TEYSEER CONTRACTING COMPANY /
CONSOLIDATED CONTRACTORS GROUP S.A.L. (OFFSHORE)
(CCC) JV
New Port Project
Container Terminal, Infrastructure and Utility Buildings
Contract No.: NPP/0026
Page 1 of 2
Title: New Doha Port Project
Participants
S.No Name Designation Status
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Edgardo De Francia
Ronald Marteja
Arnel L. Reyes
Regino O. Rocamora
Manu S. Pillai
Ravindra Babu
Sajan Peter
F. Aquino
Joel Catubig
Vinay Varghese
Arun Kumar
Muzzafar
Rahim Batcha
Jarnail Singh
Mohammed Abutaha
Bader Eldeen Jarrar
Amr Mahmoud Hussein Selem
Ranjeet Kumar
V. Prabakaran
HSE Officer
HSE Officer
HSE Officer
Sr. HSE Officer
HSE Officer
HSE Officer
HSE Officer
HSE Officer
HSE Officer
HSE Officer
ERT Leader
Sr. HSE Officer
Sr. HSE Trainer
HSE Officer
Dy. HSE Manager
Sr. Environmental Officer
Sr. HSE Officer
Sr. HSE Trainer
HSE Manager
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Present
Absentees:
1 Dionision Panganiban HSE Officer
Distribution As per the direction
Attachment Weekly HSE Officers Minutes of Meeting
Prepared By Suresh Babu
Minutes of Internal Weekly HSE Officers Meeting No. 16
02.03.2014
Date: 2nd March, 2014 Time: 16:00
Location: DPCT Training Room
TEYSEER CONTRACTING COMPANY /
CONSOLIDATED CONTRACTORS GROUP S.A.L. (OFFSHORE)
(CCC) JV
New Port Project
Container Terminal, Infrastructure and Utility Buildings
Contract No.: NPP/0026
Page 2 of 2
Next Meeting: 17th Weekly HSE Meeting will be held on 9th March, 2014 @ 4 pm at
Main Office HSE Training Room
Minutes of Meeting No. 16
S.No Description Action 1 The meeting started at 4 pm and is chaired by HSE Manager
2 Ranjeet – Sr. Trainer shared his safety moments on Welding activity All to note
3 Last Minutes of Meeting were discussed elaborately and recorded. All HSE
Officers
4
HSE Manager has briefed the last week 2 incidents (RWC and
RTA) vide the presentation of slides for the information and
precautions to be taken by the HSE Officers to avoid such incidents
in future
All HSE Officers
5 Various lagging items raised in the last HSE Management Meeting
were discussed in detail and the relevant HSE Officers clarified the
reasons and the precautions required.
All HSE Officers
6
Sign ages - Lack of sign ages were reported by the Management on
Site. This was discussed and came to a conclusion that the
manpower and the resources has to be provided to HSE
Department, in order to dedicate a Carpenter and Helper for the
preparation/alterations of signs required for the Project. At present
such facility is not available.
HSE Manager
7
Banks Man ID – To be prepared internally - HSE Manager
authorized Ranjeet – Sr. HSE Trainer – to take necessary measures
to prepare the ID at the very earliest for the Banks Man those who
had training.
HSE Manager
8
Confine Space Training to be improved. Dy. HSE Manager
suggested calling PMV to arrange ventilation, etc. to be provided.
Until such action is taken, the training to be stopped. Since last week
no training is conducted.
HSE Manager
9
Mr. Bader Jarrar draws the attention to the work being done after the
duty hours and on lunch time without the coverage of HSE Officers.
He suggested that the Construction Team should inform in advance
to HSE with regard to the activity they are going to carry out after the
duty hours, in order to take sufficient measures to post the required
HSE Officers to cover the job.
HSE Manager
10 Heat Stress – Flag system to be established. Required Items to be
ordered without delay. HSE Manager
11 Mr. Bader Jarrar pointed out the non availability of Reflection Signs
for Night Works. Action to be taken without delay HSE Manager
12 The meeting adjourned by 5 pm