in the field of risk assessment. Risk assessments
are often a multi-disciplinary task and require input
from a range of professions so the risk assessor
must have access to, and be able to coordinate
inputs from multiple disciplines (NEPM 1999).
There are four main components of a risk
assessment:
1. Hazard Identification and Data Collection –
acquisition and analysis of data from the
site that may affect human health or the
environment. This may involve a review
of the site history, local geological and
hydrogeological regime, potential on-site and
offsite receptors, nature and extent of the
site contamination and evaluation/collection
Assessment & Selection of Remediation or Management Options
of data from the installation of soil bores,
groundwater monitoring wells and vapour
sampling bores;
2. Toxicity Assessment – examines the
possible effects of the chemicals of
potential concern on human health and
the environment, and is used to assess the
levels of exposure that could give rise to
adverse effects. The toxicity assessment
considers the:
Nature of adverse effects related; –
Dose-response relationship for various –effects;
Weight of evidence for effects such –as carcinogenicity; and
Relevance of animal data to humans –(NEPM 1999).
3. Exposure Assessment – documents
the selection of potentially exposed
populations and exposure pathways
used in estimating the potential health risks
arising from exposure to the chemicals of
potential concern. The exposure assessment
examines the frequency, extent and duration
of exposures in the past, currently and in
the future.
4. Risk Characterisation – the purpose
of the risk characterisation is to combine
the results of the toxicity assessment (i.e.
the potential for health effects) with the
predicted exposures to determine whether
the chemicals of potential concern pose
an unacceptable health risk and therefore
what measures need to be taken to reduce
the risk. The risk assessment process is
depicted in Figure 5.
When a Risk Assessment Can Be Used
A risk assessment may be used:
To determine whether contamination poses •
an unacceptable risk for a given scenario,
existing or proposed (eg. A site development);
To develop site-specific remediation •
targets; and
To assess the adequacy of control •
measures for in-situ management of
contamination (eg. containment).
3.4 field TriAls
Once a remediation or management option has
been identified you may consider undertaking
a field trial of the option, or options, selected.
Field trials are typically undertaken to assess the
performance of the proposed remediation method
prior to committing time and resources to a full
scale remediation project.
Some key considerations when planning a remediation field trial include:
• Size and Scope of Trial – the size and
scope of the trial should be commensurate
with the volume of soil/sediment proposed
for treatment. Where a large soil/sediment
remediation project is proposed, undertaking
an initial field trial can result in significant cost
and time savings in the future;
• Trialling Multiple Remediation Options –
depending on the volume and composition
of the soil/sediment, a number of remediation
options may be considered suitable for
achieving the desired end-point. In this
scenario undertaking a field trial to assess
the performance of a number of remediation
options can result in significant cost and time
savings in the future; and
Figure 5 – Health and Environment Risk Assessment Model
HAZARD IDENTIFICATION
site characterisation• nature and extent •of contaminationpotential to cause harm•data evaluation•
RISK CHARACTERISATION
likelihood of effects occurring•
uncertainty•
summarise and communicate•
EXPOSURE ASSESSMENT
receptor groups (land use)•contamination releases•exposure pathways•exposure concentrations• estimates of contaminant •intake
TOXICITY ASSESSMENT
possible effects•
acceptable intakes•
carcinogens vs non-carcinogens•
ecological criteria•
• Design of Field Trial – when designing a field
trial you will need to consider similar elements
to a full scale trial. It is important to prepare a
Field Trial Plan which sets out:
Environmental risks (e.g. discharge to –environment) and controls (e.g. bunding);
Human heath risks (e.g. vapour emissions) –and controls (e.g. location of field trial and vapour capture and control);
Sampling requirements and –frequency monitoring of the soil/sediment during the implementation of the remediation trial; and
Proposed duration, and desired endpoint, –of the trial.
For large remediation projects, where
field trials are applicable, it is common for
Defence personnel to seek external technical
support (refer to Section 1.5) for assistance
in the selection of remedial options and the
implementation of field trials.
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments15 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 16
4.
Validation & Endpoint
As discussed in Section 2.2, following the implementation of remediation/management of petroleum hydrocarbon contaminated soil/sediment, four potential endpoints are possible, these include:
Off-site disposal; •
Management ex-situ; •
Reuse of treated soil/sediment on-site; and •
Management in-situ. •
The validation requirements for each of these end
points vary based on whether an in-situ or ex-situ
remediation/management approach is selected.
This section is linked to Stage 4 (Validation &
Endpoint) of Figure 2.
4.1 hoW do i vAlidATe And documenT ThAT An endPoinT hAs been reAched?
4.1.1 ex-situ remediation/management Approach endpoints
When an ex-situ remediation/management
approach has been adopted validation of
the approach needs to be undertaken to
assess whether soil/sediment disposal off-site
or re-use can occur. To validate the success
of the treatment, representative soil samples
need to be collected and analysed for the key
chemicals of concern.
Soil/Sediment for Reuse
If treated soil/sediment are proposed for re-use
on-site, representative sample(s) of the material
should be collected and submitted to an analytical
laboratory for analysis of:
Total concentrations of the key contaminants •
of concern; and
(If necessary) a suite of chemicals set out •
in the National Environmental Protection
(Assessment of Site Contamination) Measure
Schedule B (1) Guideline on the Investigation
Levels for Soil and Groundwater (referred to
as the NEPM suite).
Depending on state or territory (refer to
Appendix A) you may also consider selecting
samples for ASTM neutral leach analysis to assess
the potential for treated soil/sediment to leach
contaminants when exposed to precipitation.
Validation & Endpoint
TPHs Speciation for Assessing Suitability for Reuse
In order to assess soil/sediment for reuse,
TPHs specification for aromatic and aliphatic
composition is recommended. Unless specifically
requested, analysis for TPHs is likely to be
reported as undifferentiated TPH fractions, namely
TPH C6 – C9, C10 – C14, C15 – C28, C29 – C36.
These fractions exhibit very different health and
ecological risk properties making it extremely
difficult to produce health and ecological risk
profiles that accurately model the effect of the
hydrocarbon contamination on human health and
the environment. The speciation of TPHs into the
aliphatic and aromatic fractions however, allows
use of criteria established in the NEPM of these
compounds, If a sample contains high levels
of TPHs but no identifier compounds (such as
volatile organic compounds) then speciation of
the TPHs should be undertaken to determine the
aromatic and aliphatic composition. The current
NEPM Health Investigation Levels (HILs)5 use the
aromatic and aliphatic composition to determine
human health risk. Based on the nominated land
use, the appropriate NEPM Health Investigation
Level should be adopted. Concentration of the
aromatic and aliphatic compounds below the
adopted HILs is suitable for reuse on site.
Soil/Sediment for Off-site Disposal
If treated soil/sediment is proposed for off-site
disposal (a) representative sample(s) of the
material should be collected and submitted to
an analytical laboratory and selected for total
concentration and Toxicity Characteristic Leaching
Procedure (TCLP) or Australian Standard Leaching
Procedure (ASLP) of the contaminants as required
by the State or Territory waste regulations
(refer to Appendix A).
4.1.2 in-situ remediation/ management Approach endpoints
Where in-situ remediation/management
is undertaken, in order to achieve a management
in-situ end-point, a Risk Assessment may be
required to assess whether following remediation,
an unacceptable risk to human health or
environment exists. Information with regard
to the Risk Assessment process is provided
in Section 3.3.5.
If an in-situ remediation/management approach
is undertaken it is likely that future monitoring
and management of the contaminated soil/
sediment may be required. On-going monitoring/
management may include regular:
Visual inspections of the integrity of the wall •
or capping (if containment is pursued);
Groundwater monitoring to assess the •
potential for the condition of the groundwater
at the source site to have changed; and
Vapour monitoring to assess the potential •
for vapour to be emanating from the site.
The presence of an in-situ contamination impact
should also be included in site management plans
(e.g. Environmental Management Plan (EMP) or
Contamination Management Plan). By updating
site management plans with this information:
The location of the contamination can
be communicated to Defence personnel
or contractors working at the site; and
Requirements for regular monitoring
can be documented and serve as a trigger
for undertaking monitoring.
4.2 WhAT if The oPTion selecTed does noT Achieve The desired end-PoinT?
If the selected remediation/management
approach is not successful in achieving the
desired endpoint you may consider:
Adjusting the selected remediation option •
to optimise the treatment approach/method;
Returning to the Remediation Options •
Screening Matrix (Section 3.2) to reconsider
the available options; and
Reconsidering the key constraints (Section •
2.1) and desired endpoint (Section 2.2).
5 It is noted that the current NEPM HILs are under revision may change in 2010.
Content • Exit • Print
2.
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments
Section Title to go here
17 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 18
5.
Other Information & Key Contacts
If you have any questions or require further information with regard to the contents of this manual please contact a representative from the Defence Contamination Team, located at Brindabella Park, Canberra Airport, ACT, on (02) 6266 8058.
A list of Defence Regional personnel who
have experience in remediation of petroleum
impacted soil / sediment can be made available
by contacting the Defence Contamination Team.
Appendix A
Appendix ASummar y of State & Territor y Requiremnts
summAry of sTATe & TerriTory requiremenTs
This section provides an overview of the remediation / waste disposal regulatory framework for each state. It is noted that environmental and waste
regulations/legislation are dynamic and this section should be reviewed annually to ensure its’ contents is still relevant.
Defence maintains a Legal Obligations Register (LOR) to provide a system for identifying potential legal and other requirements that might be applicable to
Defence activities and to ensure accessibility to the detail of the requirement. The register provides detail on the extent of compliance, a gap analysis, action
to address gap and acceptance of the current position. The reader is encouraged to access the LOR to keep updated with regard to the state regulatory
framework for remediation / waste disposal.
new south Wales
Soil Remediation
The ‘Guidelines for the NSW Site Auditor Scheme (2nd Edition) Section
4.3.2, NSW Department of Environment and Conservation’ ( specify that
soil remediation and management in NSW is to be implemented in the
following preferred order:
1. On-site treatment of the soil so that the contaminant is either destroyed
or the associated hazard is reduced to an acceptable level;
2. Off-site treatment of excavated soil so that the contaminant is either
destroyed or the associated hazard is reduced to an acceptable level,
after which the soil is returned to the site;
3. Removal of contaminated soil to an approved site or facility, followed
where necessary by replacement with clean fill; and
4. Consolidation and isolation of the soil on-site by contaminant within a
properly designed barrier.
While the NSW Department of Environment and Climate Change (DECC)
does not endorse any particular remediation technology it has stated
(Auditor’s meeting 2008) that “land farming as a matter of principle is not
acceptable to the DECC” unless it can be showed that land framing is a
bioremediation technique.
Waste Classification and Disposal
The following excerpts are taken from the ‘Waste Classification Guidelines,
NSW Department of Environment and Climate Change, 2008’.
Waste classification in NSW is undertaken using either the Specific
Contaminant Concentration (SCC) test or a combination of the SCC and
Toxicity Characteristics Leaching Procedure (TCLP). There are also a number
of wasters that are pre-classified.
The SCC test acts as an initial screening test for the classification of a waste.
Based on SCC alone, the test value for each contaminant must be less than
or equal to the Contaminant Threshold (CT) specified in the guidelines for
that contaminant.
To establish the waste classification using both SCC and TCLP, the test
values for each chemical contaminant must also be compared to the
CT values as specified in the guidelines. Depending on the contaminant
concentrations, waste can be classified into the following groups:
General solid waste ≤ SCC1 ≤ TCLP1. •
Restricted solid waste ≤ SCC2 ≤ TCLP2. •
Hazardous waste > SCC2 > TCLP2. •
If any of the specified SCC or TCLP threshold values are exceeded for
general solid waste, the waste must be classified as restricted solid
waste. If any of the SCC or TCLP threshold values are exceeded for
Restricted Solid Waste, the waste must be classified as Hazardous
Waste.
northern Territory
Soil Remediation
The Office of Environment and Heritage, Department of Infrastructure,
Planning and Environment is responsible for the implementation of
the National Environment Protection Measure (NEPM) in the Northern
Territory. Contamination resulting from activities impacting land and water
are dealt with under provisions of the Waste Management and Pollution
Control Act 1998. Auditing of contaminated sites in the Northern
Territory is also currently administered under the Waste Management
and Pollution Control Act 2007.
Waste Classification and Disposal
The Northern Territory Government currently has no official position
with regard to which state waste regulatory guidelines they default to.
However it is noted that key waste management facilities in the Northern
Territory operate in accordance with NSW Assessment, Classification
& Management of Liquid and Non-liquid Waste, Department of
Environment and Conservation, 1999. Note that NSW currently has an
updated (2008) version of this guideline, which the Northern Territory
does not currently refer to.
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments19 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 20
Appendix A
queensland
Soil Remediation
The Draft Guidelines for the Assessment & Management of Contaminated
Land in Queensland, Department of Environment (DoE, 1998) specifies
that the DoE (now Department of Environment and Resource Management
DERM) is committed to minimising the quantities disposed in licensed
landfills in keeping with national waste reduction targets and encourages
remediation of soils containing readily degradable contaminants.
The preferred order or options for site clean-up and management are:
on-site treatment of the soil so that the contaminant is destroyed or the •
associated hazard is reduced to an acceptable level, and
off-site treatment of excavated soil so that the contaminant is destroyed •
or the associated hazard is reduced to an acceptable level, after which
the soil is returned to the site.
The following inserts have been taken from the Queensland Government,
DERM Website (http://www.derm.qld.gov.au).
Removing Contaminated Soil
If disposal is the only viable option, all possible efforts should be made to
reduce the volume of soil requiring disposal. Very highly contaminated or
leachable soils should be separated from less contaminated soils. Separation
will reduce volumes requiring specific treatment and will significantly reduce
the disposal and treatment costs associated with highly contaminated soil.
An in-situ Stage 2 investigation (see the DERM’s Draft Guidelines for
the Assessment and Management of Contaminated Land in Queensland),
based on laboratory sampling, will normally be required to delineate
the extent of contamination and determine the volume and level of
contamination before commencement of any excavation. This will ensure
that mixing of contaminated soils with uncontaminated soils does not occur.
Reducing contaminant concentrations by dilution is not an acceptable
remediation strategy.
Waste Classification and Disposal
Queensland have no specific guiding document with relation to
waste classification and disposal. Guidelines are, however set by the
individual landfills that are run by the local councils. Brisbane has the
majority of suitable landfill sites in Queensland that are set up to accept
contaminated waste.
victoria
Soil Remediation
Victoria EPA has recently re-developed the framework under which they
administer and provide guidance on industrial waste re-use and disposal.
They have provided a one stop shop web page for all elements of industrial
waste legislation, policy, classication; sampling and registration. This web
page can be found at:
Victorian EPA Industrial Waste Resource Guidelines
All guidelines on waste classification and soil sampling can be found
on the above web page.
The Victorian EPA expects that any soil will be managed in
accordance with the waste hierarchy of avoidance, reuse, recycling,
recovery of energy, treatment, containment and disposal as set out
in the Environment Protection Act 1970.
Further to this, where it is proposed to manage contaminated soil
on-site (e.g. by treatment and re-use) EPA will require that the environmental
outcome is equivalent to that which would be achieved through off-site
treatment at a licensed soil remediation facility.
The EPA Victoria recommends that for soils contaminated with Total
Petroleum Hydrocarbons (TPHs) suitable treatment technologies include
bioremediation and thermal treatment.
Soil Sampling
Vic EPA provides guidance on how to sample contamination to determine
its hazard category and reuse classification
Soil Sampling Guidance
Sampling and Analysis of waters, wastewaters, soils, waste
Waste Classification and Disposal
Following this sampling, the soil can be categorised into a Hazard Waste
Category using the following guidance:
Soil Hazard Categorisation and Management
Guidance is also specifically supplied for classifying hydrocarbon
contaminated soil where reuse is viable option. These guidelines are at
Contaminated Soil – Organic Compounds
Tasmania
Soil Remediation
The Environmental Management and Pollution Control (Waste
Management) Regulations, Department of Tourism, Arts and Environment
2000 (the ‘Regulation) encourages effective waste management by
promoting on-site remediation, treatment and/or re-use, where appropriate,
as the preferred options for dealing with contaminated soil. In accordance
with the hierarchy of waste management options, direct disposal of soil to
landfills should be used only when no other approved method of dealing with
the contaminated soil is available. If disposal is the only viable management
option, all possible efforts should be made to reduce the volume of material
requiring disposal by minimising excavated volumes and segregating and
sorting of wastes prior to disposal.’
Further to this, Information Bulletin No. 108, Landfarming Petroleum
Contaminated Soil, Department of Tourism, Arts and Environment 2000
outlines that:
‘Under suitable conditions, landfarming is an effective bioremediation
technology for reducing concentrations of nearly all of the constituents
of petroleum products typically found at petroleum storage sites. In the
hierarchy of remedial options, this Division favours appropriately managed
landfarming over the option of off-site soil disposal.’
Appendix A
Waste Classification and Disposal
The Environmental Management and Pollution Control (Waste
Management) Regulations, Department of Tourism, Arts and Environment
2000 define criteria used for the classification of contaminated soil that
requires treatment and/or off-site disposal, and outlines the management
of each classification.
Criteria as listed in the Regulation are maximum total concentrations
and leachable concentrations for specific contaminants that are used
as a guide to classify soil for off-site disposal. The Environment Division
uses 4 categories to classify contaminated soil: (Level 1) Fill Material;
(Level 2) Low Level Contaminated Soil; (Level 3) Contaminated Soil; and
(Level 4) Contaminated Soil for Remediation. Generally, where a leachable
concentration is prescribed, that value takes precedence over the total
concentration and is used as the sole determinant of final classification
for disposal. Also, in-situ sampling is generally not recommended for
classification of soils that are to be excavated later for disposal.
south Australia
Soil Remediation
The primary regulatory requirements in relation to remediation and the
environment in South Australia are the:
• Environment Protection Act 1993 (the Act), Regulations and
Environment Protection Policies (EPPs); and
• National Environment Protection (Assessment of Site Contamination)
Measure (NEPM), 1999.
The document Soil Bioremediation, EPA Guidelines, 2005 states that the
EPA supports and encourages the controlled use of bioremediation to assist
in the remediation of site contamination in South Australia, particularly when
the treated soil is suitable for reuse (e.g. on-site backfill), thereby reducing
disposal of waste soil to landfill.
Further to this the document Soil Bioremediation (EPA 2005) states
that the EPA considers that landfarming may be an acceptable form of
bioremediation only “on large isolated sites that are remote from potentially
susceptible receptors or within approved EPA-licensed facilities where
conditions are included in the EPA authorisation”
Consideration should be given to the NEPM hierarchy for site remediation or
management, outlined below from the most preferred to the least preferred:
1) On-site treatment of the chemical substances to reduce risk to an acceptable level;
2) Off-site treatment of excavated soil to reduce risk to an acceptable level, after which the treated soil is returned to the site;
3) Containment of soil on site with a properly designed barrier; and
4) Disposal of affected soil to an approved landfill.
Waste Classification and Disposal
There are no specific documents or guidelines relating to waste
classification and disposal for South Australia. Information suggests
that each landfill in South Australia holds its own classification criteria
and waste must be classified and disposed of in a case-by-case basis.
When a waste is to be disposed, the landfill must be contacted and
the relevant paperwork can be acquired.
Upon speaking with one of the major landfill facilities in South Australia,
their three classifications for soil are:
1) Waste fill;
2) Intermediate landfill cover; and
3) Low-level contaminated soil.
Western Australia
Soil Remediation
To meet the EPA’s objectives and achieve the desired outcomes, the
following principles should be considered and addressed when determining
remediation methods or options for the remediation of contaminated land:
Principle 1: Contaminated material shall preferably be either treated
on-site and the contaminants reduced to acceptable levels, or be treated
off-site and returned for reuse after the contaminants have been reduced
to acceptable levels.
Principle 2: Disposal of contaminated material to an approved waste
disposal facility or landfill. ‘Cap and contain’ management options will only
be considered if:
a) treatment of the contaminated material is shown or demonstrated not to be practicable;
b) the options to dispose to landfill or ‘cap and contain’ are undertaken in an environmentally acceptable manner; and
c) the risk of disturbance of the contaminant exceeds the risk of leaving it undisturbed and contained on site.
The Bioremediation of hydrocarbon-contaminated soils in Western
Australia, Department of Environment (DoE), Draft 2004 was developed
to encourage a consistent approach to contaminated site assessment and
management. The following statements have been taken from the report and
outline the DOE’s (now DEC – Department of Environment and Conservation)
position on remediation methods:
‘The DoE supports the use of bioremediation for hydrocarbon contaminated
soils where the contaminated soil can be treated to enable it to be used as a
resource (e.g. backfill), to reduce disposal of soil to landfill and where works
are managed so as not to pose a risk to the environment or human health.’
‘The DoE does not consider the stockpiling and tilling of hydrocarbon
impacted soils as an acceptable remediation method. This process merely
changes the form of contamination to the vapour phase rather than
reducing the total load into the environment. The DoE does not endorse
bioremediation of hydrocarbon-impacted soils in residential areas due to
public concerns with issues such as odour, dust and noise emissions.’
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments21 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 22
Appendix B
Waste Classification and Disposal
The document Landfill Waste Classification and Waste Definitions 1996, As Amended, Department of Environment is the following categories of waste:
Class 1 (inert Landfill), Class II (Putrescible Landfill), Class III (Putrescible Landfill), Class IV (Secure Landfill) and Class V (Intractable Landfill). The following six
steps outline the waste classification process:
Step 1 Ensure that an assessment needs to be done The broad classifications used in Western Australia when assessing wastes for landfill disposal are described in the guidelines along with detailed examples of the specific waste types involved. If a waste can be classified according to the table, there is no requirement for more detailed assessment.
Step 2 Assess the waste If the waste cannot be classified in Step 1, based on an assessment of the waste source and characteristics, determine the concentration of relevant contaminants in the waste.
Step 3 Compare total concentration values with CT criteria as outlined in guidelines
Compare the contaminant concentrations with the maximum Contaminant Threshold (CT) values in the guidelines and assign a classification for each contaminant. Provisionally classify the waste according to the highest category assigned to any contaminant. If this classification is satisfactory, dispose of the waste accordingly.
Step 4 Determine contaminant ASLP leachate concentrations If the classification in Step 2 is not acceptable, or any contaminant concentration exceeds the relevant CT value, determine the Australian Standard Leaching Procedure (ASLP) leachate concentrations for all relevant contaminants.
Step 5 Compare total and leachate concentrations with CL and ASLP criteria as outlined in guidelines
Compare the contaminant ASLP concentrations and total concentrations with the ASLP and Concentration Limit (CL) values. Provisionally classify the waste in the highest category assigned to any contaminant. If this classification is satisfactory, dispose of the waste accordingly.
Step 6 Test the immobilized waste against the ASLP criteria as outlined in guidelines
If the classification in Step 4 is unacceptable, apply some form of immobilisation to the waste, then, after further leachate testing, apply the ASLP criteria only, to determine the appropriate waste classification as set out in Step 5. Encapsulated waste need not be further tested, but approval of the encapsulation method must be obtained from the Department of Environment (DoE). Note that separate DoE approval is not required for disposal of immobilized waste, but it must be disposed of as follows:
Immobilised or encapsulated Class V waste - to Class IV landfill. •
Immobilised or encapsulated Class IV waste - to Class III landfill. •
Immobilised Class III waste - to Class II landfill.•
Table Notes 1 USEPA How To Evaluate Alternative Cleanup Technologies For Underground Storage Tank Sites: A Guide For Corrective Action Plan Reviewers, EPA 510-R-04-002, May 2004
Appendix BRemediation Options Facts Sheets
biopile remediation
What is Biopile Remediation?
Under optimal soil conditions (non-compacted, sandy loam is ideal), indigenous
microorganisms can use hydrocarbons present in the soil substrate as a food source
and convert them to carbon dioxide and water.
Biopiling is a technology that uses the bioremediation process to economically
cleanup hydrocarbon-contaminated soils containing petrol, diesel, and jet fuels. These
systems typically consist of an aeration system to provide oxygen to the microbes, an
irrigation/nutrient injection system to provide nutrients and moisture after pile construction,
and a leachate collection system for controlling excess moisture in the pile. A liner, berm,
and cover protect the soil piles from storm events and prevent the spread of contaminants.
Remediation times vary depending on hydrocarbon concentrations, soil, nutrients,
temperature, and microbial conditions.
Essential Biopile Components
Table 1 summarises the applicability and constraints of biopiles with respect to contaminants, climatic conditions and soil types.
Table 1 Biopile Overview
item comments/Possible solutionsApproximate Cost$40-100/tonne of soil treated1
Chemicals of Concern Petrol, diesel or jet fuel Chemical parameters: •TotalTPH<50,000mg/kg
If heavy metals are greater than 2,500 mg/kg, bacterial growth may be inhibited. If chemical parameters are outside these specified ranges, other remedial systems may need to be considered.
Appendix B
Ideal Climatic Conditions Less than 750 mm of annual precipitation Ambient temperature of 10-45°C (at least 4 months/yr) Light or infrequent winds
If rainfall is greater enclosing biopile under roof or impervious cover may be necessary Biopiles should be suitable for most Australian locations If high winds are frequent, windrows, covering the biopiles or spraying to reduce dust or other protective measures may be necessary
Soil Characteristics Non clay soil (clay prevents effective aeration) pH between 6.0 to 8.0 Carbon : Nitrogen : Phosphorus (C:N:P) ratio of between 100:10:1 and 100:1.0:0.5 Moisture Content between 40-60%
If clay is present, mechanical shredding of soil, and/or soil amendments (gypsum, sawdust or straw) may be necessary If pH it outside of specified range, site specific testing may need to be conducted to assess biopiles design. Nutrient addition may be necessary(example:manure)If<40%moistureadditionisnecessary.If>60%waterdrainageand/orimperviouscovershouldbeconsidered.
Bacteria–HeterotrophicPlateCount>103CFU/gram If<103CFU/gramtoxicconditionsmaybepresent,furtherevaluationisnecessary(soilsamplingandanalyticalanalysis).Notethatsamples taken for HPC analysis must arrive at the laboratory within 48 hrs and therefore this analysis may not be achievable at remote sites.
System Construction
Bioplie systems can be set up in two ways – temporary and permanent. In the temporary system, the biopile is built on top of a clean soil layer over
a liner1 and base. In the permanent system, a concrete pad replaces the clean soil layer. Temporary facility construction costs are less than permanent
concrete facilities. The major construction steps for a biopile remediation facility are:
Choose site (level area not located in a flood plain)•
Prepare site for padbase construction•
Construct pile base•
Install liner and protection over liner to prevent puncture during placement of soil to be biopiled•
Construct clean soil layer •
Install piping for vapour extraction/air injection unit•
Install irrigation/nutrient injection system •
Install leachate collection system•
Load soil into facility and begin remediation•
A typical biopile system configuration is presented in Figure 1 below, adapted from the United States Environmental Protection Agency (US EPA),
2006 Technology Screening Matrix.
Typical Biolpiling Operation
Air Injection(CR Extraction)
Contaminated Soil Berm
Soil VapourMonitoring Probes Air Inlet/Exhaust
Leachate Collection and Treatment (Optional)
Nutrient and Moisture Addition
1 Generally compacted clay or impermeable rolls of high density polyethylene (HDPE) are used for liners
Figure 1 – Typical biopile construction
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments23 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 24
Appendix B
System Monitoring
In order to ensure the biopile is operating effectively and to assess possible contaminant migration to soil, surface water and groundwater, regular
monitoring is necessary. Endpoint monitoring is also necessary to assess which of the three endpoints will be applicable: off-site disposal, ex-situ
management or re-use on-site (refer to Section 3.0). Table 2 summarises information on biopile monitoring and sampling.
Table 2 Biopile Monitoring Overview
function medium sampling location Analytes to be monitored
suggested frequency
Monitor Biodegradation Soil Biopile HPC1, CoC concentrations, pH, ammonia, phosphorus, moisture
Monthly to quarterly
Air Biopile CO2, O2, CH4, H2S, CoCs Weekly for 3 months, reduced to monthly or quarterly thereafter
Contaminant Migration Air Ambient CoCs, particulates Quarterly
Surface Water Runoff from biopile As required / if required by statutory stormwater discharge permit
Groundwater Groundwater downgradient of biopile CoCs To be assessed on a case by case basis
Endpoint Monitoring Soil Soil beneath biopile (if unlined) CoCs Before and after biopiling
Soil Biopile To be undertaken In accordance to relevant State Guidelines (refer to Appendix A)
Table Notes Biopile Remediation 1 Note that samples taken for HPC analysis must arrive at the laboratory within 48 hrs and therefore this analysis may not be achievable
at remote sites. COC: Contaminants of concern Source USEPA How To Evaluate Alternative Cleanup Technologies For Underground Storage Tank Sites: A Guide For Corrective Action Plan
Reviewers, EPA 510-R-04-002, May 2004
Bioventing Remediation 1 USEPA How To Evaluate Alternative Cleanup Technologies For Underground Storage Tank Sites: A Guide For Corrective Action Plan Reviewers,
EPA 510-R-04-002, May 2004
bioventing remediation
What is Bioventing?
Bioventing is a mechanical means of remediation in which oxygen is
delivered to contaminated, unsaturated soils by forced air movement
(through injection of air) to increase oxygen concentrations and stimulate
biodegradation of contaminants in the subsurface.
Bioventing is an in situ remediation technology that stimulates the natural
in situ biodegradation of any aerobically degradable compounds in soil, by
providing additional oxygen to existing soil microorganisms. Bioventing is
based on injection of air at low flow rates to provide only enough oxygen
to sustain microbial activity. Oxygen is most commonly supplied through
direct air injection into the contaminated soil. In addition to degradation of
adsorbed and residual-phase petroleum hydrocarbons can be biodegraded
as hydrocarbon vapours move slowly through biologically active soil.
Essential Bioventing Components
Table 1 summarises the applicability and constraints of bioventing with respect to contaminants, climatic conditions and soil types.
Table 1 Bioventing Overview
item comments/Possible solutionsApproximate Cost$60-160/tonne of soil treated1
Typical SizeIn-situ technique, size based on area of contamination • The radius of influence for one vapour extraction well can range from between •0.15 m and 30 m
Radius of influence is dependent on soil type (i.e. permeability). There may be significant limitations with applying this technique in fine grained (i.e. clayey or silty soils).
Appendix B
Chemicals of Concern Petrol, kerosene, diesel, jet fuel or fuel oils Physiochemical and thermodynamic parameters:
TotalTPH<25,000mg/kg•Vapourpressure<0.5mmHg•Boiling<250-300°C•HenryLawconstant>100atm•
Most effective for more volatile fuels (petrol or kerosene) If heavy metals are greater than 2,500 mg/kg, bacterial growth may be inhibited. If chemical parameters are outside these specified ranges, other remedial systems may need to be considered.
Ideal climatic conditions Ambient temperature of 10-45°C (at least 4 months/yr) Bioventing should be suitable for most Australian locations
Soil Characteristics Non clay soil (clay prevents effective aeration) Intrinsicpermeability(k)of>10-10 cm-1 Depthtogroundwater>1.0mbglpHbetween6.0-8.0
Carbon : Nitrogen : Phosphorus (C:N:P) ratio of between 100:10:1 and 100:1.0:0.5
Moisture Content between 40-85% Bacteria–HeterotrophicPlateCount>103 CFU/gram
If clay is present, bioventing is not considered a suitable remediation technique. Consider biopiles or landfarming as alternatives. Siltysand,sand,gravelandsomesiltsgenerallymeetthisrequirement.Ifk<10-10 cm-1, bioventing may not be a suitable remediation technique. If the depth to groundwater is between 1.0 mbgl and 3.0 mbgl dewatering may be needed. Ifdepthtogroundwateris<1.0mbglbioventingisnoteffective.If pH is outside this range, pH adjustment may be warranted. Nutrient solution addition may be necessary via nutrient delivery system. If the moisture content is less than 40% addition of water is necessary. If the moisture content is greater than 85 % groundwater pumping or impervious cover (if rainfall is high) should be considered. If<103 CFU/gram toxic conditions may be present, further evaluation is necessary (soil sampling and analytical analysis)
System Construction
Once a bioventing system has been designed (and a pilot trial successfully completed) the main elements of constructing a bioventing system are as follows:
Installation of extraction (or injection) wells•
Installation of pipe infrastructure•
Vapour treatment (and pre-treatment if necessary) system•
Installation of nutrient addition system (such as injection wells or trenches) (if necessary)•
Installation of blowers•
Installation of instrumentation and controls•
Installation of sampling/monitoring points•
A typical bioventing system configuration is presented in Figure 1 below, adapted from the United States Environmental Protection Agency (US EPA),
2006 Technology Screening Matrix.
Typical Bioventing System
Figure 1 – Typical bioventing system construction
Air Injection(CR Extraction)
UST
Blower
Vapour Treatment (If Needed)
Atmospheric Discharge
Vapour Phase
Adsorbed Phase
Dissolved Phase
Optional Depending on the site Condtions
Nutrients
Groundwater Gradient
Air Flow
Air Flow
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments25 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 26
Appendix B
System Monitoring
In order to ensure the bioventing system is operating effectively, regular monitoring of environmental and mechanical parameters is necessary.
Table 2 summarises the key monitoring and sampling requirements during operation of the bioventing system.
Table 2 Bioventing System Monitoring Overview
function medium sampling location Analytes to be monitored
suggested frequency
Monitor Biodegradation Air Extraction vents, manifold and effluent stack CoCs, CO2, O2 Weekly to fortnightly (daily during system start up)
Mechanical Extraction vents, manifold and effluent stack Vacuum and flow Weekly to fortnightly (daily during system start up)
Contaminant Migration Groundwater Groundwater Groundwater downgradient of bioventing area
CoCs Annually
Endpoint Monitoring Groundwater Groundwater Groundwater downgradient of bioventing area CoCs, to be undertaken In accordance to relevant State Guidelines (refer to Appendix A)
Soil Bioventing area
Once CoCs and carbon dioxide concentrations from the soil vapour (gas collected from the extraction vents) system modification or system termination
may be appropriate.
containment Walls
What is a Containment Wall?
A cut-off or containment wall is a physical subsurface barrier designed to contain, capture or divert a dissolved or non-aqueous phase liquid (NAPL)
contaminated groundwater plume present at a site. The main purpose of constructing a containment wall is to prevent the migration of contamination,
usually offsite. Containment walls may be used as a temporary short term measure while a remedial strategy is being developed or as a long-term measure
in combination with other remedial techniques.
Essential Containment Wall Components
Table 1 summarises the applicability and constraints of containment walls with respect to contaminants, climatic conditions and soil types.
Table 2 Containment Wall Overview
item comments/Possible solutionsApproximate CostCost will be dependant on site-specific conditions, including size of contamination source zone and depth to the aquitard and/or bedrock.
Typical SizeIn-situ technique, size based on area of contamination and depth to aquitard.
Chemicals of Concern Petrol, kerosene, diesel, jet fuel or fuel oils
Containment walls may also be used for non-hydrocarbon contaminants
Ideal climatic conditions Technique can be applied in all climates.
Soil Characteristics Technique can be applied to most soil types.
Depthtogroundwater<15.0mbgl
pH is less than 4.5, Chloride greater than 12,000 mg/LSulphate greater than 2,500 mg/L
Depending on the permeability of the soils, certain design features may need to be considered including, but not limited to, groundwater dewatering bores, funnel and gate construction or a partially permeable wall to allow groundwater to pass through the wall. If the depth to groundwater is greater than 15.0 mbgl, construction costs may make the construction of a containment wall unviable. If pH, chloride or sulphate are outside these ranges, construction materials will need to consider these parameters.
Table Notes Bioventing Remediation COC: Contaminants of concern Source USEPA How To Evaluate Alternative Cleanup Technologies For Underground Storage Tank Sites: A Guide
For Corrective Action Plan Reviewers, EPA 510-R-04-002, May 2004
Appendix B
System Design and Construction
Containment walls are typically designed to anchor into the bedrock
or aquitard unit. These structures may be constructed as a slurry wall
(bentonite), grout curtain or sheet pile wall. Background information on
each technique, and the specific considerations of each technique is
presented below. A typical containment wall layout is presented in Figure 1.
Slurry Walls and Grout Curtains
Slurry walls are installed by excavating a trench which is then filled with
a slurry which, when cured, forms a low permeability barrier. The slurry
typically comprises bentonite and water. The slurry mix can be modified in
response to site-specific conditions, such as the presence of the water table
or the permeability of the strata into which the wall is installed. Modifications
to the slurry mix can include adding soil and more bentonite to enhance
solidification and in other cases the slurry contains cementing agents so
that it cures and hardens over time.
Grout curtains are similar to slurry walls except that the slurry (the grout)
is injected into the soil through drilled boreholes instead of filling a trench.
Injection is achieved using high pressure to force the grout slurry into the
pore spaces of the soil. Typically a drill rig is used to drill the holes where
the grout is injected. Injection is performed at numerous locations along
the wall alignment so that an impermeable barrier or “curtain” is formed.
Many different types of grout are available including bentonite, cement,
silicates, ligneous materials and organic chemicals. Grout can be injected
selectively to only a certain depth if required.
Slurry walls and grout curtains are long-term structures that are often
installed in combination with an impermeable capping material to prevent
infiltration of rainwater.
Sheet Pile Walls
An impermeable wall can be created by driving (preferably self-sealing) sheet
piles into the ground along the alignment of the containment wall. Sheet piles
are sections of steel plate, usually corrugated for strength, which can be
driven into the ground using a pile driver. The steel plate sheets interlock at
the edges so a continuous subsurface wall can be guaranteed. Small gaps
do exist at the interlocking points so a water-tight seal may be difficult to
achieve, however the gaps can be filled with grout, may seal itself with fine
particles over time or be joined by use of self sealing sheet piles.
An alternate sheet piling material is the PlastipileTM; sheet piling
manufactured from recycled plastic. This type of sheet piling can form
a water-tight retaining wall of varying heights and can be built in locations
where access for large equipment is limited.
Sheet pile walls are considered a short-term structure that may be employed
as an interim measure while a detailed remedial strategy is being developed.
Geosynthetic Clay Liners
In additional to the more traditional techniques mentioned above,
an alternate method using a geosynthetic clay liner (GCL) can also be
used as a containment wall. GCLs are a liner technology that combines
geosynthetics and clay materials. The GCL is made from polypropylene
geotextiles and premium grade sodium bentonite powder and is fibre-
reinforced by needle-punching the composite across the entire surface area
of the product. Unique to this product, is the high tenacity fibres that are
thermally-locked to ensure high long-term shear strength.
Due to its low permeability and high internal shear strength GCLs have
a good liquid containment capability and have been used in reservoirs,
wetlands and irrigation canals, as well as effluent, industrial and landscaped
ponds and lagoons.
Using the GCL technique, a 0.6 m trench is excavated and material
stockpiled, the geosynthetic liner is then installed and the stockpiled
material can then be used as backfill to reinstate the trench.
Figure 1 – Typical containment wall construction (slurry wall pictured) (Source: United States Naval Facilities Engineering Command)
Fill
Bentonite Slurry
Aquitard
Contaminant Plume
Water Table
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments27 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 28
Appendix B
System Monitoring
As a containment wall is a physical barrier the integrity of the barrier
should be monitored regularly. The requirement for monitoring should
be included in site management plans, for example an Environmental
Management Plan (EMP), so that:
The location of the containment wall can be communicated •
to Defence personnel or contractors working at the site; and
Requirements for regular monitoring can be documented and •
serve as a trigger for undertaking the monitoring.
landfarm remediation
What is Landfarming?
Landfarming involves the application of excavated contaminated soil in a thin
layer across the ground. Minerals, nutrients, moisture and air (via aeration
of the soil) are then added to the thin layer of contaminated soil to stimulate
the indigenous microorganisms (usually present in most soils), which use
hydrocarbons as a food source and convert them to carbon dioxide and water.
Table Notes Landfarm Remediation 1 USEPA How To Evaluate Alternative Cleanup Technologies For Underground Storage Tank Sites: A Guide For Corrective Action Plan Reviewers,
EPA 510-R-04-002, May 2004
Monitoring of the integrity of the containment system may include:
Visual inspections of the barrier wall and capping; and•
Groundwater monitoring to assess the potential for the integrity of the
barrier system to have been breached and the potential for groundwater
impacts to be migrating from the source zone.
Landfarms are facilities that use the bioremediation process to economically cleanup hydrocarbon-contaminated soils containing petrol, diesel, and jet
fuels. These systems typically involve the application of hydrocarbon contaminated soils to a vacant land area (or paddock), which are then aerated via
tilling or ploughing. If necessary nutrients, minerals and moisture can be added when the landfarm is tilled or ploughed. Landfarms may also be constructed
using an impermeable liner underneath the area (to control contaminant migration) and a leachate collection system for controlling excess moisture in the
landfarm. Remediation times vary depending on hydrocarbon concentrations (and type), soil, nutrients, temperature, and microbial conditions. As landfarms
may not be permitted in all States and Territories, the relevant State or Federal legislation must be checked before undertaking landfarming for hydrocarbon
remediation.
Essential Landfarm Components
Table 1 summarises the applicability and constraints of landfarms with respect to contaminants, climatic conditions and soil types.
Table 1 Landfarm Overview
item comments/Possible solutionsApproximate Cost$40-70/tonne of soil treated1
Typical SizeOverall size will vary depending on the land available•Typical depth varies from 300 mm to 600 mm•
Depth of land farm depends on the equipment used to till or plough.
Chemicals of Concern Petrol, diesel, jet fuel or lubricating oil.
Chemical parameters:TotalTPH<50,000mg/kg•
Volatile components (BTEX) should be pre-treated (or potential emissions controlled) to avoid volatilisation during application of this process.If heavy metals are greater than 2,500 mg/kg, bacterial growth may be inhibited. If chemical parameters are outside these specified ranges, other remedial systems may need to be considered.
Climatic ConditionsLess than 750 mm of annual precipitationAmbient temperature of 10-45°C (at least 4 months/yr)Light or infrequent winds
If rainfall is greater, enclosing the landfarming area under roof or impervious cover may be necessaryLand farms should be suitable for most Australian locationsIf high winds are frequent, windrows, covering the land farm or spraying to reduce dust or other protective measures may be necessary
Appendix B
1 Generally compacted clay or impermeable rolls of high density polyethylene (HDPE) are used for liners
Soil Characteristics Non clay soil (clay prevents effective aeration)
pH between 6.0-8.0
Carbon : Nitrogen : Phosphorus (C:N:P) ratio of between 100:10:1 and 100:1.0:0.5Moisture Content between 40-60%
Bacteria–HeterotrophicPlateCount>103 CFU/gram
If clay is present mechanical shredding of soil, and/or soil amendments (gypsum, sawdust or straw) may be necessaryIf pH it outside this specified range, site specific testing may need to be conducted to assess the land farm design.Nutrient addition may be necessary (example: manure) If the moisture content is less than 40%, water addition is necessary. If the moisture content is greater than 60 % water drainage and/or impervious cover should be considered. If<103 CFU/gram toxic conditions may be present, furtherevaluation is necessary (soil sampling and analytical analysis). Note that samples taken for HPC analysis must arrive at the laboratory within 48 hrs and therefore this analysis may not be achievable at remote sites.
System Construction
The major construction steps for a landfarm remediation facility are:
Choose site (large level area not located in a flood plain)•
Construct berms around perimeter of area into which landfarming is to take place•
Install liner• 1 (if necessary) and install protection over liner to prevent puncture during construction
Install leachate collection system (if necessary)•
Load soil into landfarming area and begin remediation•
Other important considerations for the construction of landfarms are soil erosion control. The soils to be treated may be placed in windrows to lessen the
effect of high winds. The landfarm may also require frequent spraying to control dust and monitoring of odours and volatile contaminants.
A typical landfarm configuration is presented in Figure 1 below, adapted from the United States Environmental Protection Agency (US EPA), 2006 Technology
Screening Matrix.
Typical landfarm process
Tilling for Soil Aeration
Porous Cup Lysameters
Leachate Collection and Treatment (Optional)
Groundwater Monitoring Wells
Contaminated Soil
Berm
Figure 1 – Typical landform process
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments29 Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments 30
Appendix C
Appendix CFurther Referencesremedial Technologies
evaluations/selection of Technologies
other relevant information
remedial Technologies
General Remedial Technologies
CLU-IN Technology Focus – US EPA
The CLU-IN Technology Focus area bundles information for particular
technologies that may be used in a variety of applications. This information
is presented in categories such as Overview, Guidance, Application, Training
and Additional Resources. Technology Focus will be continuously updated
with information from federal cleanup programs, state sources, universities,
non-profit organizations, peer-reviewed publications, and public-private
partnerships. A wide range of remedial technologies are included.
In-situ and Ex-situ Biodegradation Technologies – US EPA
This EPA document summarises the latest available information on
selected treatment and site re-mediation technologies and related issues.
The document is designed to help remedial project managers (RPMs),
on-scene coordinators (OSCs), contractors, and other site managers
understand the type of data and site characteristics needed to evaluate
a technology for potential applicability to their specific sites.
System Monitoring
In order to ensure the landfarm is operating effectively and to assess possible contaminant migration to soil, surface water and groundwater,
regular monitoring is necessary. Endpoint monitoring is also necessary to assess which of the three endpoints will be applicable: off-site disposal,
ex-situ management or re-use on-site (refer to Section 3.0). Table 2 summarises the key monitoring and sampling requirements of land farming.
Table 2 Landfarming Monitoring Overview
function medium sampling location Analytes to be monitored
suggested frequency
Monitor Biodegradation Soil Landfarm HPC1, CoC concentrations, pH, ammonia, phosphorus, moisture
Monthly (or quarterly if land farming operation is long term)
Contaminant Migration Air Ambient CoCs, particulates Quarterly (if landfarming operation is long-term)
Surface Water Runoff from landfarm As required/If required by statutory stormwater discharge permit
Groundwater Groundwater Groundwater downgradient of landfarm
CoCs To be assessed on a case by case basis
Endpoint Monitoring Soil Soil beneath landfarm (if unlined) CoCs Before and after land farming
Soil Bioventing area To be undertaken In accordance to relevant State Guidelines (refer to Appendix A)
Table Notes Landfarm Remediation 1 Note that samples taken for HPC analysis must arrive at the laboratory within 48 hrs and therefore this analysis may not be achievable
at remote sites. COC: Contaminants of concern Source USEPA How To Evaluate Alternative Cleanup Technologies For Underground Storage Tank Sites: A Guide For Corrective Action Plan
Reviewers, EPA 510-R-04-002, May 2004
Bioremediation General
EPA Guidelines: Soil Remediation – S.A. EPA, 2005
This document aims to assist those undertaking bioremediation in
South Australia to comply with their general environmental duty (s25 of
the Environment Protection Act 1993 (the Act)). It does not provide direction
on the methods of bioremediation, rather it outlines appropriate management
measures that can minimise environmental impacts arising from the process.
Biopiles Biopile
Design and Construction – US EPA.
This EPA document summarises the latest available information on
selected treatment and site re-mediation technologies including biopiles.
The document provides some technical guidance on the design, operation,
and maintenance of biopiles to remediate soils contaminated with petroleum-
based organic contaminants.
Bioventing & Soil Vapour Extraction
Bioventing – AF Center for Engineering and the Environment
This website provides general information regarding bioventing and its
use for petroleum-contaminated sites. Topics covered include development
history, cost estimates, site screening, when to use, when to avoid and
examples of bioventing sites. This site also provides links to references in
regards to procedures, principles and practices of bioventing.
Appendix C
other relevant information
Acid Sulfate Soils
Draft Strategy for Coastal Acid Sulfate Soils – Victoria EPA 2009.
A draft strategy for coastal acid sulfate soils (CASS) in Victoria,
developed by the Victorian Coastal Acid Sulfate Soils steering committee,
has been released for public comment. The draft strategy builds on existing
policies for CASS in Victoria with a particular focus on strengthening the
identification of CASS and its potential effects at the planning stage. It aims
to ensure that risks are identified and management strategies to avoid
disturbing CASS are put in place.
Site Contamination – Acid Sulfate Soil Materials – S.A. EPA, 2007.
This guideline has been prepared to provide information to those
involved in activities that may disturb acid sulfate soil materials (including
soil, sediment and rock), the identification of these materials and measures
for environmental management.
Non-Aqueous Phase Liquids (NAPLs)
Answers to Frequently Asked Questions About Managing Risk at
LNAPL Sites – API, 2003.
This document intends to provide a concise overview of current knowledge
through the format of “Frequently Asked Questions.” Each question is first
addressed with a short answer. This is followed by a more detailed answer
in a shaded box area for those who wish to know more
Asbestos
Guidelines for the Assessment, Remediation and Management
of Asbestos Contaminated Sites – Western Australian Department
of Health (2009). This document provides a background to sites
contaminated with asbestos and a framework for the assessment,
remediation and management of asbestos contaminated sites.
Soil Vapour Extraction – AF Center for Engineering and the Environment
This website provides general information into soil vapour extraction (SVE)
and principle elements of an SVE system.
Soil Vapour Extraction and Bioventing, Engineer Manual – US Army Corps
of Engineers, 2002.
This manual provides practical guidance for the design and operation of soil
vapor extraction (SVE) and bioventing (BV) systems. It is intended for use by
engineers, geologists, hydrogeologists, and soil scientists, chemists, project
managers, and others who possess a technical education and some design
experience but only the broadest familiarity with SVE or BV systems.
evaluation/selection of Technologies
How to Evaluate Alternative Cleanup Technologies for Underground
Storage Tank Sites: A Guide for Corrective Action Plan Reviews – US EPA.
The purpose of this manual is to provide guidance in evaluating remediation
technologies. This manual focuses on appropriate technology use, taking
into consideration site specific conditions and the nature and extent of the
contamination. While it focuses on the remediation of leaking underground
storage tank sites, some the basic concepts in the manual can be applied at
hazardous substance and hazardous waste sites also.
Technical Guidelines for Hazardous and Toxic Waste Treatment and
Cleanup Activities, Engineer Manual – US Army Corps of Engineers, 1994.
This manual provides design guidelines that may aid in the selection of
remedial actions at uncontrolled hazardous waste sites. Topics covered
include: identification and selection of remedial action/corrective measure
alternatives; control and containment technologies; treatment technologies
and off-site and on-site disposal technologies.
Guide for Conducting Treatability Studies under CERCLA: Biodegradation
Remedy Selection, Interim Guidance – US EPA, 1993.
The primary purpose of this guide is to provide standard guidance for
designing and implementing a biodegradation treatability study in support
of remedy selection testing. Additionally, it describes a three-tiered approach
that consists of
1. Remedy screening testing;
2. Remedy selection testing; and
3. Remedial design/remedial action testing.
It also presents a guide for conducting treatability studies in a systematic
and stepwise fashion for determination of the effectiveness of biodegradation
in remediating a site.
Content • Exit • Print
Department of Defence Manual for the Management & Remediation of Petroleum Hydrocarbon Contaminated Soil and Sediments31
Appendix D
Appendix D Case Studies & Examples
Case studies for petroleum hydrocarbon management and remediation projects
Table E1 – case studies for Petroleum hydrocarbon management and remediation Projects
Title / Theme manual section
case study details
1. Re-use of Contaminated Soil Section 2.2 Issue: A large amount of petroleum hydrocarbon impacted soil was excavated from a former refuelling site at a military base in Northern Australia. Disposal of the excavated material off-site was not viable due to the large distance between the site and the licensed waste disposal facility. Analysis: The impacted soil was characterised by the heavier-end Total Petroleum Hydrocarbon (TPH) C15-C36 concentrations which were observed to be of low volatility and solubility. Groundwater at the site was at a depth of greater than 20m and the local geology was characterised by loamy topsoils underlain by low permeability clays. The facility was undergoing redevelopment works including the construction of new site roads. Solution: Impacted soil material was re-used as road-base underneath the new site roads constructed following sampling and chemical/physical analysis to assess its suitability for the purpose. The presence of the material was documented and recorded on the site management plan.
2. Remediation & Removal of On-going Liability Section 2.2 Issue: The site was located adjacent to a residential area and river. The soil at the site had been contaminated with petroleum hydrocarbons following a one off fuel spill. The shallow groundwater at the site and the proximity of human and environmental receptors presented a risk. Analysis: A small amount (i.e. 5 m3) of heavily impacted material existed at the site; the extent of which was confirmed though a Stage 2 investigation involving installation of soil bores and soil sampling. Solution: An in-situ waste classification was undertaken, the impacted soil was excavated, the excavation validated and the waste material disposed of at a licensed waste disposal facility. By removing the impacted soil (contamination source) the on-going liability, and requirement to continue to monitor the potential surface water and groundwater impacts, was removed.
3. More Data Leads to Less Uncertainty and Reduced Remediation Risks
Section 2.3 Issue: The site was located adjacent to a residential area and river. The soil at the site had been contaminated with petroleum hydrocarbons following a one off fuel spill. The shallow groundwater at the site and the proximity of human and environmental receptors presented a risk. Analysis: A small amount (i.e. 5 m3) of heavily impacted material existed at the site; the extent of which was confirmed though a Stage 2 investigation involving installation of soil bores and soil sampling. Solution: An in-situ waste classification was undertaken, the impacted soil was excavated, the excavation validated and the waste material disposed of at a licensed waste disposal facility. By removing the impacted soil (contamination source) the on-going liability, and requirement to continue to monitor the potential surface water and groundwater impacts, was removed.
4. Management v Remediation - Sustainability Considerations
Section 3.3.3 Issue: Remediation of foreshore land in Sydney – combination of off site removal and capping and containing with management plan. Analysis: The site (forming part of the foreshore of Sydney harbour) was earmarked for redevelopment as a park. Site investigations had identified substantial amounts of fill containing chemicals (including petroleum hydrocarbons) at concentrations in excess of the proposed land use investigation levels. The traditional approach of removing the material to landfill could have resulted in the removal of more than 20 000 cubic metres of material followed by import of a similar volume of validated soil to backfill the excavation. Energy use, CO2 generation and resource consumption were considered in developing a suitable remedial solution. Solution: The remedial design was incorporated into the design for the park. The solution included assessment of ongoing impacts to the environment and human health if the material was left in situ (groundwater testing, leachate analysis and consideration for volatile generation), selected removal of small volumes of amounts of material that could have an ongoing legacy and incorporation of the capping of the remaining material as part of the playing area.
5. Risk-Based Approach Section 3.3.5f Issue: Industrial site with demonstrated discharge (via groundwater flux) of ammonia in tidal creek – this approach could be implemented with sites where groundwater is impacted by hydrocarbons Analysis: Investigations at the site identified the presence of ammonia at concentrations greater than the ANZECC water quality guidelines. As a consequence, the NSW EPA declared that the site posed a significant risk of harm. Remedial options that were initially considered included the installation of a cut off wall and interception trench – an exercise likely to cost in the order of millions. Solution: An ecological risk assessment was conducted to evaluate the direct exposure impacts to five species (including fish, algae and sea urchins) to the ammonia concentrations in the groundwater. An estimate was made of the daily volume of water in the creek along with an estimate of the overall flux of ammonia into the creek. This information was used to calculate the average concentration of ammonia that species in the creek could be exposed to. Given that the average calculated concentration was significantly less than the concentrations at which effects were observed in the test species, it was concluded that the ammonia concentrations in groundwater did not present a significant risk of harm and the EPA removed its declaration.
Content • Exit • Print
dPs dec009/09
Content • Exit • Print