EPCM Approach for Steam Power Projects
Multi Packages Concept
Asem Elgawhary
January 2019
2
Steam Power Plant
3
Steam Power Plant
CP/PO DESCRIPTION
CP Civil works
CP Environmental Monitoring
CP Switchyard
CP Steam Generator
CP Turbine Generator and condenser
CP Yard Tanks
CP Insurance
PO Pumps and drivers
PO Heat Exchangers
CP Water and waste water treatment/Desalination Plant
PO Critical piping and valves
PO Power Transformers
PO Instruments and control
CP Electrical and instrument installation.
CP Mechanical and piping installation
CP Offshore Works
CP Colony
PO Medium & Low Switchgear
CP Site Services
EPCM
4
The Steam Power Plant project will be executed by Multi contractsand purchase orders include the following packages:
1. Site Services: (Contract Package)Designing, Fabrication, Furnishing and Installing constructionbuildings, construction power, Potable water system and Sewagesystem for construction and complete site preparation to be readyfor civil constructions.
2. Civil Works: (Contract Package)Fabrication, Furnishing and Installing providing associated servicesfor piling, foundation, buildings, structure steel, intake anddischarge structures for circulating water system, undergroundpiping, chimneys, and access roads for the project.
Description of Steam Power Plant
5
Description of Steam Power Plant (Cont.)
3. Environmental Monitoring: (Contract Package)Designing, Fabrication, Furnishing, Delivery, Installing, start up andCommissioning, and Testing the required environmental MonitoringStation with all associated electrical instrumentation equipment.
4. Switchyard: (Contract Package)Designing, Fabrication, Delivery, Installing, start up and
Commissioning of indoor Gas insulated Switchyard “GIS” including
the building construction and the connection between the main
transformers and the switchyard, Protection and communication,
control systems and all related civil, mechanical, electrical works
required for complete operational system.
6
5. Steam Generators: (Contract Package)Designing, Fabrication, Furnishing, Delivery, Installing, start up andCommissioning, and Testing two outdoor supercritical Steam Generators,capable of sliding pressure operation with associated systems and equipment,including water walls, economizers, reheaters, super heaters, startupequipment, safety valves, burners and ignition systems, burner managementsystems, soot blowers, flue gas ductworks, regenerative air preheaters, forceddraft fans, gas recirculation fans, and associated pumps & motors.
Natural gas will be utilized for main burners and ignitors, Mazout oil (No.6) willbe utilized as a backup fuel for main burners, Solar Oil (No.2) will be utilizedfor warm up burners.
The scope of work will also include: Related mechanical equipment, and piping Related electrical equipment, instrumentation and control CEMS-Continuous emission monitoring system
Description of Steam Power (Cont.)
7
Description of Steam Power Plant (Cont.)
6. Steam Turbine Generators & Condensers: (Contract Package)
Designing, Fabrication, Furnishing, Delivery, Installing, start up and Commissioning,
and Testing two supercritical, four flow condensing steam turbines. The steam turbine
will be tandem compound, single reheat, and 3000 rpm, with uncontrolled
extractions for feed water heating. The turbine generator and controls shall be
designed for both sliding and constant pressure operating modes. The steam will be
exhausted to a condenser with divided water box. The turbine will be coupled to a
hydrogen cooled generator.
The scope of work will also include: Related mechanical equipment, and piping Related electrical, instrumentation and control. Heater # 1 and # 2 in a combined shell mounted in the condenser neck including
the extraction steam piping to the heaters and drain piping to the condenser. Closed low pressure heaters. Closed high pressure heaters, Deaerator heater and deaerator storage tank Steam Turbine building bridge crane.
8
Description of Steam Power Plant (Cont.)
7. Yard Tanks: (Contract Package)Designing, Furnishing, Testing and Installing of Demineralized watertank/ condensate storage tank, Mazout oil (No.6) storage tanks, solaroil (No.2) storage tank and water treatment tanks.
8. Wrap Up Insurance: (Contract Package)Provision of insurance during the construction, start up, testing andcommission construction period up to the end of warranty period.
9. Pumps & Drives: (Purchase Order)Designing, Furnishing, Shop testing, Delivery, Supervision of erectionand technical services for erection and commissioning of turbinedriven boiler feed pumps, motor driven start up feed pump,condensate pumps, circulating water pumps, and service waterpumps.
9
Description of Steam Power Plant(Cont.)
10. Water & Waste Water Treatment Systems: (Contract Package)Designing, Fabrication, Furnishing, Delivery, Installing, start up andCommissioning, and Testing of raw water pumps, raw water pre-treatment system, makeup demineralized water system, condensatepolishing system, hypochlorite system, feed water chemical feedsystem, and waste water treatment system with all associatedelectrical instrumentation and associated piping and valves. The scopeof works may include multistage flash type desalination plant andnecessary accessories and auxiliary systems.
11. Critical Piping & Valves: (Purchase Order)Furnishing, Shop testing, Delivery, Supervision of erection andtechnical services for erection and commissioning of critical piping &valves, supports, thermo wells, thermocouples and flow elements forcritical piping systems (main steam, cold reheat, hot reheat, feedwater, extraction steam and auxiliary steam systems).
10
12. Power Transformers: (Purchase Order)Designing, Furnishing, Shop testing, Delivery, Supervision of
erection and technical services for erection and commissioning of
main power transformers, unit auxiliary transformers and start-
up transformers (if required). Generator Circuit breakers and
isophase buses for connection between the Generator and the
transformers.
13. Instrumentations & Control: (Purchase Order)Designing, Furnishing, Shop testing, Delivery, Supervision of
erection and technical services for erection and commissioning of
DCS, Operator and Auxiliary control consoles, Auxiliary control
devices and data high way cables and a complete simulator for
owner personnel operational training.
Description of Steam Power Plant (Cont.)
11
Description of Steam Power Plant (Cont.)
14. Electrical Equipment / Instrument Installation: (Contract Package)
Designing, Fabrication, Furnishing, Delivery, Installing, start up and
Commissioning and Testing of DC equipment, electrical distribution
panels, relay panels, UPS equipment, medium, low voltage and
control cables, cable trays, conduits and other miscellaneous
electrical and instrumentation equipment. Receive at site, store,
install, test, maintain, and place into successful operation the
electrical and instrumentation equipment furnished by owner (main
and unit auxiliary transformers, generator circuit breaker, isophase
bus, medium and low voltage switchgear, M.C.Cs, distributed control
system, control panels, etc).
12
Description of Steam Power Plant (Cont.)
15. Mechanical & Piping Installation: (Contract Package)
Designing, Fabrication, Furnishing, Delivery, Installing, start up and
Commissioning and Testing of fire water suppression system, HVAC
system, small bore piping, valves, pipe supports and hydrogen
generation system. Furnishing, Delivery, Installing, start up and
Commissioning and Testing of diesel driven fire pump, main motor
driven fire pump, jockey pump, air compressors, closed cooling water
heat exchangers, closed cooling water pumps, diesel generator unit,
sampling system, non critical large bore piping, valves, and shop
fabricated tanks. Receive at site, store, install, maintain and test the
miscellaneous mechanical equipment designed and furnished by
owner (Critical piping and their supports, Critical valves, desalination
plant, Heat exchangers and pumps & drivers etc).
13
Description of Steam Power Plant (Cont.)
16. Medium and Low Voltage Switchgear: (Purchase Order)Designing, Furnishing, Shop testing, Delivery, Supervision oferection and technical services for erection and commissioning of(6.3 KV) Medium voltage switchgears, low voltage Switchgears andmotor control centers.
17. Offshore Facility (if required): (Contract Package)Supply and install offshore intake and discharge facilities includingoffshore piping, dredging and supporting structures.
18. Colony (if required): (Contract Package)Fabrication, Furnishing and Installing providing associated servicesfor a housing residential colony.
14
19. Engineering Services:Perform the professional services of the project management,engineering, design, procurement of the plant packages and theirbalance of plant. The main activities are as follows: Prepare the bid packages Evaluate the bid document and negotiate the successful
bidder. Prepare the contracts document. Preliminary and Final design for civil activities and the
balance of plant. Manage and coordinate the interfaces between contractors. Supervise the construction works and perform the
commissioning start up, and test up to handling over theproject.
Description of Steam Power Plant (Cont.)
15
Steam Power PlantSummary Milestone Schedule
Year
Quarter 1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND 3RD 4TH 1ST 2ND
Month 1,2,3 4,5,6 7,8,9 10,11,12 13,14,15 16,17,18 19,20,21 22,23,24 25,26,27 28,29,30 31,32,33 34,35,36 37,38,39 40,41,42 43,44,45 46,47,48 49,50,51 52,53,54 55,56,57 58,59,60 61,62,63 64,65,66
PLANTCLEAR SITE FIRST ENERGIZATION STEAM T. ROLL START
NTP AVAILABLE CONCRETE BLOW R.RUN
ENGINEERING
CONSTRUCTION MANAGEMENT
AWARD START COMPLETE COMPLETE
PROCUREMENT CYCLE PILING BOILER FND STG BUILDING
AWARDPROCUREMENT CYCLE DELIVERY
AWARDDELIVERY T. ROLL
R.RUN
AWARD STEAMBLOW
DELIVERY
SWITCHYARDAWARD ENERGIZATION
DELIVERY
BOILER
Dates
SWITCHYARD
STEAM TURBINE
OFFSHORE PACKAGE
CIVIL PACKAGE
EPCM
ENGINEERING
CONSTRUCTION
MANAGEMENT
CONTRACTS CLOSING
Project Milestones
5 61 2 3 4
The Schedule is based on three months gap between Unit #1 and Unit #2
16
Eligibility Requirements and Past Experience
17
Eligibility Criteria – Electrical and Mechanical Packages
Open to International Tenderers
Contractors applying independently;
or
A consortium of two or more, local or foreign partners with either a
Local or Foreign Contractor as the Lead Partner of the Consortium.
All partners shall be jointly and severally liable
18
Eligibility Criteria – Electrical and Mechanical Packages
Past Experience
Contractor applying independently or lead partner in consortium
Two Power Station Projects of similar complexity during the last 10
years.
One industrial Project of similar complexity during the last 10 years.
Three different locations, one of which is outside contractor’s
country of origin (for foreign contractors).
Tenderer executed projects as Main contractor/partner of a
consortium.
Projects value = USD 30 million.
Projects must have been completed in a duration not exceeding 48
months .
19
Civil Works Package
Past Experience
Other partner(s) in consortium (if applicable)
One Power Station Projects of similar complexity during the last 15
years.
Two industrial project during the last 10 years.
Three different locations. For foreign contractors, one of the project
locations is outside country of origin.
Minimum value of each project USD 25 million
Tenderer executed projects as a Main contractor/partner of aconsortium.
Projects must have been completed in a duration not exceeding 48months.
20
Electrical Works Package
Past Experience
Contractor applying independently /Lead Partner
Three Power Station Projects of similar complexity during the last 15
years at three different locations.
Tenderer executed projects as Main contractor/lead partner of a
consortium.
For non-Egyptian contractors, one of the referenced projects shall be
outside the country of origin of Tenderer/Lead Partner.
Projects value = USD 10 million.
Projects must have been completed in a duration not exceeding 36
months.
21
Electrical Works Package
Past Experience
Partner in a consortium
One Power Station Projects and one industrial project of similar
complexity during the last 15 years at two different locations.
Tenderer executed projects as Main contractor/ subcontractor/
partner of a consortium.
Projects value = USD 5 million.
Projects must have been completed in a duration not exceeding 36
months.
22
Mechanical Works Package
Past Experience
Contractor applying independently /Lead Partner
Two Power Station Projects of similar complexity during the last 15years at two different locations.
Tenderer executed work as a Main contractor/partner of aconsortium.
For foreign contractors one of the two referenced projects shall beoutside the country of origin of Tenderer.
Projects value = USD 20 million.
Projects must have been completed in a duration not exceeding 36months.
23
Mechanical Works Package
Past Experience
Partners Other than Lead
One Power Station Project of similar complexity during the last 15years.
One industrial Project of similar complexity during the last 15 years.
Two different locations.
Main contractor/Subcontractor/partner of a consortium.
Projects value = USD 10 million.
Projects must have been completed in a duration not exceeding 36months.
24
Tender Evaluation Criteria
25