protect the environment by ensuring whether to grant planning permission for a project
evaluate the effectiveness of mitigation measures applied to the environment, a program of monitoring and oversight of the project will be implemented.
authorities in charge are the Ministry of Industry Control Department,Ministry of Environment,Ministry of Public Health.
appoint an Environmental Engineer that is responsible for the internal environmentalmanagement and monitoring of the plant
Introduction
Project information
Project informatio
n
Lebanon electricity supply is
earmarked but frequent current interruptions and
by important energy imports.
The existing power plants with their
limited capacities are unable to meet the
demand for electricity which is expected to further grow in the
future. The extension of the power plant in Zouk is an important project for the
national electricity provider EDL towards a
reliable a stable electricity supply in the greater
Beirut area and in Lebanon.
Project description●The area of the Zouk power plant is in close neighbourhood to the highway Beirut Tripoli, therefore a good and fast road accession to the area is given. So, it will not be a problem to a traffic system.
1.Design basis
2.Water supply
and treatment 3.Gaseou
s pollutants and noise emissions
4.Waste water
treatment5.Solid waste
disposal
Condition of existing environment
Description of the relevant physical conditions
-Seismic data-climate -temperature-wind-ambient air quality-noise pollution
-the coastal zone-the mount Lebanon range-bekaa plain-The anti Lebanon range-south lebanon
Description of the relevant biological conditions
NO. IMPACT POSSIBLE EFFECT MITIGATION1.
Traffic/ Transportation
Increase in traffic volume
Temporarily affects. Transport of all plant equipment by road. Keep the traffic slow for safety
2.
Construction labour
Andactivities
Increase in air pollution, noise and
waste quantity
Temporarily affects. Avoiding of dust pollution by periodic watering of site during civil works. Avoiding of noisy activities during the night. Wastewater and
solid waste disposal according to the local regulations
3.
Ambient air quality
Increasing of pollutant concentration
Stack height supports good dispersion and reduces impact on ambient air quality in the vicinity of the plant.
4.
Noise
Plant surrounding Applying noise protection measures in order to meetthe required standard
5.
Wastewater discharge
Pollution of the sea, soil and ground water
Applying of wastewater treatment in order to meet the required standards
6. Solid waste disposal
Pollution of the sea, soil and ground water
The solid waste will be disposed by an authorised local disposal company according to local regulations
7. Socio economic Country and future development
The impact of the project on the local and nationalLebanese socio-economic development can be
assessed as positive and important
Potential IMPACT AND MITIGATION measures
environmental related issues that will be monitored are
• Stack emission monitoring• Internal noise monitoring• Internal waste management• Waste water monitoring• Labour safety• Coordination with local and regional authorities• Power plant related reporting• Cooperation in performing labour/staff training• Ambient air monitoring• Noise monitoring at residential area• Waste management for the total complex
The Zouk Management Board should be responsible for the internal environmental management and monitoring of the plan.
Management and monitoring.
Atmospheric Pollution
Monitoring Plan
• monitored by measuring the emissions of the Zouk power plant and the ambient air quality and meteorological parameters in the area around the plant site
Noise monitoring
• operation phase, noise measurements performed to monitor the noise level within the boundary of the Zouk plant as well as the residential area outside of the plant site.
Water pollution monitoring
• The discharge of waste water from within the Zouk power plant boundary shall be monitored regularly by the Zouk EMG during the operation phase
The monitoring should be done during the construction phase and operation phase.
Public Participation Stage of EIA process Objectives of public involvement
Screening Identification of significant impacts
Scoping Identification of public's interest and values
Identification of priorities for assessment
Encouraging public understanding of the proposed project
Prediction and mitigation The public can contribute local knowledge and values to the prediction,
evaluation and mitigation of impacts
Improvement in quality and acceptability of EIA report
Monitoring Public evaluate impacts that occur and support project environmental
management process
EIA Audit Public contribute to evaluation of quality and acceptability of report.
Public comment on acceptability of project impacts
Public Administration
Ministry of Public Health (MoPH)
Ministry of Environmen
t(MoE)
Local Municipal
Public Representa
tive
Zouk Thermal Power
Generation EIA Report
2- 4 towers will be installed for better electric transmission of power to national grid
As a result, Zouk organisation, local
municipals and public representatives arranged a
consultation meeting to discuss relevant issues and came up with some reliable
solutions.
Public representatives comprises of all level of
communities
Zouk public consultations
Summary of P.ConsultationsZouk community concerns Proposed solution by Zouk
Thermal Org•Sound pollutions•Noise pollutions •Facilitate stable electricity connection for local area. •Accommodate employment opportunity•Plant authority should arrange meeting with local public representative•Water temperature to be maintained at minimum
•To take care of the public safety•Works should be completed as quickly as possible•The electricity should be made available to the people•Reduction in the capacity to the use of HFO •Follow all rules, regulations and standards in the construction of the project.•Contingency plan should be taken to meet any eventual accident
Due to acute shortage of electrical
supply, Zouk Thermal finds need
to cope to consumer’s demand.
There is a NEED in this proposed project
90% of arising impacts are
temporary and has a proper mitigation
plan
Project will result in positive
environmental and economic beneficial
impacts
The completion of this EIA fully meets the MoPH standards and applicable EMP.
Conclusion