222
Readings on APIICP650 Reading 9 - Q&A Practices My Pre-exam Self Study Notes 11 th March 2016 Charlie Chong/ Fion Zhang

Understanding API ICP653 Reading 9-Worksheet-6

Embed Size (px)

DESCRIPTION

Understanding api icp653 reading 9 worksheet-6

Citation preview

  • Readings on APIICP650 Reading 9 - Q&A PracticesMy Pre-exam Self Study Notes11th March 2016

    Charlie Chong/ Fion Zhang

  • Charlie Chong/ Fion Zhang

    Petroleum Tanks

  • Charlie Chong/ Fion Zhang

    Petroleum Tanks

  • Charlie Chong/ Fion Zhang

    Petroleum Tanks

  • API 653 Exam Administration -- Publications Effectivity Sheet FOR: November 2015, March 2016 and July 2016 Listed below are the effective editions of the publications required for this exam for the date(s) shown above. API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry, Second Edition, April 2011

    Charlie Chong/ Fion Zhang

  • ATTENTION: Only the following sections / mechanisms from RP 571 are included on the exam:

    1. Section 3, Definitions 2. Par. 4.2.7 Brittle Fracture 3. 4.2.16 Mechanical Fatigue 4. 4.3.2 Atmospheric Corrosion 5. 4.3.3 Corrosion Under insulation (CUI) 6. 4.3.8 Microbiologically Induced Corrosion (MIC) 7. 4.3.9 Soil Corrosion 8. 4.3.10 Caustic Corrosion 9. 4.5.1 Chloride Stress Corrosion Cracking (Cl-SCC) 10. 4.5.3 Caustic Stress Corrosion Cracking (Caustic Embrittlement) 11. 5.1.1.10 Sour Water Corrosion (Acidic) 12. 5.1.1.11 Sulfuric Acid Corrosion

    Charlie Chong/ Fion Zhang

  • Charlie Chong/ Fion Zhang

    API Recommended Practice 575, Inspection of Atmospheric and Low-Pressure Storage Tanks, Third Edition, April 2014

    API Recommended Practice 577 Welding Inspection and Metallurgy, Second Edition, December 2013

    API Standard 650, Welded Tanks for Oil Storage, Twelfth Edition, March 2013 with Addendum 1 (September 2014), Errata 1 (July 2013), andErrata 2 (December 2014).

    API Recommended Practice 651, Cathodic Protection of AbovegroundPetroleum Storage Tanks, Fourth Edition, September 2014.

    API Recommended Practice 652, Lining of Aboveground Petroleum Storage Tank Bottoms, Fourth Edition, September 2014

    API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction, Fifth Edition, November 2014.

  • Charlie Chong/ Fion Zhang

    American Society of Mechanical Engineers (ASME), Boiler and Pressure Vessel Code, 2013 Edition i. ASME Section V, Nondestructive Examination, Articles 1, 2, 6, 7 and

    23 (section SE-797 only) ii. Section IX, Welding and Brazing Qualifications (Welding Only)

    See end of this study note for API Official BOK

  • http://independent.academia.edu/CharlieChong1http://www.yumpu.com/zh/browse/user/charliechonghttp://issuu.com/charlieccchong

    Charlie Chong/ Fion Zhang

  • http://greekhouseoffonts.com/Charlie Chong/ Fion Zhang

  • Charlie Chong/ Fion Zhang

    The Magical Book of Tank Inspection ICP

  • Charlie Chong/ Fion Zhang

  • Charlie Chong/ Fion Zhang

  • Fion Zhang at Xitang11th March 2016

    Charlie Chong/ Fion Zhang

  • Charlie Chong/ Fion Zhang

    SME- Subject Matter Expert,. .http://cn.bing.com/videos/search?q=Walter+Lewin&FORM=HDRSC3https://www.youtube.com/channel/UCiEHVhv0SBMpP75JbzJShqw

  • Charlie Chong/ Fion Zhang

    Practice-01API 653 PREPARATORY COURSEFinal Exam Open Book

  • Charlie Chong/ Fion Zhang

    Q 1. Exclusive of corrosion allowance, what is the minimum nominal thickness for all new construction bottom plates?a. inchb. inchc. 3/16 inchd. 5/8 inch

    ANS: b

    Q 2. For new or repaired shell horizontal joints, how many radiographs shall be taken for each 50 feet of horizontal joint, not including those required at intersection of vertical and horizontal joints?a. 1b. 2c. 3d. 4

    ANS: a1st 10 and subsequent 200 without regards to the welders/operator

  • Charlie Chong/ Fion Zhang

    Q 3. The recommended minimum development time (penetrant testing )allowed for a material made of high temperature alloy is:a. 5 minb. 10 minc. 7 min (?)d. 60 minANS: b

    T-672 Penetration (Dwell) TimePenetration (dwell) time is critical. The minimum penetrationtime shall be as required in Table T-672 or asqualified by demonstration for specific applications.

  • Charlie Chong/ Fion Zhang

    Q 4. Select suitable Hole type (source side) penetrameter for following weld joint

    a) No 20b) No 25 (?)c) No 30d) None of the aboveANS: total thickness 1 3/16 used c

  • Charlie Chong/ Fion Zhang

    Q 5. If type of penetrameter is Q.4 is changed to wire type whatshall be the wire designation (wire diameter in inch)a. 0.025 (NO. 10)b. 0.016 (NO. 8)c. 0.032 (NO. 11)d. none of the above (?)ANS: a Set B/ wire #10

    Q 6. For steel plates and weld to be checked LP, what shall be thepenetration time for penetranta. 10 min for weld, 5 min for plateb. 5 min for bothc. 10 min for bothd. 5 min for weld, 10 min for plateANS: d

  • Charlie Chong/ Fion Zhang

    Q 7. After applying the developer the examiner checked four welds for surface defects after following period, weld A- after 5 minute, weld B after 10 minute, weld C was checked after 30 minutes and weld D after 65 minutes which of the weld were checked wronglya. weld A and Bb. weld C and Dc. weld D onlyd. weld A and D (?)ANS: not less than 10 min nor more than 60 min, answer C

  • Charlie Chong/ Fion Zhang

    Q 8. Following combination of base metal and welding electrode wasqualified by a certain PQRimpact testing is not required.Base Metal =SA 285 Gr C Plates, thkWelding electrode = AWS E 6015This PQR will qualify which of the following combination of basemetal- welding electrodes.

    a. 1 thk SA 515 Gr 60 plates, E 6013 electrodesb. 1 thk SA 285 GrC plates, E 6013 electrodesc. 1 thk plates SA 516 Gr 70, E 7018 electrodes (?)d. None of the aboveANS SA-283 C K02401 55 (380) P1SA-516 60 K02100 60/70 (415)(485) P1E6013 F2 SFA-5.1 EXX13E7018 F4 SFA-5.1 EXX18Over 38 (10), but less than 34 (19) qualified min 316 (5) / max 2TAnswer: a

  • Charlie Chong/ Fion Zhang

    Q 9. For MT examination by prod techniques the spacing betweenprods shall be betweena. 4 inch to 12 inchb. 4 inch to 10 inchc. 3 inch to 10 inchd. 3 inch to 8 inchANS: d

    Q 10. For a tank with 130 ft diameter thickness of top course workedout was td=5mm tt=4mm. What will be minimum nominal thickness provided for this course according to API 650 for anew tank?a. 3/16 (5mm)b. 1/4 (6mm)c. 5/16 (8mm)d. None of the aboveANS: ctd is the design shell thickness, in mm;tt is the hydrostatic test shell thickness, in mm;

  • Charlie Chong/ Fion Zhang

    Q 11. For a tank with diameter 100ft was found to have thickness reduction in a localized area. Minimum thickness observed (t2) was 1 inch. What will be the minimum vertical length of for the area?a. 40 inches b. 37 inchesc. 45 inches d. None of the aboveANS L =3.7(Dt2) = 37, used bQ 12. On a tank roof plate two corroded areas was observed at locations A and B for Location A, average thickness = 0.085 inches, area = 105 in2Location B, average thickness = 0.095 inches, Area = 105 in2your decision will be:a. Both A and B are within limitsb. Location A is OK, location B is art of limitsc. Both A and B are out of limitsd. Location B in OK, location A is out of limitsANS: d. min 0.09 in 100in2

  • Charlie Chong/ Fion Zhang

    Q 13. Hot tap connection is to be made on tank with following description shell plate thickness = inch. Design temperature =30F the plates were not tested for impact testing, (Consr. Code API 650-1974). What will be the maximum size of tapping connection?a. 8 inches NPSb. 6 inches NPSc. 10 inches NPSd. 4 inches NPSANS: d, for plate with unknown toughness. If toughness is known and acceptable 18 NPS allowed.Q 14. A replacement plate to be used on a shell thickness of 5/8 inch,on the second course of the tank. Thickness of first course andthird course is also 5/8 inch. Following 3 plates are availablewhich one is most suitable to be used as replacement plate.a. Plate thickness = b. Plate thickness = 5/8c. Plate thickness = 1/2d. Plate thickness = 1

    ANS: b

  • Charlie Chong/ Fion Zhang

    Q 15. A tank is having remaining corrosion allowance of 2.5mm andcorrosion rate of the shell is 0.1mm per year. What will beinspection interval for next ultrasonic thickness inspection fromoutside of the tank?a. 15 Yearsb. 12.5 Years (?)c. 10 Yearsd. 5 YearsANS: interval = 2.5/0.1 = 25 years, used 5 yr.. max. answer= d

    Q 16. Typical corroded areas on a shell plate are exhibited below infigure 1 with measured thickness in inches indicated on thesketch. The un-corroded thickness of the shell palte is 0.750inches and C.A is 0.125

    The total length of a arrow line drawn is 8 inches. The length of theline in each of the corroded areas A, B and C are 1.5, 0.8 and 0.5inches respectively.

  • Charlie Chong/ Fion Zhang

    Comment on the acceptability of the corroded condition.a. The pitting can be ignored as a case of widely scattered pitting as both

    pitting depth and dimensions are within limitsb. Not acceptable as size are not OK, total length of the pit dimensions is

    more than permittedc. The pitting can be ignored as a case of widely scattered pitting since depth

    are OKd. The pitting cannot be ignored as a case of widely scattered pitting since

    depth are not OK

    ANS Line of corroded area = 2.8in exceed 2 max.td = 0.625 / td = 0.3125, Pitmax is okNot acceptable. Answer b

  • Charlie Chong/ Fion Zhang

    Q 17. Two plates sample A and B were tested for longitudinal impacttesting. Following were results observed. They belonged toGroup No.1 as per API 650: Results of impact test for sample A were 18ft lb, 8ft lb, 16ft lb.sample B were 12ft lb, 14ft lb, 20 ft. lbYour assessment will be:a. sample A and B both OK b. sample A and B both to be re-testedc. sample B is OK, A shall be re-tested (?)d. sample a is OK, B shall be re-testedANS: G1, longitudinal 15 ft-lbf / transverse 13 ft-lbfA with sample less than 2/3, B with 2 specimen less than specified. Both not OK, answer: b

  • Charlie Chong/ Fion Zhang

    Q 18. For replacement to an existing 0.25 thick shell plate of an AST,another plate of 0.25 thickness to ASTM A36 is used. What should be the minimum clear distance between the outer edges of the adjacent butt welds of vertical and horizontal joints, respectively?a. 10 & 6b. 6 & 3c. 8 & 4d. 12 & 6ANS: b

  • Charlie Chong/ Fion Zhang

    Q 19. Repair of a 5/8 thick shell, using lapped (lap welded) patch plate of 1/8thick was carried out, without informing the Owner. Such a repair is not acceptable as per API standard 653, because:a. Owner had not specified use of patch plate repairsb. Lap patch plate of less than 3/16 is not permittedc. Lap patch plate repair on shell thickness more than above is not permittedd. All of aboveANS: d

    Q 20. As per API Standard 650, the offset between vertical seams of adjacent shells shall be a minimum distance of:a. 5 t, where t is the plate thickness of thicker shell course at the offsetb. 4t, where t is the plate thickness of thicker shell course at the offsetc. 3 t, where t is the plate thickness of thicker shell course at the offsetd. 2 t, where t is the plate thickness of thicker shell course at the offsetANS: a

  • Charlie Chong/ Fion Zhang

    Q 21. When butt welded annular bottom plates are used, in an ASTbuilt to API Standard 650, their width from inside of the shellshall be at least:a. 900 mmb. 300 mmc. 600 mm (24)d. None of the aboveANS: c5.5.2 Annular bottom plates shall have a radial width that provides at least 600 mm (24 in.)

    Q 22. Misalignment in a completed 20 mm thick vertical seam of anAST built to API Standard 650 shall be more than:a. 2 mmb. 1.5 mmc. 0.8 mmd. 3 mm

    ANS: aMisalignment in completed vertical joints for plates greater than 16 mm (5/8 in.) thick shall not exceed 10 % of the plate thickness or 3 mm (1/8 in.), whichever is less;

  • Charlie Chong/ Fion Zhang

    Q 23. Out of roundness measured as deviation from radius measured 1 foot above the bottom corner weld of a 250 ft diameter AST built to API Standard 650, shall not exceed:a. 1 (25 mm) (?)b. (12.7 mm)c. (19 mm)d. 1-1/4 (32 mm)ANS: d

    Q 24. Local deviations from theoretical shape of an aboveground storage tank (AST), built to API Standard 650, specifically Peaking at vertical joints or Banding at horizontal weld joints as measured over an appropriate sweepboard of 36 shall not exceed:a. 19 mm (3/4)b. 13 mm (1/2)c. 16 mm (5/8)d. 1/8 mm (3)ANS: b

  • Charlie Chong/ Fion Zhang

    Q25. An AST has remaining corrosion allowance of 3.2 mm. The known rate of corrosion of shell is 200 microns per year. As per API Standard 653, when should the external visual inspection by an Authorized Inspector shall be carried out at an interval not exceeding:a. 5 yearsb. 8 yearsc. 4 years (?)d. 15 yearsANS: interval = 3.2/0.2 = 16 years. Used 5 year max. Answer: a

  • Charlie Chong/ Fion Zhang

    API 653 PREPARATORY COURSE Final Exam Open Book Answer Key

  • Charlie Chong/ Fion Zhang

    Practice-02API 653 PREPARATORY COURSEFinal Exam Closed Book

  • Charlie Chong/ Fion Zhang

    Q1. The complete or partial removal and replacement of morethan 12 inches of a vertical weld joining shell plates isconsidered a :(a) minor alteration; (b) minor repair;(c) major alteration; (d) major repair.ANS: d

    Q2. A single film technique was used to make a radiograph using aCobalt-60 source. The minimum permitted density in the area ofinterest is:a. 4.0b. 1.8c. 2.0d. 1.3ANS: c

  • Charlie Chong/ Fion Zhang

    Q3. At what level is the atmosphere considered oxygen-deficient?a. Less than 19.5%b. Less than 21.9%c. Less than 24.9%d. Less than 16.0%ANS: a

    Q4. __________ is a change from previous operatingconditions involving different properties of the storedproduct such as specific gravity or corrosivity and / ordifferent service conditions of temperature and / orpressure:(a) Re-rating; (b) Change in service;(c) Repair; (d) ReconstructionANS: b

  • Charlie Chong/ Fion Zhang

    Q5. Describe how a liquid penetrant examination should be performed in order to detect discontinuities which are open to the surface.

    a. Clean the part, apply the developer, apply the penetrant, remove excess penetrant, inspect the part, clean the part

    b. Clean the part, apply penetrant, remove excess penetrant, apply the developer, inspect the part, clean the part

    c. Clean the part, apply the developer, apply the penetrant, inspect the part, remove excess penetrant, clean the part

    d. Clean the part, apply the developer, apply the penetrant, inspect the part, clean the part

    ANS: b

    Q6. A radiographic technique in which radiation passed through two walls and both the walls are viewed on the same radiograph (double wall, double image ellipse) the limitation for the outside diameter is:a. 3-1/2 b. 2c. 4 d. Any diameter possibleANS: a

  • Charlie Chong/ Fion Zhang

    Q7. Information needed when determining the rate of corrosion:a. Original thickness or last inspection thicknessb. Current thicknessc. Length of time in serviced. All the aboveANS: d

    Q8. The maximum acceptable undercutting for base metal inrepaired or altered horizontal welds is :-(a) 1/64"; (b) 1/32"; (c) 1/16"; (d) 1/8"ANS: b

  • Charlie Chong/ Fion Zhang

    Q9. The definition of a confined space is:a. large enough to enterb. restricted means of entryc. not designed for continuous occupancyd. all of the above are requiredANS: d

    Q10. An individual stationed outside one or more permit spaces whomonitors the authorized entrants and orders the authorizedentrants to evacuate the permit space under unsafe conditions.This individual is referred as:a. Supervisorb. A qualified personc. An attendantd. None of aboveANS: b

  • Charlie Chong/ Fion Zhang

    Q11. A corroded area of a tank bottom plate is repaired by welding overlay. There is no change in the rating and no change is made on the nameplate. Which of the following is the correct term to describe this process?

    a. Reconstructionb. Repairc. Alterationd. None of the aboveANS: b

    Q12. The maximum interval between internal inspections shallnot exceed ____ years:(a)10; (b) 20; (c) 5; (d) 15.ANS: b

  • Charlie Chong/ Fion Zhang

    Q13. Hot taps are not permitted under which of the followingconditions?a. On plates requiring PWHT.b. On ultrasonically sound platec. On tanks with dia. more than 80 feet.d. None of above.ANS: a

    Q14. For a tank of 160ft dia. Is to be checked for shell settlement.Minimum number of equally spaced settlement points to bechecked will be:a. 16b. 20c. 24d. 12ANS: a

  • Charlie Chong/ Fion Zhang

    Q15. For a tank made by reconstruction, under what circumstances may a new shell-to-bottom weld be exempt from hydrostatic testing?

    a. When the root pass has been visually inspected and the final weld is fullyexamined, visually and radiographically.

    b. Reconstructed tank is never exempted from hydrostatic testing.c. When the root pass has been visually inspected and the final weld is fully

    examined, visually and by vacuum box.d. When the welding method has been reviewed and approved by an

    engineer experienced in tank design in accordance with API Standard 650.ANS: c

  • Charlie Chong/ Fion Zhang

    Q16. In atmospheric conditions, bottom coatings may be applied if thesteel temperature is:a. 2F above the dew pointb. 5F below the dew point.c. 10F above the dew point.d. at the dew point.ANS: b

    Q17. Procedure qualification for welding of tanks is done in accordanceWitha. AWS D1.1b. API 1104c. ASME Section IXd. All of the aboveANS: c

  • Charlie Chong/ Fion Zhang

    API 652: 8.3 Temperature and Humidity ControlThe temperature of the steel surface should conform to the lining manufacturers recommended application and curing ranges. As a general rule, the surface temperature must be at least 5F (3C) above the dew point temperature in the tank and the relative humidity should be below 80 % at the steel surface. If the surface temperatures and/or humidity level expected to deviate from the recommended range, climate control equipment should be employed to ensure the proper conditions are maintained. It should be noted that durations of surface preparation, lining application, and cure may be continuous over a 24-hour period. If so, the required environmental conditions must be maintained around the clock. Owner operations may interfere with continuous use of environmental control equipment. These operational considerations should be reviewed prior to the execution of the tank lining project. NACE 6A192/SSPC-TR 3 provides guidance on the use of dehumidification and heating equipment for environmental controls during tank lining work. Climate control equipment is also used to advantage by protecting workers from heat stress during hot summer months. Improved productivity, due to better working conditions, is a secondary benefit.

  • Charlie Chong/ Fion Zhang

    Q18. Widely scattered pits may be ignored under the followingconditionsa. Where the service fluid is corrosive or hard to hold.b. If sum of bit length along 8 vertical line does not exceed 2c. When no pit has depth which results in the minimum thickness being less than one-half the minimum acceptable thickness of the shell plate exclusive of corrosion allowanced. b and cANS: d

    Q19. For verification of radiographic sensitivity and image quality, which of the following are used:a. Cassettesb. Penetrametersc. Camerasd. CollimatorsANS: b

  • Charlie Chong/ Fion Zhang

    Q20. Internal corrosion in the vapour space above liquid level occursdue to:a. Hydrogen Sulphide vapourb. Water vapourc. Oxygend. Any combination of the above threeANS: d

    Q21. API 650: Appendix M provides requirements for Tanks designedto operate at the following range of temperatures :a. exceeding 260 deg Cb. above 90 deg Cc. below 90 deg Cd. B or CANS: b

  • Charlie Chong/ Fion Zhang

    Q22. For a reconstructed tank as per API 653 Verticality (out-ofplumbness)of top of the shell shall not exceed,a. 1/300 of total tank heightb. 1/250 of total tank heightc. 1/400 of total tank heightd. None of the aboveANS: d

    Q23. Tank bottom linings are called thick film lining when the liningthickness is:a. more than 1 mm thkb. equal or more than 20 milsc. more than 20 milsd. more than 2 mm thkANS: c

  • Charlie Chong/ Fion Zhang

    Q24. Hot tap can be performed on:a. vapour space in the shella. on the roofb. in the shell below liquid levelc. anywhere on the tankANS: b

    Q25. A radiograph was having density near the penetrameter equal to3.0. Hence the acceptable density range of the radiograph is:a. 1.7 to 4b. 2.55 to 3.9c. 2.0 to 4.0d. None of the aboveANS: min = 3x 0.85, max 3x1.3 = 2.55~3.9. answer b

  • Charlie Chong/ Fion Zhang

    T-282.2 Density Variation(a)General. If the density of the radiograph anywhere through the area of

    interest varies by more than minus 15% or plus 30% from the density through the body of the hole IQI or adjacent to the designated wire of a wire IQI, within the minimum/maximum allowable density ranges specified in T-282.1, then an additional IQI shall be used for each exceptional area or areas and the radiograph retaken. When calculating the allowable variation in density, the calculation may be rounded to the nearest 0.1 within the range specified in T- 82.1.

    (b)With Shims. When shims are used with hole-type IQIs, the plus 30% density restriction of (a) above may be exceeded, and the minimum density requirements of T-282.1 do not apply for the IQI, provided the required IQI sensitivity of T-283.1 is met.

  • Charlie Chong/ Fion Zhang

    Q26. The examiner for conducting magnetic particle testing on the tank welds shall be:a. Qualified as per ASNT Level II or IIIb. Able to read Jagger-2c. Qualified as per ASME Sec. Vd. None of the aboveANS: b

    Q27. In atmospheric conditions, bottom coatings may be applied if thesteel temperature is:a. 2F above the dew point.b. 5F below the dew pointc. 10F above the dew pointd. at the dew pointANS: b

  • Charlie Chong/ Fion Zhang

    API 652: 8.3 Temperature and Humidity ControlThe temperature of the steel surface should conform to the lining manufacturers recommended application and curing ranges. As a general rule, the surface temperature must be at least 5F (3C) above the dew point temperature in the tank and the relative humidity should be below 80 % at the steel surface. If the surface temperatures and/or humidity level expected to deviate from the recommended range, climate control equipment should be employed to ensure the proper conditions are maintained. It should be noted that durations of surface preparation, lining application, and cure may be continuous over a 24-hour period. If so, the required environmental conditions must be maintained around the clock. Owner operations may interfere with continuous use of environmental control equipment. These operational considerations should be reviewed prior to the execution of the tank lining project. NACE 6A192/SSPC-TR 3 provides guidance on the use of dehumidification and heating equipment for environmental controls during tank lining work. Climate control equipment is also used to advantage by protecting workers from heat stress during hot summer months. Improved productivity, due to better working conditions, is a secondary benefit.

  • Charlie Chong/ Fion Zhang

    Q28. How many equally spaced measurements are required forthe thickness averaging technique?(a)2; (b) 5; (c) 4; (d) 3.ANS: b

    Q29. How many specimens and impact tests must be performedfrom a single test coupon or test location?(a)1; (b) 2; (c) 3; (d) 4.ANS: c

    Q30. Hydrostatic tests shall be held for ____ hours:-(a)2; (b) 8; (c) 24; (d) 72.ANS: c

  • Charlie Chong/ Fion Zhang

    Q31. In a radiographic film of a weld, how is back scatter checked?(a) by use of a penetrameter;(b) by film density;(c) using lead letter B;(d) all of the above.ANS: c

    Q32. In general, if shell thickness does not exceed ____ inch, it does not require further assessment for brittle fracture:-

    (a)0.25; (b) 0.75; (c) 1.00; (d) 0.50ANS: d

  • Charlie Chong/ Fion Zhang

    Q33. Potential for brittle fracture exists for tanks constructed according to:(a) API 650 7th edition(b) API 650 latest edition(c) API 650 4th edition(d) none of the aboveANS: dAPI653: 5.3.2 Step 1The tanks meet the requirements of API 650 (Seventh Edition or later) or API 650, Appendix G (Fifth and Sixth Editions) to minimize the risk of failure due to brittle fracture. Alternatively, tanks may also be shown to meet the toughness requirements of API 650 (Seventh Edition or later) by impact testing coupon samples from a representative number of shell plates.

    Q34. Three types of external inspections are :-(a) scheduled, routine and liquid penetrant;(b) scheduled, routine and UT thickness;(c) scheduled out of service, routine and UT thickness;(d) unscheduled, routine and liquid penetrant.ANS: b

  • Charlie Chong/ Fion Zhang

    Q35. Welders qualifications shall expire as they do not weld :-(a) within a given process for a 6 month period;(b) using a given procedure for a 6 month period;(c) on a tank for 6 months;(d) for a 3 month period.ANS: a

    Q36. What are penetrameters used for :-(a) A penetrameter is used for radiographic technique in that it serves as an image quality indicator(b) It indicates the magnetic properties of the materials(c) To check penetrant quality in PT inspection(d) To check weld penetration during weldingANS: a

  • Charlie Chong/ Fion Zhang

    Q37. Unless otherwise agreed to by the purchaser, what is theminimum nominal width of a shell plate?(a)36 inches; (b) 48 inches; (c) 72 inches; (d) 96 inches.ANS: b5.6.1.2 Unless otherwise agreed to by the Purchaser, the shell plates shall have a minimum nominal width of 1800 mm (72 in.). Plates that are to be butt-welded shall be properly squared.

    Q38. Vertical welds must be fully radiographed if the shellthickness exceeds inches :-(a)3/4; (b) 1; (c) 1 1/4; (d) 1 1/2.ANS: d

    Q39. Welding filler metals are grouped into groupings based ontheir AWS classification:-(a) P-numbers; (b) F-numbers;(c) Z-numbers; (d) ASTM spec.ANS: b

  • Charlie Chong/ Fion Zhang

    Q40. When reviewing a radiograph, a light image of the letter Bcan be seen on the film with dark background.(a) This is cause for rejection;(b) This is not cause for rejection;(c) This is the same as a light letter B;(d) An unusual safety hazard existed during the exposure.ANS: a

    Q41. Which of the following penetrant system is generally considered least sensitive?a. Water-washable visible dye.b. Solvent removable visible dye.c. Water-washable fluorescent dye.d. Post-emulsification visible dye.ANS: a

  • Charlie Chong/ Fion Zhang

    Q42. The nondestructive examination method to be used for aparticular inspection should be determined by the:a. Availability of certified NDE examiners.b. Length of time since the last inspection.c. Age of the component to be inspected.d. Type, location, and orientation of the expected flaws.ANS: d

    Q43. Most suitable UT equipment for use on rough surface is:a. CRT typeb. Direct readout typec. Either a or b, anything is okayd. a and b, both are not suitableANS: a

  • Charlie Chong/ Fion Zhang

    API 653 PREPARATORY COURSE Final Exam Closed Book Answer Key

  • Charlie Chong/ Fion Zhang

    Practice-03API 653 PREPARATORY COURSEFinal Exam

  • Charlie Chong/ Fion Zhang

    The following is a collection of questions remembered by various students who took the API 653 Exam in the past.

  • Charlie Chong/ Fion Zhang

    Q 1. What is the minimum thickness for a tank floor plate with no means for leak detectionor secondary containment if an RBI program is not in place?a. .005b. .050c. .075d. .100

    Q 2. Which one of the following types of external floating roofs does not require a checkvalve in the roof drain?a. Annular pontoon (single deck)b. Double deckc. Pan-typed. Plastic sandwich-panel-sphere type floating roof

  • Charlie Chong/ Fion Zhang

    Q 3. Surface preparation is a critical part of the lining operation, generally abrasive blast to a whitemetal finish of __________ is desired.a. NACE No. 1/SSPC-SP5b. NACE No. 2/SSPC-SP10c. NACE No. 3/SSPC-SP15d. NACE No. 4/SSPC-SP20

    Q4. When a full hydrostatic test is required, it shall be held for _____ hours.a. 8b. 12c. 16d. 24

  • Charlie Chong/ Fion Zhang

    Q 5. If any provision of API 653 presents a direct or implied conflict with any statutoryregulation and the statutory regulation is more stringent .a. the government regulations governb. the API 653 standards governc. the owner/operator requirements governd. the inspector will decide which regulations govern

    Q 6. The maximum permissible limit for exposure to organic lead in a normal 8 hour workday is .a. 2 micrograms per cubic footb. 1 PPM in airc. 0.075 pounds per cubic feet per dayd. .05 grams per cubic centimeter

  • Charlie Chong/ Fion Zhang

    Q 7. Radiographic film density shall be checked by a densitometer calibrated on a stepwedge film traceable to .a. API 650b. ASNT-SNT-TC-1Ac. ASME Section IXd. a national standard

    Q 8. A 200 diameter tank, 40 tall, storing a product with a specific gravity of .85. A corroded area was noted with UT on the bottom course with a minimum thickness of .51 at1 above the weld. No thinning was noted within 10 of any weld. What is the L length ofthe corroded area?a. not enough information to answerb. 10.10c. 37.37d. 40

  • Charlie Chong/ Fion Zhang

    Q 9. A gummy carbonaceous substance, fouling service, is stored in a tank. Where wouldproblems most likely occur?a. The floating suctionb. The operation of check valvesc. Around nozzlesd. On the floor

    Q 10. Routine visual in-service inspections of aboveground storage tanks from the groundmay be done by ?a. authorized inspectors onlyb. owner/user personnel other than authorized inspectorsc. jurisdictional inspectors onlyd. insurance inspectors only

  • Charlie Chong/ Fion Zhang

    Q 11. An existing tank, 48 feet high with a diameter of 127 feet, is undergoing majorrepairs. What is the maximum out-of-plumbness allowed?a. 1.27b. 4.8c. 5.0d. 5.76

    Q 12. Which of the following is not considered shell distortion?a. Uniform settlement of a tankb. Out-of-roundness of a tankc. Flat spotsd. Peaking and banding at weld joints

  • Charlie Chong/ Fion Zhang

    Q 13. A welder that qualifies on a plate groove weld can weld .a. groove weld onlyb. groove and fillet weldsc. fillet welds onlyd. J welds only

    Q 14. An 8 NPS hot tap is to be added to a tank. What is the minimum wall thickness of thenozzle neck?a. Schedule 40b. Schedule 60c. Standard weightd. Extra-strong

  • Charlie Chong/ Fion Zhang

    Q 15. A welder may be qualified by RT in any welding process except for which of thefollowing?a. GMAW (short-circuiting mode)b. GMAW (spray-arc mode)c. GTAWd. SMAW

    Q 16. Which of the following repairs are allowed within the critical zone of a tank bottom?a. Welded-on patch plates over existing patches.b. Welding of widely scattered pits, pinholes and cracks in the bottom plate.c. Welded-on structural steel angles to the tank shell and the annular plate.d. One pass perimeter welds on welded-on patch plates.

  • Charlie Chong/ Fion Zhang

    Q 17. What is the maximum spacing for MT prods?a. 2b. 4c. 8d. 10

    Q 18. A formal visual external inspection by an Authorized Inspector shall be made at leastevery ______ years or RCA/4N years, whichever is less.a. 2b. 3c. 4d. 5

  • Charlie Chong/ Fion Zhang

    Q 19. During the inspection of an AST it is discovered that the ground wire connection hascome loose. How should the ground system be inspected?a. Ignore itb. Test the current using a volt ohm meterc. PT or MTd. Visually checked

    Q 20. The presence of rock under the steel bottom of an AST would have what effect?a. Porosity in the bottomb. Promote corrosionc. Create longer tank bottom lifed. Have no effect on the tank bottom

  • Charlie Chong/ Fion Zhang

    Q 21. During a welder qualification test on 3/8 plate in the horizontal position, how manytransverse bends are required?a. 6 side bendsb. 2 nick breaksc. 1 face and 1 root bendsd. 4 tinsel specimens

    Q 22. If a contractor is to relocate or reconstruct an aboveground storage tank, the limits ofresponsibilities are defined by ?a. API 653b. the contractorc. the authorized inspectord. the owner/operator

  • Charlie Chong/ Fion Zhang

    Q 23. A new tank is to be hydrostatically tested. The tank is constructed from ASTM A 36Msteel. What allowable stress must be used to determine the maximum hydrostatic testhead for the tank.a. 29,400 psib. 23,200 psic. 24,900 psid. 27,000 psi

    Q 24. Where should the numbers be placed on a radiograph?a. Under the film.b. On the material being radiographed.c. Under the material being radiographed.d. On the film source pack.

  • Charlie Chong/ Fion Zhang

    Q 25. A new tank is placed in service. In seven years, which of the following inspectionsshould have been made?a. routine inspectionb. routine and external inspectionsc. routine, external, visual and internal inspectionsd. routine visual, formal visual (external) and UT inspections

  • Charlie Chong/ Fion Zhang

    Q 26. How many roof rafters must a plank cross over for inspection of the roof of a tank? a. 1b. 2c. 3d. 4

    Q 27. The maximum acceptable undercutting on horizontal butt welds of a reconstructed tank is _____ inch.a. 1/64b. 1/32c. 1/16d. 1/8

  • Charlie Chong/ Fion Zhang

    Q 28. The minimum number of settlement points around a tank periphery is .a. 12b. 10c. 8d. 6

    Q 29. A weld shall be acceptable by visual inspection if the inspection shows which of the following?

    a. The weld has no cracks, no undercutting, and less than 20% coldlap.b. The weld has no cracks, undercutting is acceptable, and any surface

    porosity does not exceed one cluster in any 2 of length and the diameter of each cluster does not exceed 1/16.

    c. The weld has no crater cracks or other surface cracks, undercutting isacceptable, and any surface porosity does not exceed one cluster in any 3of length and the diameter of each cluster does not exceed 1/8.

    d. The weld has no crater cracks, other surface cracks or arc strikes in or adjacent to the welded joint, undercutting is acceptable, and any surface porosity does not exceed one cluster in any 4 of length and the diameter of each cluster does not exceed 3/32.

  • Charlie Chong/ Fion Zhang

    API650: 8.5.2 A weld shall be acceptable by visual examination if the inspection shows the following.

    a) There are no crater cracks, other surface cracks or arc strikes in or adjacent to the welded joints.

    b) Maximum permissible undercut is 0.4 mm (1/64 in.) in depth for vertical butt joints, vertically oriented permanent attachments, attachment welds for nozzles, manholes, flush-type openings, and the inside shell-to-bottom welds. For horizontal butt joints, horizontally oriented permanent attachments, and annular-ring butt joints, the maximum permissible undercut is 0.8 mm (1/32 in.) in depth.

    c) The frequency of surface porosity in the weld does not exceed one cluster (one or more pores) in any 100 mm (4 in.) of length, and the diameter of each cluster does not exceed 2.5 mm (3/32 in.).

    d) The reinforcement of the welds on all butt joints on each side of the plate shall not exceed the following thicknesses:

  • Charlie Chong/ Fion Zhang

    Q 30. Penetrameters are normally placed on the _____ of the part being examined.a. source sideb. film sidec. weld sided. obverse side

    Q 31. External, UT measurements of a new tank shell shall be made not later than _____ years after commissioning.a. 5b. 4c. 3d. 2

  • Charlie Chong/ Fion Zhang

    Q 32. A liquid having a closed cup flash point equal to or greater than 100F is considered.a. flammable materialb. combustible liquidc. gasolined. diesel

    Q 33. Thin film linings are usually used for application to .a. the bottoms of new storage tanks.b. pitted bottoms of older storage tanks.c. corroded bottoms of previous service tanks.d. rough and pitted surfaces.

  • Charlie Chong/ Fion Zhang https://www.wisconsin.edu/ehs/osh/flam-liq/

  • Charlie Chong/ Fion Zhang

    Q 34. With a horizontal sweep board 36 long, peaking shall not exceed _____ inch.a. 0.250b. 0.375c. 0.500d. 0.625

    Q 35. If a welder tests in a 6G position, he qualifies to weld .a. all positionsb. uphill onlyc. downhill onlyd. vertical only

  • Charlie Chong/ Fion Zhang

    Q 36. An anode is .a. an electrode of an electrochemical cell at which no corrosion occursb. an electrode of an electrochemical cell at which corrosion occursc. a chemical substance containing ions that migrated. a metallic connection that provides electrical continuity

    Q 37. Widely scattered pits may be ignored, provided .a. no pit depth results in the remaining shell thickness being less than 1/2t min acceptable tank shell thickness, exclusive of corrosion allowance.b. the average pit depth is greater than 1/2t min, exclusive of the corrosionallowancec. no pit depth is greater than 1/2t min, including the corrosion allowanced. no pit depth is less than 1/2t min, including the corrosion allowance

  • Charlie Chong/ Fion Zhang

    Q 38. The critical zone of the tank bottom is within the .a. Annular plate ring, within 6 of the shell or within 6 of the inside edge of

    the annular ring.b. Annular plate ring, within 10 of the shell or within 10 of the inside edge of

    the annular ring.c. Annular plate ring, within 12 of the shell, or within 12 of the inside edge of

    the annular plate ring.d. Annular or bottom plates within 3 inches of the inside edge of the shell.

    Q 39. The space between the outer periphery of the roof and the tank shell of an external floating roof tank shall be sealed by a flexible device that provides .

    a. a minimum 1/2 gap over no more than 24b. an area of no more than 15 square inches opening calculated by

    measuring the length and width of the gaps.c. a reasonably close fit to the shell surfacesd. a minimum of 3 openings 24 long with gaps no more than 1/4

  • Charlie Chong/ Fion Zhang

    Q 40. What is the minimum thickness for a tank floor plate with a > 0.05 or thicker reinforced internal lining?a. .005b. .050c. .075d. .100

    Q 41. A full hydrostatic test is always required on .a. a tank that has an annular plate installed with the longest dimension less than 12b. a tank that has a door sheet installedc. a tank that has a nozzle 12 NPS installedd. a reconstructed tank

  • Charlie Chong/ Fion Zhang

    Q 42. What is the maximum temperature that dry MT can be used?a. 600 Fb. 135 Fc. 400 Fd. Within the temperature range limitations set by the manufacturer

    Q 43. If a repair/modification weld is made on a tank shell plate that is thicker than 1, the base metal within 3 inches of the welding shall be heated to a temperature of approximately degrees.a. 120o Fb. 140 Fc. 160 Fd. 200 F (1)

    10.4.2.3 No welding of any kind shall be performed when the surfaces of the parts to be welded are wet from rain, snow, or ice; when rain or snow is falling on such surfaces; or during periods of high winds unless the welder and the work are properly shielded. No welding of any kind shall be performed when the temperature of the base metal is less than 0 F. When the temperature of the base metal is between 0 F and 32 F or the thickness is in excess of 1 in.,the base metal within 3 in. of the place where welding is to be started shall be heated to a temperature warm to the hand (approximately 140 F) before welding. (See 10.4.4.3 for preheat requirements for shell plates over 1 1/2-in. thick.)

  • Charlie Chong/ Fion Zhang

    Q 44. What is the main factor in determining the efficiency of a rivet joint in a tank?a. The allowable stress of the rivetsb. The number of rivet rows and type of jointc. The allowable stress of the plated. Whether the joints have butt straps or not

    Q 45. It is not necessary for the inspector to check which of the following?a. All test results on the PQRb. All essentials and non-essentials on WPSc. All essentials and non-essentials on WPS and PQRd. All non-essentials on PQR

  • Charlie Chong/ Fion Zhang

    Q 46. A new tank built in January, 1984, was removed from service and internally inspected in January, 1994. The bottom course of the tank showedthe most general corrosion (no isolated corrosion was found). The originalthickness of the bottom course of the tank was 1. The measured thickness ofthe bottom course at the inspection was 0.93. Determine the yearly corrosionrate.a. .0035 b. .0070c. .0140 d. .0700

    Q 47. When the corrosion rates of a tank are not known and the bottom plate thickness can not otherwise be determined, inspection(s) should beperformed within the next _____ years of tank operation to establish corrosionrates.a. 5b. 10c. 15d. 206.4.2.1.1 The interval from initial service date until the first internal inspection shall not exceed 10 years unless a tank has one or more of the leak prevention, detection, corrosion mitigation, or containment safeguards listedin Table 6.1. The initial internal inspection date shall be based on incremental credits for the additional safeguards in Table 6.1 which are cumulative.

  • Charlie Chong/ Fion Zhang

    Q 48. The maximum spacing of settlement points is _____ feet around the circumference ofthe tank.a. 40b. 35c. 32d. 25

    Q 49. A 100 foot diameter tank must have at least _____ inch thick shell plates.a. 1/8b. 3/16c. 1/4d. 1/2

  • Charlie Chong/ Fion Zhang

    Q 50. The maximum acceptable undercutting on vertical butt welds of a reconstructed tank is _____ inch.a. 1/64b. 1/32c. 1/16d 1/8

  • Charlie Chong/ Fion Zhang

    Dinner Time

  • Charlie Chong/ Fion Zhang

    Q51. The letter B is placed on radiographic film holder for what reason?a. To determine if back scatter radiation is exposing the film.b. To show the distance from the source of radiation to the weld.c. To function as a location marker for the radiograph.d. To designate whether the penetrameter is on the film side or the back side.

    Q52. A tanks bottom course has corroded in a general uniform manner (including the welds). The tanks diameter is 137 and its height is 40 (5-eightfoot courses). The liquid stored in the tank is hydrocarbon with a specificgravity of 0.82 and it is not corrosive. The tank was constructed from ASTMA-283, Grade C (A 283M, Grade C) carbon steel. Determine the minimumthickness of the bottom course for full height operation. Round to the nearesthundredth. (This tank was built to API 650, Eighth edition).a. 0.805b. 0.691c. 0.200d. 0.483Ans: tmin = 2.6(H-1)DG/SE = 2.6(39)137x0.82/(23600)= 0.483, answer: d

  • Charlie Chong/ Fion Zhang

    Q53. When preparing to enter a storage tank for inspection, the most important thing to do is .a. obtain a written entry permitb. to have all equipment needed for inspection ready and availablec. to be wearing protective clothingd. to check all platforms and ladders for serviceability

    Q54. A tank course made from 3/4 plate is welded with low hydrogen electrodes. The welder undercuts a horizontal butt weld to a depth of 0.02and he reinforces the weld with a 0.20 reinforcement.a. The weld is acceptableb. The weld is unacceptable because of the excess undercutc. The weld is unacceptable because of the excess reinforcementd. The weld is unacceptable because of the excess reinforcement and excessUndercutAns: under cut 3/16 Not OK, answer: c

  • Charlie Chong/ Fion Zhang

    Q55. What is the inspection frequency for flame arrestors?a. 2 yearsb. 5 yearsc. 10 yearsd. Annually

    Q56. How many tensile tests are required to qualify a 1/4 plate groove weld?a. 2b. 3c. 4d. 6

  • Charlie Chong/ Fion Zhang

    Q57. The minimum bottom plate thickness for a tank with an applied reinforced lining greater than 0.05 thick, applied in accordance with API RP 652, is inch.a. 0.10b. 0.05c 0.125d. 0.0625

    Q58. The oxygen content for non-permit required confined space must be __________.a. 0 - 10%b. 10% - 15%c. 19.5% - 23.5%d. 25.2% - 32.7%

  • Charlie Chong/ Fion Zhang

    Q59. The acceptance criteria for a radiograph of a tank repair weld is found in .a. Section V of the ASME Codeb. Section IX of the ASME Codec. Section VIII of the ASME Coded. ASNT SNT-TC-1A

    Q60. All leaks in pontoons or compartments of double deck floating roofs shall be repaired by .a. caulking the leaking joints and/or using soft patch materialb. rewelding the leaking joints and/or the use of patch platesc. cutting out the leaking area and flush patchingd. weld overlay any cracks and/or use soft patch material

  • Charlie Chong/ Fion Zhang

    Q61. For what diameter tank is the variable point method for calculating shell thickness mandatory?a. Tanks with a diameter of 200 feet and greaterb. Tanks with a diameter greater than 300 feetc. Tanks with a diameter greater than 200 feetd. Tanks with a diameter of 300 feet and greater

    Q62. What is the minimum lifting power of an AC electromagnetic yoke used in magnetic particle inspection?a. 40 pounds lifting power at the maximum pole spacingb. 10 pounds lifting power at the maximum pole spacingc. 10 amps lifting power at the maximum pole spacingd. 30 pounds lifting power at the minimum pole spacing

  • Charlie Chong/ Fion Zhang

    Q63. What is the allowable edge settlement of a 100 diameter tank that has an area of settlement that starts to slope 36 from the shell and the bottom lap weld is approximately parallel to the shell?a. 13.32b. 3.75c 18.5d. 2.22

    Q64. A tank was constructed from welded ASTM A-516, Grade 60 (A 516M, Grade 415) steel. The third course must be evaluated for continued service. What is the allowable stress that must be used in the calculations?a. 21,300 psib. 25,560 psic. 28,200 psid. 28,320 psi

  • Charlie Chong/ Fion Zhang

    Q65. A 125 diameter X 40 high storage tank has questionable thickness annular plates. The first shell course thickness is .61. The thickness of the corrosion allowance for the tank is 0.125. The product specific gravity is less than 1. What is the minimum thickness for the annular plate?a. 0.17b. 0.20c. 0.325d. 0.295

    Q66. The principal advantage of thin-film linings are .a. better protection of older storage tank bottoms and ease of applicationb. less susceptible to mechanical damage and easier to repairc. lower cost and not as sensitive to pittingd. lower cost and ease of application compared to thick-film coatingsystems

  • Charlie Chong/ Fion Zhang

    Q67. In no case shall the internal inspection interval of an aboveground storage tank exceed _____ years, if an RBI program is not in place.a. 5b. 10c. 20d. 25The initial inspection interval shall not exceed 20 years for tanks without a Release Prevention Barrier, or 30 years for tanks with a Release Prevention Barrier.6.4.2.1.2 As an alternative to establishing the initial interval in accordance with Section 6.4.2.1 and Table 6.1, the initial internal inspection date and reassessment can be established using Risk Based Inspection (RBI) assessment per 6.4.2.2.2. These assessments may establish an initial inspection interval exceeding 10 years but shall not exceed 20 years for tanks without a Release Prevention Barrier, or 30 years for tanks with a Release Prevention Barrier except as follows.

    Q68. Welders are qualified to what standard or code?a. Section VIII of the ASME Codeb. Section V of the ASME Codec. Section I of the ASME Coded. Section IX of the ASME Code

  • Charlie Chong/ Fion Zhang

    Q69. What is the maximum acceptable undercut of a nozzle to shell weld?a. 1/64b. 1/32c. 1/16d. 1/8

    Q70. The nameplate for a reconstructed tank shall be attached to the tank shell adjacent to.a. the existing nameplateb. a manway in bottom tank coursec. the stairway or ladder to the tank roofd. the door sheet

  • Charlie Chong/ Fion Zhang

    Q71. When a welder has not welded with a process during a period of _____, his qualifications for that process shall expire.a. 3 months or moreb. 6 months or morec. 9 months or mored. 12 months or more

    Q72. What allowable stress is used in evaluating a riveted joint when using joint efficiencies given in Table 4-3 of API 653?a. 16,000 psib. 18,000 psic. 19,000 psid. 21,000 psi

  • Charlie Chong/ Fion Zhang

    Q73. Radiographs of repaired work and records of radiographs of repaired work shall be marked with .a. a grease pencilb. the mark of the welder who made the repairc. the letter Rd. the initial of the inspector

    Q74. The transmitted film density through the radiographic image of the body of the appropriate hole penetrameter and the area of interest shall be _____ minimum for radiographs made with a gamma ray source.a. 1.8b. 2.0c. 2.2d. 2.6

  • Charlie Chong/ Fion Zhang

    Q75. A tank has a corroded area on its second course. It is elliptical in shape with the major axis parallel to the horizontal weld seam. The major axisdimension is 35 and the vertical minor axis is 21. The tank diameter is 127and its height is 40 (5-eight foot courses). The minimum thickness measuredin the corroded area is 0.52. The general thickness of the second course (away from the corroded area) is 0.75. What is the maximum critical lengththat can be used in determining the averaging out of the hoop stresses around the corroded area. Round to the nearest 0.1.a. 40b. 36.1c. 30.1d. 28.1

    L = 3.7(Dt2) = 30.1

  • Charlie Chong/ Fion Zhang

    Q76. What is the P number for the tank as listed above?a. 1.5b. 1c. 6d. 24

  • Charlie Chong/ Fion Zhang

    Q77. What is the maximum fill rate for the tank as listed above?a. 3 feet per secondb. 6 feet per secondc. 3 feet per minuted. 6 feet per minute

    Q78. What is the SFA number for E 7018 electrodes?a. 5b 5.1c. 5.29d. 5.42

  • Charlie Chong/ Fion Zhang

    API 650: 7.3.6.5 The minimum fill and discharge rate, if any, shall be specified by the Purchaser on the Data Sheet, Line 23. When settlement measurements are specified by the Purchaser, the maximum filling rates shall be as follows, unless otherwise restricted by the requirements in 5.8.5.

  • Charlie Chong/ Fion Zhang

    Q79. What is the filler number (F) for E-7018 electrodes?a. 1b. 2c. 3d. 4

    Q80. What is the minimum acceptable shell plate thickness for the first course of T 3-27, if the specific gravity of the stored product is 1.3? NOTE: current inspection (2003) based on product alone, and full height operation.a. .316b. .500c. .262d. Not enough information given

    t min = 2.6(39)47x1.3/(20000) = 0.309 or 3/16 whichever greater, used 0.309.t min = 2.6(39)47x1.3/(23600) = 0.262 inservice tank

  • Charlie Chong/ Fion Zhang

    Q81. What is the hydrostatic test height of T 3-27 if the joint efficiency is .85 and the specific gravity of the product is 1.3?a. 57.24'b. 40'c. 28.27'd. Not enough information giventmin = 2.6(Ht-1)x47/ (26000x0.85), Ht = 44.71, used 40

    Q82. What is the minimum acceptable shell plate thickness for the top course of T 3-27 if each course is 120" tall?a. .1"b. .062"c. .269"d. Not enough information givent min = 2.6(9)47x 1.3/26000 = 0.05 used 0.1, answer = a

  • Charlie Chong/ Fion Zhang

    Q83. What is the joint efficiency for T 3-27?a. 1b. .85c. .70d. .35

    Q84. What is the corrosion allowance for T 3-27?a. .185"b. .125"c. .0625"d. Not enough information given (?)

  • Charlie Chong/ Fion Zhang

    Q85. If T 3-27 was new, what would be the minimum first course thickness, based on product alone?a. .269"b. .310"c. .500"d. Not enough information givent min = 2.6(39)47x1.3/(20000) = 0.309 or 3/16 whichever greater, used 0.309

    Q86. How many settlement points are required for an external settlement of T 3-27?a. 4b. 6c. 8d. 10

  • Charlie Chong/ Fion Zhang

    Q87. A depression in the floor is discovered near the east manway of T 3-27. The diameter of the depression is 96", the deepest point in the depression is 4". The area _________.a. is rejectable.b. is acceptable.c. must be monitored.d. can be filled in with epoxy and accepted.BB = 0.37R = 1.48

    Q88. During the internal inspection of T 3-27, a patch plate welded to the floor, with a tombstone shaped pad, extending to the inside of the shell wasdiscovered. The plate had been seal welded to the floor and shell, with aminimum dimension of 12 inches. The inspector should _____________.a. have the patch removed.b. inspect the patch.c. recommend removal of the patch and floor plates in the repaired area, replacing withnew floor plates.d. this repair is in the critical zone and not allowed.

  • Charlie Chong/ Fion Zhang

    Q89. During the same internal inspection of T 3-27, a square lap-welded patch was found over an existing nozzle. The inspector should __________.a. have the patch removed.b. inspect the patch.c. cut out the entire shell plate.d. radiograph the patch for weld quality.

    Q90. T 3-27 has a hole, less than 1" in diameter, in the roof. Rain water does not contaminate the stored product. Is a repair required by API 653?a. A repair may be made by using duct tape.b. Only if the owner requires the repair.c. Nod. Yes

  • Charlie Chong/ Fion Zhang

    Q91. What is the position designation for welding pipe in the horizontal fixed position?a. 2Gb. 3Gc. 5Gd. 6G

    Q92. During a fluorescent MT test, the black light intensity shall be measured at least once every .a. hourb. 2 hoursc. 4 hoursd. 8 hours

  • Charlie Chong/ Fion Zhang

    Q3. Terminology for weld metal in excess of the specified weld size.a. Weld reinforcementb. Good weld techniquec. Weld toed. Weld throat

    Q94. If T 3-27 had a new nozzle installed in the third course, north side, could the shell-to-nozzle weld be made using the oxyfuel welding process, if impact testing is not required?a. Yesb. Noc. The oxyfuel process is not allowed by ASME Section IXd. Nozzle welds must be made using SMAW only

  • Charlie Chong/ Fion Zhang

    Q95. A diesel oil test is required for ______________.a. all new nozzle weldsb. all new floor weldsc. all new shell weldsd. all new shell-to-bottom welds

    Q96. The minimum PSIG for a vacuum box test is __________.a. 1 PSIGb. 2 PSIGc. 3 PSIGd. 4 PSIG

  • Charlie Chong/ Fion Zhang

    Q97. A pipe welder is qualified to API 1104 only. What welds can he make on the tank if he is qualified in the 6G position?a. Nozzle Weldsb. Shell Weldsc. Floor and roof fillet weldsd. None

    Q98. A procedure is qualified on plate .500" thick. Which of the following thicknesses is not qualified?a. 1"b. 1/2"c. 1/4"d. 1/8"

  • Charlie Chong/ Fion Zhang

    Q99. A procedure is qualified on plate .500" thick. Four nick break specimens were substituted for the four side bends.a. The procedure is qualified.b. ASME does not allow nick breaks.c. Two tension specimens were required.d. Nick breaks are used only on pipe.

    Q100. A welder is qualified in the 3F and 4F positions. Which of the following groove welds can he make?a. 1Gb. 2Gc. 6Gd. None

  • Charlie Chong/ Fion Zhang

    Practice-04API 653 PREPARATORY COURSEFinal Exam Open Book

  • Charlie Chong/ Fion Zhang

    Q 1. The liquid penetrant examination method is an effective means for detecting _______. a. internal discontinuities of a weld b. surface discontinuities of a weld c. both internal and surface discontinuities of a weld d. subsurface discontinuities of a weld

    Q 2. A WPS is a written qualified welding procedure prepared to ________. a. provide direction for making production welds to Code requirementsb. provide direction for the welder to make temporary welds c. provide direction for the inspector for inspection of the welds d. provide direction for the welder to use as a general guideline

  • Charlie Chong/ Fion Zhang

    Q 3. Welding in the 3G position qualifies a welder in what positions? a. Flat and horizontal b. Horizontal and vertical c. Flat and vertical d. Vertical and overhead

    Q 4. Which of the following is an essential variable for the WPS? a. A change in groove design b. A change in backing c. A change in post weld heat treatment d. A change in electrode angle

  • Charlie Chong/ Fion Zhang

    Q 5. A welder may be qualified by RT if ___________. a. the welder uses SMAWb. the welder uses GMAW Short Circuiting mode c. the welder uses GMAW Short Circuiting mode root pass with SMAW fill and reinforcement d. the welder obtains approval from the inspector

    Q 6. A peripheral seal, on an internal floating roof, shall be designed to accommodate ______ of local deviation between the floating roof and the shell. a. the manufacturers standardb. 4 inches c. 1/8inch d. inspectors experience

    API650: H.4.4.3 All peripheral seals and their attachment to the floating roof shall be designed to accommodate 100 mm (4 in.) of local deviation between the floating roof and the shell.

  • Charlie Chong/ Fion Zhang

    API650: H.4.4.3 All peripheral seals and their attachment to the floating roof shall be designed to accommodate 100 mm (4 in.) of local deviation between the floating roof and the shell.

  • Charlie Chong/ Fion Zhang

    Q 7. What is the maximum allowable prod spacing using an AC prod (yoke?)technique? a. t/2 b. 8 inches c. 10 inches d. No spacing required

    Q 8. Welders that weld tank shell vertical joints shall be qualified in accordance with______.

    a. API 1104 b. ASME Section V c. ASME Section IX d. AWS D1.1

  • Charlie Chong/ Fion Zhang

    T-752 Prod TechniqueT-752.3 Prod Spacing. Prod spacing shall not exceed 8 in. (200 mm).Shorter spacing may be used to accommodate the geometric limitations ofthe area being examined or to increase the sensitivity, but prod spacings ofless than 3 in. (75 mm) are usually not practical due to banding of theparticles around the prods. The prod tips shall be kept clean and dressed. Ifthe open circuit voltage of the magnetizing current source is greater than 25 V,lead, steel, or aluminum (rather than copper) tipped prods are recommendedto avoid copper deposits on the part being examined.

  • Charlie Chong/ Fion Zhang

    Q 9. Geometric unsharpness of the radiograph of a component under 2 thick shall not exceed __________. a. 0.020 b. 0.030 c. 0.040 d. 0.050

    Q 10. For measuring the thickness of materials using the contact pulse-echo method, temperatures are not to exceed________. a. 200F b. 93C c. both 1 and 2d. 50F

    SE797: 1. Scope1.1 This practice provides guidelines for measuring the thickness of materials using the contact pulse-echo method at temperatures not to exceed 200F (93C).

  • Charlie Chong/ Fion Zhang

    Q 11. Each piece of magnetizing equipment shall be calibrated ___________. a. at the beginning of each shift b. at least once a year or whenever the equipment has been subject to

    major electrical repair c. whenever the technician feels like it d. at least once every 90 days

    Q 12. During calibration of an ammeter the unit shall not deviate by more than ____ of full scale.

    a. 10% b. 20% c. 30% d. 40%

  • Charlie Chong/ Fion Zhang

    T-761 Frequency of CalibrationT-761.1 Magnetizing Equipment(a) Frequency. Magnetizing equipment with an ammeter shall be calibrated at least once a year, or whenever the equipment has been subjected to major electric repair, periodic overhaul, or damage. If equipment has not been in use for a year or more, calibration shall be done prior to first use.(b) Procedure. The accuracy of the units meter shall be verified annually by equipment traceable to a national standard. Comparative readings shall be taken for at least three different current output levels encompassing the usable range. (c) Tolerance. The units meter reading shall not deviate by more than 10% of full scale, relative to the actual current value as shown by the test meter. T-761.2 Light Meters. Light meters shall be calibrated at least once a year or whenever a meter has been repaired. If meters have not been in use for one year or more, calibration shall be done before being used.

    T-762 Lifting Power of Yokes(a) Prior to use, the magnetizing power of electromagnetic yokes shall have been checked within the past year. The magnetizing power of permanent magnetic yokes shall be checked daily prior to use. The magnetizing power of all yokes shall be checked whenever the yoke has beendamaged or repaired.(b) Each alternating current electromagnetic yoke shall have a lifting power of at least 10 lb (4.5 kg) at the maximum pole spacing that will be used.(c) Each direct current or permanent magnetic yoke shall have a lifting power of at least 40 lb (18 kg) at the maximum pole spacing that will be used.

  • Charlie Chong/ Fion Zhang

    Q 13. An inspector is evaluating a radiograph, a bright white image of a Bappears on a darker background of the radiograph, __________. a. the radiograph shall be considered unacceptableb. the radiograph should not be rejected c. the B is for identification of the welder d. the B is for identification of the weld

    Q 14. Ultrasonic examination of hot tap connections or reinforcement is required by API 653 when _______. a. in lieu of radiographic testing b. searching for weld flaws c. searching for laminations d. requested by the welder

  • Charlie Chong/ Fion Zhang

    Q 15. During an internal inspection of a tank, pitting that measures 0.30 inches deep was found in the shell (0.625 Thickness). The required thickness of the shell in this area is 0.5 inches. Based on the above information should a repair be made? a. Yesb. Noc. The inspector option d. Repair contractors option

    API653: 4.3.2 Actual Thickness Determination4.3.2.1e) The criteria for continued operation is as follows:i) the value t1 shall be greater than or equal to tmin (see 4.3.3 or 4.3.4), subject to verification of all other loadings listed in 4.3.3.5;ii) the value t2 shall be greater than or equal to 60 % of tmin; andiii) any corrosion allowance required for service until the time of the next inspection shall be added to tmin and 60 % of tmin.

  • Charlie Chong/ Fion Zhang

    The following applies to questions 16 through 25 below: An inspection is performed on an AST 24 tall, 22 fill height, 94 diameter, water storage service, earth foundation. There is one area of general internal corrosion on the south side of the shell 20 wide and 20 in vertical length. There is evidence of bottom settlement.

    Q 16. Calculate the minimum thickness of the first course based on product alone. a. 1.175b. 0.228c. 0.551d. 0.217tmin = 2.6(21)94/23600 = 0.2174, however, tmin shall not be less than 0.1 in. for any tank course; used 0.2174 OK answer: d

    Q 17. Calculate the minimum thickness for the third course, if each course is 4 in height. a. .122 b. .100c. .275 d. .132tmin = 2.6(13)94/26000 = 0.0094, used 0.1 answer: b

  • Charlie Chong/ Fion Zhang

    Q 18. Calculate the L length for an area of general corrosion found 10 from the bottom on the south side of the shell, T2= .125. a. 40b. 12.68c. 680d. 11.75L =3.7(Dt2) = 12.68, answer: b

    Q 19. There are three pits aligned vertically on the north side of the tank, in the first course. The diameter of the pits are 1 .250, 1 , and .500 in length along a vertical line 8 long. Note: Assume pit depth of slightly less than one-half of the minimum acceptable tank shell thickness, exclusive of the corrosion allowance. a. Because the pits are aligned vertically no repair is required (?)b. Scattered pits may be ignored c. If the pit is round, it may be ignored d. A repair is required answer: d4.3.2.2 Widely scattered pits may be ignored provided that:a) no pit depth results in the remaining shell thickness being less than one-half the minimum acceptable tank shell thickness exclusive of the corrosion allowance; andb) the sum of their dimensions along any vertical line does not exceed 2 in. in an 8-in. length (see Figure 4.2).

  • Charlie Chong/ Fion Zhang

    Q 20. Three circumferentially scattered pits are located on the west side of the tank 18 from the bottom. The pits measure .500, .477 and .732 in diameter. Note: Assume pit depth of one-half of the minimum acceptable tank shell thickness, exclusive of the corrosion allowance. a. Because the pits are scattered circumferentially no repair is required b. All pits may be ignored c. If the pit is round, it may be ignored d. A repair is requiredAnswer: b,

  • Charlie Chong/ Fion Zhang

    Q 22. An area of edge settlement in the tank bottom 6 from the shell has sloped down and settled. The settlement measures 2 at the deepest point. (The bottom lap welds are approximately parallel to the shell). a. A more rigorous stress analysis must be performed b. The area should be repaired c. Sloped edge settlement is usually no problem d. The area should be documented and checked during the next inspection Answer: d

    Q 23. What is the hydrostatic test height of this tank based on a minimum thickness found in question 16, as the controlling thickness? a. 24b. 34.2c. 18.6d. Not enough information given(Ht -1)= tmin StE/(2.6D), given tmin =0.217Ht = 24.085, tested to full height 24. Answer = a

  • Charlie Chong/ Fion Zhang

    Q 24. A depression is noted on a section of the bottom near the middle of the east quadrant. The depression measures 5/8 deep, with a diameter of 36 inches. Should a repair be recommended? a. Yes b. No c. Not enough information given d. The tank holds water, no problem BB = 0.37R = 0.55 < 5/8 thus OK, answer: bBB is maximum height of bulge or depth of local depression, in inches;R is radius of inscribed circle in bulged area or local depression, in feet.

    Q 25. If the maximum liquid level in the tank were to be lowered by 5, what is the minimum thickness of the first course? a. 1.73b. .166c. .200d. No change from original design thicknesstmin = 2.6(16)94/23600 = 0.1656, answer = b

  • Charlie Chong/ Fion Zhang

    The following applies to questions 26 through 27 below: Or = 10 years RTbC = .200 RTip = .190 StPr = .002 UPr = .010

    Q 26. Using data from above, calculate MRT. (metal loss from the bottom side corrosion). a. .250 b. .070 c. .002 d. .080 MRT = (Minimum of RTbc or RTip) Or (StPr + UPr) = 0.07!Answer = 10x0.002 = 0.02 answer: cQ 27. Using data from above, calculate MRT. (metal loss from internal corrosion). a. .250 b. .070 c. .002 d. .080 Internal corrosion 10x 0.01=0.1

  • Charlie Chong/ Fion Zhang

    Q 28. The weld ripples of reinforcement of butt-welded joints shall be before _________ radiography. a. removed b. ground flush, with grinding direction parallel to the weld c. ground flush, with grinding direction perpendicular to the weld d. removed if irregularities mask discontinuities answer: d

    Q 29. What is the hydrostatic test height of an in-service welded AST built to API 650, 8th Edition, 82 diameter, 40 tall with a minimum first course thickness of 0.197. The material of construction is A-516, Grade 70 (A 516M Grade 485). a. 40b. 36-2c. 32-8d. 31-6Ht = SEtmin/2.6D +1 = 33000 x 0.197/(2.6x82) +1 = 31.49, answer: d

  • Charlie Chong/ Fion Zhang

    Q 30. For a single-wall material thickness, over 0.375 through 0.50, what is the hole-type designation for a source side penetrameter? a. 15 b. 17 c. 20 d. 25 answer:b

    Q 31. The temperature range to conduct a standard technique liquid penetrant examination is ______. a. 500 F to 1350 Fb. 500 F to 1250 Fc. 700 F to 1150 Fd. 500 F to 800 F

    T-652 Techniques for Standard TemperaturesAs a standard technique, the temperature of the penetrant and the surface of the part to be processed shall not be below 40F (5C) nor above 125F (52C) throughout the examination period. Local heating or cooling is permitted provided the part temperature remains in the range of 40F to 125F (5C to 52C) during the examination. Where it is not practical to comply with these temperature limitations, other temperatures and times may be used, provided theprocedures are qualified as specified in T-653.

  • Charlie Chong/ Fion Zhang

    Q 32. During an MT examination, __________ shall be performed on each area. a. 100% coverage at the required sensitivity b. a calibration of each piece of magnetizing equipment c. at least three separate examinations d. prod spacing of at least 10 ans: a

    Q 33. An AC yoke shall have a lifting power of at least ____________. a. 5lbs. b. 8 lbs. c. 10 lbs. d. 40 lbs.Ans: c

  • Charlie Chong/ Fion Zhang

    Q 34. A DC yoke shall have a lifting power of at least _________. a. 5lbs. b. 8 lbs. c. 10 lbs. d. 40 lbs.Ans:d

    Q 35. A new tank will hold a product with the specific gravity of 1.05; The corrosion allowance is .10; The thickness of the first course is 1 .25 inches; Hydrostatic test stress 25,000 PSI. What is the thickness required for the annular plate? (Note: Include corrosion allowance). a. 5/16b. 11/16c. 3/8 (6/16)d. 7/16Ans: 0.236 + .1 = 0.336 used 3/8 (0.375) answer= c

  • Charlie Chong/ Fion Zhang

    Q 36. A leak is noted 1 1/2 away from the shell-to-bottom weld in the floor of an existing welded tank. The hole in the floor is 4 in diameter. What type of repair, in compliance with API 653, 3rd Edition, should be made?a. Use RBI. Because the product might not contaminate the soil or waterways, no repair is required. b. Weld build-up the area. c. Install a tombstone shaped, welded-on patch plate, intersecting the shell-to-bottom joint at approximately 90. d. Install a non-welded patch plate and fiberglass/epoxy to coat the area. Ans:c

    Q 37. When using the SMAW process, a welder has changed from an F#4 electrode to an F#3 electrode. Does the procedure need to be requalified? a. Yes b. No c. Only if low hydrogen electrodes are used d. API 650 allows this changeQW-404.4 A change from one F-Number in table QW-432 to any other F-umber or to any other filler metal not listed in table QW-432.Ans: b

  • Charlie Chong/ Fion Zhang

    Q 38. During a welder qualification test, for plate coupons, all surfaces (except areas designated discard) shall _______. a. show complete joint penetration with complete fusion of weld metal and base metal b. show no more than 1/3t inadequate penetration c. show no more than 1/3t nonfusion d. be allowed one 5/32 crater crack ans: a

    Q 39. What is the hydrostatic test thickness for a new tank whose diameter is 150, and has a fill height of 40? The shell material is A 36M. a. 0.655 b. 0.611 c. 0.563 d. 0.500

    tmin = 2.6(39)150/(24900) = 0.611 answer: b

  • Charlie Chong/ Fion Zhang

    New Tank

  • Charlie Chong/ Fion Zhang

    Old Chinese Tank

  • Charlie Chong/ Fion Zhang

    Old Japanese Tank

  • Charlie Chong/ Fion Zhang

    Old German Tank

  • Charlie Chong/ Fion Zhang

    Q 40. In order to comply with API 650, the finished surface of a weld reinforcement on plate 1/2 thick, horizontal butt joints, may have a reasonably uniform crown not to exceed ____________ for radiographic examination. a. 1/4b. 3/16c. 1/8d. 1/16 ans: d

    Q 41. If piping near the tank enters the ground, the soil should be excavated ______ inches for inspection. a. 13 b. 36 c. 612 d. Piping is not addressed by any of the documents listed in the API 653 Body of Knowledge.Ans: c

  • Charlie Chong/ Fion Zhang

    Q 42. Floating roofs on new tanks shall be sufficiently buoyant to remain floating after ______. a. Fifteen inches of rainfall in a 24-hour period b. Ten inches of rainfall in a 24-hour period c. Thirty inches of snow in a 24-hour period d. Thirty inches of sand in a 24-hour period

    Q 43. A sudden rapid fracture under stress, where the material exhibits little or no evidence of ductility or plastic deformation, is called _________? a. brittle fracture b. cavitation c. atmospheric corrosion d. caustic corrosion

    C.3.4 Pontoon DesignC.3.4.1 Floating roofs shall have sufficient buoyancy to remain afloat on liquid with a specific gravity of the lower of the minimum design specific gravity or 0.7 and with primary drains inoperative for the following conditions. a)250 mm (10 in.) of rainfall in a 24-hour period over the full horizontal tank area with the roofs intact. This condition does not apply to double-deck roofs provided with emergency drains designed to keep water to a lesser volume that the roofs will safely support. Such emergency drains shall not allow the product to flow onto the roof. NOTE The rainfall rate for sizing the roof drains in C.3.8 may result in a larger accumulated rainfall.

  • Charlie Chong/ Fion Zhang

    Pontoon

  • Charlie Chong/ Fion Zhang

    Q 44. Each floor scanning operator, who only use the bottom scanning equipment, shall receive a minimum of ________ hours of training. a. 8 b. 12 c. 20 d. 40G.4.4 The authorized inspection agency is responsible for training each scanning operator they employ. Eachscanning operator should receive a minimum of 40 hours of training. This training should include: ans: d

    Q 45. Variables in the procedure that can be changed without having to re-qualify the procedure and/or the scanning operators are ________. a. essential variables b. non-essential variables c. qualification tests d. TBEQ Ans: b

  • Charlie Chong/ Fion Zhang

    Questions 46 through 50 apply to the WPS)PQR Procedure which begins on page 12.

    Q46. What is the root face limitation as listed on the attached WPS and PQR? a. 3/32b. 1/8c. No limit d. Not designated Non essential variable

    Q47. If the supporting PQR is used, are the P-nos correct on the attached WPS? a. Yes b. No c. Could be if properly preheated d. Not enough informationP8 is for stainless steel, PQR tested P1 to P1

  • Charlie Chong/ Fion Zhang

    Q48. Is the thickness range on the WPS supported by the PQR? a. Yes b. No c. Requalification is required by API 570 d. Requalification is required by ASME V Range qualified = 0.187~2T

    Q49. Is the attached PQR properly qualified? a. No, because RT is not allowed during PQR qualification b. No, because there are not enough tensile testsc. No, because peening is allowed by B31.3 d. Yes

  • Charlie Chong/ Fion Zhang

    Q50. What should have been the correct number and type of guided bends on the PQR? a. 6 side bends b. 2 face and 2 root bends c. 1 side, 1 face and 1 root bend d. 2 face, 2 root and 4 side bends

  • Page 12 of 36

  • Page 13 of 36

  • Page 14 of 36

  • Page 15 of 36

  • Charlie Chong/ Fion Zhang

    Reference

  • Charlie Chong/ Fion Zhang

    Reference

  • Charlie Chong/ Fion Zhang

    Practice-05API 653 PREPARATORY COURSEFinal Exam Closed Book

  • Charlie Chong/ Fion Zhang

    Please close all materials. The remainder of the exam is Closed Book.

  • Charlie Chong/ Fion Zhang

    Q51. Who has the ultimate responsibility for complying with the provisions of API Standard 653? a. API b. Owner/operator c. Inspector d. Contractor/builder ANS: b

    Q52. If cracks are suspected in nozzles or nozzle welds they should be checked by ______. a. ultrasonic digital thickness gauge b. MT or PT examination c. eddy current testing d. infra-red thermographyANS: b

  • Charlie Chong/ Fion Zhang

    Q53. Localized corrosion due to the concentration of caustic or alkaline salts is ______? a. erosion b. brittle fracture c. caustic corrosion d. phase failure ANS: c

    Q 54. Per API 653, tanks shall have a formal visual inspection once every _____ years or RCA/4N years, whichever is less.

    a. three b. four c. five d. sevenANS: c

  • Charlie Chong/ Fion Zhang

    Q 55. Monthly visual inspections of the external condition of in-service tanks may be performed by ___________. a. API 653 inspectors b. owner/operator personnel c. NDE technicians d. plant managersANS: b

    Q 56. The critical zone for repairs to tank bottoms is that portion of the bottom or annular plate within _______ inches of the inside edge of the shell. a. 3 b. 6 c. 12 d. 24 ANS: a

  • Charlie Chong/ Fion Zhang

    Q 57. On a fixed-type roof, planks long enough to span at least _____ roof rafters should be laid and used as walkways. a. none allowed b. 1 c. 2 d. 3 ANS: c

    Q 58. Cathodic protection surveys are recommended to ensure the effectiveness of cathodic protection. How often should this survey be done? a. Every 10 years b. Every time the tank is empty c. Annually d. Semi-annuallyANS: c

  • Charlie Chong/ Fion Zhang

    Q 59. The deflection of an arc from its normal path because of magnetic forces is _____. a. arc blow b. arc length c. arc strike d. arc angle ANS: a

    Q 60. During the reconstruction of a tank shell, welding operators, welders and welding procedures must be qualified in accordance with _______. a. API 650 b. ASME Section V c. ASME Section IX d. API 1104ANS: c

  • Charlie Chong/ Fion Zhang

    Q 61. Upon completion, the roof of a tank designed to be gas tight shall be tested by which one of the following methods? a. Magnetic particle testing of all welds b. Application of internal air pressure not exceeding the weight of the roof plates and applying a solution suitable for the detection of leaks c. Penetrant testing the weld joints d. Visual inspection of the weld joints ANS: b

    Q 62. In regard to API 653, roof plates corroded to an average thickness of _______ inch in any 100 square inch area shall be repaired or replaced.

    a. less than 0.09 b. 0.09 c. greater than 0.09 d. no API 653 requirement, owners requirementANS: a4.2.1.2 Roof plates corroded to an average thickness of less than 0.09 in. in any 100 in.2 area or roof plates with any holes through the roof plate shall be repaired or replaced.

  • Charlie Chong/ Fion Zhang

    Q 63. A fusion weld made without filler metal is _______. a. brazing b. SMAW weld c. autogenous weld d. SAW weld ANS: c

    Q 64. Each welder making welds on a tank shall be certified by _________. a. erection/fabrication manufacturer b. purchaser c. Nuclear Regulatory Commission d. certified inspectorANS: a

  • Charlie Chong/ Fion Zhang

    Q 65. A discontinuity with a length that is substantially greater than its width is called a ______. a. round discontinuity b. linear discontinuity c. non-linear discontinuity d. rejectable defect ANS: a

    Q 66. A form of corrosion that occurs from moisture associated with atmospheric conditions is called ______ a. brittle fracture b. caustic corrosion c. stress cracking d. atmospheric corrosionANS: d

  • Charlie Chong/ Fion Zhang

    Q 67. Which of the following tanks are used to reduce filling and breathing loss by eliminating vapor space? a. Cone roof tank b. Umbrella-roof tank c. Vapor-dome roof tank d. Floating roof tank ANS: d

    Q 68. Per API 650, external floating roof deck plates having support leg or other rigid penetrations closer than_____ inches to lap weld seams must be full fillet welded not less than 2 inches on 10 inch centers. a. 6 b. 12 c. 14 d. 18ANS:

  • Charlie Chong/ Fion Zhang

    Q 69. Foundation pads that have washed out or settled under the bottoms of atmospheric storage tanks can be repaired by _________. a. pumping in water b. pumping in argon c. pumping in sand, dirt or thin concrete d. pumping in gas ANS: c

    Q 70. When corrosion rates are not known and similar service experience is not available, the actual bottom thickness shall be determined by inspections within the next _____ year(s) of tank operation to establish corrosion rates. a. five b. ten c. three d. oneANS: b

  • Charlie Chong/ Fion Zhang

    Q 71. The mechanical working of metals using impact blows is referred to as ______. a. inclusion b. corrosion c. fatigue d. peeningANS: d

    Q 72. Calcining can occur when concrete has been exposed to ______. a. chemical attack b. sulfate - type alkalis c. chlorides d. high temperature ANS: d

  • Charlie Chong/ Fion Zhang

    Q 73. A contributing factor for determining internal inspection intervals shall be time, not to exceed _____ years for any reason, if an RBI program is not in place. a. 10 b. 5 c. 20 d. 15 ANS: c

    Q 74. Upon completion of welding of the new tank bottom, the welds shall be inspected by which one of the following methods? a. Radiographs b. Vacuum c. Penetrant testing d. Hammer testingANS: b

  • Charlie Chong/ Fion Zhang

    Q 75. The junction of the weld face and the base metal is the __________. a. heat affect zone b. weld toe c. stress riser d. dilution zone ANS: b

    Q 76. Tank plates being welded which do not have proper identification shall be subjected to _______. a. chemical analysis b. UT thickness measurements c. PT testing d. RTtesting ANS: a

  • Charlie Chong/ Fion Zhang

    Q 77. An assembly whose component parts are joined by welding is a_________. a. spool piece b. weldment c. fillet weld d. groove weldANS: b

    Q 78. ______ identifies a procedure for installing a nozzle in the shell of a tank that is in service. a. Repair b. Alteration c. Hot tap d. Reconstruction ANS: c

  • Charlie Chong/ Fion Zhang

    Q 79. Annular bottom plates shall have a radial width that provides at least ________ inches between the inside of the shell and any lap-welded joint in the remainder of the bottom. a. 10 b. 30 c. 24 d. 18 ANS: c

    Q 80. For known materials, all shell plates and bottom plates welded to the shell shall meet, as a minimum, the chemistry and mechanical properties of material specified for the application with regard to thickness and design metal temperature, per ________. a. ASM Requirements b. ASME Requirements c. API 650 Requirements d. ASTMA 7 RequirementsANS: c

  • Charlie Chong/ Fion Zhang

    Q 81. What action should be taken after a flat spot is discovered in the second ring of a 200 diameter AST? a. The shell distortion shall be evaluated b. The area shall be cut out and replaced c. Since no product is leaking out of the area, it may be ignored d. The inspector has the option to repair or ignore ANS: a

    Q 82. Routine in-service visual inspections of the external condition of the tank shall not exceed _______. a. one month b. six months c. one year d. five yearsANS: a

  • Charlie Chong/ Fion Zhang

    Q 83. A separation at the joint root between the work pieces is referred to as a ________. a. gap b. root face c. root edge d. root opening ANS: d

    Q 84. Minimum thickness for tank bottom plate, when there is no means of leak detection and containment, is ________ inch. a. .10 b. .075 c. .15 d. .05ANS: a

  • Charlie Chong/ Fion Zhang

    Q 85. When used, the ultrasonic thickness measurements shall be made at intervals not to exceed ________. a. one month b. one year c. five years, (unknown corrosion rate) d. ten years, (unknown corrosion rate) ANS: c

    Q 86. Cavity-type discontinuities formed by gas entrapment during solidification of the weld are ________. a. cracks b. tungsten inclusion c. slag d. porosityANS: d

  • Charlie Chong/ Fion Zhang

    Q 87. The most likely point of occurrence of cracks in riveted tanks is around _________. a. internal piping b. flanged connections c. roof seals d. rivet holesANS: d

    Q 88. Qualified inspectors shall have education and experience equal to at least one of the following: a. a degree in engineering plus 1 year of experience in inspection of tanks, pressure vessels or piping b. two years of experience in work related field c. two year certificate in technology from technical college d. high school educationANS: a

  • Charlie Chong/ Fion Zhang

    Q 89. The maximum acceptable undercutting of the base metal for vertical butt joints is _______ inch. a. 3/32 b. 1/8 c. 1/64 d. 3/64 ANS: c

    Q 90. When used, ultrasonic thickness measurements shall be made at ____ year intervals after commissioning new tanks. a. 5 b. 7 c. 10 d. 15ANS: 5

  • Charlie Chong/ Fion Zhang

    Q 91. On a reconstructed tank, all new shell joints shall be __________. a. full fillet welded with complete fusion b. butt-welded with complete penetration and complete fusion c. lap-welded with complete penetration and complete fusion d. single grove with backing strip ANS: b

    Q 92. A non-metallic product resulting from the mutual dissolution of flux and non-metallic impurities in some welding processes is __________. a. porosity b. tungsten inclusion c. slag d. crackingANS: c

  • Charlie Chong/ Fion Zhang

    Q 93. A double-welded butt weld is ___________. a. a joint between two abutting parts lying in approximately the same plane b. a joint between two abutting parts lying in approximately the same plane that is welded from both sides c. a joint between two overlapping members in which the overlapping edges of both members are welded with fillet welds d. a fillet weld whose size is equal to the thickness of the thinner joined member ANS: b

    Q 94. All requirements of API 650, _____ shall be considered before changing the service of a tank to operation at temperatures above 200F. a. Appendix M b. Appendix J c. Appendix C d. Appendix KANS: a

  • Charlie Chong/ Fion Zhang

    Q 95. Openings in tank shells larger than required to accommodate a _______ inch flanged or threaded nozzle shall be reinforced. a. one b. two c. three d. four ANS: b

    Q 96. The API 653 standard employs the principles of _________. a. API 650 b. ASME Article 4 c. AWS D1.1 d. API 1104ANS: a

  • Charlie Chong/ Fion Zhang

    Q 97. Qualification test plates for floor scan, with flaws, should be a minimum of ___________ sq. ft.

    a. 20 b. 70 c. 90 d. 150ANS: bG.5 Qualification TestingG.5.1 Qualification Test PlatesG.5.1.1 The qualification test will be performed on a sample tank bottom with designed flaws. The sample tank bottom should be a minimum of 70 ft2 to provide space for the designed flaws. The plate material used to fabricate sample plates may be either new steel or used steel. It should be noted that the results obtained during qualification tests might not be indicative of the results of examinations performed on other plates of differing quality or permeability. When used steel is utilized for qualification purposes, the qualification test acceptance standards recommended in G.5.2 may not be appropriate. The owner/operator should establish its own acceptance standards in such cases.

    Q 98. A fracture-type discontinuity characterized by a sharp tip and high ratio of length to width to opening displacement is referred to as _______. a. crack b. slag c. porosity d. spatter ANS: a

  • Charlie Chong/ Fion Zhang

    Q 99. The acceptability of welds examined by radiography shall be judged by the standards in ______. a. ASME Section V, Division 7 b. ASME Section IX, Paragraph QW191 c. ASME Section VIII, Division 1, Paragraph UW-51 (b) d. API1104 ANS: c

    Q 100. Per API 653, what is the maximum allowable banding, using a vertical 36 sweep board? a. 1b. 1/2c. 3/8d. 3/32ANS: aAPI653: 10.5.5 BandingWith a vertical sweep board 36-in. long, banding shall not exceed 1 in.

  • Charlie Chong/ Fion Zhang

    Q 101. The arrangement of direct current arc welding leads in which the electrode is the negative pole and the work piece is the positive pole of the welding arc is _____? a. DCEN b. DCEP c. AC d. AC/DC ANS: a

    Q 102. Any work on a tank that changes its physical dimensions or configuration is considered a/an ____________. a. reconstruction b. rebuilding c. reworking d. alterationANS: d

  • Charlie Chong/ Fion Zhang

    Q 103. When bottom annular plates are required by paragraph 3.5.1 of API 650, the radial joints shall be radiographed. For single welded joints using a backup bar, one spot radiograph shall be taken on _____ percent of the radial joints