Managing Projects Chapter 10

Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Embed Size (px)

Citation preview

Page 1: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Managing Projects

Chapter 10

Page 2: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

What is a Project?

A project has a unique purpose A project is temporary A project requires resources A project should have a primary sponsor or

customer A project involves uncertainty

Page 3: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

What is Project Management?

The application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements

Page 4: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Benefits of Project Management

Better coordination among functional areas Ensure that tasks are completed even when there

is personnel turnover Minimize the need for continuous reporting Identification of realistic time limits Early identification of problems Improved estimating capability Easier to monitor success

Page 5: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Measures of Project Success

Completed on-time Completed within budget Delivery of required specifications Acceptance by customer Minimum number of scope changes (change

orders)

Page 6: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

What do Project Manager do?

Manage the people and resources necessary to meet scope, time, cost, and quality goals Reinforce excitement in the project Manage conflict Empower team members Encourage risk taking and creativity

Communicate the progress of the team with managers and customers

Page 7: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Building the Project Team

Forming Storming Norming Performing

Page 8: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Quantitative Tools

Gantt Charts Project Network Diagram

PERT uses AON (Activity on Node) methodology Many software programs (i.e., MS Project) use

boxes and arrows to display activities

Page 9: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Quantitative Analyses

Constructing PERT diagrams and analyzing the critical path

Developing cost-time trade-off slopes Incorporating uncertainty into activity times

Page 10: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Constructing PERT DiagramsBaking a Cake ExampleActivity Code Immediate

Predecessor

Duration (minutes)

Preheat oven A - 1.0

Measure ingredients B A 8.0

Mix ingredients for frosting C B 5.0

Mix ingredients for cake D B 5.0

Pour batter into cake pan E D 1.0

Bake F E 30.0

Cool cake G C, F 60.0

Frost cake H G 5.0

Page 11: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

PERT

A1 B8

C5

D5 E1 F30

G60 H5

Note:* Notation represents the activity code and the expected duration (t)* Critical Path = A-B-D-E-F-G-H = 110 minutes

Page 12: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Notation for Critical Path Analysis

Item Symbol Definition

Activity duration t The expected duration of an activity

Early start ES The earliest time an activity can begin if all previous activities are begun at their earliest times

Early finish EF The earliest time an activity can be completed if it is started at its early start time

Late start LS The latest time an activity can begin without delaying the completion of the project

Late finish LF The latest time an activity can be completed if it is started at its latest start time

Total slack TS The amount of time an activity can be delayed without delaying the completion of the project

Page 13: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

PERT

A1 B8

C5

D5 E1 F30

G60 H5

ES = 0EF = 0+1=1

ES = 1EF = 1+8=9

ES = 9EF = 9+5=14

ES = 9EF = 9+5=14

ES = 14EF = 15

ES = 15EF = 45

ES = 45 (larger of 45, 14)EF = 105

ES = 105EF = 110

Begin at 1st activity andmake ES = 0

ES = EFpredecessor (if more than 1 EFpredecessor then use the largest value)EF = ES + t

Page 14: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

PERT

A1 B8

C5

D5 E1 F30

G60 H5

LS = 0LF = 1

LS = 1LF = 9 (smaller of 40, 9)

LS = 40LF = 45

LS = 9LF = 14

LS = 14LF = 15

LS = 15LF = 45

LS = (105-60)=45LF = LSsuccessor=105

LS = (LF-t) =(110-5)=105LF = EF = 110

Begin at last activity andmake LF=EF = 110

LF = LSsuccessor (If more than 1 LF = LSsuccessor then use the smallest value)LS = LF-t

Page 15: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

PERTActivity ES EF LS LF TS

A 0 1 0 1 0

B 1 9 1 9 0

C 9 14 40 45 31

D 9 14 9 14 0

E 14 15 14 15 0

F 15 45 15 45 0

G 45 105 45 105 0

H 105 110 105 110 0

Total Slack (TS) = LS-ES or LF-EF

Activities that have zero slack are critical, meaning they cannot be delayed without delaying the project completion time

Page 16: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Gantt Chart

See either: Demonstration in MS Project Hardcopy distributed in class

Page 17: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Project Network Diagram(produced by MS Project)

See either: Demonstration in MS Project Hardcopy distributed in class

Page 18: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Tennis Tournament ExampleActivity Code Immediate Predecessor Estimated

Duration (days)

Negotiate for location A - 2

Contact seeded players B - 8

Plan promotion C A 3

Locate officials D C 2

Send RSVP invitations E C 10

Sign player contracts F B,C 4

Purchase balls and trophies G D 4

Negotiate catering H E,F 1

Prepare location I E,G 3

Tournament J H,I 2

Page 19: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Tennis Tournament ExamplePERT

Possible paths: A-C-D-G-I-J (16), A-C-F-H-J (12), A-C-E-I-J (20), A-C-E-H-J (18), B-F-H-J (15)Critical path = A-C-E-I-J (20)

Page 20: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Tennis Tournament ExamplePERT

Activity ES EF LS LF TS

A

B

C

D

E

F

G

H

I

J

Page 21: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Gantt Chart

See either: Demonstration in MS Project Figure 10.8 in textbook

Page 22: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Project Network Diagram(produced by MS Project)

See either: Demonstration in MS Project Figure 10.9 in textbook

Page 23: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Trades-OffsCost and Time

Cost and time are inversely related

As time to complete a project goes down, costs for the project go up

As time goes up, costs go down

Page 24: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Project Costs

Page 25: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Activity Crashing

An activity is considered to be “crashed” when it is completed in less time than is normal by applying additional labor or equipment

Page 26: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Determining the Impact of Activity Crashing

To determine the impact of activity crashing begin by identifying the Expedite-Cost Slope for each activity

To do this, a manager must identify “normal” and “crash” time and cost estimates

Page 27: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Tennis Tournament ExampleCost and Time Estimates

8201212J

210823I

-101011H

110934G

715834F

54020610E

6171112D

3131023C

4302268B

1015512A

Slope ($/day)CrashNormalCrashNormalCode

Expedite-Cost*Direct Costs ($)Time Estimate (Days)

8201212J

210823I

-101011H

110934G

715834F

54020610E

6171112D

3131023C

4302268B

1015512A

Slope ($/day)CrashNormalCrashNormalCode

Expedite-Cost*Direct Costs ($)Time Estimate (Days)

*Slope = Crash Cost – Regular Cost (15 – 5) = 10 = 10 Normal Duration – Crash Duration (2 – 1) 1

Page 28: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Activity Cost-Time Trade-off(Activity Code E)

Activity E: Normal Time = 10, Crash Time = 6, Normal Cost = $20, Crash Cost = $40)

Page 29: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Incorporating Uncertainty into Activity Times

When a manager is unsure of the activity duration times, he/she needs to estimate activity times using a Beta distribution

The Beta distribution allows the manager to develop a probable range of times in which the activity time will fall

Page 30: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Beta Distribution of Activity Duration

Page 31: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Beta Distribution Time Estimates

Optimistic Time (A) – activity duration if no problems occur

Most Likely Time (M) – activity duration that is most likely to occur

Pessimistic Time (B) – activity duration if extraordinary problems arise

Page 32: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Formulas

Activity time (t) = (A + 4M + B)/6 Standard deviation (σ) = (B - A)/6 Variance (σ2) = (B – A)2/36

Page 33: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Assessing ProbabilityTennis Tournament Example

Let’s say we plan to begin the tennis tournament project on October 25th and plan to have it completed within 24 days (November 18th) because the tennis stadium is booked after that.

As a manager, you have estimated the optimistic, most likely, and pessimistic times for each activity

Now you want to find the probability that you will be able to finish the project in 24 days

Page 34: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Time Estimates Tennis Tournament Example

Time Estimates

Activity A M B t σ σ2

A 1 2 3 2.00 0.33 0.11

B 5 8 11 8.00 1.00 1.00

C 2 3 4 3.00 0.33 0.11

D 1 2 3 2.00 0.33 0.11

E 6 9 18 10.00 2.00 4.00

F 2 4 6 4.00 0.67 0.44

G 1 3 11 4.00 1.67 2.78

H 1 1 1 1.00 0.00 0.00

I 2 2 8 3.00 1.00 1.00

J 2 2 2 2.00 0.00 0.00

Page 35: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Time Estimates – Critical Path Tennis Tournament Example

Time Estimates Activity A M B t σ σ2 A 1 2 3 2.00 0.33 0.11 B 5 8 11 8.00 1.00 1.00 C 2 3 4 3.00 0.33 0.11 D 1 2 3 2.00 0.33 0.11 E 6 9 18 10.00 2.00 4.00 F 2 4 6 4.00 0.67 0.44 G 1 3 11 4.00 1.67 2.78 H 1 1 1 1.00 0.00 0.00 I 2 2 8 3.00 1.00 1.00 J 2 2 2 2.00 0.00 0.00

∑t = 2.00 + 3.00 + 10.00 + 3.00 + 2.00 = 20 days∑σ2 = 0.11 + 0.11 + 4.00 + 1.00 + 0.00 = 5.22 days∑σ = 0.33 + 0.33 + 2.00 + 1.00 + 0.00 = 3.66

Page 36: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have

Building Time DistributionTennis Tournament Example

Z = (X – μ)/σ

Z = (24 – 20)/√5.22

Z = 1.75

Z Table (p. 579 of textbook) shows that a Z value of 1.75 refers to a probability of (0.5000 – 0.4599)= 0.0401 or .04

Therefore, there is a 4% probability that the project would not be completed in 24 days