    ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440.

    ROUTING SUPER-HEAVY VEHICLES USING

    ARCVIEW GIS

    Octavio Melchor-Lucero & Roberto A. Osegueda

    The University of Texas-El Paso developed a GIS for Texas DOT to automate the routing of super-

    heavy vehicles. The GIS uses a network representation of the highways with attributes linking to a bridge

    information database. Given vehicle characteristics and points of origin and destiny, shortest paths and

    bridges along routes are found. Information is retrieved from the database and bridge adequacy is

    evaluated from established formulae. Network segments containing inadequate bridges are disabled and

    new paths are searched repeating the process until a suitable route is found. Information management

    issues are addressed that may benefit the transportation community.

    Background and Objective

    The Motor Carrier Division (MCD) of the Texas Department of Transportation (TxDOT) is the agency

    that issues permits for overweight and oversize vehicles traveling through the state highways (see Figure 1)

    These are referred to as the On-system highways. With the continuing increase in commerce and trade in

    Texas, the MCD continues to experience increases in the number of permits issued for these types of

    vehicles. Some of thepermit requests are for super-heavy loads, that is vehicles in excess of 300,000

    pounds up to one mi lionpounds.

    Figure 1. Typical super-heavy vehicle (Courtesy of MCD, TxDOT).

    The customary procedure for processing these requests is time consuming and costly. The process consists

    a) manualy establishing a tentative

    route,b) identifying all the bridges on

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    2/42

    ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    the route,

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    3/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 3

    ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    c) obtaining the information of the bridges to be crossed;

    d) analyzing for the structural adequacy of the bridge for the super-heavy vehicle.

    Alternate routes are investigated, as some bridge structures are found inadequate. As an effort of

    reducing the time to process the permits, it is becoming customary to re-use portions of routes already

    analyzed for greater loads. This approach may cause future infrastructure problems due to repeated

    overloads.

    The current permitting procedure followed by MCD is based on the rules and regulations for

    movement ofoversize/overweight loads governed by the Texas Administrative Code [1] (TAC).

    These regulations limit the loads based on a gross axle weight criterion (which depends on the number of

    axlesper axle group) and a tire pressure criteria of 650 pounds per inch of tire width, except for special

    vehicles such as mobile cranes where the pressure criteria is 850 pounds perinch.

    If either criterion is exceeded, TxDOT's Design Division performs an analysis of the bridges along the

    vehicle's route to determine if a permit may sti l be issued. The significant drawback of analyzing each

    bridge is that the engineering efforts are time consuming and costly.

    TxDOT sponsored research aimed at developing guidelines for effective general procedures for issuing

    permits for super-heavy vehicles passing through Texas. Two different types of formulae were developed

    forbridges exceeding or reduced to designations other than H15, H20, HS-15 and HS-20 (i.e. HX or

    HSX):

    1) a general formula, not dependant on the bridge span length, and

    2) a bridge-specific formula that accounts for the bridge span length.

    The bridge load formulae (BLF) developed at TTI [2] were found suitable for implementation in an

    automated route evaluation system.

    This paper describes the development of an operational Geographic Information System (GIS) to route

    super- heavy and oversize vehicles on the Texas highways using ArcView software.

    Components fora Route Evaluation GIS

    To develop the proposed GIS a series of requirements were defined and a thorough survey wasperformed to identify the available information.

    Required basic components:

    1) A highway network model representing the On-system roads, developed from digitized map

    containing at least a classification of highways, e.g. Interstate highways, State highways, Farm t

    Market roads, etc. and their corresponding designations. Other desired features include direction

    of travel and road mileagepreferably in database format;

    2) A bridge network coverage with a access to a comprehensive series of attributes such a

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    4/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 4

    ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    bridge identification, number of spans, span lengths, design ratings;

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    5/42

    16/07/13 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 5

    3) A route evaluation model to handle heavy-loads and

    3) GIS software suitable for transportation

    modeling. Selected resources identified during the

    survey:

    1) Use TxDOTs official digitized County/Urban maps available from the Mapping Office othe Transportation Planning and Programming Division (TPP) in Intergraph's DGN format. Th

    primary reason for selecting these drawings was the completeness and comprehensiv

    amount of details, containing the geometric characteristics of overpasses, underpasse

    interchanges and exit ramps, needed to perform a comprehensive routing through the On

    system roads. The geographic features are classified and organized in 64 layers. One of th

    layers contains the symbols representing the location ofbridges. A limited database containing

    few highway names was available and was linked to the maps.

    2) Use TxDOT's Bride Inventory Inspection and Appraisal Program (BRINSAP) database

    BRINSAP was the only bridge database available with sufficient bridge geometry data, includin

    the geographic locations in world coordinates format. The database is available in MS Acces

    format.

    3) Use ArcView GIS software to develop the routing application.

    3) Implement within the routing model, both the rules adopted by MCD and the developed bridg

    formulae to determine the feasibility of issuing a permit for heavy/overdimensional vehicles.

    Two critical elements for the success of the routing GIS were:

    a) to account for a l bridges along a given route, and

    b) to have an accurate road network model that includes traffic flow directions.

    Geographic Data: Problems and Solutions

    The GIS routing application mainly requires two coverages. One consists of a line coverage with the On-

    system roads and a point coverage representing the bridge locations. Additional, non-required line

    coverages maybe created for spatial reference of the roads and bridges. These include a bridge symbols

    coverage and a city streetscoverage.

    A l line coverages were created, exporting the corresponding layers in the TxDOT County/Urban file

    drawings and converting them into the GIS coverages. The bridge locations were mapped into a point GIS

    coverage using the longitude and latitude coordinates of the bridges stored in BRINSAP.

    After superimposing a l coverages, several problems were identified. The bridge coverage showed several

    bridge location problems, including incorrect/offset bridge coordinates or missing coordinates (see Figure

    2). The database was further explored for completeness of information and as a result, occasional missing

    attributes (e.g. span lengths, ratings, etc.) were observed for some records.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    6/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 6

    16/07/13 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    Figure 2. Problems with bridge coordinates.

    On the other hand, the roads coverage required significant amount of processing to convert it into a

    networkmodel. Typical problems encountered include: duplicate line segments, undershoots, overshoots,

    crossoverwithout connection and disconnectivity (see Figure 3). Moreover, the only attributes available

    include the highway names, which are only attributed to the centerlines of divided highways, and travel

    directions were not available.

    Figure 3. Problems with road network connectivity.

    Other occasional problems include missing bridge symbols and geographic features a located in different

    layers with respect to their corresponding ones.

    Corrective measures were conducted to prepare the road network for routing. The corrections were

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    7/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 7

    16/07/13 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    accomplished by re-importing a l previously mentioned geographic features from the County/Urban files

    into a third party GIS software.

    The corrective measures include:

    An exhaustive verification ofbridge locations

    The locations were verified using database information in BRINSAP and printed

    maps. The bridge locations were corrected by editing the points to its correct

    location.

    Prepare the road network for routingby correcting connectivityproblems

    Eliminate repeated line segments, fix overshoots and undershoots

    Complete the road database attributes

    Assign highway names and directions of travel to divided highways, one-way roads,

    interchanges and exit ramps.

    Define overpasses/underpass at intersections.

    Create a relational database between the road networkand the bridge database

    Assign bridge structure number to corresponding road segments to automatica ly identify

    bridges as functions of vehicle routes.

    The road network preprocessing was accomplished using previously developed custom-made macros thasemi- automated the editing tasks. During the preprocessing phase, the database structures of the GIS

    coverages were slightly altered to accommodate for compatibility with the software.

    The GIS conversion process as we l as the corrective strategies is described in detail in reference [3]

    since it isbeyond the scope of thispaper.

    Route Evaluation Methodology

    As stated earlier, the MCD verifies that the maximum legal weights are met, to determine the feasibility ofissuing a travel permit for a given vehicle. The disadvantage of this criteria is that it only considers the

    vehicle axle loads and configuration, ignoring bridge geometry and type.

    To avoid the excessively long waiting periods and expensive structural analyses of a l the bridges

    along aproposed route, a set of bridge load formulae were developed.

    In general, the criteria to determine a routes adequacy is as fo

    lows:

    a. evaluate the vehicle against TAC requirements;

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    8/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 8

    16/07/13 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEWb. propose a route where a l bridge clearances (vertical and horizontal) are met;

    c. check load postedbridges;

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    9/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 9

    16/07/13 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW

    d. if TAC requirements are not met, evaluate the load-carrying capacity applying the

    BLF. BRINSAP includes several fields where bridge data is co lected, stored and updated

    periodica ly. Some of the bridge information includes:

    Bridge structure numbers as identifiers

    Minimum underneath vertical clearance

    Total horizontal clearance (over and underneath)

    Number of bridge spans

    Total bridge length

    Length of largest span

    Bridge type (simple orcontinuous)

    HX or HSX operating rating

    Considering the available bridge information, and that the information can be retrieved from BRINSAP,

    sincebridges can be identified as a function of traveled routes through the bridge structure identification

    numbers (SN) attributed to the road segments of the network, the aforementioned route adequacy

    evaluation process can easilybe implemented in the proposed automated routing system.

    Legal Weight Limits (TAC Restrictions)

    The Texas Rules and Regulations under the TAC specify various limits in vehicle size and weight fo

    movement of oversize/overweight vehicles. The fo lowing is a summary of the axle group weight limits

    lowed forissuingpermits that are in excess of the maximum legal weights.

    Table 1. TAC Axle Group Weight Restrictions

    Number

    of Axles

    per

    Group

    Maximum

    Allowable Axle

    GroupWeight

    (Kips )

    Maximum Dis

    tance Between

    Extremes of any

    Group of

    Two or MoreAxles

    (Feet)

    Maximu

    m Legal

    Loads

    (Kips )

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    10/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440.

    16/07/13 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW1 25.0 - 20

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    11/42

    2 45.0 10 34

    3 60.0 32 42

    4 70.0 51 50

    5 81.4 51 58

    Alternative Bridge Load Formulae

    The bridge load formulae developed by Keating et al [2] determines the maximum a lowable loads for the

    axles groups associated with a given vehicle. A brief overview of the formulation fo lows.

    The maximum a lowable axle group weight as defined by Equation (1) is corrected by incorporating

    reduction factors that account for gage distance and number of tires per axle. Equation (3) defines a

    general formula to limit the weight of any group of axles by the bridge design type and the group

    wheelbase; while equation (4) defines a bridge-specific formula that in addition to the above factors

    also accounts for the span length ofthe bridge.

    (1)

    where:

    GWrev = Revised axle group weight, kN (kips);

    Si = reduction factor for each axle with more than four tires peraxle;

    1.0 for axles with four tires orfewer;

    0.96 for axles with eight or more tires;

    n = number ofaxles;

    Ri = reduction factor accounting for gages wider than 1.8 m (6 ft.) calculated by the folowing formula;

    (2)

    GW = axle group weight, kN (k), calculated from either equations (3) or (4 and 5):

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    12/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 8

    GW = ( a + b WBrev) X (3)

    GW = w * WBrev (4)

    (5)

    where:

    w = a lowable distributed load, kN/m

    (k/ft.); L = span length, m (ft.);

    WBL = WBrev , m (ft.) when WB = L;

    X = design rating of thebridge;

    a,b,c,d = regression constants (see Tables 2 and 3 or Osegueda et al 1999)

    [4]; WBrev = revised wheelbase, m (ft.);

    The revised wheelbase is defined in equation (6) as:

    (6)

    where:

    WB = vehicle wheelbase, m (ft.);

    b = correction factor for concentrated loadings;

    1.0 for continuous spanbridges;

    defined for simple span bridges as the lesser of Equations (7 or8):

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    13/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 9

    (7)

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    14/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    (8)

    where:

    D = distance between the center of gravity and nearest axle, m

    (ft.); GD = greatest distance between any of two axles, m (ft.).

    Table 2. Constants for General Formula

    Bridge type Impact a b

    0% 17.83 - 0.034X 1.973 - 0.0119X

    (4.009 - 0.0077X) (0.1265 - 0.0012X)

    HX 10% 16.21 - 0.031X 1.804 - 0.0172X

    (3.645 - 0.007X) (0.1157 - 0.0011X)

    30% 12.81 - 0.027X 1.684 - 0.016X

    (2.88 - 0.006X) (0.108 - 0.001X)

    HSX 0% 0.0 3.103 - 0.016X

    0.0 (0.199 - 0.001X)

    WB < 11.6 m 10% 14.45 + 0.0013X 2.791 - 0.013X

    (WB < 38 ft.) (3.249 + 0.0003X) (0.179 - 0.0008X)

    30% 13.08 - 0.0623X 2.136 + 0.0062X

    (2.94 - 0.014X) (0.137 + 0.0004X)

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    15/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    HSX 0% 35.52 - 0.0342X 1.380 - 0.016X

    (7.985 - 0.0077X) (0.0885 - 0.001X)

    WB < 11.6 m 10% 32.27 - 0.0756X 1.258 - 0.014X

    (WB < 38 ft.) (7.255 - 0.017X) (0.0807 - 0.0009X)

    30% 24.64 + 0.0356X 1.325 - 0.016X

    (5.54 + 0.008X) (0.085 - 0.001X)

    Table 3. Constants forBridge-SpecificFormula

    BridgeType

    Impact a b c d

    0% 2.262 - 0.0204X 0.0 459.1 - 1.376X 225.5 + 0.994X

    (0.155 - 0.0014X) 0.0 (-1111 - 3.33X) (166.3 + 0.733X)

    HX 10% 2.320 - 0.0350X 0.0 442.5 + 0.4835X 202.7 - 0.949X

    (0.159 - 0.0024X) 0.0 (-1071 + 1.17X) (149.5 + 0.7X)

    30% 1.883 - 0.0175X 0.0 281.8 - 1.405X 143.4 - 1.36X

    (0.129 - 0.0012X) 0.0 (-682 - 3.4X) (105 + X)

    0% 0.7588 - 0.0623X 126.3 - 2.85X 1771 - 52.89X 835.1 + 24.63X

    (0.052 - 0.0043X) (28.4 - 0.64X) (4287 - 128X) (-616 + 18.17X)

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    16/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 12

    HSX 10% 0.861 - 0.0204X 59.16 + 0.22X 556.1 + 4.13X 264.4 - 2.350X

    (0.059 - 0.0014X) (13.3 + 0.05X) (1370 + 10X) (-195 - 1.733X)

    30% 0.730 56.49 - 0.5916X 633.1 - 10.99X 295.6 + 4.61X

    0.05 (12.7 - 0.133X) (1532 - 26.6X) (-218 + 3.4X)

    BLF Evaluation Procedure

    The BLF evaluation procedure requires a description of the vehicle that

    includes:

    a) number ofaxles;

    b) location of each axle, e.g. steering axle is located at the origin (0.0) of the reference axis;

    c) gage of each axle ;

    d) weight of each axle ;

    e) number of tires, and

    f) tire width (assumed the same peraxle).

    This information is used to determine several parameters such as the center of gravity of the vehicle, and

    the gage and tire reduction factors (R and S).

    In addition, an impact factor needs to be selected to enable the selection of the proper regression constants.

    The impact factor value depends on the vehicle' speed while crossing a bridge. Three options are

    available: {0%,

    10% and 30%}.

    For example, a 0% factor should be selected, if the vehicle is assigned an escort, or its speed is restricted

    to less than 5 km/hr (3 mph). An impact factor of 10% is recommended for most cases when the speed is

    restricted to approximate a smooth walking speed as a condition of issuance. In addition to this speed

    restriction, no

    stopping, starting, or gear changing of the pu ling truck is a lowed while the load is on the bridge. If the

    speed ofthe vehicle cannot be contro led or monitored, a maximum impact factor of 30% should be used.

    As mentioned before, BRINSAP contains the necessary bridge data to use the formulation and can be

    accessed and retrieved easily, such as the number of spans and the operating rating.

    If the number of spans is three or more, the general" BLF is used. Otherwise, the specific BLF is

    applied on each bridge span.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    17/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    For a detailed description of the BLF evaluation procedure refer to Osegueda et al 1999

    [4].

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    18/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 14

    Routing Application in ArcView

    After preparing the road network for routing by correcting a l connectivity problems and completing road

    attributes and having established a link between the roads and BRINSAP, the next step is to develop the

    routing application in the ArcView platform for the PC environment.

    Key Elements Base Software

    ArcView 3.0a was selected as the GIS software package to develop the proposed routing application

    Recently, it has been upgraded to v3.2. ArcView has a number of built-in tools that a low visualization

    query and analysis of geographic data and has its own integrated object-oriented programming (OOP

    language (Avenue).

    ArcView does not have an integrated capability for routing analysis.

    NetworkAnalysis Extension

    To overcome the routing analysis limitation in ArcView, a separate extension is available as an add-on

    program that enables the solution of problems using geographic networks. The Network Analyst

    extension v.1.0a includes advanced tools that can be accessed through Avenue scripts and it a lows

    delivery ofsophisticated

    network analysis applications. The Network Analyst (NA) extension can find the most direct route

    between two locations and generate detailed directions across the route. It can also do point-to-point

    routing (also known as mid-arc routing), as opposed to endpoint-to-endpoint routing. The NA needs to be

    loaded into ArcView to add the Avenue classes that enable routing analysis.

    Program Interface

    Since ArcView has the capability of establishing a communication with another application throug

    Dynamic Data Exchange (DDE), a Visual Basic (VB) program was envisioned to execute the main step

    in the routing evaluation process and minimize computation time compared to the time it would take

    implemented in ArcView alone.

    Visual Basic also has de capability of accessing PC-based databases using Microsoft Jet database

    engine through data access objects (DAO) method. BRINSAPs original format is in MicrosoftAccess, which is a suitable format for DAO use.

    The communication capabilities between ArcView and MS Access via Visual Basic promoted the

    idea ofdeveloping an interface that would link a l three for the routing application.

    Geographic Data Prepared forRouting

    To perform routing analysis in ArcView using the Network Analyst extension, a system of interconnected

    linearfeatures (network) is required. The road network previously prepared for routing is exported in

    Esri shapefile format, along with other geographic features and then imported into ArcView.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    19/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    The geographic features imported into themes

    include:

    a) The On-System roads (ROADS) represented by line

    features.b) The bridges (BRINSAP) represented bypoints.

    c) The bridge symbols (SYMBOLS) as line

    features.

    d) The endpoints of the road segments (ENDPOINTS imported separately from the line

    layer). e) The political boundaries layer(D12BND).

    f) And, the streets of the individual counties (e.g. 020STR, 080STR,

    etc.)

    Only the ROADS theme is required to generate a highway network on which the routing analysis i

    performed. The other themes are used as visual reference to aid in the location of geographic featuresWhen the ROADS coverage is imported into ArcView, the corresponding endpoints to the line segment

    are not associated to them since a shapefile is non-topological; therefore, theyre imported separately.

    Pathpoints Definition

    Theme

    To avoid the limitation of performing endpoint-to-endpoint routing and for the practical purpose of savin

    the set of pathpoints (origin and destination of travel) separately, a new point theme (OD) is required. I

    this theme, thepathpoint locations are identified bypoints.

    A l themes mentioned above complete the composition of the view or map used for routing in

    ArcView.

    NetworkRules and Modifications

    The Network Analyst extension requires that a set of specific rules be observed when workin

    networkproblems to obtain solutions that are more realistic. For example, identifying traveling direction

    and representing the cost of traversing each line feature. The roads theme table was modified to accoun

    for the incorporation ofthese rules.

    Five fields were created and populated either to enable-disable the flow of traffic in the network

    or to facilitate the extraction of field information or as backup of existing information. These include:

    1. ONEWAY : backup of traffic flow directions;

    2. HWYINFO : backup of traffic headings and highway identification;

    3. OPbackup : backup of a l overpass bridges attributed to each road segment;

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    20/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    4. UPbackup : backup of a l underpass bridges attributed to each road segment;

    5. Costbackup : backup of the road segment length.

    During the conversion of the Urban files into GIS format, a directional field (Dir) is automatica ly

    created

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    21/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    containing topological directions represented by numeric values (1,1 and 2). Those values are updated

    during the preparation of the network when directional flows are assigned using a pre-existing macro

    (see Reference [3]). Since NA requires that the roads theme contain a field to handle traffic flow

    directions using alphanumeric characters (TF, FT, B, N), the ONEWAY field was created to convert the

    assigned travel directions from numeric to alphanumeric.

    The fields HWYINFO, OPbackup and UPbackup were created to facilitate the extraction of the

    information from the Roads table, since occasiona ly, some ce ls are blank and the incorrect values maybe retrieved. The Costbackup field was created for future reference.

    These fields are checked for existence each time the application is executed.

    Two existing fields were set an alias to a low the NA to recognize them and extract their contents

    during the analysis and reporting phases. These are:

    1. Highway_id (alias ROADNAME)

    2. Length (alias MILES)

    Travel cost and connectivity information for the generated network, is kept in a network index

    directory automatica ly created and maintained byNA.

    Steps to Solve a Routing Problem

    According to the authors, the solution to the routing problem for super-heavy and/or oversize vehicles in

    ArcView using the Network Analyst extension consists of four basic steps:

    After verifying that the NA and any other extensions are loaded into ArcView as we l as thecorrespondingproject file:

    1) Initialize the NetworkObject

    Specify the Roads theme as the line theme from which the networkwi l be created.

    Verify feasibility of performing network analysis on the Roads theme.

    Build the topology to create the NetworkObject.

    Specify the cost field from which the length of each segment is read (e.g. MILES).

    2) Specify the locations of the pathpoints in the corresponding point theme (OD theme)

    Enable editing capabilities in OD theme.

    Either create new points or move existing ones to the desired locations.

    3) Provide a description of the vehicle (dimensions and axle configuration).

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    22/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    Read from a text file or enter/modify the description and/or save it to a text file.

    4) Solve for a feasible shortest path and report.

    Check the location of the points against a preset tolerance to indicate whether theyre on

    orclose enough to the network. If they are within tolerance, retrieve the geographic

    coordinates.

    Create a graphic representing the route and find the corresponding segment records in the

    roads table.

    Evaluate each bridge attributed to the road segments for clearance and weight constraints

    (according to TAC and/or

    BLF).

    Close to traffic road records with bridges that do not meet any of the criteria.

    Rebuild the topology and search for a new path OR display the final route (ifany)

    Write search results into a report.

    These steps can be automated using an interface program that ca ls Avenue commands and execute

    Visual Basic code. The fo lowing section briefly describes the set of scripts written to perform repetitiv

    GIS tasks and customize the routing application.

    Automation and Customization

    Automat

    ion

    Several scripts were written in Avenue language to automate and control the sequence of execution of a

    numberof repetitive tasks that range from loading the view, initializing the themes and corresponding

    attribute tables, initializing the highway network, and retrieving the geographic coordinates to searching

    for a path, retrieving road link attributes, closing links to traffic and finalizing the search.

    The fo lowing is a list of scripts used in the overweight routing application and a brief description of

    the tasks performed:

    1. Load.map : verifies the existence of the required themes and creates the view

    2. Load.theme : loads the themes into the view

    3. Load.scripts : loads a l the scripts related to overweight routing (scripts with an ovrprefi

    4. Load.project : ca ls the previous three scripts

    5. Load4 : loads the previous four scripts into the script manager

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    23/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    6. Ovr.initialize_for_ovr : initializes the view document for routing analysis

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    24/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    7. Ovr.backup_fields : verifies the existence of fields created to comply with rules required to

    8.

    networkanalysis)

    Ovr.dde : launches a VB program and establishes DDE communication

    9. Ovr.main : main script that ca ls the previous three scripts sequentia ly

    10. Ovr.pathremove : remove themes with previous route solutions

    11. Ovr.getcleargraphics : removes a l graphical elements (tentative routes) in the view

    12. Ovr.ini_dir : initializes traffic flow directions in the roads table

    13. Ovr.network_topology : verifies feasibility of performing network analysis and builds the

    network topology

    14. Ovr.get_cost_fields : sets the cost field and the units for reportingpurposes

    15. Ovr.initialize_network : ca ls the previous five scripts

    16. Ovr.get_path_points : retrieves the geographic coordinates of the pathpoints

    17. Ovr.path_exists : verifies connectivity between two pathpoints

    18. Ovr.search_path : finds the shortest path between two pathpoints

    19. Ovr.pathmake : generates a theme after finding a route

    20. Ovr.readctyrd : retrieves county road identification number per road segment

    21. Ovr.getrdid : retrieves internal record number per road segment perroute

    22. Ovr.gethwyid : retrieves highway identification per road segment perroute

    23. Ovr.getdirhe : retrieves directional heading of traffic per road segment

    24. Ovr.gethwyinfo : ca ls the previous two scripts

    25. Ovr.getup : retrieves number of underpass bridges per road segment

    26. Ovr.getop : retrieves number of overpass bridges per road segment

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    25/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    27. Ovr.closetraf : writes an N to the directional field to close road segment to

    traffic

    28. Ovr.clearsel : clears the selected records from the Roads attribute

    table

    29. Ovr.finalize_search : generates final path report and displays it on theview

    30. Ovr.getODcount : reads the number of path points in the OD

    theme

    31. Ovr.getODinfo : retrieves the internal ID of each path

    point

    32. Ovr.getdisk : identifies the current disk

    drive

    33. Ovr.getinstdir : identifies the insta lation

    directory

    34. Ovr.gettempdir : identifies the temporary

    directory

    The first five scripts create the project from scratch and the remaining scripts relate to the execution of the

    routing application.

    Customization

    In addition, an extension named Ovr.avx was created to enable portability and delivery of the

    overweight routing application to work in ArcView. This extension adds a button component to

    ArcViews interface.

    When the extension is loaded into ArcView, the object button labeled [OVR] appears at the end of the

    buttonbar. Pressing this button starts running the overweight routing application. First, it initializes the

    view, verifies thepresence of backup fields in the Roads attribute table, and fina ly launches and

    establishes communication with the interface program described in the next section.

    VB Program Interface

    The authors decided to run the entire routing evaluation process by executing an external program

    launched from AV. The external program, written and compiled in Visual Basic 5.0, has the capability o

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    26/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    establishing and maintaining a DDE communication between AV and the bridge database (BRINSAP)

    The VB program is referred from now on as the OVRprogram.

    The main reason for developing the OVR program was to minimize computation time in the evaluation o

    the bridges in accordance to TAC requirements and BLF. In addition, programming dialog form

    would also be easily implemented.

    The OVR program is a toolbox with eight buttons and a panel that displays status messages (see Figur

    4). Each button has code that executes specific tasks within the toolbox (initialize variables, ca lsubroutines, open

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    27/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 1

    dialog boxes, perform mathematical calculations, etc.) and/or some code that requests ArcView to ru

    specific scripts (pertaining to visualization, query and analysis of geographic data) to obtain require

    information and pass it back for further analysis. A help file has also been included to assist the user in

    the flow of execution and to interpret the results.

    Figure 4. External VB program. Main toolbox.

    During a typical run of the routing application, both ArcView and the OVR program, may act as Client o

    Serverdepending on the stage ofexecution.

    For example, after pressing the OVR button, ArcView (client) launches the OVR program (server

    and establishes a DDE conversation between each other. By pressing some buttons in the OVR toolbox

    the OVRprogram (client) requests ArcView (server) to run scripts to initialize the network or retrieve th

    location ofthepath points or find the shortestpath.

    As mentioned before, a VB application can easily communicate directly with BRINSAP database i

    Access format. When the OVR program is launched, a communication channel opens the table wit

    corresponding bridge records (BRGON table containing On-system bridges). To rapidly access an

    retrieve the attributes (number of spans, span length, ratings, etc.) of a specific bridge recordBRINSAPs structure number field is previously indexed. The index is defined outside and befor

    opening the routing application.

    The considerable advantage of accessing the bridge attributes in BRINSAPs original format is that an

    updates to the attributes of the bridges wi l immediately be accounted for in the routing analysis. Th

    only drawback is that if some bridges are removed from the On-system table (BRGON), because they

    were closed to traffic orassigned to the Off-System jurisdiction, and the relational database between th

    roads network and BRINSAP is not updated accordingly, those bridges wi l not be accounted for in th

    routing analysis. Therefore, the version of BRINSAP must coincide with the one used to develop o

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    28/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    update the network.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    29/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    Typical Run

    To run a typical case, the fo lowing items are required:

    ArcView software v3.0a orlater,

    Network Analyst extension v1.0a orlater,

    ArcView project [e.g. Texas.apr] *,

    Customized extension [OVR.avx] that loads the OVR button, used to launch the externalprogram,

    External program executable [OVR.exe], and

    BRINSAP database (in Access format); version should correspond to current roads network.

    * The ArcView project consists of a view that contains the required themes for routing analysis

    (ROADS and OD), and any additional themes that aid in the identification of geographic features (e.g.BRINSAPbridge locations, Political boundaries, Streets, etc.) and the customized scripts (see Figure 5).

    Figure 5. Routing application interface.

    The main steps have been listed in the Steps to Solve a Routing Problem section. The fo lowing

    paragraphsprovide detailed information on each of the tasks performed after pressing the buttons in the

    toolbox.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    30/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 22

    Project initialization

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    31/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    Once the project is opened, clicking on the OVR button begins the initialization of the project. This

    includes:

    Verifying the presence of the themes needed to generate the network and define the path point

    (Roads and

    OD);

    Removing unwanted path themes (k_shp_xx.shp) created on previous runs that might have been save

    to the

    OVRproject;

    Preparing the Roads theme with the required fields and field names, to facilitate the extraction of

    information, and open the corresponding attributes table.

    Establishing the cost

    units.

    Launching the external program and establishing the DDE

    communication

    A soon as the toolbox is displayed on the screen, two events take

    place:

    A communication channel with the BRINSAP database is opened,

    and

    Vehicle configuration and other variables are

    initialized.

    Initialize the HighwayNetwork

    After project initialization and the OVR program has been invoked, the first step towards solving a

    routingproblem is to initialize the highway network. The network initialization consists in:

    Generating/regenerating the highway network

    topology.

    Enabling road segments that were closed to traffic in previous runs,

    and

    Identifying the cost field from which the total cost route wi l be reported. The default cost is th

    length of the road segment.

    During network initialization, the existing graphics representing trial routes generated in previous runs (if

    any) are deleted from the view and table records currently selected are deselected to initialize the Roads

    table.

    A status message is displayed in the panel after the network has been

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    32/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    initialized.

    Selection of

    Pathpoints

    The location of the origin and destination of the vehicle needs to be specified to be able to start

    searching fora route. The OD theme is included for definition of the location of thepathpoints.

    To define the location of the pathpoints, the OD point theme must be selected as the workingtheme and checked accordingly to enable viewing of the points that (wi l) represent the ODpair.

    Enable editing capabilities to the OD theme, to add or modify the location of the path points, usin

    ArcViews tools. Zoom in or out as needed. Save the edits on the theme to account for them in th

    routing analysis (see Figure 6).

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    33/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 22

    This version of the program does NOT support "intermediate" stop points where the vehicle could pass

    through,before reaching the specified destination.

    The retrieval of the geographic coordinates of the path points is accomplished through a customize

    script in

    ArcView, which is executed when clicking on the Select Path Points button in the

    toolbox.

    For every new problem to be solved, the location of the path points must be defined and

    retrieved.

    Figure 6. Pathpoint selection.

    Vehicle

    Information

    Next, a description of the characteristics of the vehicle is required. Two options areavailable:

    1. Read the vehicle description from an existing file.

    2. Enter a new vehicle description or modify an existing file.

    If the first option is selected, the user is prompted to select an existing text file with the vehicle

    information.

    By selecting to edit the vehicle description, several dialog boxes may appear prompting the user fo

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    34/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    pertinent data. Initial data includes: vehicle model, type, nominal capacity, height, width, total number o

    axles and the selection of an impact factor associated to the speed at which the vehicle is expected t

    cross the bridges. See the BLF Evaluation Procedure section for detailed information on the impac

    factor. The vehicle's total number of axles includes the tractor's axles as we l as the trailer's. Th

    parameters in these boxes are initialized if a new vehicle description is to be entered.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    35/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 24

    The axle configuration information consists of: distance from the previous axle (zero for the first o

    steering axle), total axle weight, number of tires in the axle, axle gage, and tire width (a l tires per axle ar

    assumed to have the same width). The axle gage is the distance measured between the centers of gravit

    of the two tire groups.

    If a new vehicle description has been entered or an existing description modified, the information can be

    saved to a text file, by clicking the "Save Vehicle Description" button (see Figure 7).

    Figure 7. Vehicle information editboxes.

    Route Search andReport

    Once a l the above steps have been executed, the search for a route that meets a l clearance anweight conditions may be initiated.

    To start searching for a route, verify that the Roads theme is the active theme, then press the Find

    Route / Report button and select an output file to write the search results. Some activity wi l b

    noticed in both ArcViews interface and the OVR programs panel. In ArcView, each time a shortest pat

    is found, the records corresponding to the selected road segments are highlighted in the Road

    attributes table, and a graphic representing the selected route is drawn on the view. In addition, a new

    path theme is added to the view.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    36/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    The OVR program retrieves attribute information from the Roads table, pertaining to each recor

    that corresponds to the path under evaluation. This information includes the structure numbers of th

    overpass and/orunderpass bridges (if any). Then BRINSAP is accessed to retrieve the correspondin

    bridge attributes (e.g.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    37/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    number of spans, span length, operating rating, etc.) for further evaluation. Several messages appea

    on the panel, reporting the status of the bridge evaluation (e.g. evaluation for vertical clearance, fo

    horizontal clearance, evaluation of TAC requirements or Bridge Load Formulae, etc).

    If a clearance or weight capacity condition is not met, the corresponding road record is closed to traffic

    If a route does not meet the criteria, the process iterates and a new search is initiated. The networ

    topology is re- generated to account for any road segments closed to traffic (see Figure8).

    Figure 8. Typical route search case.

    When the routing program finishes the route searching process, two possible outcomes can be

    expected:

    1. A route is found that meets the specified

    constraints.

    2. A route is NOT found for the specified vehicle and path

    points.

    If a feasible route is found, the path is highlighted (in randomly chosen colors). In either case, a fina

    report is generated.

    At this point, the run is completed and the user may choose to exit the application or continue with anothe

    case. The final report can be viewed using WordPad or NotePad. Three main sections can be identifie

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    38/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    in a typical

    routingreport.

    The first section at the beginning of the report describes the vehicle configuration and dimensions,

    reports the

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    39/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    impact factor selected and reports the computed center of gravity of the total vehicle

    load.

    The next section describes the results of the route search, including the geographic coordinates of th

    origin and destination pair specified on the view. The description for a found route include

    headings, highway ID's, mileage, and the cumulative mileage. If a route was not found, the possibl

    reasons are reported in the fo lowing sections. The total number of trial routes tested before the OVR

    application gives a result is also reported.

    The third and final section includes a list of disabled links with bridges that were avoided due to the

    different insufficiencies or problems encountered during the search. Depending on the type of problem

    encountered, the information is classified in five different categories:

    a) Bridges avoided due to insufficient vertical clearance.

    b) Bridges avoided due to insufficient horizontal

    clearance. c) Bridges avoided due to insufficient weight

    capacity.

    d) Bridges avoided due to missing information in BRINSAP,

    and e) Bridges avoided due to Load posting according to

    BRINSAP.

    The application does not include turn-penalty (intersections where long vehicles might be unable to make

    sharp turns) nor restricted access information (road sections under repair or closed to traffic for otherreasons). The disadvantage of not having this real-time information implemented is that the program may

    find unrealistic routes.

    Conclusions

    This paper documents the development of an ArcView application for routing of super-heavy an

    oversize vehicles using the Network Analyst extension. The procedure uses a network representatio

    of a system ofroads and bridges to identify feasible routes. The route evaluation methodology

    consistent with Texas Administrative Code regulations and uses bridge load formulae (BLF) tfurther analyze load-capacity to expedite the heavy/oversize vehicle permit process. The applicatio

    utilizes vehicle and bridge information to automatica ly search for the shortest path between an origin an

    a destination, closing to traffic a l road segments with inadequate bridges and locations of restricte

    clearances.

    The routing application features an external program, developed in Visual Basic that interfaces betwee

    ArcView and the bridge database.

    Problems with geographic information sources, interface details and a typical run are addressed. Inclusio

    ofrestricted access and turn-penalty information is yet to be implemented.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    40/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 2

    Acknowledgements

    This project was funded by the Texas Department of Transportation under studies 0-1482 and 0-1823

    The authors wish to express their appreciation to Mr. John Holt, Mr. Mike Lynch and Mr. Wi l Watso

    from DOT for their invaluable and continuous support.

  • 7/27/2019 ROUTING SUPER-HEAVY VEHICLES USING ARCVIEW GIS.doc

    41/42proceedings.esri.com/library/userconf/proc00/professional/papers/pap440/p440. 3

    A very special thanks to the NAFTA Intermodal Transportation Institute for providing additiona

    financial assistance to continue this research, and to the Center for Highway Materials Research fo

    supporting and encouraging this work.

    The authors would also like to acknowledge Dr. Alberto Garcia-Diaz from Texas A&M University, Dr

    CesarCarrasco and Dr. Suleiman Ashur from UTEP for their valuable contributions during the earl

    stages ofthe research.

    Fina ly, to a l the graduate and undergraduate students who participated, for their patience in the laborious

    tasks.

    References

    [1] Texas Administrative Code, 1992 Supplement, West Publishing Co., St. Paul, MN,

    (1992).

    [2] P.B. Keating, "Overweight Permit Rules," Research Report 1433-IF, Texas Transportation

    Institute, Texas A&M University, Co lege Station, TX. (1994).

    [3] R.A. Osegueda, et al., "Development of Automated Routing of Overweight/Oversize Vehicl

    System for

    Houston District," Report TX-96-1482-1, The University of Texas at El Paso, TX, April 1997.

    [4] R.A. Osegueda, et al., "GIS-Based Network Routing Procedures for Overweight and Oversize

    Vehicles," Journal of Transportation Engineering, July/August 1999.

    Octavio Melchor-Lucero

    MSCE Research Engineer

    m e lc h o r @ u te p.e du

    &

    Roberto A. Osegueda PhD,

    PE Professor

    o s e gu e d a @ u te p.e d

    u

    University Of Texas at El

    Paso

    Center for Highway Materials

    Research

    Civil Engineering

    Department

    500 W University

    Ave.

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]