ABOUT COMPANY

BITECO BIOGAS company specializes in the construction of modern biogascomplexes that convert the energy of organic substances into electrical andthermal energy, as well as combustible gas (biomethane), which is an analogueof natural gas. Such organic substances can be specially grown crops,agricultural or food waste.

The company was founded in 2013, but draws on many years of experience of itsemployees (more than 15 years in the biogas industry and more than 25 years inindustrial energy), who have successful experience in implementing many biogasprojects in the CIS countries, Europe and Asia. BITECO is a registeredtrademark.

BITECO technology is proven technical solutions that are based on our ownimplementations (patents for receiving tanks for removing unwanted inclusions inraw materials), and also have incorporated the successful experience of buildingbiogas plants by our European colleagues.

BITECO BIOGAS specialists have more than 20 biogas projects with rawmaterials of various complexity.

OUR SERVICES

- technology development;

- engineering;

- construction;

- equipment supply;

- installation;

- start-up;

- training;

- maintenance;

- biogas plants operation.

FEED STOCK FOR BIOGAS PLANTSThe raw materials for biogas production are usuallylivestock waste (manure, litter, etc.), as well asagricultural raw materials processing wastematerials (spent grains and corn, vegetable and fruitpulp, waste from slaughter and dairy production,etc.). Also, in order to produce energy crops in theform of silage can be used (corn, sorghum, goat's-rue, etc.) can be prepared.

ENERGY GENERATION FROM BIOGASThe biogas production technology is relatively simple: organic matter (manure, waste,etc.) is periodically fed into the reactor tank, where the fermentation process takesplace. For the process to proceed in the normal mode, it is necessary to maintain acertain temperature in the reactor and mix the contents. All operations are carried outin such a way as to prevent air from entering the reactor. Bacteria are responsible forthe fermentation process. Usually they enter the plant along with biomass (containedin manure). Or they are introduced specifically at the time of launch of the reactor. Theupper part of the reactor, the gas tank, serves to collect and store biogas. The“fermented” biomass is allocated in the bottom part of the digester. Fermentedbiomass is essentially a universal organic fertilizer (biohumus).

To produce biogas, biogas plants are used in places of large concentration of rawmaterials (livestock farms and complexes). A biogas plant consists of a biogasextraction unit (digester, gasholder, separator, etc.) and an energy generation unit(cogeneration equipment).

For the direct generation of heat and electric energy from biogas, as a rule,cogeneration plants based on gas piston engines are used. In such installations,biogas is burned to rotate the electric generator, and the heat generated in the pistongroup is removed and also used for domestic and industrial needs. Thus, themaximum efficiency of such installations is achieved.

BITECO BIOGAS PROJECTS

2013 – 2020

Projects implemented by BITECO BIOGAS within 2013 – 2020 years

No. Plant location Power, kW

Type of plant Implementation

year1 Thailand 1200 Sales to grid 20142 Ukraine 330 Sales to grid 20163 Ukraine 400 Sales to grid 20174 Ukraine 528 Sales to grid 2019

In stage of design and implementation5 Ukraine 1501 Sales to grid 2020

PROJECTS2013-2020

1200 KW2014

#

1 Location – Ubon Ratchathani, Thailand.

2 Plant area – 1,2 Ha3 Installed electric power – 1200 kW

4 Installed heat power – 1248 kW

5 Feed stock – Napier grass + ethanol residues

VIDEO

330 KW2016

#

1 Location – village Bziv, Kiev region, Ukraine.

2 Plant area – 0,5 Ha

3 Installed electric power – 330 kW

4 Installed heat power – 413 kW

5 Feed stock – cow manure + corn silage

VIDEO

400 KW2017

#

1 Location – village Mostove, Nikolaev region, Ukraine.

2 Plant area – 0,8 Ha

3 Installed electric power – 400 kW

4 Installed heat power – 528 kW

5 Feed stock – cow manure + corn silage

VIDEO

528 KW2019

#

1 Location – v. Bokiima, Mlyniv district, Rivne region, Ukriane.

2 Plant area – 0,8 Ha

3 Installed electric power – 528 kW

4 Installed heat power – 623 kW

5 Feed stock – pig manure + corn silage

VIDEO

1501 KW2020

#

1Location – v. Chesnyki, Rogatin district, Ivano-Frankivksregion, Ukraine.

2 Plant area – 1,64 Ha

3 Installed electric power – 1501 kW

4 Installed heat power – 911 kW

5 Feed stock – cow manure + corn silage

«Biteco Biogas» Ltd.

02091, Kyiv, 150/15 Kharkiv highway, of. 5.,

Ukraine+38 044 3627675

Biteco Biogas s.r.l.

62010 Via Firenze 6 Treia, MC, Italy

+39 0733 1960280

CONTACTS

WWW.BITECO-ENERGY.COM