21
CE 4101 Project Planning and Construction Management Credit 3.0 Md Khalekuzzaman BSc(Civil Eng.), MASc(Env.Eng.), P.Eng. (Canada), FIEB Assistant Professor Department of Civil Engineering

Project Management with PERT & CPM Lecture 1

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

CE 4101

Project Planning and Construction Management

Credit 3.0

Md KhalekuzzamanBSc(Civil Eng.), MASc(Env.Eng.), P.Eng. (Canada), FIEB

Assistant Professor

Department of Civil Engineering

PERT –Program Evaluation And Review Technique

CPM –Critical Path Method

2CE4101

3CE 4101

References:

1. Introduction to Operations Research

By Frederick S Hillier and Gerald J. Lieberman (Chapter 10)

2. Project Management for Engineering & Construction By

G.D. Oberlender (2nd Ed.)

3. Operations Research: An Introduction Eighth EditionBy

Hamdy A. Taha

4CE 4101

Definition:

• Activity

• Network

• Duration

• Early Start (ES)

• Early Finish (EF): ES+D

• Late Finish (LF):

• Late Start (LS): LF- D

• Total Float (TF): LE- EF = LS – ES

• Free Float (FF) : FFi = ESj – EFi

• Critical Path: TF & FF = 0

• Dummy Activity

Page 145 of G.D. Oberlender (2nd Ed)

“PM for Engineering & Construction”

5CE 4101

Definition:

• Activity on Node (AON): is a project network, where each activity is

represented by a node.

• Activity on Arc (AOA): is a project network, where each activity is

represented by an arc.

6CE 4101

Example – The Reliable Construction CO. Project

(10.1 from Hillier & Lieberman):

7CE 4101

Example – The Reliable

Construction CO. Project

(10.1 from Hillier & Lieberman):

8CE 4101

Problem:

9CE 4101

Problem:

Start End

1

4

5

6

3

2

10CE 4101

Problem:

11CE 4101

Problem:

Start

EndA

C

D G

E

B

F

H

12CE 4101

The Critical Path:(Table 10.2

From Hillier & Lieberman):

Critical path:

START → A→B → C → E → F → J → L → N → FINISH

(Estimated) project duration = 44 weeks.

13CE 4101

14CE 4101

G E

H

ES=2

EF=29

ES=16

EF=22

ES=29

64

D

E

C

LS=20

LF=26

LS=16

LF=20

LF=16

ILS=18

LF=25

7

7

4

9

15CE 4101

Example – The Reliable

Construction CO. Project

(10.7 from Hillier & Lieberman):

16CE 4101

Example 6.5-2

Pg-270/Taha

Determine the critical path for the project network. All the

durations are in days.

activity (4,6) satisfies the first two conditions for a

critical activity (∆4=□4=13 & ∆6=□6=25) but not the

third(□6-□4≠D46). Hence, the activity is noncritical.

PERT Network:

• PERT differs from CPM in that it bases the duration of an activity on three

estimates:

1. Most likely estimate (tm or m)

= estimate of the most likely value of the duration

2. Optimistic estimate (t0 or a or 0)

= estimate of the duration under the most favorable conditions.

3. Pessimistic estimate (tp or p or b)

= estimate of the duration under the most unfavorable

conditions.

CE4101 17o Optimistic Most likely Pessimistic

Figure: Time Distribution Curve

PERT Calculation Procedure:

• PERT Procedure:

1. Draw the project network.

2. Expected duration of each activity, µ or 𝑡𝑒 =𝑡𝑜+4𝑡𝑚+𝑡𝑝

6

3. Standard normal deviation, 𝑧 =𝑇𝑠−𝑇𝑒

𝜎𝑐where, 𝜎𝑐

2 =𝑡𝑝−𝑡𝑜

6

2

σc = Variance

Ts = Specified or scheduled time to complete the project

Te = Duration of the project.

CE4101 18

CE4101

19

Calculation of µp(te)

and σ2 for Critical

Path

µp(te) = 2+4+10+4+5+8+5+6=44

σ2 =1/9+1+4+4/9+1+1+1+4/9 =9

Activity on

Critical Path

CE4101 20

PERT Calculation Procedure (cont.):

Approximating the probability of Meeting the deadline (Ts=47 as mentioned at

the beginning of the Problem)

𝑧 =𝑇𝑠−𝑇𝑒

𝜎𝑐=

47−44

√9= 3

3= 1

P ( T ≤ d) = P ( Standard normal ≤ z)

≈0.8413

≈ 84%

CE4101

21