Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
CPRI
Phasor Measurement Units - Applications in Power Systems and Renewable Energy Systems
1
Dr. Amit Jain
Joint Director Smart Power & Energy System
Central Power Research Institute [email protected]
CPRI
Energy Management System - EMS
EMS capabilities have evolved over the past five decades
EMS manage the flow of electricity in the grid
Operate the electric grid within safe limits
Operate the system reliably - Prevent Blackouts
Keep the Lights On !
Automatically adjust generation to follow instantaneous customer load changes (Electricity Cannot be Stored)
Identify potential risks and take preventive action
Expedite restoration of customers after an emergency
2
CPRI
EMS Applications
Supervisory Control and Data Acquisition (SCADA)
- Monitor physical system conditions in real time (2-4 sec)
- Perform supervisory controls
- Exchange data with external functions
Transmission Grid Management
- State Estimation (SE) for real-time transmission system
- Network Security Analysis: real time contingency analysis (CA) for N-1 system security
- System Optimization: remedial actions, volt/var control
3
CPRI
Current New Influences
Types of Generation and Customers
Renewable Generation and uncertainty in Wind, Solar generation etc.
Central markets (ISOs, RTOs, etc)
Market Participants (Gencos, retail, traders)
Network & Operations planning
Distribution management
Mandates from Regulators
RTOs (very large networks, UI, robustness)
Transmission planning & Congestion management
Technologies & Tools
Software advances: Artificial Intelligence, optimization engines, visualization
engines, integrated development/UI environments, Desktop applications
Economic communication and standardized device protocols
Web-enabled IT systems
New types of synchronized, fast measurements 4
CPRI
SCADA Architecture
Other control sites
Operators Reports
SCADA
Communication network
Supervisory C`ontrol Data Acquisition
RTU IED
IED
IED RTU
RTU PLC
Distributed
SCADA
RTU IED
IED
PLC RTU
RTU RTU
Distributed
SCADA
RTU
IED RTU
RTU
PLC
Front-end Power System Analysis
Decision Making
PMU
CPRI
Motivation/Need for Synchrophasor Technology
A wish list for system operators to empower them:
Visualisation of dynamic behaviour
Stability aspects
Operate the system at its limits
State determination
6
CPRI
Phasor Representation of the Sinusoid
CPRI
8
CPRI
9
Inputs and type of Data
Voltage inputs from Bus CVT/PT
Line currents from line CT of selected feeder
GPS clock input
Synchrophasor data available at the control centre
Voltage & Current phasor (Positive, negative & zero sequence)
Frequency & Rate of change of frequency
Power flow (MW and MVAr)
Angular difference
Inputs to PMU
Time synchronized
CPRI
10
Synchrophasor Applications
Situational Awareness
Decision Support
Real Time Analysis (SE/CA)
Oscillation monitoring
Planning
Automated Control
CPRI
11
The lack of wide-area visibility prevented early
identification of the August 14, 2003 Northeast blackout
The U.S.-Canada investigation report into the blackout
hypothesized that if a phasor system had been in
operation at that time, the blackout preconditions — in
particular, the growing voltage problems in Ohio —
could have been identified and understood earlier in the
day
In the last few minutes before the cascade, there was a
significant divergence in phase angle between Cleveland
and Michigan
CPRI
12
Diverging phase angles on the afternoon of August 14, 2003
CPRI
13
Cleveland Separation –Aug 14 , 2003
CPRI
14
CPRI
15
Wind Generation on 03-06-10
CPRI
16
CPRI
17
CPRI
18
PMUs collect data at a much higher sampling rate than SCADA, the
granularity of the data can reveal new information about dynamic
stability events on the grid
This is evident when comparing the phasor data to SCADA data
collected for the same event on February 7, 2010
This offers an example of the information that SCADA misses because
its relatively slow scan times cannot capture the dynamic response of
the system.
CPRI
19
PMU Data v. 4-second SCADA data for February 7, 2010 event
This plot shows 4 second scan rate SCADA frequency data for several
sites in a small geographic area. Some small fluctuations in system
frequency are visible but since only two units recorded a change, the
signals appear to be more noise than a measurement of anything of
note.
CPRI
20
PMU data from several sites for the same event. Not only did the
PMUs reveal system dynamics that the SCADA data missed, it
captured more accurate information about the event
The observed frequency excursion captured by the PMUs shown was
much larger than what the SCADA data indicated (59.91 HZ
minimum versus 60.00 HZ). The PMUs also captured system
oscillations that continued for about 7 seconds after the event
PMU data for February 7, 2010 event
CPRI
The voltage and angle at the wind turbine generator
transients in wpp has very small window, conventional SCADA is not able to capture them. But PMU has the ability to capture these small transients too.
CPRI
PSS tuning at Karcham Wangtoo Hydro Electric Power Plant
Screenshot of PMU data display at NRLDC on 23-August 2012 at 19:02 hrs
R phase to Neutral voltage of Wangtoo 400 kV Bus
Source: Synchrophasors - Initiative in India 2013
PMUs high resolution data is used in online tuning of hydro power plant. This is extremely helpful in the situations when dam is overflowing and it is difficult to shut down the hydro station.
CPRI
Wide Area Monitoring
A Wide Area Monitoring System acquires
GPS-synchronized current, voltage and
frequency phasor measurements, which are
measured by Phasor Measurement Units
(PMUs), from selected locations across the
power system.
23
CPRI
24
Wide Area Monitoring (cont…)
CPRI
25
Potential PMU Applications for Wide Area Monitoring and
Control
Wide-Area Visualization and Monitoring
Angle and Frequency Monitoring
Inter-area Oscillation Detection & Analysis
Proximity to Voltage Collapse
State Estimation
Fast Frequency Regulation
Transmission Fault Location Estimation
Dynamic Model Validation.
CPRI
Visualization Applications
26
Frequency and rate-of-change of frequency
Positive, negative, and zero sequence plots of system voltage
Damping constant calculations
Power flow / change in power flow / general change detection
Oscillation Identification / frequency calculation
Historical Trends
Event Signature Analysis
CPRI
PMU placement
It is not at all necessary to place PMUs at all busses in the
power system to make it observable.
When a PMU is placed at a bus, then it's neighbouring
busses also become observable.
In general, a system can be made observable by placement
of PMUs on approximately 15% to 25% of the busses in the
system
Optimal PMU placement problem i.e., minimum PMU
placement problem for system observability, can be
formulated as an Integer Linear Programming (ILP)
problem.
27
CPRI
28
CPRI
Present Indian Grid Plan
National Load Dispatch Center (NLDC) in Delhi
Regional Load Dispatch Center (RLDC) North
Regional Load Dispatch Center (RLDC) W, S, E, NE
State Load Dispatch Center (SLDC)
Sub Load Dispatch Center (SubLDC)
Substation
State Load Dispatch Center (SLDC)
Substation
Sub Load Dispatch Center (SubLDC)
User User
CPRI
30
CPRI
System Architecture
31
CPRI
Modeling of Power System Components
Generators
Transformers
Transmission Lines
Shunts (Reactors and Capacitors)
HVDC etc
LoadS
Appropriate Simulation/Analysis Software
Power System Modeling
Most critical for Appropriate results
CPRI
Real-Time Market
Security Constrained Economic Dispatch using:
Load Forecast or Current Demand
Telemetered generator output, dispatch limits or ramp rates
Energy offers
Transmission Constraints
Good and reliable State Estimation crucial
Run every 5 minutes and also on demand
CPRI
Measurements from SCADA
- Line power flows, bus voltage, line current magnitudes, generator outputs, loads
- Circuit breaker, switch status information
- Transformer tap positions, and switchable capacitor bank values
- Used for various EMS applications at the control center like state estimation,
contingency analysis, load forecasting, AGC and optimal power flow
Limitations
- Unreliable due to errors in measurements, telemetry failures, communication noise
- Not the direct operating state of the system ( V, θ )
- Every point cannot be telemetered
CPRI
The main objective of the real time monitoring is to maintain the secure operation of the system as the operating conditions vary.
The basis for the security analysis is the knowledge of the system state or the state vector under steady state conditions.
State Estimator consists of:
Topology processor
Observability Analysis
State Estimation Solution
Bad data processing
Parameter and Structural Error Processing
The output of the state estimation is in turn used for other functions in the control center such as load forecasting, optimal load dispatch, security analysis, generation scheduling etc
35
CPRI
State Estimation (SE)
The State Estimation (SE) is used for assessing (Estimating) the
Electric network state.
It shall assess loads of all network nodes, and, consequently,
assessment of all other state variables (voltage and current phasors
of all buses, sections and transformers, active and reactive power
losses in all sections and transformers, etc.) in the Electric network.
36
CPRI
PMUs in Static State Estimation (SSE)
The accuracy of the measurements used is an important parameter in determining the accuracy of the estimation process.
The high accuracy of the PMU measurements and their ability to measure voltage angular measurements, allow them to have a special status in the state estimation techniques.
As the PMUs may not be installed at all locations, the measurements available at the control center will have a mixture of both normal and PMU measurements.
The state estimation function has to carefully use both the measurement sets and estimate the state of the power systems accurately.
37
CPRI
PMUs in the system and estimation error
PMU location
Minimum Average Voltage
magnitude Estimate
Minimum Average Angular
Estimate
No PMU 2.9821% 8.7062%
2 0.3765% 1.5356%
7 0.3301% 1.6898%
15 0.4608% 0.7545%
22 0.2934% 0.8028%
28 0.3360% 1.9609%
PMU location
Minimum Average Voltage
magnitude Estimate
Minimum Average Angular Estimate
No PMU 2.9821% 8.7062%
2 and 7 0.3280% 1.6981%
7 and 15 0.3874% 0.8469%
22 and 28 0.2587% 0.8361%
2 and 28 0.3240% 1.6861%
2, 7 and 15 0.3931% 0.9483%
15, 22 and 28 0.2237% 0.8039%
2, 7, 15 and 22 0.2562% 0.8831%
2, 7, 15, 22 and 28 0.2173% 0.7958%
Single PMU case Multiple PMU case
38
CPRI
0.0000%0.5000%1.0000%1.5000%2.0000%2.5000%3.0000%3.5000%
No P
MU 2 7
15
22
28
2 a
nd 7
7 a
nd 1
5
22 a
nd 2
8
2 a
nd 2
8
2,
7,
and 1
5
15,
22 a
nd 2
8
2,
7,
15 a
nd 2
2
2,
7,
15,
22 a
nd 2
8
PMU Location
Vari
ait
on
of
Vo
ltag
e m
ag
nit
ud
e
sti
mate
Err
or
(%)
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
No
PM
U 2 7 15 22 28
2 an
d 7
7 an
d 15
22 a
nd 2
8
2 an
d 28
2, 7
, an
d 15
15,
22 a
nd 2
8
2, 7
, 15
and
22
2, 7
, 15
, 22
and
28
PMU location
Var
iait
on
of
Err
or
in V
olt
age
An
gu
lar
Est
imat
es (
%)
Average Voltage Magnitude Estimates with
PMU
Average Voltage Angular Estimates with PMU
weight
39
CPRI
Dynamic State Estimation
Power system is dynamic system and its dynamism is triggered by its
continuous variation of loads.
These dynamic changes in the power system cannot be captured by the
traditional Static State Estimation (SSE) techniques
The estimation techniques are computationally intensive to be used
continuously, hence, they are run at fixed instants of time or when there is
sufficient change in the power system.
An advance Estimation technique will help:
Dynamic State Estimation
40
CPRI
DSE algorithms use mathematical modeling of the time
behavior of the system to cater to the dynamic changes of the
power system and predict the state of the system one step
ahead.
Once the new measurements at the next instant of time arrive,
the predicted values are simply upgraded or filtered to obtain a
more accurate estimate of the states.
This ability of predicting the system state ahead of time is a
big advantage as the security analysis can be performed ahead
of time and hence, gives the system operator more time to
decide on the future course of action, in case of an emergency.
41
CPRI
Dynamic State Estimation (DSE) The quasi static nature of the power system necessitates a more accurate
model to describe its time varying nature, which led to the use of DSE.
The Steps of DSE are:
Mathematical Modeling
State Prediction
State Filtering
42
CPRI
Model Used for DSE
Mathematical Model:
State Prediction:
Where
The covariance of the predicted state vector is given by:
1k k k k kx F x G w
1ˆ
k k k kx F x G
‘k’ refers to present instant of time and ‘k+1’ refers to the next instant of time.
( ) (1 )i i iF k
( ) (1 )(1 ) ( ) ( 1) (1 ) ( 1)i i i i i k iG k x k a k b k
( ) ( ) (1 ) ( )i i i ia k x k x k
( ) [ ( ) ( 1)] (1 ) ( 1)i i i i ib k a k a k b k
1
T
k k k k kN F F Q
43
CPRI
State Filtering:
The problem of incorporating the PMU measurements in to the DSE has to be dealt in the state filtering stage
Here the optimization function is given by:
The Extended Kalman Filter (EKF) technique is used for optimizing the above equation and the final equation for the filtering step can be written as
Where
1 1( ) [ ( )] [ ( )] [ ] [ ]T TJ x Z h x R Z h x x x N x x
1 1 1 1 1ˆ [ ( )]k k k k kx x K Z h x
1 1 1 1 1
1 1 [ ]T T T
k kK H R H R H N H R
44
CPRI
14 bus single PMU case
Location of PMU
Average Predicted Voltage
magnitude estimate error
(%)
Average Predicted
Voltage angular estimate error
(%)
Average filtered Voltage
magnitude estimate error
(%)
Average filtered Voltage angular estimate error (%)
No PMU 0.9363% 3.6236% 0.5368% 2.8683%
2 0.6603% 1.4824% 0.1662% 0.6247%
3 0.6832% 2.1125% 0.1641% 1.1004%
4 0.5618% 1.3379% 0.0970% 0.6088%
5 0.7029% 2.3787% 0.2115% 1.4202%
6 0.6373% 0.9601% 0.1864% 0.6438%
7 0.5538% 1.1105% 0.0448% 0.5825%
8 0.6603% 1.4824% 0.1662% 0.6247%
9 0.5841% 1.0379% 0.0429% 0.4715%
10 0.5167% 1.4697% 0.0513% 0.6662%
11 0.5517% 2.1092% 0.1020% 1.2301%
12 0.3175% 1.6836% 0.0697% 0.9207%
13 0.4259% 0.9797% 0.0995% 0.4142%
14 0.4540% 2.1743% 0.0459% 1.4805%
45
CPRI
IEEE 14 bus – Multiple PMU Case
location
Average Predicted
Voltage magnitude
estimate error (%)
Average Predicted
Voltage angular
estimate error (%)
Average filtered
Voltage
magnitude
estimate error
(%)
Average filtered
Voltage angular
estimate error
(%)
No PMU 0.9363% 3.6236% 0.5368% 2.8683%
7 and 9 0.5672% 1.0532% 0.0394% 0.4749%
7 and 10 0.5627% 1.2402% 0.0490% 0.5505%
7 and 14 0.5406% 1.2711% 0.0407% 0.6210%
9 and 10 0.5766% 1.2276% 0.0500% 0.6379%
9 and 14 0.5816% 1.0432% 0.0421% 0.4395%
10 and 14 0.5190% 1.6028% 0.0490% 0.7399%
7, 9 and 10 0.5816% 1.2153% 0.0453% 0.6159%
7, 10 and 14 0.5413% 1.2225% 0.0383% 0.5305%
7, 9, 10 and 14 0.5837% 1.2101% 0.0473% 0.5635%
46
CPRI
0.0000%
0.2000%
0.4000%
0.6000%
0.8000%
1.0000%
No
PM
U 7 9
10
14
7 a
nd
9
7 a
nd
10
7 a
nd
14
9 a
nd
10
9 a
nd
14
10
an
d 1
4
7,
9 a
nd
10
7,
10
an
d 1
4
7,
9,
10
an
d 1
4
location of PMU
Av
era
ge
Vo
lta
ge
Ma
gn
itu
de
Err
or
(%)
Predicted Values
Filteerd Values
0.0000%0.5000%1.0000%1.5000%2.0000%
2.5000%3.0000%3.5000%4.0000%
No
PM
U 7 9 10 14
7 an
d 9
7 an
d 10
7 an
d 14
9 an
d 10
9 an
d 14
10 a
nd 1
4
7, 9
and
10
7, 1
0 an
d 14
7, 9
, 10
and
14
Location of PMU
Ave
rag
e V
olt
age
An
gu
lar
Err
or
(%)
Predicted values
Filtered Values
Variation of voltage magnitude error for various locations of PMU
Variation of voltage angular error for various locations of PMU
47
CPRI
IEEE 30 bus - Single PMU case
Location
of PMU
Average
Predicted Voltage
magnitude
estimate error
(%)
Average
Predicted Voltage
angular estimate
error (%)
Average filtered
Voltage
magnitude
estimate error
(%)
Average
filtered Voltage
angular
estimate error
(%)
No PMU 1.3202% 13.2941% 0.7030% 5.8810%
2 1.2974% 7.4226% 0.4862% 3.6865%
7 1.2644% 7.4909% 0.4663% 3.1897%
15 1.3140% 5.9341% 0.3799% 1.6914%
22 1.1873% 6.3590% 0.3641% 1.8900%
28 1.3058% 7.1982% 0.5201% 3.5637%
48
CPRI
IEEE 30 bus – Multiple PMU case
Location of
PMU
Average
Predicted Voltage
magnitude
estimate error
(%)
Average Predicted
Voltage angular
estimate error (%)
Average filtered
Voltage magnitude
estimate error (%)
Average filtered
Voltage angular
estimate error
(%)
No PMU 1.3202% 13.2941% 0.7030% 5.8810%
2 and 7 0.9675% 8.6076% 0.4453% 2.9504%
7 and 15 1.2562% 6.3429% 0.3451% 1.7686%
22 and 28 1.1288% 6.7794% 0.2928% 2.2906%
2 and 28 1.2520% 7.5604% 0.4359% 3.5984%
2, 7 and 15 1.2512% 6.6138% 0.3360% 1.8787%
15, 22 and 28 1.1214% 5.9944% 0.2007% 1.9395%
2, 7, 15 and
22 1.1187% 6.0148% 0.1933% 1.7209%
2, 7, 15, 22
and 28 1.1037% 6.2560% 0.1818% 1.9434%
49
CPRI
IEEE 30 bus – Multiple PMU case
0.0000%0.2000%0.4000%0.6000%0.8000%1.0000%1.2000%1.4000%1.6000%
No
PM
U 2 7
15
22
28
2 a
nd
7
7 a
nd
15
22
an
d 2
8
2 a
nd
28
2, 7
an
d 1
5
15
, 2
2 a
nd
28
2, 7
, 1
5 a
nd
22
2, 7
, 1
5, 2
2 a
nd
28
PMU location
Avera
ge v
olt
ag
e m
ag
nit
ud
e E
rro
r
Predicted Values
Filtered Values
0.0000%
2.0000%4.0000%
6.0000%8.0000%
10.0000%12.0000%
14.0000%
No
PM
U 2 7 15 22 28
2 an
d 7
7 an
d 15
22 a
nd 2
8
2 an
d 28
2, 7
and
15
15, 2
2 an
d 28
2, 7
, 15
and
22
2, 7
, 15,
22
and
28
location of PMU
Ave
rae
Vo
ltag
e A
ng
ula
r E
rro
r
Predicted values
Filtered Values
Variation of error in predicted and filtered voltage magnitude estimates
Variation of error in predicted and filtered voltage angular estimates
50
CPRI
51
By 2013, many projects in North America are using
the following applications (though not in real-time
operations yet):
Wide-area monitoring and visualization
Voltage stability monitoring
Islanding and restoration
Post-event analysis
Model validation
CPRI
Summary
Growing power systems also result in a growing need for more accurate monitoring for detection and control of risks
Wide Area Monitoring Systems (WAMS) to have better visualization of grid to improve real time monitoring of power systems to enhance system operation capabilities
Integration of Wind and Solar Generations, and distributed generation and latency and time skew in data necessitates installation of PMUs
With developments in hardware and software technologies resulting in reduction of the prices of phasor measurement units, more and more utilities are increasing their PMU installations for Wide Area Monitoring of Power Systems
CPRI
Thank You
53