Upload
trandang
View
217
Download
1
Embed Size (px)
Citation preview
MONITORING OF RENEWABLE
ENERGY PERFORMANCE
PROGRESS UPDATE FOR FIRST QUARTER 2016
ISSUE 7
APRIL 2016
2
CONTENTS
Glossary of Terms and Abbreviations........................................................................................ 3
1. INTRODUCTION AND BACKGROUND ................................................................................. 6
2. STATUS OF RENEWABLE ENERGY PROJECTS ...................................................................... 8
3. PLANT PERFORMANCE ..................................................................................................... 12
3.1 Daily energy production of solar and wind energy power plants ........................... 12
3.2 Monthly Energy Production ..................................................................................... 14
3.3 Capacity factors of Renewable Energy ...................................................................... 15
4. CONCLUDING REMARKS ................................................................................................... 16
ANNEXURE A: GEOGRAPHICAL MAPS OF IPP RENEWABLE ENERGY PROJECTS ...................... 17
ANNEXURE B: NEW RENEWABLE ENERGY POWER PLANT ADDITIONS .................................. 20
3
Glossary of Terms and Abbreviations
GLOSSARY
BID WINDOW
Means any of the procurement phases under the Renewable Energy Independent
Power Producer Procurement Programme of the Department of Energy.
CAPACITY FACTOR
Means the ratio of the power plant output over a period of time, to its potential output if
it were possible for it to operate at full nameplate capacity continuously over the same
period of time.
ENERGY REGULATOR
Means the regulatory authority established as a juristic person in terms of Section 3 of
the National Energy Regulator Act, 2004 (Act No. 40 of 2004).
GOVERNMENT
Means the Government of the Republic of South Africa, and any of its departments,
agencies or other entities that it manages or controls.
GIGAWATT HOUR
Energy unit in which electricity consumption is measured. 1GWh = 1000MWh.
INDEPENDENT POWER PRODUCER (IPP)
IPPs are defined as typically limited-liability, investor-owned enterprises that generate
electricity either for bulk sale to an electric utility or for retail sale to industrial or other
customers with certain conditions.
MEGAWATT HOUR
Energy unit in which electricity consumption is measured. 1MWh = 1000kWh.
4
MINISTER
Means Minister of Energy
RENEWABLE ENERGY (from the 2003 White Paper on Renewable Energy)
Renewable energy harnesses naturally occurring non-depletable sources of energy,
such as solar, wind, biomass, hydro, tidal, wave, ocean current and geothermal, to
produce electricity, gaseous and liquid fuels, heat or a combination of these energy
types.
TERAWATT HOUR (TWh)
Energy unit in which electricity consumption is measured. 1TWh = 1000GWh = 3,600 x
103 GJ (Gigajoule) (a Joule is a unit of energy).
5
ABBREVIATIONS
BW Bid Window
CF Capacity Factor
COD Commercial Operation Date
CSIR Council of Scientific and Industrial Research
CSP Concentrated Solar Power
DoE Department of Energy
IPP Independent Power Producer
IRP Integrate Resource Plan
MW Megawatt
MWh Megawatt hour
GWh Gigawatt hour
NERSA National Energy Regulator
PPA Purchase Power Agreement
PV Photovoltaic
RE Renewable Energy
REIPPP Renewable Energy Independent Power Producer
Programme
RfP Request for Proposal
TWh Terawatt-hour
6
1. INTRODUCTION AND BACKGROUND
South Africa has demonstrated to the world that renewable energy can be implemented
successfully in power systems that are still dominated by a large power utility.
Government policy on renewable energy (RE), coupled with solid regulatory framework
have ensured that Independent Power Producers (IPPs) are afforded an opportunity to
contribute in this important electricity industry. The National Energy Regulator of South
Africa (NERSA) supports Government's RE plans set out in the Integrated Resource
Plan 2010-2030 (IRP2010-2030). In order to implement the plan, the Minister has so far
made three Determinations under the Renewable Energy Independent Power Producer
Programme (REIPPP) of the Department of Energy (DoE). In the first Independent
Power Producer (IPP) Determination, issued in 2011 ('the IPP Determination 2011'), a
target of 3 825MW of RE was set. In the second IPP Determination, ('the IPP
Determination 2012), 3 455MW of RE capacity will be procured until 2020.
In the third IPP Determination, ('the IPP Determination 2015'), a procurement of
renewable energy capacity of 6300MW is envisaged for the period 2021- 2025, in
accordance with the promulgated IRP2010-2030. In total, the renewable energy
capacity to be procured by 2025 is estimated at 13 580 MW. In November 2015, the
Minister issued a fourth Determination, (‘the Renewable Energy (Solar) Procurement
Programme 2015’). The Solar Procurement Programme proposes 1 500MW of capacity
to be procured from Solar PV or any other solar technology. Table 1 below lists all four
Ministerial Determinations for RE and technology capacity allocation. Table 2 lists other
Determinations on non-renewable technologies.
Four RE IPPP bid windows, including a mini-bid window of Concentrated Solar Power
(CSP) projects (termed 'Window 3.5'), have been concluded successfully by the
Department of Energy (DoE). Table 2 below shows a summary of capacity allocations
for each bid window.
7
Table 1: Ministerial Determinations for Renewable Energy
Technology Ministerial Determination (Renewable Energy)
IPP Procurement
Programme 2011
IPP Procurement
Programme 2012
IPP Procurement
Programme 2015
IPP Procurement
Solar 2015
Onshore Wind 1850 1600 3040
Solar PV 1450 1200 2200
1500** CSP 200 400 600
Biomass 12.5 47.5 150
Biogas 12.5 47.5 50
Landfill Gas 25 0 0
Small hydro 75 60 60
Small Projects 100 100 200
Total Allocation 3725 3455 6300 1500
** According to the Ministerial Solar Determination 2015, 1 500MW will be for solar technologies i.e. CSP and Solar PV only.
Table 2: Capacity allocations for bid windows (BW)
RE Type Adjusted
Capacity (MW)
BW 1
(MW)
BW2
(MW)
BW 3
(MW)
BW 3.5
(MW)
BW 4
(MW)
Onshore wind 3 320 634.0 562.5 787 0 1362.4
Solar photovoltaic 2 525 631.5 417.1 435 0 812.9
Concentrated solar
power
600 150.0 50.0 200 200 0
Small hydro
(≤40MW)
135 0 14.3 0 0 5
Landfill gas 25 0 0 18 0 0
Biomass 60 0 0 16 0 25
Biogas 60 0 0 0 0 0
Small Projects 200 0 0 0 0 0
Total 6 925 1 415.5 1 043.9 1 456 200 2205.3
8
On 26 May 2014, the DoE released the Request for Proposal (RfP) for the fourth bid
window. A total of 77 bids amounting to 5 804 MW were received against the available
capacity allocation of 1 105 MW. Preferred bidders were announced in two groups. The
first group of 13 preferred bidders were announced on 10 April 2015, while the second
group of 13 preferred bidders were announced on 07 June 2015. Annexure A shows
the location of projects from all four RE IPP bid windows.
In terms of section 4 of the Electricity Regulation Act 2006 (Act No. 40 of 2006) ('the
Act'), NERSA has a mandate to 'establish and manage monitoring and information
systems and co-ordinate the integration thereof with other relevant information
systems', The Renewable Energy (RE) Independent Power Producers (IPPs) are
required to submit reports on their monthly energy production, pursuant to section 15 of
Grid Connection Code for Renewable energy version 2.8 of 2015. The sections below
will cover the status of RE IPP projects and performance of the power plants during the
year 2015/16.
2. STATUS OF RENEWABLE ENERGY PROJECTS
Table 3 shows the update of the capacity under commercial operation since the last
update on 01 September 2015. As of 09 February 2016, the total grid connected
capacity of REIPP projects is 2 626.16MW. Out of this grid-connected capacity, 2
144.72MW is in commercial operation as illustrated in Table 3 below.
Table 3: Update from previous Monitoring Renewable Energy Performance Report (Issue 6)
Date Commercial Capacity (MW)
(Commercial and Early Operation)
Increase in MW
(since last report)
01 September 2015
(last report)
2021.44 ─
09 February 2016
(this report)
2144.72 123.28
Table 4 below provides a list of all REIPPP projects in commercial operation. The
projects in commercial operation are from BW1 and BW2 of REIPPP. The pictures of
9
the new RE power plants added to the grid are shown in ANNEXURE B. The RE IPP
projects of BW 3 are currently under construction and the first Commercial Operation
Dates (CODs) are expected from July 2016 onwards.
Table 4: REIPPP projects that achieved COD as at 09 February 2016
Power Plant Technology Contracted Capacity (MW)
Achieved Capacity (MW)
Scheduled COD (As per PPA)
Achieved COD
1 155 RustMo1 Solar PV 6.93 6.93 15-Nov-13 15-Nov-13
2 202 Hopefield Wind 65.4 65.4 01-Feb-14 01-Feb-14
3 138 MetroWind Wind 27 27 01-Feb-14 07-Feb-14
4 159 Kalkbult Solar PV Solar PV 72.5 72.4 01-Jan-14 19-Mar-14
5 163 Aries Solar PV Solar PV 9.65 9.65 13-Dec-13 20-Mar-14
6 128 Konkoonsies Solar PV Solar PV 9.65 9.65 13-Dec-13 20-Mar-14
7 182 PV De Aar Solar PV 45.6 45.6 03-Apr-14 05-Apr-14
8 572 Droogfontein Solar PV 45.6 45.4 03-Apr-14 06-Apr-14
9 696 Herbert Solar PV Solar PV 19.98 19.9 11-Apr-14 11-Apr-14
10 443 Greefspan Solar PV Solar PV 9.9 9.9 11-Apr-14 11-Apr-14
11 123 Dassieklip Wind 27 27 27-Jan-14 07-May-14
12 186 Jeffreys Bay Wind 138 135.11 15-May-14 15-May-14
13 031 Letsatsi Solar PV 64 64 21-May-14 21-May-14
14 032 Lesedi Solar PV 64 64 21-May-14 21-May-14
15 523 Linde ** Solar PV 36.8 36.8 30-Jun-14 30-Jun-14
16 052 Soutpan Solar PV 28 27.94 14-Feb-14 04-Jul-14
17 036 Nobelsfontein Wind 75 73.8 11-Jul-14 12-Jul-14
18 064 Mulilo de Aar Solar PV 10 10 01-Apr-14 19-Jul-14
19 375 Vredendal** Solar PV 8.8 8.8 06-Jun-14 31-Jul-14
20 764 Upington Solar ** Solar PV 8.9 8.9 31-Jul-14 31-Jul-14
21 043 Dorper Wind 97.53 97.53 01-Jul-14 09-Aug-14
22 564 Solar Capital de Aar Solar PV 75 75 28-Feb-14 15-Aug-14
23 444 Reisa Kathu Solar PV 75 75 15-Aug-14 15-Aug-14
24 035 Witkop Solar PV 30 29.68 25-Apr-14 20-Sep-14
25 065 Mulilo Prieska Solar PV 20 19.93 01-Apr-14 01-Oct-14
26 750 Boshoff ** Solar PV 60 57 30-Sep-14 25-Oct-14
27 225 Cookhouse Wind 138.6 135.8 31-May-14 19-Nov-14
28 207 Sishen ** Solar PV 74 74 26-Nov-14 29-Nov-14
29 037 Touwsrivier Solar PV 36 36 20-Jun-14 05-Dec-14
30 562 Jasper ** Solar PV 75 75 17-Dec-14 17-Dec-14
31 373 Aurora Rietvlei ** Solar PV 9 8.9 05-Sep-14 23-Dec-14
32 527 Dreunberg ** Solar PV 69.6 69.6 31-Dec-14 31-Dec-14
33 815 Kakamas Hydro** Hydro 10 10 31-Jan-15 31-Jan-15
34 118 Kaxu Solar One CSP 100 100 06-Feb-15 06-Feb-15
35 148 Kouga Red Cap Wind 80 77.7 16-Dec-14 17-Mar-15
36 364 Grassridge ** Wind 59.8 59.8 06-Jun-15 06-Jun-15
37 309 West Coast** Wind 90.82 90.82 09-Jun-15 09-Jun-15
38 164 SlimSun** Solar PV 5 5 01-Jul-14 05-Aug-15
39 014 Gouda** Wind 135.5 135.5 11-July-15 28 -Aug-15
40 372 Chaba** Wind 21 21 12 -Sep-15 12-Sep-15
41 362 Waainek** Wind 23.28 23.28 26-Sep-14 10-Jan-16
42 798 Khi Solar One CSP 50 50 30-Jan-16 05-Feb-16
43 002 Bokpoort CSP** CSP# 50 50 28-Jan-16 06-Feb-16
TOTAL CAPACITY COD 2144.72 Source: ESKOM ** Bid Window 2 projects # Early Operation
10
The monthly cumulative capacity of the RE IPPs in commercial operation is shown in
Figure 1 below. From the plot it can be seen that the capacity of renewable increased
substantially from February 2014.
Figure 1: Monthly Cumulative commercial capacity of REIPP projects on 09 February 2016.
Figure 2 overleaf shows the commercial capacity of RE by technology. Wind technology
has 969.74MW of commercial capacity and is followed by Solar PV, with 964.98MW.
CSP capacity has increased by 100MW this year, following the commissioning of Khi
Solar One and Bokpoort CSP plants, both of which have 50MW of commercial capacity.
11
Figure 2: Commercial capacity of various technologies on 09 February 2016.
Figure 3 below shows the commercial capacity of RE power plants for each province in
South Africa. Also shown in the figure are the number of projects for each province.
The Northern Cape has the highest RE capacity in the country due favourable solar
energy resource while the Western and Eastern Cape provinces follow with RE capacity
mainly from wind farms.
Figure 3: Capacity of renewable energy IPP power plants per province. (Data last updated on 09 February
2016).
12
3. PLANT PERFORMANCE
Performance monitoring of the RE power plants is based on the hourly energy profiles,
which are reported monthly, and on total monthly energy sales, which are reported on
a quarterly basis. Below is the analysis of hourly and monthly energy production of
commercial RE power plants:
3.1 Daily energy production of solar and wind energy power plants
Energy data used for the analysis of photovoltaic (PV) plant hourly performance was
based on a sample of plants that provided timely information to NERSA, as listed in
Table 5. It covers the period, from 1 January 2015 to 31 December 2015. The total
contracted capacity of the analysed sample of RE plants is approximately 695MW. The
majority of the RE projects in South Africa are located in the Northern Cape where most
solar resource is plentiful. Figure 4 shows the average hourly energy profiles of sixteen
solar PV and seven Wind plants for 12 months, starting from January 2015 to end
December 2015.
Table 5: IPP data sources for hourly energy.
PV Plants (695 MW) Wind Plants (562.84MW) CSP Power Plants (100MW)
Hydro Power Plants (10.9MW)
155 Rustmo1 123 Dassieklip 118 KaXu CSP Kakamas hydro plant
163 Aries 159 Dorper
128 Konkoosies 202 Hopefield
696 Herbert 128 Nobelsfontein
443 Greefspan 182 Jeffreys Bay
562 Jasper 138 Metro Wind Van Stadens
523 Linde 225 Cookhouse
527 Dreunberg
159 Kalkbult
034 Lesedi
031 Letsatsi
065 Mulilo Prieska
064 Mulilo DeAar
444 Reisa Kathu
564 SolarCapitalDeAar
13
From the plot it can be seen that wind energy production is higher in the early afternoon
hours up to and including the peak evening hours i.e. from 16:00 PM and 20:00PM.
Therefore it can be concluded that wind energy contributes to meeting the evening peak
demand, while solar PV contributes to meeting the portion of the morning peak demand
of the system since solar irradiation increases rapidly before 09:00 AM. The annual
average ratio of morning to evening peak demand is about 0.95 (i.e. there is a small
difference between the two peak load period).
Figure 4: Daily average energy profile of Wind and PV power plants for 2015.
The first CSP power plant, KaXu, started commercial operation on 06 February 2015.
Figure 5 shows energy profile of the CSP power plant on 19 September 2015. From
the energy profile it can be seen that the power plant produced energy during sunshine
hours of the day, but in addition to that, the storage system of the plant fed power to the
grid for a further three hours of the evening. On that day 314MWh (24% of the daily
energy) of the total daily energy produced of 1 310MWh was dispatched to the grid from
14
the thermal storage facility of the CSP plant during the evening. This demonstrates that
CSP technology combined with thermal storage is able to serve load during peak hours.
Figure 5: Energy production profile of KaXu CSP on 19 September 2015
3.2 Monthly Energy Production
Figure 6 shows the monthly energy production of RE IPP power plants for the period
September 2013 to December 2015. The plot also shows respective energy
contributions from various technologies. From October 2013, there was a significant
increase in monthly energy produced due to additional power plants commissioned from
BW1. The cumulative capacity additions (see Fig 1 above) are consistent with the
cumulative energy production (see Fig 6 overleaf). . In general, 2015 had fewer plant
capacity additions compared to 2014. This is evident from the appearance of seasonal
variation (i.e. PV production dropped in winter months of 2015), something which was
overshadowed by new plant additions in 2014. Table 6 shows the total energy
production of RE technologies from 2013 till 2015. During 2015 calendar year,
approximately 4 393GWh of energy was generated by RE IPP power plants. The latter
996MWh generated
before 6pm
314MWh
generated
after 6pm
15
figure is almost double than the previous year, when 2 189GWh of energy was
produced. Energy production of solar PV and wind power plants was approximately,
2.19TWh and 1.98TWh, respectively. CSP and hydro power plant combined produced
approximately 0.22TWh. Furthermore, on average, the RE IPP power plants produced
more than 350GWh per month in 2015.
Figure 6: RE IPP monthly energy production over the past three years. Table 6: Annual energy production of RE technologies.
RE technology 2013
(GWh) 2014
(GWh) 2015
(GWh)
PV 63.66 1183.00 2185.43
Wind 2.63 1006.00 1985.48
CSP 0 0 187.54
Hydro 0 0 34.22
Total Energy (GWh) 66.29 2189.00 4392.66
3.3 Capacity factors of Renewable Energy
The monthly energy production of the Wind and PV power plants was used to calculate
the monthly capacity factors (CFs). For the majority of the projects, the data represents
the first full-year performance. The CFs of solar PV power plants over a 12-month period
16
were between 18% and 32%, with an average CF of 25%. Wind energy CFs varied
from 26% to 35%, with an average of 31%. The latter figure is expected to increase as
more modern wind turbines are employed.
Fig 7: Monthly average capacity factors of solar PV and Wind power plant.
4. CONCLUDING REMARKS
A total of 43 REIPPP projects are feeding power into the grid. As of 09 February 2016,
the total installed capacity on the grid was 2 626.16MW. Out of this total installed
capacity, 2 144.72 is in commercial operation. Based on submitted energy production
data by IPPs, renewable energy power plants produced nearly 4.4TWh of energy in
2015. The hourly energy profiles of wind farms and one CSP plant show that RE is
contributing energy in the evening peak-period. In 2015, the average monthly capacity
factor for wind power plants was 31%, while the average capacity of solar PV was 25%.
17
ANNEXURE A: GEOGRAPHICAL MAPS OF IPP RENEWABLE ENERGY
PROJECTS
Source: http://energy.org.za
Figure A1: Western Cape RE IPPs. Courtesy of Stephen Forder.
18
Source: http://energy.org.za
Figure A2: RE IPP plants in the Eastern Cape. Courtesy of Stephen Forder.
19
Source: http://energy.org.za
Figure A3: RE IPP plants in John Taolo and ZF Mgcawu District Municipalities in Northern Cape.
20
ANNEXURE B: NEW RENEWABLE ENERGY POWER PLANT ADDITIONS
Table B1: New CSP power plants
POWER PLANT PHOTOS
KHI SOLAR CSP (50MW)
Located in Northern Cape near
Upington.
BOKPOORT CSP PLANT (50MW)
Located near Groblershoop in the
Northern Cape.
Source:http://crowieconcessions.co.za/portfolio-item/bokpoort-
csp-plant/. Last accessed 20 February 2016.
`