Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Presented by Dr Chris Piddington
VertaseFLI
The UK experience and its applicability to the Irish market
Brightwater FLIWater
Engineering
ABiC FLIEngineering
Services
3NRGMunicipal
WasteTo Energy
FLI FranceLandfill Lining
Specialist Lining
Vertase FLIRemediation
Lining Applications
FLI Eire Special Projects
World Wide
FLI EireLandfill Lining
The FLI Group
In-situ Bio
Contaminated Land Capability
Ex-situ Bio
Ex-situ Vapour Extraction
Vapour Extraction
Cement Based
Fixation
Hazardous Waste Pre-Treatment
Hazardous WasteStabilisation
Excavation and Disposal
Surfactant Addition
Thermal Enhancementsand Treatments
Stabilisation
Air Sparging
Pump and Treat
In-situ Chemical
Oxidisation
Free Product Recovery
Biochemical Amendments
Thermal Enhancements
Physical Barriers and Permeable Reactive Barriers
Enhanced Natural
AttenuationDual or Multi Phase Extraction
Presentation Overview
Today I want to present case studies of three of our recent projects.
They are each very different sites, each with different histories, different remedial solutions and different uses post remediation.
However, one common factor is that they all represent remedial solutions equally applicable in the UK as in Ireland.
In each instance the remediation elements were conceived, designed and executed by VertaseFLI
What is the Irish Market?Within the UK site based remediation has a relatively short track record extending back approximately 20 years.However fair to say that within Ireland there has been limited on site remediation to date.Hard to estimate extent of the contaminated land problem but EPA estimate that there are over 2,500 sites that potentially pose a risk to environmental receptors, including up to 80 disused gasworks sites.In 2006 over 400,000T of contaminated material was exported from development sites, potentially this could have been treatedon site.However there is a growing recognition, aided by evolving European Legislation that on-site remediation represent a cost effective, sustainable and appropriate solution for brownfield sites.The case studies presented all illustrate situations and solutions that are applicable to the Irish market place.
Case Study 1Cannock, Bellway Homes, Pritchard Developments, Former Automotive
Lighting Factory
Large scale demolition and decommission effluent treatment plant.Significant underground structures to be removed.Uplift, crush and recycle all concrete slabs and remove below ground obstructions and foundations.Ex-situ Bioremediation of selected soils from earthworks cut to fill.3 separate in-situ treatment areas for removal of TCE and Chlorinated Solvents.Cut to fill earthworks and provision of piling mats.
Value: £1,000,000 (demolition, remediation and earthworks).Duration 42 Weeks total.Techniques, Air Sparging and Soil Vapour Extraction, Ex situ biological treatment.
Reclamation Strategy
Warehouse Facility to be Demolished
Ongoing demolition with careful segregation and recycling of materials
Below ground structures and basements requiring removal
Concrete slab lifted, underlying soils chemically tested
Concrete slab crushed, tested and re-used on site.
Treatment Well Installation and Well Monitoring Works
System Installation and Surface of Vapour Recovery Trenches
Process Plant including effluent treatment
Schematic of Treatment Configuration
Well Monitoring Data.
Cannock Lakeside Area 1 Cumulative Removal (kg)
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
0 5 10 15 20 25
Week No.
KG
rem
oved
Cannock Lakeside Area 1 Mass Removal (kg/week)
0
5
10
15
20
25
30
0 5 10 15 20 25Week No.
KG
rem
oved
Cannock Lakeside Area 2 Cumulative Removal
0
10
20
30
40
50
60
0 2 4 6 8 10 12 14 16 18 20Week No.
KG
rem
oved
Cannock Lakeside Area 2 Mass Removal (kg/week)
0
5
10
15
20
25
0 5 10 15 20 25 30
Week No.
KG
rem
oved
Treatment system recovery data.
Earthworks to achieve site development levels
Case Study 2Former Chemical & Tar Works, Cadishead, Manchester
Scheme Headlines
o Value: £3,200,000
o Site Area: 65,000m2
o Contaminated soil: 120,000m3
o Contaminants: Tar, Oils, Diesel, Naphthalene, BTEX, Phenol
o Geology: Made ground over Alluvial Silts over Sandstone
o Groundwater plumes: 3
o Development plans: 380 New Homes
o Timescale: 70 weeks
o Terms: Lump Sum All Risk
Soil Problems
Site Soils Contaminated With: General Oils and HydrocarbonsPAH’sPhenolsBTEXNaphthalene
From Surface to 5 Metres:
Total Volume = 120,000m3
Geotechnically Unsuitable = 60,000m3
Chemically Unsuitable = 120,000m3
Ground Water ProblemsShallow groundwater within made ground severely impactedFree product over significant area of the site
Contaminated with: PhenolsPAHHydrocarbonsBTEXNaphthaleneCreosoteTars
Deep Groundwater 5-8m below ground level
Contaminated with: PhenolsNaphthaleneBTEX
Reclamation StrategyComplete demolition and re-use all available materials on-site wherever possible
Recover all effluent from underground structures.
Gain access to shallow perched effluent table for dewatering and treatment on site
Excavate contaminated soils, characterise on-site and process for treatment
wherever possible.
Segregate materials for treatment by biological methods, ex-situ vapour recovery,
ex-situ oxidation or off site disposal.
Remediate deeper groundwater and remove as much mass as practicable.
Provide capillary break layer and levels at the site to allow for clean cover layer.
Restore site for Housing, with detailed geotechnical specification to allow for no
geotechnical abnormals.
Pre-Remediation Planning and PhasingPetroleum Contamination 0.5 to 1m Phased Works Plan
Sequence of Works
Phase 5 (48 weeks)
Installation and operation of 3 dedicated in-situ systems to treat deeper groundwater plumes.
One plume general hydrocarbons
One plume Phenol and xylene
One plume naphthalene
Systems installed beneath Bio treatment beds
Phase 1 (4 weeks)
Mobilise water treatment plant
Dig Grips across site to collect free oils and water
Dewater made ground for excavation
Phase 2 (4 weeks)
Demolish remaining buildings
Uplift slabs
Remove foundations
Recycle and treat hard standing
Phase 3 (40 weeks)
Excavate site in progressive manner
Sort and prepare for Bio-treatment
Dispose untreatable contaminated soils
Phase 4 (10 weeks)
Validate and re-compact
Practical Aspects: Main Challenges
Contaminated from Surface to 5 m above water tableContaminated effluent throughout made groundGeotechnically poor materialsWhole footprint of the site was contaminated above targetsStrict controls on discharge of water to sewerResidential end useRestricted lorry movements and accessResidential properties close to siteDifficult soilsDeep excavations required
Demolition of buildings, Thorough soft strip of building first with waste segregation, collapse steel structure, collect, gauge and send steel for recycling.
Segregate hard materials and separate from contaminated hard for re-use on site.
Carefully breaking out structures separating hard from soft materials. Hard materials for segregation and processing, on site.
Segregating grossly contaminated pipe runs
typical below ground drainage run. Note contamination inside and outside the pipe
Recovering unusable materials for off site disposal from effluent pit
Typical surface effluent for collection and treatment on site
Recovering perched groundwater/effluent
Selective excavation, key to maximising treatment efficiency and minimising costs.
Planned, phased remediation, with excavation, pumping, treatment beds and validation all running concurrently.
Bespoke modular groundwater treatment plant for treatment of effluent. Allows for re-use on many sites.
Latest, most efficient screens for processing to maximise reuse of materials.
Ex-situ Biological Treatment Beds
Lining and turning treatment windrows
Reduced Level installation of Naphthalene in-situ treatment
In-situ Installation of Dual Phase System.
Naphthalene sparging and vapour recovery units.
Ex-situ Oxidation of recalcitrant contamination just above remediation target.
Restoration and compaction
Knotweed, treated and re-incorporated into POS area.
Naphthalene at in-situ 1
0100200300400500600700800900
1000
0 10 20 30 40 50 60
Week sampled
Nap
htha
lene
con
tent
ug/
l
TPH Concentrations in In-situ 2
0
10
20
30
40
50
60
20 25 30 35 40 45 50
Week sampled
TPH
cont
ent m
g/l
PID readings from exhaust on zone 1 in-situ system (Naphthalene Plume)
0.001
0.01
0.1
1
10
100
1000
10000
0 50 100 150 200 250 300 350 400 450
Days
VOC
/SVO
Cs'
(Nap
htha
lene
) ppm
Sustainability of treatment Versus Targets for remediation. A difficult decision for Regulators!
Case Study 3Enhanced Anaerobic Degradation, Killingworth, Newcastle-Upon-Tyne
Value: £200,000 Duration: ongoingSolution: Enhanced and Augmented in-situ Anaerobic degradation
• High levels of TCE in shallow groundwater
• Large plume area
• Ongoing Issues regarding spillage
• 24hr, 360 days year operational plant.
• Extremely confined access
• Concerned American parent company
Scheme Headlines
• Contaminated with Trichloroethene TCE (39,000ug/l).
• Designed in-situ recirculation plant.
• Abstraction, dosing, and injection of site groundwater with Emulsified Soya Bean Oil (EVO) and Sodium Lactate.
PrincipalReductive de-halogenation
TCEAnaerobic
DCEAnaerobic
VCAnaerobic / aerobic?
Ethene/Ethane/CO2
Some Chemistry;
Installed Borehole location plan
Site Injection Equipment
• Unit containing injection and abstraction pumps
• Emulsified Soya Bean Oil (EVO) inside bund
Injection and Abstraction System
Site Injection and recirculation Equipment
Abstraction well
Injection wells
KB-1 Injection
KB-1 cultureO2 Free Nitrogen
Anaerobic injection of KB-1 on completion of injection works
KB-1 Injection and associated monitoring
BH204
0
250
500
750
1,000
1,250
24/0
9/20
08
14/1
0/20
08
03/1
1/20
08
23/1
1/20
08
13/1
2/20
08
02/0
1/20
09
22/0
1/20
09
11/0
2/20
09
Time
Con
cent
ratio
n μg
/l
TCE
DCE
VC
BH119
01,0002,0003,0004,0005,0006,0007,0008,0009,000
10,00011,00012,00013,00014,00015,000
22/0
5/20
08
11/0
7/20
08
30/0
8/20
08
19/1
0/20
08
08/1
2/20
08
27/0
1/20
09
Time
Con
cent
ratio
n μg
/l
TCE
DCE
VC
Changes in TCE, DCE and VC Concentration
1602,5071.215/12/2008<103601,00001/10/2008
BH206
191,2032.315/12/2008<10281,40001/10/2008
BH202
8.25,314<1.005/08/2008371,00017,00015/07/2008
BH112
711,9112.618/11/2008352932017/07/2008
BH109
44012,0001,80018/11/20082405,30038,00006/08/2008
MW1
VCDCETCEDateConcentration μg/l
Well
Troll 9500 Water Level Data
Troll 9500 ORP (REDOX) Data
On completion of current injection works:
• Abstracted and injected 243,330 litres of groundwater.
• Injected 11,854 litres of EVO.
• Injection of 165kg of 60% sodium lactate.
• Injected 71kg of KB-1 into 26no. Wells.
Ground conditions:
• Dissolved Oxygen <0.5 mg/l.
• Redox Negative (-50 greater).
• Anaerobic ground conditions achieved across plume.
•Degradation & monitoring ongoing but decreased TCE levels and increased DCE demonstrate success of augmentation to date.
Summary
Summary
Project 2. Former Tar Works via ex-situ bio and in-situ techniques for residential end use for EP
Project 1. Former automotive manufacturer via in-situ Air Sparging and Vapour Extraction for mixed end use.
Project 3. Active Manufacturing site via In-situ anaerobic degradation for continued operation without disruption to
business for American Manufacturer
Thanks For Listening
Chris Piddington
Contact Us: