Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Period: 3/19/20 - 3/25/20
Community High School District 99
Master Facility Plan Implementation
Wight Construction Services2500 North Frontage RoadDarien, IL 60561
Weekly Construction Progress Report
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase B - Fine Arts Addition
360° Pictures: 1st Floor Alley 2nd Floor Bridge 2nd Floor Corridor 2nd Floor Classroom
• MEP/Fire Alarm/Fire Sprinkler Trades continue to work on rough-in.
• Piping insulation completed on the first floor.
• Controls for HVAC equipment in progress.
• DBM continues wall framing and Hargrave installs in-wall wood blocking.
• Lake Shore Glass is installing the glass at curtainwall locations.
• Waukegan Steel delivered the metal stair and started installation.
• Green Demolition is working on openings from school to new Arts Addition.
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase B - Bleachers & Squad Rooms
• Dant Clayton working on visitor bleachers ramps and stairs.
• JWI completed the structure for the bleachers prior to start decking. Their crew returned homefor the week of 3/23/20 due to COVID-19 challenged for lodging and will be back week of3/30/20.
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase C - Auditorium
• Arc 1 mobilized to the site to start removal/salvage of existing can light & controls to bedelivered to Downers Grove North.
• MG Mechanical started the gas piping relocation in the band hallway.
• Colfax started abatement of existing areas in preparation for new Phase C work. GBTA has beensupervising and monitoring work onsite.
• Weekly BIM coordination meetings are schedule with trade partners to resolve any futurepotential conflicts with MEP rough-in and equipment.
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase C - Learning Commons
• Compass set control points and grid lines for layout in existing courtyard.
• Green Demolition completed demolition necessary for access to the courtyard.
• Kane County Excavating & Werner Nugent preparing to mobilize equipment to start demolition,excavation & underground utilities in the courtyard.
• Colfax removed existing window for access to courtyard from band hallway.
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase B - Gym, Kitchen, Alley, Multipurpose,and Gymnastics Loft Addition
360° Pictures: Main Gym Kitchen Multi-Purpose Room Gymnastics Room
• Completed exterior brick work with the exception of where construction access ramp is. Masonshave moved into the building for interior CMU walls.
• Poured gym slab on grade. All interior concrete work has been completed.
• Overhead MEP rough in continues to progress on both floors.
• Roofers have completed the high roof and are working on the lower roof currently. Currentlyscheduled to have the roof complete next week.
• Metal framing throughout 2nd floor continues to progress along with in wall rough in.
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase B - Bleachers & Squad Rooms
• Home bleachers will be complete with all 180 ea rammed aggregate piers this week. Will beginbleacher foundations next week.
• Visitor Bleacher will complete concrete foundations next week, followed by the remainingbleacher assembly.
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase C - Cafeteria, Culinary Arts, Commons,and Southeast Addition
• Installed temp fence, removed trees & shrubs, and removed 1 story building.
• Performing environmental abatement ahead of schedule with school being closed. Currentlyscheduled to jump ahead with abatement scheduled for beginning of summer.
• Weekly BIM coordination meetings are schedules with Trade Partners to identify and resolve anypotential conflicts with rough-in and equipment location in the field.
360° Pictures: Servery Commons