TO: KOICA Representative Attention: KIM SANG JUN Deputy Representative RO HI YOUL TOPEC CM Subject: Document Drawing Calculation Quality Document Type Sample Catalogue Report Method Statement Proposed Review Information For Approved Record 1 = No. Objection Action 2 = No. Objection with Comment Status 4 = Objection 5 = Return to Contractor (Resubmit) KOICA's Comment: Received by Date: Reviewed by Position: Approved by Project Manager/ HWASHIN TAI GONE, WON Position: SUBMITTAL FORM BATHEAY REFERRAL HOSPITAL PROJECT Weekly Progress Report (WR41) 20-Oct-2013 HSBA-110 Submission Date: Submission No.: Schedule FOR KOICA USE Thank you for your good cooperation, We would like to submit you the Weekly Progress Report (WR41) for October 2013. Please find attached report.

Weekly Progress Report.pdf

Embed Size (px)

DESCRIPTION

It is the full set of weekly progress report in building construction company. It can be used as the general form of weekly report.

Citation preview

Page 1: Weekly Progress Report.pdf

TO: KOICA Representative

Attention: KIM SANG JUN Deputy Representative

RO HI YOUL TOPEC CM

Subject: Document Drawing

Calculation Quality Document

Type Sample Catalogue

Report Method Statement

Proposed Review Information

For Approved Record

1 = No. Objection

Action 2 = No. Objection with Comment

Status 4 = Objection

5 = Return to Contractor (Resubmit)

KOICA's Comment: Received by

Date:

Reviewed by

Position:

Approved by

Project Manager/ HWASHIN TAI GONE, WON Position:

SUBMITTAL FORM

BATHEAY REFERRAL HOSPITAL PROJECT

Weekly Progress Report (WR41)

20-Oct-2013

HSBA-110

Submission Date:

Submission No.:

Schedule

FOR KOICA USE Thank you for your good cooperation,

We would like to submit you the Weekly Progress Report (WR41) for October 2013.

Please find attached report.

Page 2: Weekly Progress Report.pdf

DESCRIPTION THIS WEEK (2013.10.13-10.19) NEXT WEEK (2013.10.20-10.26) REMARK

1. Site Survey Work 1. Site Survey Work

2. Gutter Canopy Formwork & Rebar Work 2. Gutter Canopy Concrete

TEMPORARY WORK 3. Roof Floor of Mechanical Room Beam & Slab Rebar Work 3. Roof Floor of Mechanical Room Beam & Slab Concrete

CONCRETE WORK 4. Under Roof Floor Column Part B Formwork 4. Under Roof Floor Column Part B Concrete

& MASONRY WORK 5. Line Marking for Ground Floor Brick Work 5. Line Marking for Ground Floor Brick Work

6. Laying Brick Work for Ground Floor 6. Laying Brick Work for Ground Floor

7. Install Air-con Pipe for Ground Floor 7. Install Air-con Pipe for Ground Floor

8. Curing Water for Under Roof Floor 8. Curing Water for Under Roof Floor

SAFETY STATUS None

PERCENTAGE (DONE/PLAN) ( 35.80% / 40.10% )

BATHEAY REFERRAL HOSPITAL PROJECT

SPECIAL ITEMS

WEEKLY PROGRESS REPORT (WR41)

Page 3: Weekly Progress Report.pdf

9/1-9/7 9/8-9/14 9/15-9/21 9/22-9/28 9/29-10/5 10/6-10/12 10/13-10/19 10/20-10/26 10/27-11/2 11/3-11/9 11/10-11/16 11/17-11/23 11/24-11/30

Line marking

Concrete curing

Form support

External Scaffolding

Earth work Finished

Footing con'c Finished

Level extension work Finished

Ground floor con'c Finished

First floor con'c Finished

Under roof con'c

2nd floor slab con'c

Roof column con'c

Steel frame work

Masonry work

Tiling work

Carpentry work

Roofing work

Metal work

Plaster work

Door & window work

27.10 28.90 30.70 32.70 34.50 37.30 40.10 42.90 45.70 49.15 52.60 56.05 59.5024.80 25.30 26.60 29.80 31.20 32.70 35.80

MECHANICAL WORKS

ELECTRICAL WORKS

PERCENTAGE (Plan/Done)

ARCH

ITEC

TURA

L W

ORK

S

Site cleaning

Date: 30-Sep-2013

DESCRIPTIONSEPTEMBER OCTOBER NOVEMBER

REMARK

MONTHLY SCHEDULE (OCTOBER)

Page 4: Weekly Progress Report.pdf

1 2UNDER ROOF FLOOR COLUMN FORMWORK UNDER ROOF FLOOR COLUMN FORMWORK

DATE: 14-Oct-2013 DATE: 15-Oct-2013

SITE PHOTOS

Page 5: Weekly Progress Report.pdf

3 4

DATE: 15-Oct-2013 DATE: 17-Oct-2013

BRICK WORK INSTRUCTION MEETINGGUTTER CANOPY FORMWORK

SITE PHOTOS

Page 6: Weekly Progress Report.pdf

5 6LAYING BRICK WORK FOR GROUND FLOOR LAYING BRICK WORK FOR GROUND FLOOR

DATE: 17-Oct-2013 DATE: 19-Oct-2013

SITE PHOTOS

Page 7: Weekly Progress Report.pdf

7 8

DATE: 18-Oct-2013 DATE: 19-Oct-2013

ROOF FLOOR OF MECHANICAL ROOM BEAM REBAR WORK ROOF FLOOR OF MECHANICAL ROOM BEAM & SLAB REBAR WORK

SITE PHOTOS