Tutorial 33 Two Tunnel Lining Design

Embed Size (px)

Citation preview

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    1/37

    Two Tunnel Lining Design 33-1

    Phase2 v.8.0 Tutorial Manual

    Two Tunnel Lining Design

    In this tutorial,Phase2is used to design two reinforced concrete tunnel

    liners in adjacent tunnels. This tutorial combines elements presented in

    Tutorial 18 (3D tunnel simulation) and Tutorial 24 (Tunnel LiningDesign) and uses the Distributed load induced stress option to help

    determine the tunnel deformation at support installation.

    The final model can be found in the Tutorial 33 Two Tunnel Lining

    Design 02.fez file. All tutorial files installed withPhase28.0 can be

    accessed by selecting File > Recent Folders > Tutorials Folder from the

    Phase2main menu.

    Topics covered

    Reinforced concrete liners

    3D tunnel simulation

    Adjacent excavations

    Distributed loads induced stress option

    Support capacity curves

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    2/37

    Two Tunnel Lining Design 33-2

    Phase2 v.8.0 Tutorial Manual

    Problem

    Two circular tunnels of radius 7.6 m are to be constructed in Shale at a

    depth of 50m. The in-situ stress field is assumed to be isotropic in all

    three dimensions, and equivalent to the vertical stress due to gravity,

    using a unit weight of 25kN/m3. The strength of the Shale can be

    represented by the Generalized Hoek-Brown failure criterion with the

    uniaxial compressive strength of the intact rock equal to 25 MPa, the GSI

    equal to 30 and mi equal to 6. To compute the rock mass deformation

    modulus, the modulus ratio (MR) is assumed to be 200. The support is to

    be installed 2m from the tunnel face.

    The goal of this tutorial is to design two adjacent reinforced concrete

    linings with a factor of safety greater than 1.4.

    To design a support system for a single tunnel (see tutorial 24), the

    following three steps must be performed:

    1. Determine the amount of tunnel wall deformation prior tosupport installation. As a tunnel is excavated, there is a certain

    amount of deformation, usually 35-45% of the final tunnel wall

    deformation, before the support can be installed. Determining

    this deformation can be done using either a) observed field values,

    or b) numerically from 3D finite-element models or axisymmetric

    finite-element models, or c) by using empirical relationships such

    as those proposed by Panet or Vlachopoulos and Diederichs.

    2. Using either the internal pressure reduction method, or the

    modulus reduction method (see tutorial 18), determine the

    internal pressure or modulus that yields the amount of tunnel

    wall deformation at the point of and prior to support installation.

    This is the value determined in step 1.

    3. Build a model that relaxes the boundary to the calculated amountin step 2 using either an internal pressure or modulus. Add the

    support and determine whether a) the tunnel is stable, b) the

    tunnel wall deformation meets the specified requirements, and c)

    the tunnel lining meets certain factor of safety requirements. If

    any of these conditions are not met, choose a different support

    system and run the analysis again.

    Model

    The first step is to determine the amount of tunnel wall deformation priorto support installation. For this tutorial, well use the relationship

    proposed by Vlachopoulos and Diederichs. The Vlachopoulos and

    Diederichs method is documented in Appendix 1 of the Kersten Lecture

    by Hoek, Carranza-Torres, Diederichs and Corkum. The paper is in the

    Hoeks published papers area on the Rocscience website:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    3/37

    Two Tunnel Lining Design 33-3

    Phase2 v.8.0 Tutorial Manual

    http://www.rocscience.com/hoek/references/Published-Papers.htm

    This method requires that we build a model of the tunnel and determine

    a) the deformation far from the tunnel face using a simple plane strain

    analysis, and b) for the same model determine the plastic zone radius.

    Well start by building a single model that also combines step 2 with step1. Well build a plane strain model that relaxes an internal pressure on

    the tunnel boundary from a value equal to the applied in-situ stress to

    zero. The final stage, with zero internal pressure, will be used to

    determine the amount of deformation prior to support installation (step

    1). The factoring of the applied internal pressure over a number of stages

    will be used to determine the pressure that yields the amount of tunnel

    wall deformation at the point of support installation (step 2).

    In this tutorial well start by opening aPhase2file with predefined

    geometry, material properties, boundary conditions, and meshing. The

    tunnels and their respective liners will be installed sequentially, with the

    second tunnel being installed after the first has been supported with its

    liner.

    Start thePhase2Model program.

    Open Tutorial 33 boundaries.fez from File > Recent Folders >

    Tutorials Folder.

    Project Settings

    Open the Project Settings dialog from theAnalysis menu and select

    the Stages tab. Change the number of stages to 11 (see following figure).

    Close the dialog by clicking OK.

    http://www.rocscience.com/hoek/references/Published-Papers.htmhttp://www.rocscience.com/hoek/references/Published-Papers.htmhttp://www.rocscience.com/hoek/references/Published-Papers.htm
  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    4/37

    Two Tunnel Lining Design 33-4

    Phase2 v.8.0 Tutorial Manual

    Excavation

    The tunnel is to be excavated in the second stage so click on the Stage 2

    tab at the bottom of the screen. Simply place the mouse pointer inside the

    right excavation boundary and right-click the mouse. From the menu thatpops up, select theAssign Material > Excavate option.

    The material inside the excavation should now be removed.

    Adding an Internal Pressure to the Excavat ion

    Now lets add a uniform distributed load to the tunnel in Stage 2. The

    magnitude and direction of the load will be equal and opposite to the in-

    situ stresses thus forming a balance between the stresses in the rock and

    the pressure inside the tunnel. Since the pressure is equal and opposite to

    the in-situ stress, no deformation should occur. However, in Stage 3 and

    after, we will factor the load and gradually reduce the magnitude of the

    pressure. As a result, tunnel deformation will increase as the pressure is

    lowered to zero.

    Select: Loading Distributed Loads Add Uniform Load

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    5/37

    Two Tunnel Lining Design 33-5

    Phase2 v.8.0 Tutorial Manual

    In the Add Distributed Load dialog, select the Induced stress

    orientation option. Select the Stage Load checkbox, and select StageFactors to show the Stage Factors dialog.

    In the Stage Factors dialog enter the factors shown in the following

    image:

    Factor = 1 means the magnitude will be the same as the field stress while

    a Factor = 0 means no load will be applied at that stage. Other values of

    Factor can be used to increase or decrease the magnitude of a load at any

    stage of a model.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    6/37

    Two Tunnel Lining Design 33-6

    Phase2 v.8.0 Tutorial Manual

    Select OK in both dialogs. You will now be asked to pick the boundary

    segments on which the load will be applied.

    NOTE: The Field stress vector orientation option could also have been

    selected to equally oppose the in-situ stresses around the tunnel (see

    tutorial 24) for this first tunnel excavation, as it would yield the same

    results as the Induced stress distributed load in the case of a singleexcavation. The two load types differ in that an Induced stress load

    opposes the stresses that exist along its surface from the preceding stage,

    encompassing both the far field stresses and local stress field

    perturbations. The Field stress vector load only opposes the defined far

    field stresses, and it opposes the field stresses in the stage in which it is

    applied. Thus, an Induced stress distributed load must be used to

    oppose redistributed field stresses due to adjacent excavations, as in the

    case of the second tunnel excavation later in this tutorial.

    Select the excavation line segments to be loaded:

    Sel ect boundar y segment s [ ent er=done, esc=cancel ] : use themouse to draw a selection window around the entire excavation.After the excavation segments are selected, right-click and

    select Done Selection, or press Enter.

    Note: to draw a selection window, simply pick one of the window corners

    by moving the mouse cursor to a point, and press AND HOLD DOWN the

    left mouse button. Now move the cursor while still holding down the left

    mouse button, you should see a window forming. Now move the mouse

    cursor to the opposite corner of the window and release the left mouse

    button when done.

    Click the Zoom Excavation button on the toolbar. You should see the

    following in Stage 2:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    7/37

    Two Tunnel Lining Design 33-7

    Phase2 v.8.0 Tutorial Manual

    Now click through the stage tabs. You should see the internal pressure

    factor reduce as the stage increases beyond Stage 2.

    NOTE: the values displayed along the Induced stress distributed load

    vectors are factors of the stress at each respective location along theexcavation boundary. Thus, the distributed load will directly oppose the

    in-situ stresses around the unexcavated tunnel in Stage 1.

    We are now ready to run the analysis.

    Compute

    Before you analyze your model, lets save this as a new file called

    Tutorial 33.fez. (Make sure you select Save As and not Save, or you will

    overwrite the initial file.)

    Select: File Save As

    Save the file as Tutorial 33.fez.

    Select: Analysis Compute

    ThePhase2Compute engine will proceed in running the analysis. When

    completed, you will be ready to view the results in Interpret.

    Interpret

    From Model, switch to the Interpret program.

    Select: Analysis Interpret

    After you select the Interpret option, the Interpret program starts and

    reads the results of the analysis. You will see the maximum stress, sigma

    1 for Stage 1. Click on the Stage 2 tab. Notice that there is no variation of

    stress and that the stress is equal to the in-situ field stress. This means

    that the internal pressure is equal and opposite to the field stress and the

    model is behaving as if the tunnel did not exist.

    Now click the Zoom Excavation button on the toolbar.

    Lets set the reference stage to Stage 1, so that all displacements are

    measured relative to those in Stage 1 (which are essentially 0).

    Select: Data Stage Settings

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    8/37

    Two Tunnel Lining Design 33-8

    Phase2 v.8.0 Tutorial Manual

    Drag the reference stage slider to Stage 1, and select the

    Displacements Only option from the drop-down menu. Press OK.

    Change the contours to plot Total Displacement using the pull down

    menu in the toolbar. The model for Stage 2 will look like this:

    You can see that there no displacement in the first or second stages.

    Now click through the stages. Youll see an increase in deformation

    around the tunnel as the internal pressure is reduced.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    9/37

    Two Tunnel Lining Design 33-9

    Phase2 v.8.0 Tutorial Manual

    Step 1 Computing tunnel deformation before supportinstallation using the Vlachopoulos and Diederichsmethod

    To compute the tunnel deformation at the point of support installation,

    well use the empirical relationship developed by Vlachopoulos and

    Diederichs. To use the Vlachopoulos and Diederichs method, you need

    two pieces of information from the finite-element analysis. You need to

    know a) the maximum tunnel wall displacement far from the tunnel face,

    and b) the radius of the plastic zone far from the tunnel face.

    Both of these values can be computed from a plane strain analysis with

    zero internal pressure inside the excavation. In the model we just built,

    the results from Stage 11 are used since there is zero internal pressure in

    this stage.

    Switch to the last stage, Stage 11. Look in the lower left corner of the

    program window on the status bar. Youll see that the maximum

    displacement for this stage is approximately 0.050m. This is the value ofmaximum wall displacement far from the tunnel face. The location of this

    displacement is in the floor of the excavation. The location of this

    displacement is important since any comparisons of displacement for

    various internal pressures must be made at the same location.

    To determine the radius of the plastic zone, first turn on the display of

    yielded elements using the Display Yielded Elements toolbar button.

    Youll see a number of crosses representing elements in the finite element

    analysis that have failed. Zoom Out so that the entire extent of

    failed points is visible (see below).

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    10/37

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    11/37

    Two Tunnel Lining Design 33-11

    Phase2 v.8.0 Tutorial Manual

    For our problem, Rp=10.5m, Rt=7.6m, X=2m, and umax=0.050m. The

    Distance from tunnel face/tunnel radius = 2/7.6 = 0.26. The Plastic zone

    radius/tunnel radius = 10.5/7.6 = 1.4. From the above plot this gives

    Closure/max closure approximately equal to 0.45. Therefore the closure

    equals (0.45)*(0.050) = 0.023m.

    As computed above, the tunnel floor displaces 0.023m before the support

    is installed.

    Step 2 - Determining the internal pressure factor

    The next step is to determine the internal pressure that yields a

    displacement of 0.023m in the floor of the tunnel. It is important to

    maintain the same location as is used to determine umax, since the

    location of maximum displacement can change depending on the

    magnitude of the internal pressure.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    12/37

    Two Tunnel Lining Design 33-12

    Phase2 v.8.0 Tutorial Manual

    To determine the internal pressure that yields a 0.023m floor

    displacement, well plot the displacement versus stage for a point on the

    floor of the excavation.

    Make sure you have Total Displacement selected as the data type.

    Graphing Displacement in the Floor of the Excavation

    To create the graph:

    Select: GraphGraph Single Point vs. Stage

    1. When asked to enter a vertex, type in the value 25,-7.6 for the

    location and press Enter. This is a point on the floor of the

    excavation.

    2. You will see the Graph Query Data dialog.

    3. Press the Plot button. The following figure shows the plotgenerated by the program. This is a plot of displacement versus

    stage for a point on the floor of the tunnel:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    13/37

    Two Tunnel Lining Design 33-13

    Phase2 v.8.0 Tutorial Manual

    Right-click in the plot and choose the Sampler option. Move the sampler

    by moving the mouse with the left mouse button. Move the sampler untilthe displacement value on the right side of the plot is equal to 0.023m.

    From this plot, you can see that in Stage 4, the wall displacement in the

    floor of the tunnel is 0.023m. This represents an internal pressure factor

    of 0.4 as was defined in the modeler for the induced stress vectordistributed load.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    14/37

    Two Tunnel Lining Design 33-14

    Phase2 v.8.0 Tutorial Manual

    Creating a convergence confinement graph in Excel

    Often you want to create a convergence confinement graph which plots

    displacement versus internal pressure. This is easily done by exporting

    the above graph to Microsoft Excel. This requires that you have Excel

    installed on your computer.

    Right-click in the Graph you just created and choose the Plot in Excel

    option.

    Excel will launch with a plot of stage number versus displacement. You

    can easily modify the plot to change the stage number data to the

    internal pressure factor. A sample of the Excel file for this example is

    included in the Tutorials folder with thePhase2data files.

    The following image shows the convergence-confinement plot in Excel for

    this example. You can see by this plot that an internal pressure factor of

    approximately 0.4 yields the tunnel wall displacement computed above

    for the point of support installation (0.023m).

    NOTE: to obtain a load stage factor that would more precisely match the

    closure at which to apply the liner (0.023m), stage factors of the applied

    load could be iterated and recomputed. However, for the purpose of this

    tutorial, an error of 2mm is acceptable.

    We have now completed steps 1 and 2 as defined in the Problem section

    at the beginning of this tutorial. It is now time to actually design our

    support system.

    From Interpret, switch back to thePhase2Model program by pressing

    the Model button on the toolbar.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    15/37

    Two Tunnel Lining Design 33-15

    Phase2 v.8.0 Tutorial Manual

    Model

    You should now be in thePhase2Model program with the 11 stage model

    you created above loaded into the program.

    We will use this file and modify it to do the support design.

    Project Settings

    Open the Project Settings dialog from theAnalysis menu and select

    the Stages tab. Change the name of Stage 1 to Original In-situ. Change

    the name of Stage 2 to Initial Stage. Change the name of Stage 4 to

    Tunnel Relaxation. Change the name of Stage 11 to Support Installed.

    The dialog should look like this:

    Now delete all other stages except these three stages (i.e. stages

    3,5,6,7,8,9,10). Note: you can select multiple stages by scrolling down the

    number column with the left mouse button depressed. Use the Delete

    Stages button to delete the stages. After deleting these stages, the dialog

    should look like:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    16/37

    Two Tunnel Lining Design 33-16

    Phase2 v.8.0 Tutorial Manual

    We chose Stage 4 from the old model because it represents the stage in

    which the internal pressure in the tunnel yields the necessarydeformation before we install the support. Close the dialog by clicking

    OK.

    Make sure the Stage 1 tab is selected. Click the Zoom Excavation button

    on the toolbar.

    You should see the following:

    Click through the stages. Stage 2, the initial stage, should look like:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    17/37

    Two Tunnel Lining Design 33-17

    Phase2 v.8.0 Tutorial Manual

    Note: you can use the LoadingDistributed LoadsEdit Distributed

    Load option to select any of the loads on the boundary to verify that thestage factor is 0.4 for Stage 3.

    Stage 4, the Support Installed stage should have no load on the boundary.

    Setting the Reinforced Concrete Liner Properties

    Now define the liner properties. The properties we enter will correspond

    to a 100 mm thick layer of concrete reinforced with W100X19.3 I-beams

    spaced at 2 meter intervals along the tunnel axis.

    Select: Properties Define Liners

    1. Change the Name of the liner to Tunnel Liner.

    2. Change the Liner Type to Reinforced Concrete.

    3. Click on the Common Types button. You will see theReinforcement database dialog shown below. For the

    Reinforcement, we will select an I-beam from a list of standard

    reinforcement types.

    4. In the Reinforcement database dialog, select the W100 x 19.3 I-beam. Click OK, and the I-beam reinforcement properties will be

    automatically loaded into the Define Liner Properties dialog.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    18/37

    Two Tunnel Lining Design 33-18

    Phase2 v.8.0 Tutorial Manual

    5. In the Define Liner Properties dialog, for the Reinforcement,enter a spacing of 2m.

    6. Enter the properties for the concrete. Thickness=0.1m,Modulus=25000MPa, Poisson Ratio=0.15, Compressive

    Strength=45MPa, Tensile Strength=5MPa. The liner properties

    dialog should look like:

    7. Press OK to save your input and exit the dialog.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    19/37

    Two Tunnel Lining Design 33-19

    Phase2 v.8.0 Tutorial Manual

    Adding a Reinforced Concrete Liner to the Tunnel

    We will now line the tunnel with the liner defined above. First make sure

    that Stage 4, the Support Installed stage, is selected.

    Select: Support Add Liner

    1. You will see the Add Liner dialog. Make sure it looks like thefollowing image. Select OK.

    2. Click and hold the left mouse button, and drag a selection windowwhich encloses the entire excavation. Release the left mouse

    button. Notice that all excavation line segments are selected.

    3. Right-click the mouse and select Done Selection, or just press theEnter key. The entire tunnel will now be lined, as indicated bythe thick blue line segments around the excavation boundary (see

    below).

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    20/37

    Two Tunnel Lining Design 33-20

    Phase2 v.8.0 Tutorial Manual

    Click through the stages. Notice how the color of the liner changes from

    light blue in Stages 1, 2, and 3 to dark blue in Stage 4. This indicates thatthe liner is being installed in Stage 4.

    We are now ready to run the analysis.

    Compute

    Before you analyze your model, lets save the file.

    Select: File Save

    Select: Analysis Compute

    ThePhase2Compute engine will proceed in running the analysis. When

    completed, you will be ready to view the results in Interpret.

    Interpret

    From Model, switch to the Interpret program.

    Select: Analysis Interpret

    If any other files are loaded into the Interpret program, close them. Clickon the tab at the bottom of the program window associated with the file

    and use the FileClose menu option to close the file.

    Make sure the Stage 4 tab is selected. Click the Zoom Excavation button

    on the toolbar.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    21/37

    Two Tunnel Lining Design 33-21

    Phase2 v.8.0 Tutorial Manual

    Support Capacity Diagrams

    Support capacity diagrams give the engineer a method for determining

    the factor of safety of a reinforced concrete liner. For a given factor of

    safety, capacity envelopes are plotted in axial force versus moment space

    and axial force versus shear force space. Values of axial force, moment

    and shear force for the liner are then compared to the capacity envelopes.If the computed liner values fall inside an envelope, they have a factor of

    safety greater than the envelope value. So if all the computed liner values

    fall inside the design factor of safety capacity envelope, the factor of

    safety of the liner exceeds the design factor of safety.

    Select: Graph Support Capacity Plots

    The Support Capacity Plot dialog allows you to choose the support

    element (i.e. liner type), the number of envelopes, and the stages from

    which the liner data is taken.

    Use the spin control to increase the number of envelopes to 3. The dialog

    should look like:

    Press OK.

    The following plot is generated. The dark red lines represent the capacity

    envelopes for the 3 factors of safety (1, 1.2, 1.4). Notice that all of the liner

    data points fall well within the 1.4 design factor of safety envelope,

    meaning that they have a factor of safety of greater than 1.4. According to

    this analysis, this liner should not experience cracking or crushing.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    22/37

    Two Tunnel Lining Design 33-22

    Phase2 v.8.0 Tutorial Manual

    Refer to Tutorial 24 for an example of an inadequate liner, and the design

    steps necessary for the selection of an adequate liner. Tutorial 24 alsoexplores some of the options available with support capacity plots.

    Model

    Now that the first tunnel liner has been successfully installed, the second

    tunnel will now be excavated.

    We must add a new set of 10 stages, to repeat the stage factor loading

    procedure used to define the critical deformation for the first tunnel.

    Project Settings

    Open the Project Settings dialog from theAnalysis menu and select

    the Stages tab. Increase the Number of Stages to 14, and insure that the

    stages are added after the Support Installed stage. The dialog should look

    like this:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    23/37

    Two Tunnel Lining Design 33-23

    Phase2 v.8.0 Tutorial Manual

    Close the dialog by clicking OK.

    Excavation

    The tunnel is to be excavated in the second stage so click on the Stage 5tab at the bottom of the screen. Place the mouse pointer inside the left

    excavation boundary and right-click the mouse. From the menu that pops

    up, select theAssign Material > Excavate option.

    The material inside the excavation should now be removed.

    Adding an Internal Pressure to the Excavat ion

    Lets add a distributed load to the newly excavated tunnel in Stage 5,

    with the same initial stage factor sequence as in the case of the first

    tunnel. Insure that the Stage 5 tab is selected at the bottom of the screen.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    24/37

    Two Tunnel Lining Design 33-24

    Phase2 v.8.0 Tutorial Manual

    Select: Loading Distributed Loads Add Uniform Load

    Again, select the Induced stress load option, insure the Stage Load

    checkbox is selected, and select the Stage Factors button.

    In the Stage Factors dialog enter the factors shown in the following

    image:

    Select OK in both dialogs. You will now be asked to pick the boundary

    segments on which the load will be applied.

    Select the excavation line segments to be loaded using the selection

    window.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    25/37

    Two Tunnel Lining Design 33-25

    Phase2 v.8.0 Tutorial Manual

    Click the Zoom Excavation button on the toolbar. You should see the

    following in Stage 2:

    Now click through the stage tabs. You should see the internal pressure

    factor reduce as the stage increases beyond Stage 5.

    We are now ready to run the analysis.

    Compute

    Before you analyze your model, lets save this as a new file called

    Tutorial 33 tunnel 2.fez. (Make sure you select Save As and not Save,

    or you will overwrite the initial file.)

    Select: File Save As

    Save the file as Tutorial 33 tunnel 2.fez.

    Select: Analysis Compute

    ThePhase2Compute engine will proceed in running the analysis. When

    completed, you will be ready to view the results in Interpret.

    Interpret

    From Model, switch to the Interpret program.

    Select: Analysis Interpret

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    26/37

    Two Tunnel Lining Design 33-26

    Phase2 v.8.0 Tutorial Manual

    After you select the Interpret option, the Interpret program starts and

    reads the results of the analysis. You will see the maximum stress, sigma

    1 for the Original In-situ stage. Click on the Stage 5 tab, and compare the

    contours to those on the Support Installed tab. Notice that there is no

    variation of stress between the two stages. This means that the internal

    pressure applied within the second tunnel on the left is equal and

    opposite to the field stress and the model is behaving as if the secondtunnel on the left did not exist.

    Now click the Zoom Excavation button on the toolbar.

    Change the contours to plot Total Displacement using the pull down

    menu in the toolbar. The model for Stage 5 will look like this:

    Lets set the reference stage to the Support Installed stage, to view

    deformation of the rock mass relative to after the installation of the liner

    on the first tunnel on the right.

    Select: Data Stage Settings

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    27/37

    Two Tunnel Lining Design 33-27

    Phase2 v.8.0 Tutorial Manual

    Drag the reference stage slider to the Support Installed stage, and

    select the Displacements Only option from the drop-down menu. Press

    OK.

    Insure that the Stage 5 tab is selected. Model should look like this:

    Step 1 Computing tunnel deformation before support

    installation using the Vlachopoulos and Diederichsmethod

    Switch to the last stage, Stage 14. Look in the lower left corner of the

    program window on the status bar. Youll see that the maximum

    displacement for this stage (relative to the Support Installed stage) is

    again 0.050m. The location of this displacement is in the floor of the

    excavation.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    28/37

    Two Tunnel Lining Design 33-28

    Phase2 v.8.0 Tutorial Manual

    To determine the radius of the plastic zone, first turn on the display of

    yielded elements using the Display Yielded Elements toolbar button.

    Youll see a number of crosses representing elements in the finite element

    analysis that have failed. Zoom Out so that the entire extent of

    failed points is visible (see below).

    The extent of this failed zone represents the extent of the plastic zone

    around the tunnel. To determine the radius of the plastic zone, you can

    use either the measuring tool or the dimensioning tool to measure the

    distance from the center of the tunnel to the perimeter of the

    yielded/plastic zone. In this tutorial well use the measuring tool.

    Select: Tools Add Tool Measure

    Pi ck t he l ocat i on t o measur e f r om[ esc=qui t ] : 0,0Pi ck the l ocat i on t o measur e to [ esc=qui t ] : use the mouse toextend the measuring line vertically until you get to the edge

    of the yield zone, press the left mouse button.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    29/37

    Two Tunnel Lining Design 33-29

    Phase2 v.8.0 Tutorial Manual

    As seen above, the radius of the plastic zone is again, approximately

    10.5m.

    Computing displacement prior to support installation using the Vlachopoulosand Diederichs Method

    Since the maximum displacement and the plastic zone radius are

    equivalent to those values for the first tunnel, we can also conclude that

    the tunnel floor will again experience a displacement of 0.023m before the

    support is installed, without repeating the Vlachopoulos and Diederichs

    Method.

    Step 2 - Determining the internal pressure factor

    The next step is to determine the internal pressure that yields a

    displacement of 0.023m in the floor of the tunnel. It is important to

    maintain the same location as is used to determine umax, since the

    location of maximum displacement can change depending on the

    magnitude of the internal pressure.

    To determine the internal pressure that yields a 0.023m floor

    displacement, well plot the displacement versus stage for a point on the

    floor of the excavation.

    Make sure you have Total Displacement selected as the data type.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    30/37

    Two Tunnel Lining Design 33-30

    Phase2 v.8.0 Tutorial Manual

    Graphing Displacement in the Floor of the Excavation

    To create the graph:

    Select: GraphGraph Single Point vs. Stage

    1. When asked to enter a vertex, type in the value 0,-7.6 for thelocation and press Enter. This is a point on the floor of theexcavation.

    2. You will see the Graph Query Data dialog.

    3. Press the Plot button. The following figure shows the plotgenerated by the program. This is a plot of displacement versusstage for a point on the floor of the tunnel.

    Right-click in the plot and choose the Sampler option. Move the sampler

    by moving the mouse with the left mouse button. Move the sampler until

    the displacement value on the right side of the plot is equal to 0.023m.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    31/37

    Two Tunnel Lining Design 33-31

    Phase2 v.8.0 Tutorial Manual

    From this plot, you can see that in Stage 7, the wall displacement in the

    floor of the tunnel is 0.023m. This again represents an internal pressurefactor of 0.4 as was defined in the modeler for the induced stress vector

    distributed load.

    From Interpret, switch back to thePhase2Model program by pressing

    the Model button on the toolbar.

    Model

    You should now be in thePhase2Model program with the 14 stage model

    you created above loaded into the program.

    We will use this file and modify it to do the support design.

    Project Settings

    Open the Project Settings dialog from theAnalysis menu and select

    the Stages tab. Change the name of Stage 5 to Initial Stage Tunnel 2.

    Change the name of Stage 7 to Tunnel Relaxation Tunnel 2. Change the

    name of Stage 14 to Support Installed Tunnel 2. The dialog should look

    like this:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    32/37

    Two Tunnel Lining Design 33-32

    Phase2 v.8.0 Tutorial Manual

    Now delete all other stages except these three stages, and the stages from

    the installation of the first tunnel (i.e. delete 6,8,9,10,11,12,13). Afterdeleting these stages, the dialog should look like:

    We chose Stage 7 from the old model because it represents the stage in

    which the internal pressure in the tunnel yields the necessary

    deformation before we install the support. Close the dialog by clickingOK.

    Make sure the Initial Stage Tunnel 2 stage tab is selected. Click the

    Zoom Excavation button on the toolbar.

    You should see the following:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    33/37

    Two Tunnel Lining Design 33-33

    Phase2 v.8.0 Tutorial Manual

    Click through the stages. Stage 6, the initial stage for tunnel 2, should

    look like:

    Note: you can use the LoadingDistributed LoadsEdit Distributed

    Load option to select any of the loads on the boundary to verify that thestage factor is 0.4 for Stage 3.

    Stage 7, the Support Installed Tunnel 2 stage should have no load on

    the boundary.

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    34/37

    Two Tunnel Lining Design 33-34

    Phase2 v.8.0 Tutorial Manual

    Adding a Reinforced Concrete Liner to the Tunnel

    Since the liner properties have already been defined for the liner of the

    first tunnel and this liner was adequate, we do not need to redefine liner

    properties.

    First make sure that Stage 7, the Support Installed Tunnel 2 stage, isselected.

    Select: Support Add Liner

    4. You will see the Add Liner dialog. Make sure it looks like thefollowing image. Select OK.

    5. Click and hold the left mouse button, and drag a selection windowwhich encloses the entire excavation. Release the left mouse

    button. Notice that all excavation line segments are selected.

    6. Right-click the mouse and select Done Selection, or just press theEnter key. The entire tunnel will now be lined, as indicated by

    the thick blue line segments around the excavation boundary (see

    below).

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    35/37

    Two Tunnel Lining Design 33-35

    Phase2 v.8.0 Tutorial Manual

    Click through the stages. Notice how the color of the second liner changes

    from light blue in Stages 1 6 to dark blue in Stage 7. This indicates thatthe liner is being installed in Stage 7.

    We are now ready to run the analysis.

    Compute

    Before you analyze your model, lets save the file.

    Select: File Save

    Select: Analysis Compute

    ThePhase2Compute engine will proceed in running the analysis. When

    completed, you will be ready to view the results in Interpret.

    Interpret

    From Model, switch to the Interpret program.

    Select: Analysis Interpret

    If any other files are loaded into the Interpret program, close them. Clickon the tab at the bottom of the program window associated with the file

    and use the FileClose menu option to close the file.

    Make sure the Stage 7 tab is selected. Click the Zoom Excavation button

    on the toolbar. Select Total Displacement as the data type. Your display

    should look like this:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    36/37

    Two Tunnel Lining Design 33-36

    Phase2 v.8.0 Tutorial Manual

    Support Capacity Diagrams

    Lets confirm that our support capacity diagrams again show factors of

    safety being greater than 1.4.

    Select: Graph Support Capacity Plots

    Use the spin control to increase the number of envelopes to 3. Deselect

    the checkboxes for Stages 4 6, so that only the Support Installed

    Tunnel 2 checkbox is selected. The dialog should look like:

  • 7/28/2019 Tutorial 33 Two Tunnel Lining Design

    37/37

    Two Tunnel Lining Design 33-37

    Press OK.

    The following plot is generated:

    Note that the data points on these plots are from both the first and the

    second liner. If you wish to view the data points of a particular liner, you

    can right-click in the plot and select Export Data to Excel.

    Alternatively, to view the support capacity diagrams for just the first

    liner, simply select only the Support Installed stage checkbox in the

    Support Capacity Plot dialog shown above.

    Notice again that all of the liner data points fall well within the 1.4

    design factor of safety envelope, meaning that they have a factor of safety

    of greater than 1.4. According to this analysis, this liner should not

    experience cracking or crushing.

    This concludes the tutorial; you may now exit thePhase2Interpret and

    Phase2Model programs.