Period: 3/19/20 - 3/25/20 Community High School District 99 Master Facility Plan Implementation Wight Construction Services 2500 North Frontage Road Darien, IL 60561 Weekly Construction Progress Report

Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Period: 3/19/20 - 3/25/20

Community High School District 99

Master Facility Plan Implementation

Wight Construction Services2500 North Frontage RoadDarien, IL 60561

Weekly Construction Progress Report

Page 2: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase B - Fine Arts Addition

360° Pictures: 1st Floor Alley 2nd Floor Bridge 2nd Floor Corridor 2nd Floor Classroom

• MEP/Fire Alarm/Fire Sprinkler Trades continue to work on rough-in.

• Piping insulation completed on the first floor.

• Controls for HVAC equipment in progress.

• DBM continues wall framing and Hargrave installs in-wall wood blocking.

• Lake Shore Glass is installing the glass at curtainwall locations.

• Waukegan Steel delivered the metal stair and started installation.

• Green Demolition is working on openings from school to new Arts Addition.

Page 3: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase B - Bleachers & Squad Rooms

• Dant Clayton working on visitor bleachers ramps and stairs.

• JWI completed the structure for the bleachers prior to start decking. Their crew returned homefor the week of 3/23/20 due to COVID-19 challenged for lodging and will be back week of3/30/20.

Page 4: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase C - Auditorium

• Arc 1 mobilized to the site to start removal/salvage of existing can light & controls to bedelivered to Downers Grove North.

• MG Mechanical started the gas piping relocation in the band hallway.

• Colfax started abatement of existing areas in preparation for new Phase C work. GBTA has beensupervising and monitoring work onsite.

• Weekly BIM coordination meetings are schedule with trade partners to resolve any futurepotential conflicts with MEP rough-in and equipment.

Page 5: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Community High School District 99

Master Facility Plan Implementation

Downers Grove South High School

Phase C - Learning Commons

• Compass set control points and grid lines for layout in existing courtyard.

• Green Demolition completed demolition necessary for access to the courtyard.

• Kane County Excavating & Werner Nugent preparing to mobilize equipment to start demolition,excavation & underground utilities in the courtyard.

• Colfax removed existing window for access to courtyard from band hallway.

Page 6: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Community High School District 99

Master Facility Plan Implementation

Downers Grove North High School

Phase B - Gym, Kitchen, Alley, Multipurpose,and Gymnastics Loft Addition

360° Pictures: Main Gym Kitchen Multi-Purpose Room Gymnastics Room

• Completed exterior brick work with the exception of where construction access ramp is. Masonshave moved into the building for interior CMU walls.

• Poured gym slab on grade. All interior concrete work has been completed.

• Overhead MEP rough in continues to progress on both floors.

• Roofers have completed the high roof and are working on the lower roof currently. Currentlyscheduled to have the roof complete next week.

• Metal framing throughout 2nd floor continues to progress along with in wall rough in.

Page 7: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Community High School District 99

Master Facility Plan Implementation

Downers Grove North High School

Phase B - Bleachers & Squad Rooms

• Home bleachers will be complete with all 180 ea rammed aggregate piers this week. Will beginbleacher foundations next week.

• Visitor Bleacher will complete concrete foundations next week, followed by the remainingbleacher assembly.

Page 8: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM

Community High School District 99

Master Facility Plan Implementation

Downers Grove North High School

Phase C - Cafeteria, Culinary Arts, Commons,and Southeast Addition

• Installed temp fence, removed trees & shrubs, and removed 1 story building.

• Performing environmental abatement ahead of schedule with school being closed. Currentlyscheduled to jump ahead with abatement scheduled for beginning of summer.

• Weekly BIM coordination meetings are schedules with Trade Partners to identify and resolve anypotential conflicts with rough-in and equipment location in the field.

360° Pictures: Servery Commons