139
COMMONWEALTH GAMES 2010. DELHI UNIVERSITY NORTH CAMPUS DELHI QUALITY ASSURANCE MANUAL (REVISION - II) VOLUME – I CIVIL & PLUMBING WORK PREPARED BY: M/s. NAGARJUNA CONSTRUCTION COMPANY LTD. SUBMITTED TO: M/s. ENGINEERS INDIA LTD.

QAM-VSB-02

Embed Size (px)

Citation preview

Page 1: QAM-VSB-02

COMMONWEALTH GAMES 2010.

DELHI UNIVERSITY NORTH CAMPUS

DELHI

QUALITY ASSURANCE MANUAL(REVISION - II)

VOLUME – I

CIVIL & PLUMBING WORK

PREPARED BY:

M/s. NAGARJUNA CONSTRUCTION COMPANY LTD.

SUBMITTED TO:

M/s. ENGINEERS INDIA LTD.

Page 2: QAM-VSB-02
Page 3: QAM-VSB-02

Name of Project: - Development of sports facilities & Associated Infrastructure Development works for Commonwealth Games 2010 at North Campus- Delhi University Delhi. (Package – 1 + Package - II)

Contractor

M/S Nagarjuna Construction Company Ltd.

PMC

M/s Engineers India Limited

Quality Assurance Manual

(REVISION - II)

Prepared by : Approved by: Reviewed by: Accepted by :

Signature

Name Mr. Anil Bhima Mr. Ajit Singh

Mr. V.S. Bhalkar

Mr. R. K. Rathi

Date

Designation

Asst. Manager

NCCL

JGM,

NCCL

Sr. Engineer

EIL

Project Manager,

EIL

Page 4: QAM-VSB-02
Page 5: QAM-VSB-02

INTRODUCTION

CHAIRMAN’S MESSAGE

A journey of success always requires the qualities of foresight, strategy and preparedness. All these, along with the power of trust are at the core of all our operation comes from your trust and willingness to believe in our capability to deliver.

NCC possesses a rich and diversified presence across the core growing sectors in the infrastructure arena. New windows of opportunity are opening up and NCC is prepared for an eventful future marked with important milestones. At NCC, we are leveraging on our rich past to address projects for the present with the objective to build the India of tomorrow.

Commitment, hard work, commonsense and perseverance have helped the Company to be on par with international companies in terms of standards of performance and utility of projects. The journey towards excellence is inspired by what NCC has always done-deliver superior value for all those who depend on us, work with us and invest in us.. I wish to finally quote a famous writer, Ralph Waldo Emerson, “What lies behind us and lies before us are small matters compared to what lies within us”.

I assure all of you that NCC will re-dedicate itself towards its commitments and strive for continuous growth.

With best Wishes

Page 6: QAM-VSB-02

AVS Raju

Page 7: QAM-VSB-02

VISION

To be a world - class construction and infrastructure enterprise committed to quality, timely completion, customer satisfaction, continuous learning and enhancement of stakeholders value.

MISSION

To build a strong future ensuring increased returns to shareholders and enhanced support to associates.

To adopt latest technologies in the field of engineering. Construction, operation & maintenance of infrastructure projects.

To encourage innovation, professional integrity. Up gradation of knowledge and skills of employees and a safe working environment.

To be a responsible corporate citizen committed to the social cause.

VALUES

Openness and trust

Integrity & reliability

Teamwork & collaboration

Commitment

Creativity

AN OVERVIEW OF NCC

The year 1978 saw Sri AVS Raju take that single step along with like-minded people to establish NCC. It was the vision of this simple man who believes in human values, common sense and value of time.

It has been journey of excellence since then. Starting off with the corporate office in Hyderabad, regional offices were opened to facilitate the geographical spread of new projects. NCC was listed on the BSE & NSE stock exchanges in 1992.

The year 1995 saw NCC crossing a turnover of Rs. One billon. The Property Division was established in 1996 followed by the Transportation Division in 1998. The Water Electrical, Power, Irrigation, Metals, Oil & Gas Divisions are established subsequently. The GDRs, of the Company are listed on the Luxembourg stock exchange. The enormous trust placed by foreign institutional investors is reflected

Page 8: QAM-VSB-02

by the investment of US $ 100 million as on date by the Blackstone group of USA.

The Company has offices in Muscat (Oman) and Dubai (UAE) and has bagged projects in these countries.

Today, NCC is the only construction company from India hailed a ‘Best Under a Billion’ in Asia Pacific by Forbes Asia. It is ranked as the fastest growing construction company in the country by Construction World - NICMAR and also as the 2nd largest company in terms of turnover for the year 2006-07. It is also rated as one of India’s most admired companies by Construction World and is the 4th fastest growing company in India across all sectors in a study conducted by Dalal Street Magazine. NCC has a super ranking of 103 among India's top 1000 companies. It has also been ranked third on the basis of total income in construction and allied activities sector by Dun and Bradstreet in their acclaimed publication “India's Top 500 companies” in 2006.

The Company’s projects have been recognized as the ‘Outstanding Structure of the Year” by the Indian Concrete Institute two years in a row. NCC was awarded a bonus of Rupees 20 million for early completion of its projects. Its turnover for the financial year 2006-07 stood at Rs.29 billion.

Through the years and into the future. NCC continues to be on a steady drive towards perfection by maintaining old customs and adding new endeavors-across decades, across countries, across disciplines. It has marched on, towards newer horizons and newer challenges. The saga of excellence continues.............

HEALTH, SAFETY AND ENVIRONMENT

NCC is strongly committed to safety and accident prevention on project sites and work places to ensure that accidents do not take place, employees’ morale and satisfaction is improved, and in turn, the performance of Company is enhanced.

One of our priorities is to protect the environment and the health and safety of the people who work for us. The effective management of health and safety and protection of the environment are integral to our business success.

Everyone at NCC is accountable for health, safety and environment (HS&E) and we work hard to foster a culture where these three factors are taken into account wherever we operate.

NCC integrates HS&E into all areas of its operation, so that its sites are healthy and safe for all who work in them. NCC is committed to carrying out all its activities without detriment to the Environment.

Page 9: QAM-VSB-02
Page 10: QAM-VSB-02

WELCOME

NCC is a vision seen in exemplary clarity by Sri. AVS Raju, architect, planner and builder close to three decades ago. Years that have seen the Company creating history, time and again in the dynamic arena of infrastructure while contributing in incomparable measure in nation building. NCC has earned a remarkable reputation and trust in thirty years of dedicated service.

It has a turnover of Rs. 34.78 billion as on 31st March 2008 with an order book crossing Rs. 113 billion as on 31st March 2008 and growing at a compounded annual growth rate of 36% for the past five years. NCC’s human resource is now more than 3620 and growing day by day. –

Total income for the first quarter ended 30th June 2008 in FY2008-09, rose 27.43% to Rs. 9,717.92 million, compared to Rs. 7630 million in the previous year for the same period.

The net profit of the company for 01 FY09 stood at Rs. 370.81 million as compared to Rs. 360.30 million in the same quarter previous year.

NCC’s range of business verticals comprising of Buildings & Housing, Transportation, Water & Environment, Irrigation, Power, Electrical, Metals. Oil & Gas and International business reflect an expertise positioned to capture every infrastructure upturn. NCC has a reputed record of completing projects on time without compromising on quality and is the only construction company in India to achieve the recognition as one of the 250 “best under a billion” listed companies in Asia Pacific in 2005 by Forbes Asia.

Discover NCC-where excellence is always at work.

Page 11: QAM-VSB-02
Page 12: QAM-VSB-02

INDEX

S. No.

DescriptionFrom Page

toTo Page No

1 INTRODUCTION

2 QUALITY ASSURANCE PLAN – MATERIAL

3 INSPECTION AND TEST PLAN

4 TEST / JOB PROCEDURE

5 FORMATS

Page 13: QAM-VSB-02
Page 14: QAM-VSB-02
Page 15: QAM-VSB-02

QUALITY ASSURANCE PLAN Doc. NO. NCC / CWG-2010/QAP/MAT

Project : Commonwealth Games 2010, D. U. (North Campus), Delhi

PMC : M/s. Engineers India Ltd. Rev. – II

Contractor: M/s Nagarjuna Construction Company Ltd.

QUALITY ASSURANCE PLAN – MATERIAL

S. No.

Item Test to be carried out Code of Testing

NCCL Role / Frequency of test

EIL Role / Frequency of test

Code of Confirmatio

n1 Borrowed

Soil, Natural Soil

- MDD I S – 2720

Per Source - Review test reports

I S – 2720

Compacted Earth

- OMC - FDD

- per 250 M2 for road work /- Per 100M3 Back filling/ - 1000 M² for FOP

- Review test reports - Randomly Witness

2 Cement (Physical Test )- Initial Setting time - Final Setting Time - Compressive Strength- Fineness - Soundness

IS – 4031

- To be procured from approved Make.- Submission of MTC - Per source of Brand / - Per Week No./- Per 1000 bag receiving

- Review of MTC & Test reports IS – 8112-

1989

Page 16: QAM-VSB-02
Page 17: QAM-VSB-02

S. No.

Item Test to be carried out Code of Testing

NCCL Role / Frequency of test

EIL Role / Frequency of test

Code of Confirmatio

n2 Cement - (Chemical Test )

- Lime Saturation Factor

- Ratio of Alumina to Iron Oxide

- % Insoluble Residue - % magnesia - %Sulphuric

Anhydride - % Loss of Ignition - Chloride - Tri calcium

Aluminate

IS - 4031

- To be procured from approved Brand

- Submission of MTC

- Per Source of Brand

- Review of MTC & Test Reports

IS – 8112-1989

3 Aggregate 20 mm 10 mm

- Specific Gravity - Water Absorption - Deleterious Material

IS : 2386-1963

Once Per Source

- Review test reports - Randomly Witness

IS : 393-1970- Sieve Analysis 50 M3 Receiving / Weekly

- Crushing Value - Abrasion Value - Aggregate Impact

Value - Flakiness Index - Elongation Index

Weekly

Page 18: QAM-VSB-02

S. No.

Item Test to be carried out Code of Testing

NCCL Role / Frequency of test

EIL Role / Frequency of test

Code of Confirmatio

n4 Sand - Specific Gravity

- Organic Impurities - Water Absorption IS : 2386-

1963

- Once Per Source

- Review test reports - Randomly Witness

IS: 383-1970- Sieve Analysis - 50 M3 Receiving

- Silt Content CPWD Specification

- Per Lot CPWD Specification

5 Steel - (Physical Test)- Dimension & Unit

weight - Ultimate tensile

Strength - 0.2% Proof Stress - Elongation %- Bend & rebend test - (Chemical Test)- Carbon, - Sulpher - Phosphorus - Sulpher+Phosphorous

IS: 1608-1972IS : 1599-1974

- Submission of MTC - Once per Brand / - Once per Batch/- Once Per 50 Mt

Review MTC & test reports

IS : 1786-2008

6 Bricks - Dimensional Tolerance - Water Absorption - Crushing Strength - Efflorescence

IS: 3495-1976

- Per Source/- Per Brand /- Per 25,000 Bricks

- Review of Test reports

- Randomly WitnessIS : 1077-1976

7 Water (construction Purpose )

All Tests as per IS : 456 IS – 3025 - Per Source - Every 3 Month

- Review test reports IS : 456

Page 19: QAM-VSB-02

S. No.

Item Test to be carried out Code of Testing

NCCL Role / Frequency of test

EIL Role / Frequency of test

Code of Confirmati

on8 Anti

Termite All tests as per IS : 8944 IS – 6313 - Submission of

MTC - Per Brand

Review MTC & test reports

IS – 8944

9 EPDM Water Proofing

- Thickness, - Unit Weight - Tensile Strength - Ultimate Elongation

%- Water Absorption - Tearing resistance - Liner Dimension

Change - Hardness - Puncher resistance

ASTM D412D471D624’D 1204D 2240E 154

- To be procured from approved Make.

- Submission of MTC

- Per Brand/

- Per 1000 M²

Review MTC & Test reports

ASTM D412D471D624’D 1204D 2240E 154

10 Admixture - Workability - Setting Time - Bleeding - Air Permeability - Compressive

Strength- Flexural strength - Chemical

composition

IS- 9103 To be procured from approved Make.

Submission of MTC

Randomly

Review test reports & MTC

IS- 9103

11 RCC Pipe - Permeability - Dimensional Test - Hydrostatic

Pressure - Water Absorption

IS - 458

- Submission of MTC

-Factory Testing (Randomly)

Review of MTC & test reports Randomly Witness

IS – 458

Page 20: QAM-VSB-02

S. No.

Item Test to be carried out Code of Testing

NCCL Role / Frequency of test

EIL Role / Frequency of test

Code of Confirmatio

n12 Bitumen

Impregnated fiber board

- Compression - Extrusion - Water Absorption - Density - Bitumen Content

IS : 10566-1983

- Per Batch

- Per 100 Sqm

Review test reports

Randomly Witness

IS : 1838

13 Glazed Tiles/ Vitrified tiles

- Compression - Extrusion - Water Absorption - Density - Bitumen Content

IS : 777/ IS : 13753

To be procured from approved Make.

Per Batch

Per 3 000 Nos

Review test reports Relevant IS Code

14 Marble/ Granite /Kota Stone

- Moisture Absorption - Hardness - Specific Gratuity

IS : 1122-1974IS : 1124-1974

Per Type Per 500 sqm./Per lot receiving.

Review test reports

Randomly witnessed

IS : 1130-1969 IS : 3316

15 Pre-polished decorative designer cement concrete tiles

- Water Absorption - Wet Transverse

Strength - Resistance to wear

IS :1237-1980

Per BrandPer 10000 Nos

Review test reports IS : 1137-1980

Page 21: QAM-VSB-02

S. No.

Item Test to be carried out Code of Testing

NCCL Role / Frequency of

test

EIL Role / Frequency of test

Code of Confirmation

16 Footpath Tiles/ Paver Blocks

- Water absorption - Crushing strength - Harness

Relevant IS Code

Per Branch Per 10,000 Nos

Review of test report

IS : 15638

17 Wood + Door Frame

- Moisture - Permissible

Defects - Borer Hole - Centre Heart - Cup - Cup shake - End Split - Knots - Surface Crack - Wane

As per CPWD specification IS : 3364

Per Source Per 5 Cum

Review of Test reports

IS : 190-1974

18 Flush Door - End Immersion test

- Knif Test- Glue adhesion test

IS 4020 Per BrandPer 200 Sqm

Review Test reports IS 2202:1999

19 Aluminum - Thickness of anodic / powder coating

- 0.2% proof stress, - Tensile strength - Elongation

Relevant IS Code

To be procured from approved Make.Per Brand Per 5 MT

Review of Test Reports

IS:733-1975IS : 1285-1975

20 Gypsum Board for false ceiling

- Dimension - Transverse

strength

IS : 2542-1981

To be procured from approved Make.

Once for 1000 Sqm

Review of test reports

IS : 2095-1982

Page 22: QAM-VSB-02

S. No.

Item Test to be carried out Code of Testing

NCCL Role / Frequency of test

EIL Role / Frequency of test

Code of Confirmati

on21 Coarse

Aggregate for (WBM, Premix Carpet Asphalt Concrete)

- Gradation - Los Angles

Abrasion Value - Specific Gravity - Water absorption

IS : 2386BIS : 812

IS : 6241

Per Source Per 200 M3

Review of Test reports Randomly

IRC/ Morth

22 Binder (Bitumen )

Specific Gravity Flash Point Softening Point Penetration Ductility Loss on heating

IS: 1202-1978IS: 1209-1978IS: 1205-1978IS: 1205-1978IS: 1208-1978IS: 1212-1978

Submission of MTC Per source

Review MTC & test reports

IS : 73-1961

23 Open graded carpet / BM/ BC

- Job Mix - Sieve Analysis - Temperature - Marshal stability - Flow Value test - Percent Air voids - Density of

compacted layer

MORTH Submission of job mix design /Randomly/Core test per 250 Sqm

Review of Test reports Randomly

IS : 73/ MORTH

24Kerb stone - Transverse

StrengthAppendix-AAppendix-B

To be procured from approved Make.

Review MTC & test reports

IS: 5758-1984

Page 23: QAM-VSB-02

- Water AbsorptionSubmission of MTC

Per 1500 Nos

25 ACP - Aluminum Thickness

- Compressive Strength

- Tensile Strength- Water resistance- Fire Resistance

To be procured from approved Make.

Submission of MTC

Per 2000 Sqm

Review MTC & test reports

ASTM D-638

26 Glass - Distribution of Allowable Defects (Gaseous Inclusions, Open Gaseous Inclusions, Knots, Dirts and Stones, Scratches, Rubs and Crush, Reams, Strings and Lines, Waviness, Sulphur Stains, Corner Breakage and Chip)

- Cluster of defects- Thickness- Warp- Fragmentation Test- Resistance to

Shock Test

IS: 2835-1987

IS: 2835-1987IS: 2553-1990IS: 2553-1990IS: 2553-1990IS: 2553-1990

To be procured from approved Make.

Submission of MTC Per 1000 Sqm

Review MTC & test reports

Relevant IS Code

27 Pre-coated - Chemical Tests IS: To be procured from Review MTC & test IS:14246-

Page 24: QAM-VSB-02

metal False ceiling & Panel

- Mass of Zinc Coating

- Bend Test- Pencil Hardness

Test- Impact Resistance

Test- Cross Hatch Test

513:2008IS277

approved Make.

Submission of MTC

Per 500 Sqm

reports 1995

28 Stainless steel

- Tensile Strength- Yield Stress- Elongation- Mass per meter

IS: 1608-2005

To be procured from approved Make.

Submission of MTC

Per 50 MT

Review MTC & test reports

IS: 1608-2005

30 Laminated Sunmica

- Resistance to immersion boiling water

- Resistance to dry heat

- Dimensional Stability

- Resistance to impact

- Resistance to Scratching

- Resistance to stem

IS 2046 To be procured from approved Make

Submission of MTC

Per 1000 Sqm

Review MTC & test reports

IS 2046:1995

31 GI pipe - Dimensions- Mass per meter- Visual Test- Uniformity of Zinc

Coating- Adhesion Test- Tensile Strength

IS: 1239(Pt-I)-2004IS:2629-1985IS:2633-1986

To be procured from approved Make

Submission of MTC

Per 500 Rmt

Review MTC & test reports

IS: 1239-2004IS: 4736-1986

Page 25: QAM-VSB-02

- Elongation on guage length

- Bend Test- Mass of Zinc

Coating- Chemical Analysis

IS:2629-1985IS:1608-2005IS:1608-2005

IS:2329-1985IS:6745-1972IS: 228

32 CI Pipe - Hammer Test- Brinell Hardness

Test- Hydrographic Test- Dimension Test- Coating Test

IS 1500 To be procured from approved Make

Submission of MTC

Per 500 Rmt

Review MTC & test reports

IS: 3989-1984

33 SW pipe - Hydrographic Test- Water Absorption- Resistance to acids- Resistance to

alkalies- Crushing Strength- Dimensions-

IS: 651-1992

Submission of MTC

Per 1000 Rmt

Review MTC & test reports

IS: 651-1992

34 PVC pipe - Dimensions- Visual Appearance- Opacity- Effect on Water- Reversion Test- Density- Sulphated Ash- Hydrostatic

IS: 4985-2000

To be procured from approved Make

Submission of MTC

Per 1000 Rmt

Review MTC & test reports

IS: 12235IS: 133660

Page 26: QAM-VSB-02

Pressure 35 CPVC pipe - Dimensions

- Visual Appearance- Flattening Test- Hydrostatic

Pressure Test- Reversion Test

ASTM D2846ASTM D2846ASTM D2846ASTM D2846

IS: 12235

To be procured from approved Make

Submission of MTC

Per 1000 Rmt

Review MTC & test reports

ASTM D 2846IS: 4985-2000

36 HDPE pipe - Dimension Test- Construction- Compression Test- Impact Test- Bend Test

Submission of MTC

Per 2000 Rmt

Review MTC & test reports

IS: 14930

37 PVC perforated & corrugated pipe

- Dimensions- Water Inlet Area- No. of rows- Perforation size

width- Perforation size

length- Visual appearance - Impact Strength- Elongation on

guage length- Bend Test- Joint Test

IS: 9271-2004IS: 9271-2004IS: 9271-2004IS: 9271-2004IS: 9271-2004

IS: 9271-2004

IS: 13360IS: 9271-2004IS: 9271-2004IS: 9271-

Submission of MTC Per 1000 Rmt

Review MTC & test reports

Relevant IS Code

Page 27: QAM-VSB-02

2004IS: 9271-2004IS: 9271-2004IS: 9271-2004

Page 28: QAM-VSB-02
Page 29: QAM-VSB-02

INDEX

SL. NO.

Name Of Documents Document No.

1 Inspection and test plans for Surveying. NCC/CWG-2010/ITP-CIVIL/01 2 Inspection and test plans for Earthwork. NCC/CWG-201 0/ITP-CIVIL/O2 3 Inspection and test plans for ATT. NCC/CWG-2010/ITP-CIVILIO3

4Inspection and test plans for Filling of earth/ Borrowed earth.

NCC/CWG-2010/ITP-CIVIL/04

5 Inspection and test plans for PCC NCC/CWG-2010/ITP-CIVIL/05

6Inspection and test plans for EPDM (Waterproofing)

NCC/CWG-2010/ITP-CIVIL/O6

7Inspection and test plans for RCC (Sub- Structure)

NCC/CWG-2010/ITP-CIVIL/07

8Inspection and test plans for RCC (Super- Structure)

NCC/CWG-201 0/ITP-CIVIL/08

9 Inspection and test plans for Brick Work NC/CWG-201 0/ITP-CIVIL/O9

10Inspection and test plans for Plastering Work

NCC/CWG-2010/ITP-CIVIL/1O

11 Inspection and test plans for Flooring Work NCC/CWG-2010/ITP-CIVIL/11 12. Inspection and test plans for Doors/Windows NCC/CWG-2010/ITP-CIVIL/12

13 Inspection and test plans for Painting Work NCC/CWG-2010/ITP-CIVIL/13

14Inspection and test plans for Roof Sheeting Work

NCC/CWG-2010/ITP-CIVIL/14

15 Inspection and test plans for False Flooring NCC/CWG-2010/ITP-CIVIL/15 16 Inspection and test plans for Sand Filling NCC/CWG-2010/ITP-CIVIL/16

17Inspection and test plans for Earth Work in Road

NCC/CWG-2010/ITP-CIVIL/17

18Inspection and test plans for WBM in Road work

NCCICWG-201 0/ITP-ROAD/18

19Inspection and test plans for BM in Road work

NCC/CWG-201 0/ITP-ROAD/19

19Inspection and test plans for Asphalt Concrete in Road work

NCC/CWG-201 0/ITP-ROAD/20

20Inspection and test plans for Concrete Pavement Road work

NCC/CWG-201 0/ITP-ROAD/21

21Inspection and test plans for False ceiling work

NCC/CWG-201 0/ITP-CIVIL/22

22Inspection and test plans for Aluminum Composite Panel work

NCC/CWG-201 0/ITP- CIVIL /23

23 Inspection and test plans for C I Pipe work NCC/CWG-201 0/ITP-PBL/01 24 Inspection and test plans for G I Pipe work NCC/CWG-201 0/ITP-PBL/02

25Inspection and test plans for CPVC Pipe work

NCC/CWG-201 0/ITP-PBL/03

26Inspection and test plans for Stone Ware Pipe work

NCC/CWG-201 0/ITP-PBL/04

Page 30: QAM-VSB-02

INSPECTION AND TEST PLAN

Doc No. NCC/CWG2010 /ITP-CIVIL/01

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. - 01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR SURVEYING

S. No. Activity/ Description NCCL EIL Documents to be submitted

1 Calibration certificates of Survey Equipment

WC RW Calibration Certificate

2 Establishment of control pillars & Bench Marks.

WC S

3 Co-ordinates of Control Points.

WC W

4 Checking Layout & Level. WC S Level Book

5 Preparation of Drawing of Spot levels & contours

WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION BY OWNER/EIL

Page 31: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/02

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No.-01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR EARTH WORK

S. No. Activity/ Description NCCL EIL Documents to be submitted

1 Marking for Excavation WC S Level Book

2 Taking Initials Levels WC W

3 Barricading of area and other safety measures

WC S

4 Check existing service/ obstacle encountered (cables pipe Conduits Etc.)

WC W

5 Slope of Excavation, benching & Overburden

WC S

6 Check for Subsoil water & dewatering if required

WC S

7 Bottom level of excavation & Compaction

WC W

8 Neatly dressing & leveling of disposed soil

WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION BY OWNER/EIL

Page 32: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/03

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR ATT

S. No. Activity/ Description NCCL EIL Documents to be submitted

1 Checking testing of material & spraying device including personal protective equipment like facemask, gloves, shoes etc.

WC RW MTC/ Lab test Reports

2 Preparation of surface for taking dosage of emulsion by ramming of each layer of soil by Roding the earth at specified interval.

WC S

3 Backfilling and compaction in specified layer along with application of emulsifier along the side of RCC utilized.

WC S

4 Check the consumption of emulsifier utilized.

WC W

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION BY OWNER/EIL

Page 33: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/04

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. - 01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR FILLING OF EARTH/ BORROWED EARTH

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1 Selection of material/ selected earth for filling WC S MDD Test Report

2 Check for treatment of soil, if any WC W

3 Check initial levels before start filling WC S

4 Filling the soil in specified layers, watering & consolidation

WC RW

5 Review of Calibration Certificate of testing instrument

WC RW Calibration Certificate

6 Compaction test for each layer & specified area

WC S FDD Test Reports

7 Filling to required level, check the top level

WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

INSPECTION AND TEST PLAN Doc. No.

Page 34: QAM-VSB-02

NCC/CWG2010 /ITP-CIVIL/05

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR PLAIN CEMENT CONCRETE

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1 Checking lay out and compaction of sub grade

WC S MTC/ Lab Report

2 Checking of material including water

WC S

3 Calibration of weigh batcher/ batching plant

WC W Calibration Report

4 Mix Proportion & use of water proofing material if any

WC S

5 Check for shuttering , dewatering if any

WCW Pour Card

6 Concreting works as per specification.

WCS

7 Finishing & checking of top level and thickness of PCC

WCS Pour Card

8 Curing WC

S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 35: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/06PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR EPDM (WATER PROOFING)

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1 Approval of Material WC RW MTC/ Lab Report

2 Checking condition/finishing of P.C.C. WC W

3 Laying of Geotextile Material, (150 gm/m2) Checking joints of WC S Geotextile Materials

WC S

4 Laying EPDM material checking joints of EPDM( Mm. overlap of 150mm)

WCS

5 Laying Geotextile materials (300 gm/m2) checking joints of Geotextile material

WC S

6 Check for extra length provided for vertical water proofing in all sides.

WC S

7 Check level pads for PCC above water proofing.

WC S

8 Casting for PCC above water proofingWC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

Page 36: QAM-VSB-02

CIVIL/07

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR RCC (Sub-Structure)

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1 Approval of source of materials WC W MTC/ Test Reports

2 Calibration certificate of instruments testing equipments

WC RW

3 Checking of layout & condition of PCC/ Leveling course

WC W

4 Checking/ testing of materials WC RW

5 Design of mix proportion WC RW/HP Mix design

6 Check for Sub-soil water & dewatering arrangement, if any

WC S

7 Check for line & level of shuttering including its condition, quality and rigidity

WC S

8 Verification of dimension WC S

9 Reinforcement & covers to reinforcement

WC S

10 Inserts Anchor bolts & Pipe sleeves, pockets, dowels etc.

WC S

11 Check for obstacle encountered (Electrical conduits, pipeline etc.)

WC S

12 Filling Pour Card WC HP Pour Card

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 37: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/07

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

S. No.

Activity/ Description NCCL EIL Documents to be submitted

14 Check for pouring arrangement WC S

15 Concreting, testing, compaction & finishing

WC S

16 Checking of Slump WC W

17 Casting of Cubes WC W

18 Curing Arrangement WC S

19 Testing of cubes WC W Cube testing Report

20 Removal of shuttering WC S

21 Check for water tightness, rendering if any

WC S

EGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 38: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/08

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR RCC (SUPER STRUCTURE)

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1. Approval of source of materials WC Rw MTC & Test Reports

2. Concept & design of Shuttering WC Rw Shuttering Design

3. Checking of layout WC S

4. Checking/ testing of materials WC W MTC & Test Reports

5. Mix design/Ready mix concrete WC Rw / HP Lab report of Mix Design

6. Check for line & level of shuttering and scaffolding/ vertical bracing including hoisting arrangements.

WC S

7. Check for Rubber liner shuttering if any

WC S

8. Verification of dimension WC S

9. Reinforcement & cover to reinforcement

WC W

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 39: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/08PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

S. No.

Activity/ Description NCCL EIL Documents to be submitted

10. Inserts, bolts, pipe sleeves, MS rungs, concealed electrical conduits, fan hooks, dowels, etc. including welding if any

WC S

11. Pockets/ openings WC W

12. Expansion joints, if any WC S

13. Check for water stops, slopes, stoppers, if any WC S

14. Filling of Pour Card WC HP Pour Card

15. Check for pouring arrangement in case of RMC

WC S

16. Concreting, testing, compaction & finishing WC S

17. Checking of Slump WC W

18. Casting of cubes WC W

19. Curing WC S

20. Testing of cubes WC W Cube test Report

21. Removal of formwork/ staging WC S

22. Hacking the exposed surface if necessary WC S

23. Check for water tightness, rendering, if any WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 40: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/09PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INPECTION TEST PLAN FOR BRICK WORK

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1. Approval of material WC WTest Report

2.Cleaning of surface

WC S

3. Wetting of bricks WC S

4.Cement mortar proportion/ Water cement Ratio

WC S

6.Check for thickness of Brick Work/ Locations of Doors & Window

WC S

7. Staging & scaffolding WC S

8.Hacking of concrete surface/Cement Punning to the concrete surface.

WC S

9.Check for bond/closers, thickness of joints, and height of masonry work in a day.

WC S

10. Line, level & plumb. WC S

11.Raking out joints, keys in brick work, if any.

WC S

12.Check for RCC bonds/Reinforcement/PCC flooring, in case of partition brick work

WC S

13.Embedment of fixtures

WC S

14Curing

WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 41: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/10PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR PLASTERING WORK

Location - Date –

Grid No. - Level -

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1 Checking curing of required portion.

It should start before 12 hours.

WC S

2 Checking/testing of material WC W Test Reports

3 Check for completeness of all hidden jobs like piping, conducting.

WC S

4 Sample preparation for finish and its approval.

WC W

5 Fixing of Chicken Mesh as applicable WC W

6 Hacking and cleaning the surface, removing loose particles, wetting the surface.

WC S

7 Checking thickness of plastering work, plumb and even surface.

WC W

8 Check for grooves, openings, plumb and even surface.

WC S

9 Curing WC S

Remarks if any –

NCCL EIL

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR

Page 42: QAM-VSB-02

W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/11

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR FLOORING WORK

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1 Cleaning the surface for flooring WC S

2 Approval of material by shade, colour & design pattern etc.

WC RW/HP Lab Reports

3 Checking the material test results of flooring checking concrete/checking cement mortar

WC RW

4 Checking of underneath floor level & Finished floor level as per drawing.

WC S

5 Check design pattern of decorative/marble flooring before actual laying

WC S

6 Checking mortar preparation & thickness WC S

7 Checking the Joint & filling of required colour pigments in joint

WC S

8 Checking the thickness of the flooring Checking the Level

WC S

9 Curing WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 43: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/12PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR DOORS / WINDOWS

S. No.

Activity/ Description NCCL EIL Documents to be submitted

1 Checking the material and its test report WC RW LAB REPORT

2 Check for sections & dimensions WC W

3 Section joinery details WC S

4 Checking dimensions of the window/Doors WC W

5 Grouting with lugo/dash fasteners WC S

6 Checking of Hold Fasteners. WC S

7 Checking of anchorage and fixing of hold fasteners & rubber gas kit

WC S

8 Check for thickness & type of glazing WC W

9 Checking of Pataam. WC W

10 Checking of Facia WC S

11 Checking of plumb/levels WC S

12 Shade of pints, no. of coats including surface preparation.

WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 44: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/13PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR PAINTING

SI

no.

Activity/Description NCCL EIL Documents to be

submitted

1 Surface preparation WC S

2 Checking colour scheme WC RW/HP

3. Approval of material WC RW Lab Reports

4. Checking type/Quality of putty/primer/paint/putty.

WC S

5. Checking and matching of colour coats/pattern/texture.

WC S

6. Checking number of coats/thickness. WC S

8. Curing if required. WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 45: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/14PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR ROOF SHEETING

SI

no.

Activity/Description NCCL EIL Documents to

be submitted

1 Checking/testing of material including manufacturers test certificate. WC RW MTC/ lab report

2Checking of line, level, bolting of truss and perlines. WC W

3. Checking completion of final structural works.

WC S

4. Sequence of sheeting. WC S Shop Drawing

5. Check for mitering, overhang, laps etc. WC S

6. Slopes line, level of sheets, barge boards, ridges and gutters, overhang of sheets

WC S

7. Bolting by drilling only, length of bolts, nos., and type of washers.

WC S

8. Check for slopes of rain gutters, down take pipes, north lighting curves/supports for gutters.

WC S

9 Check for leakage / passing of light WC W

10 Final inspection WC W

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING

Page 46: QAM-VSB-02

RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/15

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR FALSE FLOORING

SI

no.

Activity/Description NCCL EIL Documents to be

submitted

1 Checking/testing of material WC W/RW MTC/ test report

2 Clean base floor WC S

3. Check the existing floor to meet required WC floor level.

WC S

4. Painting the base floor with polyurethane based paint (as specified)

WC S

5. Proper line, level and layout. WC S

LEGEND

Page 47: QAM-VSB-02

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/16

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR SAND FILLING

SI

no.

Activity/Description NCCL EIL Documents to be

submitted

1 Checking quality of material testing. WC RW Lab Reports

2 Laying of material WC S

3. Watering. WC S

4 Checking of compaction WC W Field Test Report

5 Leveling the top surface WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 48: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/17

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR EARTH WORK IN ROAD

SI no.

Activity/Description NCCL EIL Documents to

be submitted

1

Setting out and survey

A. Verifying centre line & level B. Fixing of Row Pillars C. Taking OGL

WC W Survey Book

2Testing of Borrow earth or excavated material

WC RW MDD Test Report

3Rerouting of existing underground pipe line & laying of proposed underground lines.

WC S

4Preparation of embankment and Sub grade layer with suitable Borrow earth material/excavated material

WC S

5If Necessary, Removal of unsuitable material

WC S

6Level Checking of top layer of Embankment/sub grade

WC S Level Book

7Checking of FDD of Embankment/ Sub grade

WC S FDD Test Report

LEGEND

Page 49: QAM-VSB-02

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 50: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/18

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR WBM IN ROAD WORKS

S. No.

Activity / Description NCCLEIL Documents to be

submitted

1 Checking of material WC RW Lab Test Report

3Laying of Material at site over compacted sub grade.

WCS

4Spreading of filler material & properly filled with brushing.

S

5Checking Level of Compacted 1st Layer

WCW

6 Laying of Second Layer of WBM WC S

7 Compaction of layer WC S

8 Spreading of filler material S

9 Checking final level WC W

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 51: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/19PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR BM IN ROAD WORKS

S. No.

Activity/Description NCCLEIL Documents to be

Submitted 1 Checking of material WC RW TEST REPORTS

2. Checking of MTC of asphalt WC S MTC /LAB TEST

REPORTS

3. Checking of outside laboratory test results of asphalt

WC RW

4 Preparation of Job Mix WC HP/RW Job MIX

5 Scarifying/cleaning road surface of water bound macadam

WC RW

6 Laying of tack coat WC S7 Checking quantity of tack coat WC S

8Checking temperature of bituminous mix and gradation of aggregate

WC W

9 Lying of BM on tack coated surface. WC S

10Checking of level, gradient & undulations of BM surface after completing work/next day

WC RM

11Core cutting for Density checking of mix

WC WLAB TEST REPORT

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 52: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/20

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR BITUMINOUS CONCRETE IN ROAD WORKS

S. No.

Activity/Description NCCLEIL Documents to be

Submitted 1 Approval of Material WC W LAB TEST REPORTS3. Approval of job mix WC HP/RW JOB MIX4 Preparation of mix design WC S MTC/TEST REPORT5 Laying of tack coat WC S6 Checking quantity of tack coat WC S

Checking temperature of bituminous mix and gradation of aggregate

WC W

7Laying of Bituminous Concrete on tack coated surface.

WC S

8 Checking of level of Bituminous Concrete surface after completing work/next day

WC S

9 Core cutting for Density checking of mix in the lab

WC S

10 Checking of aggregate gradation, strength, shape at the time of production of mix.

WC S

11Checking of quantity of asphalt in mix.

WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 53: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/21

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR CONCRETE PAVMENT

S.No.

Activity/DescriptionNCC

L

EIL Documents to be

submitted

1. Approval of materialWC RW MTC/LAB

REPORT2 Preparation of mix design WC S MIX DESIGN

3Rerouting of underground pipe lines

WC S

4. Scarifying/cleaning road surface of water bound macadam

WC S

5. Fixing of MS channels WC S6 Fixing of top levels of road surface WC W7 Filling Pour card WC S Pour Card8 Check pouring Arrangement WC S

9Concreting, testing, compaction & finishing

WC S

10Checking of Slump & casting of cubes

WC S

11 Necessary Curing WC S

12Cube testing on 7 days and 28 days.

WC W

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 54: QAM-VSB-02
Page 55: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/22

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -0

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR FALSE CEILING WORK

SI

no.

Activity/Description NCCL EIL Documents to be

submitted

1 Checking/testing of material WC W/RW MTC/ Lab test report

2 Checking of rendering of slab WC S

3. Clearance of services above false ceiling WC S

4. Checking of BoFC level as per drawingWC

S

5. Checking hanging arrangement & grid arrangement

WCS

6 Fixing of false ceiling tiles WC S

7Marking, cutting & fixing of electrical & AC points as per drawing.

WC W

8 Checking of final leveling & alignment. WC W

9Removal plastic coating in case of metal tiles

WC S

10Filling of joints & painting in case of gypsum board

WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 56: QAM-VSB-02

INSPECTION AND TEST PLAN Doc. No. NCC/CWG2010 /ITP-CIVIL/23

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -0

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR

ALUMINIUM COMPOSIT PANEL

SI

no.

Activity/Description NCCL EIL Documents to be

submitted

1 Checking/testing of material. WC W/RW MTC/ Lab test report

2 Checking of frame work for ACP WC S

3. Checking of Mullions & Transoms as per shop drawing.

WC S Shop drawing

4. Checking of cleat angles & fasteners at junctions

WCS

5. Fixing of ACP as per design pattern shown in drawing.

WCS

6Filling of joints with baker rods & sealant.

WC S

7 Removal plastic coating from ACP WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 57: QAM-VSB-02

INSPECTION AND TEST PLAN Doc.No. NCC / CWG 2010 /ITP-PBL/01

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR C I PIPE WORK

SI.NO Activity/Description NCCL EIL Documents to be submitted

1 Checking of materials /Manufacturers Test Report WC RW MTC & Lab test report

2 Marking of layout & levels as per drawing WC W Sketch for layout & level

3 Laying of CI pipe WC S

4 Checking the Filling of Lead in joints. WC W Joint record

5 Checking of slope & supports of pipes WC S

6 Testing of leakage of lead joints WC W

7 Painting of pipes WC S

8 Checking the honchoing over pipes if required. WC S

9 Check for leakage. WC W

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 58: QAM-VSB-02

INSPECTION AND TEST PLAN Doc.No. NCC / CWG 2010 /ITP-PBL/02

Project : COMMNONWEALTH GAMES,2010 D.U (NORTH CAMPUS)PMC : M/S ENGINEERS INDIA LTD Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR G I PIPE WORK

SI.NO Activity/Description NCCL EIL Documents to be submitted

1 Checking of materials /Manufacturers Test Report WC RW MTC & Lab test report

2 Marking of layout & levels as per drawing WC S

3 Painting & raping coating of GI pipe WC S

4 Excavation, Laying & fixing of GI pipe WC S

5 Checking of slope & supports of pipes WC W

6 Pressure testing of leakage from joints WC W

7 Painting & raping coating for joints of GI pipe WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 59: QAM-VSB-02

INSPECTION AND TEST PLAN Doc.No. NCC / CWG 2010 /ITP-PBL/03Project : COMMNONWEALTH GAMES,2010 D.U (NORTH

CAMPUS)

PMC : M/S ENGINEERS INDIA LTD Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR CPVC PIPE WORK

SI.NO Activity/Description NCCL EIL Documents to be submitted

1 Checking of materials /Manufacturers Test Report WC RW MTC & Lab test report

2 Marking of layout & levels as per drawing WC S

3 Check fixing arrangement of CPVC pipe WC S

4 Checking of slope & supports of pipes WC W

5 Pressure testing of leakage from joints WC W

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 60: QAM-VSB-02

INSPECTION AND TEST PLAN Doc.No. NCC / CWG 2010 /ITP-PBL/04

Project : COMMNONWEALTH GAMES,2010 D.U (NORTH CAMPUS)PMC : M/S ENGINEERS INDIA LTD Rev. No. -01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

INSPECTION AND TEST PLAN FOR STONE WEAR PIPE WORK

SI.NO Activity/Description NCCL EIL Documents to be submitted

1 Checking of materials /Manufacturers Test Report WC RW MTC & Lab test report

2 Marking of layout & levels of pipe & chambers as per drawing

WC S

4 Excavation, Compaction & Level checking for PCC work as per drawing.

WC S

5 Checking of slope & joints of the joints WC W

6 Testing of leakage from joints WC W

7 Checking the honchoing over pipes. WC S

LEGEND

HP - HOLD POINT WC - 100% EXAMINATION BY CONTRACTOR W - WITNESS POINT RM - RANDOM CHECKING RW - REVIEW OF CONTRACTOR’S DOCMENTATION RFI - REQUEST FOR INSPECTION S - SURVEILLANCE INSPECTION

Page 61: QAM-VSB-02
Page 62: QAM-VSB-02

INDEX

SR. NO

.PROCEDURE NAME PROCEDURE NUMBER

1 DETERMINATION OF DRY DENSITY OF SOIL BY CORE CUTTER METHOD

NCCL/CWG-2010/JP - 01

2 PROCEDURE FOR COMPRESIVE STRENGTH TESTING OF CONCRETE

NCCLJCWG-2010/JP - 02

3 PROCEDURE FOR DETERMINATION OF AGG. CRUSHTNG VALUE

NCCL/CWG-2010/JP — 03

4 PROCEDURE FOR DETERMINATION OF AGG. ELONGATION INDEX

NCCL/CWG—2010/JP 04

5 PROCEDURE FOR DETERMINATION OF AGG. FLACKINESS INDEX

NCCL!CWC-2010/JP 05

6 PROCEDURE FOR DETERMINATION OF AGG. SPECIFIC GRAVITY & WATER

NCCL/CWG-2010/JP — 06

7 PROCEDURE FOR FIELD TEST TO DETERMINE SILT CONTENT IN SAND

NCCL/CWC-2010/JP — 07

8 PROCEDURE TO FELL CUBES OF FRESH CONCRETE

NCCL/CWG-2OIOJJP — 08

9 PROCEDURE FOR SAMPLING .JNSPECTION TEST1NG OF RMC

NCCL/CWG-2010/JP — 09

10 PROCEDURE FOR SEWE ANALYSIS OF COARSE AGGREGATE

NCCL/CWG-20]0/JP — 10

11 PROCEDURE FOR SEIVE ANALYSIS OF FINE AGGREGATE

NCCL/CWG-2010/JP - 11

12 PROCEDURE FOR SLUMP TEST NCCL/CWG-2010/JP - 12

13 PROCEDURE FOR COMMON BURNT CLAY BRICKS

NCCL/CWG-2010/JP - 13

14 PROCEDURE FOR SAMPLING OF AGGREGATE NCCLJCWG-2OIOJJP - 14 15 PROCEDURE FOR SAMPLING OF BRICKS NCCL/CWG-2010/JP - 15 16 PROCEDURE FOR SAMPLING OF EARTH SOW NCCL/CWG-2OIOIJP - 16

17 PROCEDURE FOR SAMPLING OF FRESH CONCRETE

NCCL/CWG-2010/JP - 17

18 PROCEDURE FOR DETERMINATION OF WATER CONTENT OF SOIL SAMPLE

NCCL/CWG-2010/JP - 18

19 JOB PROSEDURE FOR SURVEY WORK NCCLJCWG-2OIOJJP - 19 20 JOB PROSEDURE FOR EXCAVATION NCCL/CWG-2010/JP -20 21 JOB PROSEDURE FOR BACK FILLING NCCL/CWG-2010/JP - 21 22 JOB PROSEDURE FOR P.C.C. NCCL/CWG-2010/JP - 22 23 JOB PROSEDURE FOR R.C.C. NCCL/CWG-2010/JP - 23 24 JOB PROSEDURE FOR BRICK WORK NCCL/CWG-2010/JP -24 25 JOB PROSEDURE FOR PLASTERING NCCL/CWG-2010/JP -2526 JOB PROSEDURE FOR LAYONG OF R.C.C. PIPE NCCL/CWG-2010/JP -2627 JOB PROSEDURE FOR ATT NCCL/CWG-2010/JP -27

Page 63: QAM-VSB-02

Dry Density of Soil In-Place of Core Cutter Method

Doc. No. NCC /CWG-2010/JP-01

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

DETERMINATION OF DRY DENSITY OF SOIL IN-PLACEBY CORE-CUTTER METHOD

(I.S: 2720-XXIX)

Aim: To determine the Field density of Fine grained soil by using Core-cutter. (Itis less accurate than sand Replacement Method and recommended for wellCompacted soils.

Apparatus:

Core cutter / Dolly / Rammer.

Balance of 1 g accuracy.

Pallet knife, Straight edge, Steel rule, Pick axe etc.

Soil sample is termed as fine-grained if 90% by weight is passes through IS sieve4.75 mm.

Procedure:

Internal Volume ( Vc, cm3 ) of core cutter shall be calculated by takingDimensions to nearest to 0.25 mm (By vernier).

Cutter shall be weighed to nearest g. ( Wc, g )

A small area, approximately 30 cms square of the soil layer to be tested shallbe exposed and leveled.

Cutter shall be placed vertically on soil with dolly on top.

Cutter shall be rammed down vertically into the soil layer until only about 15mm of dolly protrudes above surface.

Care to be taken that cutter shall not rock sideways while hammering.

The cutter shall be dug out of surrounding soil by pick axe. Please take care soas to have some protruding soil mass from the lower edge.

Page 64: QAM-VSB-02

Soil from both the ends shall be trimmed flat to the ends of cutter.

The cutter containing soil mass shall be weighed to nearest g ( Ws, g )The soil mass shall be removed from cutter and representative sample shall betested for water contents.

At least 3 tests are required to make average result.

Remarks – Often problem encountered when soil mass is dry and cutter is notproperly filled up or looses soil while handling. In such case test is to be doneby sprinkling water and testing after suitable lapse of time. Core cutter shall beremoved, trimmed and kept in polythelene bag to take it to laboratory. It shallbe weighed with cutter and any loose soil mass collected in bag.

Calculations :

Bulk Density Yb of Wet Soil is as below:

Yb = ( Ws – Wc ) / Vc , gms /cm3

Dry Density Yd is as below:

Yd = 100 Yb / ( 100 + w ) , gms /cm3 Where w = Water content %

Format to be used:

NCC/CWG-2010/F-13

Compressive Strength Testing Doc. No. NCC /CWG-2010/JP-02

Page 65: QAM-VSB-02

for ConcreteProject : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR COMPRESSIVE STRENGTH TESTING FOR CONCRETE

Aim : To establish Compressive strength of concrete sample for acceptance

Apparatus :Compressive Testing machine having adequate capacity.Weighing Balance.Measuring Scale.

Procedure :Remove the cubes required for testing from curing tank wipe clean of water andair dry them to surface dryness.

Stack cubes in sequence as per mix, dates, locations etc.

Record the actual surface area ( Sq cm)of the cube which will be in contact withplaten of CTM ( A in cm2 or mm2 ).

Weigh the cubes and record the weights in the register in kg.

Place the cube on platen centrally keeping trowelled side in front.

Position the top platen on cube surface. See that there is no gap left betweencube top and platen.

Load the CTM at desired speed without any shocks.( Pointer and needle shallmove together)

When crushing takes place in the specimen, needle will start falling back butpointer will remain at maximum reading.

Record the reading shown by pointer viewing perpendicular to the face of dial.( Load applied in kN or tonne- W)

Relieve the load from CTM. Remove the cube. Clean the platens.

Check the features of cube failure. Good failure is that cube mass retainedshall have concavity on sides. If failures are occurring consistently by crack developing only on one side it means cubes are eccentrically loaded. If cracksare always developed centrally means point load is getting applied due toConvexity of platens. Remedial measures are required to be taken for this.

Page 66: QAM-VSB-02

Calculations:

Compressive Stress ( c ) in N / mm2 or Kg / cm2 as below :

c = Wx1000 /A in N/mm2 or Kg /cm2

Average of the set of Three or more cubes to be recorded (c’ ).

When three or more cubes from single batch/lot is tested, max variation isallowed +/- 15%. If any cube is showing more variation, result of that cube isdiscarded and average of two or more is to be taken.

Recording :

Record is generated as per the sample format given in chronological order.

Format to be used: Cube Register Compression testing of cube testing - NCC/CWG-2010/F-08

AGGREGATE CRUSHING VALUEDoc. No. NCC /CWG-2010/JP-03

Project : COMMONWEALTH GAMES 2010, D.U Rev.-01

Page 67: QAM-VSB-02

( North Campus)PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR DETERMINATION OF AGGREGATE CRUSHING VALUE

( I.S : 2386-IV )Aim:

To calculate aggregate Crushing value by testing aggregate passing 12.5 mm sieve and retained on a 10 mm sieve. ( This is Alternative method to Aggregate Impact Value.)

Apparatus:

15 cm dia steel cylinder with plunger and base plate, tamping rod 16 mm dia and 600 mm long with one end rounded, Weighing balance of accuracy 1 g, Sieves 12.5 mm , 10 mm & 2.36 mm, Drying Oven, CTM

Procedure :

Take sample of aggregates by sieving through 12.5mm and retained on 10mm.

The aggregate shall be tested in surface dry condition. If dried by heating, theperiod of drying shall not exceed 4 hours and temp shall be 100-110 deg C.

Sample shall be cooled down to room temperature before testing. Takeapproximately 6 kgs of sample.

The quantity of the sample shall be such that the depth of material in thecylinder after tamping shall be 10cms.

Cylinder shall be filled up in 3 layers and each layer shall be tamped 25 timeswith tamping rod and finally leveled off.

The weight of material comprising the test sample shall be determined. ( A ), g

The plunger shall be placed in position and the apparatus shall be then placedbetween the platens of CTM.

Load shall be applied at uniform rate so that load of 40t is reached in 10 minutes.

The load shall be removed from the cylinder and sieved through 2.36 mmSieve. The fraction passing sieve 2.36 mm shall be weighed to nearest 1gSuch two tests shall be taken.

Reporting:

Aggregate Crushing Value, % = (B / A) x100

Page 68: QAM-VSB-02

The mean of the two results shall be reported to the nearest whole

Format to be used:

NCC/CWG-2010/F-03A

ELONGATION INDEX OF AGGREGATE

Doc. No. NCC /CWG-2010/JP-04

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India Ltd

Page 69: QAM-VSB-02

Name of Contractor : M/s NCCL

PROCEDURE FOR DETERMINATION OF ELONGATION INDEX OFAGGREGATE

(IS: 2386 – I)

Aim:

To determine the Elongated shape of particles of Coarse Aggregate greater than 6.3 mm size.

Apparatus:

Balance with accuracy of 0.1% of weight of the sample, Elongation Index GaugeAll other as per Sieve analysis.

Sample:

It shall be taken from retained material from Sieve analysis preferably and shouldHave at least 200 pieces of any fraction.

Procedure:

Each sample of 20mm and 10mm metal shall be taken from retained fraction.

Each fraction shall be gauged in turn for thickness on metal gauge.

The total amount passing the gauge shall be weighed.

Report:

The Elongation Index is the total weight of the material passing the variousThickness gauges; expressed as a % of the weight of total sample gauged.

Format to be used:

NCC/CWG-2010/F-01

FLAKINESS INDEX OF AGGREGATEDoc. No. NCC /CWG-2010/JP-05

Project : COMMONWEALTH GAMES 2010, D.U Rev.-01

Page 70: QAM-VSB-02

( North Campus)PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR DETERMINATION OF FLAKINESS INDEX OF AGGREGATE

(IS: 2386 – I)

Aim:To determine the Flakiness of particles of Coarse aggregate greater than 6.3 mmsize.

Apparatus :

Balance with accuracy of 0.1% of weight of sample, Flakiness Index GaugeAll other as per Sieve analysis..Sample :

It shall be taken from retained material from Sieve analysis preferably and shouldhave at least 200 pieces of any fraction.

Procedure :

Each sample of 20 mm and 10mm shall be taken from retained fraction.

Each fraction shall be gauged in turn for thickness on metal gauge.

The total amount retained on the gauge shall be weighed.

Report :

The flakiness Index is the total weight of the material passing the variousthickness gauges; expressed as a % of the weight of total sample gauged.

Format to be used:

NCC/CWG-2010/F-02

SILT CONTENT IN SANDDoc. No. NCC /CWG-2010/JP-07

Project : COMMONWEALTH GAMES 2010, D.U Rev.-01

Page 71: QAM-VSB-02

( North Campus)PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR FIELD TEST FOR SILT CONTENT IN SAND(Ref: A. M. Neville)

Aim : To determine Silt content in Sand by volumetric method field test.

Apparatus :Measuring cylinder 250 ml, Common Salt.

Procedure :Prepare 1% solution by mixing 10gms of common salt in 1litre of water.

Put this solution in measuring cylinder upto the mark of 50 ml.

Add Sand as received in the cylinder till its level reaches 100 ml.

Add Solution again so that the mixture reaches the level of 150 ml.

Cylinder top is now covered with the palm of hand and shake vigorously byturning upside down.

Then allow it to stand undisturbed for 3 hours.

Take reading for top layer of Silt ( A ) and layer of Sand ( B ).

Calculations :Silt content % Volumetric = (A / B ) x100

Reporting :% Silt contain (Volumetric ) shall be reported in whole number.

Note : This method is approximate and conversion to weight basis ( which isAcceptance criteria ) is dependent on fineness of material. However 8% volumetric content is treated as reliable. It was suggested that weight ratio is obtained by multiplying volumetric ratio by ¼ for natural sand and ½ for Crushed sand. Accurate test when 8% limit of silt contain is exceeded can be done as per IS method of Sedimentation if required.

Format to be used:

NCC/CWG-2010/F-21

FILLING CUBES FROM FRESHLY MIXED CONCRETE

Doc. No. NCC /CWG-2010/JP-08

Page 72: QAM-VSB-02

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR FILLING CUBES FROM FRESHLY MIXED CONCRETE

Aim : To prepare specimens for the test of Compressive Strength of concrete.

Apparatus :

Cube moulds fitted tightly on base plate (size in mm 150x150x150) in required set (One set comprises of 6 moulds.)

Smooth Tamping rod of size 16 mm dia and length of 600 mm with one rounded edge.

Trowels small and large.Collection pan, scoop, measuring scale etc.Flat working platform of adequate size.

Procedure of Cube Casting:

Cube moulds shall be verified for dimensions and tight fitting assembly. Theyshall be lightly oiled and have clean surfaces.

Cube moulds shall be arranged in sets on working platform.

Sample is collected as per the procedure given earlier.

Concrete is filled in cubes one by one in three layers. Each layer is tamped 35times with tamping rod evenly. Tamping shall penetrate the layer below. Careto be taken particularly at corners. Small trowel can be used at the sides toensure proper surface of sides and allow entrapped air to escape.

Cubes shall be filled slightly above top surface of mould.

The top extra layer shall be struck off by large trowel, flush to the top.

Cubes shall not be disturbed till at least 6 hours after the casting.

Cube concrete surface shall be marked with Cube I.D. , Mix, location of use,date, source of concrete ( additional) when adequately set.

Cubes thus cast, shall be covered with wet gunny bags till they are replaced incuring tank.

After about 10-12 hours cubes can be opened and place them in curing tank.

Page 73: QAM-VSB-02

Cubes shall be checked for surface correctness, sharp edges and incorrect filling. Such defective cubes may be rejected there it self. In such case Corrective /Preventive actions shall be taken.

Procedure for Tank Curing :

Cubes shall be arranged in the curing tank sequentially as per ID mark,datewise.

Cubes shall be sorted out for 7 days , 28 days tests. Cubes shall be placed inthe tank in layer of three cubes with marked top upside.

Cubes once placed in tank shall not be handled, disturbed frequently so thatedges are not broken.

Water in tank shall cover cubes by at least 50-75 mm all the time.

Water temperature must be maintained in winter.

Procedure for In-Situ Curing :

This method is deployed to decide stripping time of shuttering when shutteringstripping is planned earlier than given as per IS: 456. This method shall not bedeployed for the cubes to be tested for compressive strength of concrete at 28 days.

Record :

Details of Cubes thus sampled shall be entered serially in Cube Register maintained for testing compressive strength. The number of cube samples cast shall also be entered in pour card with proper traceability to cube register.

Format to be used: It shall be recorded in Cube register & pour card

Doc. No. NCC /CWG-2010/JP-09

Page 74: QAM-VSB-02

SAMPLING / INSPECTION / TESTING RMC CONCRETE

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR SAMPLING / INSPECTION / TESTING RMC CONCRETE

Aim:

To Check, Inspect Conformity of RMC Concrete which is manufactured outside and supplied at site.

Pre-requisites:

RMC supplier shall be given prior information by the site regarding following:

1. Grade of Concrete.

2. Minimum Cement or cementations material contents. (EIL Appro. required)

3. Slump required and tolerances in slump. (EIL Approval required)

4. W/C ratio.

5. Method of Concreting (Manual, Bucket or Pumping)

6. Control of temperature if required shall be specified in case of Mass concreting.

7. Quantity of Concrete required – Total, Phase wise, day wise.

8. Supplier shall know site condition, distance and shortest route to the site from his plant.

RMC Supplier shall give following Information to Site:

1. Mix design details including admixtures/ additives and cement used.

2. Material testing results for Cement, Admixtures / Additives, water, Coarse andFine aggregate.

Page 75: QAM-VSB-02

3. Transit mixer Capacity & time to travel from RMC plant to site.

4. Minimum and maximum quantity that can be supplied in a single pour.

5. Supplier’s In-house testing facilities.

6. Method of concreting which Supplier can undertake for the pours.

7. Communication system which Supplier adopts.

8. Name of Important Plant Personnel.

Doc. No. NCC /CWG-2010/JP-10

Page 76: QAM-VSB-02

SIEVE ANALYSIS OF COARSE AGGREGATES

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR SIEVE ANALYSIS OF COARSE AGGREGATES( I.S. : 2386-I )

Aim : To determine the properties of Coarse aggregate for size and gradingdistribution ( Nominal 20mm/12.5or10 mm metal).

Apparatus :

Drying Oven, IS Sieves 40 mm, 20 mm,16 mm, 12.5 mm, 10mm, pan. – for Analysis of 20 mm metal.

IS Sieves 20 mm, 16 mm,12.5 mm, 10 mm, 4.75 mm ,2.36mm pan - for Analysis of 10/12.5 metal.

Weigh scale to the accuracy of 1gm, Brush, Metal trays etc.

Procedure:

Sample of aggregate shall be collected as given earlier.

Sieves shall be cleaned and arrange in sequence in descending order. Panshall at the lower most end and Lid on top.

Take around 5 kg of sample and dry it in oven at temp of 100-110 deg C.

Dried sample shall be then weighed ( 5 kg preferably) and sieved successivelyon sieves starting with 40mm and then through 4.75mm( For 20 mm down aggregate size ) and through 2.36 mm (For 12.5/10 mm down aggregate size) .

Each sieve shall be shaken at least for two minutes on clean tray until no moretrace passes.

Motion shall be varied like back and forth, left to right, circular clockwise andanti-clockwise and with frequent jarring.

Material shall not be forced through the mesh. But for coarser than 20mmparticles, placing is permitted (passing particles through sieve openingmanually).

Sieves shall be brushed from underneath of mesh and pass on to the next.

On completion of sieving, material retained on each sieve is to be weighSeparately.Reporting:

Page 77: QAM-VSB-02

The cumulative % by weight of the total sample passing each sieves, to theNearest whole number.OrThe % by weight of the total sample passing one sieve and retained on the nextsmaller sieve to the nearest 1 decimal.

Check for permissible limits for passing.

Format to be used:

NCC/CWG-2010/F-14

SIEVE ANALYSIS OF FINE AGGREGATES

Doc. No. NCC /CWG-2010/JP-11

Page 78: QAM-VSB-02

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR SIEVE ANALYSIS OF FINE AGGREGATES( I.S. : 2386-I )

Aim : To determine the properties of Fine aggregate for size and distribution bycalculating Fineness modulus and deciding Grading Zone.

Apparatus :

Drying Oven, IS Sieves 10 mm, 4.75mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron, 150 mm, Pan, Weigh scale to the accuracy of 1g, Brush , Metal trays etc.

Procedure:

Sample of sand shall be collected as given earlier.

Sieves shall be cleaned and arrange in sequence in descending order. Panshall at the lower most end and Lid on top.

Take around 1 kg of sample and dry it in oven at temp of 100-110 deg C.

Dried sample shall be then weighed ( 1 kg preferably) and sieved successivelyon sieves starting with 10mm and then through 150 micron.

Each sieve shall be shaken at least for two minutes on clean tray until no moretrace passes.

Motion shall be varied like back and forth, left to right, circular clockwise andanti-clockwise and with frequent jarring.

Material shall not be forced through the mesh. Lumps in fines shall be brokenagainst the wall of sieve.

Sieves shall be brushed from underneath of mesh and pass on to the next.

On completion of sieving, material retained on each sieve is to be weighseparately.

Calculations :

Fineness Modulus : Add values of Cumulative % Retained on each sieves and

SIEVE ANALYSIS OF FINE AGGREGATES

Doc. No. NCC /CWG-2010/JP-11

Project : COMMONWEALTH GAMES 2010, D.U Rev.-01

Page 79: QAM-VSB-02

( North Campus)PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

Divide by 100. (Normally accepted limit of FM is value between 2.2 to 3.2.

Higher value of FM indicates Coarser sand whereas lesser value indicates Finer one. )

Grading Zone of Fine Aggregate – Value is shown between I to IV. Where zone- I is associates with Coarser Fine aggregate and Zone IV is Finer.

Zones are decided from values of 600 micron passing % in sieve analysis.( Refer Table-4 of IS : 383 )

Zone –I – 15-34%, Zone-II – 35-59 %, Zone-III- 60-79%, Zone-IV- 80-100%

Reporting:

The cumulative % by weight of the total sample passing each sieves, to thenearest whole number.OrThe % by weight of the total sample passing one sieve and retained on the nextsmaller sieve to the nearest 1 decimal.

Calculate F.M. of the material and decide Grading Zone of material.

Format to be used:

NCC/CWG-2010/F-14

Page 80: QAM-VSB-02

SLUMP TEST Doc. No. NCC /CWG-2010/JP-12

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR SLUMP TEST FOR FRESH CONCRETE ( IS : 1199)

Aim : To check Workability of Freshly mixed Concrete by Standard Slump ConeMethod. This method is suitable for max size of aggregate upto 38 mm only.

Apparatus :

Slump cone with base plate and cone having bottom dia 20 cms , top dia 10 cms and height 30 cms.

Smooth Tamping rod 16 mm dia and 600 mm long with one rounded edge.

Scoop , Trowel, Collection pan, measuring scale ( Tamping rod also have marking ).

Smooth / Leveled platform for working.

Procedure :

Sample is collected as per the sampling procedure given earlier.

Internal surface of the cone shall be cleaned and freed from extra moisture andany layer of set cement slurry.

Conical mould shall be fixed tight on the base with screw arrangement ensuringthat no cement slurry will leak from the joint.

Assembly shall be placed on smooth and truly horizontal surface rigidly.

Mould shall be filled up in 4 layers. Each layer shall be tamped with tampingrod for 25 times evenly. Tamping shall penetrate in layer below.

The top level shall be struck off by trowel or rod flush to the top of cone.

The Cone shall loosened at the base and shall be lifted carefully verticallywithout disturbing concrete mass.

The subsidence shall be measured immediately.

Above operations shall be carried out at place free from vibrations and shock.

The whole exercise is to be done within two minutes from sampling.

Page 81: QAM-VSB-02

In any test in which specimen collapses or shears the test will be repeated.

Record :

Slump shall be recorded in mm.

If in repeat test the slump shears, it is to be recorded.

Format to be used:

NCC/CWG-2010/F-17

PROCEDURE FOR TEST ON COMMON BURNT CLAY

Doc. No. NCC /CWG-2010/JP-13

Page 82: QAM-VSB-02

BRICKS Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR TESTS ON COMMON BURNT CLAY BRICKS

( I.S : 3495-I&II )

A. DETERMINATION OF COMPRESSIVE STRENGTH OF BRICKS:

Aim: To determine Compressive Strength of Common Burnt Clay bricks

Apparatus :

M.S. Packing Plates 10 / 12 mm thk of adequate size ( 250mm x 150 mm)- 2 nos, minimum Plywood sheets 3mm thk /3 ply – 2 nos, CTM, Measuring ScaleClean sand screened through 3 mm sieve ( Remark-Sieving through 4.75 mmnormally will do), O.P. Cement, jute cloth

Pre- Conditioning:

Record the measurements of the samples to nearest 1mm.

Remove the unevenness observed in the bed faces to provide two smooth andparallel faces by grinding ( rubbing )

Immerse the specimens in the water at room temperature for 24 hours.

Remove specimen and drain out surplus moisture. Fill the frog and voids in thebed faces with CM 1:3 flushed to the surface.

Store under damp jute cloth for 24 hrs and then immerse in water for 3 days.

Remove specimen from water and wipe traces of moisture.

Procedure :Place the specimen with flat faces horizontal and mortar filled face upwardbetween two ply sheets and required packing plates. Center it carefully.

Apply load at rate of 140 kg /cm2 per minute ( 30 tonne per minute ) , tillfailure occurs.

Note the maximum load at the failure.

Calculations :Compressive Strength, kg /cm2 = Max Load in Kg / Avg area of the bed faces of the specimen, cm2

Page 83: QAM-VSB-02

Report: Average of the results shall be reported.

B. DETERMINATION OF WATER ABSORPTION :

Aim :

To determine water absorption of specimen by 24 hours immersion in cold water.

Apparatus :

Balance with accuracy of 1g, Oven, Measuring scale.

Pre- conditioning :

Dimensions shall be measured to accuracy of 1 mm of test specimen

Dry specimen in oven at temperature 105-115 deg C till it attains substantiallyconstant mass.

Cool the specimen to room temperature and obtain weight – M1, g ( Specimenwarm to touch shall not be weighed. )

Procedure:Immerse completely dried specimen in clean water at temperature 27+/- 2 deg C.

Remove specimen after 24 hours and wipe out any traces of water with dampcloth.

Weigh the specimen within 3 minutes after removing from water. ( M2, g )

Calculations :

% Water Absorption = ( M2-M1 /M1) x100

Report :

Average of the results to be reported.

Format to be used:

Field Dry Density Test - NCC/CWG-2010/F-09

SAMPLING OF AGGREGATESDoc. No. NCC /CWG-2010/JP-14

Page 84: QAM-VSB-02

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROCEDURE FOR SAMPLING

FOR AGGREGATES (IS: 2430):

Sample from Stock Pile of the Coarse / Fine aggregate:

Samples from stock piles should be made up of at least 10 increments; taken Equally from top third, mid point and bottom third.

Outer layer of sampling point shall be removed and the sample is taken from the material beneath.

Gross Sample – the sample thus collected will be the gross sample. Qty of gross sample is depends on the aggregate size :

SL. No. Aggregate Size Gross Sample1 2.36mm/4.75mm 10 KG2 12.5 mm 15 KG3 20 mm 25 KG4 40 mm 80 KG

Reduction of Gross Sample : Will be done as per method of Quartering torequired sample size for testing.

Quartering Method :Take the gross sample on plain platform. For Fine aggregate use Tray so thatresidual fines can be collected by brushing.

The aggregate shall be mixed and then scooped into a cone shape pile.

After the cone is formed, it shall be flattened by pressing the top.

Then it is divided in four quadrants diagonally.

The bulk of the sample is reduced by rejecting any two diagonally oppositeQuarters

This method is repeated till sample size is approximately achieved for given

SAMPLING OF BRICKSDoc. No. NCC /CWG-2010/JP-15

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

Page 85: QAM-VSB-02

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

BRICKS (As per IS: 5454)

Sampling a lot which shall contain maximum 50000 bricks. In case a consignment has bricks more than 50000 bricks of same classification, size and manufactured under relatively similar conditions, it shall be divided into lots of 50000 bricks or part thereof.

Sampling from the stack – When it is necessary to take sample from the stack, the stack shall be divided into number of real or imaginary sections and required number of bricks shall be drawn from each section. For the purpose bricks in the upper layers of the stack shall be removed to enable units to be sampled from places within the stack.

Sample size – For Visual / Dimensional Characteristics –

Lot Size of bricks Sample size for Individual brick Sample size For group of Check 20 bricks Check

Sl. No. Range Min. Sample Collection1 2001-10000 20-402 10001-35000 32-603 35001-50000 50-80

Sample size For Physical Characteristics –

Lot size of bricks Sample size for Comp. Strength, water absorption, Efflorescence etc.

Sl. No. Range Min. Sample Collection

1 2001-10000 5-102 10001-35000 10-203 35001-50000 15-30

Page 86: QAM-VSB-02

FOR EARTH / SOILDoc. No. NCC /CWG-2010/JP-15

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

FOR EARTH / SOIL (IS: 2720 -I)

If the earth received for testing is wet for handling then same is air dried onplatform in outdoor.

The Gross sample shall be as below:

Max size of particles Min. Gross Sample in Substantial qty in kg

Sl. No. Max Size of particles Min. Gross Sample

1 75 mm 100 KG2 40 mm 80 KG3 19mm 35 KG4 10mm 25 KG5 4.75 mm 20 KG

Sample size for required test shall be made as per quartering methoddescribed above.

Care to be taken that no fines are lost in the operation as soil properties mostlydepend on them for testing.

Doc. No. NCC /CWG-2010/JP-17

Page 87: QAM-VSB-02

FRESH CONCRETE IN THE FIELD

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

FOR FRESH CONCRETE IN THE FIELD( IS : 1199 )

Sample from Mixer:

At least three approximate equal samples totaling 0.02 m3 (equivalent to fill 6Cube moulds) shall be taken from a batch.

For collection a scoop shall be used. No tool with flat edges ( like phawra) shallbe used.

3 samples are taken at about the time interval when ¼, ½ and ¾ of concrete isdischarged.

Sample from Place and Time of Deposition:

Sample shall be taken immediately after or during discharge at site.

Samples shall be collected from not less than 5 well distributed points avoidingthe edges of the mass where segregation may have occurred.

Mixing of Sample :

Sample thus received shall be immediately remixed on non-absorbent platformand made ready for testing.

Frequency of Sampling :

The minimum frequency of sampling of concrete of each grade shall be as below:

Qty of Concrete in the No of Samples *

SL. No. Qty of Concrete –M3 No. of Sample- Set1 1-5 12 6-15 23 16-30 34 31-50 45 51 & above 4+1 additional sample for

each additional 50 m3 or part thereof.

FRESH CONCRETE IN THE FIELDDoc. No. NCC /CWG-2010/JP-17

Page 88: QAM-VSB-02

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

Note:

At least one sample taken from each shift.

Where concrete is produced at continuous production unit such as RMC plant, frequency of sampling may be agreed upon mutually.

Three specimens shall be made for each sample for testing at 28 days.

Additional samples may be required for determining strength at 7 days or at the time of striking formwork.

Remarks :

Sample* means qty of concrete required to fill one set of cubes ( 3nos / 6 nos ) for testing.

Hence number of sample is equivalent to number of cube sets (3 / 6 nos.). 3 cubes are drawn when only cube testing is done at 28 days. 6 cubes are drawn for tests at 7 / 28 days required.

CONCRETING IN HIGH TEMPERATURE REGIONS (IS: 7861-1)

Ice is added

Water Cement Ratio should not change with addition of Ice

Adjust Quantity of water accordingly to the volume of melting ice

CONCRETING IN LOW TEMPERATURE REGIONS (IS: 7861-2)

Precautions must be taken to keep the temperature in control during mixingand placing Concrete.

The commonly adopted method is by using hot water upto 60 C .

In extreme frost conditions the concrete surface is covered with dry blanketsof straw, cement bags, tarpaulins etc.

WATER CONTENT IN SOIL SAMPLEDoc. No. NCC /CWG-2010/JP-18

Page 89: QAM-VSB-02

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

PROECEDURE FOR DETERMINATION OF WATER CONTENT IN SOIL SAMPLE

(IS: 2720-II)A. By Oven Drying Method:

Aim :

To determine Water Content in Soil Sample at Laboratory by Oven Method

Apparatus :

Container – Any suitable non-corrodable air tight container. ( Remarks- These can be 300ml aluminum or stainless steel boxes with lid )

Balance – Having accuracy of 0.04% of the weight of soil taken for test.

Remarks-Balance of capacity 500 g and accuracy of 0.1g can be used when accurateworking is required. If normal weighing balance with 1g accuracy is used thenaccuracy of water content will be around 0.2 to 0.5% only; depending on samplesize 500 to 200 g respectively.

Drying Oven – Thermostatically controlled.

Soil Specimen:

It shall be true representative of soil mass. The size of specimen is recommended for general laboratory use as below. However, the dryer the soil,Greater shall be size. Remarks: Preferably take 500g sample when weighingAccuracy is 1g.

Size of particles - 37.5mm, 19mm, 9.5mm, 4.75mm, 2mm

More than 90% passing

Min qty of soil specimen 1000gm, 500gm, 300gm, 200gm, 50gm

Procedure:

Clean the container with lid, dry and weigh (W1, g)

Page 90: QAM-VSB-02

WATER CONTENT IN SOIL SAMPLEDoc. No. NCC /CWG-2010/JP-18

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

Take the required quantity of the soil specimen in container, crumble clods andplace loosely and weigh with the lid ( W2, g )Keep filled container in an oven with the lid removed and maintain thetemperature at 110+/- 5 deg C. for maximum 24 hours.

Cool the container and record Final mass of container with lid and dried sample( W3, g ).

Calculations :

% of Water Content = 100 x ( W2-W3 ) / ( W3- W1)

Report :

The water content % shall be expressed to two significant figures ( e.g.- 23, 2.3,0.23 )

Note : Oven drying at 110 +/- 5 deg C does not result in reliable values for soilcontaining Gypsum and any other mineral having water of hydration or significantamount of organic matter. Reliable values can be obtained in an oven by drying at temperature around 60-80 deg C.

Remarks: Traces of Gypsum / lime / Alum can be seen as white particles. That of organic matter will show black colour fibrous traces. Particles of Green / BluishGreen can be minerals having water of hydration.

B. By Sand Bath Method ( Suitable as Field Test )

This method is not suitable for soil containing a large portion of Gypsum ,Calcareous Matter or Organic matter.

Aim :To determine water content in soil specimen in the field.

Apparatus:

Container – Any suitable Air tight container as given in Oven drying method.Sand Bath : Suitable size and containing clean sand to a depth of 3 cms.Stove, Spatula

Page 91: QAM-VSB-02

WATER CONTENT IN SOIL SAMPLEDoc. No. NCC /CWG-2010/JP-18

Project : COMMONWEALTH GAMES 2010, D.U ( North Campus)

Rev.-01

PMC : M/s. Engineers India LtdName of Contractor : M/s NCCL

Soil Specimen :As given in Oven drying method.

Procedure :Clean the container with lid, dry and weigh ( W1 , g )

Take the required quantity of the soil specimen in container, crumble the clodsand place loosely and weigh ( W2, g )

Add few pieces ( 3-4 small) of white paper if necessary. This the indicator forover-heating. While heating the soil paper pieces shall not turn brown.

Place the container with lid removed on sand bath and heat sand bath on thestove.

During heating sample shall be turned frequently and thoroughly to assistevaporation. It shall be done carefully so as no soil mass is spilled over.

When drying is complete, remove the container and cool it down. Removepieces of papers.

Weigh the container with lid on. ( W3, g )

Calculations :

w % = 100x ( W2 - W3 ) / ( W3 –W1 )

Report :

Same as Oven drying method to two significant figures (e.g. – 23, 2.3, 0.23

Page 92: QAM-VSB-02

JOB PROCEDURE FOR SURVEY WORK

Doc. No. NCC/CWG 2010 /JP-19

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No.-01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE

The purpose of this procedure is to proper control in survey works.

2. SCOPE

This procedure covers activities for carrying out survey works.

3. PROCEEDURE

Transfer the bench mark/grid pillar nearer to work spot.

Reference pillars to be constructed to facilitate easy construction. These pillars are to he checked by theologize and protected till the completion of major activities.

Level of existing ground to he taken jointly with EJL before commencing of earth work.

During construction, level at required stages to be taken and checked by leveling instruments.

The survey work to be carried out by an experienced surveyors and to he checked by construction engineer and in line with the instructions of engineer in charge.

Permanent ‘id pillars to be approved by concerned engineer and to be maintained till completion of job.

in case of conflict between procedure and specification. specification shall supersede procedure.

Page 93: QAM-VSB-02

JOB PROCEDURE FOR EXCAVATION (for foundations, trench, embankment etc.)

Doc. No. NCC/CWG 2010 /JP-20

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No.01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE

The purpose of this procedure is to provide a guideline for supervision of excavation at site and to ensure that

Proper locations are identified for exaction. Size of excavation is determined for all foundation so as to incorporate all

working space. Proper safe working area should be maintained. Proper documents are generated so as to quantify the actual quantity of

work done.

2. SCOPE

This procedure covers supervision and record keeping methods for excavation; which includes.

Average Ground Level at the time of handing over for any particular area. Allowance for working space Identification of proper location of excavation.

3. REFERENCE DOCUMENTS

Method Statement / CPWD Specification IS: 1200. IS: 2720 Pan VII AFC drawing

4. DETAIL ACTION PLAN

Before starting earth work in excavation, the areas will he surveyed. After completing the checking procedure of survey work, soil has to be identified.

Page 94: QAM-VSB-02

Classification of soil shall be as soft/loose/dense soil/hard rock/mud/soft disintegrated rock.

After classification of soil, the area will be started true to its lines, levels and contours as shown in drawing. In ease of excavation in foundation, trenches etc. excavated soil has to be deposited in such a distance from excavation pit so that the sides of pit does not collapse due to surcharge load of soil. The sides of excavation may be cut sloping or shored and strutted to hold the face of earth as per site requirement. Foundations, pits/trenches shall be excavated to the depth just before starting lean concrete. Where the excavations carried out below the foundation level of an adjacent structure, the precaution has to be taken such as under pinning, shoring and. strutting etc. any obstacle encountered during excavation shall be reported immediately to the engineer in charge.

Excavated area shall be barricaded by steel pipes for safety measures & also inclined cutting should be done to avoid sliding of soil.

5. DOCUMENTATION

Record shall be generated as per ITP.

Page 95: QAM-VSB-02
Page 96: QAM-VSB-02

JOB PROCEDURE FOR BACK FILLING

Doc. No. NCC/CWG 2010 /JP-21

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No.01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE The purpose of this procedure is to provide a guideline for proper supervision of back filling of earth at site and to ensure that —

Proper type of soil is used for back filling Proper procedure is followed for back filling Documents are generated so as to confirm adherence to the procedure

2. SCOPE This procedure covers supervision and record keeping method for back filling, which includes –

Selection of soil for backfilling. Layer wise backfilling is adhered to achieve maximum compaction. Records submitted for compliance of the same.

3. REFERERENCE DOCUMENTS Method Statement / CPWD Specification 1S2720 Test records

4. DETAIL ACTION PLAN

Material used for earth filling will he free from clods larger than 7mm in any direction organic matter &other deleterious material. All clods of the filling material will be broken or removed if the filling material (normally excavated material) shall contain deleterious substance saltpeter earth etc the same shall not he used the spaces all around the foundations will he cleared of all debris, brick bats etc. filling will be done in layers of 20 cms and each layer will he moisture conditioned, rammed with vibro rammer and consolidated to obtain 95% of the MDD & OMC in approved lab\field lab. Wherever hammer cannot be put due to constraint of space, hand ramming with crow bar shall be done as a special case. The moisture content of the back filled soil shall be maintained at ±\- 2% at site

5. Documentation As per ITP

Page 97: QAM-VSB-02

JOB PROCEDURE FOR PCC Doc. No. NCC/CWG 2010 /JP-22

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No.01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE The purpose of this procedure is to provide guideline on supervision and surveillance of plain cement concrete work and to ensure that —

Size of PCC is determined for all foundation Proper procedure is followed for PCC work Documents are generated so as to quantity the actual quantity of work

done 2. SCOPE This procedure covers supervision and record keeping methods for PCC which includes.

Ground level over which mud —mat will be laid Marking top & bottom level of PCC Proportions of the concrete mixture as per the grade, water-cement ratio

etc. 3. REFERENCE DOCUMENTS

Method Statement/ CPWD Specification IS:456, 1199, 8112, 4925, 2386, 1791, & 516 AFC drawing SOR

4. DETAIL ACTION PLAN Before starting the plain cement concrete work all the material such as cement coarse aggregate, fine aggregate etc. has to he tested either at field or at approved laboratory in the frequency stipulated in QAP . Manufacture test certificate will be submitted whenever applicable; if MTC correlation is not done, the material has to he tested at either field laboratory or at approved laboratory. For plain cement concrete, nominal mix will be used and the proportion of cement: CA:FA and water cement ratio will be as per IS: 456. For plain cement concrete: at the time of nominal mix, the volume of cement per bag shall he considered, as 0.0347 cum. The bulk age of sand and water content in CA shall he account for & amount of water to be added will be adjusted accordingly keeping in the view of workability & water cement also. Formwork shall be place true to its line & slope wherever required. Mixing of concrete will be done in mechanical mixer; the mixing times will him such that all the components mix properly. If hand mixing is done, 10% cement access will be poured. Line, levels, slope, and hand tamping should be done. Before concreting the ground level shall he insured as per the AFC drawing, virgin ground.

Page 98: QAM-VSB-02

JOB PROCEDURE FOR RCC Doc. No. NCC/CWG 2010 /JP-23

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS

PMC : ENGINEERS INDIA LIMITED Rev. No.01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE

The purpose of this procedure is to provide methodology for effective surveillance of various activities involved in supervision of RCC work at site and to ensure that

Shuttering is placed as per correct line & level Reinforcement is laid on as per approved drawing\BBS\specifications Proper procedures are followed for RCC work documents are generated so

as to quantity the actual work done.

2. SCOPE

This procedure covers supervision and record keeping methods for RCC which includes.

Top & bottom level of RCC. Proportioning of concrete mix as per grade. Preparation of pour card and adhering to prescribed quality standards.

3. REFERENCE DOCUMENTS

CPWD Specification IS; 456, IS 8112, IS 2386, IS 383, IS 1786 AFC drawing SOR

4. DETAIL ACTION PLAN

A. Materials

Testing of materials; for cement manufacture test certificate shall be submitted for each batch of cement, in case of MTC correlation is not done, the same shall be tested at approved laboratory. RCC shall be used as per SOR item. & AFC drawings.

Coarse aggregate shall be tested at field laboratory or at approved laboratory, gradation of coarse aggregate shall confirm to 1S 383. Crushing value, impact value, abrasion value, flakiness index of coarse aggregate shall be tested at approved laboratory per IS 2386. Frequency of testing shall be as per QAP.

Page 99: QAM-VSB-02

Fine aggregate shall be tested at field or at approved laboratory .Gradation of coarse aggregate shall confirm to IS 383 & shall be tested at field presence of deleterious material shall he tested at laboratory .frequency of testing shall he as per QAP

For reinforcement steel., manufacturer test certificate shall be submitted

B. Design Mix:

Before establishment of design mix all the materials such as CA, FA cement etc. shall be tested. Design stipulation such as water cement ratio, degree of quality control, minimum cement control, workability etc. shall he considered as stated in of contract document. In case of change of design stipulation or change of source of ingredients using for concrete re-design mix will be done.

Trial mix shall be taken at site condition for design mix & cube of respected mix shall be tested for approval of design mix.

C. Mixing of Concrete:

For weight — batching in hatching plant, the entire ingredient shall be poured by weight. Cement shall be stored in cement a so silo through bucket - elevator. Water shall be measured in volume. For solid admixture it shall is added by mass, & in case of liquid or poster admixture it shall be added by volume, capacity of batching plant in 30 cum per hour. During hot/cold weather, the mixing shall be as per IS 7861.

D. Transportation, Placing & Compaction:

Concrete shall be transported from batching plant to pouring pit through transit mixer concrete shall he poured to pit immediately after its transportation to working site. For concreting in depth chutes shall be used. Chutes shall be designed so that concrete is to some extent remixed at lower end the vertical fall should not he more than l.5m height. Immediately after pouring of concrete in the formwork, it shall be compacted by using mechanical vibrating equipment. Immersion type vibrator shall be inserted in vertical position and care should be taken so that it did not over or under vibrate at the time of transportation and placing of concrete all the precautionary measure has to be taken to avoid any sort of deterioration in quality. In case of placing of concrete in layers which are advancing horizontally as the work progress. Great care shall be taken to ensure adequate vibration, hounding and mounding of concrete between the succeeding batches. Before placing of concrete the pit shall be cleaned properly concrete shall be deposited as near as practicable in its final position to avoid re-handling concrete shall not be started unless electrical conduits, pipes fixtures etc whenever required are laid before concreting all metal inserts anchor bolts pipe sleeves etc shall be fixed as per relevant drawing and that shall be checked W.R.T. its lines & levels

E. Joints:

Construction joints shall he provided as shown in drawings or as decided by EIL as far as possible the number of construction joints have to be minimized in column. The joint shall be formed 100-150mm below the lowest soft of the beam

Page 100: QAM-VSB-02

the joint in beam & slab shall be vertical with in 1/3-1/4 of the span with approved stop board at the time of resume of the next work the hardened surface shall be cleared off foreign materials, roughened property & wetted by pouring cement slurry or mortar.

Separation joints shall be obtained by using an approval alkathene sheet struck on the surface against which concrete shall he placed adequate care shall be taken to cause no damage to the sheet

Expansion /isolation joints in structure shall be formed in the position and to shape down in the drawing & subsequently it shall be filled with filling material PVC water stops shall be accurately cut, fitted & integrally joint to provide a continuous water tight diaphragm at all points.

F. Curing:

Concrete shall be cured by keeping it continuously moist wet for specified period of lime to ensure complete hydration of cement & its hardening. Curing shall be started after 8 hrs of placement of concrete in normal weather in hot weather after 4hrs. Exposed surface of concrete shall be maintained continuously in a damp or wet condition for at least for first 7 days after placing concrete. Curing shall be done 10 days for dry /hot weather condition in case of mineral admixture is used curing may be extended to 14 days.

G. Strength Test of Concrete

Samples in the form of 15 cm x I5cm x 15cm cubes shall be taken from fresh concrete as per is 119 cured and tested at 7 days & 28 days in accordance with IS 516 required strength of cubes depending on grade of concrete will be as per IS 456. Frequently of sampling as per IS 456. The concrete shall be deemed to comply with the strength requirement if satisfies the acceptance criteria as per IS 456.

H. Finishing of Concrete

On striking the form work, al1 the surface defects observed shall be rectified immediately the surface of non shuttered faces shall be smoothened with a wooden float to give a finish similar to that of the rubbed down shuttered faces the top faces of the concrete intended to be covered with screed or any other work shall be left with a rough finish.

I. Form work

Forms for concrete shall be of plywood confirming to IS: 6461 or steel & shall give smooth & even surface after removal thereof. Formwork & its support shall maintain their correct position & shall he of correct shape & profile so that the final concrete structure is within the limits of dimensional tolerance specified in IS: 456. The form shall be true, rigid & adequately braced both horizontally & diagonally the form shall have smooth and even surface & be sufficiently rigid to carry without deformation .the dead weight of green concrete, working load wind

Page 101: QAM-VSB-02

load & also the side pressure the green concrete form joint shall not permit any leakage. The form shall be strong; enough to withstand the effect of vibrations.

Before re-use all form shall be thoroughly scrapped, cleaned, examined & whenever necessary shall he repaired & retreated before re-setting, in the determination of time for removal of form, consideration shall he given to the location & character of structure the weather & other condition including the setting & curing of concrete & material used in the mix the form shall be removed without shock & method of form removal likely to cause over stressing or damage to concrete shall not be adopted. In normal circumstances form shall he removed below soffits of beams & slabs as per IS: 456.

Staging & scaffolding shall be properly designed & steel tubes will be used, for smaller works or works in remote areas wooden ballies shall be used. For circular shuttering, care shall be taken so that it is supported properly & diameter has been kept accurately.

J. Reinforcement Steel

Before placing the reinforcement bar bending schedule shall be prepared & got checked by EIL. Reinforcement shall be cut bend to shape & dimension as shown in BBS/drawing. All reinforcement shall be fixed in the correct position as shown in the drawing & shall be properly supported to ensure that displacement will not occur when the concrete is displaced & completed. Reinforcement bars shall he tied at every intersection cover blocks of specified thickness, constructed & cured properly shall be placed in between forms & reinforcement to provide sufficient clearance. In case of overlapping of two bars, lap length shall be provided as shown in the drawing the lap shall he staggered. At any section lap should not be more than 50% of total area. Tolerance of placing of reinforcement shall be as per IS 456.

Page 102: QAM-VSB-02

JOB PROCEDURE FOR BRICK WORK

Doc. No. NCC/CWG 2010 /JP-24

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS PMC : ENGINEERS INDIA LIMITED Rev. No.01CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE:

The purpose of this procedure is to. Provide uniform. Predetermined, well methodology for execution of brick masonry

work. Establish a guide line for record keeping. Minimize the errors. Control of non-conformance.

2. SCOPE:

The scope involved the various activities such as checking of material, laying, jointing. curing related to brick work. This procedure has been established which subject to revision is depending on its requirement.

3. REFERENCE DOCUMENTS Method Statement, CPWD Specification IS 1077, IS 3495, IS:2250 & IS:2212 AFC Drawing

4. DETAIL ACTION PLAN:

Prior to start the work strength & water absorption of bricks shall be tested at filed &. Efflorescence at approved Lab.

Manufacturer’s test certificate for each hatch of dement shall be provided. Cement shall he tested h at approved laboratory as per direction of Engineer-In-Charge.

Sand and cement should he mixed (1:4) by required ratio of volume using mechanical mixture machine or Measuring trays should be used for proper mix proportion. Mortar should be used immediately after mixing and before it has began to set. Volume of cement per bag shall L considered as 0.035 cum. In case of wet sand, volume of sand should be increased cons during its bulk age. Water has to be mixed to the quantity required to achieve a workable condition of mortal.

While using the bricks of lass 75 it has to be soaked in water sufficiently to wet the bricks, proper soaking of bricks shall prevent the suction of water from wet mortar.

Page 103: QAM-VSB-02

Brick should be placed on mortar-bed true to its line plumb in English/Flemish bond. Joint of (120 mm) bricks should be staggered and all the joints should be filled with mortal property. Any gap between the finished brick work and offices roof slab/beam shall be suitably scaled with mortar.

In case of brick of half brick thickness, walls shall he reinforced with 2 nos. 6mm dia steel bars placed at every third course with 1: 4 mortar.

Curing shall be done after 24 hrs. of completion of days work and shall be done for a period of 10 days. All fixture, pipes, conduits, holdfasts of doors and windows etc. required to be built in walls has to be embedded properly.

Page 104: QAM-VSB-02

JOB PROCEDURE FOR PLASTERING

Doc. No. NCC/CWG 2010 /JP-25

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS PMC : ENGINEERS INDIA LIMITED Rev. No.01CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE

The purpose covers supervision and method of record keeping for plastering works.

2. SCOPE

This procedure covers supervision and method of record keeping for plastering works.

3. REFERENCE DOCUMENTS

IS: 1542 Method Statement / CPWD Specification AFC drawings & SOR.

4. DETAIL ACTION PLAN

Before plastering work is started over masonry work the joints shall he raked out properly. Dust and loose mortar shall he brushed off Efflorescence if any shall be removed by brushing and scrapping. For concrete surface, the surface will be thoroughly chipped. Then surface shall be thoroughly washed with clean water with sufficient pressure. Chicken mesh should be used prior to start brick work

A. Application of plaster (Plain Cement)

Ceiling plaster of C.M. (1:4) shall be completed before commencement of wall plaster of CM (1:4)

Plastering shall he started from the top and worked downwards to the floor.

Neat cement slurry shall be applied on the surface before plastering. Mortar shall be mixed in a mixer M/c for hand Mix 10% extra cement to be

used. The mortar shall be then applied on the wall between the gauges with

trowel. The mortar shall then be applied in an uniform surface slightly more than

the specified thickness. Finally the surface shall be finished off with trowel or wooden/Aluminium float.

After completing the plaster the curing shall be done for minimum 7 days.

Page 105: QAM-VSB-02

B. Sand Faced Plaster:

Sand faced plaster shall have 1 layer of 12 mm thick with 1:4 Cement mortar shall be finished rough with sponge or as directed by Engineer-In-Charge. Curing shall be done for minimum 7 days.

4. DOCUMENTATJON

Record shall be generated as per approved ITP.

Page 106: QAM-VSB-02

JOB PROCEDURE FOR LAYING OF RCC PIPE

Doc. No. NCC/CWG 2010 /JP-26

PROJECT: COMMONWEALTH GAME 2010, D.U. NORTH CAMPUS PMC : ENGINEERS INDIA LIMITED Rev. No.01CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

Excavation to the required line & level shall be done as per the job procedure for excavation.

The so excavated bed shall be rammed properly & hollows shall be cut at th.e required position to receive the socket of the pipes.

The pipes shall be inspected carefully & broken or cracked pipes shall be rejected. After proper inspection the pipes shall be lowered carefully without any type of damage.

The Pipes shall be aligned & leveled properly care shall be taken in laying that the socket of the pipe shall face the up-stream side.

After laying the pipe to the required line & level the joint shall he caulked properly, first by bitumen impregnated jute and then by cement mortar of proportion 1:2

The pipeline shall be tested for water tightness by filling with water upto a level 1.5 in above the top of pipe. The above list are applicable if the pipe are said for sewer line, drain line etc.

Page 107: QAM-VSB-02

JOB PROCEDURE FOR ATT Doc. No. NCC/CWG 2010 /JP-27PROJECT: COMMONWEALTH GAME 2010, D.U.

NORTH CAMPUS PMC : ENGINEERS INDIA LIMITED Rev. No.01

CONTRACTOR : NAGARJUNA CONSTRUCTION COMPANY LIMITED

1. PURPOSE

The purpose of this procedure is to:

1) Provide a well-defined, uniform and predetermined procedure for proper guidance of execution of Anti-Termite Treatment.

2) Provide guideline for record keeping

3) Minimize the errors

4) Control of non conformance.

2. SCOPE

The scope of work includes the various activities related to anti-Termite Treatment. This procedure establishes the quality of material to he used over ground, floors and wall.

3. REFERENCE DOCUMENTS

Method Statement / CPWD Specification

4. DETAIL ACTION PLAN

Site Preparation

Prior to start of chemical treatment area(s) shall be made free from logs, stumps, timber off cuts, leveling pegs, roots of plants/trees etc. Soil treatment shall start when foundation trenches/pits are ready to take concrete/masonry on foundations and plinth area ready for laying the sub grade. Treatment shall not be carried out when it is raining or the subsoil water level is at the same or higher grade than the level of treatment. On the event of water logging of foundations. The water shall be pumped out and the chemical emulsion applied when the soil is absorbent.

Treatment of the excavated pits/trenches and backfill for foundation

The bottom surface and the lower 300mm. side surface of the excavated pits/trenches for foundations of masonry works and RCC plinth beams supporting such masonry works shall be treated with specified chemical emulsion 5 liters/Sqm. of the surface area. However, no such treatment shall be required in case of pits. Trenches made from RCC foundations supporting walls.

On completion of construction of masonry foundation the backfill in immediate contact with the substructure shall be treated in layers, of 300mm, with emulsion @7.5 Itrs/Sqm of the vertical surface of the sub-structure (i.e. 7.5X.3002.25 liters/meter of perimeter) for each side. The treatment shall he given after ramming of each layer of soil, by roding the earth at 150 mm centers close.

Page 108: QAM-VSB-02

To the wall surface and working the rod backward and forward (parallel to the wall surface) arid then spraying the specified dosage of emulsion

Page 109: QAM-VSB-02

directed towards the masonry surfaces so that the soil in contract with these surfaces in well treated with the chemical. After the treatment, the soil shall be tamped back into place. This shall be done for full depth of the fill.

For RCC walls and columns, the treatment as specified above shall start from a depth 500mm below the finished ground level, and shall be gone up to the FGL.

Treatment of Plinth/Basement and Apron

The top surface of the consolidated earth below the non-suspended floor slabs and the peripheral, aprons of widths up to 750mm, the bottom surface and side surfaces of the excavated pits for the basements shall he treated with chemical emulsion @ 5 liters/Sqm. of the surface area. Holes 50 to 75 mm deep at 150 mm centers, both ways. shall he made on the surface with 12 mm diameter mild steel rod and then emulsion shall, be sprayed uniformly over the area. At expansion joint locations, anti-termite treatment shall be supplemented by treating through the expansion joint @. 2.0 liters per linear meter of joint after the sub grade has been laid.

Treatment of Junctions of Plinth Filling Sand Wall/Column Faces shall he done after making a small channel 3OmmX3Omrn by making rod holes 150mm apart(up to the ground level) in the channel and then by moving the rod backward and forward to break up the earth. The chemical emulsion shall be poured along the channel (ZI 7.5 liters/Sqm. of the vertical wall/Column surface so as to soak the soil right to the bottom. The soil shall he tamped back into place after the treatment.

Treatment of Soil along External Perimeter of Building.

After the building is complete, the earth along the external perimeter shall be rodded at intervals of 150mm and to depth of 300mm. The rod shall be moved backward and forward. Parallel to the wall to break up the earth and chemical emulsion poured along the wall 7.5 liters/Sqm. of vertical surface (i.e. 7.5X0.300 = 2.25 liters/meter of perimeter). After the treatment, the earth shall be tamped back into place. Mixing shall he done as per manufacturing of approved company.

Page 110: QAM-VSB-02

FORMATS