Upload
lekhuong
View
219
Download
2
Embed Size (px)
Citation preview
Wilburton Trestle – East Rail Corridor Bridge No. SA-9 Preliminary Design Report (DRAFT)
Department of Natural Resources and Parks Parks and Recreation Division Capital Planning and Land Management Section King Street Center 201 South Jackson St., Suite 700 Seattle, WA 98104-3856 December 23, 2015
Table of Contents
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 1
Introduction ................................................................................................................................................... 2
Project Background .............................................................................................................................. 2
Bridge Description ........................................................................................................................................ 3
Year of Construction and Previous Repairs ..................................................................................... 3
Bridge Inspection........................................................................................................................................... 4
Structural Analysis ......................................................................................................................................... 5
Load Rating Vehicles ........................................................................................................................... 5
Methods and Assumptions ................................................................................................................. 6
Results and Recommendations .................................................................................................................... 7
Trail Width and Decking Options ..................................................................................................... 8
Timber Stringers ................................................................................................................................... 9
High Level Caps ................................................................................................................................ 10
Posts and Piles ................................................................................................................................... 10
Mid- and Low- Level Caps ............................................................................................................... 12
Foundation Piles ................................................................................................................................ 12
Lateral Bracing ................................................................................................................................... 12
Steel Girders ....................................................................................................................................... 13
Repair Cost and Constructability ............................................................................................................. 13
Equipment and Access ..................................................................................................................... 13
Concrete Deck, Stringers, and High Level Cap Replacement .................................................... 13
Posts ................................................................................................................................................ 14
Mid- Level Caps ................................................................................................................................. 14
Piles ...................................................................................................................................................... 14
Lateral Bracing ................................................................................................................................... 14
Additional Member Replacement ............................................................................................................ 15
Continued Monitoring ............................................................................................................................... 15
Full Bridge Replacement ........................................................................................................................... 15
W
W i l b u r t o
Intr This rOur aand thseverbridg Proje The WCorrialongmaintmaintBellev Existi• “E
StR
• “Wan
n T r e s t l
oduction
report descriassessment anhe results of al options wh
ge, and deckin
ect Backgrou
Wilburton Tridor as part og this corridotenance vehitenance vehivue and roug
ing documenEastside Railtructures Un
Report, 1980; Wilburton Tnd cost opini
l e ( B r i d g
ibes our rehand recommea load ratinghich are baseng type.
und
restle (King Cof the King Cr and the Cocle structure.cles equippedghly parallels
nts available al Corridor Sa
nit, 2011, incl
restle – Concions prepare
I‐405
SE
g e S A - 9 )
abilitation assendations areg analysis. Weed on estimat
County ParkCounty Regioounty seeks to. The trestle d with rail traI-405 from s
at the time oafety Inspectiluding the Hi
ceptual Estimd by Parame
F
E 8th St.
P r e l i m i
sessment ande based on dae provide repted lifespan o
s Bridge No.onal Trail Syso evaluate it is currently cack wheels. Tsouth of SE
of our assessmion” report pistoric Ameri
mates of Probetrix.
igure 1: Vicinit
i n a r y D e
d recommendata we acquirpair recommof the repairs
. SA-9) is locstem. The trefor suitability
closed to pedThe trestle is9th Street to
ment includeprepared by tican Enginee
bable Cost (R
ty map
s i g n R e p
dations for thred during ouendations ans, types of ve
cated along thestle is a signty to be used destrians but located withnorth of SE
ed: the King Couering Record
Revised)” tec
Wilburton T
p o r t
he Wilburtonur bridge inspnd cost estimehicles utilizin
he Eastside Rnificant struct
as pedestrianis used by C
hin the City o8th Street.
unty Bridges d (HAER) Inv
chnical mem
Trestle
2
n Trestle. pection
mates for ng the
Rail ture n and
County of
and ventory
orandum
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 3
Bridge Description The trestle consists of 60 timber trestle spans and one steel girder span with a total length of approximately 975 feet. The timber trestle spans are supported on driven timber pilings. The steel girder span is supported on tall concrete piers. The trestle crosses over SE 9th Street, Richards Creek, and SE 8th Street. The south end of the bridge has a slight horizontal curve through about Bent 9 with a straight alignment beyond. The bridge deck is roughly 100 feet above ground at its maximum height. Year of Construction and Previous Repairs Based on the HAER report referenced above, The bridge was originally constructed in 1904 and completely rebuilt in 1913, 1924, 1933, and most recently in 1944. The concrete piers and steel girders were installed in 1972. All timber is assumed to be fir based on information in the HAER report. Numerous piles have been repaired with what appears to be a patching compound. A timber cover piece is placed over the patch and secured with metal banding. The age of these repairs is not known. We are referring to these types of repairs below as banded patch repairs. It also appears numerous members have received a fumigant or other internal treatment. We observed plugged access ports for the treatment and metal ID markers indicated Osmose treatment. Bents 1 – 11: These bents consist of six driven timber piles that are full height extending up to the deck level. The piles have lateral and longitudinal timber bracing in the horizontal and diagonal directions along their height, creating a frame with several levels. The pile diameter increases from the ground level up. Sizes averaged 12” at the bottom and roughly 22” at the top. All timber is creosote treated. Bents 12 and 13: These two bents are unique and consist of seven timber piles, continuous up to the deck level, that are slanted in the longitudinal direction in order to make room for SE 9th Street at the base while maintaining desirable span lengths for the stringers at the top. Timber framework spans between these two bents to provide stability for the slanted piles. Unlike the longitudinal bracing members in other spans, these are considered as primary load members. Lateral bracing between the piles is also present. All timber is creosote treated. Bents 14 – 35: These bents are similar to Bents 1 – 11. At the time of our inspection, the piles at Bents 20-31 were submerged in approximately 12 inches of water. Bents 35 – 46: These bents consist of six driven timber piles that extend several feet above ground. On top of the piles are six square timber posts with caps and framing above. The square piles are discontinuous between levels with a timber cap beam between levels. The posts are braced to one another with
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 4
lateral and longitudinal bracing members. The drive piles are creosote treated, however, the square posts and framing likely were treated with Wolman salts based on the HAER report. Wolman salts are a wood preservative treatment used in the early and middle part of last century but do not appear prevalent in newer construction. Bent 47: The foundation for this bent consists of driven steel H-piles with steel framing supporting six square timber posts with caps and framing above. Bents 48 and 51: These are short timber pony bents with five square posts that sit on top of the tall concrete piers and support the end of the timber stringer span just prior to and after the steel girder span. Bents 49 and 50: These bents are the tall concrete piers that support the steel girder span. Bent 52, 53, and 54: These bents have steel piles and framework at the base supporting 5 square posts with caps and framing above. The timber framing on top of the steel assembly is not creosote treated and likely treated with Wolman salts. Bents 55 – 60: These bents have five driven piles that support five square posts with caps and framing above. The timber framing on top of the steel assembly is not creosote treated and likely treated with Wolman salts. Bents 61 - 64: Bents 61 - 64 are circular continuous piles with the top pile cap extending beyond the superstructure. These bents have old, relic piles from previous portions of the bridge. Many of them show severe defects but are not considered to be a load carrying portion of the structure. Superstructure The existing superstructure consists of steel rails and 8”x8”x10’-0” long timber cross ties supported on timber stringers or steel girders. The timber stringers are 9x17 solid sawn lumber. Twenty one of the 60 spans have 8 stringers total while the rest have 6. The steel girders are plate girders with both riveted and bolted connections. The girders are 8 feet deep and spaced 8 feet apart.
Bridge Inspection We conducted a bridge inspection for the purpose of obtaining and confirming sufficient information to perform a structural assessment of the bridge in its current condition and for future trail amenities. The inspection report was prepared as a stand-alone document and is not included with this report.
W
W i l b u r t o
Stru We pto cheapplieanalyCounbridg Usingfor eavehic The R
Load The v
n T r e s t l
uctural An
erformed a leck whether ed. The load sis of the stru
nty-specific mges and anoth
g these live loach member le used. RF’s
RF for each m
Rating Vehivehicle config
l e ( B r i d g
nalysis
oad rating anindividual brrating calculucture. Each
maintenance vher for highw
oads as well aevaluated. M
s less than 1.0
member is ca
Rat
cles gurations are
g e S A - 9 )
nalysis of theridge compolations are sh
h member witvehicles as w
way bridges (s
as the membMembers with
0 indicate tha
alculated acco
tingFactor(R
e as follows:
P r e l i m i
e bridge, acconent’s had su
hown in Appth observed d
well as two AAshown below
er’s tributaryh a RF aboveat the memb
ording to the
RF)=(CapaLiveLoad
i n a r y D e
ounting for oufficient streendix B and deteriorationASHTO desi
w).
y dead load, re 1.0 are deember’s capacity
e following fo
acity–Deadd
s i g n R e p
observed defeength for the
were complen was load raign live loads
rating factorsmed sufficienis exceeded
formula:
Load)/
p o r t
ects or deterivehicle load
eted using a 2ated for two Ks – one for p
s (RF) were cnt for the spefor that vehi
5
ioration, s being 2D King pedestrian
calculated ecific icle.
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 6
Methods and Assumptions Additional methods and assumptions are as follows:
1) Timber members were load rated per allowable stress design methods (ASD) and the steel girders per the Load and Resistance Factor Rating (LRFR) method according to the following specifications:
a. AASHTO Manual for Bridge Evaluation 2nd Edition, 2011 (AASHTO MBE) b. AASHTO Standard Specifications for Highway Bridges, 17th Edition (AASHTO
SSHB) c. WSDOT Bridge Design Manual (WSDOT BDM)
2) For timber members, Inventory Level allowable stresses were used for the AASHTO design vehicles and Operating Level (33% higher allowable than Inventory) for the King County maintenance vehicles.
a. We believe the Operating Level is prudent for the maintenance vehicles because the specific weights and spacings are known and the frequency of these heavy loads will be relatively low over the lifespan of the bridge.
3) The structural analysis considered vertical loads only which included self weight of the bridge members and the weight of the vehicles being applied. The load rating did not consider seismic, wind, or lateral loads.
4) No live load impact was applied to the timber members. For the steel girders, an impact factor of 10% was added to the King County live loads and 33% for the AASHTO design vehicles.
5) The pile end conditions are pinned and a braced frame effective length factor, K, of 1.0 applies.
6) Timber deterioration was accounted for by adjusting the section properties of the section. The cross sectional area and section modulus were reduced based on the estimated dimension if internal decay.
7) Material properties were determined based on guidance provided in AASHTO MBE and WSDOT BDM and were taken as follows: Timber (AASHTO SSHB Table 13.5.1A)– Douglas Fir #1 for stringers and Douglas Fir Select Structural for all other timber (WSDOT BMD 13.2.14 – “Unless the species and grade is known, assume Douglas fir. Use select structural for members installed prior to 1955 and No. 1 after 1955. The allowable stresses for beams and stringers shall be as listed in the AASHTO Specifications.”)
a. Allowable bending stress in timber stringers, Fb = 1,350 psi b. Allowable bending stress in timber posts and caps, Fb = 1,200 psi c. Allowable shear stress in all members, Fv = 85 psi d. Allowable compression parallel to grain in timber posts, Fc = 1,000 psi e. Allowable compression perpendicular to grain in timber posts and caps, Fpc = 625
psi f. Wet Service Factors, CM = 1.0 for shear and bending, 0.91 for compression, 0.67 for
bearing
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 7
g. Load Duration Factors, CD = 1.15 all loadings except compression perpendicular to grain
h. Shear Stress Factor, CH = 1.0 for timber stringers (conservative assumption to account for uncertainty in aging wood structure and difficult inspection access)
i. Allowable stress values are to be modified by additional modification factors such as size factor and beam stability factor, see load rating
Steel (AASHTO MBE Table 6A.6.2.1)– Douglas Fir #1 for stringers and Douglas Fir Select Structural for all other timber (WSDOT BMD 13.2.14 – “Unless the species and grade is known, assume Douglas fir. Use select structural for members installed prior to 1955 and No. 1 after 1955. The allowable stresses for beams and stringers shall be as listed in the AASHTO Specifications.”)
a. Structural steel yield strength, Fy = 36 ksi (steel built after 1963, AASHTO MBE 6A.6.2.1)
b. Condition factor, c = 1.00 (Structural condition good or satisfactory, AASHTO MBE 6A.4.2.3-1)
c. System factor for flexure and axial effects, s = 0.90 (Riveted members in two-girder bridges, AASHTO MBE 6A.4.2.4-1)
.
Results and Recommendations Based upon the results of the load rating and observations made during inspection, we recommend repairing or replacing certain bridge components in order to utilize the bridge for maintenance vehicle and pedestrian access. We are recommending repair or replacement when:
Any member has a RF less than one; The member has defects or deterioration to an extent that we believe will limit its remaining
lifespan, even if the member currently has sufficient load carrying capacity. The overall level of repair for the bridge will depend on which maintenance vehicles will be allowed to use the bridge, the desired lifespan of the structure, the desired decking type and width, and the construction budget. We are presenting repair options for the following three vehicle groups, each with three different lifespans and two decking options –
Group 1 – King County truck and trailer with 75,000 lb. excavator, AASHTO HS20 design highway load;
Group 2 – King County 10-yard dumptruck; Group 3 – AASHTO H10 and 90 psf pedestrian bridge design live loads.
In addition, we have evaluated repair requirements for the following approximate lifespans –
Up to 25 years
W
W i l b u r t o
Appevehic Trail Both weariwith mefficie RailinThe rcost orailingperspassumexamdiscu
n T r e s t l
Up to 35 yUp to 50 y
endix A inclule groups wit
Width and 12 foot and
ing surface. Tminimum coent layout bo
ng railing can beor can includg is a highly v
pective on themed a railing
mples of railinssion.
Figure 2 :
Figure 3:
l e ( B r i d g
years years
udes summaryth correspon
Decking Op14 foot trail
These types oost differenceoth from a st
e a basic formde aesthetic fevisible bridgee bridge. Wecost in the m
ngs (graphics
Example of ste
Example of mo
g e S A - 9 )
y tables indicnding lifespan
ptions widths are fe
of decking sye. The timberringer loadin
m, such as galeatures such e componentdid not gene
mid-level rangtaken from o
eel railing with l
ore simplistic ra
P r e l i m i
cating which ns, decking al
feasible for thystems can ber stringers wing and deck s
lvanized steeas coated fint of the new erate railing dge for the ovother Otak p
lean rail and ove
ail. Similar to ra
i n a r y D e
repairs are nalternatives, a
his bridge, wie designed foill be evenly ssupport persp
el posts with nishes and/obridge, partidetails for th
verall construprojects) that
erlooks. Concre
ail on other King
s i g n R e p
necessary for and estimated
ith either a coor any of the spaced out topective.
chain link) inor special railiicularly from
he preliminaryuction cost. B
could be use
ete deck plank w
g Co. Regional
p o r t
these differed costs.
oncrete or asthree vehicle
o provide a m
n order to ming elements the user’s y design beca
Below are twoed for railing
wearing surface
Trail crossings
8
ent
sphalt e groups more
minimize . The
ause but o
g design
e
W
W i l b u r t o
ConcThe CdeckiWe reeffectOur pshoulas popanelmoistgirder AsphAn assurfaccan bbe plamore TimbThe sWe othe wsignifstringstring For ththem
We pfor st
n T r e s t l
crete DeckinCounty is conng could eithecommend ptive and we apreliminary dld be designessible. We prls on top of tture on the tors using conc
halt Wearingsphalt wearince beneath fo
be achieved waced between cost effectiv
ber Stringersstringers are 9bserved som
west side of thficant decay. gers. Lookinggers were rep
he new deckitogether as i
erformed thetringers with
Fig
l e ( B r i d g
ng Wearing nsidering bother consist oprecast panelsalso recognizdesign drawined to minimizropose to remthe timber strops of the strcrete inserts o
g Surface ng surface is aor pavement
with precast cn the asphalt ve and are ind
9 inches wid
me type of defhe structure (This is likely
g north, the splaced when t
ing configurais currently th
e load rating minor or no
gure 4: Existing
g e S A - 9 )
Surface th concrete df precast pans over cast-ine that they ar
ngs and cost ze the gap bemove all of thringers and sringers and gon the under
also feasible placement a
concrete or trand its supp
dicating this
e by 17 inchefect in appro(Stringer A) ry due to highestringers are cthe most rece
ation, we prohe case.
analysis assuo deterioratio
g stringer layou
P r e l i m i
decking and anels or a cast-n-place as were common testimates ref
etween adjacehe existing crsteel girders, girders. The prside of the p
for this strucand to providreated timber
porting surfacin our prelim
es deep and voximately 30 represented ter exposure tcalled out A ent bridge re
opose to even
uming the pron, all vehicle
t
i n a r y D e
asphalt as we-in-place dece believe the throughout tflect a precasent panels toross-ties, railseparated byplanks can beplank so they
cture. The asde the structur crossties. Wce below. We
minary design
vary between% of the strithe vast majoto sunlight ththrough F fr
econstruction
nly spread ou
oposed condes used in the
Figure
s i g n R e p
earing surfacck with stay inprecast panethe County Rst panel systeo produce as ls, and walkwy a rubber she attached to
y are not visib
sphalt would ure componeWaterproofine believe trean drawings an
n eight per spingers. The oority of the shey receive crom left to rin was done, a
ut the stringe
dition. Our ane load rating
5: Proposed str
p o r t
e options. Con place formels will be moRegional Traiem. The panesmooth of a
ways and placheet to minimo the stringerble.
require a conent of the decng membraneated timber wnd estimate.
pan and six poutside stringtringers with
compared to ight. We susparound 1945.
ers versus gro
nalysis indicaproduce a RF
ringer layout
9
oncrete mwork. ore cost il System. els a surface ce the
mize rs and
ntinuous ck. This e should will be
per span. gers on h the other pect the .
ouping
ates that F greater
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 10
than 1.0, but numerous stringers with moderate levels of decay and above has RF’s < 1 for one or more of the vehicles. The total number of replaced stringers depends on which vehicle group and decking configuration the County chooses. Our estimate assumes re-use of existing stringers where possible except for the 50-year lifespan, where we assumed full replacement of all of the stringers. If all stringers are replaced, glu-laminated stringers can be used to reduce the overall number of stringers. These options are summarized in the following table:
Vehicle Group # Vehicles Deck Width Minimum No. of
Solid Sawn Stringers Minimum No. of Glu‐Lam Stringers
1 Truck + Trailer with 75,000 Lb. Excavator,
AASHTO HS20
14 7 5
12 6 4
2 Loaded 10‐yard dumptruck
14 6 4
12 5 4
3 AASHTO H10,
AASHTO Pedestrian Load
14 5 4
12 5 4
High Level Caps The high level caps typically consist of two 8-inch wide by 15-inch deep members placed side by side. This configuration was likely used to provide increased bearing width for the piles at the top since the pile diameters here are greater than 12 inches. Numerous caps are being recommended for replacement due to observed levels of deterioration. The replaced pile cap will be similar dimensions as existing. Posts and Piles Posts are discontinuous members between cap beams while piles are the foundation components of the bridge and more numerous bents are full-height members extending to the top cap. Posts and piles were analyzed for compression parallel to grain and end bearing. The area of decay was deducted from the load bearing area when calculating capacity. The maximum unbraced length of the post was taken as the distance from the cap to the mid-height brace, approximately 10-15 feet. Looking northwest, the posts are labeled A, B, C, D,… from left to right. In our analysis, we distributed loads equally to each pile. In our experience, it is infrequent that piles load rate below 1.0 for compression, except for cases where piles have severe rot. The redundant nature of trestles and the compressive strength of timber typically result is adequate load carrying capacity.
Photo 1: Stringer group and high level cap
W
W i l b u r t o
We anconsibent, transfpiles htrestle WhencompresultBent
n T r e s t l
nalyzed indivdered as a unis compared
fer from decahave significe bents have
n analyzing inpared against ted in four pi47 6B.
l e ( B r i d g
vidual piles anit, the total d against the tayed piles to ant decay, a mRF’s > 1.0 f
ndividual pilethe pile com
iles with RF’
g e S A - 9 )
s well as trescompressivetotal dead anadjacent pilemore detailefor all vehicle
es, the tributampressive caps less than 1.
Figure 6:
P r e l i m i
stle bents as c area of the b
nd live load. Tes. It should d evaluation es.
ary dead andpacity, consid.0 – Bent 18
Trestle Bent N
i n a r y D e
conglomeratebent, less anyThis approacbe noted thais warranted
d live loads ardering decay Pile 6F, Ben
Nomenclature
s i g n R e p
e units, whery decayed arech is intendedat in the cased. When con
re applied to in that pile. T
nt 25 Pile 6A,
p o r t
re appropriatea in the piled to capture
e that two adjnsidered as a
the pile and This approac, Bent 30 6A
11
te. When s at that load jacent unit, all
ch , and
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 12
Our replacement recommendations and cost estimate are based on lifespan estimates. Mid- and Low- Level Caps Mid- and low-level caps consist of double 12x12” members at Bents 35-47 and 52-60. The posts are sufficiently aligned above one another so that minimal to no shear or bending moments are produced. Based on our inspection and analysis, we recommend replacing several caps due to observed deterioration and in some cases, crushing beneath a portion of the post. While bearing capacity appears to be sufficient, replacement should be done to meet the desired lifespan of the bridge. Foundation Piles Foundation piles are the pile portion extending up from the ground to the lowest cap or main horizontal brace. Pile diameters at the ground level were primarily in the 12-inch range. Several bents had submerged foundation piles at the time of our inspection. We checked the piles at the water surface elevation and just below, and up to the low cap.
We observed moderate or advanced rot in several piles at Bents 10, 12, 22, 25, 28, 30, 31, 32, 33, 38, and 43. Even with this rot, our analysis indicates that the piles have sufficient capacity for all vehicle groups. Our visual observations during inspection did not reveal any existing scour around the piles at Bent 41 within Richards Creek. It is unclear whether the creek channel has migrated horizontally during the lifespan of the bridge and how long the piles have been exposed to the stream. This will be an item for future monitoring, which is discussed further below.
Lateral Bracing Lateral bracing members are considered secondary structural members but are critical to provide bracing for the posts and load distribution from lateral loads. These members were typically 2.75” x 9” for the lateral bracing members and 4 x 12 or 6 x 12 for the longitudinal bracing members. Our load rating assumes that all braces are connected and capable of providing lateral restraint to the posts. We sounded each bracing member to check for internal decay where accessible and visually inspected each member. We paid particular attention to the end condition of the brace to check for end grain rot or end splitting. We observed numerous members will end grain rot or split ends and recommend replacing the entire length of brace with this condition. Braces with split ends were prevalent especially at Bents 35-47 and 52-60. These timbers were originally treated with Wolman salts as opposed to creosote like the other timbers.
Photo 2: Foundation piles (partially submerged)
W
W i l b u r t o
Steel The slifespand bcleanithe pamost contaprobapaint
RepConsequipseen fthis wand eor neRehabtrestleappro EquipIdeallanticiantici
can gcost. Conc
n T r e s t l
Girders steel girders apan by prevenbeginning to ing/preparataint surface heconomical.
ainment measably very simwould remai
pair Cost truction cost
pment than bfor most brid
work. Membeeffort to accear the deck lbilitation proe rehabilitatiooaches from
pment and Aly the contracipate this willipate that a tr
gain access aloOur cost est
crete Deck,
Figure 7: Sm
l e ( B r i d g
are structuralnting corrosioshow areas otion, paintinghas failed and Because of sures over th
milar and the sin as part of
and Consts to replace
by material codge rehabilitaers located atss the area anevel. We are
oject and receon over the Sthat project a
Access ctor has accel be feasible druck-mounte
ongside of thtimates are ba
Stringers, an
mall crane for wo
g e S A - 9 )
lly sufficient on from takiof paint failurg, and testingd specifically
f the scale of he roadway, tsavings of pathe paint sys
structabiland repair m
osts. Labor anation work dt mid-height nd to install te currently wently went toSammamish and applied t
ess along the due to the w
ed crane or a
he bridge witased on acce
nd High Leve
ork access from
P r e l i m i
but we are reng place. Thre. Repaintin
g/disposal of y about 15% partial remov
the activities artial removastem.
lity members will
nd equipmenue to the difor lower on temporary shorking with K
o bid on a traRiver. We hathem to Wilb
side of the bwetland enviro
carry deck con thof theplatfoprogrcranewith a Othebe maworkcap, pa slouconfir
th equipmentss primarily f
el Cap Repla
m deck
i n a r y D e
ecommendinhe existing pang requires fuf containmenis in distress val to full remcosts partial
al is not a sign
likely be inflnt costs will bfficult access the trestle w
horing and bKing Countyail project witave taken uniburton Trestl
bridge to set onment and crane with a che deck to reme materials. Torm on top oress from one is always seappropriately
er equipment an buckets th
ker access as wpost, and pileugh and sensrmed during t. This will hafrom the dec
acement
s i g n R e p
ng repaintingaint system isull containment waste. App
leading to fumoval, lead premoval andnificant bene
luenced morebe higher thaand time-con
will require cobracing than my on the Tokth City of Re
nit costs and cle.
up a crane, himpact to thcapacity of 3-move, set, orThe crane canof the stringene end of the tting up on ay spaced strin
t that will be hat can be rawell as adjuse repair. Whisitive natural g final design ave an impacck.
p o r t
g to extend ths about 42 yeent, proximately 2ull removal apaint, and d full removaefit. Addition
e by labor anan what woulnsuming natu
onsiderably mmembers loc
kul Creek Treedmond invoconstruction
however, we e slough. We-4 tons will br deliver the mn sit on a temers. Work wilbridge in so
a refurbishedngers.
employed wiaised or lowetable shore pile the bridgearea, it shouwhether the
ct on the con
13
heir ears old
25% of as the
al are nally lead
nd ld be ure of
more time cated at estle olving a
do not e be placed majority mporary ll that the
d bent
ill likely ered for posts for e crosses uld be contract
nstruction
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 14
This work will be fairly straightforward due to ease of access from the deck. If concrete planks are proposed, the weight of the plank versus capacity of the crane will need to be verified. This work will involve removing and replacing concrete planks, or timbers and asphalt, rails, stringers, and high level caps as well as disassembling and reassembling lateral braces. Equipment and personnel will access this work from the bridge deck. Each stringer to be replaced is roughly 15.5 feet long and is supported by two trestle bents. The high level caps will be replaced concurrently with the stringers and it is also likely that the contractor will elect to perform all the work on one trestle at a time. If this is done, some disassembly and re-assembly time for the stringers and decking will be shared with the repairs on the lower portions of the trestle. Posts Our costs assume that deteriorated posts will be fully replaced. Installing a splice appears to be present a slight cost savings, but we believe the value of having a new post outweighs the cost savings. Work access and shoring installation represent the bulk of the cost for post repair. Disassembling and re-assembling lateral bracing will require additional time. Based on our experience, the contractor will prefer to shore off of the ground or that is not possible that may shore off of the cap level below. Shoring is necessary to release the load off of the member to be replaced. Mid- Level Caps We anticipate that access to these members will be similar to that of the posts with material, personnel, and tools being lowered from the deck level. We recommend fully replacing the caps rather than partial replacement due to significant deterioration along their length. Each post will have to be temporarily supported during cap replacement, and therefore the shoring system will be more expensive and time consuming than for posts. Friction collars will likely be employed for this temporary support where numerous posts need to be lifted off of the cap for replacement. Piles Pile repair will consist of removing only the length of exposed decayed pile above ground and splicing on a new section. We are not proposing to drive any new piles. The cap beam, along with posts above, that bears on the pile will need to be temporarily shored. This work may have to be done in wet conditions and it should be anticipated that small cofferdams will be installed around the piles to dewater to ground level. Lateral Bracing Replacing lateral braces will require disassembly of the existing brace and lowering new material from the deck. The braces will be lighter and easier to handle than the posts or mid-level caps. Lateral bracing members could be accessed from either the deck or the ground, depending on where the braces are located. We anticipate minimal temporary shoring, if any when replacing lateral braces.
W i l b u r t o n T r e s t l e ( B r i d g e S A - 9 ) P r e l i m i n a r y D e s i g n R e p o r t 15
The construction documents should include a construction sequence and approach information that clearly defines the limitations that the contractor must follow. This should include, at a minimum, maximum construction loads on the deck, sequencing requirements, and the submittal requirements for a demolition and construction plan to be prepared by the contractor’s engineer.
Additional Member Replacement During construction of the trestle repair, each member that is detached and re-installed, or exposed during detachment of adjacent members, should be inspected by a qualified inspector to check for decay or deterioration not previously found. Given the age of the bridge and number of bridge components, it is possible that members in addition to those specified in the contract quantities, will need to be replaced. The contractor can be compensated for this work in a number of ways – per unit price if the quantity does not exceed 25% of original contract quantity, by negotiated unit price, by force account, or by having the contractor purchase additional materials at the beginning of the work. Larger treated timber material typically has a long lead time. We recommend including in the contract extra material for the contractor to furnish and have on hand. Having this on hand will avoid delays in construction if additional material needs to be ordered. The contract should have language that defines how the contractor will be paid if this material is then installed due to unforeseen condition.
Continued Monitoring Due to the nature of timber structures exposed to the environment, decay will continue to occur regardless of the level of rehabilitation done. Existing members without observed rot, or with minor levels of rot, could have a remaining service life in the 25-year range but beyond that it is less predictable. Inspection of both newly installed members and existing members should continue to occur at regular intervals established by King County.
Full Bridge Replacement Full replacement of the bridge was not part of the scope of work nor was it discussed with the King County. Wilburton Trestle is a historic structure and preservation is the preferred option. If the County desires, a comparison of the lifespan of a new bridge, which is on the order of 75 years, and its associated cost could be done against the lifespan of the selected repair alternative and its associated cost. Appendix A contains an alternatives matrix, the estimated cost breakdown, and the repair summaries. Concept-level typical deck sections and trestle bent elevations with repairs of various substructure components.
Appendix A – Cost Estimates and Proposed Details
Alternatives Matrix Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐912/23/2015 King County Department of Natural Resources and Parks
The following are the alternativs we considered:
Vehicle Groups
Group 1Truck + Trailer with 75,000 Lb.
Excavator, AASHTO HS20
Group 2 Loaded 10‐yard dumptruck
Group 3AASHTO H10, AASHTO Pedestrian
Load
Lifespan Options
Up to 25 years
Up to 35 years
Up to 50 years
Deck Type Options
Concrete deck
Asphalt wearing surface
Deck Width Options
12 feet
14 feet
STRUCTURE COST ITEMS ‐ ALL VEHICLES
Vehicle Group Vehicle Use Estimated Life SpanEstimated Construction Cost ‐
14' Concrete Deck
Estimated Construction Cost ‐
12' Concrete Deck
Estimated Construction Cost ‐
14' Asphalt Deck
Estimated Construction Cost ‐
12' Asphalt Deck
Up to 25 years 4,874,925$ 4,481,950$ 4,310,488$ 3,998,225$
1Truck + Trailer with 75,000 Lb.
Excavator, AASHTO HS20Up to 35 years 6,661,875$ 6,268,900$ 6,097,438$ 5,785,175$
Up to 50 years 8,085,963$ 7,692,988$ 7,521,525$ 7,209,263$
Up to 25 years 4,724,638$ 4,290,138$ 4,160,200$ 3,806,413$
2 Loaded 10‐yard dumptruck Up to 35 years 6,470,063$ 6,077,088$ 5,905,625$ 5,593,363$
Up to 50 years 7,894,150$ 7,692,988$ 7,329,713$ 7,209,263$
Up to 25 years 4,702,225$ 4,290,138$ 4,137,788$ 3,806,413$
3AASHTO H10, AASHTO Pedestrian
LoadUp to 35 years 6,278,250$ 6,077,088$ 5,713,813$ 5,593,363$
Up to 50 years 7,894,150$ 7,692,988$ 7,329,713$ 7,209,263$
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Repair Cost Estimate Tabulation Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
STRUCTURE COST ITEMS ‐ ALL VEHICLES
Item Unit Quantity Unit Cost Total Quantity Unit Cost Total Quantity Unit Cost Total
TESC LS 1 45,000$ 45,000$ 1 55,000$ 55,000$ 1 65,000$ 65,000$
SPCC LS 1 5,000$ 5,000$ 1 5,000$ 5,000$ 1 5,000$ 5,000$
Construction Survey LS 1 8,000$ 8,000$ 1 10,000$ 10,000$ 1 12,000$ 12,000$
Restoration LS 1 6,000$ 6,000$ 1 8,000$ 8,000$ 1 10,000$ 10,000$
Bridge Railing LF 1950 165$ 321,800$ 1950 165$ 321,800$ 1950 165$ 321,800$
High Level Cap Replacement EA 16 5,000$ 80,000$ 33 5,000$ 165,000$ 40 5,000$ 200,000$
Mid‐Level Cap Replacement EA 10 20,000$ 200,000$ 12 20,000$ 240,000$ 25 20,000$ 500,000$
Post Replacement EA 10 14,000$ 140,000$ 20 12,500$ 250,000$ 30 11,000$ 330,000$
Pile Splice EA 44 16,000$ 704,000$ 74 14,500$ 1,071,300$ 116 13,000$ 1,507,000$
Lateral Bracing LF 2179 85$ 185,300$ 4340 80$ 347,200$ 5132 75$ 384,900$
Longitudinal Bracing LF 1370 95$ 130,200$ 2536 90$ 228,300$ 3010 85$ 255,900$
Steel Girder Painting LS 1 250,000$ 250,000$ 1 250,000$ 250,000$ 1 250,000$ 250,000$
Extra Material On Hand and Installation (10%) LS 1 143,950$ 144,000$ 1 230,180$ 230,200$ 1 317,780$ 317,800$
SUBTOTAL 2,219,300$ 3,181,800$ 4,159,400$
DECKING COSTS ‐ ALL VEHICLES
Item Unit Quantity Unit Cost Total Quantity Unit Cost Total Quantity Unit Cost Total
Concrete Deck (12' Wide Trail) SF 11700 75$ 877,500$ 11700 75$ 877,500$ 11700 75$ 877,500$
Asphalt Deck (12' Wide Trail) SF 11700 45$ 525,700$ 11700 45$ 525,700$ 11700 45$ 525,700$
Concrete Deck (14' Wide Trail) SF 13650 75$ 1,023,800$ 13650 75$ 1,023,800$ 13650 75$ 1,023,800$
Asphalt Deck (14' Wide Trail) SF 13650 45$ 613,300$ 13650 45$ 613,300$ 13650 45$ 613,300$
STRINGER COSTS ‐ GROUP 1 VEHICLES
Item Unit Quantity Unit Cost Total Quantity Unit Cost Total Quantity Unit Cost Total
Stringer Replacement (12' Wide Trail) LF 1085 150$ 162,800$ 3333 150$ 499,900$ 3720 150$ 558,000$
Stringer Replacement (14' Wide Trail) LF 2015 150$ 302,300$ 4263 150$ 639,400$ 4650 150$ 697,500$
STRINGER COSTS ‐ GROUP 2 VEHICLES
Item Unit Quantity Unit Cost Total Quantity Unit Cost Total Quantity Unit Cost Total
Stringer Replacement (12' Wide Trail) LF 155 150$ 23,300$ 2403 150$ 360,400$ 3720 150$ 558,000$
Stringer Replacement (14' Wide Trail) LF 1287 150$ 193,000$ 3333 150$ 499,900$ 3,720.00 150$ 558,000$
STRINGER COSTS ‐ GROUP 3 VEHICLES
Item Unit Quantity Unit Cost Total Quantity Unit Cost Total Quantity Unit Cost Total
Stringer Replacement (12 foot trail) LF 155 150$ 23,300$ 2403 150$ 360,400$ 3720 150$ 558,000$
Stringer Replacement (14 foot trail) LF 1178 150$ 176,700$ 2403 150$ 360,400$ 3,720.00 150$ 558,000$
Up to 50 years
Up to 25 years
Up to 25 years Up to 35 years Up to 50 years
Up to 25 years Up to 35 years Up to 50 years
Up to 35 years Up to 50 years
Up to 25 years Up to 35 years Up to 50 years
Up to 25 years Up to 35 years
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Repair Cost Estimate Tabulation Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
TOTAL CONSTRUCTION COST PER VEHICLE GROUP AND DECKING OPTION
Addition Project Costs Include:
Mobilization 10%Contingency 25%
Lifespan14' Wide Trail ‐
Concrete
12' Wide Trail ‐
Concrete
14' Wide Trail ‐
Asphalt
12' Wide Trail ‐
Asphalt
Up to 25 years 4,874,925$ 4,481,950$ 4,310,488$ 3,998,225$
Up to 35 years 6,661,875$ 6,268,900$ 6,097,438$ 5,785,175$
Up to 50 years 8,085,963$ 7,692,988$ 7,521,525$ 7,209,263$
Up to 25 years 4,724,638$ 4,290,138$ 4,160,200$ 3,806,413$
Up to 35 years 6,470,063$ 6,077,088$ 5,905,625$ 5,593,363$
Up to 50 years 7,894,150$ 7,692,988$ 7,329,713$ 7,209,263$
Up to 25 years 4,702,225$ 4,290,138$ 4,137,788$ 3,806,413$
Up to 35 years 6,278,250$ 6,077,088$ 5,713,813$ 5,593,363$
Up to 50 years 7,894,150$ 7,692,988$ 7,329,713$ 7,209,263$
Construction Cost Notes:Costs are in present day dollarsCosts do not include any utility relocationsCosts do not include final engineering or construction administration
Group 1 Vehicles
Group 2 Vehicles
Group 3 Vehicles
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Stringer Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Assumptions:
Replace all stringers with observed defect
Lifespan of new stringer 50 years
Remaining lifespan of existing stringer with no observed defect 25 years
Input:
Total number of stringers 396
Total number of stringer spans 60
Number of stringers with defect observed 106
Number of stringers with severe deterioration observed 13
Number of stringers with advanced deterioration observed 7
Number of stringers with moderate or minor deterioration observed 54
Number of stringers with other form of defect observed 32
Total number of auxilary stringers 42
Number of auxilary stringers with defect 8
Required Stringer Configuration for Different Options
Vehicle Group # Vehicles Deck WidthMinimum No. of Solid
Sawn Stringers
Minimum No. of Glu‐Lam
Stringers
14 7 5
12 6 4
14 6 4
12 5 4
14 5 4
12 5 4
1
Truck + Trailer with
75,000 Lb. Excavator,
AASHTO HS20
2Loaded 10‐yard
dumptruck
3AASHTO H10, AASHTO
Pedestrian Load
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Stringer Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Removal and Replacement Quantities for Different Options
Vehicle Group # Vehicles LifespanNo. of Existing Stringers to
be Removed
No. of New Stringers to be
Installed
No. of Existing Stringers to
be Removed
No. of New Stringers to be
Installed
Up to 25 years 106 130 106 70
Up to 35 years 251 275 251 215
Up to 50 years 396 300 396 240
Up to 25 years 106 83 106 10
Up to 35 years 251 215 251 155
Up to 50 years 396 240 396 240
Up to 25 years 106 76 106 10
Up to 35 years 251 155 251 155
Up to 50 years 396 240 396 240
12 foot wide deck
Replace all stringers
Replace stringers with observed defect plus half of remaining
Replace only stringers with observed defect
Replace all stringers
Replace stringers with observed defect plus half of remaining
Replace only stringers with observed defect
Replace all stringers
3AASHTO H10, AASHTO
Pedestrian Load
14 foot wide deck
1
Truck + Trailer with
75,000 Lb. Excavator,
AASHTO HS20
Replace stringers with observed defect plus half of remaining
Replace only stringers with observed defect
2Loaded 10‐yard
dumptruck
Recommendation
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Stringer Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Vehicle Group # Vehicles Lifespan Disposal Quantity Disposal Total Cost Stringer Quantity Stringer Total Cost Disposal Quantity Disposal Total Cost Stringer Quantity Stringer Total Cost
Up to 25 years 39 10,801.44$ 2015 403,000.00$ 39 10,801.44$ 1085 217,000.00$
Up to 35 years 93 25,577.00$ 4263 852,500.00$ 93 25,577.00$ 3333 666,500.00$
Up to 50 years 147 40,352.55$ 4650 930,000.00$ 147 40,352.55$ 3720 744,000.00$
Up to 25 years 39 10,801.44$ 1287 257,300.00$ 39 10,801.44$ 155 31,000.00$
Up to 35 years 93 25,577.00$ 3333 666,500.00$ 93 25,577.00$ 2403 480,500.00$
Up to 50 years 147 40,352.55$ 3720 744,000.00$ 147 40,352.55$ 3720 744,000.00$
Up to 25 years 39 10,801.44$ 1178 235,600.00$ 39 10,801.44$ 155 31,000.00$
Up to 35 years 93 25,577.00$ 2403 480,500.00$ 93 25,577.00$ 2403 480,500.00$
Up to 50 years 147 40,352.55$ 3720 744,000.00$ 147 40,352.55$ 3720 744,000.00$
Unit Costs
DISPOSAL OF CREOSOTE TREATED TIMBERS
Unit Costs
Disposal of Creosote Treated TON 275.00$ Unit costs from Tokul Creek Trestle Bid Tab
Stringer LF 200 Unit costs from Tokul Creek Trestle Bid Tab
TIMBER STRINGERS
Unit Costs
Stringer LF 150.00$
Stringer LF 250.00$ Tokul Creek Trestle Bid Tab
Stringer LF Supplier provided delivered cost, estimate labor cost
14 foot wide deck 12 foot wide deck
1
2
3
Truck + Trailer with
75,000 Lb. Excavator,
AASHTO HS20
Loaded 10‐yard
dumptruck
AASHTO H10, AASHTO
Pedestrian Load
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Post and Pile Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Assumptions and Approach:
Replace full length of square posts
Splice piles at each cap
Replace high priority (HP) piles/posts for 25 year lifespan
Replace HP and medium priority (MP) for 35 year lifespan
Replace HP, MP, and low priority LP for 50 year lifespan
Bent Highest Pile Rot Pile # Square / Round LP MP HP
7 LR PB round 46
9 MR PB round 56
10 none PA round 62
11 MR PA round 69
11 MR PE round 69
12 MR PA round 70
14 AR PA round 77
14 PF round 77
15 AR PA round 82
17 AR PB round 85
18 SR PA round 85
18 PF round 85
19 AR PF round 86
21 AR PA round 87
21 PD round 87
22 AR PA round 87
24 AR PA round 87
24 PD round 87
25 AR PA + PB round 174
26 PD PF round 174
26 MR PA round 87
26 PB round 87
28 AR PE round 87
29 AR PB round 83
29 PD round 83
29 PE round 83
30 SR PA round 80
Length of Pile to Replace
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Post and Pile Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
PF round 80
31 MR PA round 78
32 AR PC round 78
32 PE + PF round 156
34 MR PA round 82
34 PD round 82
37 MR PA+PC Square 50
39 LR PA Square 25
41 none PA Square 25
43 AR (PB) PB round 20
45 LR PA Square 50
45 PC Square 50
46 MR Square 50
47 SR PB Square 25
47 PE Square 25
53 LR Square 50
54 MR Square 25
57 AR (PD) PA Square 25
57 PD Square 25
58 AR (PD) PD Square
LP MP HP
Round 1051 996 851
Square 225 75 125
Total 1276 1071 976
Estimated No. of Pile Splices 42 40 34
Estimated Post Replacements 10 10 10
LifespanEstimated No. of
Pile SplicesUnit Costs
Estimated Post
ReplacementsUnit Costs
Up to 25 years 44.00 16,000.00$ 10 14,000.00$
Up to 35 years 73.88 16,000.00$ 20 14,000.00$
Up to 50 years 115.92 16,000.00$ 30 14,000.00$
POST FULL REPLACEMENT
Post Replacement ‐ LP EA 14,000.00$ Unit costs from Tokul Creek Trestle Bid Tab used as a guide
Post Replacement ‐ MP EA 12,500.00$
Post Replacement ‐ HP EA 11,000.00$
Level 1 EA 15,000.00$
Level 2 EA 15,000.00$
Level 3 EA 15,000.00$
Level 4 EA 15,000.00$
PILE SPLICE
Pile Splice ‐ LP EA 16,000.00$ Use full replacement cost plus extra for splice
Pile Splice ‐ MP EA 14,500.00$
Pile Splice ‐ HP EA 13,000.00$
Splice fabrication and insta EA 3,000.00$ Level 1 EA 18,000.00$
Level 2 EA 18,000.00$
Level 3 EA 18,000.00$
Level 4 EA 18,000.00$
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Cap Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Topmost Caps Assumptions and Approach:
Replace full length of cap
Replace high priority (HP) piles/posts for 25 year lifespan
Replace HP and medium priority (MP) for 35 year lifespan
Replace HP, MP, and low priority LP for 50 year lifespan
Bent LP MP HP
1 14
2 14
3 14
4
5
6
7
8
9 14
10
11
12 14
13 14
14
15 14
16 14
17
18 14
19 14
20
21 14
22 14
23
24 14
25 14
26
27
28 14
29 14
30
31
32
33 14
34 14
Topmost cap
Length by Repair Priority
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Cap Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
35 14
36 14
37 14
38 14
39 14
40 14
41 14
42 14
43 14
44 14
45 14
46 14
47 14
52 14
53 14
54 14
55 14
56 14
57 14
58 14
59 14
60
61
62
63
64 14
LP MP HP
98 238 224
560 Ft top cap to replace
High Level Cap at Tops of Piles/Posts
Up to 50 years Up to 35 years Up to 25 years
Total Linear Feet 560 462 224
Pile Caps (EA) 40 33 16
Cost (EA) 5,000.00$ 5,000.00$ 5,000.00$
Total Cost 200,000.00$ 165,000.00$ 80,000.00$
HIGH LEVEL CAPS
Unit Cost
High Level Cap EA 5,000.00$ Unit costs from Tokul Creek Trestle Bid Tab
MID‐LEVEL CAPS
Unit Cost
Level 1 EA 20,000.00$
Level 2 EA 20,000.00$
Level 3 EA 20,000.00$
Average EA 20,000.00$
Bent
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Cap Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Internal Cap Beams (Not at top)
Length by Repair Priority
Bent LP MP HP
Cap Beam
Total
Replace
Number
Average
length of CAP
BEAM to
replace
# Cap Splice
Repair Level 1 Level 2 Level 3
1
2
3
4 16.5
5 16.5
6
7
8
9
10
11
12
13
14
15
16 50
17 50
18 50
19 50
20 50
21 50
22 50
23
24 50
25
26 50
27 50
28 50
29 50
30
31 50
32
33
34
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Cap Repair Summary and Unit Cost Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Bent
35 52 52 1 52 1 1
36 0 50 1
37 52 52 1 52 1 1
38 104 104 2 52 1 1 1
39 52 52 1 52 1 1
40 52 52 1 52 1 1
41 52 52 1 52 1 1
42 104 104 2 52 1 1 1
43 52 52 1 52 1
44 37 37 1 37 1 1
45 52 52 1 52 1 1
46 52 52 1 52 1
47 0 52 1
52 47 47 1 47 1
53 47 47 1 47 1
54 47 47 1 47 1
55 25 25 1 25 1
56 25 25 1 25 1
57 50 50 2 25 1
58 25 25 1 25 1
59 25 25 1 25 1
60 0 25
61 0 25
62 25
63 52
64
LP MP HP HP
583 89 280 11 5 14 2
952 Ft internal caps to replace # of splices to replace
Mid‐Level Caps at Walkway Levels
Up to 50 years Up to 35 years Up to 25 years
Mid‐Level Caps (EA) 25 12 10
Cost (EA) 20,000.00$ 20,000.00$ 20,000.00$
Total Cost 500,000.00$ 240,000.00$ 200,000.00$
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Bracing Replacement Summary Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Longitudinal Braces 6x12
Bent Longitudinal Repair Priority
LP MP HPLength of xbrace to replace
per bent
1 0
2 30.5 30.5
3 0
4 0
5 0
6 0
7 0
8 0
9 61 61
10 122 122
11 30.5 30.5
12 278.5 278.5
13 267 267
14 152.5 152.5
15 0
16 0
17 0
18 0
19 0
20 30.5 30.5
21 0
22 103 103
23 30.5 30.5
24 30.5 30.5
25 30.5 30.5
26 0
27 30.5 30.5
28 122 122
29 0
30 61 61
31 0
32 61 61
33 0
34 61 61
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Bracing Replacement Summary Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Bent 0
0
35 0
36 61 61
37 122 122
38 206 206
39 93.5 93.5
40 164 164
41 84 84
42 175.5 175.5
43 42 42
44 248 248
45 93.5 93.5
46 208 208
47 61 61
52 0
53 0
54 82 82
55 63 63
56 227 227
57 30.5 30.5
58 93.5 93.5
59 91.5 91.5
60 288 288
61 84 84
62 51.5 51.5
63 0
64
429 824 2819
LP MP HP 4072
6x12 Longitudinal BracesUp to 50 years Up to 35 years Up to 25 years
6x12 Longit. Brace (LF) 429 824 2819Cost (EA) 95.00$ 90.00$ 85.00$
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Bracing Replacement Summary Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Lateral Braces
Bent Xbrace Repair Priority
LP MP HP Length of xbrace to replace Number Average
1 none
2 none
3 none
4 none
5 none
6 none
7 none
8 19 19 1 19
9 none
10 none
11 none
12 none
13 none
14 none
15 none
16 68 68 2 34
17 none
18 136 136 4 34
19 none
20 none
21 none
22 none
23 136 136 4 34
24 87 87 3 29
25 none
26 none
27 none
28 136 136 4 34
29 none
30 none
31 none
32 none
33 none
34 none
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Bracing Replacement Summary Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Bent
35 261 261 9 29
36 290 290 10 29
37 120 120 6 20
38 348 348 12 29
39 200 200 10 20
40 406 406 14 29
41 377 377 13 29
42 290 290 10 29
43 340 340 10 34
44 442 442 13 34
45 374 374 11 34
46 348 348 12 29
47 100 100 5 20
52 48 48 3 16
53 16 16 1 16
54 32 32 2 16
55 95 95 5 19
56 57 57 3 19
57 48 48 3 16
58 48 48 3 16
59 32 32 2 16
60 48 48 3 16
61 0
62 80 80 4 20
63 150 150 5 30
64 0
792 2161 2179
LP MP HP 5132ecommended to be repa
3x9 Lateral Braces
Up to 50 years Up to 35 years Up to 25 years
Lateral Brace (LF) 5132 4340 2179
Cost (EA) 85.00$ 80.00$ 75.00$
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Bracing Replacement Summary Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Bent LP MP HP Cross Beam Total Replace Number
Average
length of
cross
brace to
replace
1 0
2 0
3 0
4 16.5 16.5 1 16.5
5 16.5 16.5 1 16.5
6 0
7 0
8 0
9 0
10 0
11 0
12 112 112 4 28
13 164 164 4 41
14 0
15 0
16 100 100 2 50
17 150 150 3 50
18 100 100 2 50
19 100 100 2 50
20 100 100 2 50
21 100 100 2 50
22 100 100 2 50
23 123 123 3 41
24 100 100 2 50
25 235 235 5 47
26 100 100 2 50
27 150 150 3 50
28 150 150 3 50
29 100 100 2 50
30 94 94 2 47
31 100 100 2 50
32 0 50
33 50 50 1 50
34 0 50
Cross Beams
Length by Repair Priority
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Bracing Replacement Summary Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
Bent 0
0
35 28 28 1 28
36 0 50
37 0 50
38 111 111 3 37
39 37 37 1 37
40 28 28 1 28
41 56 56 2 28
42 50 50 1 50
43 150 150 3 50
44 0 50
45 164 164 4 41
46 56 56 2 28
47 41 41 1 41
52 0 50
53 0 50
54 0 50
55 0 50
56 0 50
57 28 28 1 28
58 0 50
59 0 50
60 0 50
61 0 50
62 0 50
63 0 50
64 0
LP MP HP
474 1166 1370
3010 Ft cross brace to replace
Horizontal 6x12 Lateral Braces at Walkway Levels
Up to 50 years Up to 35 years Up to 25 years
6x12 Cross Brace (LF) 3010 2536 1370
Cost (LF) 95.00$ 90.00$ 85.00$
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Bracing Replacement Summary Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
BRACING MEMBERS
Unit Unit Cost
3x9 Treated Timber FT 80$
Furnish FT 12$
Install FT 100$
3x12 Treated Timber FT 85$
Furnish FT 14$ Unit costs from Tokul Creek Trestle Bid Tab
Install FT 100$ Unit costs from Tokul Creek Trestle Bid Tab
4x12 Treated Timber FT 90$
Furnish FT 16$ Unit costs from Tokul Creek Trestle Bid Tab
Install FT 100$ Unit costs from Tokul Creek Trestle Bid Tab
6x12 Treated Timber FT 95$
Furnish FT 19$ Unit costs from Tokul Creek Trestle Bid Tab as a guide
Install FT 100$ Unit costs from Tokul Creek Trestle Bid Tab as a guide
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Railing, Decking, Steel Girders Unit Costs Wilbutron Trestle Rehabilitation Cost Estimate
Bridge # SA‐9
12/23/2015 King County Department of Natural Resources and Parks
RAILING
Unit Quantity Unit Cost
Steel Railing LF 1950 165.00$
Unit Cost Examples
Steel Railing ‐ Basic Rail LF 115.00$ Redmond Central Connector Bid Tab (11/15)
Steel Railing ‐ Aesthetic Rail LF 200.00$ EstimateSteel Railing ‐ Average LF 165.00$
DECKING ‐ ASPHALT WEARING SURFACE
Unit Quantity Unit Cost
Asphalt Deck ‐ 14 foot wide deck SF 13650 45$
Timber Cross Ties 10"x10" SF 13650 43.00$ Asphalt Wearing Surface TON 239 110.00$
Asphalt Deck ‐ 12 foot wide deck SF 11700 45$
Timber Cross Ties 10"x10" TON 11700 43.00$ Asphalt Wearing Surface SF 205 110.00$
Unit Cost Examples
Timber Cross Ties SF 40.00$ Redmond Central Connector Bid Tab (11/15)
Asphalt Wearing Surface TON 110.00$ Redmond Central Connector Bid Tab (11/15)
DECKING ‐ PRECAST CONCRETE PANELS
Unit Quantity Unit Cost
Concrete Deck Planks ‐ 14 foot wide deck SF 13650 75.00$
Concrete Deck Planks ‐ 12 foot wide deck SF 11700 75.00$
Unit Cost Examples
Concrete Deck Planks SF 175.00$ Unit costs from Tokul Creek Trestle Bid Tab
" SF 65.00$ Redmond Central Connector Bid Tab (11/15)
PAINTING STEEL GIRDERS
Unit Cost
Painting LS 185,000$ Engr calculation and estimate
Surface Area SF 6556Cost/SF 28.22$
Painting LS 285,000$ Tokul Creek cost
Surface Area SF 4601Cost/SF 61.94$
K:\project\32400\32499A\Structures\Cost Estimate\RepairSummary&Costs.xlsx 12/23/2015
Department of Natural Resources and
Parks - Parks and Recreation Division
Capital Planning and Development
201 S. Jackson St, Suite 700
Seattle, Washington 98104
Tel (206) 296-4232 | Fax (206) 263-6217
FILE #
REVISION
CHECKED
DRAWN
DATE
PROJ #
12/11/15
NJB
DLS, PRO
32499A
WILBURTON TRESTLE
EASTSIDE RAIL CORRIDOR
KING COUNTY, WA
CONTRACT NO. E00341E14
OF X
STEEL SPAN SECTION W/14 FT WIDE TRAIL
TYPICAL DECK
SECTIONS - CONCRETE
DECK
S-1
1
STEEL SPAN SECTION W/ 12 FT WIDE TRAIL
TIMBER SPAN SECTION W/14 FT WIDE TRAIL
TIMBER SPAN SECTION W/ 12 FT WIDE TRAIL
PRECAST CONCRETE DECK
PANEL WITH 2% SLOPE
EXISTING STEEL PLATE
GIRDERS
12'-0"
12'-0"
STRINGERS EQUALLY SPACED.
NUMBER OF STRINGERS VARIES
DEPENDING ON VEHICLE LOADING
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
PRECAST CONCRETE DECK
PANEL WITH 2% SLOPE
PLACE WATERPROOFING
BARRIER. SHIM AS NECESSARY
TO ENSURE FIT UP OF PANELS
PLACE WATERPROOFING
BARRIER. SHIM AS NECESSARY
TO ENSURE FIT UP OF PANELS
PRECAST CONCRETE DECK
PANEL WITH 2% SLOPE
EXISTING STEEL PLATE
GIRDERS
14'-0"
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
PLACE WATERPROOFING
BARRIER. SHIM AS NECESSARY
TO ENSURE FIT UP OF PANELS
14'-0"
STRINGERS EQUALLY SPACED.
NUMBER OF STRINGERS VARIES
DEPENDING ON VEHICLE LOADING
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
PRECAST CONCRETE DECK
PANEL WITH 2% SLOPE
PLACE WATERPROOFING
BARRIER. SHIM AS NECESSARY
TO ENSURE FIT UP OF PANELS
Department of Natural Resources and
Parks - Parks and Recreation Division
Capital Planning and Development
201 S. Jackson St, Suite 700
Seattle, Washington 98104
Tel (206) 296-4232 | Fax (206) 263-6217
FILE #
REVISION
CHECKED
DRAWN
DATE
PROJ #
12/11/15
NJB
DLS, PRO
32499A
WILBURTON TRESTLE
EASTSIDE RAIL CORRIDOR
KING COUNTY, WA
CONTRACT NO. E00341E14
OF X
STEEL SPAN SECTION W/14 FT WIDE TRAIL
TYPICAL DECK
SECTIONS - ASPHALT
DECK
8"x8"x12'-0" TIMBER CROSS
TIES
S-2
2
STEEL SPAN SECTION W/ 12 FT WIDE TRAIL
TIMBER SPAN SECTION W/14 FT WIDE TRAIL
TIMBER SPAN SECTION W/ 12 FT WIDE TRAIL
ASPHALT CONRETE WEARING
SURFACE WITH 2% SLOPE
EXISTING STEEL PLATE
GIRDERS
12'-0"
14'-0"
8"x8"x12'-0" TIMBER CROSS
TIES
ASPHALT CONRETE WEARING
SURFACE WITH 2% SLOPE
8"x8"x12'-0" TIMBER CROSS
TIES
ASPHALT CONRETE WEARING
SURFACE WITH 2% SLOPE
ASPHALT CONRETE WEARING
SURFACE WITH 2% SLOPE
12'-0"
STRINGERS EQUALLY SPACED.
NUMBER OF STRINGERS VARIES
DEPENDING ON VEHICLE LOADING
8"x8"x12'-0" TIMBER CROSS
TIES
ASPHALT CONRETE WEARING
SURFACE WITH 2% SLOPE
ASPHALT CONRETE WEARING
SURFACE WITH 2% SLOPE
14'-0"
STRINGERS EQUALLY SPACED.
NUMBER OF STRINGERS VARIES
DEPENDING ON VEHICLE LOADING
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
REMOVE EXISTING TIMBER
TIES, STEEL RAILS, WALKWAY
AND RAILING.
EXISTING STEEL PLATE
GIRDERS
Department of Natural Resources and
Parks - Parks and Recreation Division
Capital Planning and Development
201 S. Jackson St, Suite 700
Seattle, Washington 98104
Tel (206) 296-4232 | Fax (206) 263-6217
FILE #
REVISION
CHECKED
DRAWN
DATE
PROJ #
12/11/15
NJB
DLS, PRO
32499A
WILBURTON TRESTLE
EASTSIDE RAIL CORRIDOR
KING COUNTY, WA
CONTRACT NO. E00341E14
OF X
TYPICAL TRESTLE BENT REPAIR
REPLACE EXISTING PILE WITH
NEW 12" DIA. SAWN TIMBER POST.
S-3
3
TYPICAL REPAIRS - BENTS WITH FULL HEIGHT PILES
PLACE 12X12 CAP BETWEEN
NEW POST AND EXISTING PILE,
FASTEN NEW CAP TO EXISTING
HORIZONTAL BRACE
TYPICAL EXTENTS OF
OBSERVED DEFECT IN PILE
TYPICAL REPAIRS - BENTS WITH DISCONTINUOUS POSTS
REMOVE
SUPERSTRUCTURE
AND UNLOAD BENT
FOR ALL REPAIRS
REMOVE
SUPERSTRUCTURE
AND UNLOAD BENT
FOR ALL REPAIRS
REPLACE FULL HEIGHT OF
POST. SHORE CAP BEAM
ABOVE REPLACED POST USING
TEMPORARY STEEL POST AND
HYDRAULIC JACK
REPLACE FULL OR PARTIAL
LENGTH OF CAP BEAM.
EXTENSIVE SHORING WITH
JACKING REQUIRED.
REPLACE FULL LENGTH OF
BRACING MEMBER. MINIMUM
TO NO SHORING REQUIRED
REPLACE FULL LENGTH OF
BRACING MEMBER. MINIMUM
TO NO SHORING REQUIRED
BENTS 35 - 47, 52 - 60BENTS 3 - 34
Appendix C – Load Rating Calculations