C270 (HK BIODIESEL PLANT) Safety Report
SAFETY INSPECTION / MEETING
Month: April 2012
Total Accumulated man-hour: 167,151
Man-hour without lost time injury: 167,151
Days worked since project commenced: 173
Days since last Time lost accident : N/A
Cumulative Accident Frequency Rate: 0 %
You are an important stakeholder !
SAFETY STATISTICS
POSITIVE POINTERS
All outriggers fully extended on
stable floor at lifting works
Worker wearing appropriate
PPE at work
Sunshade umbrella provided
for workers’ welfare
Temporary electric supply
cable lying on floor
Temporary electric supply
cable hanged above ground to
avoid accident damage /
electric shock
PROMPT RECTIFICATION
AREA NEED IMPROVEMENT
No safety information on
temporary electricity
distribution box
Safety warning / name &
contact of responsible
Electrician posted on the
temporary electricity
distribution box
AREA NEED IMPROVEMENT
PROMPT RECTIFICATION
76 attendees (16 classes)
SAFETY TRAINING
INDUCTION
TRAINING
TOOL BOX TALK
TRAININGSAFETY TRAINING
Fire Prevention 67 trainees
Heatstroke 59 trainees
Inclement Weather 63 trainees
General Duties 50 trainees
Excavator Safety 4 trainees
243 attendees
NO reported injury accident recorded in April 2012; all
subcontractors reported neither site accident nor
dangerous occurrence happened in their subcontract
responsible area at the Weekly Safety Meetings with
CHEC / AECOM / Jacob.
ACCIDENT / GOVERNMENT AUTHORITIES VISIT
Visitors accompanied by Project Management Team in site visit tour