October-December 2014
Quarterly Progress Report No. 9
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page i
Table of Contents
1. INTRODUCTION ......................................................................................................................... 1
1.1 Necessity ........................................................................................................................ 1
1.2 General Features ............................................................................................................ 1
1.3 The Project Road ............................................................................................................ 2
1.4 The Project Road Constraints ......................................................................................... 3
1.5 Proposed Alignment ........................................................................................................ 3
1.6 Location Map .................................................................................................................. 4
1.7 Key Plan ......................................................................................................................... 4
2. PROJECT ASSIGNMENT ........................................................................................................... 4
2.1 Background..................................................................................................................... 4
3. INDEPENDENT ENGINEER ...................................................................................................... 5
3.1 Drawl of Agreement with Concessionaire ....................................................................... 5
4. EXECUTIVE PROGRESS SUMMARY ..................................................................................... 5
4.1 Independent Engineer: .................................................................................................... 5
4.2 THE SCOPE OF INDEPENDENT ENGINEER ................................................................ 5
4.2.1 Development Period Responsibility .................................................................................. 5
4.2.2 Reporting Requirement ..................................................................................................... 6
4.2.3 Mobilization of Concessionaire (Organization Chart) ..................................................... 10
4.3 Setting up of Project Implementation Unit –Shimla. ...................................................... 11
5. PRE-CONSTRUCTION ACTIVITIES ...................................................................................... 11
5.1 Land Acquisition/ Environmental/ Forest Clearance ...................................................... 11
5.2 Utilities shifting & other hindrances: Updated Status ..................................................... 18
5.3 Centre Line Marking: ............................................................................................................. 30
5.4 Soil Investigations: ........................................................................................................ 30
6. Statement –IV ............................................................................................................................. 30
7. CONSTRUCTION SCHEDULE ............................................................................................. 34
7.1 Project Milestone .................................................................................................................... 34
7.2 Documents: Correspondence ..................................................................................................... 34
8. MEETINGS/SITE VISITS/PRESENTATIONS: ................................................................... 55
9. EXECUTING AGENCY ......................................................................................................... 56
9.1 Concessionaire ......................................................................................................................... 56
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page ii
9.2. EPC Contractor: .............................................................................................................. 56
10 . ORGANIZATION CHART (IE) .............................................................................................. 57
11. INDEPENDENT ENGINEER MOBILIZATION:................................................................... 58
11.1 Updated Status of Man months of Independent Engineer. ...................................................... 59
11.2 Invoice of Independent Engineer Services .............................................................................. 60
11.3 S-curve for Construction Schedule- ......................................................................................... 60
11.4 Financial details of Escrow Account: ...................................................................................... 60
12. CONTRACT DATA. ................................................................................................................. 60
12.1 SANCTION /APPROVAL OF PROJECT: ........................................................................ 60
12.2 Civil works Contract Details:................................................................................................... 61
13. PROJECT PARAMETERS ................................................................................................... 61
14. UPDATED REVIEW OF DESIGN & DRAWING up to September, 2014 .......................... 62
16. Review of Physical Progress .................................................................................................... 97
17 . Road Maintenance works of existing NH-21 (Km .73+200 to 186+500). .............................. 98
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 1
Independent Engineer services for four laning of Kiratpur-Ner Chowk Section of NH-21 from Km73.200 to
Km186.500 in the State of Punjab/Himachal Pradesh to be executed as BOT (Toll) on DBFOT Pattern under
NHDP Phase-III.
1. INTRODUCTION
1.1 Necessity
The Ministry of Road Transport and Highway (MORT&H) has taken decision to develop National
Highway NH-21 from Kiratpur –Ner Chowk section from Km 73.200 to Km 186.500 in the state of
Punjab/Himachal Pradesh.
The main objective of the Project is to expedite the improvement of Infrastructure in Punjab and
Himachal Pradesh and also in reducing time and cost of travel for traffic, particularly heavy traffic,
plying between Kiratpur and Ner Chowk .The NH-21 is an important link connecting Kiratpur in
Punjab and tourist destination Manali in Himachal Pradesh.NH-21 is also a major link to connect
Leh-Ladakh.
NHAI have appointed the Voyant Solution Pvt. Ltd. & Inter Continental Technocrat Pvt. Ltd. as
consultants to carry out the Technical &Financial feasibility study for improvement of NH-21
between Kiratpur to Ner-Chowk section from Km 73.200 to 186.500 in the state of Punjab &
Himachal Pradesh.
1.2 General Features
Sl. No. Item Details
1 Project Name & Location Four laning of Kiratpur to Ner Chowk Section of NH-21
From Km73.200 to Km186.500 in the State of
Punjab/Himachal Pradesh to be Executed as BOT(Toll) on
DBFOT Pattern Under NHDP Phase-III
Starting from Kiratpur(Punjab) & end point Ner Chowk
(Himachal Pradesh)
2. Contract Package No. NHPD-Phase-III/DBFOT –NHAI/11016
3. Name of Concessionaire Kiratpur – Ner Chowk Expressway Limited
4. Name of Independent
Engineer
Getinsa Ingenieria S. L. Spain
in Association with
Segmental Consulting &Infrastructure Advisory Pvt. Ltd
5. Date of Acceptance 2nd February-2012
6. Date of signing the
Agreement
16th March 2012
7. Date of signing
Substitution/Escrow
Agreement
9th October 2012 (Financial closure 5th Sep 12, GM (J&K/HP)
letter no. NHAI/11016/9/2011/HP-2011/1110
8. Date of Commencement 14 November, 2013.
9. Date of Completion (As per
Contract)
12,November,2016 (36 months from the appointed date )
10. Project Cost (As per
Concession Agreement)
Rs. 1818.47 Crs.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 2
11. Concession Period 28 years (Incl. Construction Period)
12. Construction Period 3 Years (1095 Days)
Broad Scope of Contract
12.1 Construction of
Highways/Tunnels
Construction &widening of Existing Road ( Length 25.844
Km) from Km 73.200 to Km 86.000 ,Km159.070 to
Km167.473,Km 179.582 to Km184.323 Construction of
two Lane Road to connect Barmana cement factory to New
alignment (1.971 Km)
Construction of New alignment from Km12.732( Existing
Ch 86.000) to Km159.070 including of Five Tunnels i.e.
Long Tunnel-01No (1750 Meter), Medium Tunnel- No s (1410,860,650 meter) Short Tunnel-01No (400 meters)
12.2 Construction of Escape
Tunnel
Construction of Escape Tunnel - 1905 meter Long parallel to
main long tunnel.
12.3 Major Bridges 15 Nos.
12.4 Minor Bridges (Less than 60
m length)
29 Nos+01(Rehabilitation /Repair of Existing Bridge at Km
0+450)
12.5 Fly Over/Grade separator 01 No
12.6 Pedestrian/Cattle
underpasses
04 Nos
12.7 Culverts
12.7.1 Box Culverts 64 Nos
12.7.2 Slab Culverts 98 Nos
12.7.3 Pipe Culverts 55 Nos (in addition to this, 30 nos of culverts to be
provided at different junction points).
12.8 Main Tunnels Long Tunnel-01 No (1750 Meter), Medium Tunnel-03 Nos
(1410,860,650 meter) Short Tunnel-01 (400 meters)
12.9 Escape Tunnel 1905 meter long Parallel to long Tunnel T1
1.3 The Project Road
The NH-21 National Highway will be upgraded from its present two-lane layout, to a four-lane
divided carriageway. The design of the road between Kiratpur –Ner Chowk section from Km 73.200
to Km 186.500 in the state of Punjab/Himachal Pradesh .The Project will require the construction of
numerous structures, include Fifteen Major Bridges, One Flyover/Grade separator two hundred and
forty seven culverts (in addition to this 30 nos of culverts to be provided at different junction
points). And one no 1800 meters long tunnel with one escape tunnel of 1800 meter long besides
three Medium tunnels and one short tunnel are also to be constructed along the proposed
alignment.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 3
1.4 The Project Road Constraints
The existing road alignment of the NH-21 passes between Km 73.200 and Km 186.500 is typified by
sub-standard and often steep curves with hair-pin bend and gradients, in the horizontal and vertical
planes. The proposed improvement will be new alignment & construction and widening of existing
two lane to four lane configuration in different section of the Highway to avoid many S-curves &
steeper gradient, which will also involve the construction of many new structures, including
Tunnels, bridges, Flyover/Grade Separator and retaining structures.
The Project road area is within a region that is prone to erosion & landslides, earthquakes Zone-V.
Much of the rock in the area is well jointed and highly fragmented. Combining seismic activity with
the extreme prevailing weather conditions also means the area experiences constant landslides.
The Himachal region, with its exceptional scenic landscapes, abundant wildlife, culture diversity and
profuse number of historic and religious Temples, is a one of the main tourist destination for
tourists from every corner of the globe. The NH-21 being the main route between the principal
cities of Chandigarh via Kiratpur and from Shimla through NH-88(Connected to NH-21) carries most
of the tourist for the entire area. Tourism peaks during the summer months of July and August, but
spring and autumn, can also be busy.
1.5 Proposed Alignment
The Project road of NH-21 alignment starts from Kiratpur Km 73.200 terminates to Ner Chowk Km
186.500 and passes through Rup Nagar (Punjab) and Bilaspur, Mandi district of Himachal Pradesh.
The important places through which the project highway traverses are Kiratpur, Dhangani,
NainaDevi, BhagchhalI, Ferry Ghat, Dharadsani, Auhor, Kallar, Dehar, Dhanotu, Bhaged, Panoh,
Canaid, Bhour, Dadour and end at Nagchhala village.
The new alignment of Highway starts with long Tunnel T1 from Kainchi More at Km 12.750 (Design
Chainage) to Km 14.550 with escape Tunnel 1800 meter long parallel to Tunnel T1, Short Tunnel T2
from Km 15.785 to Km 16.275 (490 meter long), Medium Tunnel T3 from km 23.550 to Km
24.130(580 meter long), Medium Tunnel T4 from Km 148.500 to Km 149.750 (1250 meter long),
another medium Tunnel T5 km 157.660 to Km158.400 (740 meter long) through Hilly
&mountainous terrain. Proposed new alignment joins the existing road near Jarhol village at Km
159.070 (Design Chainage). For Sundar Nagar Market area a bypass is proposed from Km 173.904
to 179.582. Again the project highway follows the existing road from Km179.582 (Design Chainage)
to 184.400. New bypass for Ner Chowk is proposed from Dadour Chowk at Design Chainage
184.400 to Km 188.950 near Nagchhala village which is the end point of Project Highway. To cater
the need of cement Industry a link road is proposed to be constructed from ACC cement Plant
(Barmana) connecting new alignment of NH-21 with two lane of 1.971 km. length.
The proposed four lane will open up the Himachal Pradesh and improve the socio-economic
condition of the entire region beyond the Project area. It will also improve the transportation
network and will provide rural communities better access to markets, social services and business.
Employment opportunities will be generated and also provide impetus to tourism sector of
Himachal Pradesh.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 4
1.6 Location Map
1.7 Key Plan
Fig. 1: Proposed Alignment
2. PROJECT ASSIGNMENT
2.1 Background
NHAI have appointed the Voyant Solution Pvt. Ltd. & Inter Continental Technocrat Pvt. Ltd. as
consultants to carry out the Technical & Financial feasibility study and Detailed Project Report
(DPR) for this section of highway in the states of Punjab & Himachal Pradesh. The proposed
construction of Project Road is as under:
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 5
Km 73.200 to Km 86.000 (Existing Chainage) -12.732 km Construction & widening of Existing
alignment.
Km 86.000 to Km 159.070 (Design Chainage) -56.520 Km Construction of New alignment
comprises of Five No s Tu el Total Le gth . 7 Km with one Escape Tunnel 1905 meter long.
Km 159.070 to Km 167.473 (Existing Chainage) - 8.403 Km. Construction & widening of Existing
alignment.
Km 167.473 to Km 179.582 (New Alignment, Two lane Sunder Nagar Bypass)-5.678 Km (one Two
lane already sanctioned by MORT&H – actually work not started).
Km 179.582 to Km 184.323 (Existing Road) 4.741 Km long Construction &Widening of Existing
alignment.
Km 184.323 to Km 188.874 (New alignment Ner Chowk Bypass)-4.550Km long Construction of
New Alignment.
Connection of Barmana ACC cement Factory – 1.971 Km long (Two lane).
3. INDEPENDENT ENGINEER
It was decided that Independent Engineer may be invited to participate for Project management in
order to have proper management and Quality Assurance. Accordingly Bids were invited from pre-
qualified and short listed consultants and the work was allotted to M/S Getinsa Ingenieria S. L.
Spain in association with M/s Segmental Consulting &Infrastructure Advisory Pvt. Ltd. An
agreement for Independent Engineer, services were entered into between national highways
Authority of India, Plot No. G-5 and G-6 , Sector No.10, Dwarka, New Delhi- 110045 and M/s
Getinsa Ingenieria S. L. Spain in association with M/s Segmental Consulting & Infrastructure
Advisory Pvt. Ltd. ,Unit No 204 Vipul Trade Centre, Sector-48, Sohna Road, Gurgaon -122009
(Haryana) India by Letter No. NHAI/11016/10/2011/HP-NH-21/IE-1112 dated 10th October 2012 for
commencement of service and accordingly mobilization of Key/ Sub Key Perso el s as do e.
3.1 Drawl of Agreement with Concessionaire
Agreement was drawn by NATIONAL HIGHWAY AUTHORITY OF INDIA (NHAI) with IL&FS
Transportation Networks Ltd. on 16th March 2012. For this project IL&FS Transportation Networks
Ltd has formed a Special Purpose Vehicle (SPV) by the name of Kiratpur Ner Chowk Expressway Ltd.
KNCEL herei after referred as the Co essio aire
4. EXECUTIVE PROGRESS SUMMARY
4.1 Independent Engineer:
M/S Getinsa Ingenieria S. L. Spain in Association with M/s Segmental Consulting &Infrastructure
Advisory Pvt. Ltd. Independent Engineer in accordance with the terms of the agreement, have
been deployed personnel to supervise the Project and office building has been established
which are fully functional .
Team Leader Office:
C/o Mr. Roshan Lal Sehgal, VPO-Lakhanpur, Ward No-11, District Bilaspur (HP)-174001.
4.2 THE SCOPE OF INDEPENDENT ENGINEER
4.2.1 Development Period Responsibility
The Independent Engineer will be responsible for detailed review of the Drawings as furnished by
the Concessionaire along with supporting data, including the geo-technical and hydrological
investigations, characteristics of materials from borrow areas and quarry sites, topographical
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 6
surveys and traffic surveys. Such review will be completed and send its comments/observations to
the Authority and the Concessionaire within 15 (fifteen) days of receipt of such Drawings.
Any modified Drawings or supporting Documents sent by the Concessionaire will be commented
within 7 (seven) days of receiving. The review of the detailed design, construction methodology,
quality assurance procedures and the procurement, engineering and construction time schedule
sent by the Concessionaire will be commented within 15 (fifteen) days of receipt thereof. EPC
Contract or any other contract for construction, operation and maintenance of the Project
Highway, will be reviewed and commented within 7 (seven) days from receipt.
4.2.2 Reporting Requirement
Independent Engineer shall prepare and submit to the NHAI and Concessionaire of the following
reports.
a) Design Review Phase
Concessionaire is presently working on allocated activities of development period.
b) Construction Phase
Monthly and Quarterly Progress report covering all aspects such as progress monitoring, Quality
Assurance (QA)/Quality control (QC) etc.
c) Operation and Maintenance Phase
Monthly and Quarterly report on existing condition of facility including advise on all aspects of
operation and Maintenance. Toll Booths, Bridges or other Structures, Traffic Management &
Safety, Telephone, Ambulance.
Monthly inspection report of the Project Highway at least once a month.
The Che k list to o itor Co essio aire s o ligatio u der the pro isio of CA is presented in
Table 4.2
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 7
Table – 4.2 Concessionaire's Obligation Check List
S.
No. Requirement of Submission
by Concessionaire
Reference
Submission Time Schedule Independent Engineer Action Remark Document
Clause
No.
Development Period
1 Condition Precedent
Concession
Agreement 4.1.3 Before Appointed Date
Monitoring the status of
Conditions Precedent and
subsequently applicability of
claims, if any.
a Performance Security Complied
b Escrow Agreement Complied
c Substitution Agreement Complied
d Applicable permits as in
Schedule -E In progress
e Financing Agreement complied
f Financial Package and
Financial Model Complied
g
Confirmation of the
correctness of their
representation and
warranties
h Legal opinion
2 Quality Assurance Plan
12.1
15 days before commencement of the
Work
Monitor and review as per
provisions of CA and technical
Specifications complied
3 Official Representation at site Before Appointed Date
-
4 Quarry approval
Concession
Agreement
Monitor and review as per
provisions of CA and technical
Specifications
5 Construction Methodology Before commencement of Work
6 Inventory of Site 10.3.1 Before Appointed Date Assist Authority for establishing
"The Appendix" as defined in CA Completed
7
Detail Design of Highway
Structures, Tunnels 12.1 Before Construction
First Review within 15 days and
second review on resubmitted
revised drawing with in 7th day
from Date of Submission.
Submission
in progress
i Geotechnical Investigation
Report Submission
in progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 8
S.
No. Requirement of Submission
by Concessionaire
Reference
Submission Time Schedule Independent Engineer Action Remark Document
Clause
No.
ii Hydrological Report
iii Topographical Surveys Report
iv Traffic Survey Report Submitted
v Material Report In progress
vi Pavement Design Submitted
vii Typical Cross Section Submitted
viii Plan & Profile of MCW Submitted
for 71.0 Km
ix Plan & Profile of Service
Road
x Drainage Plan & Profile
xi Cross section
xii Detailed Drawing for
individual Culvert Drawings
(pipe , Slab & Box) In progress
xiii
Detail Design and Drawing of
individual Bridges and
structures
Concession
Agreement 12.1 Before Construction
First Review within 15 days and
second review on resubmitted
revised drawing with in 7th day
from Date of Submission.
In progress
xiv
Drawings for Road Sign,
Markings Toll Plazas. Bus
Bays, Parking Areas, Truck Lay
Bys
xv
Detailed layout drawings for
traffic circulation for service
roads, for vehicular including
cross section Drawings
through PUP, Flyover at the
Project road level and the
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 9
S.
No. Requirement of Submission
by Concessionaire
Reference
Submission Time Schedule Independent Engineer Action Remark Document
Clause
No.
structure bed level.
xxi Traffic Management
drawings for safety in
construction zones
Submitted
xxii Detailed drawings of road
side furniture and safety
structures.
Construction Period
1 Insurances
32.3 30 days before Commencement Date
of Construction or Operation.
Monitor and ensure obligation of
each party is complied as per CA
provisions complied
2
Monthly Progress Report 13.1 by 7th of every month
complied
3
3 hours Video Recording in
compact disc or digital video,
covering the status and
progress of construction
works.
13.6 by 7th day from Appointed Date and
subsequently by 15th day after end of
each quarter Complied
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 10
4.2.3 Mobilization of Concessionaire (Organization Chart)
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 11
4.3 Setting up of Project Implementation Unit –Shimla.
PROJECT DIRECTOR
National Highway Authority of India
Project Implementation Unit
Kamna View Bhawan, Phase-III
New Shimla-171009 (Himachal Pradesh)
5. PRE-CONSTRUCTION ACTIVITIES
Km 73.200 to Km.186.500 (Kiratpur Ner Chowk Section)
5.1 Land Acquisition/ Environmental/ Forest Clearance
(A) Land Acquisition:
The 3D notification for land acquisition submitted by concessionaire through PIU Shimla to NHAI
Headquarters for entire stretches. The same has been published in The Gazette of India through the
Authority for Kiratpur-Bilaspur-Ner Chowk (Km 73.200 to Km 188.500) and status shown in Tables
Details of area for which vacant access and Right of way has been granted to the concessionaire as on
11th
Nov 2013
(A) RUPNAGAR DISTRICT
Sr.
No. Village Name
Area(in Sq m) Total land (
in Sq m )
Award
Letter No.
Awarded
Date Forest Private
1
Kalyanpur
- 1707 1707
Already
awarded in
previous
package
14.06.2013
2 Dabur - 4454 4454 286 to 290 14.06.2013
3 Barruwal - 20146 20146 281 to 285 14.06.2013
4 Massewal - 20301 20301 291 to 295 14.06.2013
5 Dehni - 11698 11698 296 to 300 14.06.2013
6 Chamrauli - 17472 17472 301 to 305 14.06.2013
masura - 124588 124588 306 to 310 14.06.2013
TOTAL (A) 0 200366 200366
(B) BILASPUR DISTRICT
Sr.
No. Village Name
Area(in Sq m) Total land (
in Sq m )
Award
Letter No.
Awarded
Date Forest Private
1 Gara 25448 19766 45214 360 to 362 17.04.2013
2 Ree 8420 11144 19564 363 to 365 17.04.2013
3 Bhuai 18720 14181 32901 366 to 368 17.04.2013
4 Mehla 19870 33132 53002 932 to 934 23.09.2013
5 Thapna 50196 25037 75233 938 to 940 23.09.2013
6 Sampaytoo 2735 25828 28563 941 to 943 23.09.2013
7 Jabal 29226 5045 34271 935 to 937 23.09.2013
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 12
8 Bharadi 77648 17131 94779 946 to 966 30.09.2013
9 Padgal 23668 36801 60469 970 to 972 30.09.2013
10 Kothipura 20430 4384 24814 967 to 969 30.09.2013
11 Dharadsani 40703 39476 80179 769 to 771 27.08.2013
12 Chaat 76150 18352 94502 766 to 768 27.08.2013
13 Bhated 1939 24004 25943 756 to 758 24.08.2013
14 Mahroiyan 1092 24473 25565 753 to 755 24.08.2013
15 Behiag 5080 10902 15982 750 to 752 24.08.2013
16 Kothi 2308 39476 41784 719 to 721 16.08.2013
17 Lagheda 188 5732 5920 722 to 724 16.08.2013
18 Vahna Jatta 307 22861 23168 716 to 718 16.08.2013
19 Kallar 16254 52974 69228 713 to 715 16.08.2013
20 Bhajwani 6511 31039 37550 673 to 675 06.08.2013
21 Authar 813 25818 26631 665 to 667 05.08.2013
22 Dharyana 7936 10310 18246 662 to 664 05.08.2013
23 Palthi 867 44354 45221 659 to 661 05.08.2013
24 Vakroha 531 6971 7502 605 to 607 22.07.2013
25 Vagthedu 10537 44190 54727 617 to 819 23.07.2013
26 Khuradi 1167 10258 11425 608 to 610 22.07.2013
27 Sannor 752 33748 34500 620 to 622 23.07.2013
28 Panoh 4691 37799 42490 535 to 537 28.06.2013
29 Rohin 19124 33708 52832 532 to 534 28.06.2013
30 Amarsinghpura 13217 35525 48742 520 to 522 25.06.2013
31 Malyawar 11732 47481 59213 517 to 519 25.06.2013
32 Baloh 8776 39049 47825 538 to 540 29.062013
TOTAL (A) 507036 830949 1337985
Details of area for which vacant access and Right of way has been granted to the concessionaire as
on 14th
Nov 2013
(C) MANDI DISTRICT
Sr.
No. Village Name
Area(in Sq m) Total land (
in Sq m )
Award Letter
No.
Awarded
Date Forest Private
1 Bhantrehad 3898 31201 35099 822 to 824 05.09.2013
2 Dehar 6691 76046 82737 825 to 827 06.09.2013
3 Aisu 115860 49066 164926 828 to 830 07.09.2013
4 Dayohi 6996 72288 79284 1117 to 1119 17.09.2013
5 Gamohu 0 10735 10735 1120 to 1122 17.09.2013
6 Jarol 12882 15585 28467 1124 to 1126 19.10.2013
7 Ropari 60695 7637 68332 1157 to 1159 30.10.2013
8 Chamukha 4712 26739 31451 1160 to 1162 31.10.2013
9 Thala 0 2014 2014 1154 to 1156 30.10.2013
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 13
10 Majethal 287 39879 40166 570 to 572 06.07.2013
11 Jarlu 23522 21705 45227 573 to 575 06.07.52013
12 Nagchala 804 46692 47496 567 to 569 05.07.2013
13 Dauhandi 0 22904 22904 564 to 566 05.07.2013
TOTAL (A) 236347 422491 658838
Grand Total (A+B+C) 743383 1453806 2197189
District wise summary of land for which vacant access and right of way has been granted to the
concessionaire as on 14th
Nov, 2013,
Sr.
No. District Area (in sq m ) Area (in Ha) Remarks
1 Rupnagar 200366 20.0366
2 Bilaspur 1137985 133.7985
3 Mandi 658838 65.8838
Total 2197189 219.7189
Details of area for which vacant access and right of way has not been granted to the concessionaire as
on 11th
Nov 2013.
Sr.
No. Village Name
Area(in Sq m) Total land (
in Sq m ) Present Status
Forest Private
1 Kalyanpur 76827 - 76827
3D Completed and award
pending. As Per clause
10.3.4 The Authority has
to assure to procure and
grant, no later 90 (ninety)
days from the Appointed
Date I.e. 14th of Feb,2014
Note: 15.5799 Hect. Of
forest land handed over
vide letter no
11010/3/2012/forest/PIU-
SML/1256 dated
09/01/2014
2 Dabur 0 - 0
3 Barruwal 0 - 0
4 Massewal 0 - 0
5 Dehni 3185 - 3185
6 Chamrauli 606 - 606
7 Maura 17151 - 17151
8 Sunhan 46160 23782 69942
9 Bhated 3680 240004 27684
10 Taali 25000 29907 54907
11 Tunnu 64120 33371 97491
12 Dalyar 9510 9030 18540
13 Patta 8680 47561 56241
14 Bhatehad Uprali 19362 26196 45558
15 Chowk 0 2424 2424
16 Kanaid 0 3510 3510
17 Bhour 1690 2025 3715
18 Jangal Dadnal 0 28219 28219
19 Kayariya 0 26581 26581
20 Jool 0 489 489
21 Dadour 2348 29406 31754
TOTAL (A) 278319 286505 564824
SUNDER NAGAR BYPASS
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 14
Sr.
No. Village Name
Area(in Sq m) Total land (
in Sq m ) Present Status
Forest Private
1 Thala
NA 245210
As per Concessionaire
Agreement only 2 lane
was included in project
length but later on
additionally 2 lane is also
included in the project ,
the process of land
acquisition has been
initialled.(3a published)
2 Pung
3 Derdu
4 Dhoudu
5 Kalohad
6 Bhajwanoo
7 Chowk
Work Front Available Handed over As on Date
Particulars Area(in Sq m) Existing
ROW Total obtained ( in Sq m )
Forest Private
Four Laning of Kiratpur To
Nerchowk Section of NH-
21 from Km 73.200 to Km
186.500 in the State of
Punjab & Himachal
Pradesh
743383 1453806 440500 2637689
Work Front Available/Not Handed over As on Date
Particulars Area(in Sq m) Existing
ROW
Total to be obtained ( in
Sq m ) Forest Private
Four Laning of Kiratpur To
Nerchowk Section of NH-
21 from Km 73.200 to Km
186.500 in the State of
Punjab & Himachal
Pradesh
278319 286505 0 564824
Sunder Nagar Bypass NA NA
(A) Total Land Required for Project (sqm.) 3202513
(B) Total Land handed over as on date (sqm) 2637689
(C) Total Land Handed over as on date (in Ha) 26.377
(D) % age of Land Handed over up to Dec-2013 82.36 %
Total handed over land as on date vide NHAI
Letter No 11010/3/2012/forest/PIU-SML/1256 dated 09/01/2014 95%
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 15
SUMMARY OF INVETORY OF SITE
Details of structure in the ROW
PUNJAB
Sr.No. Item Nos. Remarks
1. House/Shops 185
BILASPUR
Sr.No. Item Nos. Remarks
1. House/Shops 374
MANDI
Sr.No. Item Nos. Remarks
1. House/Shops 223
Details of Trees Cutting In the Row of NH-21
October, 2014
Sr.No. District Nos of Pvt
Trees
Nos of Govt.
Trees
Total Nos. Of
Trees Remarks
1. Rupnagar - - 2150
1444 Nos of tree
cutting
completed
2 Bilaspur - - 22810
19773 Nos of
tree cutting
completed
3 Mandi
8786
1834 10620
1822 Nos of tree
cutting
completed
Total 35586 23039
November, 2014
Sr.No. District Nos of Pvt
Trees
Nos of Govt.
Trees
Total Nos. Of
Trees Remarks
1. Rupnagar - - 2150
1447 Nos of tree
cutting
completed
2 Bilaspur - - 22810
19838 Nos of
tree cutting
completed
3 Mandi
8786
1834 10620
1942 Nos of tree
cutting
completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 16
Total 35586 23227
December, 2014
Sr.No. District Nos of Pvt
Trees
Nos of Govt.
Trees
Total Nos. Of
Trees Remarks
1. Rupnagar - - 2150
1998 Nos of tree
cutting
completed
2 Bilaspur - - 22810
20416 Nos of
tree cutting
completed
3 Mandi
8786
1834 10620
2134 Nos of tree
cutting
completed
Total 35580 24548
Details of utilities in the ROW December
PUNJAB
Sr.No. Item Nos. Hindrance Lendth,Km
1 Electrical Lines 142 7.1
2 Water Pipe Lines - 10.686 (running km)
3 Telephone poles 16
4 HT Tower
BILASPUR (HP)
Sr.No. Item Nos. Remarks
1 Electrical Lines 122 6.1 Km
2 Water Pipe Lines - 20.886 (running km)
3 Telephone poles 98
4 HT Tower 3
MANDI (HP)
Sr.No. Item Nos. Remarks
1 Electrical Lines 148 7.4
2 Water Pipe Lines - 0.761 (running km)
3 Telephone poles 354
4 HT Tower 3
(B) Environmental Clearance: Obtained for entire project.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 17
(1) Environmental clearance obtained from Km. 73.200 to Km. 134.500 vide letter no. F.No. 10-
118/2011-IA.III Government of India, Ministry of Environment & Forests (IA-III Division) 21st
march 2013 issued to C.G.M. (LA), NHAI, G-5&6, Sector-10, Dwarka, New Delhi – 110075.
(2) Environmental clearance obtained from Km. 134+350 to Km 186+650 vide letter no. F.No. 10-
52/2011-IA.III Government of India , Ministry of Environment & Forests (IA-III Division) 21st
march 2013 issued to C.G.M. (LA), NHAI, G-5&6, Sector-10, Dwarka, New Delhi – 110075.
(C) Forest Clearance: Updated Status
Proposals are under process.
Table 5.2 Updated Status of Forest Clearance
SI. Chainage Total Length Submission of
Proposal Remarks
1 Km. 0.000 to 8.800 8.800 Km. Stage-I Clearance
Obtained Stage-II clearance obtained.
2 Km. 8.800 to 26.500 17.700Km. Stage-I Clearance
Obtained Stage-II clearance obtained.
3 Km. 26.500 (Existing
129.800) to 151.100 21.600Km.
Stage-I Clearance
Obtained Stage-II Clearance Obtained.
4 Km. 151.100 to
189.000 37.900
Stage-I Clearance
Obtained stage-II Clearance obtained
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 18
5.2 Utilities shifting & other hindrances: Updated Status
October-2014
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
1
Bilaspur
Swarghat Swarghat 6,80,560.00 Sanctioned
Approved on 13-05-2014 vide
letter no. 11009/.../165 dated
13.05.2014 for an amount of Rs.
6,34,025.00
Mandatory charges yet to be
deposited. Work awarded to contractor.
Ghumarwin Ghumarwin 39,81,900.00 Sanctioned
Approved on 13-05-2014 vide
letter no. 11009/.../163 dated
13.05.2014 for an amount of Rs.
36,01,565.00
Mandatory charges yet to be
deposited. Work awarded to contractor.
Kandrore Kandrore 177,41,750.0
0 Sanctioned
Approved on 13-05-2014 vide
letter no. 11009/.../162 dated
12.05.2014 for an amount of
Rs. 1,49,57,201.00
Mandatory charges yet to be
deposited. Work awarded to contractor.
Mandi S. Nagar S. Nagar 421,36,724.0
0 Sanctioned
Approved on 13-05-2014 vide
letter no. 11009/.../164 dated
13.05.2014 for an amount of
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 19
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
Rs. 3,42,88,190.00
Mandatory charges yet to be
deposited. Work awarded to contractor.
Baggi Baggi 377,16,787.0
0 Sanctioned
NHAI CLARIFICATION-EE, IPH
HAS TO REPLY.
2 Electrical
Anandpur Sahib
(Punjab) Kiratpur Kiratpur Sahib
96,12,645.00
Sanctioned
on 04-09-
2013 vide
letter no. 807
Revised
estimate
sanctioned on
15-04-2014
vide memo no
3779/80 for
Kiratpur Sahib
feeder
34,40
,350.
00
Submitted to NHAI Revised
estimate
sanctioned on
16-04-2014
vide memo no
3633 for
Maura feeder
84,00
,832.
00
Total Revised
Cost Estimate
118,4
1,182
.00
Bilaspur Sadar Kot 98,86,198.00
Sanctioned on 30-08-
2013 vide letter no
180654(Four
Lane)/2013-6254-55
Approved by RO Jammu on
20/11/2013 vide letter no.
NHAI/RO-
Jammu/2012/11050/K-N/244 -
Mandatory charges deposited
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 20
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
on 26-12-2013.
Bilaspur-I 107,62,855.0
0
Sanctioned on 13-09-
2013 vide letter no
180654(Four
Lane)/2013-6745-46
Approved by RO Jammu on
19/11/2013 vide letter no.
NHAI/RO-
Jammu/2012/11050/K-N/241 -
Mandatory charges deposited
on 25-03-2014.
Bilaspur-II 148,29,955.0
0
Sanctioned on 13-09-
2013 vide letter no
180654(Four
Lane)/2013-6745-46
Approved by RO Jammu on
19/11/2013 vide letter no.
NHAI/RO-
Jammu/2012/11050/K-N/241 -
Mandatory charges deposited
on 26-12-2013.
Ghumarwin Kandrour 151,56,585.0
0
Sanctioned on 30-08-
2013 vide letter no
180654(Four
Lane)/2013-6250-51
Approved by RO Jammu on
15/01/2014 vide letter no.
NHAI/RO-
Jammu/2012/11050/K-N/336 -
Mandatory charges deposited
on 19-06-2014.
Mandi S. Nagar
Salapper 350,89,735.0
0
Sanctioned on 29-08-
2013 vide letter no
180654(Four
Lane)/2013-6114-15 &
6116-17
Approved by RO Jammu on
20/11/2013 vide letter no.
NHAI/RO-
Jammu/2012/11050/K-N/242 -
Mandatory charges yet to be
deposited.
S. Nagar Sanctioned on 29-08-
2013 vide letter no
180654(Four
Approved by RO Jammu on
20/11/2013 vide letter no.
NHAI/RO-
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 21
SN Department Circle Office Division Sub - Division Amount
Sanctioned Sanctioned by S.E. Client Status
Lane)/2013-6114-15 &
6116-17 Jammu/2012/11050/K-N/242 -
Mandatory charges deposited
on 26-12-2013.
Ner Chowk Ner Chowk 164,37,975.0
0
Sanctioned on 01-08-
2013 vide letter no
180654(Four
Lane)/2013-5176-77
Approved by RO Jammu on
19/11/2013 vide letter no.
NHAI/RO-
Jammu/2012/11050/K-N/240 -
Mandatory charges deposited
on 26-12-2013. Utility shifting
commenced at site.
3 Electrical
Transmission
BBMB (01 in no.) BBMB Estimate not
yet received - -
AD Hydro Pvt
Ltd. (02 in nos.) AD Hydro Pvt Ltd
Estimate not
yet received - -
HPSEBL
(05 in nos.) Bilaspur Hamirpur 21600000.00 Sanctioned
Modification in given estimate
has been desired by NHAI vide
letter no. 11009/12/2013/K-
N/PIU-SML/1582 dated
31.03.2014 and compliance is
awaited from HPSEBL
Note: - The Concessionaire has not started shifting of utilities for the sections approved by Authority as per clause 11.2 of C.A
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 22
November-2014
S. N. Department Circle Office Division Sub -
Division Amount
Sanctioned Sanctioned by S.E.
Client Status
1 I.P.H.
Anandpur
Sahib (Pb) Kiratpur Kiratpur 414,00,000.00 Sanctioned With RO-NHAI
Bilaspur
Swarghat Swarghat 6,80,560.00 Sanctioned
Approved on 13-05-2014
vide letter no.
11009/.../165 dated
13.05.2014 for an amount
of Rs. 6, 34,025.00
Mandatory charges yet to
be deposited.
Work awarded to
contractor.
Ghumarwin Ghumarwin 39,81,900.00 Sanctioned
Approved on 13-05-2014
vide letter no.
11009/.../163 dated
13.05.2014 for an amount
of Rs. 36, 01,565.00
Mandatory charges yet to
be deposited.
Work awarded to
contractor.
Kandrore Kandrore 177,41,750.00 Sanctioned
Approved on 13-05-2014
vide letter no.
11009/.../162 dated
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 23
S. N. Department Circle Office Division Sub -
Division Amount
Sanctioned Sanctioned by S.E.
Client Status
12.05.2014 for an amount
of Rs. 1,49,57,201.00
Mandatory charges yet to
be deposited.
Work awarded to
contractor.
Mandi
S. Nagar S. Nagar 421,36,724.00 Sanctioned
Approved on 13-05-2014
vide letter no.
11009/.../164 dated
13.05.2014 for an amount
of Rs. 3,42,88,190.00
Mandatory charges yet to
be deposited.
Work awarded to
contractor.
Baggi Baggi 377,16,787.00
NHAI CLARIFICATION-EE, IPH
HAS TO REPLY.
Submitted to NHAI
2 Electrical Anandpur
Sahib (Punjab) Kiratpur
Kiratpur
Sahib
96,12,645.00
Sanctioned on
04-09-2013
vide letter no.
807
Revised
estimate
sanctioned on
15-04-2014
vide memo no
3779/80 for
Kiratpur Sahib
feeder
34,40,350.00
Approved by NHAI on
13/10/2014 vide letter no.
NHAI/11016/9/HP/UTILITY
SHIFTING/2013/2079 -
Mandatory charges to be
deposited
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 24
S. N. Department Circle Office Division Sub -
Division Amount
Sanctioned Sanctioned by S.E.
Client Status
Revised
estimate
sanctioned on
16-04-2014
vide memo no
3633 for
Maura feeder
84,00,832.00
Total Revised
Cost Estimate 118,41,182.00
Bilaspur Sadar
Kot 98,86,198.00
Sanctioned on 30-08-2013 vide
letter no 180654(Four
Lane)/2013-6254-55
Approved by RO Jammu
on 20/11/2013 vide letter
no. NHAI/RO-
Jammu/2012/11050/K-
N/240 - Mandatory
charges deposited on 26-
12-2013.
Bilaspur-I 107,62,855.00
Sanctioned on 13-09-2013 vide
letter no 180654(Four
Lane)/2013-6745-46
Approved by RO Jammu
on 19/11/2013 vide letter
no. NHAI/RO-
Jammu/2012/11050/K-
N/241 - Mandatory
charges deposited on 25-
03-2014
Bilaspur-II 148,29,955.00
Sanctioned on 13-09-2013 vide
letter no 180654(Four
Lane)/2013-6745-46
Approved by RO Jammu
on 19/11/2013 vide letter
no. NHAI/RO-
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 25
S. N. Department Circle Office Division Sub -
Division Amount
Sanctioned Sanctioned by S.E.
Client Status
Jammu/2012/11050/K-
N/241 -Mandatory
charges deposited on 26-
12-2013.
Ghumarwin Kandrour 151,56,585.00
Sanctioned on 30-08-2013 vide
letter no 180654(Four
Lane)/2013-6250-51
Approved by RO Jammu
on 15/01/2014 vide letter
no. NHAI/RO-
Jammu/2012/11050/K-
N/336 - Mandatory
charges deposited on 19-
06-2014.
Mandi S. Nagar
Salapper
350,89,735.00
Sanctioned on 29-08-2013 vide
letter no 180654(Four
Lane)/2013-6114-15 & 6116-17
Approved by RO Jammu
on 20/11/2013 vide letter
no. NHAI/RO-
Jammu/2012/11050/K-
N/242 - Mandatory
charges yet to be
deposited.
S. Nagar
Sanctioned on 29-08-2013 vide
letter no 180654(Four
Lane)/2013-6114-15 & 6116-17
Approved by RO Jammu
on 20/11/2013 vide letter
no. NHAI/RO-
Jammu/2012/11050/K-
N/242 - Mandatory
charges deposited on 26-
12-2013.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 26
S. N. Department Circle Office Division Sub -
Division Amount
Sanctioned Sanctioned by S.E.
Client Status
Ner Chowk Ner Chowk 164,37,975.00
Sanctioned on 01-08-2013 vide
letter no 180654(Four
Lane)/2013-5176-77
Approved by RO Jammu
on 19/11/2013 vide letter
no. NHAI/RO-
Jammu/2012/11050/K-
N/240 - Mandatory
charges deposited on 26-
12-2013. Utility shifting
commenced at site.
3 Electrical
Transmission
BBMB (01 in
no.) BBMB Estimate not yet received
AD Hydro Pvt
Ltd. (02 in
nos.) AD Hydro Pvt Ltd Estimate not yet received
HPSEBL
(05 in nos.) Bilaspur Hamirpur 21600000.00 Sanctioned
Not Approved and
modification in given
estimate has been desired
by NHAI vide letter no.
11009/12/2013/K-N/PIU-
SML/1582 dated
31.03.2014
Note: - The Concessionaire has not started shifting of utilities for the sections approved by Authority as per clause 11.2 of C.A
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 27
December-2014
Sr.
No. Department Circle Office Division
Sub -
Division
Amount
Sanctioned Sanctioned by S.E. Client Status
1 I.P.H.
Anandpur Sahib
(Pb) Kiratpur Kiratpur 414,00,000.00 Sanctioned
Mandatory charges have to be deposited by
NHAI.
Bilaspur
Swarghat Swarghat 6,80,560.00 Sanctioned
Approved on 13-05-2014 vide letter no.
11009/.../165 dated 13.05.2014 for an amount
of Rs. 6,34,025.00
Supervision Charges yet to be deposited.
Contractors finalized
Ghumarwin Ghumarwin 39,81,900.00 Sanctioned
Approved on 13-05-2014 vide letter no.
11009/.../163 dated 13.05.2014 for an amount
of Rs. 36,01,565.00
Supervision charges yet to be deposited.
Contractors finalized
Kandrore Kandrore 177,41,750.00 Sanctioned
Approved on 13-05-2014 vide letter no.
11009/.../162 dated 12.05.2014 for an amount
of Rs. 1,49,57,201.00
Supervision charges yet to be deposited.
Contractors finalized
Mandi
S. Nagar S. Nagar 421,36,724.00 Sanctioned
Approved on 13-05-2014 vide letter no.
11009/.../164 dated 13.05.2014 for an amount
of Rs. 3,42,88,190.00
Supervision charges yet to be deposited.
Contractors finalized
Baggi Baggi 377,16,787.00
NHAI CLARIFICATION-EE, IPH
HAS TO REPLY.
With PD-NHAI
2 Electrical Anandpur Sahib
(Punjab) Kiratpur
Kiratpur
Sahib
96,12,645.00
Sanctioned on 04-
09-2013 vide
letter no. 807
Revised
estimate
sanctioned on
15-04-2014
vide memo no
3779/80 for
Kiratpur Sahib
feeder
34,40,350.00
Approved by NHAI on 13/10/2014 vide letter no.
NHAI/11016/9/HP/UTILITY SHIFTING/2013/2079
- Mandatory charges to be deposited Dispute in
Mandatory charges, hence PSEPL not accepting
the same.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 28
Sr.
No. Department Circle Office Division
Sub -
Division
Amount
Sanctioned Sanctioned by S.E. Client Status
Revised
estimate
sanctioned on
16-04-2014
vide memo no
3633 for
Maura feeder
84,00,832.00
Total Revised
Cost Estimate 118,41,182.00
Bilaspur
Sadar
Kot 98,86,198.00
Sanctioned on 30-08-2013 vide
letter no 180654(Four
Lane)/2013-6254-55
Approved by RO Jammu on 20/11/2013 vide
letter no. NHAI/RO-Jammu/2012/11050/K-N/240
- Mandatory charges deposited on 26-12-2013.
Bilaspur-I 107,62,855.00
Sanctioned on 13-09-2013 vide
letter no 180654(Four
Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide
letter no. NHAI/RO-Jammu/2012/11050/K-N/241
- Mandatory charges deposited on 25-03-2014.
Bilaspur-II 148,29,955.00
Sanctioned on 13-09-2013 vide
letter no 180654(Four
Lane)/2013-6745-46
Approved by RO Jammu on 19/11/2013 vide
letter no. NHAI/RO-Jammu/2012/11050/K-N/241
-Mandatory charges deposited on 26-12-2013.
Ghumarwin Kandrour 151,56,585.00
Sanctioned on 30-08-2013 vide
letter no 180654(Four
Lane)/2013-6250-51
Approved by RO Jammu on 15/01/2014 vide
letter no. NHAI/RO-Jammu/2012/11050/K-N/336
- Mandatory charges deposited on 19-06-2014.
Mandi
S. Nagar
Salapper
350,89,735.00
Sanctioned on 29-08-2013 vide
letter no 180654(Four
Lane)/2013-6114-15 & 6116-17
Approved by RO Jammu on 20/11/2013 vide
letter no. NHAI/RO-Jammu/2012/11050/K-N/242
- Mandatory charges yet to be deposited.
S. Nagar
Sanctioned on 29-08-2013 vide
letter no 180654(Four
Lane)/2013-6114-15 & 6116-17
Approved by RO Jammu on 20/11/2013 vide
letter no. NHAI/RO-Jammu/2012/11050/K-N/242
- Mandatory charges deposited on 26-12-2013.
Ner Chowk Ner Chowk 164,37,975.00
Sanctioned on 01-08-2013 vide
letter no 180654(Four
Lane)/2013-5176-77
Approved by RO Jammu on 19/11/2013 vide
letter no. NHAI/RO-Jammu/2012/11050/K-N/240
- Mandatory charges deposited on 26-12-2013.
Utility shifting commenced at site.
3 Electrical
Transmission
BBMB (01 in no.) BBMB Estimate not yet received
AD Hydro Pvt
Ltd. (02 in nos.) AD Hydro Pvt Ltd Estimate not yet received
HPSEBL
(05 in nos.) Bilaspur Hamirpur 2,16,000,00.00 Sanctioned
Not Approved and modification in given estimate
has been desired by NHAI vide letter no.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 29
Sr.
No. Department Circle Office Division
Sub -
Division
Amount
Sanctioned Sanctioned by S.E. Client Status
11009/12/2013/K-N/PIU-SML/1582 dated
31.03.2014
Note: - The Concessionaire has started the shifting of Electric lines for the Nerchowk, Bilaspur sections.
5.2. A. Electric Poles Shifting
Sr. No. Description Total Numbers Shifting During the month Cumulative Shifted Balance
1 Rup Nagar (Punjab) 142 142
2 Bilaspur (Himachal) 122 0 25 97
3 Mandi (Himachal) 148 0 80 68
Total 412 0 105 307
5.2. B. Water Pipe Line Shifting
Sr. No. Description Total Length
(km) Shifting During the month Cumulative Shifted Balance
A Shifting of Water Pipe Line
1 (Rup Nagar) Punjab 10.686 10.686
2 Bilaspur (Himachal) 20.886 20.886
3 Mandi (Himachal) .761 .761
Total 32.333
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 30
5.3 Centre Line Marking:
Plan & Profile of 71.0 Km as submitted by Concessionaire has already been concurred and P &P for
balance length is yet to be submitted by Concessionaire.
5.4 Soil Investigations:
The detailed sub soil investigation has been carried out for Tunnel 1, 2, 3 4 & 5 and detailed
investigation reports has been submitted by the Concessionaire on 5.9.2013 vide letter no. ITNL-
KNCEL/PRJ/TECH/ICO-581/2013/611ED 02/04/2014.
The detailed sub soil investigation has been carried out for Major Bridges (Km
1+085,17+700,19+352,20+830,24+195,26+100,130+165,133+160,135+125,143+783,152+100,155+6
70,157+750,158+775,184+650, 158+995 ,24+925,26+184,131+180,143+950,152+628, & Minor
Bridges(Km,6+140,18+910,25+221,25+300,133+830,135+990,138+330,139+565,144+270,146+870,
150+050,153+820, 185+785, 0+450,14+750,18+318,18+972,20+416,21+550, and the same has been
submitted by the Concessionaire as on date.
5.5. Inventory of Cross Drainage Structures.
Joint Verification of structures with concessionaire has been completed as per Concession
Agreement & actual site conditions.
Tree Cutting Permission:
Permission for trees cutting obtained for entire section from concerned department and the same
are in progress.
6. Statement –IV
Obligations of the Concessionaire during Construction Period
(Based on MCA National Highways)
Sr.No. Obligations of the Project
Authority
In any action
required to be
taken (Yes/No) If yes, provide details of action taken
1.
Provided Performance Security
(Article 9 ) Yes Provided on 10.09.2012
2.
Satisfied the Conditions
Precedent (Cl.4.1.3):
(a) Executed and procured
execution of the Escrow
Agreement
(b) Executed and procured
execution of the Substitution
Agreement
(c) Procured all the Applicable
Permits specified in
Schedule-E
Yes
Yes
yes
Executed on 09.10.2012
Signed on 11.03.2013
In process.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 31
(d) Delivered copies of Financial
Agreements to the Authority
(e) Delivered 3 copies of
Financial Package and
Financial Model
(f) Delivered form the
Consortium Members
confirmation of
representations and
warranties
(g) Delivered a legal opinion
with respect to the authority
of the Concessionaire
Yes
Yes
Yes
Yes
Submitted on 29.03.2012
Submitted on 29.03.2012
Submitted on 16&17.02.12
Submitted on 21.02.2012
3. Obtaining and keeping in force
the Applicable Permits
(Cl.5.1.4(f)) Yes
All applicable permits are obtained
from concerned Authorities
4. Procuring proprietary rights,
licences, permissions, etc
(Cl.5.1.4(b)) Yes Obtained
5. Maintaining harmony and good
industrial relations (Cl.5.1.4(d)) Yes CA clause 5.1.4(d) is being followed
6. Submitted drafts of Project
Agreements to the Authority
(Cl.5.2.2) Yes Details submitted
7. Obtaining consent for
amendments to Project
Agreements (Cl.5.2) No
8. Obtaining approval for Change in
Ownership (Cl.5.3) No
9. Obtaining prior consent for any
business other than Project
(Cl.5.6) No
10. Providing in each Project
Agreement the right of Authority
to step in (Cl.5.2.4) No
11. Employed foreign nationals in
accordance with Cl.5.4 No
12. Replenishing Performance
Security in event of
appropriation (Cl.9.2) Yes Under Progress
13. Remedying Concessionaire
Default within Cure Period
(Cl.9.2) Yes
Remedy will be done as per CA
Clause 9.2 as and when applicable
14. Keeping the Highway open to
traffic at all times (Cl.10.2.3) Yes
Since 80% is green alignment, hence
no traffic diversion is required as
such. However, at existing alignment
traffic is open and shall remain same
all the times.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 32
15.
Submitting its detailed design,
methodology, time schedule, etc
(Cl.12.1 (a)) Detailed Design
Methodology
Time Schedule
yes
yes
yes
Submitted Design as on date has
been Reviewed & Concurred
Review & Concurred as per site
activities.
Reviewed and observations made for
compliance.
16. Performing all other necessary
acts, deeds and things before
construction (Cl.12.1(a)) Yes Details already submitted
17. Maintaining existing lanes of the
Project Highway (Cl.12.2) Yes
Maintenance works is under
progress.
18. “u itti g a o plete set of as-
uilt dra i gs Cl. . g Yes
Will be submitted at the time of
Project completion
19. Completing four-laning within
the specified period (Cl.12.4.1) Yes
Will be completed in specified
period 12th November,2016
20. Paying damages for failure to
achieve any milestone (Cl.12.4.2) Yes
Will be liable to pay the damages for
failure as per clause 12.4.2 of CA
21. Submitting monthly progress
reports (Cl.13.1) yes MPR is being submitted regularly
22. Rectifying defects pointed out in
IE s o thly report Cl. . Yes
Will be rectified, if required as per
clause 13.2 of CA
23. Carrying out tests and furnishing
reports (Cl.13.3.1) Yes
All const. materials are being tested
at laboratory as well as at field.
24. Communicating steps taken to
expedite progress (Cl.13.4) Yes
Will be intimated as and when
required as per clause 13.4 of CA
25. Crediting the balance to the
Safety Fund (Cl.16.3.2) Yes
CA Cl 16.3.2 shall be followed if
required
26. Evolving Maintenance Manual in
consultation with IE (Cl.17.3) Yes
Maintenance Manual will be evolved
as per clause 17.3 of CA
27. Not displaying advertisements
on the Site (Cl.17.15) Yes
Advertisements will not be displayed
all the times.
28. Constructing and handing over
Traffic Aid Posts (Cl.20.2) Yes
Will be provided as per CA Clause
20.2
29. Setting up and operationalizing
Medical Aid Posts (Cl.21.1) Yes
Will be provided as per CA Clause
21.1
30. Achieving Financial Close within
the specified period (Cl.24.1.1) Yes Obtained on 05.09.2012
31. Paying Damages for delay in
Financial Package Close
(Cl.24.1.1) No No delay was made.
32. Providing 3 copies of Financial
Package and Financial Model
(Cl.24.1.2) Yes Provided on 29.03.2012
33. Depositing specified inflows and
receipts in the Escrow Account Yes
Said deposits shall be made as per
CA clause 31.2
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 33
(Cl.31.2)
34. Payments from Escrow Account
as per specified order (Cl.31.3.1) Yes
CA clause 31.3.1 shall be followed
for payments from Escrow Account
35. Appropriation from Escrow
Account after Termination
(Cl.31.4.1) No
36. Effecting and maintaining
insurance cover (Cl. 32.1 and
32.2) Yes Executed
37. Depositing and using the
proceeds from insurance claims
(Cl.32.7) Yes Executed
38. Maintaining books of
accounts(Cl.33.1) Yes
As per clause 33.1 of CA Account
Book is maintained.
39. Appointing Statutory Auditors
(Cl.33.2.1) Yes
Gyanendra & Associates were
appointed on 21.12.2013 as
Statutory auditor as per CA clause
33.2.1.
40. Issuing notice for Force Majeure
Event (Cls. 34.5.1 and 34.5.2) Yes
Notice will be issued as and when
required.
41. Informing the Authority
regarding intent to Terminate
(Cl.34.8) Yes
Will be informed as per CA clause
34.8
42. Compensating the Authority for
material default (Cl.35.1) Yes
Compensation shall be paid as per
CA clause 35.1
43. Complying with the Divestment
Requirements (Cl.38.1) Yes Applicable in event of termination
44. Paying all costs incidental to
divestments (Cl.38.5) Yes Applicable in event of termination
45. Paying to the Authority the
benefits arising out of Change in
Law (Cl.41.2) Yes Cl 41.2 of CA shall be followed
46. Complying with General
Indemnity requirements (Cls 42.1
and 42.2) Yes
Complied as per CA clause 42.1 &
42.2
47. Allowing free access to the site
at all times to the Authority
(Cl.43.2) Yes
As per CA clause 43.2 NHAI will have
free access at all times
48. Amicably resolving disputes
(Cl.44.1 and 44.2) Yes
Disputes will be resolved as per CA
clause 44.1 & 44.2
49. Availability of Specified
Documents and documents for
inspection (Cls.45.1 and 45.2) Yes
All documents are available at site
with site Engineer.
50. Maintaining public relations
office and Complaints Register
(Cl.46.1) Yes
Same are maintained as per CA
clause 46.2
51. Inspecting Complaints Register
every day and taking prompt and
reasonable action (Cl.46.2) Yes
Same is being inspected as per CA
clause 46.2
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 34
52. Any other observation,
complaint or suggestion - -
7. CONSTRUCTION SCHEDULE
7.1 Project Milestone
Milestone
Financial
Percentage Date of Achievement of
Milestone as envisaged in
Concession Agreement
Remarks
Appointed Date(As
per Agreement)
0% 14 November,2013
Appointed Date of the
Project vide letter No
NHAI/RO-
Jammu/2010/11050/K
-N/252 dated 22
Nov,2013
Project Milestone 1 10%
(181.847 Crores)
(12 May,2014)
180th Day
Project Milestone 2 35%
(636.467 Crores)
(6 February,2015) 450th Day
Project Milestone 3 70%
((1272.929 Crores)
(3 December,2015)
750th Day
Project Milestone 4 100%
(1847.00 Crores)
(12 November,2016)
1095th Day
Scheduled
Completion date
7.2 Documents: Correspondence
NHAI Incoming
October, 2014
Sr.
No. Letter No. Date Issued To Subject Remarks
1.
11009/12/2013/KNCEL/
PIU-SML/1045
Date 22.09.2014
7.10.14 SCIA
Compliance to the decision
of Executive Committee
held on 30.07.2014
2.
11009/12/2013/KNCEL/
PIU-SML/1046
Date 22.09.2014
7.10.14 SCIA
Objection regarding
acquisition of Land
comprising in Kh. No.
629,631,632,633 Mohal
Chamukha /41
3.
11009/6/2013/KNCEL/
PIU-SML/1094
Date 7.10.2014
8.10.2014 SCIA
Submission of Statutory
Auditor Certificate up to 15
se[p 2014
4. 11011/32//2013/Meetin
g/ 15.10.2014 SCIA
Operationalization of PPP
monitors system and
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 35
PIU-SML/1152
Date 14.10.2014
creation of project specific
website.
5.
11011/27/2014/QPR/
PIU-SML/1153
Date 14.10.2014
16.10.2014 KNCEL
Regarding Quarterly
progress report ending
sept, 2014 to be submitted
to CVC.
6.
11011/26/2013/MR/
PIU-SML/1155
Date 14.10.2014
16.10.2014 KNCEL MIS Report
7.
11009/6/KNCEL/2012/
PIU-SML/1094
Date 07.10.2014
21.10.2014 SCIA
Submission of statutory
Auditor certificate up to 15
Sep 2014.
8.
11011/38/2013/IE-Acc/
PIU-SML/1194
Date 28.10.2014
29.10.2014 SCIA Renewal of Professional
Liability Insurance.
9.
11011/6/IE/2012/KNCEL
/
PIU-SML/1167
Date 27.10.2014
29.10.2014 SCIA
Regarding maintaining the
access of Rural and MDRs
constructed by HPPWD in
view for laning of Kiratpur
Nerchowk section NH-21
10.
11011/8/IE/2012/NHAI/
PIU-SML/1198
Date 29.10.2014
29.10.2014 SCIA
Independent Engineer
services for Rehabilitation
and Up – gradation to four
laning of Kiratpur to
Nerchowk section of NH-21
in the state of Punjab
Himachal Pradesh
11.
11011/20/2012/GEN
PIU-SML/1202
Date 30.10.2014
30.10.2014 SCIA
Operation and Maintance
of PPP projects on BOT (Toll
) Annuity mode during
operation period.
12
NHAI / PIU-RTK
/MISC./14-15
/1870
Date 27.10.2014
31.10.2014 NHAI
“ig age s including photos
of former Ministers etc on
National Highway.
November, 2014
1.
11009/7/2013/KNCEL/
PIU-SML/1273
Date 12.11.2014
13.11.2014 SCIA
Regarding problem facing
by commuters and general
public due to shabby
condition of NH-21 from
Kiratpur to Manali.
2.
11009/7/2013/KNCEL/
PIU-SML/1274
Date 12.11.2014
13.11.2014 SCIA
Slow Progress of
Maintenance of excitation
road from Kiratpur 73+200
to Nagchhala (Km
186+500)
3.
11011/01//2012/RTGS/
PIU-SML/1280
Date
14.11.2014 Branch Manager,
Canara Bank Transfer of USD -32373
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 36
4.
11011/01//2012/RTGS/
PIU-SML/1284
Date 14.11.2014
14.11.2014
The Chief
Manager Canara
Bank
Transfer of Fund through
RTGS /NEFT.
5.
11011/01//2012/RTGS/
PIU-SML/1294
Date 14.11.2014
14.11.2014
The Chief
Manager Canara
Bank
Transfer of Fund through
RTGS /NEFT.
6.
11009/8/2012/NHAI/
PIU-SML/1310
Date 17.11.2014
18.11.2014 SCIA
Public Private Partnership
of DBFOT Pattern under
NHDP-III Placement of sub
professional. Horticulture
cum Landscaping Expert.
7.
11009/8/2012/NHAI/
PIU-SML/1311
Date 17.11.2014
18.11.2014 SCIA
Public Private Partnership
of DBFOT Pattern under
NHDP-III Placement of sub
professional.- E &M Expert.
8.
11009/8/2012/NHAI/
PIU-SML/1312
Date 17.11.2014
18.11.2014 SCIA
Public Private Partnership
of DBFOT Pattern under
NHDP-III Placement of sub
professional.
9.
11009/8/2012/NHAI/
PIU-SML/1313
Date 17.11.2014
18.11.2014 SCIA
Public Private Partnership
of DBFOT Pattern under
NHDP-III Site visit of Road
Safety Expert.
10.
11011/01//2012/RTGS
/ PIU-SML/1326
Date 18.11.2014
18.11.2014
The Chief
Manager Canara
Bank
Transfer of Fund through
RTGS /NEFT.
11.
11011/01//2012/RTGS
/ PIU-SML/1327
Date 18.11.2014
18.11.2014
The Chief
Manager Canara
Bank
Transfer of Fund through
RTGS /NEFT.
12.
11009/6/2013KNCEL/
PIU-SML/1332
Date 18.11.2014
18.11.2014 IL&FS Public Grivances
13.
11009/13/2013/IL&FS/
PIU-SML/1318
Date 17.11.2014
20.11.2014
The Executive
Engineer I&PH
Division
Estimate of Rs. 4.21 crores
under I&PH division
Sundernagar.
14.
NHAI/RO/CHD/11011/
PD-SHM/NH-21
KIR- N.CHK /165
Date 15.11.2014
20.11.2014
The Project
Director NHAI PIU
Shimla.
Slow progress of
Maintenance of Existing
Road from Kiratpur 73+200
to Ner chow Km 186+500.
15.
NHAI/RO/CHD/11011/
PD-SHM/NH-21 KIR-
N.CHK /167
Date 15.11.2014
20.11.2014 IL&FS DBFOT pattern under NHDP
(MPR No. 24).
16.
NHAI/RO/CHD/11011/
PD-SHM/NH-21 KIR-
N.CHK /169
Date 15.11.2014
20.11.2014 IL&FS Quarterly progress Report
(QPR- 8).
17. 11009/7/IE/2013/K-N/ 26.11.2014 SCIA Estimate for Re-
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 37
PIU-SML/1369
Dated :- 21.11.2014
habilitation of Chowkidar
hut cum store, Plan
display hut and irrigation
tank at Ropri (Sunder
Nagar) due to
construction of 4 lane NH
road from Chandigarh to
Manali.
18.
11009/14/2013/KN/
PIU-SML/1370
Dated :- 21-11-2014
26.11.2014 CGM/RO
Chandigarh
Request to release the
performance security Bank
Guarantee of Rs 90.92
19. 11009/5/2013/K-N/
PIU-SML/1404 28.11.2014
Labour Officer-
cum-conciliation
Officer, Bilaspur
Regarding Submission of
Demand Notice.
20.
11009/7/IE/2013/K-N/
PIU-SML/1401
Dated :- 28-11-2014
29.11.2014 SCIA
Slow Progress of
maintenance of Existing
Road from Kiratpur
(73+200) to Nagchhala (Km.
186+500).
December, 2014
1. No. 11013/1/2k Env. 121
Date 28.11.2014 1.12.2014 SCIA Circular.
2
11011/01//2012/RTGS/
PIU-SML/1421
Date 28.11.2014
13.12.2014 SCIA
To Grant NOC for
Establishment of Inter State
Check Post
3.
11011/01//2012/RTGS/
PIU-SML/1423
Date 28.11.2014
13.12.2014 SCIA
Four Laning of Kiratpur to
Nerchowk Section form Km.
73.200 Km. 186.500 of NH-
21 in the State of Punjab /
Himachal Pradesh on DBFOT
basis – Extension of Project
Milestone –II.
4.
11011/01//2012/RTGS/
PIU-SML/1436
Date 9.12.2014
10.12.2014 SCIA
Four Laning of Kiratpur to
Nerchowk Section form Km.
73.200 Km. 186.500 of NH-
21 in the State of Punjab /
Himachal Pradesh on DBFOT
basis – Special Repair and
Maintance of NH205 (Old
NH-21) Chandigarh – Manali
Highway between Km. 82.00
to Km. 19.00 reg.
5.
PW-MDI-DB-Hort. Pandoh
/2014 187496-97
Date 12.12.2014
15.12.2014
General Manager
& Project
Director.
Rehabilitation of Chowkidar
Hut cum store, plat display
hut and irrigation tank
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 38
Ropari (Sunder Nager). Due
to construction of four
lanes NH from CHD. To
Manali.
6.
11011/01//2012/RTGS/
PIU-SML/1469
Date 15 .12.2014
17.12.2014 SCIA Submission of demand
Notice
7.
11011/01//2012/RTGS/
PIU-SML/1470
Date 15 .12.2014
17.12.2014 SCIA
Four Laning of Kiratpur to
Nerchowk section form Km
. 73.200 to Km. 186+500 of
NH-21 in the state of
Punjab / Himachal Pradesh
on DBFOT basis – Reg
Deviations in quantity of
sub- station and HT/LT line
shafting the proposed four
lane road from Dadour to
Daundi Nachaa under ESDN
Nerchowk .
8.
11011/01//2012/RTGS/
PIU-SML/1517
Date 18 .12.2014
22.12.2014 SCIA
Standard public notices of
user fee rated to be
publican on the Newspaper
by the concessionaires of
BOT ( Toll ) OMT Project.
9.
11011/01//2012/RTGS/
PIU-SML/1471
Date 15 .12.2014
22.12.2014 SCIA
Use of Terra Zyme as a
replacement for GSB and
WSB and WBW in Highway
works.
10.
11011/01//2012/RTGS/
PIU-SML/1489
Date 17 .12.2014
22.12.2014
Dr. Nishant
Shrivastava.
Associate (KNCEL)
Manhandling at Tunnel -1, 2
Village Mehla and Viaduct
(15+070), dated
11.12.2014.
11.
11011/01//2012/RTGS/
PIU-SML/
Date 22 .12.2014
22.12.2014 SCIA NH-21 Repair
12.
11011/01//2012/RTGS/
PIU-SML/1536
Date 23 .12.2014
23.12.2014
Dr. Nishant
Shrivastava.
Associate (KNCEL)
Reimbursement of
remuneration cost and
Expenses of the
Independent consultants
for the month of November
13.
NHAI/11016/9/2011/HP-
2011/ 2167
Date 24.12.2014
30.12.2014 Sh. Satish Kaul,
PD, PIU Shimla. Surprise Inspection
NHAI Outgoing
October, 2014
Sr.
No. Letter No. Date Issued To Subject Remarks
1. SCIA/001/14-15/TL/NHAI- 10.10.2014 NHAI Submission of Monthly
Progress Report
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 39
00497
2. SCIA/001/14-15/TL/NHAI-
00498 10.10.2014 NHAI Submission of QPR No.8.
3. SCIA/001/14-15/TL/NHAI-
00500 13.10.2014
NHAI
Accident Report for
Kiratpur Nerchowk
Project.
4. SCIA/001/14-15/TL/NHAI-
00507 27.10.2014
NHAI
Submission of service Tax
Challan for the period
from 1th July 2014 to 30
September 2014, for
reimbursement of service
Tax.
5. SCIA/001/14-15/TL/NHAI-
00515 31.10.2014
NHAI
“ig age s I luding Photo
of Former Minsters etc,
on National Highways.
November, 2014
1. SCIA/001/14-15/TL/NHAI-
00 516 3.11.2014 NHAI
Slow progress of
Maintenance of Existing
Road from Kiratpur
(73+200 to Nagchala (Km
190+000).
2. SCIA/001/14-15/TL/NHAI-
00517 6.11.2014 NHAI
Requirement of Risk and
coverage policies as per
the consultancy
agreement
3. SCIA/001/14-15/TL/NHAI-
00518 6.11.2014
NHAI
Renewal of professional
indemnity insurance.
4. SCIA/001/14-15/TL/NHAI-
00520 8.11.2014
NHAI
Accident Report for
Kiratpur Nerchowk
Project.
5. SCIA/001/14-15/TL/NHAI-
00525 14.11.2014
NHAI
Site Visit of Road safety
Expert.
6. SCIA/001/14-15/TL/NHAI-
00528 18.11.2014
NHAI
Site Visit of Road safety
Expert.
7. SCIA/001/14-15/TL/NHAI-
00529 19.11.2014
NHAI
Request to release the
performance security
Bank Guarantee.
8. SCIA/001/14-15/TL/NHAI-
00531 21.11.2014 NHAI
Requested for removal of
encroachment from
Government land
comprised in Khasra no –
145 and 150 situated in
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 40
village Muhal Ratt.
9. SCIA/001/14-15/TL/NHAI-
00533 24.11.2014 NHAI
Site Visit of Traffic and
Transportation Expert.
10. SCIA/001/14-15/TL/NHAI-
00540 27.11.2014 NHAI
Site visit of Road Safety
Expert.
December, 2014
1.
SCIA/001/14-15/TL/NHAI-
00545 2.12.2014 NHAI
Extension Of Project
Milestone –II.
2. SCIA/001/14-15/TL/NHAI-
00551 9.12.2014 NHAI
Accident Report for
Kiratpur Nerchowk
Project.
3.
SCIA/001/14-15/TL/NHAI-
00552 9.12.2014
NHAI
Submission of Monthly
Progress Report (MPR
No.26)
4.
SCIA/001/14-15/TL/NHAI-
00553 9.12.2014
NHAI
Proposal of construction
of Major Bridge @ Ch.
24+219
5.
SCIA/001/14-15/TL/NHAI-
00558 16.12.2014
NHAI
Estimate for
Rehabilitation of
Chowkidar Hut cum
store, Plant display hut
and Irrigation tank at
Ropri (Sunder Nagar) due
to construction of four
lane NH road CHD To
Manali.
6.
SCIA/001/14-15/TL/NHAI-
00561 19.12.2014
NHAI Site visit of Legal Expert.
7.
SCIA/001/14-15/TL/NHAI-
00563 19.12.2014
NHAI
Development of Road site
Amenities.
8.
SCIA/001/14-15/TL/NHAI-
00564 22.12.2014 NHAI
Submission of Road
Accident Report of
Bilaspur Distt for the
Month of Nov 2014.
Concessionaire Incoming
October, 2014
1.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/879
Dated 30 .10.2014
4.10.2014 SCIA
Submission of Revised Plan
& Profile from Km.
178+000 to 182+215 as per
clause 12.3 of CA.
2. ITNL-KNCL/PRJ/TECH/ 4.10.2014 SCIA Submission of Design and
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 41
ICO-581/2014/898
Dated 30.10.2014
Drawing of Superstructure
of Minor Bridge @ Ch.
135+990 as per clause
12.3 of CA.
3.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/899
Dated 6.10.2014
6.10.2014 SCIA
Submission of General
Arrangement Drawing for
major bridge of 25+836.5
(C.A. Ch. 26+184 ) as per
clause 12.3 of CA.
4.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/901
Dated 6 .10.2014
6.10.2014 SCIA
Submission of Materials of
slop stabilization system
high Tensile Steel wire
Mesh, type TECCO of M/s
Geobrugg India Pvt. Ltd.
5.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/901 (A)
Dated 6.10.2014
6.10.2014 SCIA
Submission of Monthly
Progress Report for the
Mo th of “epte er
6.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/902
Dated 6 .10.2014
6.10.2014 SCIA
Submission of Design and
Drawing of Abutment A2 of
Major Bridge @ Ch
143+950 as per clause
12.3 of CA.
7.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/906
Dated 10.10.2014
11.10.2014 SCIA
Mix Design of M-15, M-20,
M-25, M-30, M-35, M-35
(Pile), M-40, M-45 & M50.
8.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/907
Dated 10.10.2014
11.10.2014 SCIA
Mix Design of M-15, M-20,
M-25, M-30, M-35, M-35
(Pile), M-40, M-45 & M50.
9.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/908
Dated 10.10.2014
11.10.2014 SCIA Mix Design of wet
shotcrete (M25A10)
10.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/910
Dated 13.10.2014
13.10.2014 SCIA
Submission of Road
Accident Report for the
Month of September 2014.
11.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/913
Dated 14.10.2014
14.10.2014 SCIA
Submission of Design and
Drawing of (1*4*4)m Cast
In-Situ Box Culvert as per
clause 12.3 of CA.
12. ITNL-KNCL/PRJ/TECH/ 16.10.2014 SCIA Submission of Concrete
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 42
ICO-581/2014/914
Dated 15.10.2014
Mix design for M-15,M-
20(PCC),M20 RCC, M-20
(KERB), M25, RCC, M35 &
M40.
13.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/915
Dated 16.10.2014
16.10.2014 SCIA Approval for Filter Media
Mix Design.
14.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/916
Dated 15.10.2014
20.10.2014 SCIA
Submission of Existing road
(shoulder) soil Test report
at Km. 8+000 to 12+500
BHS side.
15.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/917
Dated 16.10.2014
17.10.2014 SCIA Mix Design of wet
shotcrete (M-25 A-10)
16.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/918
Dated 16.10.2014
17.10.2014 SCIA
Submission of Geological
Mapping of Portals and
Tunnel.
17
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/921
Dated 17.10.2014
21.10.2014 SCIA
Submission of Design and
Drawing of substructure of
Viaduct Ch. 15+077.
18
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/922
Dated 20.10.2014
21.10.2014 SCIA
Submission of Design and
Drawing of Bearing layout,
Design forces and
Movement on bearing for
different Minor Bridges.
19
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/923
Dated 15.10.2014
21.10.2014 SCIA
Submission of Design and
Drawing of superstructure
of Minor Bridge @ Ch.
14+712 (CA. Ch. 14+750) as
per clause 12.3.
20
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/925
Dated 29.10.2014
30.10.2014 SCIA
Vendor concurrence for
supply of expansion joints
and bearings, M/s Sanfields
India Ltd.
21
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/926
Dated 29 .10.2014
29.10.2014 SCIA
Submission of Design and
drawing of Dimensional
and Reinforcement Details
of pier well Major Bridger
@ Ch. 1+085 as per clause
12.3 of CA.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 43
22
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/927
Dated 29.10.2014
29.10.2014
SCIA
Submission of Design and
Drawing of pier Layout and
Details of Pole for A-2 of
Major Bridge @ Ch.
130+165 as per clause 12.3
of CA.
23
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/928
Dated 29.10.2014
29.10.2014 SCIA
Submission of Design and
Drawings of Dearing Layout
design forces and
Movement on Bearing for
Minor Bridge @ Ch.
153+635.
24
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/929
Dated 30.10.2014
30.10.2014 SCIA
MTC Submitted for HDPE
Duct, Wedges and Anchors
to be used in PSC Girders
of Project.
25
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/930
Dated 31.10.2014
31.10.2014 SCIA
Submission of Plan and
Profile ACC Link Road from
Km. 0+000 to 1+992 (R0) as
Per clause 12.3 of CA.
November 2014
Sr.
No. Letter No. Date Issued To Subject
1.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/983
Dated 4.11.2014
5.11.2014 SCIA
Slow Progress of
Maintenance of Existing
Road from Kiratpur 73+200
to Nagchhala Km 186+500.
2.
ITNL-KNCL/PRJ/TECH/
CLO-581/2014/935
Dated 5.11.2014
7.11.2014 SCIA Various h
Hindrances at site.
3.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/937
Dated 6.11.2014
7.11.2014 SCIA
Submission of Video grapy
of KNCEL Project as per
clause 13.6 of CA.
4.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/940
Dated 5.11.2014
10.11.2014 SCIA
Submission of Design and
Drawing of Substructure
Abutment A1 and Pier P0
of MJB @ Ch : 25+837 (C A
: 26+184 )as per clause
12.3 of CA.
5.
ITNL-KNCL/PRJ/TECH/
CLO-581/2014/941
Dated 7.11.2014
7.11.2014
SCIA
Obstruction by Kishan
Morcha and local people at
Dadour to Ner Chowk by
Pass of Kiratpur to
Nerchowk Project.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 44
6.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/943
Dated 7.11.2014
7.11.2014 SCIA
Submission of Road
Accident Report for the
Month of October 2014.
7.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/944
Dated 8.11.2014
10.11.2014 SCIA
Shifting of Minor Bridge at
Ch. 153+635 by 03 m
towards Kiratpur Side.
8.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/946
Dated 8.11.2014
10.11.2014 SCIA
Approval of vendor M/s
Jindal Power and steel
Limited (JPSL ) for
procurement of structural
steel plates of size 16
x3500 x 12500 )mm E 300
BR Grade conforming to IS
: 2062 .
9.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/948
Dated 10.11.2014
12.11.2014 SCIA
Submission of Test Report
of Mix Design of Filter
Media with GHV Crusher
Aggregate of
approval.
10.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/954
Dated 11.11.2014
12.11.2014 SCIA
Submission for Approval of
Borrow area -08 at Ch.
177+800 RHS
11.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/955
Dated 12.11.2014
12.11.2014 SCIA
Submission of Statutory
Auditor Certificate up to 30
Sep 2014.
12.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/956
Dated 12.11.2014
12.11.2014 SCIA
Submission of Escrow
Accounts as per clause
31.1.1 of C.A.
13.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/957
Dated 11.11.2014
13.11.2014 SCIA
Submission of Bearing
drawings for Major bridge
Ch- 0+450 as per clause
12.3 of CA.
14.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/963
Dated 14.11.2014
14.11.2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk
186+500.
15.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/964
Dated 14.11.2014
14.11.2014 SCIA
Submission of the updated
revision for final design
and drawing of Tunnel -4 (
Ch 148+500 to 149+765 )
16.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/962
Dated 14.11.2014
17.11.2014 SCIA
Submission of OGL soil (
after C &G ) Test Report
from Km. 0+000 to 6+000
LHS side and 0+000 to
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 45
5+000 RHS side.
17.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/966
Dated 17.11.2014
15.11.2014 SCIA
Movement Deformation at
Tunnel 1 Portal 2 Right
lateral and frontal slopes.
18.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/967
Dated 14.11.2014
17.11.2014 SCIA
Geological Mapping of
Portal of Tunnel main
tunnel Portal -1.
19.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/968
Dated 17.11.2014
18.11.2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk (Km
186+500)
20.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/970
Dated 18.11.2014
18.11.2014 SCIA
Submission of Method
statement for construction
of Granular sub base (GBS)
Layer of section -1.
21.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/973
Dated 19.11.2014
20.11.2014 SCIA
Proposal for VUP against
PUP at Chainage 133+690
(CA Chainage 133+735)
22.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/976
Dated 20.11.2014
20.11.2014
SCIA
Joint Trail Assembly
Inspection for steel girder
of Minor Bridge @ Ch
135+990
23.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/977
Dated 20.11.2014
20.11.2014 SCIA
Compliance for site
instruction issued by Mr.
Sanjay Kumar , IE
representative for PCC
laying of slab culvert Ch
06+586.
24.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/978
Dated 20.11.2014
20.11.2014 SCIA
Compliances for site
instruction issued by Mr.
Pankaj Kumar , IE
Representative for back
filling of box culvert @Ch
02+348,@ Ch 03+000 @ Ch
03+508,, @Ch 05+511.
25.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/979
Dated :- 20.11.2014
22.11.2014 SCIA
Inventory of Minor inter
section/Access Road &
Major Inter section of
Proposed alignment.
26.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/980
Dated :-21.11.2014
22.11.2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk (KM
186+500)
27. ITNL-KNCL/PRJ/TECH/ 24.11.2014 SCIA Submission of Design and
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 46
ICO-581/2014/981
Dated :-22.11.2014
drawings for Pier Cap of P1
Pier of Major Bridge at Ch.
23+155 as per clause 12.3
of C.A.
28.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/982
Dated :-22.11.2014
24.11.2014 SCIA
Mix Design M15, M20,
M25, M30, M35 (Pile),
M40, M45 & M50 WITH
acc Cement (Section-II)
29.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/983
Dated :-22.11.2014
24.11.2014 SCIA
Mix Design M15, M20,
M25, M30, M35, M35
(Pile) with Ambuja Cement
(Section-II)
30.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/985
Dated :-22.11.2014
24.11.2014 SCIA
Submission of Mix Design
of Granular Sub-base (GSB)
of Section-I.
31.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/986
Dated :-22.11.2014
24-11-2014 SCIA
Submission of COS for
Major Bridges, Minor
Bridges, VUP & Box
Culvert.
32.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/987
Dated :-25-11-2014
25-11-2014 SCIA
Trial Assembly Inspection
for steel truss of Major
Bridge @ Ch. 0+450.
33.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/988
Dated :-25-11-2014
25-11-2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk (KM
186+500)
34.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/989
Dated :-25-11-2014
25-11-2014 SCIA Extension of Project
Milestone-II.
35.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/990
Dated :-26-11-2014
26-11-2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk
(K.m. 186+500)
36.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/991
Dated :-25-11-2014
27-11-2014 SCIA
Submission of Monthly
Progress Report for the
Mo th of O to er .
37.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/993
Dated :-27-11-2014
27-11-2014 SCIA
Inventory of Minor inter
section /Access Road &
Major Inter section of
proposed alignment
(Sundernagar bypass)
38.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/998
Dated :-27-11-2014
27-11-2014 SCIA
Submission of credential of
M/s Nina Concrete system
Pvt Ltd for Tunnel
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 47
Waterproofing Membrane.
39.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/999
Dated :-27-11-2014
27-11-2014 SCIA
Slop stability analysis and
back analysis for Tunnel 1
Portal 2 after
Movement/Deformation at
right lateral and frontal
slopes.
40.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1000
Dated :-27-11-2014
27-11-2014 SCIA
Deviations in quantity of
Sub-station and HT/LT line
shifting along the proposed
four lane road from
Dadour to Daundi Nagchala
under ESDN Nerchowk.
41.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1001
Dated :-27-11-2014
27-11-2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk (KM
186+500)
42.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1002
Dated :-28-11-2014
29-11-2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk (KM
186+500)
December 2014
1.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1006
Dated 29.11.2014
1.12.2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk
(Km.186+500 )
2.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1011
Dated 28.11.2014
1.12.2014 SCIA
Submission of Design and
Drawing for Sub Structure
of Minor Bridge at Ch.
179+062 (CA 185+785)
after revised FRL as per
clause 12.3 CA.
3.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1012
Dated 28.11.2014
1.12.2014 SCIA
Submission of Design and
Drawing for Pier Cap of P1
and P2 pier of Major Bridge
at Ch. 130+165 as per
clause 12.3of CA.
4.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1014
Dated 1.12.2014
1.12.2014 SCIA
Submission of Design and
Drawing for footing and
pier for LP1 of Major
Bridge at Ch. 135+125 as
per clause 12.3 of CA.
5. ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1017 3.12.2014 SCIA
Submission of typical
Design and
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 48
Dated 1 .12.2014 Drawing for Reinforced Soil
Retaining wall using panels
by M/s Sachi Geosynthetics
Pvt. Ltd.
6.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1020
Dated 2.12.2014
3.12.2014 SCIA
Compliance for Design and
Drawing for MJB @
152+100 as per clause
12.3 of CA.
7.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1021
Dated 2.12.2014
3.12.2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk
(Km.186+500 )
8.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1022
Dated 2.12.2014
2.12.2014 SCIA
Quality Assurance Plan
(QAP) (R1) of Granular Sub
Base.
9.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1023
Dated 2.12.2014
2.12.2014 SCIA
Submission for Third party
Test Report of Cement and
steel for section –III.
10.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1025
Dated 3.12.2014
3.12.2014 SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk
(Km.186+500)
11.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1026
Dated 3.12.2014
3.12.2014 SCIA
Force Majeure – Article 34-
Clause 34.2d Non Political
event.
12.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1027
Dated 29.12.2014
3.12.2014 SCIA
Slope Protection System
with Reinforced soil as per
clause 12.3 of CA.
13.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1028
Dated 2.12.2014
3.12.2014 SCIA
Slope protection system
with reinforced soil (M/s
Tenax) as per clause of CA.
14.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1029
Dated 4.12.2014
8.12.2014 SCIA
Proposal of construction of
Major Bridge @ Ch
24+2019.
15.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1033
Dated 8.12.2014
11.12.2014 SCIA
Concurrence of Plan and
Profile of ACC Link Road
form Km 00+000 to 01+992
as per clause 12.3 of CA.
16.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1034
Dated 8.12.2014
9.12.2014 SCIA
Regarding Joint Assembly
Inspection for steel Girder
of Major Bridge @ Ch
135+125.
17. ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1035 9.12.2014 SCIA
Submission of Road
Accident Report for the
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 49
Dated 9.12.2014 month of Nov, 2014.
18.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1037
Dated 12.12.2014
12.12.2014 SCIA
Submission of Design and
Drawing of pile lay out and
Details of pile for A1 of
Major Bridge @ Ch.
23+155.
19.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1035 (A)
Dated 7.12.2014
13.12.2014 SCIA
Submission of monthly
Progress Report for the
Mo th of No e er .
20.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1038
Dated 12.12.2014
13.12.2014 SCIA
Manhandling at Tunnel -1
Portal -2 Village Mehla and
viaduct 15+070 ) , Dated –
11.12.2014
21.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1039
Dated 12.12.2014
13.12.2014 SCIA
Regarding of
Administrative / Police for
tunnel -1 Portal- 2. Village
Mahila & viaduct at
15+070.
22.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1040
Dated 11.12.2014
13.12.2014
SCIA
Maintenance of Existing
road from Kiratpur
(73+200) to Nerchowk
(Km.186+500 )
23.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1043
Dated 13.12.2014
15.12.2014 SCIA
Submission of Design and
Drawing for sub Structure
of Minor Bridge Ch.
152+628 (Ch 152+835)
24.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1044
Dated 13.12.2014
15.12.2014 SCIA
Submission of Third party
test report of Various
materials.
25.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1049
Dated 15.12.2014
15.12.2014 SCIA
Trial Assembly Inspection
for steel truss of Major
Bridge @ Ch. 0+450 and
steel Girder of Major
Bridge @ Ch. 155+880.
26.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1057
Dated 18.12.2014
19.12.2014 SCIA
Submission of Profile for
Rebar of Reinforcement
steel vendors namely M/s
Hilti India Private Limited ,
M/s Fosroc India Private
Ltd.
27.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1058
Dated 18 .12.2014
19.12.2014 SCIA
Approval for mix design of
Wet Mix Macadam
(Section -1 ).
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 50
28.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1059
Dated 20.12.2014
20.12.2014 SCIA
Submission of Road
Accident Report of Bilaspur
district for the month of
Nov 2014.
29.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1062
Dated 20.12.2014
20.12.2014 SCIA
Inventory for ACC link Road
Km. 0+000 to 1+991 (ROW
20m )
30.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1064
Dated 20.12.2014
22.12.2014 SCIA
Submission of Drawing for
strip seal Expansion joint
by m/s mageba (India )Ltd
as per clause 12.3 of CA.
31.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1065
Dated 22.12.2014
22.12.2014 SCIA
Submission of Borrow area
09 at Ch. 187+500 LHS of
Section - III.
32.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1066
Dated 22.12.2014
22.12.2014 SCIA Submission of Mix design
of M 20 PCC of Section -III.
33.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1067
Dated : 22.12-2014
22.12.2014 SCIA
Submission of OGL soil test
report from Km. 154+050
to 155+000 at Dehar By
Pass.
34.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1068
Dated : 22 .12-2014
22.12.2014 SCIA
Third Party Test Report
from Independent
Laboratory ( Section- II)
35.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1069
Dated : 22 .12-2014
22.12.2014 SCIA
Observation of Concrete
Mix Design (Shotcrete
M25 A10)
36.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1070
Dated : 22 .12-2014
22.12.2014 SCIA Mix design of Filter Media
section –II.
37.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1074
Dated : 27 .12-2014
29.12.2014 SCIA
Submission of Design
calculation and shop
drawing for POT /PTFE
Bearings by M/s Sanfield
(India ) Limited as per
clause 12.3 of CA.
38.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1075
Dated : 26 .12-2014
29.12.2014 SCIA
Submission of Design and
Drawing for Pier P1 of
Major Bridge at Ch.
25+836.5 (CA 26+184 )
39.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1076
Dated : 26 .12-2014
29.12.2014 SCIA
Submission of Design and
Drawing for abutment A1
of Minor Bridge at Ch.
149+868 ( CA Ch. 150+050
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 51
)
40.
ITNL-KNCL/PRJ/TECH/
ICO-581/2014/1077
Dated : 29 .12-2014
29.12.2014 SCIA
Trial Assembly inspection
for plate girder of 74 m
span ( set 3&4) for Major
Bridge @ Ch. 135+125
Concessionaire Outgoing
October 2014
1. SCIA/001/13-14/TL/
KNCEL-00493 7.10.2014 KNCEL
Submission of revised plan
& profile from Km 178+000
to Km 182.215 as per
clause 12.3 of CA.
2. SCIA/001/13-14/TL/
KNCEL-00494 8.10.2014 KNCEL Public Grievances.
3. SCIA/001/14-15/TL/
KNCEL-00495 9.10.2014 KNCEL
Submission of Statutory
Auditor certificate up to
15th sep 2014.
4. SCIA/001/14-15/TL/
KNCEL-00496
10.10.2014
KNCEL
Submission of design &
Drawing of super structure
for Minor bridge @ Ch.
135+900 as per clause 12.3
of C.A.
5. SCIA/001/14-15/TL/
KNCEL-00497 10.10.2014 KNCEL
Submission of Monthly
Progress Report ( MPR.No
24)
6. SCIA/001/14-15/TL/
KNCEL-00498 10.10.2014 KNCEL
Submission of Quarterly
Progress Report (QPR-
No.8).
7 SCIA/001/14-15/TL/
KNCEL-00501 14.10.204
KNCEL
Observations of Concrete
Mix Design ( Shotcrete M-
25 A-10
8 SCIA/001/14-15/TL/
KNCEL-00502 18.10.2014
KNCEL
Inspection of NHAI
Vigilance team on 16 & 17
October ,2014.
9 SCIA/001/14-15/TL/
KNCEL-00503 25.10.2014
KNCEL
Geological Mapping of
Portal of Tunnel –Main
tunnel Portal-1.
10 SCIA/001/14-15/TL/
KNCEL-00504 27.10.2014 KNCEL
Soil Test Report of Existing
Pavement at Ch. 8+00 to
12+500 BHS.
11 SCIA/001/14-15/TL/
KNCEL-00505 27.10.2014 KNCEL
Submission of Pile Load
Test Report for Minor
Bridge at Ch. 0+450 as Per
clause 12.3 of C.A.
12 SCIA/001/14-15/TL/
KNCEL-00506 27.10.2014 KNCEL
Observation of Concrete
Mix Design ( Shotcrete M-
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 52
25, A10)
13 SCIA/001/14-15/TL/
KNCEL-00508 27.10.2014 KNCEL Non Conformance Report
14 SCIA/001/14-15/TL/
KNCEL-00509 29.10.2014 KNCEL
Inventory of Minor Inter
Section / Access Road &
Major Inter Section of
Proposed alignment.
15 SCIA/001/14-15/TL/
KNCEL-00510 30.10.2014 KNCEL
Submission of GAD for
Major Bridge @ Ch
25+836.5 (CA 26+184 ) as
per Clause 12.3 of CA.
16 SCIA/001/14-15/TL/
KNCEL-00511 30.10.2014 KNCEL
Submission of Design and
Drawing of Superstructure
of minor Bridge Ch.
15+077 as Per Clause 12.3
of CA.
17 SCIA/001/14-15/TL/
KNCEL-00512 30.10.2014 KNCEL
Submission of Design and
Drawing of Substructure of
(1*1*4)m cast in situ Box
Culvert as per clause 12.3
of CA.
18 SCIA/001/14-15/TL/
KNCEL-00513 30.10.2014 KNCEL
Monthly Inspection of
Project Highway.
19. SCIA/001/14-15/TL/
KNCEL-00514 30.10.2014
KNCEL
Variation of Crust thickness
as per & Longitudinal
profile (C.A)
November 2014
Sr.
No. Letter No. Date Issued To Subject
Remark
s
1. SCIA/001/14-15/TL/
KNCEL-00519 7.11.2014 KNCEL
Movements \Deformation
at Tunnel -1 Portal 2 right
lateral and frontal slopes.
2. SCIA/001/14-15/TL/
KNCEL-00523 11.11.2014 KNCEL
I.E Monthly Inspection of
Project Highway.
3. SCIA/001/14-15/TL/
KNCEL-00521 10.11.2014 KNCEL
Submission of Monthly
Progress Report (MPR No.
25)
4. SCIA/001/14-15/TL/
KNCEL-00524 13.11.2014 KNCEL
Submission of plan and
profile of ACC Link road
from Km 0+000 to 1+992
as per clause 12.3 of C.A.
5. SCIA/001/14-15/TL/
KNCEL-00526 17.11.2014 KNCEL
Non Conformation Report
(VIL/ Mat/002 )
6. SCIA/001/14-15/TL/
KNCEL-00527 17.11.2014 KNCEL
Compliance of I.E
observation during Team
leader visit on dated
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 53
4.11.2014 (through –email)
7 SCIA/001/14-15/TL/
KNCEL-00529 19.11.2014
KNCEL
Request to release the
performance security Bank
Guarantee.
8 SCIA/001/14-15/TL/
KNCEL-00530 21.11.2014
KNCEL
Concurrence of Source for
Procurements of Structural
steel plates (Sizes 12500
mmX3500mm X16mm
)from M/S Jindal Steel and
Power Limited (JSPL)
9 SCIA/001/14-15/TL/
KNCEL-00532 21.11.2014
KNCEL
Concurrence of Borrow
Area No-8 for Filling
Embankment construction,
Section –III (M/S GHV Infra.
10 SCIA/001/14-15/TL/
KNCEL-00534 24.11.2014 KNCEL
Geological study note on
the status of Excavation of
Tunnels of ongoing works
by Sr. Geologist.
11 SCIA/001/14-15/TL/
KNCEL-00535 24.11.2014 KNCEL
Submission of Design and
Drawing of Substructure
Abutment A1 and Pier P0
for Major Bridge @ Ch.
25+837 (CA. 26+184) as per
clause 12.3 of C.A.
12 SCIA/001/14-15/TL/
KNCEL-00536 24.11.2014 KNCEL
Submission of Design &
Drawing of Bearings of
Minor Bridge as per CA. @
Ch. 0+450. As per clause
12.3 of C.A.
13 SCIA/001/14-15/TL/
KNCEL-00537 24.11.2014 KNCEL
Vendor concurrence for
supply of expansion joints
& Bearings, M/s Sanfields
India Ltd. Submission of
credentials and technical
data etc..
14 SCIA/001/14-15/TL/
KNCEL-00538 24.11.2014 KNCEL
Submission of Design &
Drawing of Substructure
Abutment LA1-RA1 and
RA1-LA2 for Minor Bridge
@ Ch. 14+708 as per clause
12.3 of C.A.
15 SCIA/001/14-15/TL/
KNCEL-00539 24.11.2014 KNCEL
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 54
Proposal for VUP at
Chainage 133+690 (C.A.
Chainage 133+735)
December 2014
1. SCIA/001/14-15/TL/
KNCEL-00541 1.12.2014 KNCEL
Extension of project
Milestone -II.
2. SCIA/001/14-15/TL/
KNCEL-00542 1.12.2014 KNCEL
Submission of Design and
Drawing of substructure
abutment A2 for major
Bridge @ Ch 143+950 as
per clause 12.3 of CA.
3. SCIA/001/14-15/TL/
KNCEL-00543 1.12.2014 KNCEL
Submission of Revised
Drawing of bearings of
various Badges as per
clause 12.3 of CA.
4. SCIA/001/14-15/TL/
KNCEL-00544 1.12.2014 KNCEL
Regarding I.E Monthly
Inspection of Project
Highway.
5. SCIA/001/14-15/TL/
KNCEL-00546 3.12.2014 KNCEL
Slope stability analysis and
back analysis for Tunnel -1
Portal 2 after /deformation
at right lateral and frontal
slopes.
6. SCIA/001/14-15/TL/
KNCEL-00547 3.12.2014 KNCEL
Submission of Design and
Drawing for Bearing of
Various Bridges as per
clause 12.3 of CA.
7 SCIA/001/14-15/TL/
KNCEL-00548 3.12.2014
KNCEL
Submission of Design and
Drawing of Bearing of
Bridges at Ch. 153+820 ,
157+750 ( Composite span
) & 157+750 ( RCC span )
as per clause 12.3 of CA.
8 SCIA/001/14-15/TL/
KNCEL-00549 3.12.2014
KNCEL
Submission of Design and
Drawing of superstructure
of Minor Bridge @ Ch
14+750 as per clause 12.3
of CA.
9 SCIA/001/14-15/TL/
KNCEL-00550 8.12.2014
KNCEL
Force Majeure – Article 34-
Clause. 34.2 d Non Political
event.
10 SCIA/001/14-15/TL/
KNCEL-00555 10.12.2014 KNCEL
Granular sub base (GSB
Material.
11 SCIA/001/14-15/TL/
KNCEL-00556 10.12.2014 KNCEL
Road safety Report of Road
Safety Expert I.E.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 55
12 SCIA/001/14-15/TL/
KNCEL-00559 17.12.2014 KNCEL
Procurements of water
proofing membrane from
M/s plastisell SRL, Italy
though M/s Nina Concrete
System Mumbai (India) for
tunnel Work.
13 SCIA/001/14-15/TL/
KNCEL-00560 17.12.2014 KNCEL
Monthly inspection of
Project Highway.
14 SCIA/001/14-15/TL/
KNCEL-00565 22.12.2014 KNCEL
Deviation in quantity of
substation and HT/LT line
shifting along the proposed
four lane roads Dadour to
Daundi Nagchaa under
ESDN Nerchowk.
15 SCIA/001/14-15/TL/
KNCEL-00566 22.12.2014 KNCEL
Submission of Design and
Drawing of abutment of
CA.
8. MEETINGS/SITE VISITS/PRESENTATIONS:
Meetings
October, 2014
Meeting held under the chairmanship of A. D.C (Mandi) regarding provisions for additional service
road in Naulakha-Dadour section, representatives of IE and Concessionaire attended the meeting on
29th October,2014 at the office of Dy. Commissioner, District-Mandi.
Meeting held with all the key Professionals of IE and Concessionaire to resolve the site issues related to
quality and supervision on 31st October, 2014
November-2014.
Meeting held under the chairmanship of D.C (Bilaspur) with Concessionaire Representative & Team
Leader ( IE) representative regarding various issues pertaining to the Project at the office of D.C.
Bilaspur on 27th November,2014.
December-2014.
Site Visits
October, 2014
Team Leader along with key professionals visited the site on 15th & 16th October, 2014 regarding
progress of the Project and maintenance of the existing road.
Training Program
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 56
Training for Project Monitoring Information System (PMIS) organized by Regional Office, NHAI at
Panchkula (Haryana) from 16.10.2014 to 18.10.2014 attended by IE and Concessionaire
Representatives.
November-2014
CGM (NHAI) and PD Cum GM (NHAI) visited the project site on 25th November, 2014.
Team Leader along with key professionals visited the site on 4th & 5th November, 2014 regarding
progress of the Project and maintenance of the existing road.
December-2014
PD Cum GM (NHAI) visited the project site on 12th December, 2014.
Team Leader along with key professionals visited the project site on 26th & 27th December, 2014
regarding progress of the Project and maintenance of the existing road.
9. EXECUTING AGENCY
9.1 Concessionaire
M/s IL & FS Transportation Networks Ltd is the Concessionaire. They have created SPV in the name of
M/s KNCEL for this Project. KNCEL has mobilized staff and established its office at Bilaspur (HP). M/s
KNCEL is executing agency for the package.
9.2. EPC Contractor:
Plant/Machineries/Resources
The Concessionaire has appointed three BOQ Contractor for execution of project works.
I. M/s IL &FS Engineering and Construction Company
IL & FS Engineering House, 6-3-1186/1&2
Bugempet, Hyderabad-500016
Establishments of Base Camp at Village-Kuddi (Ghagas). 9 Nos of Concrete Batching Plant established,
Stone crusher Plant, WMM Plant, Hot mix Plant to be erected.
II. M/s Vijay Infra Limited
Pankaj Galaxy, Second Floor
Plot No-8, Sector-12
Dwarka, New Delhi-110075
Establishments of Base Camp at Masewal (Km 78.700 L/S 2km from existing NH-21) and mobilization
of Equipments /Machineries are in progress at site.
III. M/s GHV Projects (India) Pvt Limited
AML Centre-I, 8 Mahal Industrial Areas
Mahakali Caves Road,
Andheri (East), Mumbai-400093
Establishments of Base Camp at Rampur (Kanaid), Near Sunder Nagar. Concrete Batching Plant, Stone
Crusher Plant is operational WMM Plant erected and to be commissioned, Erection of Hot Mix Plant is
in progress.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 57
10 . ORGANIZATION CHART (IE)
M/s Getinsa Ingenieria S. L. Spain in association with M/s Segmental Consulting & Infrastructure Advisory Pvt. Ltd.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 58
11. INDEPENDENT ENGINEER MOBILIZATION:
No. Position Name Date of Joining
Key Personnel
1 Team Leader cum Sr. Highway
Engineer
Mr. Sanjay Kumar Singh 28-09-2012
2 Sr. Bridge Design Engineer Mr. Ramesh Chand Gupta 16-10-2012
3 Resident cum Highway Engineer Mr. Dinesh Kumar Jain 09-01-2014,
mobilized as
replacement
candidate
4 Highway Design Engineer Mr. Mangat Ram Verma 24-09-2012
5 Bridge/Structural Engineer Mr. Sanjay Kumar 16-10-2012
6 Sr. Tunnel Engineer Mr. Rajesh Kumar Thakur 01-10-2012
7 Tunnel Design Engineer Mr. Manuel Romana Garcia 05-06-2013
8 Geologist Mr. Kuldeep Singh Jamwal 20-11-2012
9 Sr. Pavement Specialist & Project
Coordinator
Mr. Shanker Lal Mahipal 16-10-2012
10 Sr. Quality cum Material Expert Mr. Girish Chandra Tiwari 16-10-2012
11 Traffic & Transportation Expert Mr. Miguel Angel Lopez De
Nieta
08-07-2014
12 Road Safety Expert Mr. Louis Polonia Sanchez 20-02-2014
13 Financial Expert Mr. Mihir Kumar Sahu 09-06-2014
14 Legal Expert Mr. Manish Kumar Sharma 10-04-2014
Sub-Professional
1
2
Survey Engineer-1
Survey Engineer-2
Mr. Ambresh Prasad Tripathi
15-12-2012
Mr. Vidhya Bushan 06-12-2012
(Demobilized in April
2014)
3
4
Assistant Highway Engineer-1
Assistant Highway Engineer-2
Mr. Hasan Ahmar 08-08-2014
Mr. Eshant Sonkar 29-04-2014
5 CAD Expert Mohd. Zia Saleem 14-11-2012
6 Environmental Engineer Mr. Raman Padha 20-11-2012
7
8
Assistant Bridge Engineer-1
Assistant Bridge Engineer-2
Mr. Hemant Sharma 05-06-2014
Mr. Pankaj Kumar Sharma 01-04-2014
9
10
Assistant Quality cum Material
Engineer -1
Assistant Quality cum Material
Engineer -2
Mr. Vinod Kumar Mishra 02-11-2012
Mr. Pradeep Kumar Pandey 02-11-2012
11 Electrical Engineer TBN To be Mobilized
12 HTMS/Toll Expert TBN To be Mobilized
13 Quantity Surveyor TBN To be Mobilized
14 Horticulture cum Landscaping Expert TBN To be Mobilized
15
16
Tunnel Engineer-1
Tunnel Engineer-2
Mr. Shashi Kumar 21-11-2012
Mr. Himanshu Kapoor 10-12-2012
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 59
No. Position Name Date of Joining
17 E&M Expert TBN To be Mobilized
18 Tunnel Ventilation Engineer TBN
TBN
To be Mobilized
19 Tunnel Safety Engineer To be Mobilized
Support Staff
1. Office Manager Mr. Ravi Sharma 16-10-2012
2. Accountant Mr. Ambikesh Tripathi 01-09-2013
3. Cashier Mr. Murari Lal Sharma 12-11-2012
4. Computer Operator Mr. Vikas Chand 17-10-2012
5. Steno Mr. Sanjeev Thakur 01-05-2014
6. Photo Copy Machine Operator Mr. Deepak Mishra 16-10-2012
7. Office Boy Mr. Lekh Ram 01-12-2012
8. Guard-1 Mr. Sanjay Kumar 01-11-2013
9. Guard-2 Mr. Raghuveer 01-04-2013
11.1 Updated Status of Man months of Independent Engineer.
S. No. Position Name Man
Month Balance MM
A. KEY PERSONNEL (PROFESIONAL STAFF)
1 Team Leader Cum Sr. Highway
Engineer Sanjay Kumar Singh 42 16.367
2 Tunnel Design Engineer Manuel Romana Garcia 10 8.600
3 Road Safety Expert Louis Polonio Sanchez 8 6.999
4 Traffic & Transportation Expert Miguel Angel Lopez De
Nieta 8 7.134
5 Sr. Bridge Design Engineer Ramesh Chand Gupta 22 8.800
6 Resident-Cum Highway Engineer Dinesh Kumar Jain 42 23.066
7 Highway Design Engineer Mangat Ram Verma 22 6.799
8 Bridge/Structural Engineer Sanjay Kumar 39 13.600
9 Sr. Tunnel Engineer Rajesh Kumar Thakur 42 15.999
10 Geologist Kuldeep Singh Jamwal 12 7.799
11 Sr. Pavement Specialist Shankar Lal Mahipal 16 10.536
12 Sr. Quality Cum Material Expert Girish Chandra Tiwari 39 13.167
13 Financial Expert Mihir Sahu 5 4.767
14 Legal Expert Manish Kumar Sharma 6 5.633
B. SUB-PROFESIONAL STAFF
1 Survey Engineer-1 Ambresh Prasad Tripathi 39 16.265
2 Survey Engineer-2 Vidhya Bushan 15 0.067
3 Assistant Highway Engineer-1 Eshant Sonkar 36 14.232
4 Assistant Highway Engineer-2 Hasan Ahmar 37 25.766
5 Asst. Quality Cum Material Engineer-1 Pradeep Kumar Pandey 36 11.166
6 Asst. Quality Cum Material Engineer-2 Vinod Kumar Mishra 37 11.332
7 Electrical Engineer TBN 8 8.000
8 HTMS /Toll Expert TBN 6 6.000
9 Horticulturalist cum Landscaping
Expert TBN 8 8.000
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 60
10 E & M Expert TBN 6 6.000
11 Tunnel Safty Engineer TBN 6 6.000
12 CAD Expert Mohammad Zia Saleem 9 -0.466
13 Environmental Engineer Raman Padha 9 0.000
14 Assistant Bridge Engineer-1 Hemant Sharma 36 15.366
15 Assistant Bridge Engineer-2 Pankaj Kumar Sharma 37 19.166
16 Quantity Surveyor TBN 10 10.000
17 Tunnel Engineer-1 Shashi Kumar 37 12.367
18 Tunnel Engineer-2 Himanshu Kapoor 36 11.800
19 Tunnel Ventilation Engineer TBN 6 6.000
C. SUPPORT STAFF
1 Office Manager Ravi Sharma 42 16.032
2 Accountant Ambikesh Tripathi 42 16.101
3 Cashier Murari Lal Sharma 42 16.434
4 Photo Machine Operator Deepak Mishra 42 16.433
5 Steno Sanjeev Thakur 42 17.167
6 Computer Operator Vikas Chand 42 16.199
7 Guard-1 Sanjay Kumar 42 16.300
8 Guard-2 Raghuveer 42 16.800
9 Office Boy Lekh Ram 42 16.033
11.2 Invoice of Independent Engineer Services
Sl. Months Letter No Amount
Claimed(Rs)
Amount
Paid (Rs)
Amount Balance
(Rs) Remarks
1 September-
2014
SCIA/001/ 13-14/
TL/NHAI-00499 Rs 41,37,308.00 Paid Nil
2 October-
2014
SCIA/001/ 13-14/
TL/NHAI-00522 Rs 43,37,500.00 Paid Nil
3 November-
2014
SCIA/001/ 13-14/
TL/NHAI-00554 Rs 44,74,130.00 Paid Nil
Note- $ 16,859 USD is balance to be paid for the Month of November, 2014
11.3 S-curve for Construction Schedule- Concessionaire has submitted S-Curve for progress vide letter
No ITNL-KNCEL/PRJ/TECH/ICO/581/2014/1035 A dated 07/12/2014 is enclosed as Annexure A for
reference.
11.4 Financial details of Escrow Account: Statutory Auditor Certificate certifying the financial progress
up to 30th September, 2014 vide letter No ITNL-KNCEL/PRJ/TECH/ICO-581/2014/955 dated
12/11/2014.
12. CONTRACT DATA.
12.1 SANCTION /APPROVAL OF PROJECT:
Project Cost (As per Concession Agreement) - Rs. 1818.47 Crs.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 61
12.2 Civil works Contract Details:
a) Concessionaire Kiratpur-Ner Chowk Expressway Ltd. b) Contract Section Kiratpur to Ner Chowk Section of NH -21 From Km 73.200 to 186.500
c) Contract Length 82.4 Km + 1.971 Km (two lane Link Road to ACC cement Factory
Barmana)
d) Agreement /MOU
Date
16th March 2012
e) Agreement Amount Rs. 1818.47 Crs.
f) Bid quoted by the
bidder
Grant Rs. 134.56 Crs.
g) Date of signing
Substitution/Escrow
Agreement
9th October 2012 (Financial closure 5th Sep 12, GM (J&K/HP) letter no.
NHAI/11016/9/2011/HP-2011/1110
h) Appointed Date 14 November,2013
i) Construction Period 36 Months (1095 days)
j) Performance
Security
Rs. 90.92 Crs.
Note- The Concessionaire has submitted the Statutory Auditor Certificate showing financial
progress up to 15th September,2014 is enclosed for reference.
13. PROJECT PARAMETERS
S. No. Important
Parameters
Original Contract Revised
1.
Total Length
82.400 Km +1.971 Km ( Two Lane link Road)
2. Carriageway width 17.50 meter wide in Plain/Rolling Terrain Excluding
Median 14.00 Meter wide in Hilly/Mountainous
terrain Excluding Median Two lane Bi-directional
Tunnel as per IRC:SP91 :2010
3. Paved Shoulders 1.5 m
4. Earthen Shoulders 2.0 m
5. Median Width 2.50 m – 4.5 m
6. Pavement type Flexible/Rigid
7. Bridges/ Culverts
Major Bridges 17 Nos.
Minor Bridge 27 Nos +01 (Rehabilitation/Repair)
Box Culverts 64 Nos.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 62
Slab Culverts 98 Nos. .
HP Culverts 55 Nos. (In addition to these 30 nos.
8. Flyover 01 No. at Km 142.680 (Length 41.375 meter)
9.
10.
Pedestrian/Cattle
Underpass
Tunnels
04 Nos
05 Nos
Tunnel T1 ( Km12.750 to Km14.550) 1800 meter
long with Escape Tunnels 1800 meter long,
Tunnel T2 (Km 15.785 to 16.275) 490 meter long
Tunnel T3 (Km 23.550 to Km24.130) 580 meter long,
Tunnel T4 (Km 148.500 to Km 149.750) 1250 meter
long.
Tunnel T5 (Km 157.660 to Km 158.400) 740 meter
long.
14. UPDATED REVIEW OF DESIGN & DRAWING up to September, 2014
Updated Status: Review of Drawing &Design of Kiratpur to Nerchowk Section of NH-21 Highways
Sl
No Chainage
Length
(Km) Subject Remarks
1 000.000 to 012.000 12.00 Plan &Profile Drawing reviewed
&Concurred P&P of 70.297
Km out of
84.38 Km as
submitted by
Concessionaire
reviewed
&Concurred
2 126.500 to 155+000 28.5 Plan &Profile Drawing reviewed
&Concurred
3 178.000 to 182.000 4.0 Plan &Profile Drawing reviewed
&Concurred
4 155.000 to 167+000 12.0 Plan &Profile Drawing reviewed
&Concurred
5 12.000 to 26+297 14.297 Plan &Profile Drawing reviewed
&Concurred
6 0.00 to 1+992 1.992 Km Plan &Profile Drawing of Link Road for
ACC Cement Factory
IE observations
to be complied
by
Concessionaire.
Pavement Design
The pavement design for flexible pavement has been reviewed & Concurred for New alignment. The
Design of widening/strengthening of existing pavement and rigid pavement could not be concurred
due to non compliance of observations raised by IE.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 63
Tunnels
Escape Tunnel- Design & drawing of escape tunnel design length 1802.25 meter (As per CA-1905
meter) parallel to Tunnel T1 has been reviewed &concurred.
Pre Final Design of Electromechanical works of Tunnel -1, T-2, T-3, T-4, and T-5 Submitted by the
concessioner and is under review.
Structures.
Minor Bridges –
Minor Bridge General Arrangement Drawing Design
Submitted Concurred Submitted Concurred
24 16 16 14 14
Sl No
Proposed
C.A
Chainage
Design
Chainage
Design
Lengt
h
(Mete
r)
Tunnels Subject Remarks
1 12.732 to
14.482
(1750M)
12.732 to
14.568
(1836M)
1836
Portals of T1 Final Design & Drawing
Reviewed & Concurred
Tunnel
T1(Linear
portion)
Final Design & Drawing
Reviewed & Concurred
2
15.810 to
16.460
( 650M)
15.783 to
16.277
(494M
494
Tunnel T2
(Linear
portion)
including
Portals
Final Design & Drawing is
under review.
3 23.700 to
24.100
(400M)
23.548 to
24.102
(554M)
554
Portals of T3 Final Design & Drawing
Reviewed & Concurred
Tunnel
T3(Linear
portion)
Final Design & Drawing
Reviewed & Concurred
4
148.580
to
149.990
(1410M)
148.468 to
149.767
(1299M)
1299
Portals of T4 Final Design & Drawing
Reviewed and concurred.
Tunnel
T4(Linear
portion)
Final Design & Drawing
Reviewed and concurred
Except 30 m Cut& Cover
Portion.
Structural Design calculation
yet not submitted for cut &
cover portion. ( volume 3
Final lining)
Due to increase in length of 15
meters at portal-2 side final
D&D resubmitted and same is
under review
5
157.800
to
158.660
(860M)
157.658 to
158.402
(744M)
744
Portals of T5 Final Design & Drawing
Reviewed & Concurred
Tunnel
T5(Linear
portion)
Final Design & Drawing
Reviewed & Concurred
Total 5070 4927
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 64
Note 1. 5 Nos Minor Bridge have been converted into Major Bridge.
2. 3 Nos of Minor Bridges (Ch 14+708, 14+927, 15+077) and one Box Culvert Ch 14+970 has been
combined to make Viaduct.
Major Bridges –
Major Bridge General Arrangement Drawing Design
Submitted Concurred Submitted Concurred
20 20 17 20 15
Note:- I - 2 Nos Minor Bridge Converted to Major Bridge as per site condition
II - 3 Nos Minor Bridge converted to Major Bridges by Concessionaire.
III - Out of 15 Major Bridges, only 11 Major Bridges of all components have been
Submitted & concurred. Part Design & Drawing for Balance of 4 bridges as submitted has been
reviewed & concurred.
Box Culverts:-
Culverts of Size 2x2 have been concurred.
Culverts of Size 3x3 have been concurred up to surcharge height 6.2 mts.
Culverts of Size 3x2 have been concurred without surcharge.
Slab Culverts:-
Culverts of Single span up to 6 mts single vent have been concurred.
Pipe Culverts:-
Culverts of Single Row have been concurred.
Gabions Wall:-
Design of Gabions wall up to 13.5 meter height has been concurred.
Retaining Wall
RCC retaining wall design up to 12 Mts height has been concurred.
RRM retaining wall design up to 4 Mts height has been concurred.
Condition Survey and Chainage demarcation for all Culverts have been completed for Entire corridor
except Sunder Nagar Bypass.
Construction Materials
Concurrence of Source for Hume pipes, Aggregates, cement, steel, Admixture, Gabions/Terramesh
System has been accorded. Three Independent Laboratory for testing of materials, Concrete Mix
Designs for grade M15 /M20/M25/M30/M35/M40/M45/M50, design of Filter media have been
reviewed & concurred. Materials for slop protection by Tecco System reviewed &confirmed by
third party testing.
Utilities Shifting
The estimates of utility shifting I&PH Pipe lines from Km 8.8 to 26.2 ,Km154 to 183.7 & Electrical
lines from Km 25.5 to 138.9 (Bilaspur Sadar), 164.3 to 182.25 (Sunder Nagar Section) have approved
by NHAI vide letter No 11009/6/KNCEL/2013/PIU-SML/1447 dated 9/12/2014 and rest of the
estimates for same has been also submitted to NHAI for approval.
Estimate of Existing Road repair
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 65
The estimates of road repair estimate have been approved by NHAI and road repair works are in
progress.
Inventory for Procurement of Site ( As per clause 10.3 of C.A)
An inventory of the site of the entire Project corridor has been done with Concessionaire
representative in accordance with clause 10.3 of C.A.
Change Of Scope (COS)
COS for additional two lane for Sundernagar Bypass, and Major Bridge at Ch 0+450 submitted by
Concessionaire for change of scope notice under clause 16.2 of C.A. The same has been reviewed
and observations made for the compliance of Concessionaire.
15. CONSTRUCTION ACTIVITIES. (Comments of Key Professionals on constructions activities)
Construction Materials
The EPC Contractors M/S IECCL and M/S GHV Infra have established the stone crusher and
aggregate production for concrete works and road works is to be expedited. Aggregates for
concrete works are also being procured from local supplier. The Concessionaire is advised to
increase the production of aggregates to meet the requirement and buffer the same. Stone Crasher
established in section-III has been sealed by district administration & in section-II Green Tribunal
stayed the running of crusher by a writ petition filed by local people, resulting in production of
aggregates has been stopped.
Earth works.
Kiratpur to Ner Chowk Road Project-NH 21
Present Status From Km 0+000 To Km 182+000 As On Date 31.12.14
Sr.
No
Location(RHS) Length RHS Status
Location(LHS) Length LHS Status
From To From To
1 0 820 820 Tree Cutting in
Progress 0 820 820
Tree Cutting in
Progress
2 820 870 50
Embankment
14th Layer in
Progress
920 1400 480 Excavation In Progress
3 870 920 50
Embankment
12th Layer in
Progress
1400 1500 100 Sub Grade Top layer in
Progress
4 8700 9250 550 Excavation in
Progress 1500 1630 130
Embankment in
Progress
5 9340 11500 2160 Excavation in
Progress 1630 2200 570
GSB Top layer in
progress
6 11600 12700 1100 Excavation in
Progress 2200 2260 60
Clearing And Grubbing
Completed
7 16600 17235 635 Excavation in
progress 2260 2540 280
Sub Grade Top in
Progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 66
8 17235 18000 765 Tree Cutting in
progress 2540 3420 880 Excavation in Progress
9 18000 20500 2500 Tree cutting
completed 3420 3810 390
GSB Top layer in
progress
10 20500 21000 500 Tree cutting
completed 3810 3920 110
Clearing And Grubbing
Completed
11 21000 21500 500 Excavation in
progress 3920 4330 410
GSB Top layer in
progress
12 24290 24390 100 Excavation in
progress 4330 4660 330
Sub Grade 1 layer in
Progress
13 26460 26560 100 Excavation in
progress 4660 5360 700
GSB Top layer in
progress
14 24730 24750 20 Excavation in
progress 5360 6600 1240
Clearing And Grubbing
Completed
15 25130 25230 100 Excavation in
progress 6600 7500 900 Excavation in Progress
16 25280 25330 50
Embankment
15 layer in
progress
7500 8700 1200 Clearing And Grubbing
Completed
17 25330 25400 70
Embankment
23 layer in
progress
8700 9250 550 Excavation In Progress
18 25400 25450 50
Embankment
25 layer in
progress
9250 9340 90 Excavation Completed
19 25450 25640 190 Excavation in
progress 9340 11500 2160 Excavation in progress
20 26000 26300 300 Excavation in
progress 11500 11600 100
Subgrade 2 layer in
progress
21 126500 127000 500 Excavation in
progress 11600 12700 1100 Excavation In Progress
22 127140 127190 50
Embankment
23 layer in
progress
16600 17235 635 Excavation in progress
23 127340 127400 60
Embankment
18 layer in
progress
17235 18000 765 Tree cutting in
progress
24 128600 128900 300
Clearing And
Grubbing In
Progress
18000 20500 2500 Tree cutting completed
25 128900 129140 240 Excavation in
progress 20500 21000 500 Tree cutting completed
26 129170 129240 70
Subgrade 1
layer in
progress
21000 21500 500 Excavation in progress
27 129240 129560 320
Subgrade 2
Layer in
progress
24290 24390 100 Excavation in progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 67
28 129600 129650 50
Embankment 6
Layer In
Progress
24400 24460 60 Clearing And Grubbing
Completed
29 130560 130680 120
Embankment
Layer In
Progress
24460 24560 100 Excavation in progress
30 130870 130980 110
Embankment
Layer In
Progress
25130 25250 120 Excavation in progress
31 130980 131110 130
Embankment
Layer In
Progress
25250 25280 30 Embankment 12th
layer in progress
32 131170 131500 330
Clearing And
Grubbing
Completed
25280 25340 60 Embankment 14th
layer in progress
33 132490 132530 40
Embankment
Layers In
Progress
25340 25400 60 Embankment 24th
layer in progress
34 133140 133160 20
Embankment
Layers In
Progress
25400 25440 40 Embankment 25th
layer in progress
35 133160 133180 20 Embankment
top in progress 25440 25640 200 Excavation in progress
36 133180 133200 20 Excavation in
progress 26000 26300 300 Excavation in progress
37 133200 133300 100 Embankment
top in progress 126500 127000 500 Excavation in progress
38 133300 133560 260 Excavation in
progress 127240 127300 60
Embankment 13th
layer in progress
39 133560 133620 60
Subgrade 1st
Layer in
progress
127300 127400 100 Embankment 38th
layer in progress
40 133830 133880 50 Excavation In
Progress 128600 128900 300 Excavation in progress
41 133880 133980 100 Excavation in
progress 128900 129140 240 Excavation in progress
42 133980 134170 190 Excavation in
progress 129140 129240 100
Subgrade 1 layer in
progress
43 134240 134340 100
Embankment
Layer In
Progress
129240 129480 240 Subgrade 2 layer in
progress
44 134340 134390 50 Excavation in
progress 129480 129800 320 Excavation in progress
45 134390 134500 110 Embankment
top in progress 130560 130770 210 Excavation In Progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 68
46 134500 134740 240 Excavation In
Progress 130770 130870 100
Clearing And Grubbing
Completed
47 134780 134860 80 Excavation in
progress 130870 131000 130
Embankment Layers in
Progress
48 134860 135000 140 Excavation In
Progress 131000 131100 100 Excavation In Progress
49 135160 135250 90
Embankment
3rd Layer in
progress
131100 131110 10 Embankment Layers in
Progress
50 135250 135400 150
Embankment
4th Layer in
progress
131170 131460 290 Excavation In Progress
51 135700 135900 200 Excavation in
progress 132020 132130 110 Excavation In Progress
52 136150 136280 130 Excavation in
Progress 133200 133620 420
Subgrade layer in
progress
53 136280 136350 70
Embankment
25 th Layer
completed
133830 134100 270 Excavation In Progress
54 136430 136500 70
Embankment
19 th Layer In
Progress
134100 134170 70 Subgrade 1 layer in
progress
55 136600 136710 110
Clearing And
Grubbing In
Progress
134240 134340 100 Embankment Top layer
in progress
56 136920 137000 80
Clearing And
Grubbing
Completed
134340 134410 70 Excavation in progress
57 137000 137270 270
Clearing And
Grubbing
Completed
134410 134540 130 Embankment Top layer
in progress
58 137270 137430 160
Embankment
Layer In
Progress
134540 134740 200 Excavation In Progress
59 137430 137500 70 Excavation in
Progress 134780 134860 80 Excavation in progress
60 137500 137630 130
Embankment
Layer In
Progress
134860 135000 140 Excavation In Progress
61 137630 137710 80
Embankment
Layer In
Progress
135160 135250 90 Excavtion in progress
62 137770 137910 140
Embankment
Layer In
Progress
135280 135310 30 Excavation In Progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 69
63 137950 138040 90
Embankment
Layer In
Progress
135310 135400 90 Clearing And Grubbing
Completed
64 138040 138220 180
Excavation
Work In
Progress
135700 135900 200 Clearing And Grubbing
Completed
65 138220 138235 15
Embankment
Layer In
Progress
136200 136250 50 Excavation In Progress
66 138460 138560 100
Embankment
Layer In
Progress
136400 136450 50 Excavation in Progress
67 138560 138740 180
Clearing And
Grubbing
Completed
136800 137270 470 Excavation In Progress
68 138740 138860 120
Embankment
Layer In
Progress
137270 137300 30 Embankment Layer In
Progress
69 138950 139210 260 Excavation in
Progress 137500 137630 130
Embankment Layer in
Progress
70 139210 139340 130
Clearing And
Grubbing
Completed
137630 137730 100 Excavation in Progress
71 139340 139620 280 Embankment
top in progress 137730 138050 320 Excavation in Progress
72 139640 139770 130
Subgrade 2
layer in
progress
138050 138220 170 Excavation in Progress
73 139770 139900 130
Embankment
Layer In
Progress
138220 138235 15 Embankment Layer In
Progress
74 139920 140040 120
Subgrade 2
layer in
progress
138250 138300 50 Excavation in Progress
75 140040 140250 210 Embankment
top in progress 138560 138700 140 Excavation in Progress
76 140360 140440 80
Clearing And
Grubbing
Completed
138740 138860 120 Embankment Layer In
Progress
77 140620 140800 180
Excavation
Work In
Progress
138950 139210 260 Excavation in Progress
78 143550 143640 90
Clearing And
Grubbing
Completed
139210 139340 130 Clearing And Grubbing
Completed
79 143820 143850 30
Embankment
Top Layer In
Progress
139340 139620 280 Embankment Top layer
in progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 70
80 143850 144010 160
Subgrade 2nd
Layer
Completed
139640 139670 30 Embankment Top layer
in progress
81 144010 144060 50
Embankment
22th Layer In
Progress
139670 139900 230 Subgrade 1 layer in
progress
82 144130 144250 120
Embankment
Top Layer In
Progress
139920 140040 120 Subgrade 2 layer in
progress
83 144250 144990 740 Excavation In
Progress 140040 140250 210
Clearing And Grubbing
Completed
84 144990 145000 10 Excavation In
Progress 140360 140440 80
Clearing And Grubbing
Completed
85 145000 145040 40
Embankment
3rd Layer In
Progress
140620 140800 180 Excavation Work In
Progress
86 145040 145130 90
Subgrade Top
layer in
progress
143550 143640 90 Clearing And Grubbing
Completed
87 145130 145360 230
Subgrade Top
Layer In
Progress
143820 143850 30 Embankment Top
Layer In Progress
88 145360 145410 50 S.G 1 Layer In
Progress 143850 144010 160
Subgrade 2nd Layer
Completed
89 145410 145500 90 Excavation In
Progress 144010 144050 40
Embankment 15th
Layer In Progress
90 145500 145580 80
Embankment
14th Layer In
Progress
144130 144200 70 Embankment Top
Layer In Progress
91 145580 145950 370 Excavation In
Progress 144200 144400 200 Excavation In Progress
92 145950 146000 50 Excavation In
Progress 144400 145000 600 Excavation In Progress
93 146000 146050 50
Embankment
26 th Layer In
Progress
145000 145040 40 Embankment 3rd Layer
In Progress
94 146050 146110 60 Excavation In
Progress 145040 145130 90 Excavation In Progress
95 146110 146130 20 Excavation In
Progress 145130 145360 230
Embankment Top
Layer In Progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 71
96 146180 146240 60 Excavation In
Progress 145360 145410 50
Subgrade 2nd layer In
Progress
97 146240 146300 60 Excavation In
Progress 145410 145510 100 Excavation In Progress
98 146300 146340 40
Embankment
29th layer in
progress
145510 145580 70 Embankment 12th
Layer In Progress
99 146340 146520 180 Excavation In
Progress 145720 145820 100 Excavation In Progress
100 146520 146620 100 Excavation In
Progress 145950 146000 50 Excavation In Progress
101 146620 146930 310 Excavation In
Progress 146000 146050 50 Excavation Completed
102 146930 147000 70 Excavation In
Progress 146050 146110 60 Excavation In Progress
103 147000 147040 40
Embankment
29th layer in
progress
146110 146130 20 Excavation In Progress
104 147040 147070 30
Embankment
27th layer in
progress
146130 146240 110 Excavation In Progress
105 147070 147150 80
Embankment
4th layer in
progress
146340 146520 180 Excavation In Progress
106 147150 147210 60
Embankment
1st Layer in
progress
146520 146620 100 Excavation In Progress
107 147210 147240 30
Embankment
6th layer in
progress
146720 146780 60 Excavation In Progress
108 147240 147440 200 Excavation In
Progress 146930 147050 120 Excavation In Progress
109 147440 147520 80
Embankment
17th layer In
Progress
147050 147320 270 Excavation In Progress
110 147520 147850 330 Excavation In
Progress 147320 147500 180 Excavation in progress
111 147850 147950 100 Excavation in
progress 147800 147930 130
Embankment 24 th
Layer In Progress
112 147950 148400 450
Clearing And
Grubbing
Completed
148100 148400 300 Clearing And Grubbing
Completed
113 149980 150260 280 Excavation In
Progress 149980 150260 280 Excavation In Progress
114 151220 151250 30 Excavation In
Progress 151220 151250 30 Excavation In Progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 72
115 151450 151900 450
Clearing And
Grubbing
Completed
151450 151900 450 Clearing And Grubbing
Completed
116 152670 152750 80 Excavation In
Progress 152300 152580 280 Excavation In Progress
117 153950 154000 50 Excavation In
Progress 152670 152800 130 Excavation In Progress
118 154050 154250 200
Embankment
7th layer in
progress
153950 154000 50 Excavation In Progress
119 154230 154900 670
Embankment
2nd layer in
progress
154050 154300 250 Excavation In Progress
120 155720 155760 40 Excavation In
Progress 154300 154900 600
Embankment 2nd layer
in progress
121 158960 159020 60 Excavation In
Progress 155720 155760 40 Excavation In Progress
122 159460 159690 230 Excavation In
Progress 158960 159020 60 Excavation In Progress
123 161100 161220 120 Excavation In
Progress 160510 160620 110
Embankment 1st layer
in progress
124 161680 161740 60 Excavation In
Progress 161760 161890 130
Embankment 1st layer
in progress
125 162000 162140 140 Excavation In
Progress 162320 162430 110
Embankment 2nd layer
in progress
126 162440 162640 200 Excavation In
Progress 166790 166880 90
Embankment 2nd layer
in progress
127 163100 163250 150 Excavation In
Progress 178060 178150 90
Embankment 2nd layer
in progress
128 163870 164050 180 Excavation In
Progress 178150 178230 80
Embankment 3rd layer
in progress
129 178060 178150 90
Embankment
2nd layer in
progress
178230 178380 150 Embankment 6th layer
in progress
130 178150 178380 230
Embankment
2nd layer in
progress
178380 178910 530 Subgrade Top layer in
Progress
131 178380 178700 320
Subgrade Top
layer in
progress
178910 179030 120 Embankment top layer
in progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 73
132 178700 178900 200
Subgrade Top
layer in
progress
179030 179100 70 Clearing And Grubbing
Completed
133 178900 179020 120
Embankment
Top layer in
progress
179100 179450 350 Embankment 12th
Layer in Progress
134 179020 179100 80
Clearing And
Grubbing
Completed
179460 179700 240 Embankment 13th
layer in progress
135 179100 179300 200
Embankment
15th Layer in
Progress
179700 179780 80 Embankment 15th
layer in progress
136 179300 179450 150
Embankment
14th Layer in
Progress
179800 180000 200 Embankment 17th
layer in progress
137 179460 179700 240
Embankment
12th layer in
progress
180000 180240 240 Embankment 9th layer
in progress
138 179700 179780 80
Embankment
15th layer in
progress
180260 180450 190 Embankment 12th
layer
139 179800 180000 200
Embankment
15th layer in
progress
180450 180550 100 Embankment 13th
layer
140 180000 180450 450
Embankment
10th layer in
progress
180580 180990 410 Subgrade 1st layer in
Progress
141 180450 180530 80
Embankment
15th Layer in
Progress
180990 181200 210 Embankment 10th
layer
142 180580 180990 410
Subgrade 1st
layer in
Progress
181200 181430 230 Embankment 6th layer
143 180990 181260 270
Embankment
10th layer in
progress
181430 181560 130 Clearing And Grubbing
Completed
144 181360 181460 100
Subgrade 2
layer in
progress
181560 182000 440 Subgrade Top in
Progress
145 181560 182000 440
Subgrade Top
layer in
Progress
In the section-1, tree cutting and earth works for sub grade & embankment are in progress as
mentioned in above table. Tree cutting in 8.0 Km area has been completed. Progress in this section is
behind the schedule and required to be expedited.
In Section-2, also the progress is behind the schedule but picking up the work since last month.
Concessionaire is required to plan the resources to get maximum output.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 74
In Section-3, works is also behind schedule and required to be reorganized to increase the progress of
works. Progress of retaining wall has picked up however the earth work in Nerchowk bypass and the
area from Km 159 to 162 where retaining wall completed, earth work should be started immediately.
Construction of Embankment at chainage 180+000 to 180+070
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 75
Structure Works
Box Culvert
Structure Component (Progress Up to December 2014)
Sr.
No.
Proposed
Chainage Excavation P.C.C
Bottom
Slab Walls Slab Return wall
Curtain
Wall
Back
Filing/
Filter
Media
Flexible/
Rigid
Appron
Stone
Pitching Remarks
1. 137+526 complete complete complete In Progress
2. 144+314 Complete complete complete A1 & A2 final
Lift completed
Slab
Culvert
3. 145+025 complete complete complete Completed Completed
4. 145+125 complete complete complete complete complete one side
completed
5. 145+325 complete complete complete complete complete
RHS
Completed
LHS 1st Lift
6. 146+024 complete complete complete Completed Completed RA1, RA2 lifts
completed
7. 146+845 complete complete complete complete complete RHS
Completed
8. 147+310 LHS
complete
LHS
complete
LHS
Complete LHS Complete LHS Complete
9. 147+578 complete complete BHS
Complete BHS Complete BHS Completed Completed
10. 148+444 complete complete complete
A1 Ist & A2
5th lift
completed
11. 150+885 LHS
complete
LHS
complete
LHS
Complete
3rd lift
completed
LHS & RHS
12. 178+550 complete complete complete complete complete complete Completed
13. 178+920 complete complete complete complete complete Completed Completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 76
14. 179+250 Completed Completed
15. 179+464 complete complete complete complete complete 4x4
16. 179+790 complete complete complete complete complete in progress
17. 180+080 BHS
complete
18. 180+250 complete complete complete Completed Completed
19. 180+555 complete complete complete Completed 4x4
20. 180+690 complete complete complete complete complete in progress
21. 180+990 complete complete complete complete complete Completed in
progress
22. 181+250 Completed Completed Completed
23. 181+350 Completed Completed LHS/RHS
Completed
LHS
Completed LHS Completed
24. 181+500 complete complete complete complete complete in progress
25. 181+800 complete
26. 2+856 LHS
complete
LHS
complete
LHS
complete LHS complete LHS complete
27. 3+000 LHS
complete
LHS
complete
LHS
complete LHS complete LHS comlpete
28. 3+508 LHS
complete
LHS
complete
LHS
complete LHS complete LHS complete
29. 7+508 LHS
complete
LHS
complete
LHS
complete
A1 & A2 final
Lift completed
2nd lift in
progress
Slab
Culvert
30. 7+383 LHS
complete
LHS
complete
LHS
Complete
A1 & A2 final
Lift completed
Slab
Culvert
31. 0+823 RHS
Complete
RHS
Complete
Pipe
Culvert
32. 1+260 LHS
complete
LHS
complete
Head wall
LHS
Complete
Pipe
Culvert
33. 2+348 LHS
complete
LHS
complete
LHS
Complete LHS Complete LHS Complete
34 3+864 LHS
complete
LHS
complete
LHS
complete
Wall 1st Lift
Completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 77
35. 5+511 LHS
complete
LHS
complete
LHS
Complete LHS Complete LHS Complete
36. 137+526 Completed Completed Completed
37. 11+950 Completed Completed Completed
Major Bridges
Major Bridge
Structure Component (Progress Up To December 2014)
Sr.
No.
Proposed
Chainage Excavatuion P.C.C Foundation Substructure Superstructure
Deck
Slab
Crash
Barrier
Expansion
Joint Remarks
1 0+450 Piling A1 & A2
completed
A1& A2
Completed
Pile cap A1& A2
Completed
RA1, LA1, RA2, LA2
lifts completed
A1, A2 Piercap
completed
Steel Truss
Fabricated
members
start arriving
at site
2 17+700
3 19+352
4 20+830
5 23+155
6 24+915
7 26+100
Piling in P7 in
Progress 8 no
completed, P9 and
A2, P0 Comp
P9 & A2, P0 PCC
Completed
P9 & A2 and P0
foundation
Completed A2, P9
RHS Lifts
Completed
A2 cap completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 78
8 130+171
Piling of P1
completed & A1,
P2,P3 & P4 in
Progress
9 131+180
10 133+160 LP1 & RP1, LA1,
RA1 Completed
LP1& RP1, LA1,
RA1 Completed
LP1& RP1& LA1,
RA1 Raft
Completed Lifts in
progress
LA1, RA2, RA1 wall
lifts in
Progress,LA1 LP1,
RP1 pier cap comp
Total RCC 6
Girder
Completed
11 135+070 A2 ,RP2, RP3, LP3,
LP1 Completed
A1& RP2, RP3,
LP3, LP1
Completed
A2, RP2, RP3 LP3,
LP1 Raft
Completed
A2 , RP2, LP1 lifts
in Progress
12 141+100
LP1,LP2,LP3 &
RP1,RP2,RP3, LA1,
RA1
LP1,LP2,LP3 &
RP1,RP2,RP3,
LA1, RA1
Raft LP1,LP2,LP3
& RP1,RP2,RP3,
RA1
Lift of Pier
LP1,LP2,LP3 &
RP1,RP2,RP3 in
Progress
Total 6 PSC
Girder Casted
13 143+783 A1, LP1, RP1, RP2
Completed
A1, LP1, RP1,
RP2, LP2
Completed
A1, LP1, RP1,
RP2, LP2
Completed
Lifts of Pier A1,
LP1, LP2 RP1, RP2
in Progress
Steel beam
fabricated
material
arriving at
site
14 152+100 LA1,RA1, LA2
Completed
LA1, RA1, LA2
Completed
LA1, LA2 Raft
Completed
LA1, LA2 lifts in
progress
15 152+835
16 155+880
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 79
17 157+750
18 158+775
19 178+013
Well Sinking
completed at LA1 &
RA1,while In
progress inLP1 &
LP2 ,RP2 & LA2 &
RA2, RA1 bottom
Pluging of RP1, LP1
Completed
LP1 completed LP1 well cap
completed
P1 RHS and LHS
1st lift completed
Total 5 PSC
Girder Casted
20 1+085
Minor Bridge
Minor Bridge
Structure Component (Progress Up to December 2014)
Sr. No. Proposed
Chainage Excavatuion P.C.C Foundation Substructure
Supers
structure Deck
Slab Crash
Barrier Expansion
Joint Remarks
1 6+140 IN Progress
LA 1& LA2 LA1
Completed
2 14+750
3 14+927
4 15+120
5 15+165
6 15+785
7 16+696
8 16+865
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 80
9 17+584
10 18+323
11 18+910
12 20+594
13 22+604
14 25+221
15 25+300
16 133+830 A2 LHS & RHS
Completed
A2 LHS &
RHS
Completed
LA2 & RA2
Raft BHS
Completed
Lifts in
progress
Wall Lifts
LA2, RA2 in
Progress
17 135+990
A1 LHS, RHS
& A2 LHS C
ompleted
A1, A2 LHS,
RHS
Completed
LA1, LA2
Raft
Completed
LA1 lifts in
Progress
18 138+330
19 138+828 P1, P2
completed
P1 LHS &
RHS
Completed
Raft LP1, RP1
completed
20 144+090
LA1, LA2 &
RA1, RA2
Completed
LA1, LA2 &
RA1, RA2
Completed
LA1 & RA1
Completed
LA1 & RA1
lifts in
Progress
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 81
21 146+702
LP1, RP1 &
LA1, RA1
completed
LP1, RP1&
LA1 & RA1
Completed
Raft LP1, RP1
,LA1 & RA1
completed
LP1& RP1
completed
and A1 BHS
Lifts
completed
RP1, LP1,
A1 Peir
Cap
Completed
Steel fabricated
material start
arriving at site
22 150+050
A2 completed
& A1 in
progress
A2
completed A2 raft
completed A2 5th lift in
progress
23 153+820
24 179+060 Completed Completed Completed A2 1st lift
comp
Retaining Wall
Retaining Wall (December 2014 )
Sr.
No. Proposed Chainage Site Excavation PCC Raft
Wall Wall Wall Wall wall
Remark 1st(Lift (M-
25) 2
nd(Lift
(M-25) 3
rd(Lift
(M-25)
4rd(Lift
(M-25)
5th(Lift
(M-25)
1 150+240 150+260 RHS Completed completed completed Completed Completed Completed completed
2 143+750 143+760 RHS Completed completed
3 145+550 145+570 RHS Completed completed completed Completed Completed Completed
4 145+700 145+715 RHS Completed completed completed Completed Completed Completed completed
5 145+715 145+734 RHS Completed completed completed Completed Completed Completed
6 145+734 145+750 RHS Completed completed completed Completed Completed
7 145+680 145+700 RHS Completed Completed Completed Completed Completed Completed completed completed
8 145+697 145+712 RHS Completed completed completed Completed Completed Completed completed completed
9 145+750 145+760 RHS Completed completed completed Completed Completed
10 145+760 145+780 RHS Completed completed completed Completed Completed Completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 82
11 145+830 145+840 RHS Completed completed completed Completed Completed
12 145+840 145+860 RHS Completed completed completed Completed Completed Completed completed
13 147+070 147+090 RHS Completed Completed Completed Completed Completed Completed completed completed
14 147+090 147+110 RHS Completed Completed Completed Completed Completed completed completed completed
15 147+110 147+130 RHS Completed completed completed Completed Completed Completed completed
16 147+130 147+150 RHS Completed Completed Completed Completed Completed Completed Completed Completed
17 147+150 147+165 RHS Completed completed completed Completed Completed Completed completed completed Final
18 147+169 147+183 RHS Completed completed completed Completed Completed Completed completed completed Final
19 147+183 147+200 RHS Completed completed completed Completed Completed Final
20 147+200 147+260 RHS Completed Completed Completed Completed Completed Completed completed completed Final
21 147+260 147+280 RHS Completed Completed Completed Completed Completed completed completed Final
22 147+280 147+300 RHS Completed completed completed Completed Completed Completed completed completed Final
23 147+300 147+314 RHS Completed Completed Completed Completed Completed Completed completed
24 147+520 147+540 RHS Completed Completed Completed Completed Completed Final
25 147+540 147+582.5 RHS Completed Completed Completed Completed Completed Final
26 148+020 148+040 RHS Completed completed completed Completed Completed Final
27 148+040 148+060 RHS Completed Completed Completed Completed Completed completed completed completed
28 132+130 132+160 RHS Completed completed completed Completed Completed Completed completed completed Final
29 132+160 132+180 RHS Completed completed completed Completed Completed Completed
30 132+180 132+190 RHS Completed completed completed Completed Completed Completed completed Final
31 132+190 132+210 RHS Completed completed completed
32 132+310 132+330 RHS Completed completed completed completed
33 132+680 132+710 RHS Completed Completed Completed Completed Completed completed completed Final
34 132+770 132+810 RHS Completed completed completed completed Completed Completed completed completed Final
35 132+810 132+820 RHS Completed completed completed
36 135+340 135+360 RHS Completed completed completed Completed
37 137+080 137+100 RHS Completed completed completed Completed Completed Completed
38 137+100 137+120 RHS Completed Completed Completed Completed Completed Completed completed Final
39 137+120 137+140 RHS Completed Completed completed Completed Completed Completed Completed Final
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 83
40 137+140 137+160 RHS
41 137+240 137+280 RHS Completed completed completed Completed
42 137+280 137+300 RHS Completed completed completed Completed Completed
43 137+300 137+320 RHS Completed completed completed Completed Completed Completed completed
44 137+320 137+340 RHS Completed completed completed Completed Completed Completed
45 137+340 137+350 RHS Completed completed completed Completed Completed Completed completed completed
46 137+350 137+370 RHS Completed Completed completed Completed Completed completed completed
47 137+370 137+390 RHS Completed completed completed Completed Completed Completed completed completed
48 137+390 137+410 RHS Completed Completed Completed Completed Completed Completed completed
49 137+530 137+570 RHS Completed Completed completed Completed Completed
50 137+570 137+600 RHS Completed Completed completed Completed
51 137+600 137+620 RHS Completed Completed
52 137+770 137+790 RHS Completed Completed Completed Completed Completed
53 138+200 138+300 RHS Completed 20 meter
completed
54 138+460 138+480 RHS Completed completed completed Completed Completed completed Final
55 138+480 138+500 RHS Completed completed completed Completed Completed Completed completed
56 138+500 138+520 RHS Completed completed completed Completed Completed Completed final
57 138+520 138+560 RHS Completed Completed Completed Completed Completed Completed final
58 138+750 138+770 RHS Completed Completed completed Completed Completed Completed final
59 138+770 138+790 RHS Completed completed completed final
60 138+790 139+810 RHS Completed completed final
61 138+810 138+840 RHS Completed Completed completed Completed Completed final
62 138+840 138+860 RHS Completed Completed Completed Completed Completed Completed final
63 159+670 159+690 LHS Completed completed completed Completed
64 159+690 159+700 LHS Completed completed
65 160+070 160+080 LHS Completed completed completed Completed Completed Completed
66 160+090 160+100 LHS Completed completed
67 160+280 160+295 LHS Completed completed completed completed completed completed
68 160+295 161+310 LHS Completed completed completed completed completed completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 84
69 160+310 160+330 LHS Completed completed completed Completed Completed
70 160+345 160+360 LHS Completed completed completed Completed
71 160+360 160+370 LHS Completed completed
72 160+510 160+520 LHS Completed completed completed Completed Completed Completed Completed completed Final
73 160+520 160+530 LHS Completed completed completed Completed Completed Completed completed completed Final
74 160+530 160+550 LHS Completed completed completed Completed Completed completed completed completed Final
75 160+550 160+560 LHS Completed completed completed Completed Completed Completed completed completed Final
76 160+560 160+570 LHS Completed completed completed Completed Completed Completed Completed completed Final
77 160+570 160+580 LHS Completed completed completed Completed Completed Completed completed
78 160+580 160+590 LHS Completed completed completed Completed Completed Completed completed completed Final
79 160+590 160+600 LHS Completed completed completed Completed Completed completed completed completed Final
80 160+600 160+620 LHS Completed completed completed Completed Completed Completed completed completed Final
81 160+810 160+820 LHS Completed completed completed Completed Completed Completed Final
82 160+840 160+850 LHS Completed completed Completed Completed Completed Completed
83 160+850 160+860 LHS Completed completed completed Completed Completed completed completed Final
84 160+860 160+870 LHS Completed completed completed Completed Completed
85 160+870 160+880 LHS Completed completed completed
86 160+880 160+890 LHS Completed completed completed Completed
87 160+890 160+900 LHS Completed completed completed Completed Completed
88 160+900 160+910 LHS Completed completed completed Completed
89 160+910 160+920 LHS Completed completed completed
90 161+070 161+080 LHS Completed completed completed Completed Completed Final
91 161+080 161+090 LHS Completed completed completed Completed Completed Completed completed
92 161+090 161+100 LHS Completed completed completed Completed Completed Completed completed completed Final
93 161+100 161+110 LHS Completed completed completed Completed Completed completed completed completed Final
94 161+310 161+320 LHS Completed completed completed
95 161+370 161+380 LHS Completed completed
96 161+380 161+390 LHS Completed completed Completed completed Completed Completed completed completed
97 161+390 161+400 LHS Completed completed completed Completed Completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 85
98 161+400 161+420 LHS Completed completed Completed Completed
99 161+450 161+470 LHS Completed completed completed Completed Completed
100 161+470 161+490 LHS Completed completed completed completed Completed
101 161+490 161+500 LHS Completed completed completed Completed Completed Completed completed Final
102 161+500 161+530 LHS Completed completed completed Completed
103 161+530 161+540 LHS Completed completed completed Completed Completed
104 161+540 161+560 LHS Completed completed completed Completed Completed completed completed Final
105 161+600 161+620 LHS Completed completed completed Completed Completed completed
106 161+760 161+770 LHS Completed completed completed Completed Completed completed completed completed Final
107 161+770 161+790 LHS Completed completed Completed completed Completed completed completed Final
108 161+790 161+805 LHS Completed completed completed Completed Completed Completed completed Final
109 161+805 161+810 LHS Completed completed completed Completed Completed Completed completed completed
110 161+810 161+820 LHS Completed completed completed Completed Completed Completed Final
111 161+820 161+840 LHS Completed completed completed Completed Completed Completed
112 161+840 161+860 LHS Completed completed completed Completed Completed Completed Final
113 161+860 161+880 LHS Completed completed completed Completed Completed Final
114 161+880 161+900 LHS Completed completed completed Completed Completed Completed Final
115 161+900 161+910 LHS Completed completed completed Completed Completed
116 162+110 162+120 LHS Completed Completed `
117 162+175 162+185 LHS Completed Completed completed `
118 162+185 162+190 LHS Completed Completed completed `
119 162+190 162+200 LHS Completed Completed `
120 162+320 162+360 LHS Completed Completed Completed Completed Completed Completed completed Final
121 162+360 162+390 LHS Completed completed completed Completed Completed
122 162+390 162+400 LHS Completed completed completed Completed Final
123 162+400 162+430 LHS Completed completed completed Completed Final
124 162+990 163+000 LHS Completed completed
125 163+000 163+010 LHS Completed completed completed Completed
126 163+010 163+020 LHS Completed completed completed completed completed Completed Completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 86
127 163+050 163+060 LHS Completed completed completed Completed Completed Completed
128 163+060 163+070 LHS Completed completed Completed completed Completed Completed Completed
129 163+070 163+080 LHS Completed completed completed Completed
130 163+080 163+090 LHS Completed completed completed Completed Completed Completed completed completed Final
131 163+130 163+145 LHS Completed completed completed
132 163+600 163+620 LHS Completed Completed completed Completed Completed
133 163+620 163+630 LHS Completed Completed completed
134 163+630 163+640 LHS Completed Completed completed
135 163+640 163+650 LHS Completed Completed completed Completed Completed
136 163+650 163+660 LHS Completed Completed completed Completed
137 163+660 163+670 LHS Completed Completed completed Completed Completed Completed
138 163+830 163+840 LHS Completed Completed completed Completed Completed
139 166+610 166+620 LHS Completed completed completed
140 166+790 166+800 LHS Completed completed completed Completed Completed
141 166+800 166+810 LHS Completed completed completed Completed Completed Completed
142 166+810 166+820 LHS Completed completed completed Completed Completed Completed
143 166+820 166+830 LHS Completed completed completed Completed Completed Completed Final
144 166+830 166+850 LHS Completed completed completed Completed Completed Completed completed
145 166+850 166+865 LHS Completed completed completed Completed Completed Completed completed Final
146 166+865 166+880 LHS Completed completed completed Completed Completed Completed
147 127+310 127+340 RHS Completed completed completed Completed Completed Completed completed
148 127+340 127+360 RHS Completed completed completed Completed Completed Completed Completed completed
149 127+360 127+380 RHS Completed completed completed Completed Completed Completed Completed completed
150 127+380 127+400 RHS Completed completed completed Completed Completed Completed Completed completed
151 127+400 127+420 RHS Completed completed completed Completed Completed Completed completed completed
152 127+420 127+440 RHS Completed completed completed Completed Completed Completed completed
153 127+470 127+480 RHS Completed completed completed Completed Completed Completed completed completed
154 127+480 127+490 RHS Completed completed completed Completed Completed Completed completed completed
155 129+740 129+760 RHS Completed completed completed Completed Completed Completed completed
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 87
156 129+600 129+625 RHS Completed completed completed completed Completed completed completed completed Final
157 129+625 129+660 RHS Completed completed completed completed completed Completed completed completed Final
158 129+710 129+720 RHS Completed Completed Completed completed
159 129+720 129+730 RHS Completed Completed Completed completed Completed Completed
160 129+730 129+780 RHS Completed completed completed completed Completed Completed completed completed
161 129+780 129+810 RHS Completed completed completed completed Completed
162 178+090 178+100 RHS Completed completed completed completed Completed completed
163 178+100 178+120 RHS Completed completed completed completed
164 178+120 178+150 RHS Completed completed completed Completed Completed
165 178+150 178+180 RHS Completed completed completed Completed Final
166 178+180 178+210 RHS Completed completed completed Completed Completed Final
167 178+210 178+240 RHS Completed completed completed Completed Final
168 178+240 178+260 RHS Completed Completed completed Completed Final
169 178+940 178+970 RHS Completed completed
170 178+970 179+000 RHS Completed completed
171 180+710 180+720 RHS Completed completed
172 178+300 178+320 LHS Completed completed completed Completed
173 178+090 178+100 LHS Completed completed
174 178+100 178+120 LHS Completed completed
175 178+120 178+150 LHS Completed completed completed Completed
176 178+150 178+180 LHS Completed completed completed Completed Completed Completed
177 178+180 178+210 LHS Completed Completed Completed Completed Completed Completed Final
178 178+210 178+240 LHS Completed Completed completed Completed Completed Final
179 178+240 178+255 LHS Completed completed completed Completed Completed Final
180 178+255 178+270 LHS Completed Completed completed Completed Final
181 178+270 178+320 LHS Completed Completed completed Completed Final
182 178+980 179+000 LHS Completed Completed Final
183 179+130 179+170 LHS Completed Completed completed Completed Final
184 179+170 179+190 LHS Completed Completed completed Completed Final
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 88
185 179+270 179+330 LHS Completed Completed Final
186 179+270 179+312 RHS Completed Completed completed Completed Completed Final
187 179+650 179+680 LHS Completed completed
188 179+680 179+700 RHS Completed completed
189 179+700 179+730 LHS Completed completed
190 179+550 179+580 RHS Completed completed
191 180+080 180+100 RHS Completed completed
192 180+710 180+720 RHS Completed completed completed
193 180+720 180+730 RHS Completed completed completed Completed
194 180+930 180+950 RHS Completed completed completed Completed Completed Final
195 180+950 180+970 RHS Completed completed completed Completed
196 181+040 181+060 RHS Completed completed completed Completed Completed Final
197 181+060 181+080 RHS Completed completed completed Completed
198 181+060 181+080 LHS Completed completed completed
199 181+070 181+120 LHS Completed completed completed
200 181+120 181+130 LHS Completed completed completed Completed
201 181+130 181+140 LHS Completed completed completed
202 181+140 181+150 LHS Completed completed completed
203 181+150 181+160 RHS Completed completed completed
204 181+950 181+960 RHS Completed completed completed Completed
205 180+710 180+720 LHS Completed completed completed Completed
206 182+820 180+830 LHS Completed completed completed Completed Completed Completed Final
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 89
The overall physical progress of structure works has picked up but still behind the schedule and can be
expedited by deploying sufficient manpower(skilled) and resources.The succeding activities especially
Bridges should be taken up timely to get maximum output and completion of the structures.
RP1 Cap Concerting of Pier Cap at 133+160(Major Bridge)
LP9 Concerting Pier using slip form shuttering at Ch126+100
(Major Bridge)
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 90
Tunnel Works
Tunnel -T1
Portal -1 (Main &Escape Tunnel) Slope Stabilization (Ch. 12+700 to Ch.12+740)
Frontal slopes, right and, left lateral slopes including all primary supports from Elevation 758 to
720 has been completed except final coloring layer yet to be done.
Main Tunnel T-1 (Portal 1&2)
Monthly Progress of Tunnel 1 (Portal1&2 )
Sr.
No
Description of
works
Total
length
of
tunnel
Length
completed
up to last
month
Length
achieved
during
the
month
Cumulative
Length
Total
Cumulative
Length
Portal -
1&2
Balance
Remarks
(m)
1
Underground
Excavation
Top
Heading(From
portal 1) 1800
49 45 94
95 1705
This tunnel will
have total of
1836 m Length,
being 1800 m of
underground
excavation and
an additional
18m each
portal
Corresponding
to the
ventilation
buildings
Underground
Excavation
Top
Heading(From
portal 2)
- 1 1
2 Benching
3
Geotextile
and water
proofing
4 Overt Lining
5 ventilation
Slab
6
Invert Lining
(Rigid
Pavement)
7
Grouting
/Drainage/
E& M & other
Misc. Work.
Rock Classification : Main Tunnel Support class C1 and B2 (From portal 1)
: Main Tunnel Support class L (From portal 2)
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 91
Escape Tunnel (From portal 1)
Monthly Progress of Escape Tunnel (From portal 1)
Sr.No.
Description of
works
Total
length of
tunnel
(m)
Length
completed
up to last
month
(m)
Length
achieved
during the
month
(m)
Cumulative
Length
(m)
Balance
(m) Remark
1
Under Ground
Excavation Heading
(full face)
1802.25 113 58 171 1631.25
2
Geotextile and
water proofing
membrane
3 Overt Lining
4 Invert Lining (Rigid
Pavement)
5
Grouting
/Drainage/ E& M
& other Misc.
Work.
Rock Classification : Escape Tunnel Support class C1 and B2
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 92
Escape Tunnel (From Portal -1)
Tunnel 1 Portal -2 (Main &Escape Tunnel Area) Slope Stabilization (Ch. 14+530 to Ch. 14+600)
Left lateral slope from elevation 693 to 683 including all primary supports has been completed
except final coloring layer yet to be done.
From elevation 683to 682 excavation of left lateral slopes, spraying of shotcrete, Fixing of two layer
wire mesh, sub horizontal drain, Drilling and installation of P.G Rock bolts, pullout testing of rock
bolts, Laying of concrete for Trapezoidal intercepting channel and half circular intercepting channel,
installation of optical survey targets at portal benches are under progress and Multipoint borehole
extensometers and inclinometers have been Installed.
Some movements/deformation has been observed at right lateral & frontal slope which is yet now
within alert limit. At right lateral and frontal slope, additional rock bolt support works at an elevation
687 and 693 is under progress. This reinforcement of supports system in 20 m of the frontal slope
from the corner between the toe of the frontal and right lateral slope. In the right lateral slope it is
applying in 45 m along the slope.
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 93
Tunnel 3
Tunnel -3 Portal-1 Slope Stabilization (Ch. 23+530 to 23+570)
Excavation of frontal, right and left lateral slopes including all supports from elevation 572 to 548 has
been completed including multi- point borehole extensometer, and inclinometer except
hydroseeding works.
From elevation 572 to 566 right lateral slope from Ch 23+490 to 23+520 slopes excavation &
installation PG rock bolts , Laying of concrete for Trapezoidal intercepting channel , half circular
intercepting channel structure is under progress.
Portal Development: Drilling for umbrella pipe roofing has been completed.
Monthly Progress of Tunnel T-3 (Portal 1 )
Sr. No. Description of
works
Total
length of
tunnel
(m)
Length
completed
up to last
month
(m)
Length
achieved
during the
month
(m)
Cumulative
Length
(m)
Balance
(m) Remarks
1
Underground
Excavation Top
Heading
554 - 02 02 552
2 Benching
4 Geotextile and
water proofing
3 Overt Lining
4 Invert Lining (Rigid
Pavement)
5
Grouting
/Drainage/ E&
M & other Misc.
Work.
Rock Classification: Main Tunnel Support class L
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 94
Tunnel 3 portal 1
Tunnel 4
Tunnel -4 Portal-1 Slope Stabilization (Ch.148+450 to Ch.148+500)
Excavation of left and right lateral slope including all primary supports from Elevation 611 to 581
has been completed except final coloring layer yet to be done.
Excavation of Frontal slope from El. 617.5 to 581 including primary supports has been completed
except final coloring layer yet to be done.
From EL.581to EL.580 Excavation of frontal and lateral(right &left)slopes, spraying of shotcrete,
Fixing of two layer wire mesh, sub horizontal drain, Drilling &installation of PG Rock Bolts, pullout
testing of rock bolts, Laying of concrete for trapezoidal intercepting channel are under progress.
Multipoint borehole extensometer and inclinometers have been Installed and Installation of optical
survey targets at portal benches are under progress.
Tunnel T-4 (Portal 1)
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 95
Monthly Progress of Tunnel T-4 (Portal P1 )
Sr. No. Description of
works
Total
length of
tunnel
(m)
Length
completed
up to last
month
(m)
Length
achieved
during the
month
(m)
Cumulative
Length
(m)
Balance
(m) Remarks
1
Underground
Excavation Top
Heading
1269 13 14 27 1242
This tunnel
will have total
of 1299 m
Length, being
1269 m of
underground
excavation
and an
additional
30m is in cut
and cover at
Tunnel-4
portal 1.
2 Benching
4 Geotextile and
water proofing
3 Overt Lining
4 Invert Lining (Rigid
Pavement)
5
Grouting
/Drainage/ E&
M & other Misc.
Work.
Rock Classification Tunnel Support class –L
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 96
Tunnel T-4 (Portal 1)
Tunnel4 Portal -2 Slope Stabilization (Ch. 149+755 to Ch.149+770)
Frontal and left lateral slope including all primary supports from Elevation 603 to 594 has been
completed except final coloring layer yet to be done.
From elevation 594 to 592 excavation of Frontal and left lateral slopes, spraying of shotcrete, Fixing
of two layer wire mesh, sub horizontal drain, Drilling and installation of P.G Rock bolts, Laying of
concrete for Trapezoidal intercepting channel are under progress. Inclinometer have been Installed.
Tunnel 4 portal 2
Tunnel-5 (Portal 2)
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 97
Monthly Progress of Tunnel 5 (Portal 2)
Sr. No. Description of
works
Total
length of
tunnel
(m)
Length
completed
up to last
month
(m)
Length
achieved
during the
month
(m)
Cumulative
Length
(m)
Balance
(m) Remarks
1
Underground
Excavation Top
Heading
744 103 47 150 594
2 Benching
4 Geotextile and
water proofing
3 Overt Lining
4 Invert Lining (Rigid
Pavement)
5
Grouting
/Drainage/ E&
M & other Misc.
Work.
Rock Classification : Tunnel-5 Support class B1 and C1
Tunnel5 Portal -1 Slope Stabilization (Ch.157+665to Ch. 157+675)
From EL.647 to EL.645 Excavation of frontal slopes, Drilling & installation of PG Rock Bolts, Fixing of
two layer wire mesh, laying of concrete for trapezoidal intercepting channel are under progress.
16. Review of Physical Progress
October-2014
Overall physical progress has improved since last month still it is behind the schedule.
Concessionaire is required to reorganize the teams deployed in section I &III without further delay
and in section –II ,the progress can be expedited by better resource managment &planning .the
progress in tunnelworks has picked up but required some more effort especially in tunnel -1 Portal-
2 where breakdown of machinaries was frequent. Sufficient nubmer of spareparts is required to be
stored. In structure works by better resource managment progress can be expedited. The progress
of road works will pick up only after construction of retaining walls in all the sections. It is expected
that the progress will further pick up in coming months.
November-2014
Overall physical progress is behind the schedule. Concessionaire is required to augment the
resources in all the sections order to achieve the targated progress as well as catch up the
Quarterly Progress Report No. 9 : October-December, 2014
Getinsa Ingenieria S. L. Spain in association with
Segmental Consulting & Infrastructure Advisory Pvt. Ltd. India
Page 98
shortfall in progress till this period . The progress structure works can be expedited bu puttting
skilled manpower especially carpentas &barbenders. Succeding activities found held up due to
insufficient skilled manpower for bridges.The progress of tunnel works has picked up and likely to
be catch up the shortfall in coming months.
December-2014
Concessionaire is required to reorganise the resources especially in section-I &III to catchup the
targated overall physical progresss which behind the schedule till date . The progress structure
works can be expedited bu puttting skilled manpower especially carpentas & barbenders.
Succeding activities found held up due to insufficient skilled manpower for bridges.The progress
of tunnel works has picked however it can be expedited by putting more resources especially at
Tunnel T1 P2 side , Tunnel T4 P1 side & Tunnel T5 P1 side.
17 . Road Maintenance works of existing NH-21 (Km .73+200 to 186+500).
October-2014
Road Maintenance works complete in Nerchowk-SunderNagar Section and balance repair works
with bituminouse materials yet to be taken up from swarghat to Gambhar & Ghagas to Slapper.
Some new potholes have redeveloped in Bamta–Ghagas section. Concessionaire has been asked to
complete the balance road repair works for traffic worthy condition.
November-2014
Road Maintenance works completed in Ghagas to Nagchhala , Kiratpur to Bilaspur, Naunichowk to
Bamta Sections of NH-21. Balance repair works for isolated redevoloped potholes from Gamroula
to Gambhar are in progress. Concessionaire has been asked to complete the balance road repair
works for traffic worthy condition.
December-2014
Road Maintenance works for entire section has been completed till the end of the month but
requires regular maintanance to keep the road in traffic worthy condition as the sub base & heavy
movement of traffic may require continouse repair of existing road.
Annexure – A