51
of the Divača-Koper railway line REPUBLIC OF SLOVENIA MINISTRY OF INFRASTRUCTURE SLOVENE INFRASTRUCTURE AGENCY second track

second track of the Divača-Koper railway line - Drugi tir · gsm-r Global System for ... 16 Second track of the Divača–Koper railway line Bases for the planning and the purpose

  • Upload
    lybao

  • View
    215

  • Download
    1

Embed Size (px)

Citation preview

of the Divača-Koper railway line

REPUBLIC OF SLOVENIAMINISTRY OF INFRASTRUCTURE

SLOVENE INFRASTRUCTURE AGENCY

second track

second track of the Divača‒Koper railway line

2 3Second track of the Divača–Koper railway line List of contents

LIST OF CONTENTS

Acronyms used .......................................................................................... 7

IntroductIon .............................................................................. 9

Bases for the plannIng and the purpose of the second track of the dIvača–koper raIlway lIne ....... 15The Divača–Koper section as part of the TEN-T network ............ 16The purpose of the second track of the Divača–Koper railway line............................................................................................... 18Cargo port of Koper .............................................................................. 19Overview of throughput in the past ........................................................ 19Planned investments of Luka Koper ..................................................... 23Forecast of throughput at the cargo port of Koper ........................... 23Reliability of the existing track ............................................................ 24Main characteristics ................................................................................... 24Main risks ...................................................................................................... 25Traffic on the Divača–Koper rail link .................................................. 26Capacity of the existing Divača–Koper line ......................................... 28Measures on the existing track ............................................................ 32Modernisation of the existing track........................................................ 32The second track between the Dekani power sub-station and Koper ..................................................................................................... 33

hIstory of the spatIal placement of the second track Between dIvača and koper ...................... 35The first round of evaluation ................................................................ 36Second round of evaluation ................................................................. 38The selected variant ............................................................................... 39

descrIptIon of the selected varIant ............................... 41The elements used in the design ......................................................... 42Activities after the adoption of National Site Plan ........................... 43General description of the route ......................................................... 45Basic geological data .............................................................................48Access roads and platforms at tunnel portals ..................................49Structures ................................................................................................. 52

Tunnels .......................................................................................................... 52Viaducts ....................................................................................................... 56Other structures ......................................................................................... 58Superstructure .........................................................................................64General .......................................................................................................... 64Ballasted track ............................................................................................. 64Ballastless track ........................................................................................... 65Electrical catenary ..................................................................................66Power sub-stations ................................................................................66Signalling and safety devices ............................................................... 67Relocation of utility lines ...................................................................... 67

estImated value of the selected varIant ........................69

effects on the envIronment ............................................... 73Geological and relief characteristics .................................................. 74Air .............................................................................................................. 75Quality of soil and plants ..................................................................... 75Features and quality of groundwater ................................................. 76Hydrographical features, chemical and ecological state of surface waters and flood safety ...................................................... 77Caves ......................................................................................................... 78Flora, fauna and habitat types .............................................................. 79Protected areas ...................................................................................... 81Valuable natural features and ecologically important areas ........ 82Cultural Heritage .................................................................................... 83Cultural landscape and visible qualities of space ............................84Agricultural land and agriculture ........................................................ 85Forests and forestry ............................................................................... 87Noise ..........................................................................................................89Vibrations ..................................................................................................89Light pollution .........................................................................................90Electromagnetic radiation ....................................................................90Waste ........................................................................................................ 91

conclusIon ................................................................................. 93

4 5Second track of the Divača–Koper railway line Introduction

6 7Second track of the Divača–Koper railway line Acronyms used

ac Alternating current

cef Connecting Europe Facility

cetra Central European Transport Model

dc Direct current

eIa Ecologically important area

ertms European Railway Traffic Management System

etcs European Train Control System

gsm-r Global System for Mobile Communications – Railway

natm New Austrian Tunnelling Method

nB Noise barrier

nsp National Site Plan

tBm Tunnel-boring machine

ten-t Trans-European Transport Networks

Acronyms used

8 9Second track of the Divača–Koper railway line Introduction

Introduction

10 11Second track of the Divača–Koper railway line Introduction 11Introduction

Slovenia is situated at the crossroads of the Alps, Dinaric Alps, the Pannonian Plain and the Adriatic Sea. Due to its geographical position, it is an important traffic hub in this part of Europe with crossings of traffic flows between North and South, and East and West. Two trans-European transport corridors pass through the country: the Baltic-Adriatic and the Mediterranean corridor.

The main transport branches in Slovenia are road

and rail transport which run on a densely branched

nearly 40,000-kilometre network of public roads and

1,200-kilometre network of railway lines, which together

with airports for international passenger and freight

transport and a port for the international transportation

of goods form an integrated and developed transport

system with more than 75 million passengers and almost

100 million tonnes of diverse cargo transported a year.

It was the estimates of future trade flows through the

port of Koper that some time ago encouraged ideas

on the new railway infrastructure that would ensure

better links to the interior of the country as well as to

the wider European area.

The existing Divača–Koper single-track line was built in

1967 as an industrial track and any possible increase in

its capacity merely by modernisation of infrastructure

is severely limited.

The first research of the possibility of the new railway

link, supported with studies, was carried out in the late

nineties. It was followed by the procedure of the spa-

tial placement of the line and the determination of the

variant for which the Government of the Republic of

Slovenia adopted the Decree on the National Site Plan

in 2005, and the Amendments to the Decree in 2014.

On the initiative of the Ministry of Infrastructure, the

spatial placement procedure was led by the Ministry

of the Environment and Spatial Planning, while pro-

fessional support and expertise were provided by the

investor, the Slovenian Infrastructure Agency, which is

a body within the Ministry of Infrastructure. In 2011,

project management and the implementation of other

professional consulting services included DRI uprav-

ljanje investicij (Družba za razvoj infrastrukture, d.o.o.)

as an internal consulting engineer.

At the time of issuing this publication (June 2015),

project designs for a building permit for the project

of the second track between Divača and Koper were

prepared and reviewed; the majority of approvals for

the project to proceed had been obtained and most of

the land required for construction had been acquired.

12 Second track of the Divača–Koper railway line

Line type: Single-track

Length: 27.1 km

Maximum speed: 160 km/h

Clearance: GC

Maximum longitudinal gradient:

17‰

Load:225 KN/axle or 80 KN/m (category D4)

Rails: 60 E1

Track superstructure: Mostly balastless

Haulage system: Electrical (3 kV DC)

Traffic management system: ERTMS (GSM-R/ETCS level 2)

Investor:

Republic of Slovenia, in accordance with the

aforementioned conclusions of the Government most

probably in the capacity of public partner and promoter

second track of the Divača–Koper railway LINE

Project designer:

SŽ – projektivno podjetje Ljubljana, d.d.

www.sz-pp.si

Consulting engineer:

DRI upravljanje investicij,

Družba za razvoj infrastrukture, d.o.o.

www.dri.si

IN CONNECTION WITH THE PROJECT REGARDING CONSTRUCTION OF THE SECOND TRACK ON THE DIVAČA–KOPER RAILWAY LINE, THE GOVERNMENT OF THE

REPUBLIC OF SLOVENIA ADOPTED THE FOLLOWING CONCLUSIONS AT THE 35TH SESSION OF CORRESPONDENCE, ON 23 FEBRUARY 2015:

The Government of the Republic of Slovenia notes

that the establishment of the TEN-T standard in the

Mediterranean and the Baltic-Adriatic rail corridor is

in accordance with the draft of the Transport Devel-

opment Strategy in the Republic of Slovenia, and that

the implementation of the new Divača–Koper railway

connection (hereinafter referred to as the second

track) is important.

1.

4.

2.

5.

3.

The last point of the conclusion cited above has

indeed been realised, and for the realisation of

other points, at the 27th regular session on 18 March

2015, the Government of the Republic of Slovenia

appointed an inter-ministerial working group to pre-

pare a set of public-private partnership forms for

the construction of the second track of the Divača–

Koper railway line.

This publication presents the key starting points for

planning, purpose, the history of spatial placement

and the technical elements of the new line. Due to the

placement of the line in a sensitive karst area, a special

section is devoted to the requirements regarding the

impacts on the environment which will need to be

strictly adhered to during the construction.

The Government of the Republic of Slovenia instructed

the Ministry of Infrastructure to apply to the first CEF

call to tender, which ended on 26 February 2015, in

the context of the so-called national envelope with the

project of upgrading the Poljčane–Slovenska Bistrica

rail link and the project of side track from the Koper

freight station, including the execution of all activities

for selecting a private partner to build a second track.

The project of the second track in the context of CEF

is applied to an open call to tender. With other projects,

Slovenia will also participate in the following CEF calls to

tender, including the latest when the unused resources

of all national envelopes are available.

The Government of the Republic of Slovenia has

instructed all stakeholders that due to the manage-

ment of all financial, technical and implementation

risks associated with this major investment project, the

investment in the second track is to be dealt with as a

complete indivisible whole in all phases or procedures.

The execution of the project cannot start prior to the

conclusion of a public-private partnership.

The Government of the Republic of Slovenia instructed

the Ministry of Infrastructure, the Ministry of Finance

and the Ministry of Economic Development and Tech-

nology to propose to the Government of the Republic

of Slovenia possible forms of public-private partner-

ship in accordance with the Public-Private Partnership

Act (Official Gazette of the Republic of Slovenia, No.

127/06) for implementing the investment of the second

track, and to do so in the shortest possible time.

The Government of the Republic of Slovenia notes that

the realisation of the construction of the second track

with public financial resources, due to other urgent

investment projects which must run in parallel on the

road and rail infrastructure, cannot be implemented in

the period of financial perspective 2014-2020 in terms

of macro-fiscal consolidations.

14 15Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

Bases for the planning and the purpose of the second track of the Divača–Koper RAILWAY line

16 17Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

MA

RIB

OR

TR

IEST

E

LJU

BLJ

AN

A

VE

NIC

E

KO

PE

R

RIJ

EK

A

GR

AZ

ZA

GR

EB

VIE

NN

A

BU

DA

PE

ST

ALG

EC

IRA

S

BO

BA

DIL

LA/

AN

TE

qU

ER

A

SEV

ILLE

CA

RTA

GIN

AM

UR

CIA

VA

LEN

CIA

MA

DR

ID

TAR

RA

GO

NA

BA

RC

ELO

NA

ZA

RA

GO

ZA

PE

RP

IGN

AN

MA

RSE

ILLE

LYO

N

TU

RIN

MIL

AN

VE

RO

NA

NO

VA

RA

TR

IEST

E

BO

LOG

NA

RA

VE

NN

AV

EN

ICE

UD

INE

KO

PE

R

LJU

BLJ

AN

AR

IJE

KA

ZA

GR

EB

KLA

GE

NFU

RT

GR

AZ

VIE

NN

A

BU

DA

PE

ST

BR

AT

ISLA

VA

BR

NO

OST

RA

VA

ZIL

INA

KA

TO

WIC

E

PO

ZN

AN

GD

AN

SK

SZC

ZE

CIN

WA

RSA

W

The Divača–Koper section as part of the TEN-T network The Divača–Koper section is an integral part of the

Trans-European Transport Network (TEN-T network).

In accordance with EU Regulation No. 1316/2013, the

territory of the Republic of Slovenia is crossed by two

corridors of the core network, an integral part of which

is also the Divača–Koper line. These are:

• the Baltic-adriatic corridor in the direction (Graz)–

Šentilj–Maribor–Ljubljana–Koper/Trieste, and

• the mediterranean corridor in the direction

(Venice)–Trieste/Koper–Ljubljana–Pragersko–

Hodoš–(Budapest).

The importance of the Divača–Koper line is most evi-

dent in international railway freight transport, which

is understandable given the role of the cargo port of

Koper in linking the hinterland Slovenian and European

economies with countries overseas.

The existing line on the section in question does not

meet the standards for the core network which were

adopted by the Council of the EU in 2012 and are

expected to be implemented by 2030. The standards

are not met in the ensured speed and the length of

trains.

Baltic-Adriatic corridor (Graz)–Šentilj–Maribor–

Ljubljana–Koper/Trieste

Mediterranean corridor(Venice)–Trieste/Koper–

Ljubljana–Pragersko–Hodoš–

(Budapest)

18 19Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

The purpose of the second track of the Divača–Koper railway line

• To provide modern and efficient railway link between

the cargo port of Koper and the rail network in the

Republic of Slovenia, and consequently also the wider

European rail network;

• To finally abolish all limitations of throughput and

transport capacity of the railway line from Koper to

the junction in Divača;

• To increase reliability of the operation of the railway

line from Koper to Divača;

• To increase the level of traffic safety;

• To shorten travel times;

• To reduce environmental impacts and risks to the

environment;

• To additionally increase the proportion of cargo trans-

ported by rail;

• To enable and to increase the use of environmentally

friendly modes of transport.

Cargo port of Koper

Overview of throughput in the past

The cargo port of Koper is almost the only generator

of cargo transport on the Koper–Divača section of the

line. The port of Koper and other important North Adri-

atic ports (Venice, Trieste, Ravenna, Rijeka) are attrac-

tive for transoceanic cargo, especially for cargo coming

from Asia via Suez. Cargo en route from Asia arrives at

these ports about a week earlier than that it would at

rival north European ports (Rotterdam, Antwerp etc.).

In 2008, the company Luka Koper, d.d., signed a con-

cession contract with the Republic of Slovenia for a

period of 35 years for the provision of port services, the

management, development and regular maintenance

of port infrastructure in the Koper cargo port.

According to the data of Luka Koper, d.d., a total of

18,965,351 tonnes of cargo was loaded/unloaded in

Koper in 2014. Of the total cargo handled, approxi-

mately 60% was transported by rail.

LOADED UNLOADED TOTAL

Million net

tonnes

20

18

16

14

12

10

8

6

4

2

0

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Throughput at the port of Koper 2002‒2014

20 Second track of the Divača–Koper railway line 21Bases for the planning and the purpose of the second track of the Divača–Koper railway line

518,900

vehicles

674,033

TEU

Cars Containers

Cars 763,621 t

General cargo 1,643,552 t

Liquid cargo 3,073,620 t

Bulk cargo 6,724,354 t

Containers 6,760,204 t

Total 18,965,351 t

Comparison by groups of goods for 2014 THROUGHPUT BY GROUPS OF GOODS 2009‒2014

8

7

6

5

4

3

2

1

0

2009 2010 2011 2012 2013 2014

Mill

ion

to

nn

es

Estimate of throughput by markets OTHER COUNTRIES 2%

SLOVENIA 29%

SLOVAKIA 8%

POLAND 1%

GERMANY 2%

AUSTRIA 32%

CZECH REPUBLIC 3%

ITALY 14%

HUNGARY 9%

CARS

GENERAL CARGO

LIqUID CARGO

CONTAINERS

BULK CARGO

22 23Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

Planned investments of Luka Koper

For the concessionaire, Luka Koper, d.d., to be able to

increase its capacity and market share, it plans to imple-

ment numerous investments of its own in the coming

years, mainly the following:

• The maximum possible extension of the first pier and

upgrading the existing coastline infrastructure;

• Increasing the number of moorings:

– basin II: arranging the south coast of the second

pier, livestock, oil tankers;

– basin III: Ro-Ro and the start of arranging the third

pier;

• Internal linking infrastructure and transport routes (in

parallel with new entrances);

• New storage capacities: tanks, warehouses;

• Expanding the port into the hinterland (the area of

disposal sites in consolidation);

• Infrastructure and a passenger terminal facility.

Forecast of throughput at the cargo port of Koper

Regarding the given space constraints in accord-

ance with the National Site Plan, it is envisaged

that with the implementation of all planned

measures, the concessionaire will be able to load/

unload approximately 40 million tonnes per year.

New tanks for petroleum

products

New Ro-Ro berthExtension and

reconstruction of the

coast Preparation of new

hinterland areas

Extension of the container

terminal on the first pier

New entrance and

truck terminalDeepening the inlet

channelConcentrating

containers into

hinterland and moving

timber

Deepening the first

basin

Livestock terminal

Passenger terminal

Long-term forecast (for 2030) of the throughput at the cargo port of Koper by groups of goods*

*Study »Evaluation of measures regarding the future Slovenian transport network, Divača–Koper Project« (PNZ svetovanje projektiranje d.o.o., November 2014).

Cars 1,081,276 t

General cargo 3,007,757 t

Liquid cargo 3,813,721 t

Bulk cargo 10,147,776 t

Containers 17,239,593 t

Total 35,290,123 t

24 25Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

KO

PE

R P

ASS

EN

GE

R S

TAT

ION

KO

PE

R F

RE

IGH

T S

TAT

ION

RIŽ

AN

A

h ~

56

m

h ~

20

0 m

h ~

30

7 m

h ~

49

6 m

h ~

49

1 m

h ~

53

8 m

h ~

43

1 m

h ~

3 m

HR

AST

OV

LJE

ČR

NO

TIČ

E

KO

ZIN

A

RO

DIK

DIV

A

STATION RECONSTRUCTION

EXISTING POWER SUB-STATIONS

INCREASE IN INST. POWER AND IMPLEMENTATION OF REMOTE CONTROLNEW POWER SUB-STATIONSMEASURES TO BE UNDERTAKEN ON THE CATENARY

KOPER FREIGHT STATION

DEKANI

RIŽANA

ČRNOTIČE PREŠNICA

HRPELJE - KOZINA

DIVAČA

LJUBLJANASEŽANA

RAKITOVECPULA

HRASTOVLJE

KOPER PASSENGER STATION

EXISTING STATIONS

Altitude graph of the existing Divača–Koper line SITUATION OF THE EXISTING TRACKmeasures that will be implemented in

the context of the modernisation, which

is expected to be completed in 2015, are

marked.

Reliability of the existing trackIn the 1960s, the track between Divača and Koper

(or between Koper and the connection to the line in

Prešnica) was built as an industrial track. An important

reason for this decision was the fact that in the former

Yugoslavia the central port was Rijeka and not Koper.

Main characteristics

The existing Divača–Koper line is the main single-track

electrified railway line. It is made up of the following

sections:

• Divača–Prešnica junction 16.5 km;

• Prešnica junction–Bivje junction 28.1 km;

• Bivje junction–Koper 3.5 km;

• Bivje junction–Koper freight station 0.9 km.

The route has a great longitudinal gradient, up to 26 ‰

between Prešnica and Bivje. Examination of route

elevation shows that the highest point Rodik is 107 m

higher than the destination in Divača. Therefore, there is

a significant altitude loss of some 107 m.

Main risks

The existing single-track line between Koper and Divača is the only rail link between

the port of Koper and the hinterland. The capacity and transportability of the line are

strongly influenced by unexpected events as well as measures that must be imple-

mented on the line (maintenance works, modernisation etc.). Summer forest fires that

can disrupt or totally put a halt to any traffic present an extremely high risk. Rock falls,

which are common due to the nature of the terrain, also present a risk.

26 27Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

Traffic on the Divača–Koper rail linkThe Divača–Koper line is characterised by an uneven

structure of freight transport by directions, as 70% of

freight transport is in the direction from Koper to Divača

and 30% in the direction from Divača to Koper. This

non-uniformity in directions is not noticed in passenger

transport. In passenger transport, a slightly higher offer

has been noticed during the summer months (holiday

trains), while in freight transport, the scope of the

transport part, expressed in the number of freight trains,

changes monthly and is usually the highest at the end

of the year.

on the divača–koper section, the number of freight trains has been increasing, with the exception of a drop in 2009, and transported net weight increased from 8.1 million tonnes in 2007 to 11 million tonnes in 2014.

the average for 2012 was 83 trains per day, of which 10 were passenger, 19 locomotive and 54 freight trains.

Million net

tonnes

DIVAČA–KOPER

Number of trains per day in 2012

Transported net weight on the Divača–Koper section

KOPER–DIVAČA

TOTAL

2007

8.1 8.6 7.1 8.8 10.2 10.4 10.4 11.0

2008 2009 2010 2013 20142011 2012

11

10

9

8

7

6

80

60

40

20

0

PASSENGER FREIGHTLOCOMOTIVE total

28 29Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

prIor to modernIsatIon

THROUGHPUT TRANSPORT

after completed modernIsatIon

modernIsed lIne wIth the second

track Between the dekanI power suB-

statIon and koper

72

trains/day

82

trains/day

85

trains/day

9.2million net tonnes

14.3million net tonnes

15.2million net tonnes

• the transport capacity of a line is information that

defines how many net tonnes of goods can be trans-

ported on a line in a specified time period. The trans-

port capacity is expressed in the unit of net tonnes

per year.

The transport capacity of the existing modernised

line is estimated at 14.3 million net tonnes per year,

assuming that the entire planned modernisation of the

existing line is implemented and taking into account

the particular configuration of freight trains - the

curtailment of locomotive trains which are driven as

push-pull trains for freight trains.

In addition to the construction of the second track

on the Divača–Koper section of the railway line, the

construction of the second track between the Dekani

power sub-station and Koper is also part of the global

project and will be carried out prior to the construction

of the second track on the Divača–Koper section.

Therefore, line capacity is also defined with regard to

on the divača–koper line after the modernisa-

tion, the following applies:

• Limited throughput capacity still remains at 85

trains per day (82 trains per day after the moder-

nisation or 85 trains per day after the construction

of the second track between the Dekani power

sub-station and Koper);

• Limited transport capacity still remains at 15.2

million tonnes (14.3 million net tonnes after the

modernisation or 15.2 million net tonnes after the

construction of the second track between the

Dekani power sub-station and Koper).

Figures for traffic load levels on the Divača–Koper

line are derived from the upgraded national trans-

port model, which consists of the basic CETRA

model and its upgraded version with the model of

maritime transport, allowing the evaluation of the

effects of individual measures on the quantity of

throughput in individual North Adriatic ports.

The capacity of the existing Divača–Koper line

and the organisation of train traffic. The throughput

capacity of a line is expressed in the number of trains

per day which can run on an individual section at a

specified time, taking into account the actual tech-

nical equipment and transport technology and the

necessary quality of service.

The throughput capacity of the Divača–Koper line

before modernisation in the case of mixed traffic and

taking into account the operation of locomotive trains

was 72 trains per day. The transport capacity of the line

before modernisation was 9.2 million net tonnes per

year.

the construction of the aforementioned parallel track.

With the construction of 1.2 km of track between

the Dekani power sub-station and Koper, the

implementation of additional measures and the

assumption that locomotive trains do not operate on

this section, the throughput capacity of the existing

modernised Divača–Koper line will be 85 trains per

day in both directions. The transport capacity of the

existing modernised Divača–Koper line with 1.2 km of

track built, one power sub-station and the optimisation

of traffic management (excluding locomotive trains or

driving with an attached push-pull train on the whole

route) and the maximum load of freight trains (1,600

gross tonnes) will be 15.2 million net tonnes per year in

both directions combined.

The capacity of a railway line is determined on the basis

of throughput capacity and transport capacity.

• throughput capacity is the ability of a line to let

through a certain number of trains in a specified time

period with the existing technical equipment of the

line, a certain series and type of traction vehicles

The throughput capacity of the existing and

modernised Divača–Koper line in the case of mixed

traffic and taking into account that locomotive trains

do not operate is 82 trains per day in both directions.

The increase in the capacity is mainly due to the

introduction of the block section on the whole line and

an increase in the power of power sub-stations, which

leads to the reduction of the train-tracking interval,

resulting in the increased capacity of the line. It is clear

from the data on the average number of trains per day

in 2012 that the throughput capacity of the existing

modernised line has already been exceeded.

Throughput and transport capacity of the Divača–Koper single-track railway line

30 31Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

Both passenger transport and the transport of goods were modelled.

The goods model was broken down into categories of goods (a total

of 56 categories), and their generation, distribution and the selection

of the means of transport were calculated. The maritime transport

model is based on the assumption that in the Northern Adriatic area,

there is one generator of maritime transport from where ships choose

the North Adriatic ports depending on the destination of goods and

the generalised cost of transport. The generalised price of transport

includes the cost depending on the distance travelled by sea, rail and

road, the cost of transport, loading and unloading, depending on the

transport time for maritime, rail and road route, the direct costs of

10 local passenger trains (5 pairs in both directions), which will operate on the existing line, and 4 regional or international passenger trains (2

pairs in both directions), which will operate on the new line between Divača and Koper, are envisaged for the needs of passenger transport. In

2040, a total of 120 to 150 trains are expected between Divača and Koper, depending on the organisation of traffic. It is important to emphasise

that after the construction of the second track, the organisation of traffic flow will change, as well as the capacity of the existing line between

Divača and Koper.

In particular, the operation of the new line changes the organisation of

traffic flow of freight trains, because they will use the new line for runs

in the Koper freight station–Divača direction, while the existing line

will be used for runs in the opposite direction, which will significantly

reduce the number of crossings on the existing line and contribute to

increasing the throughput capacity.

According to forecasts, 120 to 150 trains a day on average will run on the line from the direction of Koper. Potential connection between Trieste

and Koper could result in even greater total volume of trains and freight traffic. Thus the link between the port of Trieste and Koper would represent

an additional cross-border impact of this project.

loading and unloading at terminals, the cost of throughput depending

on time, and the loss in value of goods depending on time.

In 2040, 40 to 42 million net tonnes of cargo is expected according

to forecast, of which 60% on rail. In the concept of the train operating

model, it was assumed that the existing line will be intended for freight

trains travelling in the Divača–Koper direction, while the new line will

be intended for freight trains travelling in the opposite direction, i.e.

the Koper-Divača direction. The table below shows the results of the

redistribution of net tonnes to the existing and new line in the Divača–

Koper direction and the Koper–Divača direction.

With the investment, the throughput capacity of the existing line will

increase from 85 to 102 trains per day due to the modified organisation

of traffic flow. Taking into account the journeys of freight trains only

in the Koper–Divača direction (on the new line) and on the basis on

tracking intervals, the capacity of the new line is 120 trains per day.

The representation of the capacity of the lines between Divača and Koper in case of conditions with the investment, i.e. the operation of the new

and the existing line, and in case of conditions without the investment, i.e. the operation of only the existing modernised line with the constructed

second track between the Dekani power sub-station and Koper.

* Including the constructed second track between the Dekani power sub-station and Koper

85

trains/day

102

trains/day

222

trains/day

120

trains/day

wIthout Investment wIth Investment

modernised existing line*

modernised existing line*

new single-track line

throughput capacity

THROUGHPUT CAPACITY OF LINES BETWEEN DIVAČA AND KOPER

Distribution of the expected volume of freight transport between the existing and new line (million net tonnes)

year existing line new line total

KP–DI DI–KP Total KP–DI DI–KP Total KP–DI DI–KP Total

2020 0.000 5.611 5.611 8.891 0.000 8.891 8.891 5.611 14.502

2030 0.000 10.135 10.135 8.278 0.000 8.278 8.278 10.135 18.413

2040 0.000 10.630 10.630 12.831 0.000 12.831 12.831 10.630 23.461

32 33Bases for the planning and the purpose of the second track of the Divača–Koper railway lineSecond track of the Divača–Koper railway line

The second track between the Dekani power sub-station and Koper

The project will succeed in eliminating a bottleneck on part of the joint route of the existing and

planned line. This measure was separated from the overall project of the second track and will be

implemented separately in order to increase the capacity of the existing line until the construction of

the second track on the entire section between Divača and Koper (or the Dekani power sub-station).

The measures included in this investment are the following:

• Construction of 1.2 km-track on the section between the Koper freight station and the area of the

Dekani power sub-station,

• Measures to increase the power supply of the electrical catenary, and

• Optimisation of rail transport technology, thereby enabling the maximum possible capacity of

the existing track.

Such investment will additionally increase the transport and throughput capacities of the existing

line after the modernisation, which will be completed in 2015, but it represents only a temporary

solution. Further actions are necessary for a lasting increase in the capacity of the rail link between

Divača and Koper.

The investment in question has been applied to the tender and is expected to be co-financed by the

CEF funds - cohesion (national envelope).

On the existing line, prior to the construction of the second track between Divača and Koper, addi-

tional technological, organisational and construction measures are planned in accordance with the

professional findings and new technologies, to increase the throughput and transport capacity of

the line.

The modernisation of the existing track is divided into two

phases, and the second phase into four stages.

FIRST PHASE

In the first phase of the modernisation of the existing

Divača–Koper line, the modernisation of the signalling

and safety devices was implemented with new electronic

devices that enable remote automatic traffic management

from the traffic management centre in Postojna.

SECOND PHASE

Stage A, which was concluded in October 2014, included

measures in the context of the reconstruction of the

Hrpelje–Kozina railway station and transport power sub-

station, the reconstruction of the Koper freight station and

the construction of the new power sub-station of Dekani,

Measures on the existing trackThe most important measures intended to increase the capacity of the existing line are the following:

• The modernisation of the existing track, which is in the final stage of implementation, and

• The construction of the second track between the Dekani power sub-station and Koper (1.2 km),

which will be implemented prior to the construction of the second track between Divača and Koper.

Modernisation of the existing trackand all the work on the Divača–Koper open line (adaptation

of the traffic management centre in Postojna, rearrange-

ment of electrical installations at stations due to changes on

the return line, adaptation of signalling and safety devices).

Stages B and C which include the reconstruction of the

Divača railway station and the Divača power sub-station or

the abolition of the five level crossings of road and rail and

the construction of an underpass, are in their final stage.

In the context of stage D, which is currently in progress, it

is planned to complete the works on track devices, cate-

nary, return line, outdoor lighting and signalling and safety

devices on the part of the main port station and marshalling

group of the Koper freight station. In the context of stage D,

an underpass in Divača and two underpasses in the munici-

pality of Sežana and in Prešnica will be constructed.

34 35History of the spatial placement of the second track between Divača and KoperSecond track of the Divača–Koper railway line

History of the spatial placement of the second track between Divača and Koper

for the final spatial placement of the section of

the line, i.e. before the national site plan was

adopted in 2005, two rounds of evaluation and

assessment of variants were carried out.

36 37History of the spatial placement of the second track between Divača and KoperSecond track of the Divača–Koper railway line

The first round of evaluationActivities to increase the capacity of the Divača–Koper line

date back to 1996, when the then Ministry of Transport and

Communications commissioned eligibility study »Increas-

ing the capacity of the Divača–Koper single-track line« (the

study »Povečanje kapacitet enotirne proge Divača–Koper«;

SŽ – Projektivno podjetje Ljubljana d.d. and Austria Rail Engi-

neering (ARE), January 1999).

The study included surveys of technical, ecological, eco-

nomic and financial feasibility of two single-track lines

between Koper and Divača. The basic findings of the eligi-

bility study were that with merely technological reorgani-

sation of the existing line and interventions in the existing

infrastructure, it is not possible to handle anticipated traffic

and create reserve capacities on the rail which are necessary

for the development of the port of Koper, and that the only

permanent solution to the problem of capacities is the con-

struction of a new railway line.

As part of processing the construction of the second track of

the line, the study presented three groups of variants of the

route of the new track:

• The route of the second track completly parallel to the

existing line,

• Partly a parallel route and partly a new route,

• A completely new route of the line, which would spatially

result in two single-track lines.

Due to the high concentration of natural value, protected ecologically important areas through which

the line is planned to run, variant 4.1 proved to be unacceptable from the environmental point of view

mainly for two reasons:

• This variant passes through the first zone of water protection area, which supplies the whole coast al

region with drinking water,

• This variant passes the Karst edge twice, an area which is part of Karst Regional Park, where any

development would mean the degradation of the landscape and areas of natural beauty.

The selected variant with the working name 4.1

Variant 1: Parallel route of the second

track for Vmax

70 km/h

im = 17 ‰

Variant 2: Partly a parallel route and

partly a new route of the line

for Vmax

= 80 km/h

im = 17 ‰

Variant 3: A new route of the line for

Vmax

= 120 km/h

(first variant)

im = 17 ‰

Variant 4: A new route of the line for

Vmax

= 120 km/h

(second variant)

im = 17 ‰

Variant 4.1: A new route of the line for

Vmax

= 120 km/h

(second variant)

im = 17 ‰

Variant 5: A new route of the line for

Vmax

= 160 km/h

im = 17 ‰

Variant 6: Link to the Trieste-Ljubljana

line (new route of the line) for

Vmax

 = 250 km/h (high-speed

line)

im = 12,5 ‰

Variant 1

Variant 2

Variant 3

Variant 4

Variant 4.1

Variant 5

Variant 6

Six discussed variants for the route for the second track - with different speeds:

38 39History of the spatial placement of the second track between Divača and KoperSecond track of the Divača–Koper railway line

The selected variantthe second round of evaluation led to the selection of the variant for which the gov-ernment of the republic of slovenia later adopted the decree on the national site plan (official gazette of the republic of slovenia, no. 43/2005) and then the decree amending the decree on the national site plan (official gazette of the republic of slo-venia, no. 59/14).

Second round of evaluationDue to the unacceptability of the proposed variant

from the first round, the second round of variants dealt

only with the so-called »tunnel« variants, including

an analysis of possible connections in the direction of

Trieste.

On the basis of obtained guidelines and taking into

account points of view expressed at public presentations

and discussions of variant I/2, a modified variant was

created – variant I/3, supported by all local communities

and competent ministries.

koper

dIvača

40 41Description of the selected variantSecond track of the Divača–Koper railway line

Description of the selected variant

42 43Description of the selected variantSecond track of the Divača–Koper railway line

The elements used in the designOn the basis of the decrees adopted by the Government of

the Republic of Slovenia, which refer to the spatial place-

ment of the section in question, the project design for a

building permit was prepared using the following elements,

which represent the main characteristics of the new line:

Following the adoption of the National Site Plan in 2005, some additional

checks were implemented, in particular with regard to double tracks on the

entire Divača–Koper route. The possibility of additional connections to Tri-

este at the height of Črni Kal was studied, which would result in a junction of

two directions (from Divača to Trieste or to Koper). The possibility of imple-

menting a double-track line to the intended junction in Črni Kal and then a

single-track line towards Koper was also studied. In 2010, the Republic of Italy

withdrew from the intention to link the second track with the port of Trieste.

The entire project documentation at the level of the project design for a

building permit was made. The projects were reviewed and accordingly

amended. Some additional geological and geomechanical research was

implemented and the findings were taken into account in the already sub-

mitted project designs for a building permit.

In addition, all approvals required to acquire a building permit were

obtained (except the consent of the Slovenian Public Agency for Railway

Transport regarding interoperability). A complex Environmental Consent

was obtained, which includes the process of cross-border impacts due to

the proximity of the Republic of Italy. The report of the impacts on the

environment was also presented in Italy, comments and opinions were col-

lected and appropriate answers were prepared.

In accordance with the adopted National Site Plan and the prepared pro-

ject design for a building permit, almost all the land for obtaining a building

permit has been acquired. A small proportion of the land referred to in the

amendments to the National Site Plan, adopted in August 2014, still needs

to be acquired.

Activities after the adoption of the National Site Planline type: Single-track

length: 27.1 km

maximum longitudinal gradient: 17 ‰

maximum speed: 160 km/h

clearance: GC

load: 225 KN/axle or 80 KN/m (category D4)

rails: 60 E1

track superstructure: Mostly balastless

haulage system: Electrical (3 kV DC)

traffic management system: ERTMS (GSM-R/ETCS level 2)

BERTOKI DEKANI

ŠKOFIJE

6319

3106/2

6073/18

6316/3

5751

5782/1

5758

3104/2

6317

5791/4

3104/2

5757

3054/5

6321

2730/4

2982/3

5996/3

2981/6

3105/1

6011/1

5756

2978/3

5742/3

5746/1

3054/5

3002/1

2979/1

6010/5

2731/4

2738/3

1750/1

2971/3

2983/3

5747/3

6320 2729/1

6011/1

5996/3

6011/1

6322

3105/1

6318/1

5752/1

5998/1

2736/7

5759/1

2737/3

2980/3

3081/6

2736/6

5792/11

5994/3

3088/4

3089/3

2738/2

3088/6

5999/1

5792/9

3003/1

5996/3

2737/4

6377/1

1749/1

5753/1

3049/4

6375/13

6042/3

2732/1

5754/1

6041/3

5791/9

3049/62734/1

5786/36042/5

2736/9

5742/53095/1

5791/6

LegendaMEJA POSEGA

Izvlecni tir -PGD(parcele)

DKN

MEJA OSNOVNEGA DPN

KO

44 45Description of the selected variantSecond track of the Divača–Koper railway line

After the Divača station, the route runs the first 800 m

on the terrain or a slight embankment, and then the

following 1,350 m in a cut, the height of which increases

with chainage. At a length of 105 m before the portal

of the first tunnel, the cut widens to 40 m, so that the

front of the cut is wide enough even for the entry into

a service (security) tunnel. The service road (connected

to the Divača–Lokev road) will also lead to the widened

cut in front of the entry into the tunnel, while after the

construction of the tunnel the platform will be used

primarily for the access of maintenance staff and for the

needs of safety and rescue.

At km 2+980, the route runs into the first tunnel T1

where it is straight, with the exception of one gentle

curve. South of the Mihele village, in the upper part of

the Glinščica valley (km 9+680), the route comes to

the surface and bridges the Glinščica valley with two

bridges, and there is a gallery between them. A service

road will also run to this area (partly also over the route

of the abandoned Kozina–Trieste line). Service or safety

platforms are planned in front of both portals.

The entry into the second tunnel T2 is defined with the

portal at km 9+930. At the beginning of the tunnel, the

route runs in a curve with a radius of 1,500 m, and then

in a straight line through most of the tunnel. A passing

point is planned in the last part of the straight line, thus a

widening of the tunnel profile is also planned at this area.

A passing track will be placed to the right from the main

track, with the distance between the two axes of 4.75 m.

In the last part of the tunnel where it passes from the area

of the Karst plateau, the route of the new line runs in a

right curve. At km 15+923 the tunnel T2 ends, a service

platform is planned right after the portal. The Črni Kal

power sub-station will also be built right next to the

platform for the purpose of powering electric catenary.

Right after the platform, the route passes on the first

viaduct V1-Gabrovica, and in the long curve bypasses

the village of Gabrovica pri Črnem Kalu. On the viaduct,

the line runs below the Črni Kal motorway viaduct.

The route then continues almost entirely in tunnels T3,

T4, T5 and T6 on the south-western slope of the Osp

valley. Access service roads in this area are connected

to the connecting service road T4-T7, which runs

above the south-western slope of the Osp valley. The

route continues along the incline of Tinjan above the

Osp valley to 19+870 km and then turns south in the

penultimate tunnel T7. After the end of the tunnel, the

line runs in the dug-in and cut sections. With the viaduct

V2-Vinjan, the line crosses the valley of the Vinjanski

potok stream and approaches the state border with the

Republic of Italy.

After the viaduct V2, the line continues into the last

tunnel T8. The route runs in a long left curve under Plavje

and in the hinterland of Zgornje Škofije and Spodnje

Škofije. In the last part of the tunnel, the line continues

in a sharper right curve, which will enable a speed of

120 km/h. In the hinterland of Dekani, the line passes

to a widened pre-cut beyond the main road. Service

roads will lead to both platforms at the beginning and

end of tunnel T8. The route continues along the valley

of the Rižana River, where the gradient of 17‰ reduces.

The line continues on an embankment, approaches the

existing line and runs along it until the Bivje junction.

The envisaged speed on the part of the second track

between Dekani and the Bivje junction gradually reduces

from 120 km/h to 100 km/h and finishes at 80 km/h,

which represents the maximum allowed speed in the

deviation at the existing junction point for the Koper

passenger station.

In the final section, the line crosses a local road and a

bicycle path. The line bridges the Rižana River with a

new bridge which will be built next to the existing one.

The installation of the point connection with the existing

track is planned at the last part of the common course.

At the Bivje junction, the route of the new second track

is completed. The second track connects to the Koper

freight station.

General description of the route

46 47Description of the selected variantSecond track of the Divača–Koper railway line

700

600

500

400

300

200

100

0

CHAINAGE

RECON-STRUCTION OF DIVAČA

STATION

km 0

+8

61.

571

OPEN TRACK DIVAČA–KOPER

ČRNI KAL–KOPER SECTION

DIVAČA–ČRNI KAL SECTION

TU

NN

EL

"T1"

, L =

6,7

14 m

TU

NN

EL

T2

, L =

6,0

17 m

TU

NN

EL

T8

, L =

3,8

08

m

GLI

NŠČ

ICA

BR

IDG

E 1

, L =

70

mG

LIN

ŠČIC

A G

ALL

ER

Y, L

= 4

5 m

GLI

NŠČ

ICA

BR

IDG

E 2

, L =

10

0 m

VIA

DU

CT

V1,

L =

45

2 m

TU

NN

EL

T3,

L =

33

0 m

TU

NN

EL

T4

, L =

1,9

54

m

TU

NN

EL

T5,

L =

12

8 m

TU

NN

EL

T6

, L =

35

9 m

TU

NN

EL

T7,

L =

1,1

63

m

VIA

DU

CT

V2

, L =

64

7 m

P1

UN

DE

RP

ASS

, km

26

+8

40

RIŽ

AN

A B

RID

GE

, L =

32

.0 m

, km

27+

25

3P

2 U

ND

ER

PA

SS IN

A C

AIS

SON

, m 2

7+3

68

EN

D O

F SE

CT

ION

DIV

A–

KO

PE

R (B

IVJE

JU

NC

TIO

N)

km 2

8+

05

6.1

87

(Exi

stin

g c

hai

nag

e 2

8+

04

4.7

8)

CHAINAGE

1/0

R = 2,500 m R = 2,500 m R = 1,500 m R = 700 m R = 1,500 m

R = 1,600 m R = 1,404 m R = 2,500 m

5/0 10/0

i = 17‰

17‰10‰

10‰

PA

SSIN

G P

OIN

T Č

RN

I KA

L, k

m 1

4+

415

15/0 20/0 25/0 28/0

Relocation of the existing track

Tunnel T1, 6,714 m

Glinščica bridge 1 70 mGlinščica gallery 45 mGlinščica bridge 2 100 m

Tunnel T2, 6,017 m

Viaduct V2,Vinjan, 647 m

Tunnel T8, 3,808 m

Second track between the Dekani power sub-station and Koper, approx. 1.2 km

Viaduct V1-Gabrovica, 452 m

Tunnels:T3 330 mT4 1,954 mT5 128 mT6 358 mT7 1,163 m

route length 27.1 km

vmax

160 km/h

rmin

1,404 m (600 m)

imax

17‰

number of tunnels 8

total length of railway tunnels 20.5 km

percentage of tunnels 75%

longest tunnel 6,714 m

number of viaducts 2

total length of railway viaducts 1,099 m

percentage of viaducts 4%

clearance GC

Main elements and characteristics LONGITUDINAL PROFILE OF THE SECOND TRACK OF THE DIVAČA–KOPER LINE

Lengths of structures are indicative

koper

dIvača

48 49Description of the selected variantSecond track of the Divača–Koper railway line

arranged and will be used to access tunnel portals and

water storage tanks for maintenance needs, and in the

event of accidents on the second track of the railway

line, the roads will serve as intervention roads for rescu-

ing from tunnels. Access roads will also be used by the

local population for access to land if access was inter-

rupted with the construction of the second track. After

the construction of the second track is completed, a part

of access road T-1b1 will be arranged as a cycle path run-

ning on the Kozina–Trieste abandoned railway line.

Given the challenging configuration of the terrain

where access roads run and given the importance of

an individual road, project speeds of Vr=40 km/h or

Vr=30 km/h were taken into account. The surface of

the majority of access roads is asphalt, only individ-

ual roads are made with macadam surface, and during

the construction, these roads must also be protected

against dust (asphalt surface at least 6 cm deep).

Basic geological data On the section between Divača and Črni Kal, the

route of the second track runs on different formations

of carbonate rocks characterised by numerous

karst features (sinkholes, cracks, caverns, tunnels,

underground caves, chasms etc.). The degree of

karstification of individual areas is high, crushed zones

appear in the area of fault zones between individual

formations. Groundwater levels can vary significantly

depending on hydrological conditions as well as local

differences in porosity and permeability. A high risk of

water ingress on karst channels and cracks appears

in the area of crushed and fault zones. In the area of

crossing the Glinščica valley (between the villages

Mihele and Beka), flysch sedimentary rocks appear that

are strongly pleated and cracked due to thrusting in the

past. Sandstone strongly predominates among rocks in

this area. The difference between the permeability of

flysch and limestone is such that flysch stones represent

Access roads and platforms at tunnel portalsbarrier layers over which groundwater from limestone

flows (karst springs). Due to the concentration of water,

the probability of the occurrence of the karst formations

is the greatest in the area.

Basic rocks on the section between Črni Kal and

Dekani consist of flysch rocks, characterised by the

alternation of layers of clay stones, siltstones, marl

and sandstones. Because of the thrusting of carbonate

massif on the flysch base, flysch rocks are pleated

and tectonically cracked in the area of the hinterland

of Črni Kal. Under the Karst Edge, limestone rubble is

placed in a fan shape on the flysch base. Almost the

entire surface of flysch is covered by weathered flysch

stone. There are almost no weathered stones on the

steep slopes of erosion ravines, but they accumulate in

great quantities at the foot of the slopes and in beds of

occasional watercourses.

On the section between Dekani and the Bivje junction,

the route of the second track runs through the valley of

the Rižana River where alluviums of the Rižana appear

10 to 13 m in thickness on the flysch base. It is the

alternation of layers of clayey silt with frequent organic

remains, while sandy gravel soils appear deeper on the

flysch base. A groundwater level is located at the depth

of 1 to 3 m below the surface. Surface layers are moist

and also sodden due to poorly permeable clays.

The route of the second track descends from Divača

on the Karst plateau to the coastal area with an altitude

of a few meters above sea level. It crosses the Karst

Edge in a number of tunnels. Most tunnel portals are

located in the steep, narrow, difficult to access ravines

on sparsely populated Karst area with poor local road

infrastructure. Local roads are mainly narrow and

lacking in visibility and allow only low driving speed,

while their surfaces are mainly in poor condition. Local

roads often pass through typical karst villages, where

they run among densely placed houses and com-

mercial buildings. It is practically impossible for large,

heavy trucks and other construction machinery to pass

through such villages.

Therefore, the implementation of appropriate access

roads is a necessary condition for the start of the

construction of the new track. Such roads must be

implemented prior to the commencement of works

for the construction of tunnels and greater bridging

structures. Access roads are planned in a way that they

connect to the high-quality and adequately efficient

national road network.

During the construction, implemented access roads will

be used to access the construction sites of tunnels, via-

ducts, bridges and the route of the track. After the second

track is constructed, access roads will be adequately

51Description of the selected variantSecond track of the Divača–Koper railway line50 Nova železniška proga Divača–Koper

no. road typical

cross

section (m)

length (m)

1 N1 - left 4.50 511.00

2 T-1a 7.00 642.96

3 Connection to R1-205/1026 Divača–Lipica 8.50 140.00

4 T-1a2 4.50 1,093.55

5 Access road to water storage tank V-1 5.50 149.20

6 Connection of access road V-1 3.00 53.90

7 T-1b1 4.50 2,900.00

8 T-1b2 5.70 1,233.62

9 T-2a 5.75 1,172.03

10 Access road to water storage tank V-2 2.40 57.46

11 T-2b 8.00 293.13

12 T-3 7.20 760.41

13 T-3a 5.20 158.36

14 T-4a 7.20 407.93

15 T-4b 7.20 1,032.10

16 T-4c 7.20 501.48

17 Connecting service road T4-T7 7.25 2,032.14

18 T-5 7.20 213.05

no. road typical

cross

section (m)

length (m)

19 T-6 7.20 580.00

20 T-7 7.20 1,260.83

21 T-7a 7.20 487.00

22 T-7b 7.20 620.20

23 T-7c 7.20 290.80

24 T-7d 7.20 113.10

25 T-8a 7.20 1,704.44

26 Access road along the Škofijski potok stream 5.00 654.38

27 T-8b 7.50 301.5

28 Field path DP1 4.00 372.33

29 Field path DP2 4.00 65.00

30 Deviation of the cycle path in P1 underpass 4.00 202.41

31 Deviation of the local road in P2 underpass 7.50 164.54

32 Field path DP 3 4.00 44.50

33 Field path DP 4 4.00 428.95

total length of roads 20,642.30

Characteristics of access roads

Culverts and various supporting and retaining walls, necessary for the implementation of roads, are also planned with individual roads.

52 53Description of the selected variantSecond track of the Divača–Koper railway line

20.5 km

37.4 km

total length of tunnels:

total length of tunnels including service and exit tubes:

Structures

Tunnels

All tunnels are single-tube tunnels; tunnels T1, T2 and T8 are designed with service tubes,

which are to be used for rescue operations, while tunnels T4 and T7 have transverse exit tubes.

no. structure length (m)

1 Tunnel T1 6,714.00

2 Service tube SC-T1 6,683.11

3 Tunnel T2 6,017.34

4 Service tube SC-T2 6,028.53

6 Tunnel T3 330.00

7 Tunnel T4 1,953.61

8 Exit tunnel tube IPC-T4A 61.48

9 Exit tunnel tube IPC-T4B 144.75

10 Tunnel T5 128.00

11 Tunnel T6 358.53

12 Tunnel T7 1,162.58

13 Exit tunnel tube IPC-T7 165.00

14 Tunnel T8 3,808.00

15 Service tube SC-T8 3,818.22

total length of tunnels including service and exit tubes 37,373.15

planned tunnels with lengths of the main tunnels, service tunnels and transverse exit

(escape) tubes:

TYPICAL CROSS-SECTION OF THE MAIN TUBE TYPICAL CROSS-SECTION OF THE SERVICE TUBE

BASIC INFORMATION:

CLEARANCE WIDTH 5.00 m + 2 corridors of 0.75 m

CLEARANCE HEIGHT 6.50 m

ExCAVATION PROFILE Drained execution of 69 m2 and non-drained

execution of 71 m2

BASIC INFORMATION:

CLEARANCE WIDTH 3.60 m

CLEARANCE HEIGHT 2.50 m

ExCAVATION PROFILE Drained execution of 40 m2 and non-drained

execution of 44 m2

The axle distance between the tubes is 25.00 m.

54 55Description of the selected variantSecond track of the Divača–Koper railway line

Tunnel T1 6,714.00 m

Because of the length and the specific

terrain, the construction of service tube

SC-T1 is planned to be used for ensuring

safety, possible evacuation of passengers,

access of emergency vehicles and fire

engines. The service tube will be parallel

with the tunnel tube. The tunnel will have

separate systems for draining ground/

rock water and waste water. Waste water

will be discharged through an oil trap and

a settling basin at platform level in front

of portal T1, the direction of Koper. The

tunnel will be located mainly in limestone,

heavily karstified rocks. Special measures

are planned in order to deal with various

karst phenomena. In the areas where the

tunnel crosses the areas with possible

occasional occurrence of high ground-

water, the tunnel tube is implemented

in non-drained execution, while in other

areas, the tunnel tube is implemented

in the drained execution. In the struc-

ture by portal T1, the direction of Divača,

and SC1, the direction of Divača, and in

transverse links between the tunnel tube

and the service tube, power stations and

transformer stations are planned.

Tunnel T2 6,017.34 m

Because of the length and the specific

terrain, the construction of service tube

SC-T2 is planned to be used for ensuring

safety, possible evacuation of passengers,

access of emergency vehicles and fire

engines. The service tube will be parallel

to the tunnel tube. The tunnel will have

separate systems for draining ground/

rock water and waste water. Waste water

will be discharged through an oil trap and

a settling basin at platform level in front

of portal T2, the direction of Koper. The

tunnel will be located mainly in limestone,

heavily karstified rocks. Special measures

are planned in order to deal with various

karst phenomena. In the areas where the

tunnel crosses the areas with possible

occasional occurrence of high ground-

water, the tunnel tube is implemented in

non-drained execution, while in other

areas, the tunnel tube is implemented in

the drained execution. A passing point is

planned in the lower part of the tunnel and

thus the widening of the tunnel profile.

Directly next to portal T2, there is a ven-

tilation plant for the ventilation of tunnels

T1 and T2 and the gallery between them.

Tunnel T3 330.00 m

Due to the short length of the tunnel,

a service tube or leading tubes are not

planned. The tunnel will be located

in the flysch rocks where a large

amount of hinterland water is not

expected, therefore the drainages

will be installed for the tunnel tube

for draining captured rock water. The

tunnel will have separate systems for

draining ground/rock water and waste

water. Waste water will be discharged

through an oil trap and a settling basin

at platform level in front of portal T3,

the direction of Koper.

Tunnel T4 1,953.61 m

Because of the length and the specific

terrain, the construction of transverse

service tubes or leading tubes IPC-T4A

and IPC-T4B is planned to be used for

ensuring safety, possible evacuation

of passengers, access of emergency

vehicles and fire engines. The tunnel will

be located in the flysch rocks where a

large amount of hinterland water is not

expected, therefore the drainages will be

installed for the tunnel tube for draining

captured rock water. The tunnel will have

separate systems for draining ground/

rock water and waste water. Waste

water will be discharged through an oil

trap and a settling basin in front of portal

T4, the direction of Koper. Next to all the

portals of the tunnel tube and leading

tubes, structures of a power station with

transformer stations are planned.

Tunnel T5 128.00 m

The tunnel is characterised by a relatively

low covering and quite poor geological

and geomechanical conditions. Due to

the short length of the tunnel, a service

tube or leading tubes are not planned.

The tunnel will be located in the flysch

rocks where a large amount of hinter-

land water is not expected, therefore

the drainages will be installed for the

tunnel tube for draining captured rock

water. The tunnel will have separate sys-

tems for draining ground/rock water and

waste water. Waste water is discharged

through the sewage system of the plat-

form between tunnels T5 and T6 into the

drainage system of tunnel T6. At platform

level in front of portal T5, the direction of

Koper, an oil trap and a settling basin are

planned for waste water from the tunnel.

Tunnel T6358.53 m

The tunnel is characterised by low cov-

ering at the point of crossing the deep

transverse ravine where a cut is imple-

mented as well as filling with stabi-

lised material. Due to the short length

of the tunnel, a service tube or leading

tubes are not planned. The tunnel will

be located in the flysch rocks where a

large amount of hinterland water is not

expected, therefore the drainages will

be installed between the tunnel tube

and rocks for draining captured rock

water. The tunnel will have separate

systems for draining ground/rock water

and waste water. Waste water will be

discharged through an oil trap and a

settling basin at platform level between

tunnels T6 and T7.

Tunnel T7 1,162.58 m

Because of the length and the specific ter-

rain, the implementation of transverse ser-

vice tube or leading tube IPC-T7 is planned

to be used for ensuring safety, possible

evacuation of passengers, access of emer-

gency vehicles and fire engines. The tunnel

will be located in the flysch rocks where

a large amount of hinterland water is not

expected, therefore the drainages will be

installed between the tunnel tube and

rocks for draining captured rock water. The

tunnel will have separate systems for drain-

ing ground/rock water and waste water.

Waste water will be discharged through an

oil trap and a settling basin at platform level

in front of tunnel T7. At the T7 portal, the

direction of Divača, of the tunnel tube and

at the portal of the IPC-T7 leading tube,

two structures of a power station with

transformer stations are planned.

Tunnel T8 3,808.00 m

Because of the length and the specific ter-

rain, the construction of service tube SC-T8

is planned to be used for ensuring safety,

possible evacuation of passengers, access

of emergency vehicles and fire engines.

The service tube will be parallel with tube

T8. The tunnel is characterised by low

covering at the site of crossing the Škofijski

potok stream; therefore, the tunnel tube at

this point will be implemented according

to the technology of the Carinthia cover.

The tunnel will be located in the flysch

rocks where a large amount of hinterland

water is not expected, therefore the drain-

ages will be installed between the tunnel

tube and rocks for draining captured rock

water. The tunnel will have separate sys-

tems for draining ground/rock water and

waste water. Waste water will be dis-

charged through an oil trap and a settling

basin at platform level in front of portal T8,

the direction of Koper. In the structure by

portal T8, direction of Divača, and SC8,

direction of Divača, and in transverse links

between the tunnel tube and the service

tube, power stations and transformer sta-

tions are planned.

The water for the hydrant networks of tunnels T1, T2, T4, T7 and T8 is supplied from their own water storage tanks (V1, V2, V4, V7

and V8) with a volume of 200 m3, which are located above the tunnels. The hydrant network of tunnel T4 also supplies tunnel

T3, while the network of tunnel T7 also supplies tunnel T6. Due to its short length, a hydrant network is not planned in tunnel T5.

56 57Description of the selected variantSecond track of the Divača–Koper railway line

2423-09-000214

tel.: 02 234 14 20, fax: 02 234 14 95

Kopitarjeva ulica 5, 2000 Maribor

Jurčkova cesta 229, SI - 1000 Ljubljana

tel.: 01 300 76 00, fax.: 01 300 76 36

sž - projektivno podjetje ljubljana, d.d.

projektiranje, inženiring, svetovanje

439/09

3/1

3610/V1

Strossmayerjeva 28 , SI - 2000 Maribor

tel.: 02 234 40 61, fax.: 02 234 40 66

ponting inženirski biro d.o.o.

PGD za drugi tir železniške proge Divača - Koper, odsek Črni Kal - Koper

Viadukt GABROVICA

1 : 500 06.2010

POGLED NA VIADUKT

MERILO 1 : 500

V1 viaductV1 viaduct, or Gabrovica viaduct, is 452 m long and bridges the Osp

valley at a height of between 10 and 60 m and at an angle of approx-

imately 30 degrees crosses the existing motorway viaduct of Črni Kal.

The height difference between the two structures is 30 m at the point

of crossing. The incremental launching method for the construction

of the superstructure is planned, with a launching nose of 40 m. The

superstructure with a static length of 424 m is a pre-stressed rein-

forced concrete structure over 7 fields (52 + 5 x 64 + 52) with the

shape of a trough and provides a sufficient static height of the struc-

ture, while also providing adequate wind protection for trains (bora),

and also adequate noise protection for the surroundings. Pillars have

a polygonal box cross-section.

V2 viaductV2 viaduct, or Vinjan viaduct, is 647 m long and is designed as a

continuous pre-stressed reinforced concrete superstructure over

13 fields with a static length of 630 m (40 + 11 x 50 + 40). The

cross-section of the superstructure has the shape of a box with

top plate consoles. The pillars also a have box-shaped cross-

section, their height is up to 60 m. On the edge girder of the

superstructure, a fence is attached to protect against noise, and

on the other side, a fence to protect against the wind.

Viaducts

TYPICAL CROSS-SECTION

VIEW OF THE VIADUCT

TYPICAL CROSS SECTION OF THE SUPERSTRUCTURE »IN FIELD«

58 59Description of the selected variantSecond track of the Divača–Koper railway line

Other structures

Bridging the Glinščica valleyDue to ventilation problems in tunnels T1 and T2, the two tunnels and structures across

the Glinščica valley will be connected into a single tunnel structure. Bridges Glinščica 1

and Glinščica 2 are planned to be implemented as closed box structures, connecting to

T1 or T2 tunnel with the galleries in front of the tunnels. The bridges are designed as pre-

stressed simply supported structures of a closed box-section with one clearance span

each. The gallery of Glinščica will be implemented between the two bridges. The Glinščica

valley is bridged by three connected structures in a shape of a closed box structure with a

total length of 215 m. These three structures connect to tunnels T1 and T2 on both sides

with galleries. Thus, the impact of rail transport on the sensitive environment of the pro-

tected area of the Glinščica valley is limited to the greatest possible degree.

UnderpassesUnderpass P1 is designed for crossing the existing inter-

state bicycle path D8 and a road which provides access

to individual plots in the vicinity. After the construction

of the second track is completed, the road will also be

used as an access road to the planned power sub-sta-

tion Dekani. The underpass will be made under the new

and under the existing track.

BridgeThe bridge over the Rižana River is designed similarly as the existing bridge of a single-track line at this point, that is, as a

frame reinforced concrete structure over three fields, with a total length of 27.40 m. On the route in the area of crossing

the Glinščica valley, there are two more bridges, which are described in the section on bridging the Glinščica valley.

structure length (m)

Glinščica bridge 1 70

Glinščica gallery with a retaining wall 45

Glinščica bridge 2 100

total 215

GLINŠČICA bridge 1 GLINŠČICA bridge 2GLINŠČICA gallery

Underpass P2 is designed for crossing a categorised

local road which on the north side connects to regional

road R3-741 and on the south side to regional road

R3-625. Due to high groundwater, the underpass is

designed in the form of a caisson. The underpass will be

made under the new and under the existing track.

VIEW OF THE TWO BRIDGES AND THE GLINŠČICA GALLERY LONGITUDINAL SECTION OF THE BRIDGE OVER THE RIŽANA RIVER

CROSS SECTION OF THE BRIDGE OVER THE RIŽANA RIVER

60 61Description of the selected variantSecond track of the Divača–Koper railway line

Culverts

Most of the culverts are located on the sites

where the route of the second track crosses

transverse torrential ravines and smaller

watercourses (edges of the Osp valley and

Vinjan valley). A part of the culverts are also

used in the drainage system - for drain-

ing water from drainage ditches along the

railway line through the body of the line

embankment. On the lower part of the route

(the valley of the Rižana river), new culverts

are mostly on the locations of the existing

ones, on the route of the existing track. These

culverts are not lengthened but replaced by

new ones under both tracks. Culverts on

access roads are an integral part of the plans

of individual roads.

Supporting and retaining structures

Appropriate independent supporting and retaining structures are planned by the

Glinščica gallery between the bridges Glinščica 1 and 2, next to the Črni Kal power

sub-station, and between portals of tunnels T2 and T4. Other supporting structures

are an integral part of the portal structures of tunnels, or are located on access roads

forming an integral part of the plans of individual roads.

no. structure length

(m)

max. height

(m)

1. Anchored retaining wall between bridges

Glinščica 1 and 2

70.00 13.44

2. Retaining wall at the Črni Kal power

sub-station

85.33 10.00

3. Retaining wall between tunnels T3 and T4 114.36 7.70

total length 269.69

Characteristics of culverts:

no. structure dimension

(m)

length

(m)

1.

Flat culvert

1.00/1.00 21.31

2. 1.15/1.00 40.84

3. 5.00/2.00 44.28

4. 2.50/2.00 30.00

5. 1.0/1.0 61.61

6. 1.0/1.0 44.28

7. 1.0/1.0 32.26

8. 1.0/1.0 38.18

9. 2.0/2.0 52.54

10. 2.0/2.0 53.54

11. 2.0/2.0 67.24

no. structure dimension

(m)

length

(m)

12.

Flat culvert

2.0/2.0 57.35

13. 1.0/1.0 24.83

14. 1.0/1.0 22.83

15. 1.0/1.0 12.17

16. 1.0/1.0 11.82

17. 1.0/1.6 7.91

18. 5.0/1.8 6.42

19. 1.6/1.5 21.02

20. 1.6/1.5 24.41

21. 1.0/1.0 16.67

total length of culverts 691.51

62 63Description of the selected variantSecond track of the Divača–Koper railway line

Noise prevention measures In accordance with the requirements of the study on noise pollution, it

will be necessary to build five sets of noise barriers on the route of the

second track.

noise barriers

code type/category chainage (km) height of uer length surfacefrom km to km (m) (m) (m2)

NB 1 Absorption (A2) 15+940.00 16+075.00 2.5 135.00 337.50

NB 2 16+125.00 16+768.00 2.5-5.5 645.00 2,939.20

NB 2-1 Absorption (A2) 16+125.00 16+176.80 2.5 51.80 129.50

NB 2-2 Structure of V1 viaduct 16+176.80 16+623.30 5.5 445.20 2,439.70

NB 2-3 Absorption (A2) 16+623.30 16+768.00 2.5 148.00 370.00

NB 3 16+176.80 16+768.00 2.5-5.5 594.70 2,821.30

NB 3-1 Structure of V1 viaduct 16+176.80 16+623.30 5.5 447.50 2,453.30

NB 4 21+530.00 22+275.00 2.5 759.70 1,899.25

NB 4-1 Absorption (A2) 21+530.00 21+593.80 2.5 64.33 160.83

NB 4-2 Transparent to V2 21+593.80 22+239.40 2.5 647.50 1,618.75

NB 4-3 Absorption (A2) 22+238.50 22+275.00 2.5 47.87 119.68

NB 5 Absorption (A2) 27+175.00 27+425.00 2.5 248.50 621.25

64 65Description of the selected variantSecond track of the Divača–Koper railway line

Superstructure

General

The construction of a slab track is planned on the greater part of

the section, while a classic track on a ballast bed is planned over

the smaller area outside tunnels and structures.

Ballastless track

Slab track systemThe project includes a slab track system of type OBB PORR. Train

load is transmitted through the rails to fixing points, then to the

load-bearing plate of the track, and through the elastic contact area

to the track bed. The load-bearing plate of the track is the main

load-bearing element of the structure - it is made in a concrete

mixing plant as a prefabricated element from reinforced concrete. It

has two rectangular openings through which it is poured with self-

levelling concrete after it is installed at a suitable height and position.

The lower part of load-bearing plate and the inner and outer edges

are covered with an elastic contact layer. The load-bearing plate

of the track is installed on the reinforced concrete slab for load-

distribution, the thickness of which depends on whether the track

runs in a tunnel, on a bridging structure or on an open route.

Rails and fixing material Rails of system 60 E1 will be installed on the section, with a length of

100 m and a quality grade of at least 900. The shape and character-

istics of rails are defined in SIST EN 13674-1:2004. Tracks are welded

into a continuous welded rail with aluminothermic welding and by

taking into account the specifics of welding in tunnels.

Ballasted track

Rails of system 60 E1 will be installed on the section, with a

length of 100 m and a quality grade of at least 900. The shape

and characteristics of rails are defined in SIST EN 13674-1:2004.

The rails are welded and at the end of the section in question, a

transition rail from system 60 E1 to system 49 E1 is installed with

the length of 7.2 m.

The concrete sleepers of 260 cm of length with an axial distance

of 0.6 m are planned and must comply with SIST EN 13230-

1:2007.

The thickness of the bed is 30 cm between the bottom edge of

the sleeper and the top of the formation level (buffer layer). On

the location of underpasses, bridges and culverts, this thickness

is a minimum 35 cm. The gradient of the bed is 1 : 1.5, with inbuilt

crushed stone 32/50v in accordance with SIST 13450:2003.

Tracks and points are welded into a continuous welded rail

(CWR) with aluminothermic welding. Rails welded are 100 m

long and the welding starts at the directional and height regu-

lation of tracks.

66 67Description of the selected variantSecond track of the Divača–Koper railway line

Signalling and safety devices On the second track of the Divača–Koper line, the ERTMS/ETCS system of level 2 will be installed. In

the context of the documentation of the project design for a building permit for the construction of

the second track of the Divača–Koper line, detailed reports are prepared for the execution of:

• Signalling and safety devices;

• GSM-R system;

• Video surveillance and security;

• Powering.

These systems and devices will be installed on the railway line in the final stage of construction. Due

to the construction of a large number of tunnels, the installation of the mentioned systems will be

implemented several years after the start of the construction. Given the rapid development of pro-

fessional expertise in this field, the projects of the systems discussed would already be out-dated by

then. The plans of the systems and devices in question will therefore be prepared later in the context

of making executive design project documentation. In the context of prepared project designs for

building permit, the construction part of the installation of devices in question is adequately dealt

with. These are the sewage system and trenches for wiring with the necessary shafts, standing points

of individual devices, phones, GSM-R base stations, all the canals and similar.

Plans of the project design for a building permit are also made for the relocation of the existing sig-

nalling and safety devices of the existing track, on the part between the Divača power sub-station

and the Bivje junction where the second track runs parallel to the existing track. On this part of the

route, signalling and safety devices and lines of the existing track are located on the right side of the

track and need to be moved to the other side of the existing track prior to the construction of the

second track.

Documents of the project design for a building permit also contain the prepared plans of signalling

and safety devices and lines for the deviation of the existing track after the Dekani station, which must

be carried out within the context of the construction of the second track of the Divača–Koper line.

Relocation of utility linesOn the route of the second track, the relocation of utility power lines is

planned, as well as some low-voltage lines and water supply pipes. This

will primarily be adjustments and connection of lines needed to build the

second track, such as the connection of the power sub-station to the net-

work, the connection of the pumping stations of the caissons of under-

passes, locational removal of local water supply or telecommunication

lines. There will be no significant relocations of utility lines (high voltage

power lines, the main water supply lines or gas pipes) on the route.

Electrical catenaryOn the second track of the Divača–Koper railway line, the electrical

catenary will be implemented with the system of direct current (DC)

and voltage of 3kV. The electrical catenary will be implemented so that

it is possible to later upgrade it with the system of alternating current

(AC) with the voltage of 25 kV. An overhead line is planned with a

cross-section of 440 mm2. Steel lattice rods are planned for carrying

overhead lines, adapted for fixing to the foundation with an anchor

plate and screws. Minimal distance of the internal edge of an overhead

line rod depends on the position (straight, curves) and the height and

the orientation of the rail heightening. This distance varies from 3.45 m

to 3.85 m (at the lower part of the route, by the existing track – ballasted

track - the minimum distance is also 2.55 m)

Power sub-stations Powering of the electric catenary on the second track of the Divača–

Koper railway line is planned from the power sub-stations Divača, Črni

Kal and Dekani. Power sub-stations Divača and Dekani will be prop-

erly arranged in the context of the modernisation of the existing track,

while the Črni Kal power sub-station will be built in the context of the

construction of the second track. The powering of the Črni Kal power

sub-station will be provided with the implementation of the connection

to the 110 kV Divača–Koper power line for powering electrical traction,

and with the implementation of the connection to the 2x20 kV power

line of Dekani–Divača/Črnotiče power sub-station for powering safety

systems in tunnels and the power sub-station's own use.

68 69Estimated value of the selected variantSecond track of the Divača–Koper railway line

Estimated value of the selected variant

70 71Estimated value of the selected variantSecond track of the Divača–Koper railway line

The assessment of the investment value of the construction of the second track between Divača and Koper in the amount of

EUR 1,289,878,629.00 (including VAT, fixed prices in April 2013) was made in the context of the preparation of the investment

programme (INVP) in October 2013. The assessment was made on the basis of the designer cost estimation of the reviewed

project design for a building permit, which was made by the company SŽ - Projektivno podjetje, Ljubljana d.d., with partners. The

investment programme has not yet been adopted since the financing of the project has not yet been determined. Nevertheless,

we estimate that the part that refers to the amount of costs is estimated sufficiently realistically and will not change, while the

investment programme can be completed and confirmed only after the exact financing of the project is known.

the assessment of the investment value is divided into several main sets:

A Implementation works EUR 890,731,206

B Other costs EUR 63,986,910

C Other services EUR 105,037,178

total eur 1,059,755,294

VAT EUR 230,123,335

total IncludIng vat eur 1,289,878,629

Implementation works (A) include all works necessary for the construction of tunnels, bridging structures, access roads and

pre-cuts together with works needed to carry out the route and superstructure, catenary, signalling and safety devices, as well

as video surveillance and security. This set also includes the implementation of the second track between the Dekani power

sub-station and Koper, and 7% of the entire budget amount is designated for unforeseen works.

The set of other costs (B) includes the cost of disposal sites and the cost of processing of excess material, costs relating to the

purchase of necessary land and the purchase of two road-rail fire trucks. This set also includes the renovation of the existing

track between the Dekani power sub-station and Koper, and 5 % of the entire budget amount is designated for unforeseen works.

The set of other services (C) includes the costs required for the preparation of project documentation, archaeological investiga-

tion and excavation, and cost for project supervision and management.

72 73Effects on the environmentSecond track of the Divača–Koper railway line

Effects on the environment

during the construction of the second track between divača and koper, it will be necessary to strictly comply with the requirements related to environmental impacts. these requirements also apply to potential cross-border impacts.

74 75Effects on the environmentSecond track of the Divača–Koper railway line

Geological and relief characteristicsThe regulation of the construction site and construction works will mostly cause indirect impacts

on geological conditions and relief, which will only be short-term in nature. The greatest direct

impacts can be expected at the area of the construction of major embankments, deeper cuts,

tunnels, and at locations of the intake of excess material. Taking into account mitigation meas-

ures such as appropriate gradients of cuts and embankments, rehabilitation of temporary routes

and manipulation areas, rehabilitation of exposed areas, the impact during the construction will

be moderate to large.

Possible impacts of the intervention on the geological conditions and relief features in the

cross-border area of the Republic of Italy are not expected.

AirConstruction will take place mainly in a scarcely pop-

ulated area, while transport needed for construction of

the railway line will be carried out on construction roads

and the existing public road network. During the con-

struction, emissions of particles and exhaust gases will

be increased at construction sites, construction roads

and sites where excess material will be deposited. The

emissions of particles from open parts of construction

sites will be the highest during preparatory earthworks

of soil excavation, transport of material and its depos-

iting on temporary and permanent deposit sites. The

impact during the construction will be moderate if mit-

igation measures are implemented: the prevention of

dusting of uncovered parts of the site and manipulation

areas, regular cleaning of transport surfaces and setting

up construction fences near other buildings, and other

mitigation measures, such as cleaning the chassis of

construction machinery when leaving the site, and it will

also be necessary to strictly adhere to legal restrictions

and terms from approvals.

During the construction and operation, there will be no

cross-border impact on air quality.

Quality of soil and plantsDuring the construction, soil pollution will be caused by

the increased burdening of soil with substances orig-

inating from the excavated or construction materials

and with emissions from the transport of construction

materials and excavated material. These effects may

include the increased emissions of dust particles, the

transport of material and related emissions, inappropri-

ate handling of run-off rainwater and contamination of

soil with various surface materials. During the operation,

impacts are possible on the sections where the route

runs in the open and on exit areas due to improper han-

dling of run-off rainwater and accidents in the transport

of dangerous or harmful substances.

By taking into account mitigation measures, the impact

during the construction will be moderate. During the

construction, it will be necessary to strictly adhere to

legal restrictions and terms from approvals.

Cross-border impact of the construction of the second

track of the Divača–Koper line on soil both during the

construction and operation is reasonably not expected.

76 77Effects on the environmentSecond track of the Divača–Koper railway line

Hydrographical features, chemical and ecological state of surface waters and flood safetyThe Karst region is characterised by a shortage of permanent surface waters.

These appear on the edge karst areas of the lower Karst, where watertight

flysch rocks are found. Several watercourses are on the flysch area in the

lower part of the route. Impacts of limited duration are expected during

the construction. These are impacts on the water regime and on naturally

preserved watercourses, as well as an increase in lateral and vertical erosion in

exposed areas and, consequently, higher turbidity of watercourses. Due to the

abstraction of water for construction, there is a possibility of water discharge

falling below the biological minimum. Impacts during the construction will

be limited to the natural preservation of watercourses, which will undergo

regulation because of the construction of the line.

By taking into account mitigation measures, the impact during the construc-

tion will be moderate. During the construction, it will be necessary to strictly

adhere to legal restrictions and terms from approvals.

No cross-border impacts are expected if all measures to prevent pollution are

taken.

Features and quality of groundwaterThe route passes through the highly vulnerable and sensitive

area of karst-fissured aquifers. In the area of the route of the

second track, there are four regional aquifer systems: Kras

(Karst) and Notranjska reka, Glinščica, Boljunec and Rižana.

Several negative impacts on the quantity and chemical condi-

tion of groundwater will be possible during the construction

and the intake of material. The main effects include changes

of water permeability of the surface, damage to water sources,

changes to water balance and drainage conditions in the area

of the intervention, drainage of groundwater through tunnel

tubes, increased burden of soil due to transport and possibly

inappropriately arranged collection and drainage of rainwater.

During operation, impacts will be possible on the quantity of

groundwater due to the changed water source regime and

possible lowering of the level of groundwater.

By taking into account mitigation measures, the impact of the

construction will be large especially during the construction of

tunnels. It will be necessary to strictly adhere to legal restric-

tions and terms from approvals.

There will be no cross-border impact with the implementation

of all mitigation measures.

79Effects on the environmentSecond track of the Divača–Koper railway line78 Second track of the Divača–Koper railway line

Flora, fauna and habitat typespresence of humans in the immediate surroundings

of the construction site. Over the entire area of the

intervention, negative impact on birds could be

possible due to construction works in the nesting

period when birds cannot retreat and leave their

nests. During and after the intervention, there will be

a highly increased possibility of the introduction of

non-native plant species to the degraded areas. The

operation of the railway line may result in animals

getting run over. Since the majority of the railway line

will run in tunnels, traffic on it will have no significant

impact on birds. Birds will in particular be affected by

noise, which will reduce the density of nesting directly

along the track. Birds hitting electrical lines in the

areas where the track exits a tunnel and birds hitting

The construction will directly destroy parts of the

habitats of plant and animal species in the entire area

of the route that runs on the surface, as well as in the

area of construction sites and locations for the intake

of excavated material. Impacts in the area of tunnels

will be limited to a small number of species or groups.

During the construction, this impact will primarily be

manifested as a direct impact on underground fauna

(cave beetles, cave crickets etc.) and impact on bats

that spend nights or winters in caves. The impact

on wild animals will be manifested particularly as

a disturbance in the daily routine and rituals of the

animals, such as mating, reproduction, parturition,

feeding and similar. The cause will be an increased

pollution of the area with noise and increased

CaveseAt the Karst area, there is a high probability that the tunnel

of the route will cut through one of the passages of the

cave system, in which case the contractor must immedi-

ately inform the professional service for the protection of

nature to avoid pollution or the destruction of caves and

cave contents.

By taking into account mitigation measures, the impact

during the construction and operation will be moderate.

During the construction, it will be necessary to strictly

adhere to legal restrictions and terms from approvals.

Since neither the construction site nor the route reach the

territory of the Republic of Italy, no cross-border impact

on caves is expected during the construction or operation.

trains will be possible. Negative impacts on flora and

fauna of the area will also be present because of the

use of pesticides. There will be no impact on flora,

fauna and habitat types at the sites of the intake of

excavated material.

By taking into account all mitigation measures, the

impact during the construction and operation will be

moderate. During the construction, it will be neces-

sary to strictly adhere to legal restrictions and terms

from approvals.

There will be no cross-border impact since adequate

technical solutions for preventing possible pollution

have been planned.

80 81Effects on the environmentSecond track of the Divača–Koper railway line

Protected areasIn the wider area (up to 500 m), there are three Natura 2000 areas–

Karst Site of Community Importance, Karst Special Protection Area

and Rižana Site of Community Importance, and several protected

areas. The route physically intervenes only in the protected area of

Beka–the Glinščica gorge with the valley of Griža, sinkhole caves,

archaeological sites Lorenco and the castle above Botač. Impact

during the construction will be manifested as permanent reduction

of the habitats of qualifying and key species, increased pollution of

the environment with noise, and increased presence of humans,

which will mostly disturb mammals and birds. There may be negative

effects on active qualifying and key nocturnal animal species in case

of night lighting at construction sites and in case of chopping down

wood vegetation during nesting. The operation of the railway line

will disturb qualifying and key animal species primarily because of

the increased pollution of the environment with noise, the possibility

of birds hitting poorly visible objects and animals colliding with

vehicles, and the inadequately arranged lighting of railway stations.

The impact of construction and operation will be moderate by

taking into account mitigation measures such as a limited period of

construction and preparatory works (chopping down woods etc.),

a limited range of construction sites, and the nature conservation

surveillance. During the construction, it will be necessary to strictly

adhere to legal restrictions and terms from approvals.

There will be no cross-border impact because adequate technical

solutions for preventing possible pollution of this kind have been

planned.

82 83Effects on the environmentSecond track of the Divača–Koper railway line

This could result in a reduction in populations of animal

species in the area. During the operation of the railway

line, negative impacts will be possible on the hydrology,

ecosystem and valuable underground geomorphologi-

cal natural features in the area of intervention. Negative

impacts due to the operation will also be possible at the

ecologically important area of Karst, primarily because of

noise, possible collisions and the use of biocides along

the railway track.

By taking into account a number of mitigation meas-

ures, the impact of the construction and operation is

estimated as moderate. During the construction, it will

be necessary to strictly adhere to legal restrictions and

terms from approvals.

There will be no cross-border impact.

The route of the second track runs in the immediate

vicinity of the geomorphological natural values: Beka–

Ocizla cave system, S-4 (Socerb) and Miškotova jama

cave in Loke. It gets close to less than 20 m to the areas

Glinščica-gorge, Karst Edge, Glinščica, Radvanj–double

sinkhole and Rižana, and three points of value and nat-

ural beauty (Vroček, Glinščica–waterfall and Črnotiče–

location of fossils). The route will physically interfere with

areas of expected valuable underground geomorpho-

logical features (carbonates) and areas of Cretaceous

rocks with fossil fish sites (karst), where it will be possible

to discover and damage new caves and fossils during the

construction. In the wider area of intervention (500 m on

each side of the intervention), there are two ecologically

important areas - Karst EIA and Rižana EIA. In the area

between Divača and Črni Kal, the route will run with its

tunnels, viaducts, surface area, access and service roads

across the ecologically important area of Karst, which will

result in the physical destruction of a part of the ecolog-

ically important area and the impact on the present plant

and animal species. During the construction, noise levels

and the presence of humans will be increased which will

primarily negatively affect large mammals and birds. Due

to construction works in watercourses and their immedi-

ate vicinity, water will become cloudy (increased quantity

of suspended substances in water), and there will also be

a possibility of pollution with cement effluent and haz-

ardous substances which are toxic for aquatic organisms.

Valuable natural features and ecologically important areasThe second track interferes with several areas of cultural her-

itage. At the beginning, it intervenes in the area of Divača–

archaeological site Gorenjski Radvanj (heritage No. 8268),

then it runs over the area of Lokev–archaeological site Ravni

I (heritage No. 8261), Lokev–archaeological site Ravni II (her-

itage No. 9025), Lokev–archaeological site under Strničnik

I (heritage No. 9450) and Lokev–archaeological site under

Strničnik II (heritage No. 4140). The route with accompanying

arrangements in the area of the village of Gabrovica and Črni

Kal intervenes in the area of the cultural monument Gabrovica

pri Črnem Kalu–the historic area of Gabrovica–Osp (herit-

age No. 1283). The railway viaduct intervenes in the area of

influence of the cultural monument Gabrovica pri Črnem

Kalu–the historic area of Gabrovica–Osp (heritage No. 1283)

and in the area of influence of the cultural landscape Podpeč

pri Črnem Kalu–cultural landscape Karst Edge (heritage No.

15087). Access road T-4a intervenes in two areas: Osp–Špina

1 archaeological site (heritage No. 24205) and Osp–Špina 2

archaeological site (heritage No. 3157). The route of the line

intervenes in the area of Gabrovica pri Črnem Kalu–archaeo-

logical site Pod Tivnikom (heritage No. 8264). Access or ser-

vice road T-7a with a connection to the existing road inter-

venes in the smaller part of the protected archaeological site

Osp–Zasedski potok archaeological site (heritage No. 1340).

Part of access road T4-T7 is located in the areas Tinjan–cul-

tural landscape (heritage No. 1299), Tinjan–Vas (heritage No.

25507) and Tinjan–Tinjan hill archaeological site (heritage

No. 1298). Platform T8-Kp with road T-8b intervenes in the

area Dekani–archaeological site Pungerce–Buševca (heritage

No. 3193) and in the part where the second track runs on the

existing corridor intervenes in the area Bertoki–archeological

site Vale (heritage No. 9503). Towards the end of the section,

the second track of the line crosses a unit of cultural herit-

age Spodnje Škofije–Route of line Trieste–Poreč from Škofije

to Bertoki (heritage No. 28579). The location of the intake of

excavated material into the ground, Ankaranska Bonifika, is

located in the area of Ankaran–Bonifika archaeological site

(heritage No. 29080) and in the area of protected cultural her-

itage Ankaran–cultural landscape Ankaranska Bonifika (herit-

age No. 13925). Both direct and indirect impacts are possi-

ble during the construction. Construction works may result

in permanent or temporary degradation or damage to an

area or facility of cultural heritage due to excessive emission

of particles from a construction site, vibrations produced by

construction machinery and construction of additional access

roads to construction sites or service platforms.

By taking into account mitigation measures, the impact during

the construction will be large. During the construction, it will

be necessary to strictly adhere to legal restrictions and terms

from approvals.

Since construction sites, transport paths and the second rail-

way track with accompanying structures and arrangements

do not intrude upon the territory of the Republic of Italy, no

cross-border impacts are expected.

Cultural Heritage

85Effects on the environmentSecond track of the Divača–Koper railway line84 Second track of the Divača–Koper railway line

Cultural landscape and visible qualities of spaceDuring the construction, the visible quality of space will be impacted by

the construction site, temporary depositing of surplus material, con-

struction machinery and additional heavy traffic, primarily in the area

of service platforms, viaducts and in the area of the construction of

access roads. Due to the large proportion of tunnels, the visible expo-

sure of the route of the railway line, perceived as a whole, will be low.

The impact of the construction and operation of the second track will

be moderate by taking into account the proper formation of slopes,

appropriate planting and the design of structures.

The only part that will be visible from Italy will be the section between

tunnels T7 and T8 with viaduct V2 across the Vinjanski potok stream.

The viaduct will create a widely recognisable spatial feature. The land-

scape image and identity of the space in this area will be changed.

Since the infrastructure facilities are a part of everyday life, they are not

perceived as negative; therefore, it is estimated that there will be no

negative cross-border impact.

Agricultural land and agricultureDue to the prevailing underground construction,

the impacts on agricultural land will be less signifi-

cant than they would be in the case of surface con-

struction. Regarding agricultural land by land use,

the route with accompanying arrangements affects

27.8 ha, of which 22 ha is the best agricultural land

and 5.8 ha other agricultural land. Negative impacts

are expected primarily on the pedological and

hydrological state of agricultural space, the estab-

lished agricultural network and the network of land

amelioration canals, and the loss of produce. During

the operation, a negative impact is the permanent

loss of agricultural land.

Taking into account mitigation measures such as

preventing the pollution of agricultural land and

providing access to agricultural land, the impact of

the construction will be moderate. During the con-

struction, it will be necessary to strictly adhere to

legal restrictions and terms from approvals.

Since the route does not run on the Italian territory,

there will be no cross-border impacts on agriculture

and agricultural activity during the construction and

the operation of the second track of the line.

86 87Effects on the environmentSecond track of the Divača–Koper railway line

Forests and forestryand degradation of the Trnovščica forest reserve. Due

to the abovementioned, greater investment in the

protection and cultivation of forests will be needed, as

well as changes of forest management and other plans

in the field.

Taking into account the mitigation measures, such

as preventing soil erosion, implementing silvicultural

measures for consolidating the newly-established

forest edge, planting a new forest edge, recultivation

The route with its accompanying infrastructure affects

35.5 ha of forest land. The construction of the railway

track will interfere with the established network of forest

roads and other roads, and will also cause damage to

the newly formed forest edge and trees. In addition to

the permanent loss or damage to forests, the biggest

impact on forested land and forestry will be caused

by the construction of planned structures, which will

cause damage and changes in micro-location and

habitat conditions on the newly formed forest edge

etc., the impact of the construction and operation

will be moderate. During the construction, it will be

necessary to strictly adhere to legal restrictions and

terms from approvals.

Since the route does not run on Italian territory, there

will be no cross-border impacts on forestry and

forested land during the construction and operation of

the second track of the railway line.

88 Second track of the Divača–Koper railway line 89Effects on the environment

NoiseDuring the construction of the second track of the Divača–Koper line,

noise pollution will increase in the area of the construction of the uncov-

ered part of the route, in the area of construction site platforms of tunnels

and structures, at the construction roads, transport roads for the trans-

port of excess material, and at the areas for the intake of excess material.

In the area of construction site platforms, the dominant sources of noise

will be construction machinery and trucks, ventilation devices for blowing

air into the tunnel tubes, and at some construction site platforms also the

operation of jaw crushers, drilling machines for mining and mobile con-

crete plants. The transport of excess excavated material will be carried

out mainly on state roads. Noise pollution is expected to increase signif-

icantly along these roads. During the intake of the excavated material in

the area of the Šalara marl quarry, Ankaranska Bonifika and the Bekovec

location, occasional excessive noise pollution is expected at the most

exposed buildings, but pollution is not expected to reach critical levels.

Taking into account the mitigation measures such as the implementation

of noise barriers in the total length of approximately 1.1 km, the imple-

mentation of passive noise protection on seven structures, and taking

into account the time limits on construction, the impact of construc-

tion and operation of the second track will be moderate to large, while

the effect of the disposal of excess material will be moderate during the

construction. It will be necessary to adhere to legal restrictions and terms

from approvals.

There will be no cross-border impact with the implementation of a noise

barrier on the Vinjan viaduct, which is the closest to the border with the

Republic of Italy.

VibrationsThe occasional impact of vibrations on individual buildings is expected

during the construction of the second track mainly due to the drilling

of tunnel tubes and construction of tunnels and cuts on the open parts

with mining and blasting, while transport vehicles will be the predominant

source of vibrations on access roads between construction platforms and

the sites for the intake or loading and unloading of excavated material.

An increased impact on buildings due to vibrations is also expected on

transport roads between construction platforms and sites of the intake or

loading and unloading of excavated material. Transport of excess exca-

vated material from tunnel construction sites will mostly take place on the

national road network and partly also on local roads. The area of impact

along transport roads due to the transport of excavated material has been

estimated up to a distance of 10 m from access roads. As the poten-

tial impact on the areas of the Osp valley and the village of Lokev has

been estimated as excessive, the construction of a new construction road

T4-T7 and the use of T1-T1a have been envisaged in order to divert all

cargo traffic to an unpopulated area.

During the construction, it will be necessary to strictly adhere to mitiga-

tion measures (such as the use of appropriate devices for work and the

time limit for intensive construction works) for the impact to be mod-

erate. It will be necessary to adhere to legal restrictions and terms from

approvals.

Considering that the nearest buildings on the Italian side of the border are

far away from the construction sites, there will be no cross-border impact

from vibrations on the Italian side during the construction.

90 91Effects on the environmentSecond track of the Divača–Koper railway line

Light pollutionEnvironmental light pollution can increase primarily

during the construction due to the lighting of construc-

tion sites and construction site platforms. The impact

during the construction will be moderate, it will be

necessary to consider legal restrictions and terms from

approvals.

There will be no cross-border impact on light pollution

during the construction and operation of the second

track of the Divača–Koper line.

Electromagnetic radiationThere will be no sources of electromagnetic radiation

during the construction of the second track of the

Divača–Koper line.

The construction of the second track of the railway line

and its operation will have no impact on the Italian side

in terms of electromagnetic radiation.

WasteMost common waste during the construction will be exca-

vated material, which is not a hazardous waste. Besides

the excavated material, other waste will also appear during

the construction (construction waste, packaging, waste

oil etc.), but in small quantities. Ankaranska Bonifika and

Bekovec are locations planned for the intake of excess

excavated materials into the soil, while the greater part of

the excess material will be taken to the Koper freight sta-

tion and then by rail for processing to the Anhovo cement

factory (flysch material) and Črnotiče quarry (crushing into

useful fractions), and the remainder of the material will be

used for processing into building materials.

When it comes to burdening the environment with

waste, the impact of the intake of excavated material

on both locations of the intake will be positive during

the lifespan of this intervention, as the soil at Ankaranska

Bonifika and Bekovec locations will be improved to the

benefit of agriculture. Also, the removal and processing

in relation to environmental burden will be positive, as it

will reduce interventions required to obtain raw materi-

als for the production of cement or stone fractions.

During the construction, it will be necessary to strictly

adhere to mitigation measures, such as proper collec-

tion, storage and waste management to minimise the

impact of the construction.

There will be no cross-border environmental impact

related to waste.

92 93ConclusionSecond track of the Divača–Koper railway line

Conclusion

94 95ConclusionSecond track of the Divača–Koper railway line

conclusion The second track of the rail link between

Koper and Divača has been the subject of

planning scrutiny and analysis since the late

1990s. The process of spatial placement

determined a variant, for which the Govern-

ment of the Republic of Slovenia adopted

the National Site Plan in 2005. Even later,

after the adoption of NSP, certain checks

were implemented regarding a partial or

total system of double tracks on the line,

but since October 2010, the route of the

line has been final: it will be a single-track

line between Koper and Divača, which

will, together with the existing modernised

line, represent a double-track connection

between Koper and Divača. The route of the

line and its characteristics are described in

this document.

The construction of the line will represent

a challenge for those engaged in the con-

struction profession. It is a complex engi-

neering project with eight tunnels of dif-

ferent lengths, two viaducts, a bridge and a

demanding crossing of the Glinščica valley.

Certainly the construction of tunnels in the

karst region represents a certain risk, which

cannot be entirely avoided despite the geo-

logical and geomechanical research that

has been conducted. During the construc-

tion, special emphasis will need to be given

to following the terms and conditions which

must be met in a sensitive area of the karst

underground and underground waters, in

particular in the construction of tunnels and

in crossing the Glinščica valley.

Also, from the environmental point of view,

it will be demanding to execute accesses to

tunnel portals and to the sites of other civil

engineering structures. It is necessary to

comply with the time allowed for the execu-

tion of works (night work) and also comply

with the conditions from approvals which

at certain times even forbid construction in

some areas.

Time of the construction of the entire section

of the new line between Divača and Koper

is estimated at six to seven years. This does

not take into account the potential risk of

possible complications in the procurement

process and risks regarding any unforeseen

events during the construction of tunnels

(karst caves or abyss, water intrusion). In the

karst area, such events cannot be entirely

ruled out, despite high-quality geological

and geomechanical research. The time of

the construction is most affected by the

execution time of the longest tunnels, fol-

lowed by the time for equipping the entire

section of the new line. The planned tunnel-

ling technology is the so-called New Aus-

trian Tunnelling Method (NATM). The alter-

native implementation technology using a

tunnel-boring machine (TBM) to bore the

entire profile of the tunnel was, considering

the above mentioned findings, deemed as

too risky to be used in the karst region.

Issued and published by: Slovene Infrastructure Agency

Production: DRI upravljanje investicij, d. o.o.

Texts: Bojan Cerkovnik

Editorial board: Tina Bučić, Borut Žličar

Design: Sonja Eržen

Photographs: Miran Kambič, Iztok Ambrož, Miško Kranjec, Jaka Ivančič, Zdravko Primožič, Tom Ločniškar, Milan Marčič,

archive of arhiv DRI upravljanje investicij, d.o.o., archive of Porr Bau GmbH, Shutterstock

Illustrations are representative only.

Print: Tiskarna Januš, Miran Januš s. p.

Ljubljana, June 2015

www.di.gov.si