Project Management.pptx

Embed Size (px)

Citation preview

  • 7/22/2019 Project Management.pptx

    1/37

    Group Members

    Nipuna Weerakoon (105649)

    Sorwar Hussain (106815)

  • 7/22/2019 Project Management.pptx

    2/37

    Background of chosen project

    Project and project management

    Five phases of project

    Project parameters

  • 7/22/2019 Project Management.pptx

    3/37

    ?

  • 7/22/2019 Project Management.pptx

    4/37

    Dinner dance ceremony

    DINNER

    Date - 18thApril 2010

  • 7/22/2019 Project Management.pptx

    5/37

    Place - Avoca house hotel London on 18thApril 2010

    conduct by Hot pot event Management Company.

    Sponsors Avoca house hotel owner.

    Ticket 50 Invited guest 150

    HPEM on 20thMarch 2010 start to plan the event.

    PM has 30 days to arrange everything.

  • 7/22/2019 Project Management.pptx

    6/37

    A temporary endeavour undertaken to accomplish aunique purpose

    Temporary UniqueCharacteristicOf project

    A targetoutcome

    A defined lifespan

    Crossorganisationalparticipation

    New orunique

    Time cost andperformancerequirement

  • 7/22/2019 Project Management.pptx

    7/37

    Specific time line

    Unique outcome

    Incremental steps

    Goal driven Temporary endeavour

  • 7/22/2019 Project Management.pptx

    8/37

    ?

  • 7/22/2019 Project Management.pptx

    9/37

    Application of knowledge, skills, tools and techniques to project activates to

    achieve project requirements

    Advantage of project management

    Better control of financial, physical and human resource

    Improved customer relations

    Shorter development time

    Lower costs

    High quality and increased reliability

    High profit margins

    Improve productivity

    Better internal coordination

  • 7/22/2019 Project Management.pptx

    10/37

    Knowledge

    Understanding

    Interpersonal skills

  • 7/22/2019 Project Management.pptx

    11/37

    Beginning

    Middle End

    All projects have a beginning a middle an end.

    Project......

  • 7/22/2019 Project Management.pptx

    12/37

    Five Steps of project life cycle

    1.) Initiation

    2.) Planning

    3.) Execution

    4.Monitor/control

    5.Closeout

    Beginning

    Middle

    EndAll projects typically go through this five process

  • 7/22/2019 Project Management.pptx

    13/37

    Define the need

    Select the PM

    Document business need

    Develop project charter

    Activity Resources Start

    Date

    Finish

    Date

    Initiation

    Inspiration

    the ideas

    Getting a reflection of how the event

    goal and planning of everything

    21/03/2010 23/03/2010

  • 7/22/2019 Project Management.pptx

    14/37

    First Leading the team

    Second Managing the team

    A DB C E

    PM

    PM

    D

    CA

    E

    B

    F G H I

  • 7/22/2019 Project Management.pptx

    15/37

  • 7/22/2019 Project Management.pptx

    16/37

  • 7/22/2019 Project Management.pptx

    17/37

    Project Scope Management includes the processesrequired to ensure that the project includes all thework required to complete the project successfully

  • 7/22/2019 Project Management.pptx

    18/37

    Goal

    Sponsors Project managers

    Objectives Objectives

    .

    Goal : Charity program, ( collect money for selected Sri-Lankan poorstudent

  • 7/22/2019 Project Management.pptx

    19/37

    Objectives :

    To earn targets profit from event

    To increase good relationship between Sri Lankan younger generation in London

    To promote Avoca house hotel name between Sri Lankan people

    who still live in London

    To provide high quality food and services for invited guests

    To plane and finish event on time

  • 7/22/2019 Project Management.pptx

    20/37

    To manage the project time efficiently

  • 7/22/2019 Project Management.pptx

    21/37

    Ceremony start time : 7.30pm End time: 11.30pm

    Define the activities

    number of work periods needed to complete individual activities

    with the estimated resources

  • 7/22/2019 Project Management.pptx

    22/37

    Activity Cost

    Location Free

    Food 1500

    Drinks 750

    Decoration 300

    OtherTotal cost

    5003050

    Plan to save for charity - 4450

  • 7/22/2019 Project Management.pptx

    23/37

    Main Entrance

    BAR

    2 waiters

    Buffet, 3 waitresses working

    Kitchen

    3 Chefs 7 Kitchen supporters

    Car Park

    2 Security working

    2 Security

    Around the Hall 3 waiters and 2 waitresses giving services for guests

    DJ HIT

  • 7/22/2019 Project Management.pptx

    24/37

    Determine goals, scope and project constraints

    Identify members and their roles

    Define communication channels, methods, frequency

    and content Risk management planning

    Create WBS and timeline

    Planning

    Budget and how

    expenses will be

    start

    FinancialBudget

    NJ caters

    Decoration

    Max Beverage

    DJ Hit

    24/03/2010 28/03/2010

  • 7/22/2019 Project Management.pptx

    25/37

    Create aproject

    plan

    Create aacceptance

    plan

    Create aquality plan

    Create aresource

    plan

    Create acommunication

    plan

    Create a performanceplan

    Create arisk plan

    Create aprocurement plan

    Review phaseCreate a supplier

    content

    Work Breakdown structure (WBS)

  • 7/22/2019 Project Management.pptx

    26/37

    Activity Resources Start

    Date

    Finish

    Date

    Initiation

    Inspiration the

    ideas

    Getting a reflection of how the event goal and

    planning of everything

    21/03/201

    0

    23/03/201

    0

    Planning

    Budget and how

    expenses will be

    start

    FinancialBudget

    NJ caters

    Decoration

    Max Beverage

    DJ Hit

    24/03/201

    0

    28/03/201

    0

    Venue the Date The Avoca House Hotel

    18thof April 2010 (Fixed by sponsor)

    29/03/201

    0

    30/03/201

    0

    Arranging the

    extra guest and

    sell ticket

    OperationalSell ticket 31/03/201

    0

    08/04/201

    0

    Team meeting

    giving

    instructions

    Giving responsibilities knowing the need of the

    sponsor

    09/04/201

    0

    10/04/201

    0

    Finalizing the

    items Food, Beverage ,Decorates, Music, Parking , 15/04/201

    0

    17/04/201

    0

    Execution

    The event day

    After the day

    Observing all the activities closely

    Handling of payment and Acknowledgement of

    17/04/201

    0

    18/04/201

    0

    Work Breakdown structure (WBS)

  • 7/22/2019 Project Management.pptx

    27/37

    Influence project

    Affected by its outcome

    Various authority levels

    Project Team

    Sponsor & Supporters

    Opponents

    Suppliers Customers

  • 7/22/2019 Project Management.pptx

    28/37

    Stakeholders Responsible for,

    Devon Caters Responsible for foodsMax Beverage Responsible for drinks

    DJ Hit Responsible for all kind ofmusic activities

    Camden Decorators Responsible for all kind of

    decorating in eventTeam members : Chef 3

    Kitchen helpers 7

    Waitress 5

    Waters 5Security 4

    Photographers 2

    Guests 150

    Direct

    Indirect

  • 7/22/2019 Project Management.pptx

    29/37

    The following are the 4Ms of a project which will be used toshow the methods and resources.

    Man Everyone working in this event will be locallyemployed.

    Machine Cooking equipment and music item

    Material To cut down the cost of production everything

    will be purchased locally.

    Money The project will be fully funded by Avoca househotel

  • 7/22/2019 Project Management.pptx

    30/37

    Execute project plan and accomplish project goals

    Send and receive information

    Implement approved changes

    Continuous improvement Team building

    Lessons learned (Surveys)

  • 7/22/2019 Project Management.pptx

    31/37

    Building Deliverables

    Monitor and control

    Time Mgt Risk Mgt

    Cost Mgt Issue Mgt

    Quality Mgt Procurement Mgt

    Change Mgt Acceptance Mgt

    Performance andcommunicate Mgt

  • 7/22/2019 Project Management.pptx

    32/37

    Team

    Problem solve

    Communication

    Interpersonal skills

    Decision taking

    Functional skills

    Application

    Performance

    Achievement

  • 7/22/2019 Project Management.pptx

    33/37

    Scope verification

    Measure according to your plan

    Risk Audits

    Use issue logs Measure Team member performance

    Create forecasts

  • 7/22/2019 Project Management.pptx

    34/37

    Confirm the work is done to requirements

    Closing

    The event

    day

    After the

    day

    Observing all the activities closely

    Handling of payment and

    Acknowledgement of employees.

    17/04/2010

    19/04/2010

    18/04/2010

    20/04/2010

    Overview of Project Management Knowledge Areas and Project Management Process

  • 7/22/2019 Project Management.pptx

    35/37

    j g g j g

    Mapping of Project Management Processes to the Process Group

  • 7/22/2019 Project Management.pptx

    36/37

    Process GroupsKnowledge Area

    Initiating Planning Executing Controlling Closing

    Project IntegrationManagement

    Project Plan Development Project Plan Execution Integrated Change Control

    Project Scope Management Initiation Scope PlanningScope Definition

    Scope VerificationScope Change Control

    Project Time Management Activity DefinitionActivity SequencingActivity duration EstimatingSchedule Development

    Schedule Control

    Project Cost Management Resource PlanningCost EstimatingCost Budgeting

    Cost Control

    Project Quality Management Quality Planning Quality Assurance Quality Control

    Project Human ResourceManagement

    Organizational PlanningStaff Acquisition

    Team Development

    Project CommunicationsManagement

    Communications Planning Information Distribution Performance Reporting Administrative Closure

    Project Risk Management Risk Management PlanningRisk IdentificationQualitative Risk Analysis

    Quantitative Risk AnalysisRisk Response Planning

    Risk Monitoring and Control

    Project ProcurementManagement

    Procurement PlanningSolicitation Planning

    SolicitationSource SelectionContract Administration

    Contract Closeout

    Mapping of Project Management Processes to the Process Group

  • 7/22/2019 Project Management.pptx

    37/37