Transportation (Roads) Nairobi County

Embed Size (px)

Citation preview

  • 8/13/2019 Transportation (Roads) Nairobi County

    1/27

    JICA STUDY TEAMFor The Project on Integrated Urban Development MasterPlan for the City of Nairobi in the Republic of Kenya

    The Project on Integrated Urban Development Plan for

    The City of Nairobi in the Republic of Kenya

    4th Thematic Technical Working Group

    13th Nov 2013

    Road and Urban Transport Sector

    1

    1. Progress of the Study

    2. Future Transport Network Plan

    1) Alternative Plans

    2) Road Network Plan

    3) Public Transport Network Plan

    3. Traffic Demand Forecast Result1) General Methodology

    2) Result of Demand Forecast

    4. Analysis and Evaluation of Traffic Demand Forecast

    5. Staging Plan

    1) Basic Strategy

    2) Road Development Plan

    3) Public Transport Development Plan

    4) Demand Forecast and Evaluation of Staging Plan6. Conclusion and Recommendation

    2

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    2/27

    1. Progress of the Study

    1. Progress of the Study 4th TWG/ Road and Urban Transport Sector

    3

    2. Future Transport Network Plan

    1) Alternative Plans

    The following Alternative Plans are analyzed to establish network.

    Do-nothing Case:Future (2030) traffic demand to present network

    Case 0:On-going ProjectFuture traffic demand on existing network and on-goingprojects**Refer to next page.

    Case 1: Road Development Oriented Case

    2006 Road Networked reinforced by future traffic demandand land use plan

    Case 2: Utilization of Commuter Rail Case

    Future road network with Commuter Railway networkCase 3: Introduction of Selective MRTS Case

    Case 2+selective/modified MRTS network where demandconcentrates

    2. Future Transport Network Plan

    4th TWG/ Road and Urban Transport Sector

    4

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    3/27

    *On-going ProjectsThe following projects are included in the on-going projects. Expanding and upgrading of the Northern Corridor Road including

    the Elevated highway over the Uhuru Highway

    Construction of Southern Bypass Road Construction of Missing Link Roads financed by EU Dualling of Outer Ring Road Construction of Western Ring Roads Widening of Ngong Road from Kenyatta Ave. intersection to

    Dagoretti Widening of Juja Road Upgrading of Langata Road of KWS Gate-Bomas Junction Section

    2. Future Transport Network Plan 4th TWG/ Road and Urban Transport Sector

    5

    a) Basic Policy for Road Network Plan

    Basic network shall be 2006 M/P (NUTRANS) andreinforced in the following aspects:

    Strengthen circumferential/radial (C/R) network

    system. Strengthen radial road network connecting

    surrounding area of Nairobi.(Necessary capacity will be estimated by demandforecast.)

    Development of new road required by the land useplan.

    Strengthen east-west axis roads

    Traffic assignment of future traffic demand toexisting road(Do-nothing Case) will be analyzedand necessary capacity will be adopted.

    2) Road Network Plan

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    6

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    4/27

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    b)RoadNetworkProposedbyNUTRANS

    7

    c)ResultofTrafficAssignmentofDonothingCase2030trafficdemandtopresentnetwork

    Source: JICA Survey Team (JST) VCR: Volume Capacity RatioVolume includes all t e of vehicles

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    8

    VCR Situation

    -1.0Free flow. Trafficcongestion does notappear.

    10-1.25

    Traffic congestionmay appear at apeak hour.

    1.251.50

    Traffic congestionappears at a peakhour.

    1.50- Traffic congestionmay appear all day.

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    5/27

    d) Evaluation of Demand Forecast of Alternative 0

    Mombasa Rd Waiyaki Way shows VCR over 1.50. Thika Rd shows VCR over 1.50. Outer Ring Rd shows VCR over 1.50. Juja Rd shows VCR over 1.50. Jogoo Rd shows VCR over 1.50. Langata Rd shows VCR over 1.50. Ngong Rd. shows partially VCR over 1.50. Eastern Bypass shows VCR over 1.50.

    Widening of Langata Rd to 6-lanes. Widening of Jogoo Rd to 6-lanes. Widening of Eastern Bypass to 4-lanes. Introduction of MRTS to over capacity roads. Especially on-going

    project roads.

    In addition to the road network proposed by NUTRANS, the followingmeasures are required in future road network.

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    9

    2. Future Transport Network Plan Road Network 4th TWG/ Road and Urban Transport Sector

    e) Future Road Network in 2030

    Remark: Route of the circumferential road C2 was altered considering its feasibility. 10

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    6/27

    3) Public Transport Network Plan

    a) Commuter Rail Network Proposed by NUTRIP

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    11

    Legend

    Bus Rapid Transit

    Light Rail Transit

    Metro Rail

    Commuter RailTransit Hub

    Transit Terminal

    Transit Interchange

    c) Public Transport Network Proposed by MRTS

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    12

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    7/27

    d) Evaluation of Priority Corridor

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    13

    e) Selected Priority Corridors and Routes

    LRT circular route is

    proposed in order todecrease the number ofvehicles going into CBD andmake the CBD NMT area.

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    14

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    8/27

    Viaduct-1

    Viaduct-2

    New Bus Terminal

    g)Terminal Plan

    Development of new bus/matatu terminal in the railway city isproposed to alleviate the congestion at the present terminal.

    Inter-city bus terminals are proposed at the outskirt of urban area.

    Those terminals also assist the creation of sub-centers.

    Concept of new terminalin the railway city

    4th TWG/ Road and Urban Transport Sector2. Future Transport Network Plan

    15

    1) General Methodology : Four-step-method

    Estimation of Future Population, etc.

    Trip Generated and Attracted

    Trip Distribution

    Modal Split

    Trip Assignment

    Future Traffic Volume

    The trip generated and attracted volume by zone isforecast from the trip production.

    OD table which set trip generated and attracted volumeto an Origin/Destination is calculated.

    The traffic among zones is split by transportation mode.

    OD table by modal split is assigned to the transportationnetwork

    Trip Production The purpose-oriented trip produced in the overall area isforecast.

    Person Trip Survey

    3. Traffic Demand Forecast Result

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    16

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    9/27

  • 8/13/2019 Transportation (Roads) Nairobi County

    10/27

    VCR: Volume Capacity RatioVolume includes all type of vehicles

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    ii)AssignmentofFutureTrafficDemand(2030)toExistingNetwork(2013)

    b) Vehicle Assignment Result

    19

    Source: JICA Study Team (JST)

    VCR: Volume Capacity RatioVolume includes all type of vehicles

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    iii)Alternative0:OngoingProject VehicleAssignment

    b) Vehicle Assignment Result

    20

    Source: JICA Study Team (JST)

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    11/27

    VCR: Volume Capacity RatioVolume includes all type of vehicles

    iv)Alternative1:RoadDevelopmentOrientedCase VehicleAssignment

    b) Vehicle Assignment Result

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    21

    Source: JICA Study Team (JST)

    VCR: Volume Capacity RatioVolume includes all type of vehicles

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    b) Vehicle Assignment Result

    v) Alternative2:Utilizationof CommuterRailCase VehicleAssignment

    22

    Source: JICA Study Team (JST)

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    12/27

    VCR: Volume Capacity RatioVolume includes all type of vehicles

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    b) Vehicle Assignment Result

    vi)Alternative3:IntroductionofSelectiveMRTSCase VehicleAssignment

    23

    Source: JICA Study Team (JST)

    Source: JICA Study Team (JST)

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    c) Public Transport Assignment Result

    i)Alternative2:Utilizationof CommuterRailCase PublicTransport Assignment

    24

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    13/27

    Source: JICA Study Team (JST)

    ii)Alternative3:IntroductionofSelectiveMRTSCase PublicTransportAssignment

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    25

    Source: JICA Study Team (JST)

    ii)2Alternative3:IntroductionofSelectiveMRTSCase PublicTransportAssignment

    Scaled up

    3. Traffic Demand Forecast Result 4th TWG/ Road and Urban Transport Sector

    26

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    14/27

    Alternative YearVehicle-km TotalPCU-km000)

    Vehicle-hours TotalPCU-HourAverageSpeedkm/h)

    AverageVCRVolumeCapacityRatio)Existing Case 2013 17,780 431,690 41.2 0.54

    Do Nothing Case 2030 39,110 1,692,480 23.1 1.19

    0 On-going ProjectCase

    2030 37,670 1,173,180 32.1 1.02

    1 Road DevelopmentOriented Case

    2030 36,490 929,850 39.2 0.85

    2 Utilization ofCommuter Rail Case

    2030 35,090 880,110 39.9 0.81

    3 Introduction ofSelective MRTS Case

    2030 30,540 725,460 42.1 0.71

    Source: JICA Study Team (JST)

    a)ResultinStudyArea

    4. Analysis and Evaluation of Traffic Demand Forecast

    4. Analysis and Evaluation of Traffic Demand Forecast

    1) MajorIndicesbyVehicleAssignment

    4th TWG/ Road and Urban Transport Sector

    27

    Source: JICA Study Team (JST)

    4. Analysis and Evaluation of Traffic Demand Forecast 4th TWG/ Road and Urban Transport Sector

    b)ResultinNairobiCity1) MajorIndicesbyVehicleAssignment

    Alternative YearVehicle-km TotalPCU-km000)

    Vehicle-hours TotalPCU-HourAverageSpeedkm/h)

    AverageVCRVolumeCapacityRatio)Existing Case 2013 10,960 273,910 40.0 0.69

    Do Nothing Case 2030 25,320 1,254,120 20.2 1.60

    0 On-going ProjectCase

    2030 25,520 805,560 31.7 1.32

    1 Road DevelopmentOriented Case

    2030 24,830 621,140 40.0 1.05

    2 Utilization ofCommuter Rail Case 2030 23,790 582,600 40.8 1.003 Introduction of

    Selective MRTS Case2030 19,450 433,330 44.9 0.82

    28

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    15/27

    2) Congestion Ratio by Vehicle Assignment

    4. Analysis and Evaluation of Traffic Demand Forecast 4th TWG/ Road and Urban Transport Sector

    a)ResultinStudyArea

    Source: JICA Study Team (JST)

    Unit : km

    29

    CongestionRatio Existing in2013 Do Nothingin 2030 Alternative 0in 2030 Alternative 1in 2030 Alternative 2in 2030 Alternative 3in 2030-0.8 1,114.7 563.5 770.2 887.2 908.2 1,010.4

    0.8 - 1.0 116.4 199.7 134.8 178.7 193.3 212.81.0 - 1.2 106.9 151.9 120.3 155.7 151.7 136.41.2 - 1.5 84.1 131.3 188.2 163.8 166.1 110.8

    1.5 - 29.2 405.0 272.3 133.3 99.3 48.3TOTAL 1,451.4 1,451.4 1,485.8 1,518.7 1,518.7 1,518.7

    76.8%

    38.8%

    51.8%

    58.4%

    59.8%

    66.5%

    8.0%

    13.8%

    9.1%

    11.8%

    12.7%

    14.0%

    7.4%

    10.5%

    8.1%

    10.3%

    10.0%

    9.0%

    5.8%

    9.0%

    12.7%

    10.8%

    10.9%

    7.3%

    2.0%

    27.9%

    18.3%

    8.8%

    6.5%

    3.2%

    0% 20% 40% 60% 80% 100%

    Existing

    2013

    DoNothingCase

    2030

    Alternative0

    2030

    Alternative1

    2030

    Alternative2

    2030

    Alternative3

    2030

    0.8 0.8 1.0 1.0 1.2 1.2 1.5 1.5

    4. Analysis and Evaluation of Traffic Demand Forecast 4th TWG/ Road and Urban Transport Sector

    Source: JICA Study Team (JST)

    Unit : km

    2) Congestion Ratio by Vehicle Assignment b)ResultinNairobiCity

    30

    CongestionRatio Existing in2013 Do Nothingin 2030 Alternative 0in 2030 Alternative 1in 2030 Alternative 2in 2030 Alternative 3in 2030-0.8 510.2 171.1 243.3 329.6 343.5 450.6

    0.8 - 1.0 81.0 69.2 81.8 127.6 144.5 151.41.0 - 1.2 69.5 80.6 87.2 109.9 117.1 107.61.2 - 1.5 62.3 85.8 139.1 143.3 131.4 83.9

    1.5 - 28.1 344.5 227.4 97.6 71.4 14.5TOTAL 751.2 751.2 778.9 807.9 807.9 807.9

    67.9%

    22.8%

    31.2%

    40.8%

    42.5%

    55.8%

    10.8%

    9.2%

    10.5%

    15.8%

    17.9%

    18.7%

    9.3%

    10.7%

    11.2%

    13.6%

    14.5%

    13.3%

    8.3%

    11.4%

    17.9%

    17.7%

    16.3%

    10.4%

    3.7%

    45.9%

    29.2%

    12.1%

    8.8%

    1.8%

    0% 20% 40% 60% 80% 100%

    Existing

    2013

    DoNothingCase

    2030

    Alternative0

    2030

    Alternative1

    2030Alternative2

    2030

    Alternative3

    2030

    0.8 0.8 1.0 1.0 1.2 1.2 1.5 1.5

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    16/27

    - Comparing the indices of Alternative 0 to 3, vehicle-km,vehicle-hours and average VCR decrease due to the

    development of Mass Transit.

    - Development of roads cannot solve the traffic congestionas shown in p.21. Reinforcement of mass transit andintroduction of new transit system are requisite.

    - By reinforcement of commuter rail and introduction of BRTto 6 corridors, traffic congestion is eased especially in theeastern area of city centre.

    - As the result, Alternative 3 is recommended solutionagainst the future increasing traffic demand.

    3) Evaluation of Alternatives

    4. Analysis and Evaluation of Traffic Demand Forecast 4th TWG/ Road and Urban Transport Sector

    31

    1) Basic Strategy

    5. Staging Plan

    Target of road and urban transport1) Network in coordination with land use2) Network for world class mobility

    1st Phase

    Present to 2018

    2nd Phase

    2019 to 2023

    3rd Phase

    2024 to 2030

    Network in

    coordination

    with Land

    Use

    Study/technical

    assistance for

    development of

    infrastructure in

    Railway City

    Development of

    infrastructure in

    Railway City

    Network

    development to

    connect sub-

    centres

    Network for

    world class

    mobility

    Improvement of

    network to solve

    existing issues.

    Institutional

    arrangement for

    strengthening public

    transport

    Introduction of MRTS

    to pilot corridors.

    Development of road

    corridors to introduce

    MRTS

    Strengthening of

    circumferential roads

    to form the C/R

    network

    Expand

    introduction of

    MRTS to plural

    corridors

    Establishment of

    C/R network

    system

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    32

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    17/27

    Short Term (-2018) Road Network

    2) Road Development Plan

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    33

    Medium Term (-2023) Road Network

    2) Road Development Plan

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    34

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    18/27

    Long Term (-2030) Road Network

    2) Road Development Plan

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    35

    Medium Term (-2023) Public Transport Network

    3) Public Transport Development Plan

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    36

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    19/27

    Long Term (-2030) Publ ic Transport Network

    3) Public Transport Development Plan

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    37

    1) Result of Modal Split Forecast

    Source: JICA Study Team (JST)

    4) Demand Forecast and Evaluation of Staging Plan

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    38

    Alternative Year WALK PRIVATE BUS NewTransport RAIL TOTALExisting 2013 3,090,103 916,624 2,754,489 - 14,006 6,775,222

    3Introduction of

    Selective MRTS 2018 3,246,051 1,289,796 3,281,824 - 14,416 7,832,087

    3 Introduction ofSelective MRTS

    2023 3,606,326 1,506,186 3,564,101 - 181,736 8,858,349

    3 Introduction ofSelective MRTS

    2030 3,951,711 1,767,773 4,062,046 45,692 190,456 10,017,678

    45.6%

    41.4%

    40.7%

    39.4%

    13.5%

    16.5%

    17.0%

    17.6%

    40.7%

    41.9%

    40.2%

    40.5%

    0.2%

    0.2%

    2.1%

    1.9%

    0.5%

    0% 20% 40% 60% 80% 100%

    2013

    Alternative3

    2018

    Alternative3

    2023

    Alternative3

    2030

    WALK PRIVATE BUS RAIL NewTransport

    Unit : Trips

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    20/27

    Source: JICA Survey Team (JST)VCR: Volume Capacity RatioVolume includes all type of vehicles

    i) Existing in 2013

    2) Vehicle Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    39

    Source: JICA Survey Team (JST)VCR: Volume Capacity RatioVolume includes all type of vehicles

    ii) Alternative 3 in 2018

    2) Vehicle Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    40

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    21/27

    Source: JICA Survey Team (JST)VCR: Volume Capacity RatioVolume includes all type of vehicles

    iv) Alternative 3 in 2023

    2) Vehicle Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    41

    Source: JICA Survey Team (JST)VCR: Volume Capacity RatioVolume includes all type of vehicles

    v) Alternative 3 in 2030

    2) Vehicle Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    42

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    22/27

    Source: JICA Study Team (JST)

    ii) Alternative 3 in 2023

    3) Public Transport Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    43

    Source: JICA Study Team (JST)

    iii)-1 Alternative 3 in 2030

    3) Public Transport Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    44

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    23/27

    Source: JICA Study Team (JST)

    v) Alternative 3 in 2023 (Scaled up)

    3) Public Transport Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    45

    Source: JICA Study Team (JST)

    vi) Alternative 3 in 2030 (Scaled up)

    3) Public Transport Assignment Result

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    46

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    24/27

    i) Result in Study Area2) Major Indices by Traffic Assignment

    Alternative YearVehicle-km TotalPCU-km000)

    Vehicle-hours TotalPCU-HourAverageSpeedkm/h)

    AverageVCRVolumeCapacityRatio)Existing Case 2013 17,780 431,690 41.2 0.54

    3 Introduction ofSelective MRTS Case

    2018 24,170 618,900 39.1 0.69

    3 Introduction ofSelective MRTS Case

    2023 27,000 680,230 39.7 0.72

    3 Introduction ofSelective MRTS Case

    2030 30,540 725,460 42.1 0.71

    Source: JICA Study Team (JST)

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    47

    ii) Result in Nairobi City2) Major Indices by Traffic Assignment

    Alternative YearVehicle-km TotalPCU-km000)

    Vehicle-hours TotalPCU-HourAverageSpeedkm/h)

    AverageVCRVolumeCapacityRatio)Existing Case 2013 10,960 273,910 40.0 0.69

    3 Introduction ofSelective MRTS Case

    2018 16,210 424,160 38.2 0.92

    3 Introduction ofSelective MRTS Case

    2023 18,040 444,960 40.6 0.90

    3 Introduction ofSelective MRTS Case

    2030 19,450 433,330 44.9 0.82

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    48

    Source: JICA Study Team (JST)

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    25/27

    i) Result in Study Area3) Congestion Ratio by Traffic Assignment

    Source: JICA Study Team (JST)

    Unit : km

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    49

    76.8%

    66.8%

    67.1%

    66.5%

    8.0%

    10.9%

    9.9%

    14.0%

    7.4%

    6.8%

    8.2%

    9.0%

    5.8%

    8.8%

    7.6%

    7.3%

    2.0%

    6.6%

    7.2%

    3.2%

    0% 20% 40% 60% 80% 100%

    Existing

    2013

    Alternative3

    2018

    Alternative3

    2023

    Alternative3

    2030

    0.8 0.8 1.0 1.0 1.2 1.2 1.5 1.5

    CongestionRatio Existing in2013 Alternative 3in 2018 Alternative 3-1 in 2023 Alternative 3-2 in 2023 Alternative 3in 2030-0.8 1,114.7 989.4 980.4 1,004.1 1,010.4

    0.8 - 1.0 116.4 161.4 147.2 148.7 212.81.0 - 1.2 106.9 101.1 127.9 122.3 136.41.2 - 1.5 84.1 130.9 129.0 113.9 110.8

    1.5 - 29.2 98.1 111.7 107.1 48.3TOTAL 1,451.4 1,480.9 1,496.2 1,496.2 1,518.7

    50

    ii) Result in Nairobi City3) Congestion Ratio by Traffic Assignment

    Source: JICA Study Team (JST)

    Unit : km

    5. Staging Plan 4th TWG/ Road and Urban Transport Sector

    CongestionRatio Existing in2013 Alternative 3in 2018 Alternative 3-1 in 2023 Alternative 3-2 in 2023 Alternative 3in 2030-0.8 510.2 389.8 403.4 419.0 450.6

    0.8 - 1.0 81.0 122.6 108.6 116.9 151.41.0 - 1.2 69.5 77.7 106.5 95.9 107.61.2 - 1.5 62.3 100.9 100.9 93.1 83.9

    1.5 - 28.1 83.0 69.9 64.3 14.5TOTAL 751.2 773.9 789.3 789.3 807.9

    67.9%

    50.4%

    53.1%

    55.8%

    10.8%

    15.8%

    14.8%

    18.7%

    9.3%

    10.0%

    12.2%

    13.3%

    8.3%

    13.0%

    11.8%

    10.4%

    3.7%

    10.7%

    8.1%

    1.8%

    0% 20% 40% 60% 80% 100%

    Existing

    2013

    Alternative3

    2018

    Alternative3

    2023

    Alternative3

    2030

    0.8 0.8 1.0 1.0 1.2 1.2 1.5 1.5

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    26/27

    6. Conclusion and Recommendation 4th TWG/ Road and Urban Transport Sector

    6. Conclusion and Recommendation

    General1. In the short term and medium term, traffic condition will

    worsen because improvement of network cannot catch up the

    increasing traffic demand.2. Under the condition that the proposed plan is implemented,

    transport condition will be improved in the target year. To thisend, improvement of public transport network as well as roadnetwork is essential to realize future transport network.

    Road Network1. Improvement of Mombasa Rd-Waiyaki Way is crucial project

    for the whole Nairobi city. According to the analysis of the

    study, viaduct over Nyayo Stadium round about is necessary toreduce congestion. (See P.42)

    2. Entry of heavy vehicles inside the area surrounded by eastern,northern and southern bypass shall be restricted after thecompletion of southern bypass.

    51

    6. Conclusion and Recommendation 4th TWG/ Road and Urban Transport Sector

    Public Transport Network1. In order to materialize the MRTS plan, not only the physical

    infrastructure but also institutional framework, especiallyestablishment of operator, is basically requested.

    2. Obtaining general consensus for the improvement of transport

    network among the passengers and operators of bus/matatu isalso requested.

    Short Term MeasuresResult of traffic demand forecast shows the traffic congestionworsen in the short term and medium term . To cope with the issue,various measures should be undertaken.

    1. System signal controlIntegrated Urban Surveillance System (IUSS) is now introducedto CBD area. But traffic congestion occurs in wider area,especially along the radial trunk road in the city, system signalcontrol in the whole city area is expected.

    52

    DraftWo

    rkin

    gGrou

    pMate

    rial

  • 8/13/2019 Transportation (Roads) Nairobi County

    27/27

    2. Introduction of bus-exclusive lane.Even before introduction of BRT, bus exclusive lane is effectiveto enhance the use of public transport.

    3. Staggered working hours

    In the morning peak, more than 20% of private car arrival isfrom 7:00 to 8:00. But the before and after the peak hour,traffic volume decreases to only 5%. Staggered working hourscan use the transport facilities more efficiently.

    4. Streamline the fleet CarrierIn the information age, volume of commodity has becomesmaller but frequency has become high. Introduction ofcooperating distribution system is highly required to decreasethe number of vehicle trips in the business area.

    5. Relocation of Bus terminalsAlong with the land use plan for development of sub-centersin the outskirts area, disposition of bus terminals is expected.These terminals will function as the transfer terminal frommatatu to large bus.

    6. Conclusion and Recommendation 4th TWG/ Road and Urban Transport Sector

    53

    DraftWo

    rkin

    gGrou

    pMate

    rial