    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    Introduction to Hydrocarbon Exploitation

    2005 Abalt Solutions Limited. All rights reserved

    Development Phase

    Well Heads

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Introduction

    All Surface equipment topping off the architecture

    of a well. It consists of Hangers, Christmas treeand all other hardware suspended with respect

    to safety and reliability of a well.

  • 7/28/2019 Wellheads (2)

    2/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Introduction

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Changes in Wellhead

    Changes in wellhead during a drilling operation

    are described based on the following

    Drilling 17 Hole

    Casing 13 3/8

    Drilling 12 Hole

    Casing 9 5/8

    Drilling 8 Hole

    Casing 7

    Drilling 6 Hole

    Completions

  • 7/28/2019 Wellheads (2)

    3/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 17 Hole

    The initial architecture of well consists of bellnipple or conductor.

    Only if there is shallow gas-Diverter is used

    Surface casing is run in and cemented right tothe surface.

    Wait on Cement and then mount the Casing-

    head housing.

    Diverter Its an annular type BOP .

    Working pressure is low

    Functions to divert any blow out to a flare.

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 17 Hole

    Casing Head Housing

    First Component screwed,welded or forged to surfacecasing.

    In the event casing stringgets stuck on the waydown, connection can bemade only after pipe is cutoff and welded.

    Bore in upper part ofhousing can be cylindricalor tapered to supportcasing hangers and sealsfor next casing string.

    The surface casing andhousing support all thecasings and BOPsanticipated.

  • 7/28/2019 Wellheads (2)

    4/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 17 Hole

    Assembling BOP The Wellhead is

    complete for thisdrilling phase withmud cross andOperatorsrecommendedBOP.

    Wear bushinglocked with

    locking flange andradial threadedrods inside casinghead housing toprotect bore fromerosion.

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 17 Hole

    Pressure Tests

    Wellhead must be pressure tested Whenever anything is assembled

    Whenever anything is dismantled

    Periodically according to Operator

    All valves and pair of pipe rams aretested by pumping into annulus viakill line

    Tested using

    Tester cup Tool screwed on to end of DP and to

    10 to 30m into casing.

    All valves and pipe rams are tested

    Tester plug Plug with O rings are rested in casing

    head

    Pipe rams, annular and accessoriescan be tested.

  • 7/28/2019 Wellheads (2)

    5/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 12 Hole

    Drilling with 12 bit.

    9 5/8 casing is run and then cemented up to

    desired height from shoe.

    Wear bushing is removed from casing-headhousing.

    Casing tensioned and anchored placing weight

    of 9 5/8 on casing spider and disconnectingflanges between mud cross and CHH.

    Lift BOP Structure. Place Casing Hangers in between 9 5/8 casing

    and bore of the casing head housing.

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 12 Hole

    Casing Hangers

    Devices to anchor and hangcasing strings in the CHH.

    Each has slips to hang thecasing into tapered sectionof CHH.

    Contains rubber ring sealingassembly.

    Types

    Separate Packers andHangers

    Hangers and incorporatedpackers

    Automatic hangers.

  • 7/28/2019 Wellheads (2)

    6/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 12 Hole

    Casing Head Spools

    Also supports casingstrings.

    2 Flanges of differentsizes and workingpressures

    Lower flange-samedimension andworking pressure as

    casing-head housing.It has a cylindrical

    bore and seal system. Upper part-cylindrical

    or tapered toaccommodate casing

    hangers of next string

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 8 Hole

    Principle is same aspreceding phase

    Casing stringanchored after wearbushing has beenremoved.

    Casing cut-offaccording to thecomponents that willbe assembled on topof 7 string.

    Testing/Pack-offflange is connected

  • 7/28/2019 Wellheads (2)

    7/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 8 Hole

    Tubing Head Spools Identical to double flanged casing-head spools and suspend tubing.

    Tubing Hangers Consist of threaded hanger with seal on tapered outside part which

    corresponds to tubing head.

    Held by screws on upper flange of tubing head.

    Length of tubing is screwed on to upper female part of hanger. For dual completions, special tubing head must be used.

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 8 Hole

    Dual tubing hangerconnection

    Well head for 6 Drilling

  • 7/28/2019 Wellheads (2)

    8/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 8 Hole

    Courtesy:ABB

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Drilling 6 Hole

    The 7casing is run in holeand cemented at top of payzone.

    Producing layer is drilledand completed by running5 liner anchored in the 7

    casing. Casing is perforated and

    production packer set.

    Tubing & hanger are run in.

    After BOPs are dismantled,an adapter flange fitting onthe tubing head &supporting lower part ofmaster valves completeswellhead.

  • 7/28/2019 Wellheads (2)

    9/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Blowout Preventers

    Pressure control devices that hold and maintain pressureduring drilling operations.

    Designed to:

    Seal off the well when formations are encountered thatcontain pressure>hydrostatic pressure of drilling mud.

    Allow mud circulation & density adjustment according toformation fluids under pressure.

    Characterized by:

    Make

    Type

    Nominal size

    Working pressure

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Characteristics for each Preventer:

    Maximum opening diameter allowing drilling bits to pass through. Opening & closing ratios; ratio between pressure prevailing in well

    when the Preventer is closed or opened) and hydrostatic pressurerequired to close or open) the preventers.

    Working pressure 1000;2000;3000;5000;10,000;15,000 & 20,000

    Nominal diameters 30,29,21 ,20 ,18 ,16 ,13 5/8,11 & 7 1/6

    Make Cameron

    Shaffer

    Hydril Vetco Gray

    Blowout Preventers

  • 7/28/2019 Wellheads (2)

    10/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Types of BOPs

    Ram type preventers

    Pipe rams

    Blind rams

    Shear rams

    Annular type preventers

    Rotating preventers

    Inside preventers

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Ram preventers

    Pipe Rams Semi circular openings which match

    diameter of pipe sizes for whichdesigned.

    If more than one size of drill pipe is

    used, additional preventers must beused on stack.

    Blind rams Designed to close when no pipe is

    used.

    Will flatten drill pipe if inadvertently

    closed with drill string in hole, but willnot stop flow from well.

    Shear rams Designed to shear drill string.

    Will cause drill string to drop in hole &

    stop flow from well.

    Used mainly when all pipe rams andannular preventers have failed.

    Types of BOPs

    Courtesy :Cameron

  • 7/28/2019 Wellheads (2)

    11/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Types of BOPs

    Shear rams

    Blind rams

    Pipe rams

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Annular Preventer Sometimes called bag-type Preventer

    Stops flow from well using a ring of synthetic rubber that contractsin the fluid passage.

    Rubber packing conforms to shape pf pipe

    Working pressures:

    2000 psi

    5000 psi

    10,000 psi

    Types of BOPs

  • 7/28/2019 Wellheads (2)

    12/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Rotating Preventer This type of Preventer

    allows the drill string to

    be rotated & run in orout.

    Placed above normal

    preventers and used fordrilling under pressure

    when low density mud isrequired.

    Used for drilling with air

    or gas as fluid

    Types of BOPs

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Different BOP Stack combinations

    According to IADC:

    3-Ram and 1 Bag type-10,000 psi15,000Very High Pressure

    3-Ram and 1 Bag type-5000 psi10,000High Pressure

    2-Ram and 1 Bag type5000Medium Pressure

    2-Ram and 1 Bag type3000Low Pressure

    2-Ram or 1 Bag type2000Light

    StackWorking Pressure (psi)Duty

  • 7/28/2019 Wellheads (2)

    13/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Different BOP Stack combinations

    ??????

    ??????

    ??????

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    BOP Hydraulic Control Systems

    Principles

    All Bops and wellhead valves are hydraulically

    actuated & operated.

    There is always one line on opening side & one

    on closing side.

    Volume of fluid required to carry out a givennumber of emergency open/close functionsshould be specified by operator.

    Pressure must be exerted to get a good seal.

    Time required to close all BOPs must be

    calculated.

  • 7/28/2019 Wellheads (2)

    14/14

    Development Phase

    September October 2005abalt solutions limited - 2005

    INTRODUCTION TO HYDROCARBON EXPLOITATION

    DrillingEnginee

    ring-Wellheads

    2005 Abalt Solutions Limited. All rights reserved

    Several Air/Oil accumulators

    Set of hydraulic pumps

    Direct control manifold

    Remote controlled manifold

    BOP Hydraulic Control Systems

    DrillingEngineering-Wellhead

    s

    2005 Abalt Solutions Limited. All rights reserved

    Operation Hydraulic fluid

    discharged by pumpsto accumulatorscompress a bladderfilled with Nitrogen.

    Pressure equilibriumbetween gas & fluid inaccumulator.

    Gas acts as a springthat expels the oil whencircuit is opened bymeans of one of fourway valves that selectsthe functions.

    Hydraulic pumps start& stop automaticallyand main circuit isregulated at 1500 psi.

    BOP Hydraulic Control Systems