68
Presented by Dr Chris Piddington VertaseFLI The UK experience and its applicability to the Irish market

VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Presented by Dr Chris Piddington

VertaseFLI

The UK experience and its applicability to the Irish market

Page 2: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Brightwater FLIWater

Engineering

ABiC FLIEngineering

Services

3NRGMunicipal

WasteTo Energy

FLI FranceLandfill Lining

Specialist Lining

Vertase FLIRemediation

Lining Applications

FLI Eire Special Projects

World Wide

FLI EireLandfill Lining

The FLI Group

Page 3: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

In-situ Bio

Contaminated Land Capability

Ex-situ Bio

Ex-situ Vapour Extraction

Vapour Extraction

Cement Based

Fixation

Hazardous Waste Pre-Treatment

Hazardous WasteStabilisation

Excavation and Disposal

Surfactant Addition

Thermal Enhancementsand Treatments

Stabilisation

Air Sparging

Pump and Treat

In-situ Chemical

Oxidisation

Free Product Recovery

Biochemical Amendments

Thermal Enhancements

Physical Barriers and Permeable Reactive Barriers

Enhanced Natural

AttenuationDual or Multi Phase Extraction

Page 4: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Presentation Overview

Today I want to present case studies of three of our recent projects.

They are each very different sites, each with different histories, different remedial solutions and different uses post remediation.

However, one common factor is that they all represent remedial solutions equally applicable in the UK as in Ireland.

In each instance the remediation elements were conceived, designed and executed by VertaseFLI

Page 5: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

What is the Irish Market?Within the UK site based remediation has a relatively short track record extending back approximately 20 years.However fair to say that within Ireland there has been limited on site remediation to date.Hard to estimate extent of the contaminated land problem but EPA estimate that there are over 2,500 sites that potentially pose a risk to environmental receptors, including up to 80 disused gasworks sites.In 2006 over 400,000T of contaminated material was exported from development sites, potentially this could have been treatedon site.However there is a growing recognition, aided by evolving European Legislation that on-site remediation represent a cost effective, sustainable and appropriate solution for brownfield sites.The case studies presented all illustrate situations and solutions that are applicable to the Irish market place.

Page 6: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Case Study 1Cannock, Bellway Homes, Pritchard Developments, Former Automotive

Lighting Factory

Page 7: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Large scale demolition and decommission effluent treatment plant.Significant underground structures to be removed.Uplift, crush and recycle all concrete slabs and remove below ground obstructions and foundations.Ex-situ Bioremediation of selected soils from earthworks cut to fill.3 separate in-situ treatment areas for removal of TCE and Chlorinated Solvents.Cut to fill earthworks and provision of piling mats.

Value: £1,000,000 (demolition, remediation and earthworks).Duration 42 Weeks total.Techniques, Air Sparging and Soil Vapour Extraction, Ex situ biological treatment.

Reclamation Strategy

Page 8: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000
Page 9: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Warehouse Facility to be Demolished

Page 10: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Ongoing demolition with careful segregation and recycling of materials

Page 11: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Below ground structures and basements requiring removal

Page 12: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Concrete slab lifted, underlying soils chemically tested

Page 13: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Concrete slab crushed, tested and re-used on site.

Page 14: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000
Page 15: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Treatment Well Installation and Well Monitoring Works

Page 16: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

System Installation and Surface of Vapour Recovery Trenches

Page 17: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Process Plant including effluent treatment

Page 18: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Schematic of Treatment Configuration

Page 19: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Well Monitoring Data.

Page 20: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Cannock Lakeside Area 1 Cumulative Removal (kg)

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

0 5 10 15 20 25

Week No.

KG

rem

oved

Cannock Lakeside Area 1 Mass Removal (kg/week)

0

5

10

15

20

25

30

0 5 10 15 20 25Week No.

KG

rem

oved

Cannock Lakeside Area 2 Cumulative Removal

0

10

20

30

40

50

60

0 2 4 6 8 10 12 14 16 18 20Week No.

KG

rem

oved

Cannock Lakeside Area 2 Mass Removal (kg/week)

0

5

10

15

20

25

0 5 10 15 20 25 30

Week No.

KG

rem

oved

Treatment system recovery data.

Page 21: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Earthworks to achieve site development levels

Page 22: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Case Study 2Former Chemical & Tar Works, Cadishead, Manchester

Page 23: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Scheme Headlines

o Value: £3,200,000

o Site Area: 65,000m2

o Contaminated soil: 120,000m3

o Contaminants: Tar, Oils, Diesel, Naphthalene, BTEX, Phenol

o Geology: Made ground over Alluvial Silts over Sandstone

o Groundwater plumes: 3

o Development plans: 380 New Homes

o Timescale: 70 weeks

o Terms: Lump Sum All Risk

Page 24: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Soil Problems

Site Soils Contaminated With: General Oils and HydrocarbonsPAH’sPhenolsBTEXNaphthalene

From Surface to 5 Metres:

Total Volume = 120,000m3

Geotechnically Unsuitable = 60,000m3

Chemically Unsuitable = 120,000m3

Page 25: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Ground Water ProblemsShallow groundwater within made ground severely impactedFree product over significant area of the site

Contaminated with: PhenolsPAHHydrocarbonsBTEXNaphthaleneCreosoteTars

Deep Groundwater 5-8m below ground level

Contaminated with: PhenolsNaphthaleneBTEX

Page 26: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Reclamation StrategyComplete demolition and re-use all available materials on-site wherever possible

Recover all effluent from underground structures.

Gain access to shallow perched effluent table for dewatering and treatment on site

Excavate contaminated soils, characterise on-site and process for treatment

wherever possible.

Segregate materials for treatment by biological methods, ex-situ vapour recovery,

ex-situ oxidation or off site disposal.

Remediate deeper groundwater and remove as much mass as practicable.

Provide capillary break layer and levels at the site to allow for clean cover layer.

Restore site for Housing, with detailed geotechnical specification to allow for no

geotechnical abnormals.

Page 27: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Pre-Remediation Planning and PhasingPetroleum Contamination 0.5 to 1m Phased Works Plan

Page 28: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Sequence of Works

Phase 5 (48 weeks)

Installation and operation of 3 dedicated in-situ systems to treat deeper groundwater plumes.

One plume general hydrocarbons

One plume Phenol and xylene

One plume naphthalene

Systems installed beneath Bio treatment beds

Phase 1 (4 weeks)

Mobilise water treatment plant

Dig Grips across site to collect free oils and water

Dewater made ground for excavation

Phase 2 (4 weeks)

Demolish remaining buildings

Uplift slabs

Remove foundations

Recycle and treat hard standing

Phase 3 (40 weeks)

Excavate site in progressive manner

Sort and prepare for Bio-treatment

Dispose untreatable contaminated soils

Phase 4 (10 weeks)

Validate and re-compact

Page 29: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Practical Aspects: Main Challenges

Contaminated from Surface to 5 m above water tableContaminated effluent throughout made groundGeotechnically poor materialsWhole footprint of the site was contaminated above targetsStrict controls on discharge of water to sewerResidential end useRestricted lorry movements and accessResidential properties close to siteDifficult soilsDeep excavations required

Page 30: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Demolition of buildings, Thorough soft strip of building first with waste segregation, collapse steel structure, collect, gauge and send steel for recycling.

Page 31: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Segregate hard materials and separate from contaminated hard for re-use on site.

Page 32: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Carefully breaking out structures separating hard from soft materials. Hard materials for segregation and processing, on site.

Page 33: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Segregating grossly contaminated pipe runs

Page 34: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

typical below ground drainage run. Note contamination inside and outside the pipe

Page 35: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Recovering unusable materials for off site disposal from effluent pit

Page 36: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Typical surface effluent for collection and treatment on site

Page 37: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Recovering perched groundwater/effluent

Page 38: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Selective excavation, key to maximising treatment efficiency and minimising costs.

Page 39: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Planned, phased remediation, with excavation, pumping, treatment beds and validation all running concurrently.

Page 40: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Bespoke modular groundwater treatment plant for treatment of effluent. Allows for re-use on many sites.

Page 41: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Latest, most efficient screens for processing to maximise reuse of materials.

Page 42: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Ex-situ Biological Treatment Beds

Page 43: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Lining and turning treatment windrows

Page 44: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Reduced Level installation of Naphthalene in-situ treatment

Page 45: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

In-situ Installation of Dual Phase System.

Page 46: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Naphthalene sparging and vapour recovery units.

Page 47: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Ex-situ Oxidation of recalcitrant contamination just above remediation target.

Page 48: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Restoration and compaction

Page 49: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Knotweed, treated and re-incorporated into POS area.

Page 50: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Naphthalene at in-situ 1

0100200300400500600700800900

1000

0 10 20 30 40 50 60

Week sampled

Nap

htha

lene

con

tent

ug/

l

TPH Concentrations in In-situ 2

0

10

20

30

40

50

60

20 25 30 35 40 45 50

Week sampled

TPH

cont

ent m

g/l

PID readings from exhaust on zone 1 in-situ system (Naphthalene Plume)

0.001

0.01

0.1

1

10

100

1000

10000

0 50 100 150 200 250 300 350 400 450

Days

VOC

/SVO

Cs'

(Nap

htha

lene

) ppm

Sustainability of treatment Versus Targets for remediation. A difficult decision for Regulators!

Page 51: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Case Study 3Enhanced Anaerobic Degradation, Killingworth, Newcastle-Upon-Tyne

Page 52: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Value: £200,000 Duration: ongoingSolution: Enhanced and Augmented in-situ Anaerobic degradation

• High levels of TCE in shallow groundwater

• Large plume area

• Ongoing Issues regarding spillage

• 24hr, 360 days year operational plant.

• Extremely confined access

• Concerned American parent company

Scheme Headlines

Page 53: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

• Contaminated with Trichloroethene TCE (39,000ug/l).

• Designed in-situ recirculation plant.

• Abstraction, dosing, and injection of site groundwater with Emulsified Soya Bean Oil (EVO) and Sodium Lactate.

Page 54: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

PrincipalReductive de-halogenation

TCEAnaerobic

DCEAnaerobic

VCAnaerobic / aerobic?

Ethene/Ethane/CO2

Some Chemistry;

Page 55: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Installed Borehole location plan

Page 56: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Site Injection Equipment

• Unit containing injection and abstraction pumps

• Emulsified Soya Bean Oil (EVO) inside bund

Page 57: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Injection and Abstraction System

Page 58: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Site Injection and recirculation Equipment

Abstraction well

Injection wells

Page 59: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

KB-1 Injection

KB-1 cultureO2 Free Nitrogen

Anaerobic injection of KB-1 on completion of injection works

Page 60: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

KB-1 Injection and associated monitoring

Page 61: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

BH204

0

250

500

750

1,000

1,250

24/0

9/20

08

14/1

0/20

08

03/1

1/20

08

23/1

1/20

08

13/1

2/20

08

02/0

1/20

09

22/0

1/20

09

11/0

2/20

09

Time

Con

cent

ratio

n μg

/l

TCE

DCE

VC

Page 62: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

BH119

01,0002,0003,0004,0005,0006,0007,0008,0009,000

10,00011,00012,00013,00014,00015,000

22/0

5/20

08

11/0

7/20

08

30/0

8/20

08

19/1

0/20

08

08/1

2/20

08

27/0

1/20

09

Time

Con

cent

ratio

n μg

/l

TCE

DCE

VC

Page 63: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Changes in TCE, DCE and VC Concentration

1602,5071.215/12/2008<103601,00001/10/2008

BH206

191,2032.315/12/2008<10281,40001/10/2008

BH202

8.25,314<1.005/08/2008371,00017,00015/07/2008

BH112

711,9112.618/11/2008352932017/07/2008

BH109

44012,0001,80018/11/20082405,30038,00006/08/2008

MW1

VCDCETCEDateConcentration μg/l

Well

Page 64: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Troll 9500 Water Level Data

Page 65: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Troll 9500 ORP (REDOX) Data

Page 66: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

On completion of current injection works:

• Abstracted and injected 243,330 litres of groundwater.

• Injected 11,854 litres of EVO.

• Injection of 165kg of 60% sodium lactate.

• Injected 71kg of KB-1 into 26no. Wells.

Ground conditions:

• Dissolved Oxygen <0.5 mg/l.

• Redox Negative (-50 greater).

• Anaerobic ground conditions achieved across plume.

•Degradation & monitoring ongoing but decreased TCE levels and increased DCE demonstrate success of augmentation to date.

Summary

Page 67: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Summary

Project 2. Former Tar Works via ex-situ bio and in-situ techniques for residential end use for EP

Project 1. Former automotive manufacturer via in-situ Air Sparging and Vapour Extraction for mixed end use.

Project 3. Active Manufacturing site via In-situ anaerobic degradation for continued operation without disruption to

business for American Manufacturer

Page 68: VertaseFLI The UK experience and its applicability to the ... Brownfield... · BH112 18/11/2008 2.6 1,911 71 17/07/2008 320 29 35 BH109 18/11/2008 1,800 12,000 440 06/08/2008 38,000

Thanks For Listening

Chris Piddington

Contact Us: