Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
LHC Beam InstrumentationLHC Beam Instrumentation--
First Results & Next StepsFirst Results & Next Stepspp
Session 07 - What did we learn with beam in 2008?
LHC Performance WorkshoppChamonix 2009
Rhodri Jones on behalf of BE/BI & all our collaborators
LHC BTV SystemLHC BTV SystemAll f ll i i d● All screens fully commissioned● 18 BTV in the LHC transfer lines● 13 BTV in the LHC ring● 6 BTV in the LHC dump lines● 6 BTV in the LHC dump lines
● Both video link and digitised data acquired on first shot
Fi t f ll tFirst full turnas seen by the
BTV10/9/200810/9/2008
Uncaptured beam sweeps
through he
● Still to doFirst Beam in the LHC 8/8/2008
through he dump line
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam LHC Beam InstrumentationInstrumentation
● Still to do● Gradual replacement of the 13 LHC ring CCD cameras with rad hard cameras● Turn by turn acquisition for matching measurements using fast cameras
LHC BLM System ILHC BLM System I
● Worked well from first injection tests● Logging issues (linked to data rates) sorted out early on● Data concentration
&● on-demand capture & continuous monitoring tested
No loss seen (< 107 protons)
Injection Dump on TCT 5L
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
Clean injection (IP2 to IP5)
LHC BLM System IILHC BLM System II2 b i d d t i f h t ti t d i i j ti t t● 2 beam induced triggers of quench protection system during injection tests● Loss of between 2 - 4 × 109 protons with very different loss patterns
IP3Quench
MQ11.R2
Quench
● Quench reconstruction700m 450m
● Quench reconstruction● One quench occurred at end of MB magnet ⇒ not useable for analysis● One in middle of dipole ideal for analysis
● Beam current impact location & loss distribution width used to constrain simulations
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
● Beam current, impact location & loss distribution width used to constrain simulations● Result factor 2 lower compared to value obtained by calculating enthalpy of the coil
● ~15 mJ/cm3 estimated compared to 30 mJ/cm3 expected
LHC BLM System IIILHC BLM System IIISNext Steps
● Hardware:Di tli & i t ll ti ( t 3 4 & ll t )● Dismantling & re-installation (sector 3-4 & all warm sectors)● Opening of W-bellows ⇒ dismounting large fraction of BLM cable trays & monitors
● Separation of HV supply cables for SEM & ionisation chambersAi d t d i b d t lk b t th t t● Aimed at reducing observed cross talk between the two systems
● Implement possibility of full reset of front-end electronics● Addition of small mezzanine card to all front-end electronics cards
N i h k f i l bl t k● Noise check of signal cable network● Repair and replacement of poor connectors and cables
● Increase spare parts with new production of electronics boards● Software
● BLM threshold settings● Design of application to load and check threshold settings in database● Design of application to load and check threshold settings in database● Test of software package for handling machine critical settings● Definition of procedures for manipulation of critical settings
● FPGA code
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
● FPGA code● Construction of PASS/FAIL regression test bench to allow full qualification
of software updates before any global deployment
LHC BPM System ILHC BPM System I● Asynchronous bunch by bunch (FIFO) mode
● Used for threading & first few 100 turns (no bunch or turn tagging)● AB/CO BPM concentrator groups data from 66 front-end VME crates
● Worked first time on both beams for injection tests & on 10th September● Problem encountered with first turn overwritten by subsequent turns
● FIXED in FPGA code of the hardware the same day
First full turn for Beam 1 First full turn for Beam 2● Asynchronous orbit (IIR) mode
● Provided filtered data for 1Hz orbit update to YASP & feedback controllerRouted via orbit feedback concentrator
First full turn for Beam 1 First full turn for Beam 2
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
● Routed via orbit feedback concentrator● Worked as soon as beam was circulating for more than a few seconds
LHC BPM System IILHC BPM System IIO li l i f BPM D t● On line analysis of BPM Data● Powerful on-line tools developed by AB/OP● Polarity errors easily identified with 45° BPM sampling● Quick indication of phase advance errorsQuick indication of phase advance errors
Horizontal kickHorizontal kick
Vertical kickVertical kick
● Some statistics to date● 4 polarity errors● 2 H to V inversions & 7 BPM mapping errors (LSS8L) ● 1 B1 to B2 inversion
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
● 1 B1 to B2 inversion● Some 10 remaining suspect BPMs (noisy or incoherent data)● Total of ~24 out of 2156 channels (~1%)
LHC BPM System IIILHC BPM System III● Check of BPM Threshold Levels
● Threshold determined to be 1.5×109 protons● Compared to pre-declared limit of 2.0×109p p
● Initial values did not correspond to lab measurements● Threshold was 6dB lower in the laboratory● Accurate re-measurement of electronics & cables for final bandwidth & signal loss g● Final model now agrees with beam measurements
● Understanding important for intensity card
1000
400600800
ror (
μm)
80.0
100.0
te (%
)
Pilot
400-200
0200
Arc
BPM
Err
40.0
60.0
M T
rigge
r Rat
-1000-800-600-400
LHC
A
0 0
20.0 BPMLinearity (Lab)
Noise (Lab)Arc BPM Trigger Rate
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
10001E+08 1E+09 1E+10 1E+11
Bunch Intensity (protons)
0.0
LHC BPM System IVLHC BPM System IVO & S● Orbit & BPM Stability● Short term stability (15 minutes) better than 10μm● Alternating high/low peaks follow the beta function indicating that:
● large fraction of this noise results from beam itself (COD power supplies ⇒ 5-10μm orbit rms)● large fraction of this noise results from beam itself (COD power supplies ⇒ 5 10μm orbit rms)● resolution & stability of BPM system in orbit mode with single pilot bunch is ~5μm
● BUT - Surface electronics sensitive to temperature variations (~50μm per degree)● Point 4 – electronics in BI control room so much more sensitive to variations● Point 2 – electronics in standard SR outbuilding where source of fluctuation is unclear● Point 2 – electronics in standard SR outbuilding where source of fluctuation is unclear
● Several solutions being looked into to solve this problem
y y
Horizontal Vertical
yy yy
Horizontal Vertical
Tim
e of
day
Tim
e of
day
Drif
t (μm
)
Drif
t (μm
)
Tim
e of
day
Tim
e of
day
Tim
e of
day
Tim
e of
day
Drif
t (μm
)
Drif
t (μm
)
Drif
t (μm
)
Drif
t (μm
)
Drif
t (μm
)D
rift (
μm)
Drif
t (μm
)D
rift (
μm)
Difference orbit taken from 2 acquisitions 5 minutes apart (note scale!)
Dse
(μm
)
Dse
(μm
)
Dse
(μm
)D
se (μ
m)
Dse
(μm
)D
se (μ
m)
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
rms
nois
rms
noi
rms
nois
rms
nois
rms
noi
rms
noi
LHC BPM System VLHC BPM System V● Next Steps
● Sector 3-4● Dismount test & re-install BPMs & electronics in damaged area● Dismount, test & re-install BPMs & electronics in damaged area● Test all BPM electrodes for MLI or soot contamination after cleaning
● Other Shutdown WorkAdditi f i l BPM t● Addition of spring clamps on BPM ports
● Foreseen for all sectors remaining cold (danger of damage to cryo cables?)● Implies disconnection & re-connection of ~2000 external BPM cables● Sectors will have to be re-commissioned for polarity etc● Sectors will have to be re-commissioned for polarity etc
● Installation of intensity cards throughout the ring● Commissioning in 2009
C i i C t M d (b h & t t i )● Commission Capture Mode (bunch & turn tagging)● Automated software & hardware routines being put in place to phase in BPMs
● Commission Position Interlock BPMs for the dump channel in IR6 C i i F db k S t● Commission Feedback System
● Acquisition system already commissioned (same orbit data as YASP)● Attempt at feedback requires completion of
◦◦ Corrector polarity checksCorrector polarity checks to be reto be re donedone
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
◦◦ Corrector polarity checks Corrector polarity checks –– to be reto be re--donedone◦◦ Optics checks Optics checks –– to be reto be re--donedone◦◦ Feedback controller to PC mapping Feedback controller to PC mapping -- still to dostill to do
Analysis of BPM DataAnalysis of BPM Data● LHC alignment estimates
● Overall very good! : 200 - 500μm rms● Assumed orbits are given by Quad misalignments
● Quad rms to orbit rms propagation & correcting orbit using Quad shifts gave same results
● Systematic vertical offset from IR2 to IR5 is visible ● Source not yet understood & no obvious explanation
● Systematic misalignment or thermal drift of BPMs unlikely● Machine optics or magnet imperfections (b1 to a1 tilt) unlikely● Machine alignment – no obvious explanation according to APB/SU Section
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
LHC Q, Q’ & LHC Q, Q’ & CC Systems ISystems I● BBQ Tune Measurement Systems Commissioned for Beam 2
● Observed nice signals for injection oscillations● Allowed tune to be adjusted early-on to improve initial lifetime
Vi ibl i id l it d i l ti b t ith S/N ti > 10dB● Visible in residual non-excited circulating beam spectra with S/N ratio > 10dB
● InitiallyTrim of Q ● Initially● No RF capture● QH ≈ 0.50● Q ≈ 0 24
Trim of QH
● QV ≈ 0.24● Trim of ΔQH by -0.2
● QH ≈ 0.50 → 0.32M i f th h lf● Moving from the half-integer resonance increases circulation time to 300+ turns (still (no RF capture)
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
Before correction
After correction
LHC Q, Q’ & LHC Q, Q’ & CC Systems IISystems II● BBQ Tune On-Demand system commissioned
● Chirp excitation using transverse damper● Polarities verified to be correct (excitation & acquisition)
● Allowed first measurement of coupling● Measured coupling |C-| ≈ 0.07
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
LHC Q, Q’ & |LHC Q, Q’ & |C|C| Systems IIISystems III● First Estimates of Chromaticity
● Tune shift due to injection momentum offset● Comparison of injection tunes to circulating beam tunes● Comparison of injection tunes to circulating beam tunes
● Inconclusive as no systematic logging of momentum mismatch● Estimates from tune to synchrotron sideband amplitude ratio
● Measured chromaticity Q ’ ≈ Q ’ ≈ 32● Measured chromaticity QH ≈ QV ≈ 32
Tune changes due Q’ estimatedgTo injection energy
mismatchfrom
sidebandenvelope
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
LHC Q, Q’ & LHC Q, Q’ & CC Systems IISystems II● Head-Tail / Instability Monitor
● Beam 2 system tested but acquisition software to be finalised & tested● Will give same functionality as SPS Head-Tail system● Used for head-tail chromaticity measurement & as instability monitor
● Next Steps for Q, Q’ and C Measurement Systems – commissioning of:p , y g● Beam 1 and Beam 2 PLL Systems● Chromaticity measurement using PLL & RF modulation● Tune and Coupling feedback
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
● Schottky system
LHC BCT SystemsLHC BCT Systems● BCTDC (DCCT)
● Main Beam 2 acquisition system commissioned● Automatic range selection was blocked in highest sensitivity setting● Beam 2 circulating current measured using fixed display● Beam 2 circulating current measured using fixed display● SAFE BEAM flag & DIP transmission to experiments tested but not yet activated
● Beam 1 system still to be commissioned with beam
Beam 2DCCT sees firstcirculating beam
● BCTFR (Fast BCT)
g
● Beam 1 & Beam 2 high sensitivitychannels have seen beam
● Calibration looks OK● Still to do● Still to do
● Full timing in of system for bunch tobunch measurements
● Full commissioning of dump line systems● Commissioning of the beam
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
● Commissioning of the beampresence flags
● Adaptive lifetime algorithm● dI/dt link to MPS
LHC Wire Scanner SystemLHC Wire Scanner System● Beam 2 System Commissioned
● Low intensity single bunch gives expected noisy signals● Beam size seems to be too large● Beam size seems to be too large
● Calibration verified & looks to be OK
VerticalIn / Out
Horizontal Scan onIn / Out
Scan on Beam 2
Scan on Beam 2
S● Still to do● Commissioning of Beam 1 system● Accurate timing in of acquisition systems
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
g q y● Bunch by bunch acquisition● Commissioning of wire protection system software
The The UndulatorUndulator StoryStory● Undulators required to give enough synchrotron light below 2TeV
● Used for synchrotron light monitor & abort gap monitor● Above 2TeV the D3 produces enough light● Above 2TeV the D3 produces enough light
● Undulators should be ramped down to minimise effect of light from 2 sources
● Undulator for beam 1 (4R) commissioned in 2008● Undulator for beam 2 (4L) commissioning started in 2008
● Resistor in ll to coil found to be defective after transport to tunnel● Acts as energy extractor & distributes the produced heat in case of quench● Also equipped with standard external energy extraction system
● Is sufficient to protect the magnet without internal resistor (tested in lab)● This NC proved a problem for PC & QPS system for ramp-up / ramp down
● Can probably only be ramped up or down very very slowly – i e run in DC● Can probably only be ramped up or down very very slowly – i.e run in DC● Should be possible to add external resistor to allow ramping with existing undulator
● This is a known Non-Conformity● Can this NC degrade to cause e.g. short & so disable undulator?g g● Should we not change it while we have the chance?
● What back-ups do we have?● None for the abort gap monitor below 2TeV● None for the abort gap monitor below 2TeV● BGI could replace synchrotron light BUT
● Requires gas injection (system currently being installed by TE/VSC)LHC Performance Workshop LHC Performance Workshop -- February 2009February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
SummarySummary● A Good Start for all BI Systems
● Thanks to years of planning, testing & HW commissioning within the BI Group, with the help of many other Groups & external collaboratorsGroup, with the help of many other Groups & external collaborators
● Next Steps - Still a lot to do!● Main Shutdown Work● Main Shutdown Work
● BPM & BLM consolidation with considerable dismounting & remounting● Improvements to the synchrotron light monitor optical layout● Installation of US LARP luminosity monitors (fast ionisation chambers)● Installation of US-LARP luminosity monitors (fast ionisation chambers)
● Commissioning in 2009● Full commissioning of the already tested systems
S t ti t & fi ti i● Systematic measurements & fine timing◦◦ Fast Timing System already used for many systems and has worked very wellFast Timing System already used for many systems and has worked very well
● Commissioning of● BSRT synchrotron light monitor (requires undulator)● BSRT – synchrotron light monitor (requires undulator)● BSRA – abort gap monitor (requires undulator)● BGI – as back-up for BSRT (requires gas injection)● PLL Tune measurement & Q’ with RF modulation
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation
● PLL Tune measurement & Q with RF modulation● Orbit, tune, coupling and chromaticity feedback systems● Schottky & finally Luminosity monitors!
Analysis of BPM DataAnalysis of BPM Data● Orbit transients
● Primary sources found to be in IR2 and IR8Likely candidate● Likely candidate
● Residual MSI b1 imperfections (0.006 Tm)● Originally believed to be "easily correctable“ via orbit correction
● True if static but MSI is pulsed causing drifts of ~200 μm/s● True if static but MSI is pulsed causing drifts of 200 μm/s
● Solution● BT proposal to operate in DC mode for injection
● When do we ramp MSI up & down? (residual corrected by feedback)● When do we ramp MSI up & down? (residual corrected by feedback)
LHC LHC Performance Workshop Performance Workshop -- February 2009 February 2009 LHC Beam InstrumentationLHC Beam Instrumentation