Upload
thamestunnel
View
223
Download
0
Embed Size (px)
Citation preview
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
1/14
DCO-DT-000-ZZZZZ-071902 I February2014
Code of Construction Practice
Part B: Site-specificrequirements
Putney Embankment Foreshore
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
2/14
Code of Construction Practice Part B
This page intentionally left blank
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
3/14
Code of Construction Practice Part B i
Thames Tideway Tunnel
Code of Construction Practice Part BPutney Embankment Foreshore
List of contents
Page number
1 Introduction ...................................................................................................................12 General requirements .................................................................................................23 Communications and community/stakeholder liaison ......................................24 Site operation ................................................................................................................25 Public access, highway and river transport .........................................................46 Noise and vibration .....................................................................................................67 Air quality .......................................................................................................................78 Water resources ...........................................................................................................79 Land quality ...................................................................................................................710 Waste management and resource use ...................................................................811 Ecology (aquatic and terrestrial) .............................................................................812 Historic environment ..................................................................................................813 Other................................................................................................................................9
List of figures
Page number
Figure 1.1 Putney Embankment Foreshore: Site context and location plan..................2
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
4/14
Code of Construction Practice Part B ii
This page intentionally left blank
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
5/14
Putney Embankment Foreshore
Code of Construction Practice Part B 1
1 Introduction
1.1.1 All works described in this document are to be managed and performed tomeet the health and safety vision of Zero Incidents, Zero Harm, Zero
Compromise for the Thames Tideway Tunnel project (the project).
1.1.2 The Code of Construction Practice(CoCP) comprises two parts:
a. Part A: General requirements. These measures are applicable projectwide.
b. Part B: Site-specific requirements. These are site-specific measureswhere deviations from the general requirements are indicated in Part A.
1.1.3 This document forms the CoCPPart B for the project works at the PutneyEmbankment Foreshore site and sets out detailed site-specific measuresincluding working hours, site set-up and servicing arrangements, taking into
account environmental matters and consultations with the London Boroughof Wandsworth and other stakeholders.
1.1.4 For ease of reference,this document sets out site-specific issues anddeviations from Part A; therefore where no site-specific measures arespecified, reference should be made to PartA.
1.1.5 A plan showing the location of the site is shown in Figure 1.1 overleaf.
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
6/14
Putney Embankment Foreshore
Code of Construction Practice Part B 2
Figure 1.1 Putney Embankment Foreshore: Site context and location plan
Note: For detailed limits of land to be acquired or used, refer to the drawings in the Book of Plans.
2 General requirements
2.1.1 As per the CoCPPart A.
3 Communications and community/stakeholderliaison
3.1.1 As per theCoCP
Part A.
4 Site operation
Topic Site-specific requirement
Working hours The following working hours shall apply to this site:
a. standard
b. continuous during construction of the PutneyBridge connection tunnel.
When other types of working hours (CoCPPart A,Table 4.1) are required, these shall be subject to
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
7/14
Putney Embankment Foreshore
Code of Construction Practice Part B 3
Topic Site-specific requirement
consent from the local authority under Section 61 ofthe Control of Pollution Act 1974.
No Sunday working, including maintenance of plant
and/or equipment, shall be permitted before 11:30 oneither Putney Bridge, the vaults beneath the bridge oron any land located east of the bridge, includingworks in the external grounds of St Mary's Churchand works located on the river foreshore.
Site layout The existing Putney public slipway shall bemaintained until the temporary slipway is operationaland shall be maintained until the original slipway isreinstated.
The temporary slipway shall be constructed of steelmodular elements or similar.
Access across Watermans Green shall be restrictedduring the later stages of construction. During thisperiod, pedestrian access to the eastern end of thegreen shall be available via the existing stairwaylocated adjacent to the disused public convenience.
Emergency exit points for the vaults located beneathLower Richmond Road and a route acrossWatermans Green shall be maintained during theconstruction period and their use shall be unaffectedshould existing planning permissions for cafs or
restaurants be implemented.
Site security/hoardingrequirements
The hoarding shall incorporate suitable art work andviewing windows, as defined in CoCPPart A paras.4.3.4a and b.
Timber hoarding shall be used on Watermans Greento limit the worksite to the western part of the greenand protect users from construction activities.
If caf businesses occupy Watermans Green duringthe construction period, the Employer shall work withthe business owner(s) to develop suitable hoardings.
The external appearance of the hoarding shall beapproved by the local authority and transparenthoardings may be used, if agreed with the relevantstakeholders.
River works As per the CoCPPart A.
Other items The contractor shall ensure that the integrity of theretaining wall to Watermans Green and other flooddefence walls is maintained during construction.
The onsite lighting scheme shall be designed in
consultation with local businesses adjacent to theworksite and the local authority to limit adverse
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
8/14
Putney Embankment Foreshore
Code of Construction Practice Part B 4
Topic Site-specific requirement
impacts. Lighting shall be directed away fromsensitive receptors and light spill minimised, eg, byusing directional, capped and cowled lighting.
5 Public access, highway and river transport
Topic Site-specific requirement
Site access and gates The site access shall be from Putney High Street(A219) via Putney Bridge Road, left turn onto LowerRichmond Road and right turn into the site fromEmbankment.
During construction of the temporary slipway,construction vehicles shall access the site by turningright from Lower Richmond Road into GlendarvonStreet and right into Embankment. Vehicles shallthen stop at a designated location on Embankmentadjacent to the site to load/unload. When leaving thesite,vehicles shall route east along Embankment andturn right into Thames Place then left into LowerRichmond Road.
The contactor shall give one months notice to thelocal authority in advance of the use of GlendarvonStreet for the delivery of materials for the
construction, and subsequent removal of thetemporary jetty.
Traffic management Main site
It is proposed to change the operation ofEmbankment between the new site access and thejunction with Lower Richmond Road to two-way forconstruction vehicles only during the main site works.A minimum carriageway width of 3.25m shall beretained in each direction.
Construction vehicles associated with the main
construction site shall not be permitted to useGlendarvon Street.
A traffic marshal shall be in place for when largevehicles are required to reverse out of the site ontoEmbankment.A small section of on-street parking shall besuspended on the eastern end of Embankment
The cycle stands on Embankment shall be relocatedapproximately 20m to the west.
Temporary slipway site (construction and
dismantling)
Construction vehicle drivers shall be warned in
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
9/14
Putney Embankment Foreshore
Code of Construction Practice Part B 5
Topic Site-specific requirement
advance of the restricted road width alongGlendarvon Street and advised to look out forpotential conflicts with oncoming vehicles.
Construction vehicles shall only access the site viaGlendarvon Street between 10:00 and 15:00 Mondayto Friday. Construction vehicles shall not be permittedto use Glendarvon Street outside this period.
The contractors traffic management plan shalladdress potential conflicts between constructionvehicles and other large vehicles (such as vehiclestransporting boats) at the GlendarvonStreet/Embankment junction by means of measuressuch as timed deliveries, traffic marshals or prioritysignage.
Two-way flow on the Embankment carriageway shallbe maintained for general traffic using a priority trafficmanagement system as required during constructionof the temporary slipway.
A small section of parking on the southern end ofGlendarvon Street shall be suspended to facilitatevehicles passing each other.
Parking bays located at the southern end ofGlendarvon Street to facilitate construction vehiclemovements shall be replaced (subject to agreement
with the London Borough of Wandsworth) withparking restrictions that enable local residents to parkoutside of the hours of 10.00 to 15.00 Monday toFriday
The majority of on-street parking on Embankmentbetween Thames Place and Glendarvon Street shallbe suspended during these phases of works.
The parking suspensions listed above under theheading Temporary slipway siteshall only occurduring construction and removal of the temporary
slipway.Event restrictions Identified river race events, including the University
Boat Race,shall not be restricted by the works. Theconstruction site shall not be removed butconstruction shall be temporarily suspended and anybarges associated with the works removed.
For the University Boat Race,the contractor shallarrange additional security and take other measuresset out in the site security plan to ensure that the siteis contained and to prevent members of the publicclimbing hoardings or entering the site.
Further event restrictions may be required following
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
10/14
Putney Embankment Foreshore
Code of Construction Practice Part B 6
Topic Site-specific requirement
discussions with stakeholders.
River transport No weekend river transport shall be permitted.
Access to Putney Pier shall be maintained for the
duration of the construction works. The contractorshall liaise with Transport for London (London RiverServices) and the pier owners.
Deliveries of plant, equipment, welfare facilities andready-mix concretefor the temporary slipway worksshall be via Glendarvon Street.Other constructionmaterials shall be delivered by river to the temporaryslipway site unless marine restrictions prevent thetimely installation/removal of that slipway or unlessotherwise approved by the local authority.
Other A removable chain shall be installed across thetemporary slipway to prevent unauthorised parkingwhile maintaining access to launch vessels.
The contractor shall produce and implement a plan, inconsultation with St Marys Church, to ensure safepassage to the church and Busy Bee by the BridgeNursery School. The plan shall include measures toensure that no conflict occurs between themovements of construction personnel, materials andtools/equipment relating to works in the vaults on theeastern side of Putney Bridge and people accessingthe church and the nursery school.
Where appropriate,signage and warning systemsshall be installed to direct rowers and other riverusers around structures within the foreshore.
6 Noise and vibration
Topic Site-specific requirement
Control measuresThe noise and vibrationcontrol measures shall bedetailed (and may be modifiedor added to) in Section 61consent applications to thelocal authority.
Barges shall only be loaded and unloaded duringstandard working hours.
Outside of standard working hours,the use of surfacecranes during connection tunnel works shall beminimised. This will involve stockpiling materials/equipment at the bottom of the CSO drop shaft foruse during the evening and night to be removedduring standard working hours. In addition,thecontractor shall implement measures to reduce noiseincluding using electric gantry cranes and gas/electricforklifts, particularly when moving and unloading
skips.A 2.4m high noise screen shall be located on the
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
11/14
Putney Embankment Foreshore
Code of Construction Practice Part B 7
Topic Site-specific requirement
western edge of the sections of the cofferdam that areperpendicular to the river wall.
Except for the anchor piles, the contractor shall
construct the cofferdam using push piling unless thisis determined to be impossible. In this case, this shallbe demonstrated by the contractor who shall make anapplication to the relevant local authority for analternative piling method through the Section 61dispensation process (see Appendix A; Section A.1 inthe CoCPPart A) or through contingency measuresand arrangements if included in the original Section61 consent.
Other N/A
7 Air quality
Topic Site-specific requirement
Vehicle and plant emissions As per the CoCPPart A.
Dust emissions/control As per the CoCPPart A.
Odour As per the CoCPPart A.
Other N/A
8 Water resources
Topic Site-specific requirement
Control of pollution: surfacewater/groundwater
As per the CoCPPart A.
Control on abstraction As per the CoCPPart A.
Ground treatment As per the CoCPPart A.
Other N/A
9 Land quality
Topic Site-specific requirement
Site works As per the CoCPPart A.
Site-specific issues/mitigation As per the CoCPPart A.
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
12/14
Putney Embankment Foreshore
Code of Construction Practice Part B 8
10 Waste management and resource use
Topic Site-specific requirement
Excavated material As per the CoCPPart A
Energy usage As per the CoCPPart A.
Other N/A
11 Ecology (aquatic and terrestrial)
Topic Site-specific requirement
Protection of habitats A membrane shall be installed between the riverbedand any temporary back fill material to prevent
contamination of juvenile fish habitat.
Areas of foreshore used for temporary works shall berestored to a similar condition with appropriatematerials as prior to the works.
Protection of trees The contractor shall carry out a survey to ascertainthe location of tree roots in relation to slipways,highways and footpaths.
Roots of large London Plane trees shall be protectedfrom damage during the installation of cable ducts.
Suitable protection shall be laid on the existingcobbled slipway to protect the roots of the LondonPlane tree located on Watermans Green.
Pruning of trees located along Embankment and onWatermans Green shall be agreed with the localauthority.
Other N/A
12 Historic environment
Topic Site-specific requirement
Other When attaching the cofferdam against the southernabutment of the listed Putney Bridge, the contractorshall avoid direct fixing into the abutments stoneworkfacings, unless agreed otherwise with the localauthority.
Hand railings along Watermans Green shall beprotected during the works and reinstated followingconstruction.
Putney public slipway shall be protected duringconstruction and localised areas of cobbles removed,
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
13/14
Putney Embankment Foreshore
Code of Construction Practice Part B 9
Topic Site-specific requirement
stored and reinstated to the existing condition as faras practicable.
The University Boat Race starting stone shall be
protected from damage.The contractor shall remove, protect and reinstate thelisted bollards, which shall be securely stored for theduration of the works.
The contractor shall identify any requirements totemporarily remove the statue load located at thejunction of Lower Richmond Road and Embankment.Measures to protect the statue, whether it istemporarily removed or kept in situfor the duration ofthe works, shall be submitted to and agreed in writingwith the local authority. If removed, the statue shall be
securely stored for the duration of the works.
The contractor shall select working methods thatminimise the risk of vessels striking the listed bridge.Protection barriers shall be installed,as required,butnot attached to the listed structure unless otherwiseagreed with the local authority in consultation with theHistoric Buildings and Monuments Commission forEngland.
13 OtherTopic Site-specific requirement
Other As per the CoCPPart A.
8/13/2019 Code of Construction Practice Part B: Site Specific Requirements - Putney Embankment Foreshore - Comparite ag
14/14
Document comparison by Workshare Compare on 10 February 2014 13:53:16
Input:
Document 1 ID interwovenSite://VRT-DMS-01/Legal/34196042/1
Description#34196042v1 - CoCP Part PEF Revised 3 Feb
2014Document 2 ID interwovenSite://VRT-DMS-01/Legal/34239853/1
Description #34239853v1 - CoCP B PEF - 12 Feb 2014
Rendering set no change numbers no summary
Legend:
Insertion
Deletion
Moved from
Moved to
Style change
Format change
Moved deletion
Inserted cell
Deleted cell
Moved cell
Split/Merged cell
Padding cell
Statistics:
Count
Insertions 0
Deletions 1
Moved from 0
Moved to 0
Style change 0
Format changed 0
Total changes 1