Definition – Scheduling Agreement
A scheduling agreement is a longer-term arrangement with the vendor covering the supply of materials subject to predetermined conditions.
When to Use Scheduling Agreement
If your organization procures large quantities of material and the requirement is spread over a predefined period than you can make use of the scheduling agreement. In Our business process this can be used for in-house fabrication jobs. We can create one scheduling agreement for the entire financial year. We can keep adding line items as and when required for various projects.
Cont…..
These line items are similar to line items in purchase order where account assignment is WBS. Thus cost will be recognized accordingly. These scheduling agreements would be created separately for each Workshop. This release procedure is similar to Purchase order. After addition/ Modification of line item it will go for release. A scheduling agreement consists of a number of items, for each of which a procurement type is defined.
We can use Scheduling agreement for following procurement types
• Standard • Subcontracting
When to Use Scheduling Agreement Cont….
How to create Scheduling Agreement in SAP
Agreement Agreement type should type should
always be LPalways be LP
WorkshopWorkshop
Transaction Code – ME31LTransaction Code – ME31L
Validity End Validity End date of date of
agreementagreement
Enter Enter Payment Payment
TermTerm
How to create Scheduling Agreement in SAP Cont…
Enter Per unit Enter Per unit Value Value
Enter Tax Enter Tax codecode
How to Change Scheduling Agreement in SAP Cont…
Select Line item and click on Delivery Schedule Tab
How To Maintain Scheduling Agreement Schedule In SAP
Transaction Code – ME38Enter Scheduling Agreement No. and Press Enter
How To Maintain Scheduling Agreement How To Maintain Scheduling Agreement Schedule In SAP Cont…Schedule In SAP Cont…
Click on Delivery ScheduleClick on Delivery Schedule
Click on Create with reference to Purchase requisition
Click on Delivery Schedule
How To Maintain Scheduling Agreement Schedule In SAP Cont…
Enter Purchase requisition and Press Enter
How To Maintain Scheduling Agreement Schedule In SAP Cont…
Enter Purchase Enter Purchase Requisition NumberRequisition Number
Click on Adopt +DetailsClick on Adopt +Details
How To Maintain Scheduling Agreement Schedule In SAP Cont…
Transaction Code – ME38 (Maintain Scheduling Agreement Schedule)Save
Delivery Date Delivery Date Copied From P.R.Copied From P.R.
How To Maintain Scheduling Agreement How To Maintain Scheduling Agreement Schedule In SAP Cont…Schedule In SAP Cont…
Transaction Code – ME35L(Release Purchasing Documents)
How To Release Scheduling Agreement In SAP How To Release Scheduling Agreement In SAP
Transaction Code – ME35L
Click to releaseClick to release
How To Release Scheduling Agreement In SAP How To Release Scheduling Agreement In SAP Cont…Cont…
Transaction Code - MIGO
How To Do Good Receipt Against Scheduling How To Do Good Receipt Against Scheduling Agreement In SAPAgreement In SAP
How to view GR PO/GRN History In Scheduling How to view GR PO/GRN History In Scheduling Agreement in SAPAgreement in SAP
Transaction Code – ME32L
How To View GR PO/GRN History In Scheduling How To View GR PO/GRN History In Scheduling Agreement In SAP Cont…Agreement In SAP Cont…
If line item is added document will go for release
Transaction Code – ME32L
How to check Release of Scheduling How to check Release of Scheduling Agreement in SAP Agreement in SAP