43
1 VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic NPP Power Uprate and Modernization French-Slovak summer school Kocovce, 13.9 – 17.9 2010 Ing. Branislav Hatala, PhD. [email protected]

NPP Power Uprate and Modernization · 2010. 9. 21. · VÚJE, Inc., Okružná5, 918 64 Trnava, Slovak Republic 13 Mochovce NPP Unit 1&2 - Power Uprate Thermohydraulics and electrical

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • 1VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    NPP Power Uprate and Modernization

    French-Slovak summer schoolKocovce, 13.9 – 17.9 2010

    Ing. Branislav Hatala, PhD.

    [email protected]

  • 2VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Historical development of nuclear power

  • 3VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Content

    Background on Power Uprates

    Types of Power Uprates

    Mochovce NPP Unit 1&2 Power Uprate

    Safety Aspects of Power Uprate

    Bohunice NPP Unit 3&4 Modernization + Power Uprate

    Discussion

  • 4VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Background on Power Uprates

    To increase the power output of a reactor, typically more highly enriched

    uranium fuel. This enables the reactor to produce more thermal energy and

    therefore more steam, driving a turbine generator to produce electricity.

    In order to accomplish this, components such as pipes, valves, pumps, heat

    exchangers, electrical transformers and generators, must be able to accommodate the conditions that would exist at the higher power level.

    Depending on the desired increase in power level and original equipment

    design, this can involve major and costly modifications to the plant such as

    the replacement of main turbines.

    All of these factors must be analyzed by the licensee as part of a request for a

    power uprate, which is accomplished by amending the plant's operating license.

  • 5VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Background on Power Uprates

    Power Uprate

    Thermal reactor power increase Increase thermal efficiency of Unitupgrade

    Secondary Circuit

    Electricity part

  • 6VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Types of Power Uprates

    Measurement uncertainty recapture power uprates

    are less than 2% and are achieved by implementing enhanced techniques for calculating reactor power.

    This involves the use of state-of-the-art feedwater flow measurement devices to

    more precisely measure feedwater flow, which is used to calculate reactor power.

    More precise measurements reduce the degree of uncertainty in the power level, which is used by analysts to predict the ability of the reactor to be safely

    shutdown under postulated accident conditions.

  • 7VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Types of Power Uprates

    Stretch power uprates

    are typically up to 7% and are within the design capacity of the plant

    without major plant modifications.

    Instrumentation set-points are adjusted to achieve the higher power.

    The actual value for percentage increase in power a plant can achieve and stay within the stretch power uprate category is plant-specific and depends on the

    operating margins included in the design of a particular plant.

  • 8VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Types of Power Uprates

    Extended power uprates

    These are characterized by power increases of up to 20% , and involve significant investment into the balance of plant equipment. Large items, such

    as turbines, generators and transformers are usually involved in the task.

  • 9VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 Power Uprate

  • 10VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 Power Uprate

    Power uprate up to 7%

    Reactor thermal power

    1375 MW 1471.25 MW

    Electric power

    440 MW 470 MW

    - without hardware changes

    - without change of plant design

  • 11VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power Uprate

    Power uprate up to 7%

    Reactor thermal power 1375 MW 1471.25 MW

    Electric power440 MW 470 MW

  • 12VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power Uprate

    new type of fuel assemblies (Gd-II) (4.25% / 3.84%)

    central tube

    4.4% U235

    4.0% U235

    3.6% U235

    4.0% + 3.35% Gd2O3

    Enrichment

  • 13VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power Uprate

    Thermohydraulics and electrical measurement

    Evaluation of mass and energy balance scheme

    Evaluation of the report for Ministry of Environmen t

    Update of database for safety analysis calculations

    Performance of safety analysis calculations

    Update of Safety Report

    Update of operation procedures

    Steps

  • 14VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power Uprate

    - performed with the aim to verify turbine margins

    - performed for each turbine and generator separately

    - maximal required generator gross electrical power 235 MW

    - maximum steam flowrate to the turbine

    - electrical devices monitoringtemperature of disconnectors coolant temperature of generator coolant temperature of exciter transformer temperature vibration of generator

    Thermohydraulics and electrical measurement

  • 15VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power Uprate

    - no problem for electric power increase originating from the hardware characteristics.

    - limitation is only coolant circulation temperature, which depends on weather conditions such as outside temperature, humidity, wind speed ...

    - mass and energy balance scheme was calculated, resulting in the new nominal thermal reactor power

    The results of measurements

  • 16VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power Uprate

    mass and energy balance scheme 100%T-H PARAMETRE V TEPELNEJ SCHEME I.O BLOKU ***************************************** MIESTO V POPIS MIESTA TEPLOTA TLAK PRIETOK ENTALPIA TEPELNEJ (ST. C) (MPA) (KG/S) (KJ/KG) SCHEME (*M3/H) ====================================================================== /2/ VSTUP DO REAKTORA 267.32 12.641 9245.1 1170.0 *42552. ---------------------------------------------------------------------- /3/ VYSTUP Z REAKTORA 297.88 12.360 9245.1 1329.0 *45908. ---------------------------------------------------------------------- /51/-/56/ VSTUP DO PG 297.88 12.335 1540.9 1329.0 /61/-/66/ VYSTUP Z PG 267.27 12.245 1540.9 1169.7 ---------------------------------------------------------------------- /8/ CELKOM NV DO PG 216.21 4.690 799.66 927.0 /9/ CELKOM PARA Z PG 259.92 4.690 787.66 2792.3 ====================================================================== GLOBALNE PARAMETRE: ******************* TEP.VYKON AZ (MW) 1471.25 * ROZ.TEPLOT V R (ST.C) 30.56 ---------------------------------------------------------------------- PRIKON HCC (MW) 7.48 * ROZ.TLAKOV V R (KPA) 281.4 STRATY I.O ODV.TEPLA (MW) 6.03 * ROZ.TEPLOT V PG (ST.C) 30.61 ---------------------------------------------------------------------- STRATY I.O VYM.CHL. (MW) 0.95 * PRIEM.PRIETOK HCC (M3/H) 7100.2 TEP.VYKON DO II.O (MW) 1471.75 * ROZ.TLAKOV V HCC (KPA) 436.8 ---------------------------------------------------------------------- TEP.VYK. DO ODLUHOV (MW) 2.49 * KONC.ROZ.TEPL.PG (ST.C) 7.35 TEP.VYK. DO PARY (MW) 1469.26 * ROZ.TLAKOV PG-HPK (KPA) 170.3 ----------------------------------------------------------------------

    mass and energy balance scheme 107%T-H PARAMETRE V TEPELNEJ SCHEME I.O BLOKU

    ***************************************** MIESTO V POPIS MIESTA TEPLOTA TLAK PRIETOK ENTALPIA TEPELNEJ (ST. C) (MPA) (KG/S) (KJ/KG) SCHEME (*M3/H) ====================================================================== /2/ VSTUP DO REAKTORA 266.67 12.644 9259.3 1166.7 *42558. ---------------------------------------------------------------------- /3/ VYSTUP Z REAKTORA 295.36 12.360 9259.3 1315.2 *45642. ---------------------------------------------------------------------- /51/-/56/ VSTUP DO PG 295.35 12.335 1543.2 1315.1 /61/-/66/ VYSTUP Z PG 266.61 12.248 1543.2 1166.5 ---------------------------------------------------------------------- /8/ CELKOM NV DO PG 214.53 4.668 737.62 919.3 /9/ CELKOM PARA Z PG 259.62 4.668 733.93 2792.5 ====================================================================== GLOBALNE PARAMETRE: ******************* TEP.VYKON AZ (MW) 1375.00 * ROZ.TEPLOT V R (ST.C) 28.69 ---------------------------------------------------------------------- PRIKON HCC (MW) 7.48 * ROZ.TLAKOV V R (KPA) 283.8 STRATY I.O ODV.TEPLA (MW) 6.04 * ROZ.TEPLOT V PG (ST.C) 28.74 ---------------------------------------------------------------------- STRATY I.O VYM.CHL. (MW) 0.95 * PRIEM.PRIETOK HCC (M3/H) 7101.3 TEP.VYKON DO II.O (MW) 1375.50 * ROZ.TLAKOV V HCC (KPA) 436.5 ---------------------------------------------------------------------- TEP.VYK. DO ODLUHOV (MW) 0.79 * KONC.ROZ.TEPL.PG (ST.C) 6.99 TEP.VYK. DO PARY (MW) 1374.71 * ROZ.TLAKOV PG-HPK (KPA) 147.7 ----------------------------------------------------------------------

  • 17VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power Uprate

    440

    445

    450

    455

    460

    465

    470

    475

    14 16 18 20 22 24 26 28 30 32

    Cooling Water Temperature [°C]

    Gro

    ss E

    lect

    ric P

    ower

    [M

    W]

    94.8

    96.8

    98.8

    100.8

    102.8

    104.8

    106.8

    108.8

    The

    rmal

    Rea

    ctor

    Pow

    er [

    %]

    Gross Electric Power Thermal Reactor Power

    Prediction of gross electric power

  • 18VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Mochovce NPP Unit 1&2 - Power UprateMonthly Temperatures of Cooling Water form Cooling Towers

    0

    5

    10

    15

    20

    25

    30

    January February March April May Jun July August September October November December

    Tem

    pera

    ture

    [°C

    ]

    Year 2004 Year 2005 Year 2006

    21.8 °C

  • 19VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Nuclear Safety Aspects of Power Uprate

    Licensing documentations

    Update of Safety Analysis Report

    Update of operation procedures

    Definition of setpoints of safety and control systems

    Documentation for Ministry of environment

  • 20VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Nuclear Safety Aspects of Power Uprate

  • 21VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Nuclear Safety Aspects of Power Uprate

    In order to protect the public in case of an accident, we need to:

    1. Shut down the reactor and keep it shut down

    2. Keep the reactor cool after it's shut down

    3. Contain the reactor coolant

    Barriers

    1. Fuel matrix

    2. Fuel cladding

    3. Primary circuit

    4. Confinement

  • 22VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Nuclear Safety Aspects of Power Uprate

    Reactor core power distribution

    1

    4. SKUPINA (1,4 ; MAX>

    3. SKUPINA (1,2 ; 1,4>

    2. SKUPINA (1,0 ; 1,2>

    1. SKUPINA (1,0 ; 1,0>

    Relatívny výkon prútikov

    Fuel assembly power distribution

    1

    Relatívny výkon prútikov

  • 23VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Nuclear Safety Aspects of Power Uprate

    Thermal power 1375 MW 1471 MW

    Uncertainty 4% 2%

    Fuel type Gd-2 Gd-2

    Pellet power limit 325 W/cm 325 W/cm

    Rod power limit 56.6 kW 56.6 kW

    Average rod power 31.6 kW 33.45 kW

    Average assembly power 3.9 MW 4.2 MW

    Reactor overflow 42300m3/h 42300m3/h

    Hot channel output 321 °C 321 °C

    Assemblies output 312 °C 314 °C

    ∆T on reactor 28.9 °C 30.8 °C

  • 24VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Nuclear Safety Aspects of Power Uprate

    Schema of NPP VVER-440Break location and ECCS availability

  • 25VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Calculation result of LOCA Max. Cladding Temperature

    0

    200

    400

    600

    800

    1000

    1200

    -50 0 50 100 150 200 250 300 350 400 450

    Time [s]

    Tem

    pera

    ture

    [°C

    ]

    VUJE, a.s. RELAP5x

    •997 °C -Power uprate 107 % (1471 MW)

    •989 °C -Power 100 % (1375 MW)

  • 26VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Calculation result of LOCA Max. Cladding Temperature

    900

    920

    940

    960

    980

    1000

    1020

    200 210 220 230 240 250 260 270 280 290 300

    Time [s]

    Tem

    pera

    ture

    [°C

    ]

    VUJE, a.s. RELAP5x

    •997 °C -Power uprate 107 % (1471 MW)

    •989 °C -Power 100 % (1375 MW)

  • 27VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Calculation result of LOCA Max. Cladding Temperature

    •1200 °C Safety Limit - Regulatory acceptance cri teria

    •997 °C Power uprate 107 % (1471 MW)

    •989 °C Power 100 % (1375 MW)

    •203 °C

    •211 °C

    •Safety margin

  • 28VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Bohunice NPP Unit 3&4

    Modernization

    Power Uprate

  • 29VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Bohunice NPP Unit 3&4 – Modernization + Power Uprate

    Bohunice NPP unit 3&4 – Modernization

    Thermal reactor power increase 107%

    Increase thermal efficiency of Unit.

    new Low Pressure Turbine Rotors

    new High Pressure Turbine Rotors

    new Steam Condenser

    innovation of Steam flow Measuring Orifices, other minor changes

  • 30VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Bohunice NPP Unit 3&4 Modernization + Power Uprate

    Reactor thermal power 107%

    1375 MW 1471.25 MW

    Electric power 113%

    440 MW 500 MW

    - hardware changes on secondary circuit

  • 31VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Bohunice NPP Unit 3&4 Modernization

    Objectives

    Safety

    Requirements of regulatory bodies IAEA recommendationsNew knowledge and experience of the plant operatorReplacement of the obsolete part by the up to date technique

    Reliability

    To eliminate unplanned losses in power generation and electricity supply by equipment modernization (replacement obsolete equipment by state of the art technique)

    Economy

    To establish prerequisites for life extension and power upratingTo include units into the mode of secondary grid control

  • 32VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Bohunice NPP Unit 3&4 Modernization

    Scope of technical activities in the project V2 Mod ernization

    I&C part –the most important part of Modernization

    Modernization of the Reactor Protection System (RPS)

    Modernization of the Reactor Limitation System (RLS)

    Installation of the Post-Accident Monitoring System(PAMS)

    Modernization of information systems

    Neutron flux measurement

    Reactor power control system

  • 33VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Bohunice NPP Unit 3&4 Modernization

    Scope of technical activities in the project V2 Mod ernization

    Electric part

    Modernization of the essential power supply, category II (DG start and excitation, 0.4 kV buses, 6 kV buses)

    Replacement of 400 kV switches, electrical penetrations

    Stand by power supply from Madunice hydro power plant

  • 34VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Bohunice NPP Unit 3&4 Modernization

    Scope of technical activities in the project V2 Mod ernization

    Machinery part

    Emergency core cooling and residual heat removal system

    Pressurizer-B&F mode, qualification of safety valves

    Essential service water system modification

    Steam dump relief valves (PSA)

    Ventilation and air conditioning systems

    Emergency feedwater system

  • 35VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Conclusion

    Types of Power Uprates

    Mochovce NPP Unit 1&2 Power Uprate

    Safety Aspects of Power Uprate

    Bohunice NPP Unit 3&4 Modernization + Power Uprate

  • 36

    Approved (126 NPPs)

    Pending (16 NPPs)

    VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    USA Uprate Programme

    TYPE NPPs Uprate [%] MWtMU 44 0.4-1.7 13-65

    S 65 0.9-7.0 24-239

    E 20 6.3-20.0 105-579

    TYPE NPP’s Uprate [%] MWtMU 8 1.6 27-57

    E 8 11.9-17.0 229-521

    17 179 MWt5 796 MWe

    3 436 MWt1 145 MWe

    Expected in 2010 – 2014 (40 NPPs)

    TYPE NPP’sMU 22S 1E 17

    7 198 MWt2 399 MWe

  • 37VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Russian Uprate Programme

    Russia's nuclear plants are nowadays operating with 31 reactors generating totally 21,743 MWe. An initial proposal for a rapid expansion of nuclear capacity was based on the cost effectiveness of completing the 9 GWe of then partially

    built plant. Most reactors are being uprated.

    During 2010 the uprating program is expected to be completed for all VVER units except Novovoronezh 5: 4% for VVER-1000, 5% for VVER-440. Mass and

    energy balance scheme was calculated, resulting in the new nominal thermal reactor power.

    All RBMKs will be uprated 5% by 2013, except Leningrad 1. A major contract for upgrading Leningrad unit 4 over 2008-11 is under way, as is that for Kursk 4.

    Kursk 2 & 3 with Smolensk 3 will soon follow. Kursk 1 was the first RBMK unit to be licensed for pilot operation with 5% uprate. The R&D Institute of Power

    Engineering was preparing plans for 5% uprating of the later Leningrad, Kursk and Smolensk units.

    Rosenergoatom is investigating further uprates of VVER-1000 units to 107 or 110% of original capacity, using Balakovo 4 as a pilot plant by 2014. This could

    then be extended to other Balakovo units, then Rostov and Kalinin.

  • 38VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Finnish Uprate Programme

    Olkiluoto 1&2 (BWR)

    - Started up 1978 – 1980.

    - Designed electrical power – 658 MWe (net).

    - First power uprated after 30y – 860 MWe (net).

    - Proposes to uprate to ~ 1000 MWe.

    - As a part of this, 25 MWe PU has already been done (unit 1).

    Loviisa 1&2 (PWR)

    - Started up 1977 – 1980.

    - Designed electrical power – 445 MWe (net).

    - Already uprated to 488 MWe (net).

  • 39VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Swedish Uprate Programme

    From 2004 – ongoing:

    -Ringhals 1–4: more than 400 MWe (further uprate envisaged).

    -Forsmark 1–3: ~ 370 MWe (about 190 MWe further assumption).

    -Oskarshamn 1–3: ~ 320 MWe (500 MWe completely in 2013).

    Spain Uprate Programme

    Notable for power plants uprates – a programme to add 810 MWe (11%) to its nuclear capacity through upgrading its reactors by up to 13%.

    For instance: Almaraz NPP – +5%.

    Cofrentes NPP – uprated 4x to today’s 112%, final 120% expected.

  • 40VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    NPP Paks Uprate Programme

    - Four type VVER–440/213 units, installed between 1984–1987.

    - Total safety evaluation of the units (Project AGNES) –accomplished in 1994.

    - Over 1996–2002 – a Programme of Safety Measurements.

    - Reconstruction of the secondary loop and replacements of the turbines increased electric power to 470 MWe gross.

    - By increasing the heat power of the reactor (2009) – 500 MWegross output (1485 MWt).

    Technical conditions, modifications needed:

    New fuel introduction

    Primary loop pressure controller reconstruction

    Core Control Systemreconstruction

    Reactor Defence System modification

    Modification of the parameters of the

    hydro-accumulators

    Main circulator pumps (Unit 2) modification

    Modification of turbines

    Increasing the concentration of boric

    acid in the failure systems

  • 41VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    France Uprate Programme

    In the light of operating experience, EdF uprated its four Chooz and Civaux N4 reactors from 1455 to 1500 MWe each in 2003. Over 2008-10 EdF plans to

    uprate five of its 900 MWe reactors by 3%. Then in 2007 EdF announced that the twenty 1300 MWe reactors would be uprated some 7% from 2015, within

    existing licence limits, and adding about 15 TWh/yr to output.

    Czech Uprate Programme

    - Program to boost Dukovany's gross output by 240 MWe by 2012.

    - Four Dukovany units were uprated from 440 to 456 MWe gross 2005-2008 by replacing low-pressure turbines, two of them have been running at 462 MWe.

    - A 38 MWe uprate of unit 3 was announced in May 2009 – bringing its total gross capacity to 500 MWe – from improved fuel, replacing the high-pressure turbine, refurbishing the generator, and I&C changes.

    - Temelin 1 & 2, each performing at 994 MWe, Skoda Power modified the high pressure turbines (2004-2007) to achieve 1013 MWe gross, 963 MWe net. A further upgrade since is expected to result in 1050 MWe gross.

  • 42VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    Belgian Uprate Programme

    STATION NAME

    TYPEDESIGNED

    POWER (MWt )UPRATED POWER

    (MWe ) netUPRATE TYPE &

    POWER INCREASEDoel 2 PWR 1 192 1 311 E 10%Doel 3 PWR 2 785 3 064 E 10%

    Tihange 1 PWR 2 665 2 875 E 8%Tihange 2 PWR 2 785 2 905->3 064 S/E 4.3%/10%

    * till 2007

    German Uprate Programme

    * till 2007

    STATION NAME

    TYPEDESIGNED

    POWER (MWt )UPRATED POWER

    (MWe ) netUPRATE TYPE &

    POWER INCREASEEmsland PWR 3 765 3 850 S 2.3% Grohnde PWR 3 765 3 850 S 2.3%

    Isar 2 PWR 3 765 3 850->3 950 S/S 2.3%/4.9% Neckar 2 PWR 3 765 3 850->3 965 S/S 2.3%/5.3%

    Phillipsburg 2 PWR 3 765 3 803->3 850->3 950 MU/S/S 1%/2.3%/4.9% Unterwesier PWR 3 733 3 900 S 4.5%

  • 43VÚJE, Inc., Okružná 5, 918 64 Trnava, Slovak Republic

    43

    • Thank you for your attention.