Upload
heak-hor
View
169
Download
5
Tags:
Embed Size (px)
DESCRIPTION
It is the full set of weekly progress report in building construction company. It can be used as the general form of weekly report.
Citation preview
TO: KOICA Representative
Attention: KIM SANG JUN Deputy Representative
RO HI YOUL TOPEC CM
Subject: Document Drawing
Calculation Quality Document
Type Sample Catalogue
Report Method Statement
Proposed Review Information
For Approved Record
1 = No. Objection
Action 2 = No. Objection with Comment
Status 4 = Objection
5 = Return to Contractor (Resubmit)
KOICA's Comment: Received by
Date:
Reviewed by
Position:
Approved by
Project Manager/ HWASHIN TAI GONE, WON Position:
SUBMITTAL FORM
BATHEAY REFERRAL HOSPITAL PROJECT
Weekly Progress Report (WR41)
20-Oct-2013
HSBA-110
Submission Date:
Submission No.:
Schedule
FOR KOICA USE Thank you for your good cooperation,
We would like to submit you the Weekly Progress Report (WR41) for October 2013.
Please find attached report.
√
√
DESCRIPTION THIS WEEK (2013.10.13-10.19) NEXT WEEK (2013.10.20-10.26) REMARK
1. Site Survey Work 1. Site Survey Work
2. Gutter Canopy Formwork & Rebar Work 2. Gutter Canopy Concrete
TEMPORARY WORK 3. Roof Floor of Mechanical Room Beam & Slab Rebar Work 3. Roof Floor of Mechanical Room Beam & Slab Concrete
CONCRETE WORK 4. Under Roof Floor Column Part B Formwork 4. Under Roof Floor Column Part B Concrete
& MASONRY WORK 5. Line Marking for Ground Floor Brick Work 5. Line Marking for Ground Floor Brick Work
6. Laying Brick Work for Ground Floor 6. Laying Brick Work for Ground Floor
7. Install Air-con Pipe for Ground Floor 7. Install Air-con Pipe for Ground Floor
8. Curing Water for Under Roof Floor 8. Curing Water for Under Roof Floor
SAFETY STATUS None
PERCENTAGE (DONE/PLAN) ( 35.80% / 40.10% )
BATHEAY REFERRAL HOSPITAL PROJECT
SPECIAL ITEMS
WEEKLY PROGRESS REPORT (WR41)
9/1-9/7 9/8-9/14 9/15-9/21 9/22-9/28 9/29-10/5 10/6-10/12 10/13-10/19 10/20-10/26 10/27-11/2 11/3-11/9 11/10-11/16 11/17-11/23 11/24-11/30
Line marking
Concrete curing
Form support
External Scaffolding
Earth work Finished
Footing con'c Finished
Level extension work Finished
Ground floor con'c Finished
First floor con'c Finished
Under roof con'c
2nd floor slab con'c
Roof column con'c
Steel frame work
Masonry work
Tiling work
Carpentry work
Roofing work
Metal work
Plaster work
Door & window work
27.10 28.90 30.70 32.70 34.50 37.30 40.10 42.90 45.70 49.15 52.60 56.05 59.5024.80 25.30 26.60 29.80 31.20 32.70 35.80
MECHANICAL WORKS
ELECTRICAL WORKS
PERCENTAGE (Plan/Done)
ARCH
ITEC
TURA
L W
ORK
S
Site cleaning
Date: 30-Sep-2013
DESCRIPTIONSEPTEMBER OCTOBER NOVEMBER
REMARK
MONTHLY SCHEDULE (OCTOBER)
1 2UNDER ROOF FLOOR COLUMN FORMWORK UNDER ROOF FLOOR COLUMN FORMWORK
DATE: 14-Oct-2013 DATE: 15-Oct-2013
SITE PHOTOS
3 4
DATE: 15-Oct-2013 DATE: 17-Oct-2013
BRICK WORK INSTRUCTION MEETINGGUTTER CANOPY FORMWORK
SITE PHOTOS
5 6LAYING BRICK WORK FOR GROUND FLOOR LAYING BRICK WORK FOR GROUND FLOOR
DATE: 17-Oct-2013 DATE: 19-Oct-2013
SITE PHOTOS
7 8
DATE: 18-Oct-2013 DATE: 19-Oct-2013
ROOF FLOOR OF MECHANICAL ROOM BEAM REBAR WORK ROOF FLOOR OF MECHANICAL ROOM BEAM & SLAB REBAR WORK
SITE PHOTOS