EPCM JACOB

Embed Size (px)

Citation preview

  • 8/9/2019 EPCM JACOB

    1/19

    2011 Material Handling Industry. Copyright claimed as to audiovisual works of seminar

    sessions and sound recordings of seminar sessions. All rights reserved.

    Welcome to Session 228

    Sponsored by:Presented by:

    Stephen Donohoe, PMP Manager of

    ConstructionTed Dalferes, P.E. Director,

    Distribution Center Design

    Tim Johnson Project Manager

    The Benefits of EPCM Project Delivery

    for Your Distribution Facility

  • 8/9/2019 EPCM JACOB

    2/19

    Agenda Speaker Introductions

    Factors & Influencers Owners Control & Risk

    Why Use an EPCM* Approach?

    *Engineering, Procurement, Construction Management

  • 8/9/2019 EPCM JACOB

    3/19

    Factors & Influencers When to bring on CM or GC

    Owner Requirements How much control Schedule objectives

    Cost objective Quality objectives Safety, claims, etc. objectives

    Degree of Project Complexity

  • 8/9/2019 EPCM JACOB

    4/19

    Typical Owners Requirements Budget

    On budget Min contingency remaining at completion

    Schedule Meet commitments

    Design Quality

    Functionality

    Construction No defects No claims No accidents

    Coordination Minimize impact to operations

    LOWEST

    COST!

    SHORTEST

    SCHEDULE!

    MAXIMIZE

    CONTROL!

    NO

    CHANGES!

  • 8/9/2019 EPCM JACOB

    5/19

    Delivery Method Influencers Owners:

    Budget & risk objectives guarantees?

    Schedule objectives degree of urgency Desire for control design & construction

    Resources experienced & qualified PMs

    Project complexity & design Procurement flexibility

    Single project or multiple projects

    New construction vs. renovation

  • 8/9/2019 EPCM JACOB

    6/19

    Balancing the Variables

    Schedule Criticality

    Owner Control

    Risk ExposureLow High

    Public Private

    Min. Max.

    Low High

    Procurement Flexibility

    Schedule Criticality

    Owner Control

    Risk Exposure

    Procurement Flexibility

  • 8/9/2019 EPCM JACOB

    7/19

    Owners Control & Risk

    HIGH

    LOW

    CONTROL

    AND RISK

    OWNER CONTROL

    CM Agent CM Cost CMR CMR-GMP GC LumpMulti-Prime Plus Sum

    CMR = w/ Negotiated GMP

    CMR-GMP w/ Competit ive GMP

    Where do you

    want to be?

  • 8/9/2019 EPCM JACOB

    8/19

    Dont confuse project management

    methods with project deliverymethodsthey are different!

    Project ManagementMethods

    In-house staff

    Owners representative

    Agency constructionmanager

    Program manager

    Project Delivery Methods

    Design / bid / build (GCLump Sum)

    CM at Risk withcompetitive GMP

    CM at Risk with negotiated

    GMP CM at Risk Cost Plus

    CM Agent Multi-Prime

  • 8/9/2019 EPCM JACOB

    9/19

    Why an EPCM Approach? Provides a single point of contact, accountability and

    responsibility

    Maximizes execution flexibility

    Controls / saves cost

    Improves safety

    Reduces project schedule

    Eliminates redundant project management / siteindirects

    Focused change control

  • 8/9/2019 EPCM JACOB

    10/19

    Design-Bid-Build

    CM-Based Delivery

    CM Gives More Opportunity to Reduce Schedule

  • 8/9/2019 EPCM JACOB

    11/19

    Setting the Stage Construction costs are out of control

    Escalation of materials & equipment isunprecedented

    Project delivery time needs to be reduced

    to meet customer needs Traditional construction delivery is not

    conducive for teamwork and controlling

    cost

  • 8/9/2019 EPCM JACOB

    12/19

    Time is Money

    SCHEMATIC

    DESIGN

    DEVELOPMENT

    CONCEPT

    PROJECT LIFE CYCLEPROJECT LIFE CYCLE

    PROJECT

    PROJE

    CT

    EXPENDITURES

    EXPENDIT

    URES

    CONSTRUCTION

    DOCUMENTS

    BIDDING

    CONSTRUCTION

    CLOSE

    OUTLEVEL

    of

    LEVEL

    of

    INFLUENCE

    INFLUENCE

    selection of

    delivery method

    cost

    curve

    influence

    curve

  • 8/9/2019 EPCM JACOB

    13/19

    Clients Looking for Change

    Control & ownership of budgets Designand Construct to budget

    Schedule-driven projects

    Staffing resource challenged

    Risk mitigation critical for project success

    Lean execution for streamlined project

    delivery

  • 8/9/2019 EPCM JACOB

    14/19

    Why EPCM cost reimbursable fixedfee open book approach?

    CM GMP has bad track record for increased cost

    Costs are rising faster than can be forecasted

    Schedule does not allow for detailed GMP early

    Clients looking for integrated team by 1 firm

    single point of accountability / responsibility

    Client only pays for actual cost of project

    Client wants assurance and comfort in working

    with contractor

  • 8/9/2019 EPCM JACOB

    15/19

    Selling EPCM Cost ReimbursableFixed Fee Open Book Integrated

    Project Delivery

    Requires selling outside the box

    Requires passion for process

    Requires courage to challenge norm

    Requires discipline and strong project

    controls similar to lump-sum Requires a firm like Jacobs

  • 8/9/2019 EPCM JACOB

    16/19

    Benefits of An EPCM Delivery Model

    Integrated project delivery team

    Project execution based on the end in mind commissioning and turnover

    High degree of cost visibility we are open

    book Continually tracks & informs client of real time

    costs

    Allows escalating costs of steel, energy,shipping and labor to be managed andminimized

  • 8/9/2019 EPCM JACOB

    17/19

    continued

    Allows design to overlap construction

    Procurement can be arranged to achieve thebest value for our clients

    Pre-purchase equipment detailed in final

    design

    Allows major subcontractors to provide inputto design to allow for best value in the field

    Rapid response to field issues keeps projecton schedule

    Benefits of An EPCM Delivery Model(continued)

  • 8/9/2019 EPCM JACOB

    18/19

    Quality management plan maximizes efficiency

    through administration, communication, qualitycontrol, schedule control

    Flexibility to divert or focus resources as needed for

    the project

    Established field procedures to hit the ground

    running

    Detailed early commissioning plans and schedules

    with maximum involvement of client operations and

    maintenance staff, as well as equipment vendors

    Benefits of An EPCM Delivery Model(continued)

  • 8/9/2019 EPCM JACOB

    19/19

    2011 Material Handling Industry. Copyright claimed as to audiovisual works of seminarsessions and sound recordings of seminar sessions. All rights reserved.

    For More Information:

    Speaker: [email protected]

    Speaker: [email protected]

    Speaker: [email protected] Page: www.jacobs.com

    Visit ProMat 2011 Booth 2678