Virtual Design and Construction Case Study Martin Fischer Cristina Garcia Calvin Kam John Kunz Kathleen Liston Marcus Schreyer Vibha Singhal. Source: DPR. Virtual Design and Construction Case Study. Case Overview Baseline Delay Acceleration Summary and Analysis. Site Plan. - PowerPoint PPT Presentation

Citation preview

Page 1: Source: DPR
Page 2: Source: DPR

Virtual Design and Construction Case Study

Martin FischerCristina Garcia

Calvin KamJohn Kunz

Kathleen ListonMarcus Schreyer

Vibha Singhal

Page 3: Source: DPR

Source: DPR

Page 4: Source: DPR

Virtual Design and Construction Case Study

Case Overview• Baseline• Delay• Acceleration• Summary and Analysis

Page 5: Source: DPR

Site Plan

Page 6: Source: DPR

Construction Photos and Site Context

Page 7: Source: DPR

Virtual Design and Construction Case Study

Case Overview• Baseline• Delay• Acceleration• Summary and Analysis

Page 8: Source: DPR

Site Plan

Page 9: Source: DPR

Construction Photos and Site Context

Page 10: Source: DPR

Virtual Design and Construction Case Study

Case Overview• Baseline• Delay• Acceleration• Summary and Analysis

Page 11: Source: DPR

Site Plan

Page 12: Source: DPR

Construction Photos and Site Context

Page 13: Source: DPR

Virtual Design and Construction Case Study

Case Overview• Baseline• Delay• Acceleration• Summary and Analysis

Page 14: Source: DPR

Site Plan

AP

AR

AT

Page 15: Source: DPR

Construction Photos and Site Context

Page 16: Source: DPR

Virtual Design and Construction Case Study

Case Overview• Baseline• Delay• Acceleration• Summary and Analysis

Page 17: Source: DPR

Common Point 4D Color Legend for iRoom Demo

SimVision Color Legend for iRoom Demo

Direct Work Hidden Work

Page 18: Source: DPR

3D Legend Diagram

Page 19: Source: DPR

Virtual Design and Construction Case Study

• Case Overview Baseline• Delay• Acceleration• Summary and Analysis

Page 20: Source: DPR

Baseline Case

• Target 2002 Thanksgiving and Christmas season• Tight site -> single crew per trade• Low coordination risk, but little slack

Page 21: Source: DPR

Functional Requirements (Time and Cost)Predicted

CompletionPredicted

Project Cost

Turnover Baseline Baseline

Overall Project 11/1/02 10/30/02 13,100$ 13,069$ slack (days) 2 99.8%

Bookstore 10/1/02 9/19/02 930$ 930$ slack (days) 12 100.0%

Retail 10/15/02 10/2/02 2,170$ 2,171$ slack (days) 13 100.0%

Theater 10/15/02 10/10/02 6,770$ 6,757$ slack (days) 5 99.8%

Required Dates

Budget

Date Legend:

Cost Legend: Below 1% Over BudgetOver Budget by more than 3%

Within Budget1-3% Over Budget

Up to 30-day lateMore than 50-day late31 to 50-day late

Ahead of Time$ (in thousands)

Page 22: Source: DPR

Virtual Design and Construction Case Study

• Case Overview Baseline• Delay• Acceleration• Summary and Analysis

Page 23: Source: DPR

DESCRIPTIVE (40%)

• When do we have access to retail zone AR-7?• Where are you placing the crane?

EXPLANATIVE (20%)• What drives the turnover date for the theater?

PREDICTIVE (10%) • Can we get access to the parking a week earlier?

EVALUATIVE (30%)• Which acceleration alternative is better?

How we spend time in meetings

Page 24: Source: DPR
Page 25: Source: DPR

4D Demo (Plan View)

Page 26: Source: DPR

4D Demo (Perspective View)

Page 27: Source: DPR

MSP and Time-Controller Demo

Page 28: Source: DPR

Virtual Design and Construction Case Study

• Case Overview Baseline• Delay• Acceleration• Summary and Analysis

Page 29: Source: DPR

SimVision Demo(highlights activity received from

MSP)

Page 30: Source: DPR

MSP sends activity to SimVision

Page 31: Source: DPR

Virtual Design and Construction Case Study

• Case Overview Baseline• Delay• Acceleration• Summary and Analysis

Page 32: Source: DPR

Micro View

Page 33: Source: DPR

Macro View—Organization and Process

Page 34: Source: DPR

Virtual Design and Construction Case Study

• Case Overview Baseline• Delay• Acceleration• Summary and Analysis

Page 35: Source: DPR

Predicted Critical Path

Predicted Work Composition

Page 36: Source: DPR

Schedule Growth Risk

Predicted Work Composition

Page 37: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline Delay• Acceleration• Summary and Analysis

Page 38: Source: DPR

Delay Case

• Hazardous materials found during excavation 2-month delay (MSP #56)

Page 39: Source: DPR
Page 40: Source: DPR

4D Demo (Baseline Case)

Page 41: Source: DPR

4D Demo (Delay Case)

Page 42: Source: DPR

MSP+Time Controller Demo(Delay Case)

Page 43: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline Delay• Acceleration• Summary and Analysis

Page 44: Source: DPR

Functional Requirements (Time)

Turnover Baseline Delay

Overall Project 11/1/02 10/30/02 1/8/03slack (days) 2 -68

Bookstore 10/1/02 9/19/02 11/25/02slack (days) 12 -55

Retail 10/15/02 10/2/02 12/10/02slack (days) 13 -56

Theater 10/15/02 10/10/02 12/11/02slack (days) 5 -57

Client Requirements

Predicted Completion Dates

Date Legend:

Cost Legend:

Up to 30-day lateMore than 50-day late31 to 50-day late

Ahead of Time

Page 45: Source: DPR

Functional Requirements (Cost)

Turnover Baseline Delay

Overall Project 13,100$ 13,069$ 13,171$

slack (days) 99.8% 100.5%

Bookstore 930$ 930$ 930$ slack (days) 100.0% 100.0%

Retail 2,170$ 2,171$ 2,171$ slack (days) 100.0% 100.0%

Theater 6,770$ 6,757$ 6,757$ slack (days) 99.8% 99.8%

Budget

Predicted Project Cost

Date Legend:

Cost Legend: Below 1% Over BudgetOver Budget by more than 3%

Within Budget1-3% Over Budget

$ (in thousands)

Page 46: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay Acceleration• Summary and Analysis

Page 47: Source: DPR

How to accelerate construction?

Page 48: Source: DPR
Page 49: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay Acceleration• Summary and Analysis

Page 50: Source: DPR

4D DemoOpportunities for Acceleration

Page 51: Source: DPR

MSP DemoOpportunities for Acceleration

Page 52: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay Acceleration• Summary and Analysis

Page 53: Source: DPR

Acceleration—Hybrid Case

Concrete Acceleration

• Add crew on pile caps and grade beams (MSP #85, 151)• Add horizontal formwork for soffits 2 and 3 (MSP #263, 270)• Reuse horizontal formwork for theater Lv3 (MSP #421, 428)• Rebar crew works overtime (11-hour day) • Add crew for bolt-up and welding

Steel Acceleration

• Add crew for fireproofing • Steel erection and slab-on-deck crews work overtime work (11-hour day)• MSP #708-737, 807-823

Page 54: Source: DPR
Page 55: Source: DPR

Concrete Acceleration

• Add crew on pile caps and grade beams (MSP #85, 151)• Add horizontal formwork for soffits 2 and 3 (MSP #263, 270)• Reuse horizontal formwork for theater Lv3 (MSP #421, 428)• Rebar crew works overtime (11-hour day) • Add crew for bolt-up and welding

Steel Acceleration

• Add crew for fireproofing • Steel erection and slab-on-deck crews work overtime work (11-hour day)• MSP #708-737, 807-823

Page 56: Source: DPR

4D Demo(Hybrid Acceleration)

Page 57: Source: DPR

MSP Demo(Hybrid Acceleration)

Page 58: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay Acceleration• Summary and Analysis

Page 59: Source: DPR

Predicted Critical Path

Predicted Work Composition

Page 60: Source: DPR

Position Backlog

Resource Allocation

Page 61: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay Acceleration• Summary and Analysis

Page 62: Source: DPR

Comparison of Predicted Finish Dates

Comparison of Predicted Work Composition

Hybrid Acceleration

Delay Case

Hybrid Acceleration

Delay Case

Page 63: Source: DPR

Comparison of Predicted Work Breakdown

Hybrid Acceleration

Delay Case

Page 64: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay• Acceleration Summary and Analysis

Page 65: Source: DPR

Functional Requirements (Time)

Turnover Baseline DelayConcrete

Accel.Steel Accel.

Hybrid Accel.

Overall Project 11/1/02 10/30/02 1/8/03 12/18/02 12/11/02 11/19/02slack (days) 2 -68 -47 -40 -18

Bookstore 10/1/02 9/19/02 11/25/02 11/5/02 10/29/02 10/9/02slack (days) 12 -55 -35 -28 -8

Retail 10/15/02 10/2/02 12/10/02 11/18/02 11/11/02 10/22/02slack (days) 13 -56 -34 -27 -7

Theater 10/15/02 10/10/02 12/11/02 11/12/02 11/20/02 10/24/02slack (days) 5 -57 -28 -36 -9

Legend:

Required Dates

Predicted Completion Dates

Up to 30-day lateMore than 50-day late31 to 50-day late

Ahead of Time

Page 66: Source: DPR

Functional Requirements (Cost)

$ (in thousands) Baseline DelayConcrete

Accel.Steel Accel.

Hybrid Accel.

Overall Project 13,100$ 13,069$ 13,171$ 13,410$ 13,491$ 13,649$

99.8% 100.5% 102.4% 103.0% 104.2%

Bookstore Turnover 930$ 930$ 930$ 931$ 970$ 971$ 100.0% 100.0% 100.1% 104.3% 104.4%

Retail Turnover 2,170$ 2,171$ 2,171$ 2,173$ 2,264$ 2,265$ 100.0% 100.0% 100.1% 104.3% 104.4%

Theater Turnover 6,770$ 6,757$ 6,757$ 6,941$ 6,906$ 7,091$ 99.8% 99.8% 102.5% 102.0% 104.7%

Legend:

Budget

Below 1% Over BudgetOver Budget by more than 3%

Predicted Project Cost

Within Budget1-3% Over Budget

Page 67: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay• Acceleration Summary and Analysis

Page 68: Source: DPR

Project Total Cost

$0

$2,000,000

$4,000,000

$6,000,000

$8,000,000

$10,000,000

$12,000,000

$14,000,000

$16,000,000

4/19/01 7/28/01 11/5/01 2/13/02 5/24/02 9/1/02 12/10/02 3/20/03

Finish Date

Co

st

BaselineDelayConcreteSteelHybrid

cost increases as schedule is shortened

Page 69: Source: DPR

Alternative Solution Trade-offs

$0

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

0 10 20 30 40 50 60

Recovered Days

Ad

dit

ion

al C

ost

Delay

Concrete

Steel

Hybrid

Page 70: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay• Acceleration Summary and Analysis

Page 71: Source: DPR

Project Total Cost

$0

$2,000,000

$4,000,000

$6,000,000

$8,000,000

$10,000,000

$12,000,000

$14,000,000

$16,000,000

4/19/01 7/28/01 11/5/01 2/13/02 5/24/02 9/1/02 12/10/02 3/20/03

Finish Date

Co

st

BaselineDelayConcreteSteelHybrid

cost increases as schedule is shortened

Page 72: Source: DPR

Acceleration Cost

0

10

20

30

40

50

60

$102,000 $341,312 $422,279 $580,093

Additional Cost

Re

co

ve

red

Da

ys

Hybrid

Steel

Concrete

Delay

Page 73: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay• Acceleration Summary and Analysis

Page 74: Source: DPR

ProductNo change(4D Model)

Acceleration is possible(MS Project)Acceleration costs money(Excel)

Coordination needs increase as schedule accelerates(SimVision)

Organization

Process

VDC(iRoom)

Summary of alternative analyses

Page 75: Source: DPR

The Macro Problem

Page 76: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay• Acceleration Summary and Analysis

Page 77: Source: DPR

to be the world’s premier academic research center for Virtual Design and Construction

• Virtual Design and Construction: develop and test new ways to model, visualize, analyze and evaluate the multi-disciplinary performance of design–construction projects to support explicit business objectives

• Education: increase awareness of the value and costs of strategic IT for practitioners and Stanford students

CIFE Mission

Page 78: Source: DPR

• Need: macro and micro problems require timely stakeholder involvement

• Tools available, effective, affordable– iRoom, 4D, organization, TEI, …

• Objectives and metrics exist– Management theory– Manufacturing

• Actions: 1. Plan your VDC implementation strategy2. Become CIFE member; plan pilot

RateBaseline

($K) ChangeYear-1

(K$)Revenue 100,000 2% 102,000Cost of contracted work 85% 85,000 -2.0% 84,660Cost of self-performed work 10% 10,000 2.0% 12,240Gross Margin 5,000 5,100Sales, G&A 2% 2,000 2,040IT investment 70Amortized costs of IT/yr 33% 23Net income 3,000 3,037Time to payback (years) 1.9Net Income change (%) 1.2

Call to Action for VDC

Page 79: Source: DPR

Virtual Design and Construction Case Study

• Case Overview• Baseline• Delay• Acceleration Summary and Analysis

Page 80: Source: DPR

• Build project model early, before committing large money or time

• What– Product, process, organization

• How: – Detailed: to show the product, process, organization

entities that use significant project time, money– Virtual: in the computer– Visual: multi-discipline, multi-view, for multiple

stakeholders– Objective-based: set and track explicit public objectives

VDC Big Ideas

Page 81: Source: DPR

• Need: macro and micro problems require timely stakeholder involvement

• Tools available, effective, affordable– iRoom, 4D, organization, TEI, …

• Objectives and metrics exist– Management theory– Manufacturing

• Actions: 1. Plan your VDC implementation strategy2. Become CIFE member; plan pilot

RateBaseline

($K) ChangeYear-1

(K$)Revenue 100,000 2% 102,000Cost of contracted work 85% 85,000 -2.0% 84,660Cost of self-performed work 10% 10,000 2.0% 12,240Gross Margin 5,000 5,100Sales, G&A 2% 2,000 2,040IT investment 70Amortized costs of IT/yr 33% 23Net income 3,000 3,037Time to payback (years) 1.9Net Income change (%) 1.2

Call to Action for VDC