SMED simulation
Purpose:
Participants:
Duration:
Simulates die changeover on a very simple machine with the purpose to teach the 5 steps of SMED (Single Minute Exchange of Dies)
At least 3
2-3 hours
A. 1 wood base: 11 x 5-1/2 inchesB. 1 wood crossbar: 11 x 1 inchesC. 1wood square die “A”: 3 x 1-1/7 inchesD. 1 wood square die “B”: 2 x 1-1/7 inchesE. 1 wood square block: 1 x 1-1/7 inchesF. 1 round head bolt: 1/4 in - 20 x 2 inchesG. 1 t-handle screw: 1/4 in - 20 x 2 inches
Components
H. 1 thumb screw: 1/4 in – 20 x 1-1/2 inchesI. 1 technical measuring set: 6 piecesJ. 1 flare nut wrench: 5 piecesL. 2 thread rods: 6 in - 3/8 inchesM. 4 wing nuts: 3/8 inchesN. 6 hex nuts: 3/8 inchesO. 8 flat washers in different sizes
A
BC
D
E
F GH
I J
L
M
N
O
Procedure
a. Preparation
• Have a chronometer for time measurements
• Have a flipchart and post-its to track results during each iteration and include key notes during the simulation
• Have the tools over a table
b. Initial setup
Procedure
Raw material in production
Raw material for nextproduction
BaseDie in production
BarNuts
New die for next production
ThreadsThumb screw
Rules of the simulation
d. Allocate roles to participantsThe simulation must have at least 3 participants with the following
functions:
e. Define goals for each step (iterations)In the end of each iteration the group creates suggestions for improvement and evaluation of the cost/benefit.
• 1 operator
• 1 quality controller
• 1 material handler
• 1 time keeper/flip chart person
• 1 video recording
Recommended