Upload
priscilla-walters
View
223
Download
6
Tags:
Embed Size (px)
Citation preview
Progress report on the test facility project design and construction
P. Schnizer and L. Serio on behalf of bldg. 180 test facility project team members (TE and EN)
and GSI/FAIR colleagues
L. Serio 3
Outline
• Introduction• Project Plan update– Scope of work, financing and organization
• Progress report– Executive summary– Schedule– Individual WPs reports
• Conclusions
CERN – GSI c.tte meeting 20141205
Introduction Following the decisions at the last collaboration meeting we have:
- worked and finalised the test program and functional requ.ts - proceeded with the review of the internal / external interfaces- developed a detailed project plan and resource loaded schedule- implemented the new scope of work and financing
Several meetings have taken place between CERN and FAIR personnel leading to the definition and technical agreement of the requirements, plans, resources and design reported hereafter
- over 50 EDMS technical documents were produced- 5 general technical coordination meeting (CERN-GSI) were held- several specific technical meetings for individual WPs took place
Detailed design activities were started according to the maturity reached and the agreed schedule.
Procurements have been launched for the main long lead items.CERN – GSI c.tte meeting 20141205 L. Serio 4
46 days (41 working days - cryo also during non working days)installation & preparation number of magnets tested per yearcooling4 K tests or 1.5 magnets per monthwarm upwarm tests and disconnect
16with 3 test benches and 13 days cold magnetic 4
10
1013
4
Introduction
CERN – GSI c.tte meeting 20141205 L. Serio 5
Outline
• Introduction• Project Plan update– Scope of work, financing and organization
• Progress report– Executive summary– Schedule– Individual WPs reports
• Conclusions
CERN – GSI c.tte meeting 20141205 L. Serio 6
Project Plan: Scope of Work
Addendum n.2 to the 2010 Agreement K1727/DG CERN - GSI‐ Cryogenic testing at CERN of Super Fragmentation Separator (SUPER-FRS)
Magnets for FAIR‐ 3 prototypes, 52 series and 2 spares magnets‐ Refurbishing and upgrade of the existing cryogenic test facility located in
the test hall n. 180 at CERN - Meyrin
Addendum n.4 to the 2010 Agreement K1727/DG CERN - GSI‐ Additional equipment requested by GSI for the implementation of
Addendum n.2‐ Pre-cooler‐ Quench detection and energy extraction system ‐ Survey tools
CERN – GSI c.tte meeting 20141205 L. Serio 7
Implementation status• Scope of work – done
• Preliminary requirements fixed with GSI/FAIR• Test program and WBS established• Interface functional document released
• Schedule- done; magnets procurement reviewed schedule (?)• Test phases, sequence and overall testing rate established• Overall schedule and action plan established• Long lead items procurement phase launched
• Cost- done• PBS, WBS and financing plan established according to SOW
• Issue the Project Plan- done
• Implement the Project Plan – done; activities started
CERN – GSI c.tte meeting 20141205 L. Serio 8
Project Plan: Financing
Additional cost to refurbish the existing facility excluding available CERN infrastructure (e.g. building, cranes, cold box, …) and CERN staff involved in the project (evaluated at ~ 1 MCHF):
item budget# kCHF
1 12002 2603 1504 250
TOTAL 1860
Energy Extraction system (3 circuits)Test stand QPS based on LHC techn
description
Additional precooler w warm upAdditional survey tools
96100
7001728
78604179
12038 12039 1
Costing 3 test benches & 2 precooler - Construction - [kCHF]Material
staff (16 FTE-y but 1/3 for constr)non staff (17.3 FTE-y)GSI contributionCERN contribution
Contingency
CERN – GSI c.tte meeting 20141205 L. Serio 9
Project Plan: Organization
The project is part of the global cryogenics test facility refurbishment project of the TE department by Volker Mertens.
CERN – GSI c.tte meeting 20141205 L. Serio 10
CERN – GSICollaboration Committee
F. Bordry, M. JimenezO. Kester, E. Fischer
CERNTechnical Coordinator
Luigi Serio
FAIR Technical Coordinator
Pierre Schnizer
Magnetic Measurements
Stephan Russenschuck
Test FacilityMarta Bajko
Electrical Power Rene Necca
Power ConvertersHugues Thiesen
CryogenicsAntonio Perin
Quench ProtectionReiner Denz
Cooling and Ventilation
Michele Battistin
SurveyDominique Missiaen
Cryogenic Testing at CERN of SUPER -FRS Magnets for FAIROrganization Chart
EN Dept.
TE Dept.
HSEAndre Henriques
FAIR Mirror Organization
ICEPhilippe Gayet
IntegrationYvon Muttoni
Energy ExtractionKnud Dahlerup-
Petersen
Handling and transport
Ingo Ruehl
Platforms and structures
Mats Willhelmson
Project Mgt. support
David Hay
Outline
• Introduction• Project Plan update– Scope of work, financing and organization
• Progress report– Executive summary– Schedule– Individual WPs reports
• Conclusions
CERN – GSI c.tte meeting 20141205 L. Serio 11
Progress report: Overall Status– Project Plan finalised and implemented– Integrated planning prepared– Some resources still involved in the LHC re-commissioning
– Functional requirements received, discussed, reviewed and finalised• 2 months delay
– Detailed interface requirements pending • expected to be finalised by November 2015 (!)
– Ready to proceed with procurement of 60 to 70 % of the assets– CWS on time with procurement activities launched (MS, IT)– CRYO delayed about 3 months (MS and IT in preparation)– Remaining systems not on critical path
CERN – GSI c.tte meeting 20141205 L. Serio 12
Main interface documents
CERN – GSI c.tte meeting 20141205 L. Serio 13
Outline
• Introduction• Project Plan update– Scope of work, financing and organization
• Progress report– Executive summary– Schedule– Individual WPs reports
• Conclusions
CERN – GSI c.tte meeting 20141205 L. Serio 14
ScheduleFix layout interfaces
LLI procurements
Commissioning
3 test benches, 2 CWUs12 days cold testing J F A J J A S O N D J F A J J A S O N D J F A J J A S O N D J F A J J A S O N D J F A J J A S O N D J F A J J A S O N D J F A J J A S O N D J F A MJ J A S O N DConceptual DesignPreliminary Design/InterfFinal DesignProcurementManufacturingInstallationCommissioningMultiplet contract signDipole FDR, contract signMultiplet design, manufctDipole Design, ManufctProto magnets testingSeries Magnets TestingShort Multiplets Proto . . .Long Multiplet Proto . . .Dipole Proto . . .First Series Short MultipletFirst Series Long MultipletFirst Series DipoleFirst Energy Buncher ?Last Energy Buncher ?PANDA testing ?
2021
CERN – GSI c.tte meeting 20141205 L. Serio 15
Accruals of activitiesForecasted planning wrt current delayForecasted planning according to delayed activitiesBaseline
Main critical milestones3 test benches, 2 CWUs12 days cold testing J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F MA MJ J A S O N D J F A J J A S O N D J F A J J A S O N D J F A J J A S O N DConceptual DesignPreliminary Design/InterfFinal DesignProcurementManufacturingInstallationCommissioningMultiplet contract signDipole FDR, contract signMultiplet design, manufctDipole Design, ManufctProto magnets testingSeries Magnets TestingShort Multiplets Proto . . .Long Multiplet Proto . . .Dipole Proto . . .First Series Short MultipletFirst Series Long MultipletFirst Series DipoleFirst Energy Buncher ?Last Energy Buncher ?PANDA testing ?
2014 2015 2016 2017 2018
Outline
• Introduction• Project Plan update– Scope of work, financing and organization
• Progress report– Executive summary– Schedule– Individual WPs reports
• Conclusions
CERN – GSI c.tte meeting 20141205 L. Serio 16
WP: Integration 1/4DONE• Review of the general layout• Integration of all the different magnets types/dimensions/layout• Definition of the position, size and layout of the main equipment (ALL)• Routing of the main piping (CWS, CRYO)
IN WORK• Integration meeting on-going to support design integration and procurement activities• Routing of cabling
DELAYED• Layout and interface of magnets supporting system• Final layout of platforms and routing of water cooling cables, DAQ and control cables, proximity
cryogenics
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1314744/1• https://edms.cern.ch/document/1437783/1• https://edms.cern.ch/document/1422391/1• https://edms.cern.ch/document/1440542/1
CERN – GSI c.tte meeting 20141205 L. Serio 17
WP: Integration 2/4
CERN – GSI c.tte meeting 20141205 L. Serio 18
WP: Integration 3/4
CERN – GSI c.tte meeting 20141205 L. Serio 19
WP: Integration 4/4
CERN – GSI c.tte meeting 20141205 L. Serio 20
WP: SafetyDONE• Launch Safety Agreement prepared, reviewed and released• Review of magnets pressure ratings, safety devices and test needs• Definition of safety requirements applicable to the facility and the magnets• Review of overall layout of the facility from a safety point of view
IN WORK• Update of the Launch Safety Agreement according to the design maturity and
procurement activities
DELAYED• NA
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1326801/1• https://edms.cern.ch/document/1364870/2• https://edms.cern.ch/document/1419927/1
CERN – GSI c.tte meeting 20141205 L. Serio 21
WP: Cooling and Ventilation 1/3DONE• Preliminary design and interfaces (users) requirements definition• Layout and integration• Market Survey, firms selection• Technical Specification
IN WORK• Call for tender sent to firms
DELAYED• NA
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1435672/1• https://edms.cern.ch/document/1421010/2
CERN – GSI c.tte meeting 20141205 L. Serio 22
WP: Cooling and Ventilation 2/3
CERN – GSI c.tte meeting 20141205 L. Serio 23
WP: Cooling and Ventilation 3/3
CERN – GSI c.tte meeting 20141205 L. Serio 24
WP: CryogenicsCRITICAL PATH WP
DONE• Functional requirements for the cryogenic system• Preliminary design of the cryogenics production plant• PFDs of the overall system• Definition of the utilities requirements (EL, CW)• Preparation of bldg 279 and galleries sites (cleaning and clearing)• Preparation of the refrigerator cold box cabling and instrumentation (cleaning and clearing)• Draft Market Surveys for the Compressor Station, Pre-cooler, Transfer lines and Satellite Boxes
IN WORK• Market Survey dispatch to firms• Draft of the technical specifications• Review of cryogenic interfaces with magnets• Minimum required consolidations for abandoned facilities (bldgs repairs, clearing and cleaning)
DELAYED• MS and IT – about 2 months
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1355497/1• https://edms.cern.ch/document/1430162/0.1
CERN – GSI c.tte meeting 20141205 L. Serio 25
WP Cryogenics Progress in the detailed definition
Revised Block Diagram for Cryogenic Infrastructure Detailed scheme of Pre-cooler #2Goal: producing a temperature difference of 50 K at 50 g/s of helium flow during warm up and cool down.
• Finalization of the configuration• Production of PFDs & PIDs • Naming of components• List of instrumentation• Market surveys and technical specification documents in preparation
CERN – GSI c.tte meeting 20141205 L. Serio 26
WP Cryogenics: Integration & buildings
B180 integration: most aspects frozen Integration study of compressors in B279 by using the existing concrete blocks done.Options limited and not optimum.Decision taken to redo the compressor supports.
Integration studies
Buildings preparation
B279
• B180 de-cabling nearly completed• B279 (compressors) stripped to walls B180
CERN – GSI c.tte meeting 20141205 L. Serio 27
WP: Magnetic MeasurementsDONE• Review of magnet test program, time and tools requirements• Measurement strategy within the boundary constrains reviewed (streamlined tests, analysis and overall
test time assessed)• Specification of the required measurements, program and precision targets
– Flux meters and rotating coil probes– Main field component: 5 10-4
– Field quality dipole: 5 10-5
– Other harmonics quadrupole: 5 10-5
– Other magnets: 1 10-3 and 2 10-4
IN WORK• Development on the fluxmeter and rotating coils (challenging precision measurements, high cost of
industrially available instruments) • Review of finalised magnet database and required test data – September 2014 in order to launch the
required development and procurements
DELAYED• NA
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1416580/1
CERN – GSI c.tte meeting 20141205 L. Serio 28
WP: TF and ICEDONE• Facility test program and optimised activities duration• Instrumentation list review and finalisation
IN WORK• Specifications for DAQ and signals exchange being prepared• Specifications for main powering cables• Specifications for signal and acquisition cables
DELAYED• PBS, WBS and detailed schedule
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1416581/1• https://edms.cern.ch/document/1431417/1• https://edms.cern.ch/document/1431421/1• https://edms.cern.ch/document/1450763/1
CERN – GSI c.tte meeting 20141205 L. Serio 29
WP: Power ConvertersDONE• Detailed technical specification of power converters and utilities
requirements• Procurement of Power Converters launched (PCs expected at CERN mid-
2015)
IN WORK• Interfacing with Energy Extraction System and Powering Interlock System
DELAYED• NA
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1416136/1
CERN – GSI c.tte meeting 20141205 L. Serio 30
WP: Platforms and StructureDONE• Layout and integration with all magnets types and dimensions• Review of the interfaces requirements
IN WORK• Freezing of magnets interfaces / final design• Requirements for magnets support and anchoring• Layout of the cryogenic distribution and cabling routing
DELAYED• Detailed design and cost optimisation
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1416776/1• https://edms.cern.ch/document/1314744/1• https://edms.cern.ch/document/1437783/1• https://edms.cern.ch/document/1422391/1• https://edms.cern.ch/document/1440542/1
CERN – GSI c.tte meeting 20141205 L. Serio 31
Magnets interfaces and dimensions
CERN – GSI c.tte meeting 20141205 L. Serio 32
Platform review and optimization
CERN – GSI c.tte meeting 20141205 L. Serio 33
Platform review and optimization
CERN – GSI c.tte meeting 20141205 L. Serio 34
WP: Quench ProtectionDONE• Review of requirements • Plan to use LHC type QPS and DAQ for voltage signals
IN WORK• NA
DELAYED• NA
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1422805/1
CERN – GSI c.tte meeting 20141205 L. Serio 35
WP: Energy ExtractionDONE• Review of requirements • Conceptual design of EE system• Use of LHC extraction system with classical dump resistor
IN WORK• NA
DELAYED• NA
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1422805/1
CERN – GSI c.tte meeting 20141205 L. Serio 36
WP: Energy Extraction
• No R&D, design/ordering of 1.4 Ω - 1MJ dump-resistors (one per system)• Consolidation of the existing 6 extraction systems (from the LHC 2013)
CERN – GSI c.tte meeting 20141205 L. Serio 37
WP: SurveyDONE• Review of requirements and definition of measuring points
IN WORK• Definition and layout of surveying tools based on layout and
optimization of measuring points
DELAYED• NA
REFERENCE DOCUMENTS• https://edms.cern.ch/document/1416779/1
CERN – GSI c.tte meeting 20141205 L. Serio 38
Conclusions 1/2
• Functional requirements and testing scenario finalised• Integrated schedule and detailed workplan established• Procurement of long lead items launched• Minimal delays wrt original plan due to– Lack of maturity of SFRS design for interface definition– Resources availability (LHC commissioning)
• Cryogenics (production part) on critical path for test infrastructure availability in summer 2016
• Proximity cryogenics pending interface detailed design definition
CERN – GSI c.tte meeting 20141205 L. Serio 39
Conclusions 2/2
• Detailed interface requirements for magnets interface still pending design development (November 2015 (!))– Proximity cryogenics, platforms, support structure impacted– Remaining system can, in principle, proceed according to plan
• Proposal is to continue with what is fixed and review remaining parts later according to– Detailed design/construction planning from magnets
manufacturers– Availability of detailed design interfaces
• Advantages: less integrated resources usage, fixing of interfaces with a mature design not leading to changes and cost for CERN and GSI
• Risks: unknown availability of resources by CERN at a later stageCERN – GSI c.tte meeting 20141205 L. Serio 40
References
• Project Plan (contains all up to date information): – EDMS: https://edms.cern.ch/document/1370663/3
• Technical coordination meetings and reviewed interface parameters:– EDMS: https://
edms.cern.ch/nav/P:FAIR-000001263:V0/P:FAIR-000002500:V0/TAB3
• Interface requirements documents:– https://
edms.cern.ch/nav/P:FAIR-000001263:V0/P:FAIR-000002718:V0/TAB3 CERN – GSI c.tte meeting 20141205 L. Serio 41