Upload
sapalijo990
View
223
Download
0
Embed Size (px)
Citation preview
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 1/16
PERT Analysis Using MS Project
Scott Brunton, PMP MASc MBASenior Consultant
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 2/16
Critical Path Method
! Pre-cursor to PERT
! Developed By Dupont In 1957
! Novel, Yet Simplistic, Approach to Project
Network Modeling Requirements
! Based on ‘Fixed Estimates’ for Task
Durations
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 3/16
Program Evaluation & Review Technique
! Developed by Booz-Allen Hamilton in 1958
– Lockheed Missile Systems – Prime Contractor
! Polaris Mobile Submarine-Launched Ballistic
Missile Program – Special Projects Office Contract with US Navy
! Acknowledges ‘Randomness’ Surrounding
Task Duration Estimation
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 4/16
Outcome – Three-Point Estimate
! Studied Bias and Reliability of Task Duration
Estimates Collected by Variety of Methods
! Correlated Actual Durations with Estimates
and ‘Curve-fit’ Results
! Expected Duration
6)*4( c PessimistiMostLikelyOptimistic Expected
!!"
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 5/16
Outcome – Three-Point Estimate
! Underlying Probability Distribution
– Beta Distribution
! Expected Variance
# $%&
'()
* +"
6
2
Optimisticc PessimistiVariance
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 6/16
PMI PMBOK®
! Project Time Management
– Activity Duration Estimation
• Knowledge Area 6.4
! Risk Identification – Information Gathering Techniques
• Knowledge Area 11.2.2.2
There Are No Facts About The Future
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 7/16
Obtaining Credible Estimates
! Overcome Bias that Estimates are Optimistic
! Methods
– Expert Judgment
– Analogous Estimation
– Parametric Estimation
– Three-Point Estimation
– Reserve Analysis
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 8/16
Delphi Method of Estimation
! Experts Provide Estimates Anonymously
! Reduces Bias Injected by Influential
Participant
! Results are Summarized by Independent
Facilitator and Re-distributed to Panel
! After a Few Rounds, Estimates Will Converge
on Consensus Answer
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 9/16
Parkinson’s Law
An Activity Will Always Take
As Long As The Time Assigned To It.
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 10/16
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 11/16
Demonstration
! Single-Point Estimate
! PERT Using Native MS Project Toolbar
! PERT Using Calculated Fields
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 12/16
What If The Toolbar Isn’t Available?
! Use ‘ComAddinsDialog’ Command To Reveal
PERT Toolbar
! Microsoft Knowledgebase
– http://office.microsoft.com/en-
us/project/HA101636871033.aspx?pid=CH101759951033
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 13/16
Limitations of PERT
! Assumes Task Durations are Accurate and
Independent
! Assumes Underlying Probability Distribution Of
Estimates Can Be Represented By Beta! Does Not Account For Quality of Estimates
! Influenced by Underlying Contractual Arrangements
! Static Single-Pass Calculation Of Critical Path
Underestimates The Expected Project Duration – Neglects Effects of Near-Critical Tasks
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 14/16
Probabilistic Simulation of Task Durations
! Monte Carlo Simulation
– Statistical Method Using Random Sampling of
Configurable Probability Distribution Curves
– Apply Random Variation to Each Task Duration – Results Accumulate over Repeated Simulations
– Third Party Add-in
• Deltek – Risk+
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 15/16
References
! PMBOK® Third Edition – as referenced
! Project Management: A Systems Approach to Planning,Scheduling and Controlling, 6th Ed. – Harold Kerzner © 1998, ISBN 0-442-02551-3
! Field Guide to Project Management – David I Cleland © 1998, ISBN 0-471-29206-0
! Fundamentals of Project Management – James P Lewis © 1995, ISBN 0-8144-7835-2
! Project Management for Business & Engineering, 2nd Ed. – John M. Nicholas © 2004, ISBN 0-7506-7824-0
! Wikipedia - http://en.wikipedia.org/wiki/PERT
8/9/2019 PERT AnalysisUsingMS Project
http://slidepdf.com/reader/full/pert-analysisusingms-project 16/16
Questions
! Thank you for joining the Phoenix-MPUG
Sponsored Web N Learn today
! Information on claiming PDU for this event
will emailed to those attending
! Presentation slides will be posted to the
Member Area of the MPUG site archive
Phoenix