PERT Analysis Using MS Project

Scott Brunton, PMP MASc MBASenior Consultant

[email protected]

Page 2: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 2/16

Critical Path Method

! Pre-cursor to PERT

! Developed By Dupont In 1957

! Novel, Yet Simplistic, Approach to Project

Network Modeling Requirements

! Based on ‘Fixed Estimates’ for Task

Durations

Page 3: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 3/16

Program Evaluation & Review Technique

! Developed by Booz-Allen Hamilton in 1958

 – Lockheed Missile Systems – Prime Contractor 

! Polaris Mobile Submarine-Launched Ballistic

Missile Program – Special Projects Office Contract with US Navy

! Acknowledges ‘Randomness’ Surrounding

Task Duration Estimation

Page 4: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 4/16

Outcome – Three-Point Estimate

! Studied Bias and Reliability of Task Duration

Estimates Collected by Variety of Methods

! Correlated Actual Durations with Estimates

and ‘Curve-fit’ Results

! Expected Duration

6)*4( c PessimistiMostLikelyOptimistic Expected 

!!"

Page 5: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 5/16

Outcome – Three-Point Estimate

! Underlying Probability Distribution

 – Beta Distribution

! Expected Variance

# $%&

'()

* +"

6

2

Optimisticc PessimistiVariance

Page 6: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 6/16

PMI PMBOK®

! Project Time Management

 – Activity Duration Estimation

• Knowledge Area 6.4

! Risk Identification – Information Gathering Techniques

• Knowledge Area 11.2.2.2

There Are No Facts About The Future

Page 7: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 7/16

Obtaining Credible Estimates

! Overcome Bias that Estimates are Optimistic

! Methods

 – Expert Judgment

 – Analogous Estimation

 – Parametric Estimation

 – Three-Point Estimation

 – Reserve Analysis

Page 8: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 8/16

Delphi Method of Estimation

! Experts Provide Estimates Anonymously

! Reduces Bias Injected by Influential

Participant

! Results are Summarized by Independent

Facilitator and Re-distributed to Panel

! After a Few Rounds, Estimates Will Converge

on Consensus Answer 

Page 9: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 9/16

Parkinson’s Law

An Activity Will Always Take

As Long As The Time Assigned To It.

Page 10: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 10/16

Page 11: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 11/16

Demonstration

! Single-Point Estimate

! PERT Using Native MS Project Toolbar 

! PERT Using Calculated Fields

Page 12: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 12/16

What If The Toolbar Isn’t Available?

! Use ‘ComAddinsDialog’ Command To Reveal

PERT Toolbar 

! Microsoft Knowledgebase

 – http://office.microsoft.com/en-

us/project/HA101636871033.aspx?pid=CH101759951033

Page 13: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 13/16

Limitations of PERT

! Assumes Task Durations are Accurate and

Independent

! Assumes Underlying Probability Distribution Of 

Estimates Can Be Represented By Beta! Does Not Account For Quality of Estimates

! Influenced by Underlying Contractual Arrangements

! Static Single-Pass Calculation Of Critical Path

Underestimates The Expected Project Duration – Neglects Effects of Near-Critical Tasks

Page 14: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 14/16

Probabilistic Simulation of Task Durations

! Monte Carlo Simulation

 – Statistical Method Using Random Sampling of 

Configurable Probability Distribution Curves

 – Apply Random Variation to Each Task Duration – Results Accumulate over Repeated Simulations

 – Third Party Add-in

• Deltek – Risk+

Page 15: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 15/16

References

! PMBOK® Third Edition – as referenced

! Project Management: A Systems Approach to Planning,Scheduling and Controlling, 6th Ed. – Harold Kerzner © 1998, ISBN 0-442-02551-3

! Field Guide to Project Management – David I Cleland © 1998, ISBN 0-471-29206-0

! Fundamentals of Project Management – James P Lewis © 1995, ISBN 0-8144-7835-2

! Project Management for Business & Engineering, 2nd Ed. – John M. Nicholas © 2004, ISBN 0-7506-7824-0

! Wikipedia - http://en.wikipedia.org/wiki/PERT

Page 16: PERT AnalysisUsingMS Project

8/9/2019 PERT AnalysisUsingMS Project

http://slidepdf.com/reader/full/pert-analysisusingms-project 16/16

Questions

! Thank you for joining the Phoenix-MPUG

Sponsored Web N Learn today

! Information on claiming PDU for this event

will emailed to those attending

! Presentation slides will be posted to the

Member Area of the MPUG site archive

Phoenix