Yogesh Report

Embed Size (px)

Citation preview

  • 7/28/2019 Yogesh Report

    1/60

    BADARPUR

    THERMALPOWER

    STATION

    (A UNIT OF

    NTPC)

    CONTENTS

    BTPS

    Submitted by:

    YOGESH KUMAR

    B.TECH (ELECTICAL ENGG

    DEENBANDHU CHHOTU

    RAM UNIVERSITY OF

    SCIENCE & TECHNOLOGY

    MURTHAL,HARYANA.

    HARYANA

    SUMMER TRAINING REPORT

  • 7/28/2019 Yogesh Report

    2/60

    Certificate

    AcknowledgementTraining at BTPS

    1. Introduction

    NTPC

    Badarpur Thermal Power Station

    2. Operation

    3. Electrical Maintenance Division-I

    HT/LT Switch Gear

    HT/LT Motors, Turbine & Boilers Side

    CHP/NCHP

    4. Electrical Maintenance Division-II

    Generator

    Transformer & Switchyard

    Protection

    Lighting

    EP

  • 7/28/2019 Yogesh Report

    3/60

    CERTIFICATE

    This is to certify that Yogesh Kumar, student of bachelor of

    Technology, ELECTRICAL ENGG., 3rd Year, DCRUST Murthal, Sonipat,

    Haryana has successfully completed his industrial Training at

    Badarpur Thermal Power Corporation, New Delhi for 25 days from 4th

    of July to 29th July 2011. He has completed the whole training as per

    the training report submitted by him.

    Training Incharge

    BTPS/NTPC,

    Badarpur,

    New Delhi

  • 7/28/2019 Yogesh Report

    4/60

    ACKNOWLEDGEMENT

    With profound respect and gratitude, I take the opportunity toconvey my thanks to complete the training here.

    I do extend my heartfelt thanks to Ms. Rachna Singh forproviding me this opportunity to be a part of this esteemedorganisation.

    I am extremely grateful to all the technical staff of BTPS / NTPCfor their co-operation and guidance that has helped me a lot duringthe course of training. I have learnt a lot working under them and Iwill always be indebted of them for this value addition in me.

    I would also like to thank the training incharge and all the facultymembers of our college, NPTI, Badarpur, for their effort of constantco- operation, which have been a significant factor in theaccomplishment of my industrial training.

    YOGESH KUMAR

    B.Tech (Electrical Engg.)

  • 7/28/2019 Yogesh Report

    5/60

    Training at BTPS

    I was appointed to do 25 Days training at this esteemedorganization from 5th July to 29th July, 2011. I was assigned to visitvarious division of the plant, which were.

    Electrical Maintenance Department -1 (EMD- 1)

    Electrical Maintenance Department -2 (EMD- 2)

    These 25 Days training was a very educational adventure for me.

    It was really amazing to see the plant by yourself and learn howelectricity, which is one of our daily requirements of life, is produced.

    This report has been made by my experience at BTPS. Thematerial in this report has been gathered from my textbook, seniorstudent reports and trainers manuals and power journals provided bytraining department. The specification and principles are as learnedby me from the employees of each division of BTPS.

    YOGESH KUMAR

  • 7/28/2019 Yogesh Report

    6/60

    INTRODUCTIONABOUT NTPC

    NTPC Limited today is one of the largest companies in India in terms of MarketCapitalization and the single largest player in power sector catering toapproximately 30% of country's power needs. Set up in 1975 by Government ofIndia, today it is a Navratna PSU with a strong workforce of 24,447 powerprofessionals and an annual turnover of Rs.28, 750.7 Crores. The Company has14 coal based and 7 gas based power plants across India with a total installedcapacity of 26,404 MW. Several new projects are underway as the company hasambitious plans of achieving 75,000 MW installed capacity by 2017.

    NTPC is providing power at the cheapest average tariff in the country. With itsexperience and expertise in the power sector, NTPC is extending consultancyservices to various organizations in the power business. NTPC has entered into ajoint venture with Alstom, Germany for renovation and modernization of power

    plants in India.

    NTPC is committed to the environment, generating power at minimalenvironmental cost and preserving the ecology in the vicinity of the plants. It hasundertaken massive afforestation in the vicinity of its plants. Plantations have

    http://www.ntpc.co.in/Services_Offered/services_offered.shtmlhttp://www.ntpc.co.in/Services_Offered/services_offered.shtmlhttp://www.ntpc.co.in/aboutus/jointventures.shtmlhttp://www.ntpc.co.in/infocus/environment.shtmlhttp://www.ntpc.co.in/Services_Offered/services_offered.shtmlhttp://www.ntpc.co.in/Services_Offered/services_offered.shtmlhttp://www.ntpc.co.in/aboutus/jointventures.shtmlhttp://www.ntpc.co.in/infocus/environment.shtml
  • 7/28/2019 Yogesh Report

    7/60

    increased forest area and reduced barren land. The massive afforestation byNTPC in and around its Ramagundam Power station (2100 MW) has contributedreducing the temperature in the areas by about 3c. NTPC has also takenproactive steps for ash utilization. In 1991, it set up Ash Utilization Division tomanage efficient use of the ash produced at its coal stations. This quality of ash

    produced is ideal for use in cement, concrete, cellular concrete, building material.

    A "Centre for Power Efficiency and Environment Protection (CENPEEP)" has beenestablished in NTPC with the assistance of United States Agency for InternationalDevelopment. (USAID). Cenpeep is efficiency oriented, Eco-friendly and Eco-nurturing initiative - a symbol of NTPC's concern towards environmentalprotection and continued commitment to sustainable power development in India.As a responsible corporate citizen, NTPC is making constant efforts to improve thesocio-economic status of the people affected by its projects. Through itsRehabilitation and Resettlement programmes, the company endeavors toimprove the overall socio-economic status of Project Affected Persons. It was

    among the first Public Sector Enterprises to enter into a Memorandum ofUnderstanding (MOU) with the Government in 1987-88.

    The development of power in the country was achieved through State ElectricityBoards (SEBS) during the first three decades after independence. The outlay forpower during viii-plan was Rs.34270 crores against Rs.393 crores during the firstplan period. The outlay for power remained 19-20% during all plan periods out oftotal outlay.

    Vision:

    "To be one of the worlds largest and best power utilities, powering India'sgrowth".

    NTPC's vision for the new millennium is inspired by a glorious past, vibrantpresent and a brilliant future.

    Mission:

    1) Make available reliable and quality power in increasingly large quantitiesat appropriate tariffs, and ensure timely realization of revenues.

    2) Speedily plan and implement power projects, with contemporarytechnologies.

    3) Implement strategic diversifications in the areas of R&M, Hydro, LNG andnon-conventional and eco-friendly fuels and explore new areas like transmission,information technology etc.

    http://www.ntpc.co.in/infocus/ashutilisation.shtmlhttp://www.ntpc.co.in/otherlinks/cenpeep.shtmlhttp://www.ntpc.co.in/aboutus/rrpol.pdfhttp://www.ntpc.co.in/infocus/ashutilisation.shtmlhttp://www.ntpc.co.in/otherlinks/cenpeep.shtmlhttp://www.ntpc.co.in/aboutus/rrpol.pdf
  • 7/28/2019 Yogesh Report

    8/60

    ABOUT BTPS

    Badarpur thermal power station started working in 1973 with a single 95 mw unit.There were 2 more units (95 MW each) installed in next 2 consecutive years. Nowit has total five units with total capacity of 720 MW. Ownership of BTPS wastransferred to NTPC with effect from 01.06.2006 through GOIs GazetteNotification .Given below are the details of unit with the year they are installed.

    Address: Badarpur, New Delhi 110 044

    Telephone: (STD-011) 26949523Fax: 26949532Installed Capacity 720 MWDerated Capacity 705 MW

    Location New Delhi

    Coal Source Jharia Coal Fields

    Water Source Agra CanalBeneficiary States Delhi

    Unit Sizes 3X95 MW2X210 MW

    Units Commissioned Unit I- 95 MW - July 1973Unit II- 95 MW August 1974Unit III- 95 MW March 1975Unit IV - 210 MW December 1978Unit V - 210 MW - December 1981

  • 7/28/2019 Yogesh Report

    9/60

    OPERATIONELECTRICITY FROM COAL

    Coal from the coal wagons is unloaded with the help of wagon tipplers in the

    C.H.P. this coal is taken to the raw coal bunkers with the help of conveyor belts.

    Coal is then transported to bowl mills by coal feeders where it is pulverized and

    ground in the powered form.

    This crushed coal is taken away to the furnace through coal pipes with the help of

    hot and cold mixture P.A fan. This fan takes atmospheric air, a part of which is

    sent to pre heaters while a part goes to the mill for temperature control.

    Atmospheric air from F.D fan in the air heaters and sent to the furnace as

    combustion air.

    Water from boiler feed pump passes through economizer and reaches the boiler

    drum . Water from the drum passes through the down comers and goes to the

    bottom ring header. Water from the bottom ring header is divided to all the four

    sides of the furnace. Due to heat density difference the water rises up in the

    water wall tubes. This steam and water mixture is again taken to the boiler drum

    where the steam is sent to super heaters for super heating. The super heaters are

    located inside the furnace and the steam is super heated (540 degree Celsius)

    and finally it goes to the turbine.

    Fuel gases from the furnace are extracted from the induced draft fan, which

    maintains balance draft in the furnace with F.D fan. These fuel gases heat energy

    to the various super heaters and finally through air pre heaters and goes to

    electrostatic precipitators where the ash particles are extracted. This ash is mixed

    with the water to from slurry is pumped to ash period.

  • 7/28/2019 Yogesh Report

    10/60

    The steam from boiler is conveyed to turbine through the steam pipes and

    through stop valve and control valve that automatically regulate the supply of

    steam to the turbine. Stop valves and controls valves are located in steam chest

    and governor driven from main turbine shaft operates the control valves the

    amount used.

    Steam from controlled valves enter high pressure cylinder of turbines, where it

    passes through the ring of blades fixed to the cylinder wall. These act as nozzles

    and direct the steam into a second ring of moving blades mounted on the disc

    secured in the turbine shaft. The second ring turns the shaft as a result of force of

    steam to the stationary and moving blades together.

    MAIN GENERATOR

    Maximum continuous KVA rating 24700KVAMaximum continuous KW 210000KWRated terminal voltage 15750VRated Stator current 9050 ARated Power Factor 0.85 lag

    Excitation current at MCR Condition 2600 ASlip-ring Voltage at MCR Condition 310 VRated Speed 3000 rpmRated Frequency 50 HzShort circuit ratio 0.49Efficiency at MCR Condition 98.4%Direction of rotation viewed Anti ClockwisePhase Connection Double StarNumber of terminals brought out 9( 6 neutral and 3

    phase)

  • 7/28/2019 Yogesh Report

    11/60

    MAIN TURBINE DAT

    Rated output of Turbine 210 MW

    Rated speed of turbine 3000 rpm

    Rated pressure of steam before emergency 130 kg/cm^2

    Stop valve rated live steam temperature 535 degree Celsius

    Rated steam temperature after reheat at inlet

    to receptor valve

    535 degree Celsius

    Steam flow at valve wide open condition 670 tons/hour

    Rated quantity of circulating water through

    condenser

    27000 cm/hour

    1. For cooling water temperature (degree

    Celsius)

    24,27,30,33

    1.Reheated steam pressure at inlet of

    interceptor valve in kg/cm^2 ABS

    23,99,24,21,24,49,24

    .82

    2.Steam flow required for 210 MW in ton/hour 68,645,652,662

    3.Rated pressure at exhaust of LP turbine in

    mm of Hg

    19.9,55.5,65.4,67.7

  • 7/28/2019 Yogesh Report

    12/60

  • 7/28/2019 Yogesh Report

    13/60

    THERMAL POWER PLANT

    A Thermal Power Station comprises all of the equipment and a subsystem

    required to produce electricity by using a steam generating boiler fired with fossilfuels or befouls to drive an electrical generator. Some prefer to use the term

    ENERGY CENTER because such facilities convert forms of energy, like nuclear

    energy, gravitational potential energy or heat energy (derived from the

    combustion of fuel) into electrical energy. However, POWER PLANT is the most

    common term in the united state; While POWER STATION prevails in many

    Commonwealth countries and especially in the United Kingdom.Such power

    stations are most usually constructed on a very large scale and designed for

    continuous operation.

    1. Cooling water pump

    2. Three-phase transmission line

    3. Step up transformer

    4. Electrical Generator

    5. Low pressure steam

    6. Boiler feed water pump

    7. Surface condenser

    8. Intermediate pressure steam turbine

    9. Steam control valve

    10. High pressure steam turbine

    11. Deaerator Feed water heater

    12. Coal conveyor

    13. Coal hopper

    14. Coal pulverizer

    15. boiler steam drum

    16. Bottom ash hoper

    17. Super heater

    18. Forced draught(draft) fan

    19. Reheater

  • 7/28/2019 Yogesh Report

    14/60

    20. Combustion air intake

    21. Economizer

    22. Air preheater

    23. Precipitator

    24. Induced draught(draft) fan

    25. Fuel gas stack

    The description of some of the components written above is described as follows:

    1.Cooling towers

    Cooling Towers are evaporative coolers used for cooling water or other working

    medium to near the ambivalent web-bulb air temperature. Cooling tower use

    evaporation of water to reject heat from processes such as cooling the circulating

    water used in oil refineries, Chemical plants, power plants and building cooling,

    for example. The tower vary in size from small roof-top units to very large

    hyperboloid structures that can be up to 200 meters tall and 100 meters in

    diameter, or rectangular structure that can be over 40 meters tall and 80 meters

    long. Smaller towers are normally factory built, while larger ones are constructed

    on site.

    The primary use of large , industrial cooling tower system is to remove the heat

    absorbed in the circulating cooling water systems used in power plants ,

    petroleum refineries, petrochemical and chemical plants, natural gas processing

    plants and other industrial facilities . The absorbed heat is rejected to the

    atmosphere by the evaporation of some of the cooling water in mechanical

    forced-draft or induced draft towers or in natural draft hyperbolic shaped cooling

    towers as seen at most nuclear power plants.

    2.Three phase transmission line

    Three phase electric power is a common method of electric power

    transmission. It is a type of polyphase system mainly used to power motors and

    many other devices. A Three phase system uses less conductor material to

  • 7/28/2019 Yogesh Report

    15/60

    transmit electric power than equivalent single phase, two phase, or direct current

    system at the same voltage. In a three phase system, three circuits reach their

    instantaneous peak values at different times. Taking one conductor as the

    reference, the other two current are delayed in time by one-third and two-third of

    one cycle of the electrical current. This delay between phases has the effect of

    giving constant power transfer over each cycle of the current and also makes it

    possible to produce a rotating magnetic field in an electric motor.

    At the power station, an electric generator converts mechanical power into a set

    of electric currents, one from each electromagnetic coil or winding of the

    generator. The current are sinusoidal functions of time, all at the same frequency

    but offset in time to give different phases. In a three phase system the phases are

    spaced equally, giving a phase separation of one-third one cycle. Generators

    output at a voltage that ranges from hundreds of volts to 30,000 volts. At the

    power station, transformers: step-up this voltage to one more suitable for

    transmission.

    After numerous further conversions in the transmission and distribution network

    the power is finally transformed to the standard mains voltage (i.e. the

    household voltage).

    The power may already have been split into single phase at this point or it maystill be three phase. Where the step-down is 3 phase, the output of this

    transformer is usually star connected with the standard mains voltage being the

    phase-neutral voltage. Another system commonly seen in North America is to

    have a delta connected secondary with a center tap on one of the windings

    supplying the ground and neutral. This allows for 240 V three phase as well as

    three different single phase voltages( 120 V between two of the phases and

    neutral , 208 V between the third phase ( known as a wild leg) and neutral and

    240 V between any two phase) to be available from the same supply.

    3.Electrical generator

    An Electrical generator is a device that converts kinetic energy to electrical

    energy, generally using electromagnetic induction. The task of converting the

  • 7/28/2019 Yogesh Report

    16/60

    electrical energy into mechanical energy is accomplished by using a motor. The

    source of mechanical energy may be a reciprocating or turbine steam engine, ,

    water falling through the turbine are made in a variety of sizes ranging from small

    1 hp (0.75 kW) units (rare) used as mechanical drives for pumps, compressors

    and other shaft driven equipment , to 2,000,000 hp(1,500,000 kW) turbines used

    to generate electricity. There are several classifications for modern steam

    turbines.

    Steam turbines are used in all of our major coal fired power stations to drive the

    generators or alternators, which produce electricity. The turbines themselves are

    driven by steam generated in Boilers or steam generators as they are

    sometimes called.

    Electrical power station use large stem turbines driving electric generators to

    produce most (about 86%) of the worlds electricity. These centralized stations

    are of two types: fossil fuel power plants and nuclear power plants. The turbines

    used for electric power generation are most often directly coupled to their-

    generators .As the generators must rotate at constant synchronous speeds

    according to the frequency of the electric power system, the most common

    speeds are 3000 r/min for 50 Hz systems, and 3600 r/min for 60 Hz systems. Most

    large nuclear sets rotate at half those speeds, and have a 4-pole generator ratherthan the more common 2-pole one.

    Energy in the steam after it leaves the boiler is converted into rotational energy

    as it passes through the turbine. The turbine normally consists of several stage

    with each stages consisting of a stationary blade (or nozzle) and a rotating blade.

    Stationary blades convert the potential energy of the steam into kinetic energy

    into forces, caused by pressure drop, which results in the rotation of the turbine

    shaft. The turbine shaft is connected to a generator, which produces the electrical

    energy.

    4.Boiler feed water pump

  • 7/28/2019 Yogesh Report

    17/60

    A Boiler feed water pump is a specific type of pump used to pump water into a

    steam boiler. The water may be freshly supplied or retuning condensation of the

    steam produced by the boiler. These pumps are normally high pressure units that

    use suction from a condensate return system and can be of the centrifugal pump

    type or positive displacement type.

    Construction and operation

    Feed water pumps range in size up to many horsepower and the electric motor is

    usually separated from the pump body by some form of mechanical coupling.

    Large industrial condensate pumps may also serve as the feed water pump. In

    either case, to force the water into the boiler; the pump must generate sufficient

    pressure to overcome the steam pressure developed by the boiler. This is usually

    accomplished through the use of a centrifugal pump.

    Feed water pumps usually run intermittently and are controlled by a float switch

    or other similar level-sensing device energizing the pump when it detects a

    lowered liquid level in the boiler is substantially increased. Some pumps contain a

    two-stage switch. As liquid lowers to the trigger point of the first stage, the pump

    is activated. I f the liquid continues to drop (perhaps because the pump has

    failed, its supply has been cut off or exhausted, or its discharge is blocked); the

    second stage will be triggered. This stage may switch off the boiler equipment

    (preventing the boiler from running dry and overheating), trigger an alarm, or

    both.

    5. Steam-powered pumps

    Steam locomotives and the steam engines used on ships and stationary

    applications such as power plants also required feed water pumps. In this

    situation, though, the pump was often powered using a small steam engine that

    ran using the steam produced by the boiler. A means had to be provided, of

    course, to put the initial charge of water into the boiler(before steam power was

    available to operate the steam-powered feed water pump).the pump was often a

  • 7/28/2019 Yogesh Report

    18/60

    positive displacement pump that had steam valves and cylinders at one end and

    feed water cylinders at the other end; no crankshaft was required.

    In thermal plants, the primary purpose of surface condenser is to condense the

    exhaust steam from a steam turbine to obtain maximum efficiency and also to

    convert the turbine exhaust steam into pure water so that it may be reused in the

    steam generator or boiler as boiler feed water. By condensing the exhaust steam

    of a turbine at a pressure below atmospheric pressure, the steam pressure drop

    between the inlet and exhaust of the turbine is increased, which increases the

    amount heat available for conversion to mechanical power. Most of the heat

    liberated due to condensation of the exhaust steam is carried away by the cooling

    medium (water or air) used by the surface condenser.

    6. Control valves

    Control valves are valves used within industrial plants and elsewhere to control

    operating conditions such as temperature,pressure,flow,and liquid Level by fully

    partially opening or closing in response to signals received from controllers that

    compares a set point to a process variable whose value is provided by

    sensors that monitor changes in such conditions. The opening or closing of control

    valves is done by means of electrical, hydraulic or pneumatic systems

    7. Deaerator

    A Dearator is a device for air removal and used to remove dissolved gases (an

    alternate would be the use of water treatment chemicals) from boiler feed water

    to make it non-corrosive. A dearator typically includes a vertical domed

    deaeration section as the deaeration boiler feed water tank. A Steam generating

    boiler requires that the circulating steam, condensate, and feed water should be

    devoid of dissolved gases, particularly corrosive ones and dissolved or suspended

    solids. The gases will give rise to corrosion of the metal. The solids will deposit on

    the heating surfaces giving rise to localized heating and tube ruptures due to

    overheating. Under some conditions it may give to stress corrosion cracking.

  • 7/28/2019 Yogesh Report

    19/60

    Deaerator level and pressure must be controlled by adjusting control valves- the

    level by regulating condensate flow and the pressure by regulating steam flow. If

    operated properly, most deaerator vendors will guarantee that oxygen in the

    deaerated water will not exceed 7 ppb by weight (0.005 cm3/L)

    8. Feed water heater

    A Feed water heater is a power plant component used to pre-heat water delivered

    to a steam generating boiler. Preheating the feed water reduces the irreversible

    involved in steam generation and therefore improves the thermodynamic

    efficiency of the system.[4] This reduces plant operating costs and also helps to

    avoid thermal shock to the boiler metal when the feed water is introduces back

    into the steam cycle.

    In a steam power (usually modeled as a modified Ranking cycle), feed water

    heaters allow the feed water to be brought up to the saturation temperature very

    gradually. This minimizes the inevitable irreversibilitys associated with heat

    transfer to the working fluid (water). A belt conveyor consists of two pulleys, with

    a continuous loop of material- the conveyor Belt that rotates about them. The

    pulleys are powered, moving the belt and the material on the belt forward.

    Conveyor belts are extensively used to transport industrial and agricultural

    material, such as grain, coal, ores etc.

    9. Pulverizer

    A pulverizer is a device for grinding coal for combustion in a furnace in a fossil

    fuel power plant.

    10. Boiler Steam Drum

    Steam Drums are a regular feature of water tube boilers. It is reservoir of

    water/steam at the top end of the water tubes in the water-tube boiler. They store

    the steam generated in the water tubes and act as a phase separator for the

    steam/water mixture. The difference in densities between hot and cold water

    helps in the accumulation of the hotter-water/and saturated steam into steam

  • 7/28/2019 Yogesh Report

    20/60

    drum. Made from high-grade steel (probably stainless) and its working involves

    temperatures 390C and pressure well above 350psi (2.4MPa). The separated

    steam is drawn out from the top section of the drum. Saturated steam is drawn

    off the top of the drum. The steam will re-enter the furnace in through a super

    heater, while the saturated water at the bottom of steam drum flows down to the

    mud-drum /feed water drum by down comer tubes accessories include a safety

    valve, water level indicator and fuse plug. A steam drum is used in the company

    of a mud-drum/feed water drum which is located at a lower level. So that it acts

    as a sump for the sludge or sediments which have a tendency to the bottom.

    11. Super HeaterA Super heater is a device in a steam engine that heats the steam generated by

    the boiler again increasing its thermal energy and decreasing the likelihood that it

    will condense inside the engine. Super heaters increase the efficiency of the

    steam engine, and were widely adopted. Steam which has been superheated is

    logically known as superheated steam; non-superheated steam is called

    saturated steam or wet steam; Super heaters were applied to steam

    locomotives in quantity from the early 20th century, to most steam vehicles, and

    so stationary steam engines including power stations.

    12. Economizers

    Economizer, or in the UK economizer, are mechanical devices intended to

    reduce energy consumption, or to perform another useful function like preheating

    a fluid. The term economizer is used for other purposes as well. Boiler, power

    plant, and heating, ventilating and air conditioning. In boilers, economizer are

    heat exchange devices that heat fluids , usually water, up to but not normally

    beyond the boiling point of the fluid. Economizers are so named because they can

    make use of the enthalpy and improving the boilers efficiency. They are a device

    fitted to a boiler which saves energy by using the exhaust gases from the boiler

    to preheat the cold water used the fill it (the feed water). Modern day boilers,

  • 7/28/2019 Yogesh Report

    21/60

    such as those in cold fired power stations, are still fitted with economizer which is

    decedents of Greens original design. In this context they are turbines before it is

    pumped to the boilers. A common application of economizer is steam power

    plants is to capture the waste hit from boiler stack gases (flue gas) and transfer

    thus it to the boiler feed water thus lowering the needed energy input , in turn

    reducing the firing rates to accomplish the rated boiler output . Economizer lower

    stack temperatures which may cause condensation of acidic combustion gases

    and serious equipment corrosion damage if care is not taken in their design and

    material selection.

    13. Air Preheater

    Air preheater is a general term to describe any device designed to heat air before

    another process (for example, combustion in a boiler). The purpose of the air

    preheater is to recover the heat from the boiler flue gas which increases the

    thermal efficiency of the boiler by reducing the useful heat lost in the fuel gas. As

    a consequence, the flue gases are also sent to the flue gas stack (or chimney) at

    a lower temperature allowing simplified design of the ducting and the flue gas

    stack. It also allows control over the temperature of gases leaving the stack.

    14. Precipitator

    An Electrostatic precipitator (ESP) or electrostatic air cleaner is a particulate

    device that removes particles from a flowing gas (such As air) using the force of

    an induced electrostatic charge. Electrostatic precipitators are highly efficient

    filtration devices, and can easily remove fine particulate matter such as dust and

    smoke from the air steam.

    ESPs continue to be excellent devices for control of many industrial particulate

    emissions, including smoke from electricity-generating utilities (coal and oil fired),

    salt cake collection from black liquor boilers in pump mills, and catalyst collection

    from fluidized bed catalytic crackers from several hundred thousand ACFM in the

    largest coal-fired boiler application.

  • 7/28/2019 Yogesh Report

    22/60

    The original parallel plate-Weighted wire design (described above) has evolved as

    more efficient ( and robust) discharge electrode designs were developed, today

    focusing on rigid discharge electrodes to which many sharpened spikes are

    attached , maximizing corona production. Transformer rectifier systems apply

    voltages of 50-100 Kilovolts at relatively high current densities. Modern controls

    minimize sparking and prevent arcing, avoiding damage to the components.

    Automatic rapping systems and hopper evacuation systems remove the collected

    particulate matter while on line allowing ESPs to stay in operation for years at a

    time.

    15. Fuel gas stack

    A Fuel gas stack is a type of chimney, a vertical pipe, channel or similar structure

    through which combustion product gases called fuel gases are exhausted to the

    outside air. Fuel gases are produced when coal, oil, natural gas, wood or any

    other large combustion device. Fuel gas is usually composed of carbon dioxide

    (CO2) and water vapor as well as nitrogen and excess oxygen remaining from the

    intake combustion air. It also contains a small percentage of pollutants such as

    particulates matter, carbon mono oxide, nitrogen oxides and sulfur oxides. The

    flue gas stacks are often quite tall, up to 400 meters (1300 feet) or more, so as to

    disperse the exhaust pollutants over a greater aria and thereby reduce the

    concentration of the pollutants to the levels required by governmental

    environmental policies and regulations.

    When the fuel gases exhausted from stoves, ovens, fireplaces or other small

    sources within residential abodes, restaurants , hotels or other stacks are referred

    to as chimneys.

  • 7/28/2019 Yogesh Report

    23/60

  • 7/28/2019 Yogesh Report

    24/60

    EMD IElectrical Maintenance division II was assigned to do training in Electrical maintenance division I from 9th

    July 2011 to 15th July 2011.

    This two week - training in this division were divided as follows.

    HT/LT switchgear

    HT/LT Motors, Turbine &Boiler side

    CHP/NCHP Electrical

    EMD 1 is responsible for maintenance of:

    1. Boiler side motors

    2. Turbine side motors

    3. Outside motors

    4. Switchgear

    5. A.C. MOTORS

    INTRODUCTION & PRINCIPLE OF OPERATION:

    As in a machine is simply an electric transformer whose magnetic circuit

    is separated by an air gap into two relative movable portions, one

    carrying the primary and other secondary winding; then the latter is

    short circuited or closed through external impedance.

    The electromagnetic forces corresponding to the power thus transferred

    across the air gap by induction produce relative motion between the

    primary and secondary structure.

  • 7/28/2019 Yogesh Report

    25/60

    1. Boiler side motors: For 1, units 1, 2, 3

    1.1D Fans 2 in

    no.2.F.D Fans 2 in

    no.3.P.A.Fans 2 in

    no.4.Mill Fans 3 in

    no.5.Ball mill

    fans

    3 in

    no.

    6.RC feeders 3 in

    no.7.Slag

    Crushers

    5 in

    no.8.DM

    Make up Pump

    2 in

    no.9.PC Feeders 4 in

    no.10.Worm

    Conveyor

    1 in

    no.

    11.Furnikets4 in

    no.

    For stage units 1, 2, 3

    1.I.D Fans 2 in no.2.F.D Fans 2 in no.

    3.P.A Fans 2 in no.4.Bowl

    Mills

    6 in no.

    5.R.C

    Feeders

    6 in no.

    6.Clinker

    Grinder

    2 in no.

  • 7/28/2019 Yogesh Report

    26/60

    7.Scrapper 2 in no.8.Seal Air

    Fans

    2 in no.

    9.Hydrazin

    e andPhosphorou

    s Dozing

    2 in no.

    1. COAL HANDLING PLANT (C.H.P)

    2. NEW COAL HANDLING PLANT (N.C.H.P)

    The old coal handling plant caters to the need of units 2,3,4,5 and 1

    whereas the latter supplies coal to units 4 and V.O.C.H.P. supplies coal

    to second and third stages in the advent coal to usable form to

    (crushed) form its raw form and send it to bunkers, from where it is send

    to furnace.

    Major Components

    1. Wagon Tippler: - Wagons from the coal yard come to the tippler

    and are emptied here. The process is performed by a slip ring motor of

    rating: 55 KW, 415V, 1480 RPM. This motor turns the wagon by 135

    degrees and coal falls directly on the conveyor through vibrators.

    Tippler has raised lower system which enables is to switch off motor

    when required till is wagon back to its original position. It is titled by

    weight balancing principle. The motor lowers the hanging balancing

    weights, which in turn tilts the conveyor. Estimate of the weight of the

    conveyor is made through hydraulic weighing machine.2. Conveyor: - There are 14 conveyors in the plant. They are

    numbered so that their function can be easily demarcated. Conveyors

    are made of rubber and more with a speed of 250-300m/min. Motors

    employed for conveyors has a capacity of 150 HP. Conveyors have a

    capacity of carrying coal at the rate of 400 tons per hour. Few

  • 7/28/2019 Yogesh Report

    27/60

    conveyors are double belt, this is done for imp. Conveyors so that if a

    belt develops any problem the process is not stalled. The conveyor belt

    has a switch after every 25-30 m on both sides so stop the belt in case

    of emergency. The conveyors are 1m wide, 3 cm thick and made of

    chemically treated vulcanized rubber. The max angular elevation of

    conveyor is designed such as never to exceed half of the angle of

    response and comes out to be around 20 degrees.

    3. Zero Speed Switch:-It is safety device for motors, i.e., if belt is

    not moving and the motor is on the motor may burn. So to protect this

    switch checks the speed of the belt and switches off the motor when

    speed is zero.

    4. Metal Separators: - As the belt takes coal to the crusher, No

    metal pieces should go along with coal. To achieve this objective, we

    use metal separators. When coal is dropped to the crusher hoots, the

    separator drops metal pieces ahead of coal. It has a magnet and a belt

    and the belt is moving, the pieces are thrown away. The capacity of this

    device is around 50 kg. .The CHP is supposed to transfer 600 tons of

    coal/hr, but practically only 300-400 tons coal is transfer

    5. Crusher: - Both the plants use TATA crushers powered by BHEL.

    Motors. The crusher is of ring type and motor ratings are 400 HP, 606

    KV. Crusher is designed to crush the pieces to 20 mm size i.e. practically

    considered as the optimum size of transfer via conveyor.

    6. Rotatory Breaker: - OCHP employs mesh type of filters and allows

    particles of 20mm size to go directly to RC bunker, larger particles are

    sent to crushes. This leads to frequent clogging. NCHP uses a technique

    that crushes the larger of harder substance like metal impurities easing

    the load on the magnetic separators.

  • 7/28/2019 Yogesh Report

    28/60

    MILLING SYSTEM

    1. RC Bunker: - Raw coal is fed directly to these bunkers. These are 3

    in no. per boiler. 4 & tons of coal are fed in 1 hr. the depth of bunkers

    is 10m.

    2. RC Feeder: - It transports pre crust coal from raw coal bunker to

    mill. The quantity of raw coal fed in mill can be controlled by speed

    control of aviator drive controlling damper and aviator change.

    3. Ball Mill: - The ball mill crushes the raw coal to a certain height and

    then allows it to fall down. Due to impact of ball on coal and attraction

    as per the particles move over each other as well as over the Armor

    lines, the coal gets crushed. Large particles are broken by impact and

    full grinding is done by attraction. The Drying and grinding option takes

    place simultaneously inside the mill.

    4. Classifier:- It is an equipment which serves separation of fine

    pulverized coal particles medium from coarse medium. The pulverized

    coal along with the carrying medium strikes the impact plate through

    the lower part. Large particles are then transferred to the ball mill.

    5. Cyclone Separators: - It separates the pulverized coal from

    carrying medium. The mixture of pulverized coal vapour caters the

    cyclone separators.

  • 7/28/2019 Yogesh Report

    29/60

    6. The Tturniket: - It serves to transport pulverized coal from cyclone

    separators to pulverized coal bunker or to worm conveyors. There are 4

    turnikets per boiler.

    7. Worm Conveyor: - It is equipment used to distribute the pulverized

    coal from bunker of one system to bunker of other system. It can be

    operated in both directions.

    8. Mills Fans: - It is of 3 types:

    Six in all and are running condition all the time.

    (a) ID Fans: - Located between electrostatic precipitator and

    chimney.

    Type-radical

    Speed-1490 rpm

    Rating-300 KW

    Voltage-6.6 KV

    Lubrication-by oil

    (b) FD Fans: - Designed to handle secondary air for boiler. 2 in number

    and provide ignition of coal.

    Type-axial

    Speed-990 rpm

    Rating-440 KW

    Voltage-6.6 KV

    (c)Primary Air Fans: - Designed for handling the atmospheric air up to

    50 degrees Celsius, 2 in number. And they transfer the powered coal to

    burners to firing.

  • 7/28/2019 Yogesh Report

    30/60

  • 7/28/2019 Yogesh Report

    31/60

    NCHP

    1. Wagon Tippler:-

    Motor Specification

    (i) H.P 75 HP

    (ii) Voltage 415, 3 phase

    (iii) Speed 1480 rpm

    (iv) Frequency 50 Hz

    (v) Current rating 102 A

    2. Coal feed to plant:-

    Feeder motor specification

    (i) Horse power 15 HP

    (ii) Voltage 415V,3 phase

    (iii) Speed 1480 rpm

    (iv) Frequency 50 Hz

    3. Conveyors:-

    10A, 10B

    11A, 11B

    12A, 12B

    13A, 13B

    14A, 14B

    15A, 15B

    16A, 16B

    17A, 17B

    18A, 18B

    4. Transfer Point 6

  • 7/28/2019 Yogesh Report

    32/60

    5. Breaker House

    6. Rejection House

    7. Reclaim House

    8. Transfer Point 7

    9. Crusher House

    10. Exit

    The coal arrives in wagons via railways and is tippled by the wagon

    tipplers into the hoppers. If coal is oversized (>400 mm sq) then it is

    broken manually so that it passes the hopper mesh. From the hopper

    mesh it is taken to the transfer point TP6 by conveyor 12A ,12B which

    takes the coal to the breaker house , which renders the coal size to be

    100mm sq. the stones which are not able to pass through the 100mmsq of hammer are rejected via conveyors 18A,18B to the rejection house

    . Extra coal is to sent to the reclaim hopper via conveyor 16. From

    breaker house coal is taken to the TP7 via Conveyor 13A, 13B.

    Conveyor 17A, 17B also supplies coal from reclaim hopper, From TP7

    coal is taken by conveyors 14A, 14B to crusher house whose function is

    to render the size of coal to 20mm sq. now the conveyor labors are

    present whose function is to recognize and remove any stones moving

    in the conveyors . In crusher before it enters the crusher. After being

    crushed, if any metal is still present it is taken care of by metal

    detectors employed in conveyor 10.

  • 7/28/2019 Yogesh Report

    33/60

    SWITCH GEAR-It makes or breaks an electrical circuit.

    1. Isolation: - A device which breaks an electrical circuit when

    circuit is switched on to no load. Isolation is normally used in

    various ways for purpose of isolating a certain portion when

    required for maintenance.

    2. Switching Isolation: - It is capable of doing things like interrupting

    transformer magnetized current, interrupting line charging current and

    even perform load transfer switching. The main application of switching

    isolation is in connection with transformer feeders as unit makes it

    possible to switch out one transformer while other is still on load.

    3. Circuit Breakers: - One which can make or break the circuit on load

    and even on faults is referred to as circuit breakers. This equipment is

    the most important and is heavy duty equipment mainly utilized for

    protection of various circuits and operations on load. Normally circuit

    breakers installed are accompanied by isolators

    4. Load Break Switches: - These are those interrupting devices which

    can make or break circuits. These are normally on same circuit, which

    are backed by circuit breakers.

    5. Earth Switches: - Devices which are used normally to earth a

    particular system, to avoid any accident happening due to induction on

    account of live adjoining circuits. These equipments do not handle any

    appreciable current at all. Apart from this equipment there are a

    number of relays etc. which are used in switchgear.

    LT Switchgear : It is classified in following ways:-

  • 7/28/2019 Yogesh Report

    34/60

    1. Main Switch:- Main switch is control equipment which controls or

    disconnects the main supply. The main switch for 3 phase supply is

    available for tha range 32A, 63A, 100A, 200Q, 300A at 500V grade.

    2. Fuses: - With Avery high generating capacity of the modern power

    stations extremely heavy carnets would flow in the fault and the fuse

    clearing the fault would be required to withstand extremely heavy stress

    in process.

    It is used for supplying power to auxiliaries with backup fuse protection.

    Rotary switch up to 25A. With fuses, quick break, quick make and

    double break switch fuses for 63A and 100A, switch fuses for 200A,

    400A, 600A, 800A and 1000A are used.

    3. Contractors: - AC Contractors are 3 poles suitable for D.O.L Starting

    of motors and protecting the connected motors.

    4. Overload Relay: - For overload protection, thermal over relay are

    best suited for this purpose. They operate due to the action of heat

    generated by passage of current through relay element.

    5. Air Circuit Breakers: - It is seen that use of oil in circuit breaker

    may cause a fire. So in all circuits breakers at large capacity air at high

    pressure is used which is maximum at the time of quick tripping of

    contacts. This reduces the possibility of sparking. The pressure may

    vary from 50-60 kg/cm^2 for high and medium capacity circuit

    breakers.

    HT SWITCH GEAR:-

    1. Minimum oil Circuit Breaker: - These use oil as quenching

    medium. It comprises of simple dead tank row pursuing projection from

    it. The moving contracts are carried on an iron arm lifted by a long

  • 7/28/2019 Yogesh Report

    35/60

    insulating tension rod and are closed simultaneously pneumatic

    operating mechanism by means of tensions but throw off spring to be

    provided at mouth of the control the main current within the controlled

    device.

    Type-HKH 12/1000c

    Rated Voltage-66 KV

    Normal Current-1250A

    Frequency-5Hz

    Breaking Capacity-3.4+KA Symmetrical

    3.4+KA Asymmetrical360 MVA Symmetrical

    Operating Coils-CC 220 V/DC

    FC 220V/DC

    Motor Voltage-220 V/DC

    2. Air Circuit Breaker: - In this the compressed air pressure around 15

    kg per cm^2 is used for extinction of arc caused by flow of air around

    the moving circuit . The breaker is closed by applying pressure at lower

    opening and opened by applying pressure at upper opening. When

    contacts operate, the cold air rushes around the movable contacts and

    blown the arc.

    It has the following advantages over OCB:-

    i. Fire hazard due to oil are eliminated.

    ii. Operation takes place quickly.

    iii. There is less burning of contacts since the duration is short and

    consistent.

    iv. Facility for frequent operation since the cooling medium is

    replaced constantly.

    Rated Voltage-6.6 KV

    Current-630 A

  • 7/28/2019 Yogesh Report

    36/60

    Auxiliary current-220 V/DC

    3. SF6 Circuit Breaker: - This type of circuit breaker is of construction

    to dead tank bulk oil to circuit breaker but the principle of current

    interruption is similar o that of air blast circuit breaker. It simply

    employs the arc extinguishing medium namely SF6. the performance of

    gas . When it is broken down under an electrical stress. It will quickly

    reconstitute itself

    Circuit Breakers-HPA

    Standard-1 EC 56

    Rated Voltage-12 KV

    Insulation Level-28/75 KV

    Rated Frequency-50 Hz

    Breaking Current-40 KA

    Rated Current-1600 A

    Making Capacity-110 KA

    Rated Short Time Current 1/3s -40 A

    Mass Approximation-185 KG

    Auxiliary Voltage

    Closing Coil-220 V/DC

    Opening Coil-220 V/DC

    Motor-220 V/DC

    SF6 Pressure at 20 Degree Celsius-0.25 KG

    SF6 Gas Per pole-0.25 KG

    4. Vacuum Circuit Breaker: - It works on the principle that vacuum is

    used to save the purpose of insulation and it implies that pr. of gas at

    which breakdown voltage independent of pressure. It regards of

    insulation and strength, vacuum is superior dielectric medium and is

  • 7/28/2019 Yogesh Report

    37/60

    better that all other medium except air and sulphur which are generally

    used at high pressure.

    Rated frequency-50 Hz

    Rated making Current-10 Peak KA

    Rated Voltage-12 KV

    Supply Voltage Closing-220 V/DC

    Rated Current-1250 A

    Supply Voltage Tripping-220 V/DC

    Insulation Level-IMP 75 KVP

    Rated Short Time Current-40 KA (3 SEC)

    Weight of Breaker-8 KG

  • 7/28/2019 Yogesh Report

    38/60

    EMD IIElectrical Maintenance division III was assigned to do training in Electrical maintenancedivision II from 15th July 2010 to 29th July 2011. This two weekof training in this division were divided as follows.

    Generator & Transformer

    Switchyard

    Protection

    Lighting

  • 7/28/2019 Yogesh Report

    39/60

    Generator and Auxiliaries

    The transformation of mechanical energy into electrical energy is

    carried out by the Generator.

    Working Principle

    The A.C. Generator or alternator is based upon the principle of

    electromagnetic induction and consists generally of a stationary part

    called stator and a rotating part called rotor. The stator housed the

    armature windings. The rotor houses the field windings. D.C. voltage is

    applied to the field windings through slip rings. When the rotor is

    rotated, the lines of magnetic flux (viz magnetic field) cut through the

    stator windings. This induces an electromagnetic force (e.m.f.) in the

    stator windings. The magnitude of this e.m.f. is given by the following

    expression.

    E = 4.44 /O FN volts

    0 = Strength of magnetic field in Webers.

    F = Frequency in cycles per second or Hertz.N = Number of turns in a coil of stator winding

    F = Frequency = Pn/120

    Where P = Number of poles

    n = revolutions per second of rotor.

    From the expression it is clear that for the same frequency, number of

    poles increases with decrease in speed and vice versa. Therefore,

    low speed hydro turbine drives generators have 14 to 20 poles where

    as high speed steam turbine driven generators have generally 2 poles.

    Pole rotors are used in low speed generators, because the cost

    advantage as well as easier construction.

  • 7/28/2019 Yogesh Report

    40/60

    Generator component

    Rotor :

    The electrical rotor is the most difficult part of the generator to

    design. It revolves in

    most modern generators at a speed of 3,000 revolutions per minute.

    The problem of

    guaranteeing the dynamic strength and operating stability of such a

    rotor is complicated

    by the fact that a massive non-uniform shaft subjected to a

    multiplicity of differential

    stresses must operate in oil lubricated sleeve bearings supported

    by a structure

    mounted on foundations all of which possess complex dynamic be

    behavior peculiar to

    themselves. It is also an electromagnet and to give it the necessary

    magnetic strength

    the windings must carry a fairly high current. The passage of the

    current through the

    windings generates heat but the temperature must not be allowed to

    become so high,

    otherwise difficulties will be experienced with insulation. To keep the

    temperature down,

    the cross section of the conductor could not be increased but this

    would introduce

    another problems. In order to make room for the large conductors, bodyand this would

    cause mechanical weakness. The problem is really to get the

    maximum amount of

    copper into the windings without reducing the mechanical strength.

    With good design

  • 7/28/2019 Yogesh Report

    41/60

    and great care in construction this can be achieved. The rotor is a cast

    steel ingot, and

    it is further forged and machined. Very often a hole is bored through

    the centre of the rotor axially from one end of the other forinspection. Slots are then machined for

    windings and ventilation.

    Rotor winding:

    Silver bearing copper is used for the winding with mica as the

    insulation between conductors. A mechanically strong insulator such

    as micanite is used for lining the slots. Later designs of windings for

    large rotor incorporate combination of hollow conductors with slots

    or holes arranged to provide for circulation of the cooling gas

    through the actual conductors. When rotating at high speed. Centrifugal

    force tries to lift the windings out of the slots and they are contained

    by wedges. The end rings are secured to a turned recess in the rotor

    body, by shrinking or screwing and supported at

    the other end by fittings carried by the rotor body. The two ends of

    windings are connected to slip rings, usually made of forged steel,and mounted on insulated

    sleeves.

    Rotor balancing:

    When completed the rotor must be tested for mechanical balance,

    which means that a

    check is made to see if it will run up to normal speed without

    vibration. To do this it

    would have to be uniform about its central axis and it is most

    unlikely that this

    will be so to the degree necessary for perfect balance. Arrangements

    are therefore

    made in all designs to fix adjustable balance weights around the

  • 7/28/2019 Yogesh Report

    42/60

    circumference at each

    end.

    Stator:

    Stator frame: The stator is the heaviest load to be transported. The major part of

    this load is the stator core. This comprises an inner frame and outer frame. The

    outer frame is a rigid fabricated structure of welded steel plates, within this shell

    is a fixed cage ofgirder built circular and axial ribs. The ribs divide the yoke in the

    compartments through which hydrogen flows into radial ducts in the stator core

    and circulate through the gas coolers housed in the frame. The inner cage is

    usually fixed in to the yoke by an arrangement of springs to dampen thedouble frequency vibrations inherent in 2 pole generators. The end shields of

    hydrogen cooled generators must be strong enough to carry shaft seals. In large

    generators the frame is constructed as two separate parts. The fabricated inner

    cage is inserted in the outer frame after the stator core has been constructed and

    the winding completed. Stator core: The stator core is built up from a large number

    of 'punching" or sections of thin steel plates. The use of cold rolled grain-oriented

    steel can contribute to reduction in the weight of stator core for two main reasons:

    a)There is an increase in core stacking factor with improvement in lamination coldRolling and in cold buildings techniques.

    b) The advantage can be taken of the high magnetic permeance of

    grain-oriented steels of work the stator core at comparatively high

    magnetic saturation without fear or excessive iron loss of two heavy a

    demand for excitation ampere turns from the generator rotor.

    Stator Windings:Each stator conductor must be capable of carrying the rated

    current without overheating. The insulation must be sufficient to

    prevent leakage currents flowing between the phases to earth.

    Windings for the stator are made up from copper strips wound with

    insulated tape which is impregnated with varnish, dried under vacuum

  • 7/28/2019 Yogesh Report

    43/60

    and hot pressed to form a solid insulation bar. These bars are then

    place in the stator slots and held in with wedges to form the complete

    winding which is connected together at each end of the core forming

    the end turns. These end turns are rigidly braced and packed withblocks of insulation material to withstand the heavy forces which

    might result from a short circuit or other fault conditions. The

    generator terminals are usually arranged below the stator. On recent

    generators (210 MW) the windings are made up from copper tubes

    instead of strips through which water is circulated for cooling

    purposes. The water is fed to the windings through plastic tubes.

    Generator Cooling System :

    The 200/210 MW Generator is provided with an efficient cooling

    system to avoid excessive heating and consequent wear and tear of its

    main components during operation.

    Rotor Cooling System

    The rotor is cooled by means of gap pick-up cooling, wherein the

    hydrogen gas in the air gap is sucked through the scoops on the rotor

    wedges and is directed to flow along the ventilating canals milled on

    the sides of the rotor coil, to the bottom of the slot where it takes a turn

    and comes out on the similar canal milled on the other side of the rotor

    coil to the hot zone of the rotor. Due to the rotation of the rotor, a

    positive suction as well as discharge is created due to which a certain

    quantity of gas flows and cools the rotor. This method of cooling gives

    uniform distribution of temperature. Also, this method has an

    inherent advantage of eliminating the deformation of copper due to

    varying temperatures.

    Hydrogen Cooling System

  • 7/28/2019 Yogesh Report

    44/60

    Hydrogen is used as a cooling medium in large capacity generator in

    view of its high heat carrying capacity and low density. But in view of

    its forming an explosive mixture with oxygen, proper arrangement for

    filling, purging and maintaining its purity inside thegenerator have to

    be made. Also, in order to prevent escape of hydrogen from the

    generator casing, shaft sealing system is used to provide oil sealing.

    The hydrogen cooling system mainly comprises of a gas control stand, a

    drier, an liquid level indicator, hydrogen control panel, gas purity

    measuring and indicating instruments, The system is capable of

    performing the following functions :

    Filling in and purging of hydrogen safely without bringing in contact with air.

    Maintaining the gas pressure inside the machine at the desired value at all thetimes.

    Provide indication to the operator about the condition of the gas insidethe machine i.e. its pressure, temperature and purity.

    Continuous circulation of gas inside the machine in order to

    remove any water vapour that may be present in it.

    Indication of liquid level in the generator and alarm in case of high level.

    Stator Cooling SystemThe stator winding is cooled by distillate. Which is fed from one end of

    the machine by Teflon tube and flows through the upper bar and

    returns back through the lower bar of another slot? Turbo generators

    require water cooling arrangement over and above the usual hydrogen

    cooling arrangement. The stator winding is cooled in this system by

    circulating demineralised water (DM water) through hollow conductors.

    The cooling water used for cooling stator winding calls for the use ofvery high quality of cooling water. For this purpose DM water of

    proper specific resistance is selected. Generator is to be loaded within

    a very short period if the specific resistance of the cooling DM water

    goes beyond certain preset values. The system is designed to

    maintain a constant rate of cooling water flow to the stator winding at

  • 7/28/2019 Yogesh Report

    45/60

    a nominal inlet water temperature of 40 deg.C.

  • 7/28/2019 Yogesh Report

    46/60

    Rating of 95 MW Generator

    Manufacture by Bharat heavy electrical Limited (BHEL)

    Capacity - 117500 KVA

    Voltage - 10500V

    Speed - 3000 rpm

    Hydrogen - 2.5 Kg/cm2

    Power factor - 0.85 (lagging)

    Stator current - 6475 A

    Frequency - 50 Hz

    Stator wdg connection - 3 phase

    Rating of 210 MW Generator

    Manufacture by Bharat heavy electrical Limited (BHEL)

    Capacity - 247000 KVA

    Voltage (stator) - 15750 V

    Current (stator) - 9050 A

    Voltage (rotor) - 310 V

    Current (rotor) - 2600 V

    Speed - 3000 rpm

    Power factor - 0.85

    Frequency - 50 Hz

    Hydrogen - 3.5 Kg/cm2

    Stator wdg connection - 3 phase star connection

    Insulation class - B

    TRANFORMER

  • 7/28/2019 Yogesh Report

    47/60

    A transformer is a device that transfers electrical energy from one

    circuit to another by magnetic coupling with out requiring relative

    motion between its parts. It usually comprises two or more coupled

    windings, and in most cases, a core to concentrate magnetic flux. An

    alternating voltage applied to one winding creates a time-varying

    magnetic flux in the core, which includes a voltage in the other

    windings. Varying the relative number of turns between primary and

    secondary windings determines the ratio of the input and output

    voltages, thus transforming the voltage by stepping it up or down

    between circuits. By transforming electrical power to a high-

    voltage,_low-current form and back again, the transformer greatly

    reduces energy losses and so enables the economic transmission of

    power over long distances. It has thus shape the electricity supply

    industry, permitting generation to be located remotely from point of

    demand. All but a fraction of the worlds electrical power has passed

    trough a series of transformer by the time it reaches the consumer.

    Rating of transformerManufactured by Bharat heavy electrical limited

    No load voltage (hv) - 229 KV

    No load Voltage (lv) -10.5 KV

    Line current (hv) - 315.2 A

    Line current (lv) - 873.2 A

    Temp rise - 45 Celsius

    Oil quantity -40180 lit

    Weight of oil -34985 KgTotal weight - 147725 Kg

    Core & winding - 84325 Kg

    Phase - 3

    Frequency - 50 Hz

  • 7/28/2019 Yogesh Report

    48/60

    LIGHTING

    Lighting includes both artificial light sources such as lamps and natural

    illumination of interiors from daylight. Lighting represents a major component of

    energy consumption, accounting for a significant part of all energy consumed

    worldwide. Artificial lighting is most commonly provided today by electric lights,

    but gas lighting, candles or oil lamps were used in the past, and still are used in

    certain situations. Proper lighting can enhance task performance or aesthetics;

    while there can be energy wastage and adverse health effects of lighting

    220 KV SWITCHYARD

    BUS BARS: The arrangement in the 220kV switchyard comprises of a 220kVdouble bus bar system, with a bus coupler and a by pass bus. With thisarrangement it is possible to take out any one breaker for maintenance withoutinterruption of supply. In the eventuality of a bus bar or a circuit breaker fault theperiod for which supply is interrupted is the time taken to transfer the feedersfrom the faulty bus to the healthy one or replacing the faulty circuit breaker bythe by-pass breaker. It is only in the case of a line fault that supply cannot be

    restored to the feeder until the fault is rectified.

    For maintenance of a particular bus all feeders connected to the bus requiring themaintenance shall be transferred to the other bus by closing one bus isolator andopening the other. The bus coupler shall be tripped and the earthing switchclosed. After the maintenance work is over, the earthing switch must be openedbefore the respective bus bar is energized.

    For maintenance of the by-pass bus, it should be ensured that by-pass breaker isopen and all the by pass isolators of various bays are open.

    220KV CIRCUIT BREAKERS:There are two types of 220kV breakers being usedin BTPS switchyard: Air blast ciruit breaker

    SF6 circuit breaker

    These breakers operate with sequential isolators and suitable for three-phaseauto-reclosing facility. These breakers can be operated from the switch yard

    http://en.wikipedia.org/wiki/Light_sourcehttp://en.wikipedia.org/wiki/Daylighthttp://en.wikipedia.org/wiki/Electric_lighthttp://en.wikipedia.org/wiki/Gas_lightinghttp://en.wikipedia.org/wiki/Candlehttp://en.wikipedia.org/wiki/Oil_lamphttp://en.wikipedia.org/wiki/Light_pollution#Effects_on_human_health_and_psychologyhttp://en.wikipedia.org/wiki/Light_sourcehttp://en.wikipedia.org/wiki/Daylighthttp://en.wikipedia.org/wiki/Electric_lighthttp://en.wikipedia.org/wiki/Gas_lightinghttp://en.wikipedia.org/wiki/Candlehttp://en.wikipedia.org/wiki/Oil_lamphttp://en.wikipedia.org/wiki/Light_pollution#Effects_on_human_health_and_psychology
  • 7/28/2019 Yogesh Report

    49/60

    control board. In case of failure, emergency manual handles are provided in thecontrol kiosk.

    Feeder breaker: When it is required to maintain either a line or a generator or atransformer breaker, the feeder is transferred to the by-pass breaker. The

    earthing switches on isolators must be earthed before maintaining the breaker.

    By-pass breaker: the main purpose of the by pass breaker is to facilitatemaintenance/repair of other 220 kV breakers without the necessity of tripping outthe associated circuit.

    Bus coupler breaker: The two bus bars can be kept coupled through buscouplers. The by pass breaker cannot act as a substitute for bus coupler breakerwhen the bus coupler breaker is being maintained. If buses I and II are paralleledby means of bus coupler and by pass breaker then in order to maintain the buscoupler breaker all feeders must be transferred to one bus depending upon the

    prevalent load.

    RATINGS OF CIRCUIT BREAKERS:

    1. AIR BLAST CIRCUIT BREAKER (BHEL)

    Volts: 220 kV

    Amperes: 1200A

    Breaking capacity: symmetrical 26.31 kA

    Equivalent 10000 MVA

    Asymmetrical 32.1 kA

    Making capacity: peak 67.1 kA

    Short circuit time: 3 sec. 26.3 kA

    Closing coil voltage: 220V DC

    Tripping coil voltage: 220V DC

    Working pressure: Max. 28.1 kg/cm2-g

    Min. 26.0 kg/cm2

    -gLockout pressure: 21.1 kg/cm2-g

    2. AIR BLAST CIRCUIT BREAKER (ABB)

    Volts: 245 kV

    Amperes: 1200A

  • 7/28/2019 Yogesh Report

    50/60

    Breaking capacity: symmetrical 31.5 kA

    Asymmetrical 38.4 kA

    Short circuit time: 3 sec. 31.5 kA

    Closing coil voltage: 220V DCTripping coil voltage: 220V DC

    RIL at 50 Hz: 480 kV

    VI impulse: 1.2/50s 1050 kV per sec.

    U switching impulse: first pole to clear 1.3

    Mass: 1830 Kg

    Working pressure: max. 27.31 kg/cm2-g

    3. AIR BLAST CIRCUIT BREAKER (BHEL)

    Volts: 245 kV

    Amperes: 2000A

    Short circuit time: 3 sec. 26.3 kA

    Closing coil voltage: 220V DC

    Tripping coil voltage: 220V DC

    Working gas pressure: 6.1 kg/cm2-g at 200c

    Rated frequency and voltage for auxiliary: 415AC 50Hz

    Total weight of gas: 3900 Kg

    Rated operating scheme: O-0.3sec-CO-3 min.-CO

    Rated lightening impulse withstands voltage: 1050 kVp

    Rated short circuit breaking current: 40 kA

    Rated operating pressure: 15 kg/cm2-g

    First pole to clear factor: 1.3

    Rated duration of short circuit current: 40 kA for 3 sec

    Rated line charging breaking current: 125 A

    Gas weight: 21 kg

    ISOLATORS: These are single break, single pole isolators supplied by M/s.

    Hvelm limited, Madras. These are pneumatically operated at a pressure of 15

    kg/cm2. These isolators and earthing switches are interlocked with each other and

  • 7/28/2019 Yogesh Report

    51/60

    with the circuit breakers to prevent mal-operation. No interlocking arrangements

    are provided for the bus earthing switches.

    Main bus isolators: to maintain the main bus isolators the corresponding bushas to be shut down by transferring loads to other bus, bus earthed and circuit

    breaker and isolator opened, after transferring the requisite feeder on to the by

    pass breaker and the earthing switches are closed.

    By pass isolator: to maintain the by-pass isolators the by-pass bus has to be

    shut down, isolators opened and the earthing switches are closed.

    Feeder isolators: when the feeder is working on bus I or bus II, the earthing

    switches on both sides of the isolator are closed after opening the breaker and

    isolators and shutting down the feeder.

    PT isolators: The corresponding bus must be shut down and earthing switches

    on the isolator closed for maintenance.

    PNEUMATIC SYSTEM: This system consists of seven compressors with one

    spare air compressor. All the seven compressors are connected to two wet air

    cylinders, which are coupled to each other. This wet air is dried through an air

    drier and fed into six dry cylinders divided into a two groups each having three

    dry cylinders. The dry air through these two groups is passed through two

    separate air drier for further dryness of air up to a dew point of -70C. The dried

    air from these two dryers is fed into two separate dry cylinders which feed dry air

    into pressure reducers. From these pressure reducers the pressurized dry air is

    supplied to air blast circuit breakers. High pressure and low-pressure alarms are

    arranged on the pressure gauges and any mal-operation noticed must be rectified

    immediately.

    POWER LINE COMMUNICATION EQUIPMENT: To maintain the power line

    carrier communication equipment like wave trap or coupling capacitor the

  • 7/28/2019 Yogesh Report

    52/60

    conditions would be same as those of maintaining the concerned feeder isolator.

    Depending upon whether inter-circuit coupling or phase to ground coupling is

    used either both the circuits or the single circuit must be shut down along with

    the feeder isolator.

    220KV CURRENT TRANSFORMERS: The 220kV single phase 4 core current

    transformers supplied by Hindustan Brown Broveri Ltd. (Baroda). The

    transformation ratio 1200-600/1/1/1/1 amps are used in Tie in transformer,

    generator and transmission line bays and bus coupler bay. The secondary

    windings of these CTs are connected to protection and measurement circuits.

    220KV POTENTIAL TRANSFORMERS: These single phase potential

    transformers supplied by HE(I) Ltd., Bhopal are connected to 220kV buses. These

    are required for measurement and protection purposes. The main PTs are of ratio

    22000/53/110/53 volts and the auxiliary PTs are of ratio 62.5/63.5 volts. The

    auxiliary PTs will operate in conjunction with the main PT to provide one more

    secondary winding. Consequent by the combined set of main and auxiliary PTs

    will provide to secondary winding each of 110/53 voltage ratings.

    LIGHTING ARRESTORS: These have been supplied by M/s. W.S. insulators of

    India Ltd. (Madras). These are installed for protection of transformers and other

    electrical equipments against voltage surges.

    One set of lighting arrestors have been provided on each power transformers, tie

    in transformers and to the bus PTs.

    The 195kV, 10000 amps single pole heavy duty station class SVS type self

    supporting L.A. comprises of one metal top and metal base, having mobile arc,

    pressure relief and a transfer device. The mobile arc gap assembly consists of a

    permanent ceramic ring magnet, radially magnetized, m series with air gap. Thus

    it provides a constant magnetic field in the air gap which is always preset at full

    strength regardless of the current of the discharge, when lighting wave

    discharges through it, the spark discharge takes place in the annular space,

    causing an arc at right angles to the magnetic field. This field forces the arc to

  • 7/28/2019 Yogesh Report

    53/60

    spin around the gap electrode surfaces. Pressure relief device is provided to take

    care of the gas formed at the time of short circuit when the arrestor is damaged.

    When the diaphragm bursts due to a gas pressure, the ionized gases come out

    and are vented through the exhaust ports. The gas from the top of the unit isdeflected downward and that from the bottom is deflected upward. The gas

    steams meet and transfer the fault current is from inside the arrestor to the

    outside in less than half cycle of fault current.

    220KV LINES: all the feeders from the 220 kV bus bars are shown in the diagram

    on the previous page. All the metering and protection should normally be

    connected only to the bus VT supplies. However when necessary CVTs can be

    used for metering and protection.

    Bus-1 Bus-2

    1. Gen-Tr-1 1. Gen-Tr-2

    2. Gen-Tr-3 2. Gen-Tr-4

    3. Gen-Tr-5 3. IP line I

    4. IP line I 4. Mehrauli line II

    5. Mehrauli line I 5. Ballabgarh line II

    6. Ballabgarh line I 6. Noida line

    7. Alwar line 7. Okhla line-1I

    8. Okhla line-1 8. Stn Tr-2

    9. Stn Tr-1 9. Bus coupler

    10. Stn Tr-3 10. By pass bay

  • 7/28/2019 Yogesh Report

    54/60

    SYNCHRONISING: synchronizing facility with check feature has been provided

    for all 220KV breakers. Whenever a breaker is proposed to be closed,

    its synchronizing switch should be unlocked and synchronizing check

    relay by pass switch is in circuit position. It is ensured that voltage andfrequency of the incoming and running supplies are nearly same, and

    the red out of synchronism lamp is not continuously on. After the

    breaker has been closed, its synchronizing switch should be returned

    to off position and locked.

    Synchronizing check relay SKE prevents closing of a breaker when incoming and

    running supplies are out of synchronism. This relay has to be bypassed when

    closing a breaker one side of, which is dead.

    ANNUNCIATION SYSTEM: all breaker tripped alarms have been classed as

    emergency alarms. Whenever a breaker trips, the breaker tripped facia/flashes

    and a separate buzzer sounds to draw immediate attention of operator to tripping

    of a breaker. Whenever an alarm initiating contact closes, the corresponding facia

    of that alarm starts flashing. Simultaneously, the bell /buzzer starts ringing.

    Ringing of buzzer stops automatically after a preset time. Flashing continues unit

    accepts push button pressed, whereupon facia becomes steadily lighted if the

    initiating contact is still closed. Facial lamps should be tested for operation

    regularly by pressing lamp test button, provided separately for each control

    panel

    PROTECTION AND RELAYS USED IN MAIN CIRCUIT

    BOARD

    1. High speed biased differential relay: the DMH type relay provides high

    speed biased differential protection for two or three winding transformers. The

    relay is immune to high inrush current and has a high degree of stability

    against through faults. It requires a max of two cycles operating time for

    current above twice relay rated current. Instantaneous over current protection

    clears heavy internal faults immediately. This relay is available in two forms.

  • 7/28/2019 Yogesh Report

    55/60

    Firstly for use with time Cts, the ratios of line which are matched to the load

    current to give zero differential current under normal working conditions.

    Secondly with tapped interposing transformers for use with standard line

    current transformers of any ratio.

    2. Directional inverse time over current and earth fault relays: the CDD

    type relays are applied for directional or earth fault protection of ring mains,

    parallel transformers or parallel feeders with the time graded principle. It is

    induction disc type relay with induction cup used to add directional feature.

    3. Instantaneous voltage relay: the type VAG relay is an instantaneous

    protection against abnormal voltage conditions such as over voltage, under

    voltage or no voltage in AC and DC circuits and for definite time operation

    when used with a timer. It is an attracted armature type relay.

    4. Auxiliary relays: the VAA/CAA type auxiliary relays are applied for control

    alarm, indication and other auxiliary duties in AC or DC systems. CAA is a

    current operated and VAA is a voltage operated relay.. it is attracted armature

    type.

    5. High speed tripping relays: this VAJH type relay is employed with a high

    speed tripping duties where a number of simultaneous switching operations

    are required. This is a fast operating multi contact attracted armature relay.

    6. Definite time delay relay: this VAT type relay is used in auto reclosing and

    control schemes and to provide a definite time feature for instantaneous

    protective relay. It is an Electro mechanical definite time relay. It has two pair

    of contacts. The shorter time setting is provided by a passing contact and

    longer time setting by the final contact.

  • 7/28/2019 Yogesh Report

    56/60

    7. Trip circuit supervision relay: this VAX relay is applied for after closing or

    continuous supervision of the trip circuit of circuit breakers. They detect the

    following conditions:

    a) Failure of trip relayb) Open circuit of trip coil

    c) Failure of mechanism to complete the tripping operation

    8. Instantaneous over current and earth fault relay: an instantaneous

    phase or earth fault protection and for definite time operation when used with

    a timer. It is a CAG 12/12G standard attracted armature relay with adjustable

    settings. It may be a single pole or triple pole relay.

    9. Inverse time over current and earth fault relay: this CDG 11-type relay is

    applied for selective phase and earth fault protection in time graded systems

    for AC machines. Transformers, feeders etc. this is a non-directional relay with

    a definite minimum time which has an adjustable inverse time/current

    characteristics. It may be a single pole or triple pole relay.

    10. Fuse failure relay: this VAP type relay is used to detect the failure or

    inadvertent removal of voltage transformer sec. fuses and to prevent incorrect

    tripping of circuit breaker. It is three units, instantaneous attracted armature

    type relay the coil of each unit connected across one of the VTs. The

    secondary fuses under healthy conditions, the coil is SC by fuses and cant be

    energized. But one or more fuses blow the coil is energized and relay operates.

    11. Instantaneous high stability circulating current relay: it is used to

    serve the following three purposes

    a) Differential protection of Ac machines , reactors auto transformers and bus

    bars

    b) Balanced and restricted earth fault protection of generator of generator and

    transformer windings

    c) Transverse differential protection of generators and parallel feeders.

  • 7/28/2019 Yogesh Report

    57/60

    This CAG type relay is a standard attracted armature relay. In circulating

    current protection schemes, the sudden and often asymmetrical growth of the

    system current during external fault conditions can cause the protectioncurrent transformers to go into saturation, resulting in high unbalance current

    to insure stability under these conditions.

    The modern practice is to use a voltage operated high impedance relay, set to

    operate at a voltage slightly higher than that developed by CT under max fault

    conditions. Hence this type of relay is used with a stabilizing resistor.

    12. Local breaker back up relay: this is a CTIG type three phase or two

    phase earth fault instantaneous over current unit intended for use with a time

    delay unit to give back up protection in the event of a circuit breaker failure.

    13. Poly-phase directional relay: the PGD relay is a high speed induction

    cup unit used to give directional properties to three phase IDMT over-current

    relays, for the protection of parallel feeders, inter connected networks and

    parallel transformers against phase to phase and three phase faults. Owing to

    low sensitivity on phase to earth faults the relay is used with discretion on

    solidly earthed systems.

    14. Auto reclose relay: five types of auto reclose relays are available

    a) VAR21 giving one reclosure. The dead time and reclaim time are adjustable

    form 5 to 25 secs. If the circuit breaker reopens during reclaim time, it remains

    open and locked out.

    b) VAR41B is a single shot scheme for air blast circuit breakers. Reclaim time is

    fixed at between 15 to 20 secs. Dead time adjustment is from 0.1 to 1.0 sec of

    which first 300 millisec will be circuit breaker opening time.

  • 7/28/2019 Yogesh Report

    58/60

    c) VAR 42 giving four reclosure. It is precision timed from 0 to 60 sec. it can be

    set for max four enclosures at min intervals of 10 sec and instantaneous

    protection can be suppressed after the first reclosure so that persistent faults

    are referred to time graded protection.d) VAR 71 giving single shot medium speed reclosure with alarm and lockout for

    circuit breaker. This allows up to 10 faults clearance before initiating an alarm.

    The alarm is followed by lockout if selected no. of faults clearances exceed. If

    the circuit breaker reopens during reclaim time, it remains open and locked

    out. It offers delay in reclosing sequence. Instantaneous lockout on low current

    earth fault and suppressing instantaneous protection during reclamation time.

    e) Var81 is a single shot high-speed reclosure with alarm and lockout for circuit

    breaker This allows up to 10 faults clearance before initiating an alarm.

    REACTANCE DISTANCE SCHEME: this scheme consists of the following relays,

    XCG22-3 for phase to phase and 3 for phase to ground, YCG17, mho starting unit

    one in each place, VAT51 along with timing unit for zone 2 and 3, 86-X aux.

    tripping relay and 30G, H, and J for 1 st, 2nd and 3rd. Zone indication VAA51, CAG12

    and VAA31.

    Theses schemes provide three zone phase and earth fault protection using

    reactance relays type XCG22 and also starting relays YCG17. They are applicable

    to important line sections where high values of arc resistance would otherwise

    effect the accuracy of measurement and where high speed tripping is essential.

    High-speed protection is provided for phase and earth faults on 80-90% of the line

    section and faults on the remaining section are cleared in second zone, time. The

    third zone provides backup protection after further time interval.

    Each mho starting unit Y3 and its auxiliary Y3 X is associated with one phase and

    operates for all faults involving this phase. Each reactance unit X is connected to

    measure phase or earth fault distance, but is prevented from operating by short

    circuit across the polarizing coils

    LINE FAULT

    DETECTORS Y3

    EARTH FAULT

    DETECTORS 64

  • 7/28/2019 Yogesh Report

    59/60

    The principle of distance scheme is shown in the above block diagram

    Under the phase fault conditions, the Y3 X units unblock the appropriate X1

    reactance units, which initiate tripping immediately for faults within their setting.

    Operation of the earth auxiliary relay 64 in conjunction with the Y3 X units selects

    the appropriate reactance units for measurement of earth faults. The reach of

    reactance units is extended by the timer, 2 after successive intervals to cover

    ZONE

    TIMING 2

    EARTH FAULT

    REACTANCE

    UNITS X2

    RANGE

    EXTENSION 2X2X

    PHASE FAULT

    REACTANCE UN

    X1

    TRIPPING AND

    INDICATION 30

    DETECTOR

    AUXILIARIES

    Y3X

    TRIP REINFORCI

    86X

  • 7/28/2019 Yogesh Report

    60/60

    faults in zone 2 and 3. Discrimination is not affected by changing faults, for

    example a zone 2 earth fault which develops into a double phase to earth fault

    will be cleared correctly by the X1 (phase fault) units in zone 2 time. In the rare

    event of two faults occurring simultaneously at different points on the line; thescheme will measure to a distance approx. half way.