202
ENROLLED Page 1 of 202 ACT No. 25 Regular Session, 2014 HOUSE BILL NO. 2 BY REPRESENTATIVE ROBIDEAUX AN ACT 1 To provide with respect to the capital outlay budget and the capital outlay program for state 2 government, state institutions, and other public entities; to provide for the 3 designation of projects and improvements; to provide for the financing thereof 4 making appropriations from certain sources; and to provide for related matters. 5 Be it enacted by the Legislature of Louisiana: 6 Section 1. The following sums or so much thereof as may be necessary are hereby 7 appropriated out of any monies in the state treasury from the sources specified, from federal 8 funds and self-generated revenues belonging to the state of Louisiana and/or collected by 9 boards, commissions, departments, and agencies thereof, all for making capital outlay and 10 for the purposes and in the amounts specified herein for the Fiscal Year commencing July 11 1, 2014, and ending June 30, 2015, subject to the conditions thereafter provided: 12 A project with funding payable from General Obligation Bonds Priority 1 indicates 13 that the funding for the project includes the reauthorization of funding which was previously 14 on a line of credit granted by the State Bond Commission in Fiscal Year 2013-2014. As 15 used in this Section, the term "general obligation bonds" means state general obligation 16 bonds or other evidences of indebtedness payable from the Bond Security and Redemption 17 Fund. The amount set forth in this Section opposite each project, or so much thereof as may 18 be necessary, is hereby appropriated and payable from the proceeds available from the sale 19 of general obligation bonds, unless a different source of funding is indicated. Where such 20 a different source of funding is indicated, the corresponding amount set forth, or so much 21 thereof as may be necessary, is hereby appropriated and payable from the source of funding 22 indicated; provided, however, amounts appropriated and payable from federal funds may be 23

ACT No. 25 - Louisiana State Legislature

Embed Size (px)

Citation preview

ENROLLED

Page 1 of 202

ACT No. 25Regular Session, 2014

HOUSE BILL NO. 2

BY REPRESENTATIVE ROBIDEAUX

AN ACT1

To provide with respect to the capital outlay budget and the capital outlay program for state2

government, state institutions, and other public entities; to provide for the3

designation of projects and improvements; to provide for the financing thereof4

making appropriations from certain sources; and to provide for related matters.5

Be it enacted by the Legislature of Louisiana:6

Section 1. The following sums or so much thereof as may be necessary are hereby7

appropriated out of any monies in the state treasury from the sources specified, from federal8

funds and self-generated revenues belonging to the state of Louisiana and/or collected by9

boards, commissions, departments, and agencies thereof, all for making capital outlay and10

for the purposes and in the amounts specified herein for the Fiscal Year commencing July11

1, 2014, and ending June 30, 2015, subject to the conditions thereafter provided:12

A project with funding payable from General Obligation Bonds Priority 1 indicates13

that the funding for the project includes the reauthorization of funding which was previously14

on a line of credit granted by the State Bond Commission in Fiscal Year 2013-2014. As15

used in this Section, the term "general obligation bonds" means state general obligation16

bonds or other evidences of indebtedness payable from the Bond Security and Redemption17

Fund. The amount set forth in this Section opposite each project, or so much thereof as may18

be necessary, is hereby appropriated and payable from the proceeds available from the sale19

of general obligation bonds, unless a different source of funding is indicated. Where such20

a different source of funding is indicated, the corresponding amount set forth, or so much21

thereof as may be necessary, is hereby appropriated and payable from the source of funding22

indicated; provided, however, amounts appropriated and payable from federal funds may be23

ENROLLEDHB NO. 2

Page 2 of 202

encumbered or expended only to the extent such amounts shall have been committed or1

received. Pursuant to the provisions of R.S. 39:82, funds for planning, acquisition,2

construction, and major repair projects appropriated by this act may be retained until3

completion of the project, even if no bona fide liability exists on the last day of the fiscal4

year. 5

This Act shall constitute the comprehensive state capital outlay budget for the 2014-6

2015 Fiscal Year. Projects set forth which are payable from the proceeds available from the7

sale of general obligation bonds shall have the priorities as indicated. The Request for Line8

of Credit form used by the Attorney General and Bond Counsel in evaluating Louisiana9

Constitutional, Internal Revenue Code, and applicable income tax regulations shall be filed10

with the Commissioner of Administration, State Bond Commission, and State Attorney11

General. No general obligation bonds shall be sold, nor cash lines of credit granted to fund12

any lower priority project prior to the sale of general obligation bonds or the granting of cash13

lines of credit to fund all higher priority projects (the "general rule"), except as hereinafter14

provided. This prohibition against funding a lower priority project shall not apply upon a15

showing of an impossibility or impracticality either to proceed with all unfunded higher16

priority projects or to proceed with the funding of such projects or any part thereof through17

the issuance of general obligation bonds for any reason. Such showing shall be stated in18

reasonable detail in a certificate or certificates signed by the state agency responsible for19

administering the funding, and filed with the Commissioner of Administration and the State20

Bond Commission (hereinafter referred to as "the Commission"). Upon a determination by21

the Commission that proceeding with such a project or the funding thereof through the22

issuance of general obligation bonds is impractical or impossible, the Commission may then23

proceed with the sale of general obligation bonds or the granting of cash lines of credit24

without regard to the priority of the unfunded projects determined to be impossible or25

impractical. 26

Upon recommendation by the state agency responsible for administering the funding,27

if it is determined at any time that proceeding with the project or with the funding thereof28

is no longer impossible or impractical, the State Bond Commission may rescind the29

certificate of impossibility or impracticality and may proceed with the project or with the30

issuance of general obligation bonds or the granting of cash lines of credit to fund the31

ENROLLEDHB NO. 2

Page 3 of 202

project. Alternatively, the Interim Emergency Board (hereinafter referred to as "the Board"),1

upon reviewing certificates as described above and determining that proceeding with such2

project or the funding thereof through the issuance of general obligation bonds is impossible3

or impractical, may designate a lower priority for such project. The Board's determination4

and lower priority designation shall be submitted to the members of the Legislature for their5

approval in accordance with the provisions of Chapter 3-B of Subtitle I of Title 39 of the6

Louisiana Revised Statutes of 1950. In accordance with the provisions of Chapter 3-B of7

Subtitle I of Title 39 of the Louisiana Revised Statutes of 1950, whenever at the written8

request of the appropriate legislators and agency, the Board determines that an adjustment9

to a project description originally set forth in such capital budget adopted by the Legislature10

for a current fiscal year is necessary to correct a mistake in a project description, clarify a11

description, change the scope of a description, or make any other adjustment the Board12

deems necessary to implement the purpose of the project, such adjustment shall become13

effective only upon the approval by majority vote of the elected members of each house of14

the Legislature in the manner provided for in Chapter 3-B of Subtitle I of Title 39 of the15

Louisiana Revised Statutes of 1950. 16

If such approval is granted, notification by the chair or secretary of the Board of the17

results of the balloting shall be transmitted to the State Bond Commission, which may then18

proceed with the sale of general obligation bonds or the granting of cash lines of credit for19

each change approved upon request of the Commissioner of Administration in accordance20

with the general rule. 21

With respect to Priorities 1 through 5, a lower priority project may be moved to a22

higher priority only upon a showing of an emergency or other cause not reasonably23

anticipated by the Legislature, which shall be stated in reasonable detail in a certificate24

signed by the head of the appropriate department, political subdivision, or agency and filed25

with the Commissioner of Administration and the Board. Upon a determination by the26

Board that such project should be moved to a higher priority because of an emergency or27

other cause not reasonably anticipated by the Legislature, the Board shall designate a higher28

priority to the project. The matter then shall be submitted to and be subject to the same29

approval by the members of the Legislature in the manner previously indicated in this30

Section. If such approval is granted, notification by the chair or secretary of the board of the31

ENROLLEDHB NO. 2

Page 4 of 202

change of priority shall be transmitted to the State Bond Commission, which then upon1

request of the Commissioner of Administration, may proceed with the sale of general2

obligation bonds or the granting of cash lines of credit in accordance with the general rule.3

As to projects within a priority, the State Bond Commission acting on requests submitted by4

the Commissioner of Administration shall determine when such project, or phases thereof,5

shall be funded. In making such determination, the State Bond Commission shall consider6

the amount of proceeds of general obligation bonds to be made available in light of money7

and capital market conditions; the expenditure requirements of the project; the time required8

for architectural plans and drawings, public bidding, and site acquisition and preparation;9

availability of receipt of federal monies; litigation affecting the undertaking or completion10

of a project; federal tax laws and regulations regarding the sale of municipal bonds; and11

other items of a similar nature bearing upon the possibility or the necessity to commence a12

project or any particular phase thereof. 13

Any other provision of this Act to the contrary notwithstanding, projects described14

in Priority 5 of this Act shall not be moved to a higher priority except upon one of the15

following conditions: (1) Funding is necessary to complete or additionally fund a project16

located elsewhere in the capital outlay act. Determination of such condition shall be made17

by the head of the appropriate department or agency by means of a certificate to that effect18

filed with the Interim Emergency Board, who shall, by mail ballot, request approval of such19

change and if approved by a majority of each house of the Legislature it shall be funded, or20

(2) unless required by an emergency or other cause not reasonably anticipated by the21

Legislature, to be in accordance with procedures set forth in this Section. However, the State22

Bond Commission may authorize a non-cash line of credit for any project in Priority 5 which23

represents that portion of construction contracts which were let during a previous fiscal year,24

or construction contracts which will be let during the current fiscal year, but which will not25

require cash expenditures during the year. Such non-cash lines of credit, when combined26

with previously sold bonds or with higher priority bonds or lines of credit, or with funds27

appropriated from other sources, will provide sufficient appropriated funds to award28

equipment or construction contracts. Contracts shall not be awarded without approval of the29

Division of Administration. 30

ENROLLEDHB NO. 2

Page 5 of 202

Upon approval by the State Bond Commission, and subject to compliance with its1

policies and procedures and the procedures set forth herein, a line of credit providing for the2

use of funds in anticipation of the sale of general obligation bonds may be granted to the3

appropriate administering agency or department from the Comprehensive Capital Outlay4

Escrow Account, or if there is not a sufficient amount available in such account, from other5

available state cash in the state treasury, for capital improvement projects for which bond6

proceeds are appropriated by a current capital budget, prior to the actual issuance of bonds7

for such projects, unless the attorney general advises that an impediment exists to the valid8

issuance of the bonds on the date such line of credit is granted. 9

All bonds that are to be repaid, in whole or in part, by revenues generated by the10

project shall be designated as "Reimbursement Bonds". The State Bond Commission shall11

enter into such agreements as are necessary to provide that the agency or subdivision, whose12

project is reimbursable, shall pay the bond debt costs into the Bond Security and Redemption13

Fund. Such costs may be paid annually or at the end of the term of the bonds issued as14

determined by the State Bond Commission. 15

Priority 1 general obligation bond funding shall be limited to: 16

(1) Projects and amounts which were previously authorized by Act 24 of the 201317

Regular Session of the Legislature; and which were granted cash lines of credit by the State18

Bond Commission. The bonds to fund these projects were not sold in Fiscal Year 2013-19

2014.20

(2) The reauthorization of the portion of the outstanding Fiscal Year 2013-201421

Priority 5 Non-Cash Lines of Credit for projects which will require cash expenditures in22

Fiscal Year 2014-2015 and therefore must be converted to Cash Lines of Credit in Fiscal23

Year 2014-2015.24

(3) Commitments made in the Higher Education Desegregation Settlement25

Agreement. 26

Priority 2 general obligation bond projects are for the completion of plans and27

specifications, land acquisition, site preparation, or for construction which will begin during28

the fiscal year. It is presently anticipated that the listed projects will require the sale of29

bonds or extension of lines of credit during the fiscal year after adoption of this Act. 30

ENROLLEDHB NO. 2

Page 6 of 202

Priority 3 general obligation bond projects are for the preparation of plans and1

specifications, land acquisition, site preparation, or for construction and shall be limited to2

funding for the portion of construction contracts which will not require cash expenditures3

during the fiscal year. The projects in this category shall be considered future year projects4

in the State's five year capital outlay plan. It is presently anticipated that the listed projects5

will not require the sale of bonds or extension of lines of credit during the fiscal year. 6

Priority 4 general obligation bond projects are for the preparation of plans and7

specifications, land acquisition, site preparation, or for construction and shall be limited to8

funding for the portion of construction contracts which will not require cash expenditures9

during the fiscal year. The projects in this category shall be considered future year projects10

in the State's five year capital outlay plan. It is presently anticipated that the listed projects11

will not require the sale of bonds or extension of lines of credit during the fiscal year. 12

Priority 5 general obligation bond funding shall be limited to funding for the portion13

of construction contracts which will not require cash expenditures during the fiscal year.14

These funds, when combined with previously sold bonds or with higher priority bonds on15

lines of credit, or with funds appropriated from other sources, will provide sufficient16

appropriated funds to award contracts. Non-cash lines of credit shall be required prior to the17

award of these contracts.18

In accordance with the cash management plan adopted pursuant to R.S. 48:251(D)19

and the provisions of Act 161 of the 1998 First Extraordinary Session, the Department of20

Transportation and Development is authorized to enter into contracts or agreements for21

projects approved pursuant to the Highway Priority Program, Airport Construction and22

Development Priority Program, Port Construction and Development Priority Program, and23

Statewide Flood Control Program for projects bid and awarded, authorized, or commenced24

during the fiscal year which do not require cash expenditures for the full contract or25

agreement amount. 26

ENROLLEDHB NO. 2

Page 7 of 202

EXECUTIVE DEPARTMENT1

01/107 DIVISION OF ADMINISTRATION2

(1) Outpatient Clinics in Rapides Parish, Planning and3Construction4(Rapides)5Payable from General Obligation Bonds6

Priority 1 $ 13,600,0007Priority 2 $ 1,399,9008

Total $ 14,999,9009

Provided, however, that $1,399,900 of the Priority 2 appropriations for this project is used10to replace general obligation bond proceeds reappropriated to Department of Education, LSU11Health Sciences Center, Health Care Services Division, University Medical Center in New12Orleans (Orleans) in this Act.13

(493) Local Government Assistance Program14(Statewide)15Payable from General Obligation Bonds16

Priority 1 $ 13,935,00017Priority 2 $ 5,000,00018Priority 5 $ 5,000,00019

Total $ 23,935,00020

(494) Community Water Enrichment Program21(Statewide)22Payable from General Obligation Bonds23

Priority 1 $ 20,905,00024Priority 2 $ 3,000,00025Priority 5 $ 5,000,00026

Total $ 28,905,00027

Provided, however, that all recipients comply with the applicable Department of Natural28Resources rules and regulations, if any, on master meter installation.29

(1308) State Office Buildings Major Repairs, Equipment Replacement, 30and Renovations, Planning and Construction 31(Statewide)32Payable from General Obligation Bonds33

Priority 1 $ 1,950,00034Priority 2 $ 34,20035Priority 5 $ 1,000,00036

Total $ 2,984,20037

Provided, however, that $34,200 of the Priority 2 appropriation for this project is used to38replace general obligation bond proceeds reappropriated to Executive Department, Division39of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,40Gustav and Ike, Planning and Construction (Statewide) in this Act.41

(1326) Exterior Waterproofing at the State Capitol Building,42Planning and Construction43(East Baton Rouge)44Payable from General Obligation Bonds45

Priority 1 $ 4,075,00046

ENROLLEDHB NO. 2

Page 8 of 202

(1351) Former McDonogh School Relocation, Renovations1and Additions, Planning and Construction2(Orleans)3Payable from General Obligation Bonds4

Priority 1 $ 2,000,0005Priority 5 $ 4,000,0006

Total $ 6,000,0007

(1368) Statewide Roofing, Waterproofing, and Related Repairs8and Equipment Replacement Program 9(Statewide)10Payable from General Obligation Bonds11

Priority 1 $ 2,000,00012Priority 2 $ 9,000,00013Priority 5 $ 36,000,00014

Total $ 47,000,00015

Provided, however, that $3,541,100 of the Priority 2 appropriations for this project is used16to replace general obligation bond proceeds reappropriated to Department of Education, LSU17Health Sciences Center, Health Care Services Division, University Medical Center in New18Orleans (Orleans) in this Act and that $120,500 of the Priority 2 appropriation for this19project is used to replace general obligation bond proceeds reappropriated to Executive20Department, Division of Administration, Repairs, Restoration and Replacement for21Hurricanes Katrina, Rita, Gustav and Ike, Planning and Construction (Statewide) in this Act.22

(1369) Shreveport State Office Building Mechanical and23Electrical Renovations24(Caddo)25Payable from General Obligation Bonds26

Priority 1 $ 3,000,00027

Provided, however, the scope of this appropriation is deemed to also include a study of the28feasibility of consolidating state office space in Shreveport into a central downtown location29in accordance with HCR 202 of 2009, prior to proceeding with the mechanical and electrical30renovations.31

(1370) Capitol Complex Acquisitions, Demolitions, Sitework,32Construction and Renovation of Facilities33(East Baton Rouge)34Payable from General Obligation Bonds35

Priority 2 $ 102,40036Priority 5 $ 15,000,00037

Total $ 15,102,40038

Provided, however, that $102,400 of the Priority 2 appropriation for this project is used to39replace general obligation bond proceeds reappropriated to Executive Department, Division40of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,41Gustav and Ike, Planning and Construction (Statewide) in this Act.42

(1371) DPS and ISB Data Centers, Planning, Construction and43Renovations44(East Baton Rouge)45Payable from General Obligation Bonds46

Priority 1 $ 2,750,00047

ENROLLEDHB NO. 2

Page 9 of 202

(1372) Repair, Restoration and Replacement for Hurricanes1Katrina, Rita, Gustav and Ike, Planning, Construction, 2Renovation, and Acquisition3(Statewide)4Payable from General Obligation Bonds5

Priority 1 $ 106,760,0006Priority 2 $ 30,000,0007Priority 5 $ 5,000,0008

Payable from the balance of General Obligation Bond proceeds9previously allocated under the authority of Act 22 of 2001 for10Executive Department, Division of Administration, Capitol Complex11Acquisitions, Demolition, Sitework, Equipment, Planning and12Construction and Renovation of Facilities (East Baton Rouge); and13Act 23 of 2002 for Executive Department, Division of14Administration, Capitol Complex Acquisitions, Demolition,15Sitework, Construction and Renovation of Facilities (East Baton16Rouge); and Act 1013 of 1991 for Executive Department, Division17of Administration, Implement Energy Conservation Measures18(Statewide); and Act 45 of 1994 for Executive Department, Division19of Administration, Energy Conservation Projects, Planning and20Construction (Statewide); and Act 1096 of 1995 for Executive21Department, Division of Administration, Energy Conservation22Projects State Owned Colleges and Hospitals, Construction23(Statewide); and Act 23 of 2002 for Executive Department, Division24of Administration, Americans With Disabilities Act Implementation25For State Facilities, Planning and Construction (Statewide); and Act2624 of 2003 for Executive Department, Division of Administration,27Energy Conservation Projects, Planning and Construction28(Statewide); and Act 24 of 2013 for Executive Department, Division29of Administration, Major Repairs for State Buildings Based on30Statewide Condition Assessment, and Infrastructure, Planning and31Construction (Statewide); and Act 29 of 2008 for Executive32Department, Division of Administration, Major Repairs for State33Buildings Based on Statewide Condition Assessment, and34Infrastructure, Planning and Construction (Statewide); and Act 45 of351995 for Executive Department, Division of Administration,36Americans With Disabilities Act Implementation, Planning and37Construction (Statewide); and Act 1096 of 1995 for Executive38Department, Division of Administration, Americans With Disabilities39Act Implementation, Planning and Construction (Statewide); and Act4029 of 1998 for Executive Department, Division of Administration,41Americans With Disabilities Act Implementation, Planning and42Construction (Statewide); and Act 45 of 1995 for Executive43Department, Division of Administration, Hazardous Material44Abatement Projects, Planning and Construction (Statewide); and Act451096 of 1995 for Executive Department, Division of Administration,46Hazardous Material Abatement Projects, Planning and Construction47(Statewide); and Act 29 of 1998 for Executive Department, Division48of Administration, State Office Buildings Major Repairs, Equipment49Replacement and Renovations, Planning and Construction (Caddo,50East Baton Rouge, Lafayette, Orleans, Ouachita, Rapides, St.51Tammany); and Act 1096 of 1995 for Executive Department,52Division of Administration, Equipment Replacement, Major Repairs,53Planning and Construction (Statewide); and Act 23 of 2012 for54Executive Department, Division of Administration, Statewide55Roofing, Waterproofing, and Related Repairs and Equipment56Replacement Program (Statewide); and Act 29 of 2008 for Executive57Department, Division of Administration, Statewide Roofing,58Waterproofing, and Related Repairs and Equipment Replacement59Program (Statewide); and Act 22 of 2011 for Executive Department,60

ENROLLEDHB NO. 2

Page 10 of 202

Division of Administration, Statewide Roofing, Waterproofing, and1Related Repairs and Equipment Replacement Program (Statewide);2and Act 20 of 1999 for Executive Department, Division of3Administration, Statewide Roofing, Waterproofing, and Related4Repairs and Equipment Replacement Program (Statewide); and Act5by memorandum approved by the commissioner of Administration6pursuant to Section 5 of Act 23 of 2002 dated October 15, 2002 for7LSU-Baton Rouge Renovations to Huey P. Long Field House; and8Act 29 of 1998 for Executive Department, Division of9Administration, Hazardous Material Abatement Projects (Statewide);10and Act 22 of 2001 for Executive Department, Division of11Administration, Technical College Campus Buildings Major Repairs,12Equipment Replacement and Site Work, Planning and Construction13(Statewide); and Act 23 of 2002 for Executive Department, Division14of Administration, Technical College Campus Buildings Major15Repairs, Equipment Replacement and Site Work, Planning and16Construction (Statewide); and Act 29 of 1998 for Executive17Department, Division of Administration, Technical Colleges Campus18Buildings Major Repairs, Equipment Replacement and Site Work,19Planning and Construction (Statewide); and Act by memorandum20approved by the Commissioner of Administration pursuant to Section216 of Act 29 of 1998 dated June 17, 1999 for Hazardous Material22Abatement Projects Statewide, Planning and Construction; and of231999 for Executive Department, Division of Administration,24Hazardous Material Abatement Projects (Statewide); and Act 2 of252004 for Executive Department, Division of Administration, Third26Street Art Block Project, Development, Organization, Planning and27Construction ($23,925,377 Private/Local Match) (East Baton Rouge);28and Act 27 of 2006 for Veterans Affairs Veterans Affairs, Louisiana29State Veterans Cemetery in Vernon, Planning and Construction30(Vernon); and Act 22 of 2001 for Elected Officials Secretary of State,31Old State Capitol Site Improvements, Expansion of Educational32Facilities and Programs, Interior Renovations, Artifact Restoration,33Exhibit Design and Construction (East Baton Rouge); and Act 645 of341993 for Elected Officials Department of Agriculture and Forestry,35Feed and Fertilizer Testing Laboratory Construction and Equipment36Payable to the Louisiana Agricultural Finance Authority (East Baton37Rouge); and Act 23 of 2002 for Cultural, Recreation and Tourism38Office of State Parks, Sam Houston Jones State Park Vacation Cabins39and Visitor Center, Planning and Construction (Calcasieu); and Act4023 of 2002 for Cultural, Recreation and Tourism Office of State41Parks, Los Adaes State Historic Site, Acquisition, Planning and42Construction (Natchitoches); and Act 23 of 2002 for Cultural,43Recreation and Tourism Office of State Parks, Chemin-A-Haut State44Park, Acquisition, Planning, and Construction of New Group Camp,45Vacation Cabins, Visitor Center (Morehouse); and Act 23 of 2002 for46Public Safety and Corrections David Wade Correctional Center,47Water Well Water Treatment Plants, Planning and Construction48(Claiborne); and Act 45 of 1994 for Health and Hospitals New49Orleans Home and Rehabilitation Center, Waterproof Building,50Planning and Construction (Orleans); and Act 853 of 1990 for Health51and Hospitals Charity Hospital of New Orleans, Life Safety52Renovations (Orleans); and Act 645 of 1993 for Health and Hospitals53New Orleans Adolescent Hospital, Planning and Renovation for54JCAHO Safety Requirements for Fire Protection Standards (Orleans);55and Act 23 of 2002 for Health and Hospitals Metropolitan56Developmental Center, Replace HVAC Systems, Planning and57Construction (Plaquemines); and Act 23 of 2002 for Natural58Resources Natural Resources - Office of the Secretary, Atchafalaya59Basin Protection and Enhancement ($25,050,000 Federal and60$5,375,000 Local/Other Match) (Assumption, Iberia, Iberville, Pointe61

ENROLLEDHB NO. 2

Page 11 of 202

Coupee, St. Landry, St. Martin, St. Mary); and Act 1013 of 1991 for1Wildlife and Fisheries Office of Fisheries, Planning and Land2Acquisition and Construction of New Fish Hatchery (Statewide); and3Act 23 of 2002 for Education Southern University Baton Rouge, FG4Clark Activity Center Major Repairs, Planning and construction (East5Baton Rouge); and Act 23 of 2002 for Education LSU Baton Rouge,6Wetlands Resources and Environment Sciences Facilities, Planning7and Construction (East Baton Rouge); and Act 23 of 2002 for8Education LSU Health Sciences - Shreveport, Fire Alarm9Replacement and Life Safety Modifications, Hospital and Medical10School, Planning and Construction (Caddo); and Act 22 of 2001 for11Education Southern University Baton Rouge, Scott's Bluff Erosion12Control ($544,000 Federal Match) (East Baton Rouge); and Act 2113of 2000 for Education University of LA System Board, Higher14Education Campus Master Planning (Statewide); and Act 22 of 200115for Education Nicholls State University, Elkins East Renovation and16Addition, Planning and Construction, Furniture and Equipment17(Lafourche); and Act 45 of 1994 for Education Grambling State18University, New Health, Physical Education and Recreation Building,19Planning (Lincoln); and Act 1013 of 1991 for Education University20of LA - Monroe, Planning for New Library Building (Ouachita); and21Act 45 of 1996 for Education University of LA - Monroe, New22Library Building, Construction (Ouachita); and Act 28 of 1997 for23Education University of LA - Monroe, New Library Building,24Construction (Ouachita); and Act 23 of 2002 for Education25Northwestern State University, Morrison Hall and Family &26Consumer Science Buildings, Renovation, Planning, Construction,27Furniture and Equipment (Natchitoches); and Act 645 of 1993 for28Education Nunez Community College, Land Acquisition (St.29Bernard); and Act 21 of 2000 for Education River Parishes30Community College, Acquisition of Equipment and Library31Resources (Ascension); and Act 22 of 2001 for Education LCTCS32Board of Supervisors, Petroleum Processing Technology Equipment33Acquisitions (Multiple); and Act 22 of 2001 for Education LA Tech34College - T. H. Harris Campus, Property Acquisition (St. Landry);35and Act 27 of 2006 for Terrebonne Levee & Conservation District,36Barrier Plan for Terrebonne, Lafourche, Assumption and St. Mary,37Planning and Construction Providing Flood Protection and Interior38Drainage, Planning and Construction ($280,000 Local Match)39(Multiple); and Act 2 of 2004 for Madison Parish Port, Railroad40Rehabilitation/Improvement and New Rail Spur for Avondale41Facility, and Improvements Required for Levee Raising Including42Raise Rail, Road Utilities ($221,000 Local Match; $2,570,00043Federal Match) (Madison); and Act 2 of 2004 for Morgan City44Harbor & Term District, Atchafalaya River, Bayou Chene, Bayou45Bouef, and Bayou Black Deepening Project Feasibility Study46(Statewide); and Act 2 of 2004 for Jefferson Parish Port District,47Bayou Segnette Harbor, Planning and Construction ($250,000 Local48Match) (Jefferson); and Act 2 of 2004 for Iberia Parish, Acadiana49Fairgrounds Conference Center, Fairgrounds, Sugarena RV Park, and50Rally Park, Acquisitions, Infrastructure, Planning and Construction51(Non-State Match Required) (Iberia); and Act 27 of 2006 for52Iberville Parish, Highway 1148 Extension, Planning and Construction53($1,240,000 Local Match) (Statewide); and Act 21 of 2010 for54Jefferson Parish, Terry Parkway Drainage Between Carol Sue Drive55and Industry Canal ($500,000 Local Match) (Jefferson); and Act 2156of 2010 for Lafayette Parish, Kaliste Saloom Widening (Lafayette);57and Act 23 of 2002 for Lasalle Parish, Boat Ramp and Ball Park,58Planning and Construction (Lasalle); and Act 27 of 2006 for59Plaquemines Parish, Plaquemines Drainage Pumping Station, Belle60Chase No. 1 Improvements, Planning and Construction61

ENROLLEDHB NO. 2

Page 12 of 202

(Plaquemines); and Act 21 of 2010 for St. Martin Parish, I-101Frontage Road, LA 328-LA 347, Planning and Design (St. Martin);2and Act 2 of 2004 for St. Mary Parish, St. Mary Community Action3Agency Office Additions and Modifications, Planning and4Construction ($200,000 Local Match) (St. Mary); and Act 27 of 20065for St. Mary Parish, New Hospital in Franklin for Hospital Service6District 1, Planning and Construction ($8,200,000 Local Match) (St.7Mary); and Act 2 of 2004 for Alexandria, Implementation of Urban8Master Plan, Acquisition, Parking and Streetscape ($2,000,000 Local9Match) (Rapides); and Act 20 of 2009 for Baton Rouge,10Signage/Visitor's Amenities Program ($500,000 Federal Match11and/or Non-State Match) (East Baton Rouge); and Act 2 of 2004 for12Baton Rouge, Signage/Visitor's Amenities Program ($500,00013Federal Match and/or Non-State Match) (East Baton Rouge); and Act1427 of 2006 for Baton Rouge, Riverside Centroplex Arena and15Theatre Renovation, Exhibition Center Expansion, Parking Facilities16and Street Realignment, Planning and Construction ($28,500,00017Local Match) (East Baton Rouge); and Act 21 of 2010 for Fordoche,18Potable Water Improvements Deep Water Well and One Elevated19Water Storage Tank, Planning and Construction (Pointe Coupee); and20Act 2 of 2004 for Franklin, West St. Mary Civic & Convention21Center, Planning and Construction ($5,000,000 Local Match) (St.22Mary); and Act 2 of 2004 for Franklinton, Jones Creek Flood23Control, Planning and Construction (Washington); and Act 2 of 200424for Monroe, Northeast Louisiana Children's Museum Building25acquisition and Renovation, Planning and Construction ($160,00026Local Match) (Ouachita); and Act 27 of 2006 for Morse, Installation27of a Water Treatment Plant, Planning and Construction (Acadia); and28Act 2 of 2004 for New Orleans, Danzinger Bridge Ramps, Planning29and Construction (Orleans); and Act 2 of 2004 for New Orleans,30Gilbert Park/Carrollton Playground Boosters, Inc Improvements,31Planning and Construction ($300,000 Local Match) (Orleans); and32Act 2 of 2004 for Opelousas, Drainage Improvements to Bayou33Yarbor, Planning and Construction (St. Landry); and Act 21 of 201034for Parks, Municipal Complex, Planning and Construction (St.35Martin); and Act 23 of 2002 for Rayne, Rayne RV Park36Improvements, Planning and Construction (Acadia); and Act 27 of372006 for Vidalia, Vidalia Industrial Park Development, Planning and38Construction ($16,710,800 Local, Federal, Other, and In-Kind Match39to be provided in phases as indicated in the capital outlay request)40(Concordia); and Act 21 of 2000 for Vidalia, River Front41Development Project, Design and Construction of Facilities42Infrastructure ($1,343,000 In-Kind Local Match) (Concordia); and43Act 2 of 2004 for Vidalia, River Front Development and Visitor44Welcome Center, Design, and Construction of Facilities and45Infrastructure ($1,343,000 In-Kind Match) (Concordia); and Act 2746of 2006 for Vidalia, River Front Development and Visitor Welcome47Center, Design, and Construction of Facilities and Infrastructure48($1,343,000 In-Kind Match) (Concordia); and Act 27 of 2006 for49Jean Lafitte, Lafitte Drainage Willie Mae Subdivision, Planning and50Construction (Jefferson); and Act 27 of 2006 for St. Gabriel, Civic51Center, Planning and Construction (Local match Required)52(Iberville); and Act 23 of 2002 for New Orleans Museum of Art,53Improvements and Acquisitions ($500,000 Local/Federal Match)54(Orleans); and Act 2 of 2004 for New Orleans City Park, Botanical55Garden Conservatory Expansion, Planning and Construction56($750,000 Local Match) (Orleans); and Act 27 of 2006 for Arts57Council of New Orleans, Louisiana Artists Guild Arts Incubator,58Planning and Construction ($6,321,375 Local Match) (Orleans); and59Act 21 of 2000 for McKinley High School Alumni, Old McKinley60High Community Center on Thomas Delpit Drive in the City of61

ENROLLEDHB NO. 2

Page 13 of 202

Baton Rouge, Planning and Construction (East Baton Rouge); and1Act 27 of 2006 for McKinley High School Alumni, Old McKinley2High Alumni Community Center, Planning, Construction, Land3acquisition, Preservation, Restructure, and Renovation of Historic4Community Structure (Supplemental Funding) (East Baton Rouge);5and Act 20 of 1999 for Carrollton Comm. Econ. Dev., Renovations6for Carrollton Community Center, Planning and Construction7(Orleans); and Act 28 of 2007 for District 2 Enhancement8Corporation, Health Clinics (Orleans); and Act 28 of 2007 for9District 2 Enhancement Corporation, Eastern New Orleans10Community Center (Orleans); and Act 2 of 2004 for Republic of11West Florida Museum, Acquisition of Old McKowen High School,12Planning and Construction (East Feliciana); and Act 27 of 2006 for13Louisiana Yambilee, Louisiana Yambilee Building, Planning and14Construction, Restoration and/or Remodeling to the Yamatorium and15Facilities (St. Landry); and Act 2 of 2004 for Acadiana Arts Council,16Acadiana Center for the Arts, Acquisition, Planning and Renovation17($1,591,000 Cash and In-Kind Local Match) (Lafayette); and Act 2118of 2010 for Foundation for Science and Math Education, A Model19for A 21st Century Workforce Development Urban High School -20New Orleans Science and Mathematics High School, Planning and21Construction and Land Acquisition22(Orleans) $18,302,53023

Payable from the balance of State General Fund (Direct) previously24allocated under the authority of Act 45 of 1996 for Executive25Department Division of Administration, Statewide Roofing and26Waterproofing Projects (Statewide); and Act 479 of 1997 for Culture,27Recreation, and Tourism Office of State Parks, Lake Bruin State Park28Land Acquisition (Tensas); and Act 23 of 2002 for Westwego, Food29Bank Center, Planning and Construction ($50,000 Local Match)30(Jefferson); and Act 28 of 1997 for New Orleans Bus. & Industrial31District, Enterprise Park, Land, Roads, Infrastructure Improvement,32Planning and Construction (Orleans); and Act 27 of 2006 for Abita33Springs, Abita Springs - Trailhead, Planning and Construction (St.34Tammany); and Act 27 of 2006 for Bossier Parish, Bossier Parish -35Moore Road Reconstruction, Planning and Construction (Bossier);36and Act 27 of 2006 for St Tammany Art Association, St. Tammany37Art Association Safety Code Upgrade, Planning and Construction (St.38Tammany); and Act 203 of 2007 for Economic Development Office39of Business Development, DED New Orleans Port Cold Storage40Facility, Planning & Construction 41(Orleans) $ 837,36342

Payable from the balance of State General Fund Non-Recurring43Revenues previously allocated under the authority of Act 20 of 200944for McNeese State University, Fieldhouse Renovations and Addition45(Calcasieu); and Act 23 of 2002 for Iberia Parish, Acadiana46Fairgrounds and Sugarena RV Park, Acquisition, Infrastructure,47Planning and Construction (Iberia); and Act 2 of 2004 for Breaux48Bridge, Water Line Extension, Planning and Construction (St.49Martin); and Act 23 of 2002 for New Orleans, Behrman Park50Improvements, Planning and Construction (Orleans); and Act 23 of512002 for Westwego, Food Bank Center, Planning and Construction52($50,000 Local Match) (Jefferson); and Act 23 of 2002 for Jean53Lafitte, Lafitte Street Drainage, Planning and Construction54(Jefferson); and Act 23 of 2002 for Jean Lafitte, Lafitte Drainage55Willie Mae Subdivision, Planning and Construction56(Jefferson) $ 91,88157Total $ 160,991,77458

ENROLLEDHB NO. 2

Page 14 of 202

(1373) Louisiana Clerks of Court Data Networking System,1Planning, Construction and Acquisition2(Statewide)3Payable from General Obligation Bonds4

Priority 5 $ 500,0005

(1374) Statewide Building Condition Assessments6(Statewide)7Payable from General Obligation Bonds8

Priority 5 $ 1,435,0009

(1376) Americans With Disabilities Act Implementation for10State Facilities, Planning and Construction11(Statewide)12Payable from General Obligation Bonds13

Priority 2 $ 3,729,90014Priority 5 $ 2,000,00015

Total $ 5,729,90016

Provided, however, that $3,332,800 of the Priority 2 appropriations for this project is used17to replace general obligation bond proceeds reappropriated to Department of Education, LSU18Health Sciences Center, Health Care Services Division, University Medical Center in New19Orleans (Orleans) in this Act and that $397,100 of the Priority 2 appropriation for this20project is used to replace general obligation bond proceeds reappropriated to Executive21Department, Division of Administration, Repairs, Restoration and Replacement for22Hurricanes Katrina, Rita, Gustav and Ike, Planning and Construction (Statewide) in this Act.23

(1377) Major Repairs for State Buildings Based on Statewide24Condition Assessment, and Infrastructure, Planning and25Construction26(Statewide)27Payable from General Obligation Bonds28

Priority 1 $ 32,135,00029Priority 2 $ 10,000,00030Priority 5 $ 79,575,00031

Total $ 121,710,00032

Provided, however, that $4,493,282 of the Priority 2 appropriations for this project is used33to replace general obligation bond proceeds reappropriated to Department of Education, LSU34Health Sciences Center, Health Care Services Division, University Medical Center in New35Orleans (Orleans) in this Act and that $355,738 of the Priority 2 appropriation for this36project is used to replace general obligation bond proceeds reappropriated to Executive37Department, Division of Administration, Repairs, Restoration and Replacement for38Hurricanes Katrina, Rita, Gustav and Ike, Planning and Construction (Statewide) in this Act.39

(1378) Hazardous Material Abatement Projects40(Statewide)41Payable from General Obligation Bonds42

Priority 2 $ 211,20043Priority 5 $ 2,000,00044

Total $ 2,211,20045

Provided, however, that $133,100 of the Priority 2 appropriations for this project is used to46replace general obligation bond proceeds reappropriated to Department of Education, LSU47Health Sciences Center, Health Care Services Division, University Medical Center in New48Orleans (Orleans) in this Act and that $78,100 of the Priority 2 appropriation for this project49is used to replace general obligation bond proceeds reappropriated to Executive Department,50Division of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina,51Rita, Gustav and Ike, Planning and Construction (Statewide) in this Act.52

ENROLLEDHB NO. 2

Page 15 of 202

(1379) Mold Remediation and Indoor Air Quality, Planning1and Construction2(Statewide)3Payable from General Obligation Bonds4

Priority 2 $ 1,199,2005Priority 5 $ 3,000,0006

Total $ 4,199,2007

Provided, however, that $1,199,200 of the Priority 2 appropriations for this project is used8to replace general obligation bond proceeds reappropriated to Department of Education, LSU9Health Sciences Center, Health Care Services Division, University Medical Center in New10Orleans (Orleans) in this Act.11

(1426) Louisiana Cancer Research Center in New Orleans,12Planning and Construction13(Orleans)14Payable from General Obligation Bonds15

Priority 1 $ 12,000,00016Priority 2 $ 3,000,00017

Total $ 15,000,00018

(2069) State Emergency Shelters19(Statewide)20Payable from General Obligation Bonds21

Priority 2 $ 902,10022

Provided, however, that $902,100 of the Priority 2 appropriations for this project is used to23replace general obligation bond proceeds reappropriated to Department of Education, LSU24Health Sciences Center, Health Care Services Division, University Medical Center in New25Orleans (Orleans) in this Act.26

(2070) New Data Center and Data Replication 27Center, Planning and Construction28(Rapides)29Payable from General Obligation Bonds30

Priority 2 $ 86,80031

Provided, however, that $86,800 of the Priority 2 appropriations for this project is used to32replace general obligation bond proceeds reappropriated to Department of Education, LSU33Health Sciences Center, Health Care Services Division, University Medical Center in New34Orleans (Orleans) in this Act.35

(2071) Third Street Art Block Project, Development,36Organization, Planning and Construction37($23,925,377 Local Match)38(East Baton Rouge)39Payable from General Obligation Bonds40

Priority 2 $ 684,90041

Provided, however, that $572,100 of the Priority 2 appropriations for this project is used to42replace general obligation bond proceeds reappropriated to Department of Education, LSU43Health Sciences Center, Health Care Services Division, University Medical Center in New44Orleans (Orleans) in this Act and that $112,800 of the Priority 2 appropriation for this45project is used to replace general obligation bond proceeds reappropriated to Executive46Department, Division of Administration, Repairs, Restoration and Replacement for47Hurricanes Katrina, Rita, Gustav and Ike, Planning and Construction (Statewide) in this Act.48

(2073) Infrastructure for Cluster Development,49Planning and Construction50(Rapides)51Payable from General Obligation Bonds52

Priority 2 $ 7,50053

ENROLLEDHB NO. 2

Page 16 of 202

Provided, however, that $7,500 of the Priority 2 appropriation for this project is used to1replace general obligation bond proceeds reappropriated to Department of Education, LSU2Health Sciences Center Health Care Services Division, University Medical Center in New3Orleans (Orleans) in this Act.4

(2074) Garyville Roadway Improvements,5Planning and Construction6(St. John the Baptist)7Payable from General Obligation Bonds8

Priority 2 $ 254,0009

Provided, however, that $254,000 of the Priority 2 appropriation for this project is used to10replace general obligation bond proceeds, reappropriated to Department of Education, LSU11Health Sciences Center Health Care Services Division, University Medical Center in New12Orleans (Orleans) in this Act.13

(2124) Implement Energy Conservation Measures14(Statewide)15Payable from General Obligation Bonds16

Priority 2 $ 1,629,00017

Provided, however, that $1,629,000 of the Priority 2 appropriation for this project is used to18replace general obligation bond proceeds reappropriated to Executive Department, Division19of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,20Gustav and Ike, Planning and Construction (Statewide) in this Act.21

( ) Land Acquisition for Mitigation22(Richland)23Payable from General Obligation Bonds24

Priority 2 $ 6,000,00025

Pending submittal and approval of a capital outlay budget request pursuant to the provisions26of R.S. 30:112.27

01/109 OFFICE OF COASTAL PROTECTION AND 28RESTORATION29

(913) Morganza to Gulf of Mexico Flood Control Feasibility30Study, Planning, Design, Right of Way and Construction31of Levees, Floodgates and Other Flood Control Systems32($100,000,000 Local Match; $25,000,000 Local In-Kind 33Match; $442,000,000 Federal Match))34(Ascension, Assumption, Iberia, Iberville, Lafourche, 35Pointe Coupee, St. Martin, St. Mary, Terrebonne,36West Baton Rouge)37Payable from General Obligation Bonds38

Priority 1 $ 23,220,00039Priority 5 $ 53,000,00040

Payable from the balance of General Obligation Bond proceeds41previously allocated under the authority of Act 24 of 2013 for42Department of Transportation, Public Improvements, Morganza to43Gulf of Mexico Flood Control Feasibility Study, Planning, Design,44Right of Way and Construction of Levees, Floodgates and Other45Flood Control Systems ($100,000,000 Local Match; $25,000,00046Local In-Kind Match; $442,000,000 Federal Match) (Ascension,47Assumption, Iberia, Iberville, Lafourche, Pointe Coupee, St. Martin,48St. Mary, Terrebonne, West Baton Rouge) $ 2,94549Total $ 76,222,94550

ENROLLEDHB NO. 2

Page 17 of 202

(935) Westbank Hurricane Protection Project, Planning,1Construction, Right of Way and Utilities ($199,000,0002Federal Match and $52,800,000 Local Match)3(Jefferson, Orleans, Plaquemines, St. Charles)4Payable from General Obligation Bonds5

Priority 1 $ 2,595,0006

Payable from the balance of General Obligation Bond 7proceeds previously allocated under the authority 8of Act 24 of 2013 for Department of Transportation, 9Public Improvements, Westbank Hurricane Protection 10Project, Planning, Construction, Right of Way and 11Utilities ($199,000,000 Federal Match and $52,800,000 12Local Match) (Jefferson, Orleans, Plaquemines) $ 95713Total $ 2,595,95714

(1092) Lafitte Area Tidal Protection, Planning and Construction15(Jefferson)16Payable from General Obligation Bonds17

Priority 1 $ 2,000,00018Priority 2 $ 2,000,00019Priority 5 $ 2,000,00020

Total $ 6,000,00021

(1319) Coastal Protection Projects, Planning and Construction 22(Statewide)23Payable from Interagency Transfers $ 394,573,50024Payable from Coastal Protection and Restoration Fund $ 277,821,41825Payable from Federal Funds $ 65,676,34226Total $ 738,071,26027

(1382) Donaldsonville to the Gulf of Mexico Flood Study28($1,100,000 Local Match; $3,500,000 Federal Match)29(Ascension, Assumption, Jefferson, Lafourche, St. 30Charles, St. James, St. John the Baptist)31Payable from General Obligation Bonds32

Priority 1 $ 100,00033

Payable from the balance of General Obligation Bond 34proceeds previously allocated under the authority 35of Act 24 of 2013 for Department of Transportation, 36Public Improvements, Donaldsonville to the Gulf 37of Mexico Flood Study ($1,100,000 Local Match; 38$3,500,000 Federal Match) (Ascension, Assumption, 39Jefferson, Lafourche, St. Charles, St. James, St. John 40The Baptist) $ 79241Total $ 100,79242

01/111 HOMELAND SECURITY AND EMERGENCY 43PREPAREDNESS44

(1384) GOHSEP Building Expansion, Planning and45Construction46(East Baton Rouge)47Payable from General Obligation Bonds48

Priority 1 $ 640,00049Priority 5 $ 4,280,00050

Total $ 4,920,00051

ENROLLEDHB NO. 2

Page 18 of 202

01/112 DEPARTMENT OF MILITARY AFFAIRS1

(166) Readiness Center Replacement, Franklinton, LA,2Planning and Construction3(Washington)4Payable from General Obligation Bonds5

Priority 1 $ 3,435,0006

(168) Statewide Backlog of Maintenance and Repair7(BMAR), Phase 3, and Statewide Infrastructure8Rehabilitation, Phase 39(Statewide)10Payable from General Obligation Bonds11

Priority 1 $ 1,595,00012Priority 5 $ 2,200,00013

Payable from Federal Funds $ 3,000,00014

Payable from the balance of General Obligation Bond proceeds15previously allocated under the authority of Act A101 of for16Executive Department, Department of Military Affairs, Federal Flood17Disaster Recovery/Mitigation (Statewide); and Act DEPT of for18Executive Department, Department of Military Affairs, Federal Flood19Disaster Recovery/Hazard Mitigation, Planning and Construction20(Statewide); and Act 29 of 1999 for Executive Department,21Department of Military Affairs, Infrastructure Rehabilitation,22Planning and Construction (Statewide); and Act 29 of 1999 for23Executive Department, Department of Military Affairs, Lake Charles24Organizational Maintenance Shop, Planning and Construction25(Calcasieu); and Act 20 of 1999 for Executive Department,26Department of Military Affairs, Regional Hazard Mitigation Project,27Planning and Construction (Statewide); and Act 20 of 1999 for28Executive Department, Department of Military Affairs, Infrastructure29Rehabilitation, Planning and Construction (Statewide); and Act 22 of302002 for Executive Department, Department of Military Affairs,31Camp Beauregard Readiness Center Complex, Planning and32Construction (Rapides); and Act 22 of 2002 for Executive33Department, Department of Military Affairs, Gillis Long Multi-Unit34Readiness Center, Planning and Construction (Iberville); and Act 2435of 2003 for Executive Department, Department of Military Affairs,36Upgrade Anti-Terrorism Force Protection, Major Installations and37High Priority Units (Statewide); and Act 23 of 2003 for Executive38Department, Department of Military Affairs, Statewide Readiness39Center Backlog of Maintenance and Repair, Phase 1, and Statewide40Infrastructure Rehabilitation, Phase 4, Planning and Construction41(Statewide) $ 441,25042

Payable from the balance of State General Fund (Direct) previously43allocated under the authority of Act 20 of 1999 for Department of44Military, Regional Hazard Mitigation Project, Planning and45Construction (Statewide); and Act 20 of 1999 for Department of46Military, Armory Backlog of Maintenance and Repair, Planning and47Construction (Statewide) $ 251,10248Total $ 7,487,35249

(169) Camp Minden, Infrastructure, Rehabilitation, Phase 2,50Planning and Construction51(Webster)52Payable from General Obligation Bonds53

Priority 1 $ 2,185,00054Priority 5 $ 3,940,00055

Payable from Federal Funds $ 508,00056Total $ 6,633,00057

ENROLLEDHB NO. 2

Page 19 of 202

(171) Multi-Purpose Machine Gun Range at Camp1Beauregard, Planning and Construction2(Rapides)3Payable from Federal Funds $ 5,924,8004

(1387) State Emergency Warehouse at Camp Villere, Planning5and Construction6(St. Tammany)7Payable from General Obligation Bonds8

Priority 1 $ 3,290,0009

01/124 LOUISIANA STADIUM AND EXPOSITION DISTRICT10

(1391) Bayou Segnette Sports Complex Improvements,11Including Hall B Expansion, Planning and Construction12(Jefferson)13Payable from General Obligation Bonds14

Priority 1 $ 5,705,00015

(1392) Zephyrs Baseball Facilities Repair, Renovation and16Improvement17(Jefferson)18Payable from General Obligation Bonds19

Priority 1 $ 1,520,00020

(1393) Professional Sports Facilities, Planning and21Construction and Lease Hold Improvements22(Jefferson, Orleans)23Payable from General Obligation Bonds24

Priority 1 $ 18,350,00025

Provided that $8,500,000 in expenditures from this appropriation shall be consistent with the26deliverables as enumerated in the Arena Use Agreement and Project Development27Agreement.28

(1399) New Orleans Sports Arena Improvements, Planning29and Construction30(Orleans)31Payable from General Obligation Bonds32

Priority 1 $ 41,500,00033

Expenditures from this appropriation shall be consistent with the deliverables as enumerated34in the Arena Use Agreement and Project Development Agreement.35

(1402) Bayou Segnette Recreation Complex, Land Acquisition, 36Planning and Construction37(Jefferson)38Payable from General Obligation Bonds39

Priority 1 $ 5,500,00040Priority 5 $ 18,100,00041

Total $ 23,600,00042

(1404) Improvements to TPC Louisiana, Planning and43Construction44(Jefferson)45Payable from General Obligation Bonds46

Priority 1 $ 1,400,00047Priority 5 $ 2,600,00048

Total $ 4,000,00049

ENROLLEDHB NO. 2

Page 20 of 202

( ) Improvements to the Superdome1(Orleans)2Payable from General Obligation Bonds3

Priority 5 $ 6,000,0004

DEPARTMENT OF VETERANS AFFAIRS5

03/130 VETERANS AFFAIRS6

(1340) Northeast Louisiana State Cemetery, Planning and7Construction8(Richland)9Payable from General Obligation Bonds10

Priority 1 $ 800,00011

(1353) Fire Alarm/Call System, Planning and Construction12(East Feliciana)13Payable from General Obligation Bonds14

Priority 1 $ 180,00015

(1354) Southeast Louisiana State Cemetery, Planning and16Construction17(St. Tammany)18Payable from General Obligation Bonds19

Priority 1 $ 610,00020

(1990) Southeast Louisiana War Veterans 21Home, Planning and Construction22(St. John the Baptist)23Payable from General Obligation Bonds24

Priority 2 $ 70,70025

Provided, however, that $70,700 of the Priority 2 appropriations for this project is used to26replace general obligation bond proceeds reappropriated to Department of Education, LSU27Health Sciences Center, Health Care Services Division, University Medical Center in New28Orleans (Orleans) in this Act.29

(2072) Northwest Louisiana War Veterans Home,30Planning and Construction31(Bossier)32Payable from General Obligation Bonds33

Priority 2 $ 71,70034

Provided, however, that $71,700 of the Priority 2 appropriations for this project is used to35replace general obligation bond proceeds reappropriated to Department of Education, LSU36Health Sciences Center, Health Care Services Division, University Medical Center in New37Orleans (Orleans) in this Act.38

03/132 NORTHEAST LOUISIANA WAR VETERANS HOME39

(1229) Exterior and Interior Door Replacements40(Ouachita)41Payable from General Obligation Bonds42

Priority 2 $ 220,00043

03/136 SOUTHEAST LOUISIANA WAR VETERANS HOME44

(712) Southeast Louisiana War Veterans Home - Recreational45Activity Building, Planning and Construction46(St. John the Baptist)47Payable from Fees and Self Generated Revenues $ 240,00048

ENROLLEDHB NO. 2

Page 21 of 202

ELECTED OFFICIALS1

04/139 SECRETARY OF STATE2

(954) Louisiana State Exhibit Museum, Planning and3Construction4(Caddo)5Payable from General Obligation Bonds6

Priority 1 $ 195,0007Priority 5 $ 2,250,0008

Total $ 2,445,0009

(1149) Tioga Heritage Park and Museum, 10Planning and Construction11(Rapides)12Payable from General Obligation Bonds13

Priority 2 $ 50,00014

(1355) Old State Capitol Environmental Control Systems,15Planning and Construction16(East Baton Rouge)17Payable from General Obligation Bonds18

Priority 1 $ 1,285,00019

(2129) Eddie Robinson Museum, 20Planning and Construction21(Lincoln)22Payable from General Obligation Bonds23

Priority 2 $ 82,30024

Provided, however, that $82,300 of the Priority 2 appropriations for this project is used to25replace general obligation bond proceeds reappropriated to Department of Education, LSU26Health Sciences Center, Health Care Services Division, University Medical Center in New27Orleans (Orleans) in this Act.28

(1962) Chennault Aviation and Military Museum Hangar29Building and Equipment, Planning and Construction30(Ouachita)31Payable from General Obligation Bonds32

Priority 1 $ 50,00033

04/160 AGRICULTURE AND FORESTRY34

(1356) Louisiana Animal Disease Diagnostic Laboratory,35Planning and Construction36(East Baton Rouge)37Payable from General Obligation Bonds38

Priority 1 $ 3,255,00039

DEPARTMENT OF ECONOMIC DEVELOPMENT40

05/252 OFFICE OF BUSINESS DEVELOPMENT41

(2) Water Conference and Education Center, Planning,42Engineering, Design and Construction 43(East Baton Rouge)44Payable from General Obligation Bonds45

Priority 2 $ 8,400,00046Priority 5 $ 5,000,00047

Payable from Interagency Transfers $ 10,000,00048Total $ 23,400,00049

ENROLLEDHB NO. 2

Page 22 of 202

(1280) Economic Development Award Program For1Infrastructure Assistance (Supplemental Funding)2(Statewide)3Payable from General Obligation Bonds4

Priority 1 $ 27,200,0005Priority 5 $ 10,000,0006

Total $ 37,200,0007

(1284) Capital Improvements Projects to Meet Economic8Development Commitments, Planning, Construction, 9and Equipment10(Statewide)11Payable from General Obligation Bonds12

Priority 1 $ 14,200,00013Priority 2 $ 73,825,00014Priority 5 $ 18,395,00015

Total $ 106,420,00016

(1406) Mega-Project Site Preparation, Planning and17Construction18(Statewide)19Payable from General Obligation Bonds20

Priority 1 $ 41,800,00021Priority 2 $ 12,705,00022

Total $ 54,505,00023

(1407) Homeland Security and Environmental Technical24Center, Acquisition and Renovation, Planning and 25Construction26(East Baton Rouge)27Payable from General Obligation Bonds28

Priority 1 $ 600,00029Priority 2 $ 41,10030

Total $ 641,10031

Provided, however, that $41,100 of the Priority 2 appropriations for this project is used to32replace general obligation bond proceeds reappropriated to Department of Education, LSU33Health Sciences Center, Health Care Services Division, University Medical Center in New34Orleans (Orleans) in this Act.35

(1409) Wet-Lab Business Incubators, Planning and36Construction37(Caddo, East Baton Rouge, Orleans)38Payable from General Obligation Bonds39

Priority 1 $ 7,740,00040

(1422) Aerospace Manufacturing Infrastructure41(Orleans)42Payable from General Obligation Bonds43

Priority 1 $ 60,00044Priority 5 $ 14,200,00045

Total $ 14,260,00046

(1427) Louisiana Digital Computer Facility, Planning and47Construction48(East Baton Rouge)49Payable from General Obligation Bonds50

Priority 1 $ 25,00051

ENROLLEDHB NO. 2

Page 23 of 202

(1955) Bulk Grain Elevator, Rail Spur and Other Related1Infrastructure, Planning and Construction2(Calcasieu)3Payable from General Obligation Bonds4

Priority 1 $ 5,000,0005

DEPARTMENT OF CULTURE, RECREATION AND TOURISM6

06/263 OFFICE OF STATE MUSEUM7

(410) Cabildo Exterior Restoration and Repair, Planning and8Construction9(Orleans)10Payable from General Obligation Bonds11

Priority 1 $ 795,00012Priority 5 $ 600,00013

Total $ 1,395,00014

(411) Presbytere Exterior Restoration and Repair, Planning15and Construction16(Orleans)17Payable from General Obligation Bonds18

Priority 1 $ 700,00019Priority 5 $ 500,00020

Total $ 1,200,00021

(415) Old U. S. Mint Museum Exhibit22(Orleans)23Payable from General Obligation Bonds24

Priority 1 $ 215,00025Priority 5 $ 3,400,00026

Total $ 3,615,00027

(417) Construction of Civil Rights Museum, Planning and28Construction29(Orleans)30Payable from General Obligation Bonds31

Priority 1 $ 615,00032Priority 5 $ 650,00033

Total $ 1,265,00034

(2075) Louisiana Sports Hall of Fame and Natchitoches35State Museum of North Louisiana, Planning and36Construction37(Natchitoches)38Payable from General Obligation Bonds39

Priority 2 $ 21,90040

Provided, however, that $21,900 of the Priority 2 appropriations for this project is used to41replace general obligation bond proceeds reappropriated to Department of Education, LSU42Health Sciences Center, Health Care Services Division, University Medical Center in New43Orleans (Orleans) in this Act.44

06/264 OFFICE OF STATE PARKS45

(276) Tunica Hills State Preservation Area, Acquisition,46Planning and Construction47(West Feliciana)48Payable from General Obligation Bonds49

Priority 1 $ 4,595,00050Priority 5 $ 6,000,00051

Total $ 10,595,00052

ENROLLEDHB NO. 2

Page 24 of 202

(458) Camp Atchafalaya, Acquisition, Planning, Design and1Construction2(St. Martin)3Payable from General Obligation Bonds4

Priority 2 $ 3,900,0005Priority 5 $ 51,730,0006

Total $ 55,630,0007

(460) Louisiana State Arboretum, Planning 8and Construction 9(Evangeline)10Payable from General Obligation Bonds11

Priority 2 $ 22,00012

Provided, however, that $22,000 of the Priority 2 appropriations for this project is used to13replace general obligation bond proceeds reappropriated to Department of Education, LSU14Health Sciences Center, Health Care Services Division, University Medical Center in New15Orleans (Orleans) in this Act.16

(467) Preventive Maintenance/Major Repairs and17Improvements18(Statewide)19Payable from General Obligation Bonds20

Priority 1 $ 6,300,00021

(474) Bayou Segnette State Park, Land Acquisition,22Additional Cabins, Planning and Construction23(Jefferson)24Payable from General Obligation Bonds25

Priority 1 $ 12,820,00026Priority 2 $ 1,504,90027

Total $ 14,324,90028

Provided, however, that $1,504,900 of the Priority 2 appropriations for this project is used29to replace general obligation bond proceeds reappropriated to Department of Education, LSU30Health Sciences Center, Health Care Services Division, University Medical Center in New31Orleans (Orleans) in this Act.32

(477) Bogue Chitto State Park, Land Acquisition, 33Planning and Construction34(Washington)35Payable from General Obligation Bonds36

Priority 2 $ 362,50037

Provided, however, that $362,500 of the Priority 2 appropriations for this project is used to38replace general obligation bond proceeds reappropriated to Department of Education, LSU39Health Sciences Center, Health Care Services Division, University Medical Center in New40Orleans (Orleans) in this Act.41

(479) St. Bernard State Park, Planning and Construction -42Supplemental43(St. Bernard)44Payable from General Obligation Bonds45

Priority 2 $ 66,10046Priority 5 $ 20,00047

Total $ 86,10048

Provided, however, that $66,100 of the Priority 2 appropriations for this project is used to49replace general obligation bond proceeds reappropriated to Department of Education, LSU50Health Sciences Center, Health Care Services Division, University Medical Center in New51Orleans (Orleans) in this Act.52

ENROLLEDHB NO. 2

Page 25 of 202

(480) Poverty Point State Historic Site - Museum/Interpretive1Center and Observatory - Design, Acquisition, Expansion 2(West Carroll)3Payable from General Obligation Bonds4

Priority 2 $ 1,850,0005

(485) Lake D'Arbonne State Park - Event Facility, Planning6and Construction7(Union)8Payable from General Obligation Bonds9

Priority 2 $ 560,00010Priority 5 $ 3,440,00011

Total $ 4,000,00012

(471) South Toledo Bend State Park Emergency Erosion13Controls, Planning and Construction14(Sabine)15Payable from General Obligation Bonds16

Priority 1 $ 1,060,00017

(489) Chemin-A-Haut State Park Acquisition, Planning and18Construction of New Group Camp, Vacation Cabins, 19Visitor Center and Restrooms20(Morehouse)21Payable from General Obligation Bonds22

Priority 1 $ 270,00023Priority 2 $ 498,00024Priority 5 $ 8,000,00025

Total $ 8,768,00026

Provided, however, that $233,000 of the Priority 2 appropriation for this project is used to27replace general obligation bond proceeds reappropriated to Executive Department, Division28of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,29Gustav and Ike, Planning and Construction (Statewide) in this Act.30

(490) Fort DeRussy State Historic Site, Planning,31Development and Acquisitions32(Avoyelles)33Payable from General Obligation Bonds34

Priority 1 $ 150,00035Priority 5 $ 130,00036

Total $ 280,00037

(491) Poverty Point Reservoir State Park Group Camp,38Conference Center, Site Amenities, Acquisition, Planning 39and Construction40(Richland)41Payable from General Obligation Bonds42

Priority 1 $ 4,350,00043Priority 2 $ 1,000,00044Priority 5 $ 2,800,00045

Total $ 8,150,00046

(2012) Palmetto Island State Park Development, 47Planning and Construction48(Vermilion)49Payable from General Obligation Bonds50

Priority 2 $ 995,00051

ENROLLEDHB NO. 2

Page 26 of 202

Provided, however, that $995,000 of the Priority 2 appropriations for this project is used to1replace general obligation bond proceeds reappropriated to Department of Education, LSU2Health Sciences Center, Health Care Services Division, University Medical Center in New3Orleans (Orleans) in this Act.4

(2036) Chicot State Park Replace Cabins and Pool,5Planning and Construction6(Evangeline)7Payable from General Obligation Bonds8

Priority 2 $ 34,0009

Provided, however, that $34,000 of the Priority 2 appropriations for this project is used to10replace general obligation bond proceeds reappropriated to Department of Education, LSU11Health Sciences Center, Health Care Services Division, University Medical Center in New12Orleans (Orleans) in this Act.13

(2057) Fort Pike State Historic Site, 14Planning and Construction15(Orleans)16Payable from General Obligation Bonds17

Priority 2 $ 238,70018

Provided, however, that $238,700 of the Priority 2 appropriations for this project is used to19replace general obligation bond proceeds reappropriated to Department of Education, LSU20Health Sciences Center, Health Care Services Division, University Medical Center in New21Orleans (Orleans) in this Act.22

(2076) Sam Houston Jones State Park Vacation Cabins23and Visitor Center, Planning and Construction24(Calcasieu)25Payable from General Obligation Bonds26

Priority 2 $ 72,30027

Provided, however, that $72,300 of the Priority 2 appropriation for this project is used to28replace general obligation bond proceeds reappropriated to Executive Department, Division29of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,30Gustav and Ike, Planning and Construction (Statewide) in this Act.31

(2077) Los Adaes State Historic Site, 32Acquisition, Planning and Construction33(Natchitoches)34Payable from General Obligation Bonds35

Priority 2 $ 37,50036

Provided, however, that $37,500 of the Priority 2 appropriation for this project is used to37replace general obligation bond proceeds reappropriated to Executive Department, Division38of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,39Gustav and Ike, Planning and Construction (Statewide) in this Act.40

(2078) Poverty Point Reservoir State Park Acquisition, 41Planning and Construction, Supplemental Funding42(Richland)43Payable from General Obligation Bonds44

Priority 2 $ 39,00045

Provided, however, that $39,000 of the Priority 2 appropriations for this project is used to46replace general obligation bond proceeds reappropriated to Department of Education, LSU47Health Sciences Center, Health Care Services Division, University Medical Center in New48Orleans (Orleans) in this Act.49

ENROLLEDHB NO. 2

Page 27 of 202

06/267 OFFICE OF TOURISM1

(637) I-10 Vinton Welcome Center2(Calcasieu)3Payable from General Obligation Bonds4

Priority 1 $ 105,0005Priority 5 $ 2,565,0006

Total $ 2,670,0007

06/A20 NEW ORLEANS CITY PARK8

(532) City Park Botanical Garden - Conservatory and Entrance9Expansion, Planning and Construction10(Orleans)11Payable from Fees and Self Generated Revenues $ 300,00012Payable from Federal Funds $ 182,50013Total $ 482,50014

(1358) City Park Maintenance Complex Improvements,15Planning and Construction16(Orleans)17Payable from General Obligation Bonds18

Priority 1 $ 150,00019Priority 5 $ 2,500,00020

Total $ 2,650,00021

(1359) Splash Park, Planning and Construction22(Orleans)23Payable from General Obligation Bonds24

Priority 1 $ 275,00025Priority 5 $ 4,500,00026

Total $ 4,775,00027

(1360) City Park Golf Complex Improvements, Planning and28Construction29(Orleans)30Payable from General Obligation Bonds31

Priority 1 $ 5,865,00032Priority 5 $ 3,300,00033

Total $ 9,165,00034

(1361) Improvements to Amusement Area at New Orleans35City Park36(Orleans)37Payable from General Obligation Bonds38

Priority 1 $ 1,160,00039

(1362) New Tennis Center Improvements, Planning and40Construction41(Orleans)42Payable from General Obligation Bonds43

Priority 1 $ 50,00044

ENROLLEDHB NO. 2

Page 28 of 202

DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT1

07/270 ADMINISTRATION2

(855) LA 42 (US 61 to LA 44) Widening3(Ascension)4Payable from General Obligation Bonds5

Priority 1 $ 14,985,0006Priority 5 $ 12,000,0007

Total $ 26,985,0008

(856) Essen Lane Widening, I-10 to Perkins Road, Planning,9Utilities, Right of Way and Construction10(East Baton Rouge)11Payable from General Obligation Bonds12

Priority 1 $ 10,850,00013

(857) Cove Lane Interchange and Improvements, Planning14and Construction15(Calcasieu)16Payable from General Obligation Bonds17

Priority 1 $ 1,000,00018Priority 5 $ 19,000,00019

Total $ 20,000,00020

(858) Louisiana Highway 1 Resurfacing - Plaquemine to21White Castle, Planning and Construction22(Iberville)23Payable from General Obligation Bonds24

Priority 1 $ 1,895,00025Priority 5 $ 8,100,00026

Total $ 9,995,00027

(860) Hooper Road Extension and Widening,28Environmental, Planning, Engineering, Right of Way, 29Utilities and Construction 30(East Baton Rouge, Livingston)31Payable from General Obligation Bonds32

Priority 1 $ 2,700,00033

(861) LA 930 Reconstruction34(Ascension)35Payable from General Obligation Bonds36

Priority 1 $ 5,600,00037Priority 2 $ 250,00038Priority 5 $ 2,150,00039

Total $ 8,000,00040

(862) Verot School Road, Construction41(Lafayette)42Payable from General Obligation Bonds43

Priority 2 $ 95,00044Priority 5 $ 24,000,00045

Total $ 24,095,00046

(863) Juban Road (LA 1026) Widening (I-12 to US 190)47(Livingston)48Payable from General Obligation Bonds49

Priority 1 $ 4,500,00050Priority 5 $ 12,000,00051

Total $ 16,500,00052

ENROLLEDHB NO. 2

Page 29 of 202

(864) LA 3034 Improvements1(East Baton Rouge)2Payable from General Obligation Bonds3

Priority 1 $ 1,500,0004Priority 5 $ 10,800,0005

Total $ 12,300,0006

(865) Tarbutton Road I-20 Interchange, Engineering, Right of7Way, Utilities and Construction8(Lincoln)9Payable from General Obligation Bonds10

Priority 1 $ 9,000,00011Priority 5 $ 5,100,00012

Total $ 14,100,00013

(866) LA Hwy 616 (Caldwell Road to LA Hwy 143), 14Planning and Construction15(Ouachita)16Payable from General Obligation Bonds17

Priority 2 $ 5,270,00018Priority 5 $ 16,600,00019

Total $ 21,870,00020

(961) I-20 Interchange Improvement and Kansas-Garrett 21Connector, Planning, Engineering, Environmental, 22and Right of Way Acquisition23($500,000 Local Match; $1,000,000 Federal Match)24(Ouachita)25Payable from General Obligation Bonds26

Priority 1 $ 250,00027

(962) Port of Lake Charles Access Road, Planning and28Construction ($3,500,000 Local Match, $17,500,000 29Federal Match)30(Calcasieu)31Payable from General Obligation Bonds32

Priority 1 $ 750,00033Priority 5 $ 8,250,00034

Total $ 9,000,00035

(964) Intersection Improvement Program, Real Estate36Acquisition, Planning and Construction37(Ascension)38Payable from General Obligation Bonds39

Priority 1 $ 200,00040Priority 5 $ 1,000,00041

Total $ 1,200,00042

(967) I-10, Calcasieu River Bridge, Environmental, Planning,43Engineering, Right of Way, Utilities, Demolition and 44Construction45(Calcasieu)46Payable from General Obligation Bonds47

Priority 2 $ 2,000,00048

(968) Jimmie Davis Bridge Rehabilitation and Lighting,49Planning and Construction50(Bossier, Caddo)51Payable from General Obligation Bonds52

Priority 1 $ 6,385,00053Priority 5 $ 5,050,00054

Total $ 11,435,00055

ENROLLEDHB NO. 2

Page 30 of 202

(969) Pecue Lane/I-10 Interchange, Planning, Design, Rights1of Way, Utilities and Construction2(East Baton Rouge)3Payable from General Obligation Bonds4

Priority 5 $ 11,000,0005

(970) State Streets, Algiers, Planning and Construction6(Orleans)7Payable from General Obligation Bonds8

Priority 1 $ 2,650,0009Priority 2 $ 250,00010Priority 5 $ 1,200,00011

Total $ 4,100,00012

(971) LA 143 to US 165 Connector, Planning, Engineering,13Right of Way, Utilities and Construction14(Ouachita)15Payable from General Obligation Bonds16

Priority 2 $ 3,300,00017Priority 5 $ 30,900,00018

Total $ 34,200,00019

(974) LA 64 Widening from LA 16 to Magnolia Bridge,20Planning and Construction21(Livingston)22Payable from General Obligation Bonds23

Priority 1 $ 400,00024Priority 2 $ 600,00025

Total $ 1,000,00026

(987) LA 1 Improvements, Phase 2, Planning, Engineering,27Right of Way, Utilities and Construction28(Lafourche)29Payable from General Obligation Bonds30

Priority 1 $ 1,000,00031Priority 5 $ 39,000,00032

Total $ 40,000,00033

(991) LA 3102 (Vick Road) Improvements (LA 124 to34Avoyelles/Catahoula Parish Line), Planning and 35Construction36(Catahoula)37Payable from General Obligation Bonds38

Priority 5 $ 3,000,00039

(992) LA 182 Improvements (Iberia Parish Line to LA 670),40Planning and Construction41(St. Mary)42Payable from General Obligation Bonds43

Priority 1 $ 500,00044

(993) Highway 397 in Calcasieu Parish, North and South45Turning Lanes and Rail Spur at Farmers Rice Mill, 46Planning and Construction47(Calcasieu)48Payable from General Obligation Bonds49

Priority 1 $ 400,00050

ENROLLEDHB NO. 2

Page 31 of 202

(994) LA 22 Improvements (LA 16 to Diversion Canal),1Planning and Construction2(Livingston)3Payable from General Obligation Bonds4

Priority 1 $ 500,0005

(1026) Highway Program (Up to $4,000,000 for Secretary's6Emergency Fund)7(Statewide)8Payable from General Obligation Bonds9

Priority 1 $ 2,260,00010Priority 2 $ 505,00011Priority 5 $ 1,995,00012

Payable from Transportation Trust Fund13Regular $ 34,161,95014

Payable from Transportation Trust Fund - Federal $ 668,515,00015

Payable from the balance of General Obligation Bond proceeds16previously allocated under the authority of Act 45 of 1994 for17Department of Transportation and Development, Flood Control and18Water Management, Grand Bayou Dam and Reservoir Construction,19Right of Way, and Utilities (Red River); and Act 45 of 1994 for20Department of Transportation and Development, Flood Control and21Water Management, Poverty Point Reservoir, Planning, Right of22Way, Utilities, and Construction (Richland); and Act 45 of 1994 for23Department of Transportation and Development, Flood Control and24Water Management, Bundicks Lake Levee Control Structure,25Engineering, Plan Preparation, Right of Way, and Construction26(Beauregard); and Act 45 of 1994 for Department of Transportation27and Development, Flood Control and Water Management, Morganza28to Gulf of Mexico Flood Control Planning, Right of Way and29Construction (Ascension, Assumption, Iberville, Lafourche, Point30Coupee, St. Martin, St. Mary, Terrebonne, West Baton Rouge); and31Act 45 of 1994 for Department of Transportation and Development,32Flood Control and Water Management, Comite River Diversion33Channel, Engineering, Construction, Right of Way and Utilities (East34Baton Rouge); and Act 45 of 1994 for Department of Transportation35and Development, Flood Control and Water Management,36Construction of Right of Way Acquisition (East Carroll); and Act 4537of 1994 for Department of Transportation and Development, Flood38Control and Water Management, Hampton Canal/East Natchitoches39Drainage Improvements, Engineering, Utilities, Right of Way, and40Construction (Natchitoches); and Act 24 of 2003 for Department of41Transportation and Development, Flood Control and Water42Management, Rehabilitation and Repair of State-Owned Reservoirs43and Dams (Statewide); and Act 20 of 2009 for Department of44Transportation and Development, Administration, JCT LA 3127 -45Gramercy Bridge West Approach (La. 3213) Construction, Right of46Way, Utilities (St. John the Baptist; and Act 22 of 2001 for47Department of Transportation and Development, Administration,48Common Street (Beauregard Drive-Tank Farm Road), Construction,49Right of Way, and Utilities (Calcasieu); and Act 22 of 2001 for50Department of Transportation and Development, Administration, I-5110, Southern Railroad Underpass to Tulane Avenue, Pumping Station52Installation, Planning and Construction (Orleans); and Act 22 of 200153for Department of Transportation and Development, Administration,54Four Laning U.S. Highway 84 and LA Highway 6 from Vidalia to55Texas Border West of Many, LA, Planning ($1,000,000 Federal56Match) (Catahoula, Concordia, LaSalle, Natchitoches, Sabine,57Winn); and Act 2 of 2004 for Department of Transportation and58Development, Flood Control and Water Management, Turkey Creek59

ENROLLEDHB NO. 2

Page 32 of 202

Lake Improvements, Planning and Construction (Franklin); and Act124 of 2013 for Department of Transportation and Development,2Administration, Highway Program (Up to $4,000,000 for Secretary's3Emergency Fund) (Statewide); and Act 2 of 2004 for Department of4Transportation and Development, Administration, LA Highway 384 -5Surface Improvement, Construction (Calcasieu, Cameron); and Act62 of 2004 for Department of Transportation and Development,7Administration, Robinson Bridge Road Reconstruction (LA Hwy.83265) Construction, Right of Way and Utilities (Rapides); and Act 29of 2004 for Department of Transportation and Development,10Administration, Relocate Hickory Avenue (LA HWY. 48 - 11th11Street) (Mounes) (LA Hwy. 3154) Construction, Right of Way and12Utilities (Jefferson); and Act 24 of 2003 for Department of13Transportation and Development, Flood Control and Water14Management, Morganza to Gulf of Mexico Flood Control Feasibility15Study, Planning, Design, Right of Way and Construction of Levees,16Floodgates and Other Flood Control Systems ($100,000 Local17Match; $25,000,000 Local In-Kind Match; $442,000,000 Federal18Match) (Ascension, Assumption, Iberia, Iberville, Lafourche, Point19Coupee, St. Martin, St. Mary, Terrebonne, West Baton Rouge); and20Act 24 of 2003 for Department of Transportation and Development,21Flood Control and Water Management, Turkey Creek Lake22Improvements, Planning and Construction (Franklin); and Act 2 of232004 for Department of Transportation and Development,24Administration, I-49 from Shreveport to Arkansas Line,25Construction, Right of Way and Utilities (Caddo); and Act 26 of262005 for Department of Transportation and Development,27Administration, I-49 from Shreveport to Arkansas Line, Lafayette to28Westbank Expressway, Construction, Right of Way and Utilities29(Caddo, Lafayette, Iberia, St. Martin, St. Mary, Terrebonne,30Lafourche, St. Charles, Jefferson); and Act 20 of 1999 for31Department of Transportation and Development, Administration,32ALF Access Road, Planning, Right of Way, Utilities and33Construction (West Baton Rouge); and Act 20 of 1999 for34Department of Transportation and Development, Administration,35Common Street (Beauregard Drive-Tank Farm Road), Engineering,36Construction, Right of Way, and Utilities (Calcasieu); and Act 20 of371999 for Department of Transportation and Development,38Administration, Florida Avenue Expressway and Related Projects39Planning, Right of Way, Utilities and Construction 40(Orleans) $ 4,888,14441

Payable from the balance of State General Fund proceeds previously42allocated under the authority of Act 7 of 2008 of Second43Extraordinary Session for Department of Transportation and44Development, Administration, Rehabilitation, Restoration, and45Resurfacing Projects (Statewide); and Act 7 of 2008 of Second46Extraordinary Session for Department of Transportation and47Development, Administration, LA 28 Widening, Vernon Parish Line48to JCT LA 121 (Rapides); and Act 7 of 2008 of Second Extraordinary49Session for Department of Transportation and Development,50Administration, I-12 Widening, US 11 to JCT I-10/I-12/I-59,51Planning and Construction (St. Tammany); and Act 7 of 2008 of52Second Extraordinary Session for Department of Transportation and53Development, Administration, LA 73 Widening, JCT US 61 to JCT54I-10 (Ascension); and Act 7 of 2008 of Second Extraordinary Session55for Department of Transportation and Development, Administration,56Non-Federal Aid Highways Program, Planning and Construction57(Statewide) $ 6,721,94758Total $ 719,047,04159

ENROLLEDHB NO. 2

Page 33 of 202

Provided, however, that the Department of Transportation and Development is authorized1to implement or commence projects approved in this program for Fiscal Year 2014-20152identified for phased funding pursuant to the cash management plan established pursuant to3R.S. 48:251(D), to provide funding for said projects on an as-needed basis by utilizing4unspent cash balances appropriated in prior years’ programs, which funds when combined5with current appropriations will provide sufficient appropriated funds to award contracts.6

Provided, however, that the Department of Transportation and Development shall use the7Priority 1 General Obligation Bonds to administer the Off-System Roads and Bridges Match8Program.9

Provided further, however, that the Department of Transportation and Development shall use10the Priority 2 and Priority 5 General Obligation Bonds for the LA Highway 92 Overlay,11Preservation and Construction (Lafayette) project.12

(1031) Non-Federal Aid Eligible Highway Program 13(Statewide)14Payable from State Highway Improvement Fund $ 18,900,00015

Payable from the balance of General Obligation Bond proceeds16 previously allocated under the authority of Act 20 of 2009 for 17Department of Transportation, Administration, Junction LA Hwy.183127 - Gramercy Bridge West Approach (LA 3213) Construction, 19Right of Way and Utilities (St. John The Baptist) $ 29120Total $ 18,900,29121

(1032) Secretary's Emergency Fund for Bridge Damages,22Other Reimbursements, Local Matching Dollars, Federal 23Funds, and Opportunity Grants Subject to the Provisions 24of R.S. 48:23225(Statewide)26Payable from General Obligation Bonds27

Priority 1 $ 2,500,00028Payable from Interagency Transfers $ 12,500,00029Payable from Fees and Self Generated Revenues $ 25,000,00030Payable from Transportation Trust Fund - Federal $ 25,000,00031Payable from Federal Funds $ 5,000,00032Total $ 70,000,00033

(1052) I-49 from I-220 in the City of Shreveport to Arkansas34State Line, Construction, Right of Way and Utilities35(Caddo)36Payable from General Obligation Bonds37

Priority 1 $ 24,880,00038Priority 5 $ 46,000,00039

Total $ 70,880,00040

(1221) Turn Lanes on US 71 for Emergency Vehicle Staging41Area, Planning, Engineering, Right of Way, Utilities and 42Construction43(Rapides)44Payable from General Obligation Bonds45

Priority 2 $ 1,000,00046

(2132) Evaluation of Regional Freeway System Expansion47(East Baton Rouge, West Baton Rouge)48Payable from General Obligation Bonds49

Priority 2 $ 2,000,00050Priority 5 $ 1,500,00051

Total $ 3,500,00052

ENROLLEDHB NO. 2

Page 34 of 202

Pending submittal and approval of a capital outlay budget request pursuant to the provisions1of R.S. 39:112.2

(2131) LA70/LA22 from I-10 to the Sunshine Bridge, Planning3and Construction4(Ascension, St. James)5Payable from General Obligation Bonds6

Priority 2 $ 2,000,0007Priority 5 $ 2,000,0008

Total $ 4,000,0009

Pending submittal and approval of a capital outlay budget request pursuant to the provisions10of R.S. 39:112.11

(1364) I-12 O'Neal Lane to Walker/Satsuma Widening,12Planning and Construction13(East Baton Rouge, Livingston)14Payable from General Obligation Bonds15

Priority 1 $ 13,750,00016

(1365) Globalplex Intermodal Access Road17(St. John the Baptist)18Payable from General Obligation Bonds19

Priority 1 $ 1,500,00020Priority 5 $ 500,00021

Total $ 2,000,00022

(1366) Highway 23 Elevation for Three Miles of Emergency23Route Flood Protection, Planning and Construction24(Plaquemines)25Payable from General Obligation Bonds26

Priority 1 $ 3,945,00027Priority 5 $ 6,000,00028

Total $ 9,945,00029

(2133) West Side Expressway, Planning, Design, Right of Way, 30Utilities and Construction31(Ascension, Iberville, St. James, St. John the Baptist,32 St. Charles, West Baton Rouge)33Payable from General Obligation Bonds34

Priority 5 $ 1,650,00035

Pending submittal and approval of a capital outlay budget request pursuant to the provisions36of R.S. 39:112.37

( ) Study of Widening of LA 37 (Greenwell Springs Road)38Between Hooper Road and Sullivan Road39(East Baton Rouge)40Payable from General Obligation Bonds41

Priority 5 $ 750,00042

Pending submission and approval of a capital outlay budget request pursuant to the43provisions of R.S. 39:11244

( ) LA 38 and Avenue F Railroad Safety Improvements,45Planning and Construction46(Tangipahoa)47Payable from General Obligation Bonds48

Priority 2 $ 500,00049

Pending receipt and approval of a capital outlay budget request pursuant to the provisions50of R.S. 39:11251

ENROLLEDHB NO. 2

Page 35 of 202

07/274 PUBLIC IMPROVEMENTS1

(640) Statewide Flood Control Program2(Statewide)3Payable from Transportation Trust Fund - Regular $ 8,910,0004

Provided, however, that the Department of Transportation and Development is authorized5to implement or commence projects approved in this program for Fiscal Year 2014-20156identified for phased funding pursuant to the cash management plan established pursuant to7R.S. 48:251(D), to provide funding for said projects on an as-needed basis by utilizing8unspent cash balances appropriated in prior years’ programs, which funds when combined9with current appropriations will provide sufficient appropriated funds to award contracts.10

(652) Mississippi River Levee Raising, Arkansas to Old11River, Planning and Construction12(Avoyelles, Concordia, East Carroll, Madison, 13Pointe Coupee, Tensas)14Payable from General Obligation Bonds15

Priority 1 $ 1,410,00016Priority 5 $ 500,00017

Payable from the balance of General Obligation Bond 18proceeds previously allocated under the authority of 19Act 24 of 2013 for the Department of Transportation 20and Development - Administration for Verot School 21Road, Construction (Lafayette) $ 93,60022Total $ 2,003,60023

(700) Mississippi River Deepening, Phase 3, Planning, Design,24Construction, Rights-of-Way, Relocations and Utilities,25(Federal Match $154,500,000)26(Ascension, East Baton Rouge, Jefferson, Orleans 27Plaquemines, St. Bernard, St. Charles, St. James, 28St. John the Baptist, West Baton Rouge)29Payable from General Obligation Bonds30

Priority 2 $ 1,500,00031

(703) Houma Navigational Canal Deepening Project, Planning32Design, Construction, Rights-of-Ways, Relocations33and Utilities (Federal Match $191,000,000)34(Terrebonne)35Payable from General Obligation Bonds36

Priority 2 $ 1,000,00037

(997) Bayou Dechene Reservoir, Planning, Land Acquisition38and Construction39(Caldwell)40Payable from General Obligation Bonds41

Priority 1 $ 12,000,00042Priority 5 $ 6,000,00043

Total $ 18,000,00044

(998) Lake Bistineau Erosion Remediation, Planning and45Construction46(Bienville)47Payable from General Obligation Bonds48

Priority 5 $ 1,700,00049

ENROLLEDHB NO. 2

Page 36 of 202

(1004) Water Resources Management Program, Studies,1Planning and Construction 2(Statewide)3Payable from General Obligation Bonds4

Priority 2 $ 200,0005Priority 5 $ 1,000,0006

Total $ 1,200,0007

Provided, however, that $200,000 of this appropriation is used for a study for the Morehouse8Soil and Water Conservation District9

Provided, however, that the Department of Transportation and Development prepare and10maintain a Water Resources Management Master Plan along with an annual Program of11projects to support implementation of the Master Plan. The Department of Transportation12and Development shall adopt the necessary rules for proper management of the Master Plan13and Program, with the intended rules subject to the approval of the Joint Legislative14Committee on the Budget prior to adoption. The Master Plan and Program, and any revisions15thereto, are subject to approval of the Joint Legislative Committee on the Budget.16

(1009) Lake D'Arbonne Alternative Spillway, Planning,17Construction and Repairs18(Lincoln, Union)19Payable from General Obligation Bonds20

Priority 5 $ 1,250,00021

(1033) Port Construction and Development Priority Program22(Statewide)23Payable from General Obligation Bonds24

Priority 1 $ 3,600,00025Payable from Transportation Trust Fund - Regular $ 19,700,00026Total $ 23,300,00027

Provided, however, that the Department of Transportation and Development is authorized28to implement or commence projects approved in this program for Fiscal Year 2014-201529identified for phased funding pursuant to the cash management plan established pursuant to30R.S. 48:251(D), to provide funding for said projects on an as-needed basis by utilizing31unspent cash balances appropriated in prior years’ programs, which funds when combined32with current appropriations will provide sufficient appropriated funds to award contracts.33

(1394) Boat Launch Rehabilitation (LA Hwy 42 at Amite River), 34Planning and Construction35(Ascension)36Payable from General Obligation Bonds37

Priority 1 $ 800,00038

07/276 ENGINEERING AND OPERATIONS39

(1011) Capital Project for Ferries Formerly Operated by40CCCD, Planning and Construction41(Jefferson, Orleans, St. Bernard)42Payable from General Obligation Bonds43

Priority 1 $ 1,400,00044

(1029) Motor Vessel and Equipment Drydocking, Repairs,45Various Locations46(Statewide)47Payable from Transportation Trust Fund - Regular $ 1,500,00048

ENROLLEDHB NO. 2

Page 37 of 202

(1035) Facilities Program Major Repairs, Renovations,1Additions, New Facilities, Equipment Replacement at 2Various DOTD Sites, Planning and Construction3(Statewide)4Payable from Transportation Trust Fund - Regular $ 2,000,0005

(2066) CCCD Miscellaneous Bridge Repairs6(Jefferson, Orleans)7

Payable from the balance of Fees and Self-Generated Revenues8previously allocated under the authority of Act 20 of 1999 for9Department of Transportation and Development, Engineering and10Operations, US 90B Structures, Crescent City Connection Bridge No.111, Claiborne Ave. Interchange, and Harvey Canal Bridge, Renewing12Painting Protection (Jefferson, Orleans); and Act 22 of 2001 for13Department of Transportation and Development, Engineering and14Operations, Surface Road Settlement Repairs for Crescent City15Connection Bridges (Orleans); and Act 24 of 2003 for Department of16Transportation and Development, Engineering and Operations,17Renew Paint Protection US 90B Structures (Jefferson, Orleans); and18Act 2 of 2004 for Department of Transportation and Development,19Engineering and Operations, Renew Paint Protection US 90B20Structures (Jefferson, Orleans); and Act 2 of 2004 for Department of21Transportation and Development, Engineering and Operations,22Rehabilitate Decorative Lights on Crescent City Connection and23Harvey Canal Bridges (Jefferson, Orleans); and Act 2 of 2004 for24Department of Transportation and Development, Engineering and25Operations, Intelligent Transportation System for Crescent City26Connection Division, Planning and Construction (Jefferson, Orleans);27and Act 2 of 2004 for Department of Transportation and28Development, Engineering and Operations, CCCD Administrative29Complex, Renovation and Expansion, Planning and Construction30(Orleans); and Act 27 of 2006 for Department of Transportation and31Development, Engineering and Operations, CCCD Administrative32Complex, Renovation and Expansion (Orleans); and Act 28 of 200733for Department of Transportation and Development, Engineering and34Operations, CCCD Concrete, Structural and Drainage Repairs for35Rehabilitation (Jefferson, Orleans); and Act 29 of 2008 for36Department of Transportation and Development, Engineering and37Operations, CCCD Concrete, Structural and Electrical Repairs38Rehabilitation (Jefferson, Orleans); and Act 29 of 2008 for39Department of Transportation and Development, Engineering and40Operations, CCCD Maintenance and Police Building Repairs41(Orleans); and Act 20 of 2009 for Department of Transportation and42Development, Engineering and Operations, CCCD Maintenance and43Police Building Repairs, Vehicle Service Facilities (Orleans); and44Act 20 of 2009 for Department of Transportation and Development,45Engineering and Operations, CCCD Concrete, Structural and46Electrical Repairs Rehabilitation (Jefferson, Orleans); and Act 21 of472010 for Department of Transportation and Development,48Engineering and Operations, CCCD Ferry Dry Docking, Repairs and49Equipment Replacement (Jefferson, Orleans, St. Bernard); and Act5021 of 2010 for Department of Transportation and Development,51Engineering and Operations, CCCD Ferry Facilities Repairs and52Renovations53(Jefferson, Orleans, St. Bernard) $ 4,220,64654

ENROLLEDHB NO. 2

Page 38 of 202

07/277 AVIATION IMPROVEMENTS1

(1034) State Aviation and Airport Improvement Program2(Statewide)3Payable from Transportation Trust Fund-4 Regular $ 28,462,1905

( ) New Orleans Airport Authority, Feasibility Study, 6Interchange Modification Report and Environmental 7Assessment8(Orleans)9Payable from General Obligation Bonds10

Priority 2 $ 1,500,00011Priority 5 $ 2,000,00012

Total $ 3,500,00013

Pending receipt and approval of a capital outlay budget request pursuant to the provisions14of R.S. 39:11215

DEPARTMENT OF PUBLIC SAFETY AND CORRECTIONS16

08/400 ADMINISTRATION17

(222) Statewide Fencing Project, Planning and Construction18(Statewide)19Payable from General Obligation Bonds20

Priority 1 $ 600,00021Priority 5 $ 9,400,00022

Total $ 10,000,00023

08/402 LOUISIANA STATE PENITENTIARY24

(203) Main Prison Shower and Cellblock Plumbing 25Upgrade, Planning and Construction26(West Feliciana)27Payable from General Obligation Bonds28

Priority 1 $ 165,00029Priority 5 $ 1,000,00030

Total $ 1,165,00031

(204) Fire Marshal Health Department Violations, 32Supplemental, Planning and Construction33(West Feliciana)34Payable from General Obligation Bonds35

Priority 1 $ 2,405,00036Priority 2 $ 28,30037Priority 5 $ 2,000,00038

Total $ 4,433,30039

Provided, however, that $28,300 of the Priority 2 appropriations for this project is used to40replace general obligation bond proceeds reappropriated to Department of Education, LSU41Health Sciences Center, Health Care Services Division, University Medical Center in New42Orleans (Orleans) in this Act.43

(1436) Electrical Distribution System Upgrade, Planning and44Construction45(West Feliciana)46Payable from General Obligation Bonds47

Priority 1 $ 300,00048Priority 5 $ 2,680,00049

Total $ 2,980,00050

ENROLLEDHB NO. 2

Page 39 of 202

(2000) Emergency Water Filter System1Replacement, Planning and Construction2(West Feliciana)3Payable from General Obligation Bonds4

Priority 1 $ 2,020,0005

08/403 OFFICE OF JUVENILE JUSTICE6

(350) Swanson Center for Youth - Driveways and Parking7at Columbia, Planning and Construction8(Ouachita)9Payable from General Obligation Bonds10

Priority 2 $ 20,00011

(358) HVAC System Replacement at Columbia, Planning and12Construction13(Ouachita)14Payable from General Obligation Bonds15

Priority 2 $ 180,00016

(1440) Community Based Program, Juvenile Justice17Improvements, Planning, Construction, Renovation, 18Acquisition, and Equipment19(Statewide)20Payable from General Obligation Bonds21

Priority 1 $ 20,000,00022Priority 2 $ 2,600,00023Priority 5 $ 45,400,00024

Total $ 68,000,00025

(1442) Bridge City Center for Youth, Sewer System26Renovation, Planning and Construction27(Jefferson)28Payable from General Obligation Bonds29

Priority 1 $ 235,00030

(2058) Major Repairs and Equipment Replacement,31Planning and Construction32(Statewide)33Payable from General Obligation Bonds34

Priority 2 $ 255,90035

Provided, however, that $255,900 of the Priority 2 appropriations for this project is used to36replace general obligation bond proceeds reappropriated to Department of Education, LSU37Health Sciences Center, Health Care Services Division, University Medical Center in New38Orleans (Orleans) in this Act.39

08/407 WINN CORRECTIONAL CENTER40

(1443) Sanitation Code Violations, Planning and Construction41(Winn)42Payable from General Obligation Bonds43

Priority 1 $ 625,00044

08/408 ALLEN CORRECTIONAL CENTER45

(1444) Sanitation Code Violations, Repair and Upgrade46(Allen)47Payable from General Obligation Bonds48

Priority 1 $ 560,00049

ENROLLEDHB NO. 2

Page 40 of 202

08/409 DIXON CORRECTIONAL INSTITUTE1

(1445) Emergency Generators, Planning and Construction2(East Feliciana)3Payable from General Obligation Bonds4

Priority 1 $ 70,0005Priority 5 $ 650,0006

Total $ 720,0007

08/414 DAVID WADE CORRECTIONAL CENTER8

(1446) Fire Alarm System Renovations, Planning and9Construction10(Claiborne)11Payable from General Obligation Bonds12

Priority 1 $ 185,00013

(2079) Water Well Water Treatment Plants, Planning14and Construction15(Claiborne)16Payable from General Obligation Bonds17

Priority 2 $ 506,40018

Provided, however, that $200,000 of the Priority 2 appropriations for this project is used to19replace general obligation bond proceeds reappropriated to Department of Education, LSU20Health Sciences Center, Health Care Services Division, University Medical Center in New21Orleans (Orleans) in this Act and that $306,400 of the Priority 2 appropriation for this22project is used to replace general obligation bond proceeds reappropriated to Executive23Department, Division of Administration, Repairs, Restoration and Replacement for24Hurricanes Katrina, Rita, Gustav and Ike, Planning and Construction (Statewide) in this Act.25

08/416 RAYBURN CORRECTIONAL CENTER26

(1447) Security Perimeter Fence, Planning and Construction27(Washington)28Payable from General Obligation Bonds29

Priority 1 $ 95,00030Priority 5 $ 2,000,00031

Total $ 2,095,00032

08/419 OFFICE OF STATE POLICE33

(833) State Police, Troop L and Bureau of Investigations,34Planning and Construction35(St. Tammany)36Payable from General Obligation Bonds37

Priority 5 $ 100,00038

(835) Renovate Training Academy, Planning and Construction 39(East Baton Rouge)40Payable from General Obligation Bonds41

Priority 1 $ 3,275,00042Priority 5 $ 13,250,00043

Total $ 16,525,00044

(2080) Crime Lab Expansion,45Planning and Construction46(East Baton Rouge)47Payable from General Obligation Bonds48

Priority 2 $ 37,30049

ENROLLEDHB NO. 2

Page 41 of 202

Provided, however, that $37,300 of the Priority 2 appropriations for this project is used to1replace general obligation bond proceeds reappropriated to Department of Education, LSU2Health Sciences Center, Health Care Services Division, University Medical Center in New3Orleans (Orleans) in this Act.4

08/420 OFFICE OF MOTOR VEHICLES5

(1448) Parking and Utility Tie-In for OMV Veteran's, Planning6and Construction7(Orleans)8Payable from General Obligation Bonds9

Priority 1 $ 545,00010

DEPARTMENT OF HEALTH AND HOSPITALS11

09/304 METROPOLITAN HUMAN SERVICE DISTRICT12

(953) New Mental Health Center for Desire/Florida Mental13Health Clinic, Including the Purchase, Construction or 14Renovation of a New Facility in New Orleans East, 15Planning and Construction16(Orleans)17Payable from General Obligation Bonds18

Priority 1 $ 2,030,00019

(1449) New Mental Health Clinic for New Orleans Behavior,20Social, and Medical Support Detox Clinic, Including 21Expansion and Renovation of the Existing Facility, 22Planning and Construction23(Orleans)24Payable from General Obligation Bonds25

Priority 1 $ 2,995,00026Priority 5 $ 2,500,00027

Total $ 5,495,00028

09/319 VILLA FELICIANA MEDICAL COMPLEX29

(1450) Replace HVAC Systems in Three Patient Buildings,30Planning and Construction31(East Feliciana)32Payable from General Obligation Bonds33

Priority 1 $ 3,460,00034

09/320 OFFICE OF AGING AND ADULT SERVICES35

(888) Repair and Upgrade to Sewer System, Planning and36Construction37(East Feliciana)38Payable from General Obligation Bonds39

Priority 2 $ 285,00040Priority 5 $ 3,140,00041

Total $ 3,425,00042

(890) Water Tower Repairs and Improvements, Planning and43Construction44(East Feliciana)45Payable from General Obligation Bonds46

Priority 1 $ 160,00047

ENROLLEDHB NO. 2

Page 42 of 202

(1451) Replace Fire Alarm and Sprinkler System, Planning1and Construction2(East Feliciana)3Payable from General Obligation Bonds4

Priority 1 $ 220,0005

(1452) Replace Roof and Storm Drains on all Patient6Buildings, Planning and Construction7(East Feliciana)8Payable from General Obligation Bonds9

Priority 1 $ 2,195,00010

09/326 OFFICE OF PUBLIC HEALTH11

(1453) New Office of Public Health Central Laboratory12Facility, Planning and Construction13(Orleans)14Payable from General Obligation Bonds15

Priority 5 $ 1,000,00016

09/330 OFFICE OF MENTAL HEALTH17

(543) Replace Steam Lines/Asbestos Removal, Planning and18Construction19(East Feliciana)20Payable from General Obligation Bonds21

Priority 2 $ 175,00022Priority 5 $ 3,165,00023

Total $ 3,340,00024

(1454) Regional Pharmacies Emergency Power and Backup25HVAC Units to Protect Drug Supplies, Planning and 26Construction27(Orleans)28Payable from General Obligation Bonds29

Priority 1 $ 90,00030

(1455) Roof Replacement - Tyler Mental Health Center,31Planning and Construction32(Lafayette)33Payable from General Obligation Bonds34

Priority 1 $ 1,065,00035

(1456) Emergency Generator for ASSA Forensic Campus,36Planning and Construction37(East Feliciana)38Payable from General Obligation Bonds39

Priority 1 $ 750,00040

(1457) Emergency Generators for Greenwell Springs Campus,41Planning and Construction42(East Baton Rouge)43Payable from General Obligation Bonds44

Priority 5 $ 1,200,00045

ENROLLEDHB NO. 2

Page 43 of 202

09/331 CENTRAL LOUISIANA STATE HOSPITAL1

(239) Electrical System Sub-Station Upgrade2(Rapides)3Payable from General Obligation Bonds4

Priority 1 $ 80,0005Priority 5 $ 2,300,0006

Total $ 2,380,0007

(1979) Expansion of Shreveport Mental Health Center,8Planning and Construction9(Caddo)10Payable from General Obligation Bonds11

Priority 5 $ 100,00012

09/332 EASTERN LOUISIANA MENTAL HEALTH SYSTEM13

(1458) Center Building and Fire Alarm System Renovation14and Restoration, East Louisiana State Hospital, Planning 15and Construction16(East Feliciana)17Payable from General Obligation Bonds18

Priority 1 $ 1,260,00019Priority 5 $ 5,300,00020

Total $ 6,560,00021

(1977) Oakcrest Sprinkler System22(East Feliciana)23Payable from General Obligation Bonds24

Priority 2 $ 400,00025Priority 5 $ 500,00026

Total $ 900,00027

Provided, however, that $400,000 of the Priority 2 appropriations for this project is used to28replace general obligation bond proceeds reappropriated to Department of Education, LSU29Health Sciences Center, Health Care Services Division, University Medical Center in New30Orleans (Orleans) in this Act.31

(2010) Fire Alarm System Replacement for32Ten Buildings, Planning and33Construction34(East Feliciana)35Payable from General Obligation Bonds36

Priority 2 $ 2,551,00037

Provided, however, that $2,551,000 of the Priority 2 appropriations for this project is used38to replace general obligation bond proceeds reappropriated to Department of Education, LSU39Health Sciences Center, Health Care Services Division, University Medical Center in New40Orleans (Orleans) in this Act.41

(2081) Replacement of Emergency Generators42(East Feliciana)43Payable from General Obligation Bonds44

Priority 2 $ 250,40045

Provided, however, that $250,400 of the Priority 2 appropriations for this project is used to46replace general obligation bond proceeds reappropriated to Department of Education, LSU47Health Sciences Center, Health Care Services Division, University Medical Center in New48Orleans (Orleans) in this Act.49

ENROLLEDHB NO. 2

Page 44 of 202

09/333 SOUTHEAST LOUISIANA HOSPITAL1

(1464) Emergency Generator for Children's Complex, SELH,2Planning and Construction3(St. Tammany)4Payable from General Obligation Bonds5

Priority 1 $ 290,0006

(1976) New South Louisiana Human Services Authority7Administrative Building, Land Acquisition, Planning 8and Construction9(Terrebonne)10Payable from General Obligation Bonds11

Priority 5 $ 985,00012

(2082) Fire Alarm System Upgrade Replacement,13Planning and Construction14(St. Tammany)15Payable from General Obligation Bonds16

Priority 2 $ 523,70017

Provided, however, that $523,700 of the Priority 2 appropriations for this project is used to18replace general obligation bond proceeds reappropriated to Department of Education, LSU19Health Sciences Center, Health Care Services Division, University Medical Center in New20Orleans (Orleans) in this Act.21

09/340 OFFICE OF DEVELOPMENTAL DISABILITIES22

(1465) Central Louisiana State Hospital Relocation to23Pinecrest, Planning and Construction24(Rapides)25Payable from General Obligation Bonds26

Priority 1 $ 4,720,00027Priority 5 $ 21,000,00028

Total $ 25,720,00029

09/344 NORTH LAKE SUPPORTS AND SERVICES CENTER30

(529) Installation of Sprinkler Systems/Protection of Beams31(Tangipahoa)32Payable from General Obligation Bonds33

Priority 2 $ 1,145,70034Priority 5 $ 500,00035

Total $ 1,645,70036

Provided, however, that $1,145,700 of the Priority 2 appropriations for this project is used37to replace general obligation bond proceeds reappropriated to Department of Education, LSU38Health Sciences Center, Health Care Services Division, University Medical Center in New39Orleans (Orleans) in this Act.40

(1466) Replace Rooftop Air Conditioning Units on Residential41Homes, Planning and Construction42(Tangipahoa)43Payable from General Obligation Bonds44

Priority 1 $ 2,320,00045

(1467) Replace Cooling Tower, Planning and Construction46(Tangipahoa)47Payable from General Obligation Bonds48

Priority 1 $ 85,00049

ENROLLEDHB NO. 2

Page 45 of 202

(1973) Repairs and Renovation at the North Lake Supports and1Services Center, Planning and Construction2(Tangipahoa)3Payable from General Obligation Bonds4

Priority 5 $ 500,0005

(1975) Replacement of Underground High Temperature Hot6Water System, Planning and Construction7(Tangipahoa)8Payable from General Obligation Bonds9

Priority 2 $ 1,000,00010Priority 5 $ 1,800,00011

Total $ 2,800,00012

Provided, however, that $1,000,000 of the Priority 2 appropriations for this project is used13to replace general obligation bond proceeds reappropriated to Department of Education, LSU14Health Sciences Center, Health Care Services Division, University Medical Center in New15Orleans (Orleans) in this Act.16

(2083) Replacement/Upgrade of Emergency Generators17for Client Homes18(Tangipahoa)19Payable from General Obligation Bonds20

Priority 2 $ 452,30021

Provided, however, that $452,300 of the Priority 2 appropriations for this project is used to22replace general obligation bond proceeds reappropriated to Department of Education, LSU23Health Sciences Center, Health Care Services Division, University Medical Center in New24Orleans (Orleans) in this Act.25

09/347 PINECREST SUPPORTS AND SERVICES CENTER26

(1468) Sprinkler Systems for Residences, Porches and27Walkways, Planning and Construction28(Rapides)29Payable from General Obligation Bonds30

Priority 1 $ 60,00031

DEPARTMENT OF NATURAL RESOURCES32

11/431 OFFICE OF THE SECRETARY33

(287) Atchafalaya Basin Protection and Enhancement34(Federal Match and Local/Sponsor Match)35(Assumption, Avoyelles, Iberia, Iberville, Pointe Coupee, 36St. Landry, St. Martin, St. Mary)37Payable from General Obligation Bonds38

Priority 1 $ 6,150,00039Priority 2 $ 70,20040Priority 5 $ 4,000,00041

Total $ 10,220,20042

Provided, however, that $50,000 of this appropriation will be used to fund House Concurrent43Resolution No. 168 of 2011.44

Further, provided, however, that $70,200 of the Priority 2 appropriations for this project is45used to replace general obligation bond proceeds reappropriated to Department of Education,46LSU Health Sciences Center, Health Care Services Division, University Medical Center in47New Orleans (Orleans) in this Act.48

ENROLLEDHB NO. 2

Page 46 of 202

LOUISIANA WORKFORCE COMMISSION1

14/474 OFFICE OF WORKFORCE DEVELOPMENT2

(1469) Renovations to Louisiana Workforce Commission's3Administrative Headquarters, Planning and Construction4(East Baton Rouge)5Payable from General Obligation Bonds6

Priority 1 $ 2,700,0007

DEPARTMENT OF WILDLIFE AND FISHERIES8

16/512 OFFICE OF THE SECRETARY9

(163) Wildlife and Fisheries Enforcement Training Academy10and Emergency Facility, Planning and Construction11(East Baton Rouge)12Payable from Conservation Fund $ 1,038,72013Payable from Enforcement Emergency Situation Account $ 50,00014Payable from Federal Funds $ 450,00015Total $ 1,538,72016

16/513 OFFICE OF WILDLIFE17

(735) HQ 7 Headquarters Building- Replace Existing HVAC18Equipment19(East Baton Rouge)20Payable from Rockefeller Wildlife Refuge and Game21Preserve Fund $ 878,40022

(736) Woodworth Central Office Complex 23(Rapides)24Payable from General Obligation Bonds25

Priority 2 $ 750,00026Priority 5 $ 12,000,00027

Total $ 12,750,00028

(738) Renovate Residence Dwelling #1 - Dewey Wills, 29Planning and Construction30(LaSalle)31Payable from Conservation Fund $ 59,97632

(747) Renovation to Residence at Pearl River, Planning 33and Construction34(St. Tammany)35Payable from Conservation Fund $ 126,00036

(748) Renovate Bunkhouse at Pearl River, Planning and 37Construction38(St. Tammany)39Payable from Conservation Fund $ 126,00040

(751) Wetland Boardwalk at Floy McElroy WMA, Planning and 41Construction42(Richland)43Payable from Conservation Fund $ 126,00044

(753) Renovate Headquarters/Education Center and Bunkhouse 45Addition at Buckhorn, Planning and Construction46(Tensas)47Payable from Conservation Fund $ 576,00048

ENROLLEDHB NO. 2

Page 47 of 202

(754) New Headquarters and Bunkhouse at Boeuf, Planning and 1Construction2(Caldwell)3Payable from Conservation Fund $ 426,0004

(755) Office and Equipment Shed at Sandy Hollow, Planning 5and Construction6(Tangipahoa)7Payable from Conservation Fund $ 480,0008

(756) Replace Residence for Area Supervisor- South, Richard 9Yancey, Planning and Construction10(Concordia)11Payable from Conservation Fund $ 250,80012

(757) New Headquarters and Bunkhouse at Loggy Bayou, 13Planning and Construction14(Bienville)15Payable from Conservation Fund $ 306,72016

(758) Longleaf Conference/Education/Training Center at Sandy 17Hollow, Planning and Construction18(Tangipahoa)19Payable from Conservation Fund $ 405,00020

(759) Replace Residence for Area Supervisor- North Richard 21Yancey, Planning and Construction22(Concordia)23Payable from Conservation Fund $ 250,80024

(786) Rockefeller Refuge East End Lock Replacement 25(Cameron)26Payable from Rockefeller Wildlife Refuge and Game27Preserve Fund $ 4,000,00028

(789) Rockefeller Refuge Price Lake Shoreline Protection 29(Cameron)30Payable from Rockefeller Wildlife Refuge and Game31Preserve Fund $ 5,000,00032

(790) Rockefeller Refuge Price Lake Levee Repairs 33(Cameron)34Payable from Rockefeller Wildlife Refuge and Game35Preserve Fund $ 216,00036

(816) Monroe Headquarters, District 2, Planning and37Construction38(Ouachita)39Payable from General Obligation Bonds40

Priority 2 $ 450,00041Priority 5 $ 8,000,00042

Total $ 8,450,00043

(818) Research Facility and Bunkhouse - Sherburne, 44Planning and Construction45(Iberville)46Payable from Conservation Fund $ 78,00047

ENROLLEDHB NO. 2

Page 48 of 202

(819) Conservation Education Center Sherburne, Planning and 1Construction2(Iberville)3Payable from Conservation Fund $ 100,8004

(822) Site Improvements and Building Replacements at5Marsh Island Refuge 6(Iberia)7Payable from Russell Sage Fund #2 $ 3,500,0008

(824) District 7 Headquarters (Annex) HVAC Replacement 9(East Baton Rouge)10Payable from Rockefeller Wildlife Refuge and Game11

Preserve Fund $ 516,00012

(1108) Region 5/Lake Charles Office, Planning and13Construction14(Calcasieu)15Payable from General Obligation Bonds16

Priority 1 $ 2,900,00017Priority 5 $ 6,100,00018

Total $ 9,000,00019

(1295) White Lake Wetlands Conservation Area Office, Planning 20and Construction21(Vermilion)22Payable from Conservation Fund $ 585,46023

16/514 OFFICE OF FISHERIES24

(592) Booker Fowler Fish Hatchery Renovations, Planning25and Construction26(Rapides)27Payable from Federal Funds $ 2,415,38028

(764) Beechwood Fish Hatchery Pond Improvements 29(Rapides)30Payable from Federal Funds $ 1,500,00031

(767) Grand Isle Marine Lab 7 Bay Boat Shed, Planning and32Construction33(Jefferson)34Payable from Artificial Reef Development Fund $ 321,30035

(768) Huey P. Long Fish Hatchery Boat Storage Building,36Planning and Construction37(St. Tammany)38Payable from Artificial Reef Development Fund $ 435,48039

(769) Louisiana Marine Fisheries Enhancement Research and40Sciences Center 41(Calcasieu, Plaquemines)42Payable from Federal Funds $ 22,000,00043

DEPARTMENT OF EDUCATION44

19/601 LSU BATON ROUGE45

(3) New Residence Hall, Planning and Construction46(East Baton Rouge)47Payable from Revenue Bonds $ 80,450,00048

ENROLLEDHB NO. 2

Page 49 of 202

Provided, however, that this appropriation is in lieu of Revenue Bonds appropriated in Act124 of 2013 to LSU Baton Rouge for New Residence Hall, Planning and Construction2

(8) Patrick F. Taylor Hall Renovations and Expansion,3Planning and Construction4(East Baton Rouge)5Payable from General Obligation Bonds6

Priority 1 $ 12,500,0007Priority 5 $ 42,500,0008

Payable from Fees and Self-Generated Revenues $ 55,000,0009Total $ 110,000,00010

Provided, however, that the Fees and Self Generated Revenues in this appropriation are in11lieu of Fees and Self Generated Revenues appropriated in Act 24 of 2013 to LSU Baton12Rouge for Patrick F. Taylor Hall Renovations and Expansion, Planning and Construction.13

(9) Family Housing Complex, Planning and Construction14(East Baton Rouge)15Payable from Fees and Self Generated Revenues $ 300,00016Payable from Revenue Bonds $ 39,000,00017Total $ 39,300,00018

(10) Nicholson Gateway: Infrastructure Improvements,19Planning and Construction20(East Baton Rouge)21Payable from General Obligation Bonds22

Priority 1 $ 2,500,00023Priority 5 $ 22,500,00024

Total $ 25,000,00025

(11) French House Renovation, Acquisition, Planning and26Construction27(East Baton Rouge)28Payable from General Obligation Bonds29

Priority 1 $ 5,100,00030

(12) Evangeline Residence Hall Renovation, Planning and31Construction32(East Baton Rouge)33Payable from Fees and Self Generated Revenues $ 150,00034Payable from Revenue Bonds $ 22,350,00035Total $ 22,500,00036

Provided, however, that the Revenue Bonds in this appropriation are in lieu of Revenue37Bonds appropriated in Act 24 of 2013 to LSU Baton Rouge for Evangeline Residence Hall38Renovation, Planning and Construction39

(14) Student Health Center Renovation and Addition,40Planning and Construction41(East Baton Rouge)42Payable from Fees and Self Generated Revenues $ 4,000,00043Payable from Revenue Bonds $ 23,890,00044Total $ 27,890,00045

(22) Lakeshore House Renovation, Planning and46Construction47(East Baton Rouge)48Payable from Fees and Self Generated Revenues $ 250,00049Payable from Revenue Bonds $ 4,250,00050Total $ 4,500,00051

ENROLLEDHB NO. 2

Page 50 of 202

(1396) South Campus, Land Acquisition1(East Baton Rouge)2Payable from General Obligation Bonds3

Priority 1 $ 2,000,0004Priority 5 $ 2,375,0005

Total $ 4,375,0006

(1397) Renovate Old Engineering Shops for Art Department,7Planning and Construction8(East Baton Rouge)9Payable from General Obligation Bonds10

Priority 1 $ 2,500,00011Priority 5 $ 12,800,00012

Total $ 15,300,00013

(1996) Fire and Emergency Training Institute14(East Baton Rouge)15Payable from General Obligation Bonds16

Priority 2 $ 500,00017

(2084) Music and Dramatic Arts Facilities Renovation18and Addition, Planning and Construction19(East Baton Rouge)20Payable from General Obligation Bonds21

Priority 2 $ 258,30022

Provided, however, that $258,300 of the Priority 2 appropriations for this project is used to23replace general obligation bond proceeds reappropriated to Department of Education, LSU24Health Sciences Center, Health Care Services Division, University Medical Center in New25Orleans (Orleans) in this Act.26

(2085) College of Engineering, Renovation and 27Expansion, Planning and Construction28(East Baton Rouge)29Payable from General Obligation Bonds30

Priority 2 $ 111,30031

Provided, however, that $111,300 of the Priority 2 appropriations for this project is used to32replace general obligation bond proceeds reappropriated to Department of Education, LSU33Health Sciences Center, Health Care Services Division, University Medical Center in New34Orleans (Orleans) in this Act.35

(2086) Renovation of Hodges Dorm for Academic Use,36Construction and Equipment37(East Baton Rouge)38Payable from General Obligation Bonds39

Priority 2 $ 42,10040

Provided, however, that $42,100 of the Priority 2 appropriations for this project is used to41replace general obligation bond proceeds reappropriated to Department of Education, LSU42Health Sciences Center, Health Care Services Division, University Medical Center in New43Orleans (Orleans) in this Act.44

19/602 LSU ALEXANDRIA45

(28) Network and Telephone Cabling Infrastructure,46Planning and Construction47(Rapides)48Payable from General Obligation Bonds49

Priority 2 $ 2,000,00050

ENROLLEDHB NO. 2

Page 51 of 202

(29) Infrastructure Improvements, Construction1(Rapides)2Payable from General Obligation Bonds3

Priority 1 $ 1,950,0004Priority 5 $ 4,170,0005

Total $ 6,120,0006

(32) Multi-Purpose Academic Center, Planning and7Construction8(Rapides)9Payable from General Obligation Bonds10

Priority 5 $ 2,000,00011

(2019) Drainage Outfall Improvements, Planning12and Construction13(Rapides)14Payable from General Obligation Bonds15

Priority 2 $ 239,40016

Provided, however, that $239,400 of the Priority 2 appropriations for this project is used to17replace general obligation bond proceeds reappropriated to Department of Education, LSU18Health Sciences Center, Health Care Services Division, University Medical Center in New19Orleans (Orleans) in this Act.20

(2087) Sciences Building Renovation, Planning 21and Construction22(Rapides)23Payable from General Obligation Bonds24

Priority 2 $ 24,90025

Provided, however, that $24,900 of the Priority 2 appropriations for this project is used to26replace general obligation bond proceeds reappropriated to Department of Education, LSU27Health Sciences Center, Health Care Services Division, University Medical Center in New28Orleans (Orleans) in this Act.29

19/603 UNIVERSITY OF NEW ORLEANS30

(147) Science Building Mechanical Renovations, Planning and 31Construction32(Orleans)33Payable from General Obligation Bonds34

Priority 1 $ 1,675,00035Priority 5 $ 1,600,00036

Total $ 3,275,00037

(148) Library Fourth Floor Completion Information Resource38Center39(Orleans)40Payable from General Obligation Bonds41

Priority 1 $ 3,230,00042Priority 5 $ 2,700,00043

Total $ 5,930,00044

(149) Library Roof Replacement, Planning and Construction45(Orleans)46Payable from Fees and Self Generated Revenues $ 1,002,00047

(1470) Human Performance Center Renovations for Fine Arts48and Music Departments, Planning and Construction49(Orleans)50Payable from General Obligation Bonds51

Priority 5 $ 5,600,00052

ENROLLEDHB NO. 2

Page 52 of 202

(2039) Library HVAC System Modifications, 1Planning and Construction2(Orleans)3Payable from General Obligation Bonds4

Priority 2 $ 231,6005

Provided, however, that $231,600 of the Priority 2 appropriations for this project is used to6replace general obligation bond proceeds reappropriated to Department of Education, LSU7Health Sciences Center, Health Care Services Division, University Medical Center in New8Orleans (Orleans) in this Act.9

19/604N LSU HEALTH SCIENCES CENTER NEW ORLEANS10

(1398) Human Development Center, Planning and11Construction12(Orleans)13Payable from General Obligation Bonds14

Priority 1 $ 7,735,00015

(1400) University Medical Center, Acquisition of Equipment16(Orleans)17Payable from General Obligation Bonds18

Priority 1 $ 20,000,00019

( ) Health Science Center Facility Renovations20(Orleans)21Payable from General Obligation Bonds22

Priority 5 $ 4,200,00023

Provided, however, that this general obligation bond funding is supplemental to the Fees and24Self Generated Revenues appropriation in Act 26 of 2005 and that the combined funds are25to be used for the Dental School Simulation Facility project.26

19/604S LSU HEALTH SCIENCES CENTER SHREVEPORT27

(15) High Voltage Electrical Distribution System Upgrade,28Planning and Construction29(Caddo)30Payable from General Obligation Bonds31

Priority 1 $ 5,380,00032

(16) Boiler Replacement, Planning and Construction33(Caddo)34Payable from General Obligation Bonds35

Priority 1 $ 2,900,00036Priority 5 $ 2,500,00037

Total $ 5,400,00038

(17) Surgery and Radiology Equipment39(Caddo)40Payable from General Obligation Bonds41

Priority 1 $ 5,000,00042

(18) Feist-Weiller Cancer Research Center Planning and43Construction44(Caddo)45Payable from General Obligation Bonds46

Priority 5 $ 25,540,00047

ENROLLEDHB NO. 2

Page 53 of 202

(19) Capital Improvement Projects, Design and Engineering1(Caddo)2Payable from General Obligation Bonds3

Priority 1 $ 3,250,0004Priority 5 $ 1,750,0005

Total $ 5,000,0006

(20) Inpatient Critical Care Renovation, Planning and7Construction8(Caddo)9Payable from General Obligation Bonds10

Priority 1 $ 2,875,00011Priority 5 $ 2,645,00012

Total $ 5,520,00013

(25) Medical School B-Building HVAC Replacement14(Caddo)15Payable from General Obligation Bonds16

Priority 2 $ 1,750,00017Priority 5 $ 3,350,00018

Total $ 5,100,00019

(1401) Patient Care and Hospital HVAC Replacement, 20Planning and Construction21(Caddo)22Payable from General Obligation Bonds23

Priority 1 $ 2,870,00024Priority 2 $ 750,00025

Total $ 3,620,00026

(2001) Children's Hospital, Renovation and Expansion,27Planning and Construction28(Caddo)29Payable from General Obligation Bonds30

Priority 1 $ 1,750,00031Priority 5 $ 8,250,00032

Total $ 10,000,00033

19/605 LSU EUNICE34

(24) Replacement of Health and Physical 35Education Roof, Planning and Construction36(Acadia)37Payable from General Obligation Bonds38

Priority 2 $ 60,00039

19/606 LSU SHREVEPORT40

(21) Wellness Center, Planning and Construction41(Caddo)42Payable from Revenue Bonds $ 15,935,00043

19/607 LSU AGRICULTURAL CENTER44

(1405) Animal and Food Science Facilities Renovations and45Modernizations, Phase II, Planning and Construction46(East Baton Rouge)47Payable from General Obligation Bonds48

Priority 1 $ 3,630,00049

ENROLLEDHB NO. 2

Page 54 of 202

19/609 PENNINGTON BIOMEDICAL RESEARCH CENTER1

(157) Pennington Biomedical Clinical Research Building, Imaging 2Center and High Tech Research Instrumentation Equipment 3(East Baton Rouge)4Payable from General Obligation Bonds5

Priority 1 $ 1,000,0006

19/610 LSU HEALTH SCIENCES CENTER HEALTH 7CARE SERVICES8

(1413) Air Handler Replacement, Planning and Construction9(Lafayette)10Payable from General Obligation Bonds11

Priority 1 $ 1,980,00012

(1414) New Emergency Generator and Chillers, UMC,13Planning and Construction14(Lafayette)15Payable from General Obligation Bonds16

Priority 1 $ 3,200,00017

(1415) University Medical Center in New Orleans 18(Orleans)19Payable from General Obligation Bonds20

Priority 1 $ 141,351,10021Priority 2 $ 13,143,90022

Payable from the balance of General Obligation Bond proceeds23previously allocated under the authority of Act 27 of 2006 for24Executive Department, Division of Administration, Americans With25Disabilities Act Implementation For State Facilities, Planning and26Construction (Statewide); and Act 27 of 2006 for Executive27Department, Division of Administration, Hazardous Material28Abatement Projects (Statewide); and Act 20 of 2009 for Executive29Department, Division of Administration, New Orleans State Office30Facility, Planning and Construction (Orleans); and Act 27 of 2006 for31Executive Department Division of Administration, Mold32Remediation and Indoor Air Quality, Planning and Construction33(Statewide); and Act 20 of 2009 for Executive Department, Division34of Administration, Emergency Major Repairs, Planning and35Construction (Statewide); and Act 21 of 2010 for Executive36Department, Division of Administration, Statewide Replacement of37Single Bottom Elevator Jacks (Code Compliance), Planning and38Construction (Statewide); and Act 23 of 2012 for Executive39Department, Division of Administration, Major Repairs for State40Buildings Based on Statewide Condition Assessment, and41Infrastructure, Planning and Construction (Statewide); and Act 24 of422013 for Executive Department, Division of Administration, Major43Repairs for State Buildings Based on Statewide Condition44Assessment, and Infrastructure, Planning and Construction45(Statewide); and Act 20 of 2009 for Executive Department, Division46of Administration, State Emergency Shelters (Statewide); and Act 2047of 2009 for Executive Department, Division of Administration, New48Data Center and Data Replication Center, Planning and Construction49(Rapides); and Act Interim Emergency Board promulgated in50October 2013 for Executive Department, Division of Administration,51Outpatient Clinics in Rapides Parish, Planning and Construction52(Rapides); and Act 2 of 2004 for Executive Department, Division of53Administration, State Office Buildings Major Repairs, Equipment54Replacement, and Renovations, Planning and Construction55

ENROLLEDHB NO. 2

Page 55 of 202

(Statewide); and Act 23 of 2012 for Executive Department, Division1of Administration, Statewide Roofing, Waterproofing and Related2Repairs and Equipment Replacement Program (Statewide); and Act32 of 2004 for Executive Department, Division of Administration,4Statewide Roofing, Waterproofing, and Related Repairs and5Equipment Replacement Program (Statewide); and Act 20 of 20096for Executive Department, Division of Administration, Statewide7Roofing, Waterproofing, and Related Repairs and Equipment8Replacement Program (Statewide); and Act 21 of 2010 for Executive9Department, Division of Administration, Statewide Roofing,10Waterproofing, and Related Repairs and Equipment Replacement11Program (Statewide); and Act 22 of 2011 for Executive Department,12Division of Administration, Statewide Roofing, Waterproofing, and13Related Repairs and Equipment Replacement Program (Statewide);14and Act 27 of 2006 for Executive Department, Division of15Administration, Statewide Roofing, Waterproofing, and Related16Repairs and Equipment Replacement Program (Statewide); and Act1729 of 2008 for Executive Department, Division of Administration,18Statewide Roofing, Waterproofing, and Related Repairs and19Equipment Replacement Program (Statewide); and Act 2 of 2004 for20Executive Department, Division of Administration, Technical21Colleges Campus Buildings Major Repairs, Equipment Replacement22and Site Work, Planning and Construction (Statewide); and Act 2723of 2006 for Executive Department, Division of Administration,24Community and Technical College Campus Buildings Major Repairs,25Equipment Replacement and Site Work, Planning and Construction26(Statewide); and Act 27 of 2006 for Executive Department, Division27of Administration, Third Street Art Block Project, Development,28Organization, Planning and Construction ($23,925,377 Local Match)29(East Baton Rouge); and Act 2 of 2004 for Executive Department,30Department of Veterans Affairs, Southeast Louisiana War Veterans31Home, Planning and Construction (St. John); and Act 27 of 2006 for32Executive Department, Department of Veterans Affairs, Northwest33Louisiana War Veterans Home, Planning and Construction (Bossier);34and Act 27 of 2006 for Veterans Affairs, Veterans Affairs, Louisiana35State Veterans Cemetery in Vernon, Planning and Construction36(Vernon); and Act 20 of 2009 for Elected Officials, Secretary of37State, Garyville Timbermill Museum HVAC, Interior/Exterior38Renovation, Security System and Site Improvements, Planning and39Construction (St. John); and Act 20 of 2009 for Elected Officials,40Secretary of State, Tioga Heritage Park and Museum, Planning and41Construction (Rapides); and Act 21 of 2010 for Elected Officials,42Secretary of State, Tioga Heritage Park and Museum, Planning and43Construction (Rapides); and Act 20 of 2009 for Elected Officials,44Secretary of State, Eddie Robinson Museum (Lincoln); and Act 2945of 2008 for Elected Officials Secretary of State, Germantown Colony46Museum (Webster); and Act 2 of 2004 for Elected Officials,47Secretary of State, Louisiana State Exhibit Museum in Shreveport,48Completion of Renovations and Upgrades of Exhibits, Planning and49Construction (Caddo); and Act 26 of 2005 for Economic50Development, Office of Business Development, Homeland Security51and Environmental Technical Center, Acquisition and Renovation,52Planning and Construction (East Baton Rouge); and Act 27 of 200653for Economic Development, Office of Business Development,54Infrastructure for Cluster Development, Planning and Construction55(Rapides); and Act 21 of 2010 for Economic Development, Office of56Business Development, Garyville Roadway Improvements, Planning57and Construction (St. John The Baptist); and Act 20 of 2009 for58Cultural, Recreation and Tourism, Office of State Museum,59Louisiana Sports Hall of Fame and Natchitoches State Museum of60North Louisiana, Planning and Construction (Natchitoches); and Act61

ENROLLEDHB NO. 2

Page 56 of 202

2 of 2004 for Cultural, Recreation and Tourism, Office of State1Parks, St. Bernard State Park, Planning and Construction (St.2Bernard); and Act 20 of 2009 for Cultural, Recreation and Tourism,3Office of State Parks, Bayou Segnette State Park, Land Acquisition,4Additional Cabins, Planning and Construction (Jefferson); and Act521 of 2010 for Cultural, Recreation and Tourism, Office of State6Parks, Poverty Point Reservoir State Park, Acquisition, Planning and7Construction, Supplemental Funding (Richland); and Act 2 of 20048for Cultural, Recreation and Tourism, Office of State Parks, Fort Pike9State Historic Site, Planning and Construction (Orleans); and Act 2110of 2010 for Cultural, Recreation and Tourism, Office of State Parks,11Palmetto Island State Park Development, Planning and Construction12(Vermilion); and Act 27 of 2006 for Cultural, Recreation and13Tourism, Office of State Parks, Chicot State Park, Replace Cabins14and Pool, Planning and Construction (Evangeline); and Act 21 of152010 for Cultural, Recreation and Tourism, Office of State Parks,16Bogue Chitto State Park, Land Acquisition, Planning and17Construction (Washington); and Act 20 of 2009 for Cultural,18Recreation and Tourism, Office of State Parks, Louisiana State19Arboretum, Planning and Construction (Evangeline); and Act 20 of202009 for Public Safety and Corrections, Louisiana State Penitentiary,21Fire Marshal, Health Department Violations, Planning and22Construction (West Feliciana); and Act 20 of 2009 for Public Safety23and Corrections, Office of Juvenile Justice, Major Repairs and24Equipment Replacement (Statewide); and Act 21 of 2010 for Public25Safety and Corrections, Avoyelles Correctional Center, Replace26Windows in Dormitories, Cellblocks, and Support Buildings27(Avoyelles); and Act 2 of 2004 for Public Safety and Corrections,28Elayn Hunt Correctional Center, Skilled Nursing Care, Mental Health29Unit and Renovation of Related Support Facilities, Planning and30Construction (Iberville); and Act 2 of 2004 for Public Safety and31Corrections, David Wade Correctional Center, Water Treatment32Plants and Emergency Generators, Planning and Construction33(Claiborne); and Act 21 of 2010 for Public Safety and Corrections,34Rayburn Correctional Center, Emergency Generators (Washington);35and Act 20 of 2009 for Public Safety and Corrections, Office of State36Police, Crime Lab Expansion (East Baton Rouge); and Act 20 of372009 for Health and Hospitals, John J. Hainkel, Jr. Center, North38Wing Renovations (Supplemental Funding) (Orleans); and Act 2 of392004 for Health and Hospitals, Mental Health Area B, Oakcrest40Sprinkler System, East Louisiana State Hospital, Planning and41Construction (East Feliciana); and Act 21 of 2010 for Health and42Hospitals, Eastern Louisiana Mental Health System, Fire Alarm43System Replacement for Ten Buildings, Planning and Construction44(East Feliciana); and Act 20 of 2009 for Health and Hospitals,45Eastern Louisiana Mental Health System, Replacement of Emergency46Generators (East Feliciana); and Act 20 of 2009 for Health and47Hospitals, Mental Health Area A, Fire Alarm System Upgrade48Replacement, Planning and Construction (St. Tammany); and Act 249of 2004 for Health and Hospitals, North Lake Support/Services50Center, Replacement of Underground High Temperature Hot Water51System, Planning and Construction (Tangipahoa); and Act 2 of 200452for Health and Hospitals, North Lake Support/Services Center,53Installation of Sprinkler Systems/Protection of Beams (Tangipahoa);54and Act 21 of 2010 for Health and Hospitals, Hammond55Development Center, Replacement/Upgrade of Emergency56Generators for Client Homes (Tangipahoa); and Act 24 of 2003 for57Natural Resources, Natural Resources - Office of the Secretary,58Atchafalaya Basin Protection and Enhancement ($57,067,280 Federal59Match and $14,963,003 Local/Sponsor Match) (Assumption,60Avoyelles, Iberia, Iberville, Pointe Coupee, St. Landry, St. Martin, St.61

ENROLLEDHB NO. 2

Page 57 of 202

Mary); and Act 26 of 2005 for Natural Resources, Natural Resources1- Office of the Secretary, Atchafalaya Basin Protection and2Enhancement ($57,067,280 Federal Match and $14,963,0033Local/Sponsor Match) (Assumption, Avoyelles, Iberia, Iberville,4Point Coupee, St. Landry, St. Martin, St. Mary); and Act 2 of 20045for Education, LA Health Sciences Center - Health Care Services6Division, Sprinkler System, Charity Campus, Planning and7Construction (Orleans); and Act 2 of 2004 for Education, Louisiana8State University Board of Supervisors, Major Repairs and Reroofing,9ADA Compliance and Life Safety Code Corrections to Campus10Buildings, Planning and Construction (Acadia, Caddo, East Baton11Rouge, Orleans, Rapides); and Act 27 of 2006 for Education, LSU12Board of Supervisors, Major Repairs and Reroofing, ADA13Compliance and Life Safety Code Corrections to Campus Buildings,14Planning and Construction (Acadia, Caddo, East Baton Rouge,15Orleans, Rapides); and Act 21 of 2010 for Education, LSU Board of16Supervisors, Major Repairs and Reroofing, ADA Compliance and17Life Safety Code Corrections to Campus Buildings, Planning and18Construction (Statewide); and Act 27 of 2006 for Education, LSU19Baton Rouge, Music and Dramatic Arts Facilities Renovation and20Addition, Planning and Construction (East Baton Rouge); and Act 2121of 2010 for Education, LSU Baton Rouge, College of Engineering,22Renovation and Expansion, Planning and Construction (East Baton23Rouge); and Act 2 of 2004 for Education, LSU Baton Rouge,24Renovation of Hodges Dorm for academic Use, Construction and25Equipment (East Baton Rouge); and Act 27 of 2006 for Education,26LSU Alexandria, Sciences Building Renovation, Planning and27Construction (Rapides); and Act 21 of 2010 for Education, LSU28Alexandria, Drainage Outfall Improvements (Rapides); and Act 2 of292004 for Education, University of New Orleans, Library 4th Floor30Completion Information Resource Center, Planning and Construction31(Orleans); and Act 2 of 2004 for Education, University of New32Orleans, Library HVAC System Modifications, Planning and33Construction (Orleans); and Act 22 of 2011 for Education, LSU34Health Sciences Center New Orleans, Cooling Tower and Ancillary35Equipment (Orleans); and Act 23 of 2012 for Education, LSU Health36Sciences Center New Orleans, Cooling Tower and Ancillary37Equipment (Orleans); and Act 20 of 2009 for Education, LSU Health38Sciences - Shreveport, Emergency Care Center Expansion and39Renovation, Planning and Construction (Caddo); and Act 21 of 201040for Education, LSU Healthcare Services Division, Medical Records41Storage Building (Terrebonne); and Act 20 of 2009 for Education,42LSU Healthcare Services Division, Outpatient Clinics, University43Medical Center (East Baton Rouge); and Act 22 of 2011 for44Education, LSU Health Sciences Center, Health Care Services45Division, Urgent Care Clinic, Planning and Construction (East Baton46Rouge); and Act 2 of 2004 for Education, Baton Rouge Community47College, Office of Motor Vehicle Building and Campus Renovation,48Demolition and Improvements, Planning and Construction (East49Baton Rouge); and Act 21 of 2010 for Education, Southern50University Baton Rouge, Repair/Replacement of Hot Water Pipes for51Heating (East Baton Rouge); and Act 20 of 2009 for Education,52Southern University Baton Rouge, Repair Sloughing Off Of Ravine53(East Baton Rouge); and Act 21 of 2010 for Education, Southern54University Baton Rouge, Repair Sloughing Off of Ravine (East Baton55Rouge); and Act 2 of 2004 for Education, Southern University Baton56Rouge, Dorm Renovation or Construction Phase 3, Planning and57Construction (East Baton Rouge); and Act 27 of 2006 for Education,58Southern University Baton Rouge, Dorm Renovation or Construction59Phase 3, Planning and Construction (East Baton Rouge); and Act 2760of 2006 for Education, Southern University Baton Rouge, Electrical61

ENROLLEDHB NO. 2

Page 58 of 202

Distribution System Replacement, Planning and Construction (East1Baton Rouge); and Act 20 of 2009 for Education, Southern2University Shreveport, Site Improvement, Drainage and Security3Lights, Planning and Construction (Caddo); and Act 21 of 2010 for4Education, Southern University Shreveport, Renovation/Addition to5Student Activity Center and outdoor PE and Incubator project, Land6Acquisition, Planning and Construction ($500,000 Cash and/or7In-Kind Match) (Caddo); and Act 27 of 2006 for Education,8University of Louisiana System, Major Repairs and Reroofing, ADA9Compliance and Life Safety Code Corrections to Campus Building,10Planning and Construction (Calcasieu, East Baton Rouge, Lafayette,11Lafourche, Lincoln, Natchitoches, Ouachita, Tangipahoa); and Act1220 of 2009 for Education, University of LA System Board, Major13Repairs and Reroofing, ADA Compliance and Life Safety Code14Corrections to Campus Buildings, Planning and Construction15(Statewide); and Act 2 of 2004 for Education, University of LA16System Board, Higher Education Campus Master Planning17(Statewide); and Act 21 of 2010 for Education, Nicholls State18University, Beauregard hall Renovation, Planning and Construction19(Lafourche); and Act 21 of 2010 for Education, Grambling State20University, Campus Utility Infrastructure Assessment, Planning and21Emergency Repairs and/or Replacement (Lincoln); and Act 27 of222006 for Education, Grambling State University, Health and Physical23Education and Recreation Assembly Center, Planning, Construction24and Equipment (Lincoln); and Act 2 of 2004 for Education,25Grambling State University, Drew Hall Demolition and Replacement,26Planning and Construction (Lincoln); and Act 21 of 2010 for27Education, Louisiana Tech University, Visual Arts Building28Renovation for Business, Planning and Construction (Lincoln); and29Act 21 of 2010 for Education Louisiana Tech University, Water30Distribution System (Lincoln); and Act 21 of 2010 for Education,31Louisiana Tech University, Business Building Replacement, Planning32and Construction (Lincoln); and Act 2 of 2004 for Education, LA33Tech University, Hale Hall Reconstruction, Planning, Construction,34Furniture and Equipment (Lincoln); and Act 21 of 2010 for35Education, McNeese State University, Shearman Fine Arts Building36Renovation and Addition, Planning and Construction (Calcasieu);37and Act 21 of 2010 for Education McNeese State University,38Kaufman Hall Renovation and Repairs, Planning and Construction39(Calcasieu); and Act 21 of 2010 for Education, McNeese State40University, Frasch Hall Annex Repairs (Calcasieu); and Act 20 of412009 for Education Northwestern State University, Williamson Hall42Renovation for Engineering Technology, Planning and Construction43(Natchitoches); and Act 21 of 2010 for Education, Southeastern44Louisiana University, Department of Kinesiology, Health Studies and45College of Nursing Program, Renovation and Conversion, Planning,46Construction and Equipment (Tangipahoa); and Act 21 of 2010 for47Education, University of LA - Lafayette, Burke Hawthorne Hall48Renovation and Expansion, Planning and Construction (Lafayette);49and Act 27 of 2006 for Education, University of LA - Lafayette,50Computer Sciences Facility, Planning and Construction (Lafayette);51and Act 2 of 2004 for Education, LCTCS Board of Supervisors,52Small Capital Projects for Louisiana Community and Technical53Colleges System, Planning and Construction (Statewide); and Act 2754of 2006 for Education, LCTCS Board of Supervisors, Statewide55Student and Financial System Network (Statewide); and Act 21 of562010 for Education, Community and Technical Colleges Board of57Supervisors, Chiller Replacement, Delgado Community College58(Orleans); and Act 21 of 2010 for Education, Louisiana School for59Math, Science and the Arts, Renovation Expansion and Replacement60of Annex Building, Existing Auditorium and Cafeteria Areas,61

ENROLLEDHB NO. 2

Page 59 of 202

Planning, and Construction (Natchitoches); and Act 21 of 2010 for1Education, Louisiana School for Math, Science and the Arts,2Residence Hall Renovations, Phase 1, Prudhomme Hall Asbestos3Abatement, Pipe and Ceiling Replacement (Natchitoches); and Act427 of 2006 for Education, Board of Regents, State-Wide5Telecommunications Wiring and Equipment, Planning and6Construction (Statewide); and Act 2 of 2004 for Education, Board of7Regents, Post Secondary Education Campus Libraries Master8Planning (Statewide); and Act 2 of 2004 for Education, Board of9Regents, Governor's Information Technology Initiative to be10distributed in accordance with a plan developed and adopted by the11Board of Regents and approved by the Division of Administration12(Statewide) $ 42,936,99413Total $ 197,431,99414

(1416) Replacement of Air Handlers and Chillers, WO Moss,15Planning and Construction16(Calcasieu)17Payable from General Obligation Bonds18

Priority 1 $ 1,915,00019

(1417) University Medical Center in Baton Rouge 20(East Baton Rouge)21Payable from General Obligation Bonds22

Priority 1 $ 2,090,00023Priority 5 $ 900,00024

Total $ 2,990,00025

Provided, however, that the scope of this appropriation is deemed to also include the26demolition of the Earl K. Long Hospital facility in Baton Rouge and further provide that27$2,000,000 of this appropriation shall be used to pay the costs of demolishing the Earl K.28Long Hospital facility in Baton Rouge.29

(1418) Land Acquisition and Parking Adjacent to N. Baton30Rouge Clinic, Planning and Construction31(East Baton Rouge)32Payable from General Obligation Bonds33

Priority 1 $ 445,00034

(1419) Emergency Room Expansion, University Medical35Center, Planning and Construction36(Lafayette)37Payable from General Obligation Bonds38

Priority 1 $ 4,610,00039

(1420) Air Handling Unit Replacement, Chabert, Planning 40and Construction41(Terrebonne)42Payable from General Obligation Bonds43

Priority 1 $ 480,00044

(1421) Refurbish Elevators, UMC, Planning and Construction45(Lafayette)46Payable from General Obligation Bonds47

Priority 1 $ 1,425,00048

(1972) Construction of Levee Around the Chabert Medical49Center, Planning and Construction50(Terrebonne)51Payable from General Obligation Bonds52

Priority 1 $ 250,00053

ENROLLEDHB NO. 2

Page 60 of 202

(2088) Medical Records Storage Building, 1Planning and Construction2(Terrebonne)3Payable from General Obligation Bonds4

Priority 2 $ 372,3005

Provided, however, that $372,300 of the Priority 2 appropriations for this project is used to6replace general obligation bond proceeds reappropriated to Department of Education, LSU7Health Sciences Center, Health Care Services Division, University Medical Center in New8Orleans (Orleans) in this Act.9

(2089) Outpatient Clinics, University Medical10Center, Planning and Construction11(East Baton Rouge)12Payable from General Obligation Bonds13

Priority 2 $ 95,00014

Provided, however, that $95,000 of the Priority 2 appropriations for this project is used to15replace general obligation bond proceeds reappropriated to Department of Education, LSU16Health Sciences Center, Health Care Services Division, University Medical Center in New17Orleans (Orleans) in this Act.18

19/612 BATON ROUGE COMMUNITY COLLEGE19

(1472) Office of Motor Vehicle Building and Campus20Renovation, Demolition and Improvements, Planning 21and Construction22(East Baton Rouge)23Payable from General Obligation Bonds24

Priority 2 $ 3,236,50025Priority 5 $ 585,00026

Total $ 3,821,50027

Provided, however, that $3,236,500 of the Priority 2 appropriations for this project is used28to replace general obligation bond proceeds reappropriated to Department of Education, LSU29Health Sciences Center, Health Care Services Division, University Medical Center in New30Orleans (Orleans) in this Act.31

19/616 SOUTHERN UNIVERSITY BATON ROUGE32

(284) Central Parking Facility, Planning and Construction33(East Baton Rouge)34Payable from General Obligation Bonds35

Priority 2 $ 1,000,00036Payable from Fees and Self Generated37Revenues $ 14,000,00038Total $ 15,000,00039

(304) Provide Localized Boilers and Replace Chilled Water40Loop41(East Baton Rouge)42Payable from General Obligation Bonds43

Priority 1 $ 2,250,00044Priority 2 $ 576,90045Priority 5 $ 1,000,00046

Total $ 3,826,90047

Provided, however, that $576,900 of the Priority 2 appropriations for this project is used to48replace general obligation bond proceeds reappropriated to Department of Education, LSU49Health Sciences Center, Health Care Services Division, University Medical Center in New50Orleans (Orleans) in this Act.51

ENROLLEDHB NO. 2

Page 61 of 202

(1474) SU Laboratory School Addition and Upgrades,1Planning and Construction2(East Baton Rouge)3Payable from General Obligation Bonds4

Priority 1 $ 55,0005

(1475) Sewer and Street Improvements near Intersection 6of Jesse Stone Avenue and E. C. Harrison Drive, 7Planning and Construction8(East Baton Rouge)9Payable from General Obligation Bonds10

Priority 1 $ 35,00011Priority 5 $ 350,00012

Total $ 385,00013

(1477) Fire Detection and Alarm System Upgrades, 14Planning and Construction15(East Baton Rouge)16Payable from General Obligation Bonds17

Priority 1 $ 80,00018

(1478) Replacement of Underground Fuel Tanks and 19Pumps at Motor Pool, Planning and Construction20(East Baton Rouge)21Payable from General Obligation Bonds22

Priority 1 $ 30,00023

(1481) Southern University Laboratory School Addition 24and Upgrades, Planning and Construction25(East Baton Rouge)26Payable from General Obligation Bonds27

Priority 1 $ 1,170,00028

(1513) Major Repairs to F.G. Clark Activity Center29(East Baton Rouge)30Payable from General Obligation Bonds31

Priority 2 $ 501,20032Priority 5 $ 20,00033

Total $ 521,20034

Provided, however, that $501,200 of the Priority 2 appropriation for this project is used to35replace general obligation bond proceeds reappropriated to Executive Department, Division36of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,37Gustav and Ike, Planning and Construction (Statewide) in this Act.38

(2013) Repair of Sloughing Off of Ravine,39Planning and Construction40(East Baton Rouge)41Payable from General Obligation Bonds42

Priority 2 $ 1,358,00043

Provided, however, that $1,358,000 of the Priority 2 appropriations for this project is used44to replace general obligation bond proceeds reappropriated to Department of Education, LSU45Health Sciences Center, Health Care Services Division, University Medical Center in New46Orleans (Orleans) in this Act.47

(2090) Dorm Renovation or Construction Phase 3, 48Planning and Construction49(East Baton Rouge)50Payable from General Obligation Bonds51

Priority 2 $ 166,40052

ENROLLEDHB NO. 2

Page 62 of 202

Provided, however, that $166,400 of the Priority 2 appropriations for this project is used to1replace general obligation bond proceeds reappropriated to Department of Education, LSU2Health Sciences Center, Health Care Services Division, University Medical Center in New3Orleans (Orleans) in this Act.4

(2094) Electrical System Distribution System Replacement,5Planning and Construction6(East Baton Rouge)7Payable from General Obligation Bonds8

Priority 2 $ 458,2009

Provided, however, that $458,200 of the Priority 2 appropriations for this project is used to10replace general obligation bond proceeds reappropriated to Department of Education, LSU11Health Sciences Center, Health Care Services Division, University Medical Center in New12Orleans (Orleans) in this Act.13

( ) A. O. Williams Hall Renovations14(East Baton Rouge)15Payable from General Obligation Bonds16

Priority 2 $ 1,000,00017

Pending submittal and approval of a capital outlay budget request pursuant to the provisions18of R.S. 30:112.19

19/617 SOUTHERN UNIVERSITY NEW ORLEANS20

(285) Replace Chilled Water and High Temperature Water21Lines22(Orleans)23Payable from General Obligation Bonds24

Priority 1 $ 150,00025

( ) Student Life Center26(Orleans)27Payable from General Obligation Bonds28

Priority 2 $ 1,000,00029Priority 5 $ 7,500,00030

Total $ 8,500,00031

Pending submittal and approval of a capital outlay budget request pursuant to the provisions32of R.S. 30:112.33

19/618 SOUTHERN UNIVERSITY SHREVEPORT34

(1056) Renovations of Allen Building, Planning and35Construction36(Caddo)37Payable from General Obligation Bonds38

Priority 1 $ 3,785,00039

(2002) New Classroom Building, Southern University -40Shreveport, Planning and Construction41(Caddo)42Payable from General Obligation Bonds43

Priority 1 $ 7,155,00044

ENROLLEDHB NO. 2

Page 63 of 202

(2091) Renovation/Addition to Student Activity 1Center and Outdoor PE Incubator Project, 2Land Acquisition, Planning and 3Construction ($500,000 Cash and/or 4In-Kind Match)5(Caddo)6Payable from General Obligation Bonds7

Priority 2 $ 27,0008

Provided, however, that $27,000 of the Priority 2 appropriations for this project is used to9replace general obligation bond proceeds reappropriated to Department of Education, LSU10Health Sciences Center, Health Care Services Division, University Medical Center in New11Orleans (Orleans) in this Act.12

(2092) Site Improvement, Drainage and Security13Lights, Planning and Construction14(Caddo)15Payable from General Obligation Bonds16

Priority 2 $ 295,50017

Provided, however, that $295,500 of the Priority 2 appropriations for this project is used to18replace general obligation bond proceeds reappropriated to Department of Education, LSU19Health Sciences Center, Health Care Services Division, University Medical Center in New20Orleans (Orleans) in this Act.21

( ) Construction of Intramural Complex, Planning22and Construction23(Caddo)24Payable from Fees and Self Generated25Revenues $ 1,000,00026

Pending submittal and approval of a capital outlay budget request pursuant to the provisions27of R.S. 39:112.28

( ) Construction of New Student Housing, Planning29and Construction30(Caddo)31Payable from Fees and Self Generated32Revenues $ 11,000,00033

Pending submittal and approval of a capital outlay budget request pursuant to the provisions34of R.S. 39:112.35

(2130) Workforce Training and Technology Center, 36Planning and Correction37(Caddo)38Payable from General Obligation Bonds39

Priority 2 $ 535,00040Priority 5 $ 5,865,00041

Total $ 6,400,00042

19/620 UNIVERSITY OF LOUISIANA SYSTEM43

(1519) Life Safety Code Corrections, Planning and44Construction45(Ascension, Bossier, Calcasieu, Iberia, Lafayette, 46Lafourche, Lincoln, Natchitoches, Orleans, 47Ouachita, St. Bernard, Tangipahoa)48Payable from General Obligation Bonds49

Priority 5 $ 185,00050

ENROLLEDHB NO. 2

Page 64 of 202

(2093) Higher Education Campus Master Planning1(Statewide)2Payable from General Obligation Bonds3

Priority 2 $ 1,274,9004

Provided, however, that $963,900 of the Priority 2 appropriations for this project is used to5replace general obligation bond proceeds reappropriated to Department of Education, LSU6Health Sciences Center, Health Care Services Division, University Medical Center in New7Orleans (Orleans) in this Act and that $311,000 of the Priority 2 appropriation for this8project is used to replace general obligation bond proceeds reappropriated to Executive9Department, Division of Administration, Repairs, Restoration and Replacement for10Hurricanes Katrina, Rita, Gustav and Ike, Planning and Construction (Statewide) in this Act.11

19/621 NICHOLLS STATE UNIVERSITY12

(39) Talbot Hall Renovation and Roof Replacement,13Planning and Construction14(Lafourche)15Payable from General Obligation Bonds16

Priority 1 $ 4,400,00017Priority 2 $ 900,00018

Total $ 5,300,00019

(1520) Athletic Facilities - Didier Field, Renovation, 20Planning and Construction21(Lafourche)22Payable from General Obligation Bonds23

Priority 1 $ 500,00024Priority 2 $ 250,00025Priority 5 $ 750,00026

Total $ 1,500,00027

(1521) Building Renovation, Planning and Construction 28(Lafourche)29Payable from General Obligation Bonds30

Priority 1 $ 330,00031

(1997) Fieldhouse, Planning and Construction32(Lafourche)33Payable from General Obligation Bonds34

Priority 2 $ 835,00035Priority 5 $ 2,750,00036

Total $ 3,585,00037

(1998) Renovation of Athletic Training and Meeting 38Facility, Planning and Construction39(Lafourche)40Payable from General Obligation Bonds41

Priority 5 $ 2,750,00042

(2095) Beauregard Hall Renovation, Planning 43and Construction44(Lafourche)45Payable from General Obligation Bonds46

Priority 2 $ 103,80047

Provided, however, that $103,800 of the Priority 2 appropriations for this project is used to48replace general obligation bond proceeds reappropriated to Department of Education, LSU49Health Sciences Center, Health Care Services Division, University Medical Center in New50Orleans (Orleans) in this Act.51

ENROLLEDHB NO. 2

Page 65 of 202

19/623 GRAMBLING STATE UNIVERSITY1

(178) Library Improvements (A.C. Lewis Main/Annex),2Planning and Construction3(Lincoln)4Payable from General Obligation Bonds5

Priority 1 $ 2,000,0006Priority 5 $ 8,000,0007

Total $ 10,000,0008

(182) Campus Utility Infrastructure Assessment, Planning9and Emergency Repairs and/or Replacement, 10Planning and Construction11(Lincoln)12Payable from General Obligation Bonds13

Priority 1 $ 1,290,00014Priority 2 $ 7,90015Priority 5 $ 925,00016

Total $ 2,222,90017

Provided, however, that $7,900 of the Priority 2 appropriations for this project is used to18replace general obligation bond proceeds reappropriated to Department of Education, LSU19Health Sciences Center, Health Care Services Division, University Medical Center in New20Orleans (Orleans) in this Act.21

(184) Long-Jones Hall Renovation, Planning and22Construction23(Lincoln)24Payable from General Obligation Bonds25

Priority 1 $ 2,000,00026

(1524) Library Deficiencies, Planning and Construction27(Lincoln)28Payable from General Obligation Bonds29

Priority 1 $ 1,945,00030

(2096) Health and Physical Education and Recreation31Assembly Center, Planning, Construction,32and Equipment33(Lincoln)34Payable from General Obligation Bonds35

Priority 2 $ 176,60036

Provided, however, that $176,600 of the Priority 2 appropriations for this project is used to37replace general obligation bond proceeds reappropriated to Department of Education, LSU38Health Sciences Center, Health Care Services Division, University Medical Center in New39Orleans (Orleans) in this Act.40

(2097) Drew Hall Demolition and Replacement,41Planning and Construction42(Lincoln)43Payable from General Obligation Bonds44

Priority 2 $ 39,50045

Provided, however, that $39,500 of the Priority 2 appropriations for this project is used to46replace general obligation bond proceeds reappropriated to Department of Education, LSU47Health Sciences Center, Health Care Services Division, University Medical Center in New48Orleans (Orleans) in this Act.49

ENROLLEDHB NO. 2

Page 66 of 202

19/625 LOUISIANA TECH UNIVERSITY1

(186) Wyly Tower Fire Code/Restroom ADA 2Modifications, Planning and Construction3(Lincoln)4Payable from General Obligation Bonds5

Priority 2 $ 50,0006

(187) Pedestrian and Parking Development, 7Planning and Construction8(Lincoln)9Payable from General Obligation Bonds10

Priority 2 $ 250,00011Payable from Fees and Self Generated Revenues $ 400,00012Total $ 650,00013

(188) Business Building Replacement and Addition, 14Planning and Construction15(Lincoln)16Payable from General Obligation Bonds17

Priority 2 $ 5,039,00018Priority 5 $ 1,680,00019

Total $ 6,719,00020

Provided, however, that $39,000 of the Priority 2 appropriations for this project is used to21replace general obligation bond proceeds reappropriated to Department of Education, LSU22Health Sciences Center, Health Care Services Division, University Medical Center in New23Orleans (Orleans) in this Act.24

(189) Louisiana Tech Research Park, Real Estate 25Acquisition, Planning and Construction26(Lincoln)27Payable from General Obligation Bonds28

Priority 1 $ 1,250,00029Priority 5 $ 4,000,00030

Total $ 5,250,00031

(191) Water Distribution System Repairs and 32Improvements33(Lincoln)34Payable from General Obligation Bonds35

Priority 1 $ 2,860,00036Priority 2 $ 5,90037

Total $ 2,865,90038

Provided, however, that $5,900 of the Priority 2 appropriations for this project is used to39replace general obligation bond proceeds reappropriated to Department of Education, LSU40Health Sciences Center, Health Care Services Division, University Medical Center in New41Orleans (Orleans) in this Act.42

(198) Integrated Engineering and Science Building 43(Lincoln)44Payable from General Obligation Bonds45

Priority 2 $ 1,875,00046Priority 5 $ 35,000,00047

Total $ 36,875,00048

ENROLLEDHB NO. 2

Page 67 of 202

(1526) Visual Arts Building Renovation for Business, 1Planning and Construction2(Lincoln)3Payable from General Obligation Bonds4

Priority 1 $ 500,0005Priority 2 $ 60,8006

Total $ 560,8007

Provided, however, that $60,800 of the Priority 2 appropriations for this project is used to8replace general obligation bond proceeds reappropriated to Department of Education, LSU9Health Sciences Center, Health Care Services Division, University Medical Center in New10Orleans (Orleans) in this Act.11

(2098) Hale Hall Reconstruction, Planning, Construction,12Furniture and Equipment13(Lincoln)14Payable from General Obligation Bonds15

Priority 2 $ 57,00016

Provided, however, that $57,000 of the Priority 2 appropriations for this project is used to17replace general obligation bond proceeds reappropriated to Department of Education, LSU18Health Sciences Center, Health Care Services Division, University Medical Center in New19Orleans (Orleans) in this Act.20

19/627 MCNEESE STATE UNIVERSITY21

(34) Health/Human Performance Education Complex,22Planning and Construction23(Calcasieu)24Payable from General Obligation Bonds25

Priority 1 $ 3,800,00026Priority 5 $ 35,860,00027

Total $ 39,660,00028

(35) Alpha Hall Renovations, Planning and Construction29(Calcasieu)30Payable from General Obligation Bonds31

Priority 1 $ 1,455,00032Priority 2 $ 260,00033

Total $ 1,715,00034

(36) ADA Upgrades Campus-Wide, Planning and35Construction36(Calcasieu)37Payable from General Obligation Bonds38

Priority 1 $ 4,975,00039

(37) Shearman Fine Arts Building - Renovation of 40Existing Space, Planning and Construction41(Calcasieu)42Payable from General Obligation Bonds43

Priority 1 $ 4,400,00044Priority 2 $ 2,700,00045

Total $ 7,100,00046

(1529) Frazar Memorial Library Renovation and 47Repairs, Planning and Construction48(Calcasieu)49Payable from General Obligation Bonds50

Priority 1 $ 7,925,00051

ENROLLEDHB NO. 2

Page 68 of 202

(1534) Campus-Wide Elevator Repairs, Planning and1Construction2(Calcasieu)3Payable from General Obligation Bonds4

Priority 1 $ 690,0005

(1536) Contraband Bayou Erosion Retaining Wall 6Phase II, Planning and Construction7(Calcasieu)8Payable from General Obligation Bonds9

Priority 1 $ 1,500,00010Priority 5 $ 4,200,00011

Total $ 5,700,00012

(2009) Shearman Fine Arts Building Renovation 13and Addition, Planning and Construction14(Calcasieu)15Payable from General Obligation Bonds16

Priority 2 $ 1,089,50017

Provided, however, that $1,089,500 of the Priority 2 appropriations for this project is used18to replace general obligation bond proceeds reappropriated to Department of Education, LSU19Health Sciences Center, Health Care Services Division, University Medical Center in New20Orleans (Orleans) in this Act.21

(2015) Frasch Hall Annex Repairs,22Planning and Construction23(Calcasieu)24Payable from General Obligation Bonds25

Priority 2 $ 150,30026

Provided, however, that $150,300 of the Priority 2 appropriations for this project is used to27replace general obligation bond proceeds reappropriated to Department of Education, LSU28Health Sciences Center, Health Care Services Division, University Medical Center in New29Orleans (Orleans) in this Act.30

(2099) Kaufman Hall Renovation and Repairs, 31Planning and Construction32(Calcasieu)33Payable from General Obligation Bonds34

Priority 2 $ 2,00035

Provided, however, that $2,000 of the Priority 2 appropriations for this project is used to36replace general obligation bond proceeds reappropriated to Department of Education, LSU37Health Sciences Center, Health Care Services Division, University Medical Center in New38Orleans (Orleans) in this Act.39

19/629 UNIVERSITY OF LOUISIANA - MONROE40

(47) Sandel Hall Renovation, Planning and Construction41(Ouachita)42Payable from General Obligation Bonds43

Priority 1 $ 16,830,00044

(49) Stubbs Hall Reroofing, Planning and Construction45(Ouachita)46Payable from General Obligation Bonds47

Priority 1 $ 625,00048

ENROLLEDHB NO. 2

Page 69 of 202

19/631 NORTHWESTERN STATE UNIVERSITY1

(151) South Jefferson Street Extension2(Natchitoches)3Payable from General Obligation Bonds4

Priority 2 $ 300,0005Priority 5 $ 3,180,0006

Total $ 3,480,0007

(153) Roof Replacements, Various Campus Buildings, 8Planning and Construction9(Caddo, Natchitoches, Vernon)10Payable from General Obligation Bonds11

Priority 2 $ 450,00012Priority 5 $ 5,350,00013

Total $ 5,800,00014

(154) Parking Lot Repairs, Planning and Construction15(Natchitoches)16Payable from General Obligation Bonds17

Priority 1 $ 400,00018Priority 2 $ 1,330,00019

Total $ 1,730,00020

(155) Renovation of Roy Hall, Planning and Construction21(Natchitoches)22Payable from General Obligation Bonds23

Priority 2 $ 500,00024Priority 5 $ 8,410,00025

Total $ 8,910,00026

(1999) Multi-Purpose Assembly Center, Planning and27Construction28(Natchitoches)29Payable from General Obligation Bonds30

Priority 2 $ 355,00031Priority 5 $ 34,000,00032

Total $ 34,355,00033

(2100) Williamson Hall Renovation for Engineering34Technology, Planning and Construction35(Natchitoches)36Payable from General Obligation Bonds37

Priority 2 $ 45,00038

Provided, however, that $45,000 of the Priority 2 appropriations for this project is used to39replace general obligation bond proceeds reappropriated to Department of Education, LSU40Health Sciences Center, Health Care Services Division, University Medical Center in New41Orleans (Orleans) in this Act.42

19/634 SOUTHEASTERN LOUISIANA UNIVERSITY43

(33) Computer Science and Technology Facility44Improvements and Expansion, Planning and 45Construction46(Tangipahoa)47Payable from General Obligation Bonds48

Priority 1 $ 8,265,00049Priority 5 $ 14,350,00050

Total $ 22,615,00051

ENROLLEDHB NO. 2

Page 70 of 202

19/640 UNIVERSITY OF LOUISIANA - LAFAYETTE1

(193) Fletcher Hall Exterior Repairs, Planning and 2Construction3(Lafayette)4Payable from General Obligation Bonds5

Priority 1 $ 650,0006Priority 5 $ 2,850,0007

Total $ 3,500,0008

(2101) Burke Hawthorne Hall Renovation and Expansion,9Planning and Construction10(Lafayette)11Payable from General Obligation Bonds12

Priority 2 $ 991,10013

Provided, however, that $991,100 of the Priority 2 appropriations for this project is used to14replace general obligation bond proceeds reappropriated to Department of Education, LSU15Health Sciences Center, Health Care Services Division, University Medical Center in New16Orleans (Orleans) in this Act.17

(2102) Computer Sciences Facility, Planning 18and Construction19(Lafayette)20Payable from General Obligation Bonds21

Priority 2 $ 70,70022

Provided, however, that $70,700 of the Priority 2 appropriations for this project is used to23replace general obligation bond proceeds reappropriated to Department of Education, LSU24Health Sciences Center, Health Care Services Division, University Medical Center in New25Orleans (Orleans) in this Act.26

19/641 DELGADO COMMUNITY COLLEGE27

(1424) Facilities Improvement for Economic Development,28Planning and Construction29(Orleans)30Payable from General Obligation Bonds31

Priority 1 $ 40,00032

19/643 NUNEZ COMMUNITY COLLEGE33

(2125) Land Acquisition34(St. Bernard)35Payable from General Obligation Bonds36

Priority 2 $ 54,50037

Provided, however, that $54,500 of the Priority 2 appropriation for this project is used to38replace general obligation bond proceeds reappropriated to Executive Department, Division39of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,40Gustav and Ike, Planning and Construction (Statewide) in this Act.41

19/644 BOSSIER COMMUNITY COLLEGE42

(442) Parking Lot, Planning and Construction43(Bossier)44Payable from General Obligation Bonds45

Priority 2 $ 150,00046Priority 5 $ 1,650,00047

Total $ 1,800,00048

ENROLLEDHB NO. 2

Page 71 of 202

19/649 LOUISIANA COMMUNITY AND TECHNICAL 1COLLEGE SYSTEM2

(424) Automotive Training Facility, Planning and3Construction4(East Baton Rouge)5Payable from General Obligation Bonds6

Priority 1 $ 9,825,0007Priority 5 $ 15,250,0008

Total $ 25,075,0009

(1428) Winnsboro Campus of Delta Community College,10Acquisition, Planning, and Construction11(Franklin)12Payable from General Obligation Bonds13

Priority 5 $ 900,00014

(2103) Small Capital Projects for Louisiana Community15and Technical Colleges System, Planning and16Construction17(Statewide)18Payable from General Obligation Bonds19

Priority 2 $ 200,00020

Provided, however, that $200,000 of the Priority 2 appropriations for this project is used to21replace general obligation bond proceeds reappropriated to Department of Education, LSU22Health Sciences Center, Health Care Services Division, University Medical Center in New23Orleans (Orleans) in this Act.24

(2104) Statewide Student and Financial System 25Network, Planning and Construction26(Statewide)27Payable from General Obligation Bonds28

Priority 2 $ 50,30029

Provided, however, that $50,300 of the Priority 2 appropriations for this project is used to30replace general obligation bond proceeds reappropriated to Department of Education, LSU31Health Sciences Center, Health Care Services Division, University Medical Center in New32Orleans (Orleans) in this Act.33

(2105) Chiller Replacement, Delgado Community College34(Orleans)35Payable from General Obligation Bonds36

Priority 2 $ 187,00037

Provided, however, that $187,000 of the Priority 2 appropriations for this project is used to38replace general obligation bond proceeds reappropriated to Department of Education, LSU39Health Sciences Center, Health Care Services Division, University Medical Center in New40Orleans (Orleans) in this Act.41

19/651 LOUISIANA SCHOOL FOR VISUALLY IMPAIRED42

(1429) Removal of Existing Modular Building and43Replacement Modular Building44(East Baton Rouge)45Payable from General Obligation Bonds46

Priority 1 $ 20,00047

ENROLLEDHB NO. 2

Page 72 of 202

19/655 LA SPECIAL EDUCATION CENTER1(1127) Central Supply Renovation and Addition, Planning and2

Construction3(Rapides)4Payable from Interagency Transfers $ 768,0415

19/657 LOUISIANA SCHOOL FOR MATH, SCIENCE 6AND THE ARTS7

(868) New Dormitory Building, Planning and Construction8(Natchitoches)9Payable from General Obligation Bonds10

Priority 1 $ 1,200,00011Priority 5 $ 22,800,00012

Total $ 24,000,00013

(1027) Stair Railings - Addressing Code Violations, 14Planning and Construction15(Natchitoches)16Payable from General Obligation Bonds17

Priority 1 $ 140,00018

(1028) HVAC Issues in Caddo Hall, Planning and19Construction20(Natchitoches)21Payable from General Obligation Bonds22

Priority 1 $ 600,00023

(2106) Renovation, Expansion and Replacement of 24Annex Building, Existing Auditorium and 25Cafeteria Areas, Planning and Construction26(Natchitoches)27Payable from General Obligation Bonds28

Priority 2 $ 136,30029

Provided, however, that $136,300 of the Priority 2 appropriations for this project is used to30replace general obligation bond proceeds reappropriated to Department of Education, LSU31Health Sciences Center, Health Care Services Division, University Medical Center in New32Orleans (Orleans) in this Act.33

(2107) Residence Hall Renovations, Phase 1,34Prudhomme Hall Asbestos Abatement,35Pipe and Ceiling Replacement36(Natchitoches)37Payable from General Obligation Bonds38

Priority 2 $ 224,50039

Provided, however, that $224,500 of the Priority 2 appropriations for this project is used to40replace general obligation bond proceeds reappropriated to Department of Education, LSU41Health Sciences Center, Health Care Services Division, University Medical Center in New42Orleans (Orleans) in this Act.43

19/662 LOUISIANA EDUCATIONAL TELEVISION 44AUTHORITY45

(1187) Emergency Communication/Disaster Recovery 46(Statewide)47Payable from Federal Funds $ 300,00048

ENROLLEDHB NO. 2

Page 73 of 202

19/671 BOARD OF REGENTS1

(1315) Land Acquisition for Post Secondary Educational2Institutions 3(Statewide)4Payable from General Obligation Bonds5

Priority 1 $ 2,500,0006

Provided that this appropriation shall be used for the acquisition of the former Our Lady of7Lourdes Hospital facility.8

(1430) Jefferson West Learning Center, Land Acquisition,9Planning and Construction10(Jefferson)11Payable from General Obligation Bonds12

Priority 1 $ 495,00013

(1431) System-Wide Telecommunications Wiring and14Equipment, Planning and Construction15(Statewide)16Payable from General Obligation Bonds17

Priority 2 $ 10,20018Priority 5 $ 1,500,00019

Total $ 1,510,20020

Provided, however, that $10,200 of the Priority 2 appropriations for this project is used to21replace general obligation bond proceeds reappropriated to Department of Education, LSU22Health Sciences Center, Health Care Services Division, University Medical Center in New23Orleans (Orleans) in this Act.24

(1432) Library, Instructional and Scientific Equipment25Acquisitions for Higher Education Institutions26(Statewide)27Payable from General Obligation Bonds28

Priority 5 $ 1,870,00029Payable from the WISE Fund $ 11,000,00030Total $ 12,870,00031

(2059) Post Secondary Education Campus Libraries32Master Planning 33(Statewide)34Payable from General Obligation Bonds35

Priority 2 $ 100,00036

Provided, however, that $100,000 of the Priority 2 appropriations for this project is used to37replace general obligation bond proceeds reappropriated to Department of Education, LSU38Health Sciences Center, Health Care Services Division, University Medical Center in New39Orleans (Orleans) in this Act.40

(2108) Governor's Information Technology Initiative41to be distributed in accordance with a plan42developed and adopted by the Board of Regents43and approved by the Division of Administration44(Statewide)45Payable from General Obligation Bonds46

Priority 2 $ 146,20047

Provided, however, that $146,200 of the Priority 2 appropriations for this project is used to48replace general obligation bond proceeds reappropriated to Department of Education, LSU49Health Sciences Center, Health Care Services Division, University Medical Center in New50Orleans (Orleans) in this Act.51

ENROLLEDHB NO. 2

Page 74 of 202

19/673 NEW ORLEANS CENTER FOR THE CREATIVE 1ARTS2

(995) Press Street Studios Furniture/ Fixtures/ Equipment,3Planning and Construction4(Orleans)5Payable from General Obligation Bonds6

Priority 5 $ 900,0007

(1435) Replace HVAC System, Planning and Construction8(Orleans)9Payable from General Obligation Bonds10

Priority 1 $ 750,00011

19/731 L.E. FLETCHER TECHNICAL COMMUNITY 12COLLEGE13

(1314) Integrated Petroleum Technologies Program (IPT) Lab14and Classroom Building, Planning and Construction15(Terrebonne)16Payable from General Obligation Bonds17

Priority 1 $ 4,000,00018

(1437) Diesel Marine, Welding and Transportation Building19for Fletcher Technical Community College20(Terrebonne)21Payable from General Obligation Bonds22

Priority 1 $ 200,00023Priority 2 $ 400,00024

Total $ 600,00025

19/741 LOUISIANA TECHNICAL COLLEGE - 26LAFAYETTE CAMPUS27

(1438) LTC Lafayette Campus - HVAC Replacement,28Planning and Construction29(Lafayette)30Payable from General Obligation Bonds31

Priority 1 $ 2,545,00032

19/752 LOUISIANA TECHNICAL COLLEGE - 33MORGAN SMITH CAMPUS34

(1441) New Construction or Renovations to Morgan Smith35Campus, Planning and Construction36(Jefferson Davis)37Payable from General Obligation Bonds38

Priority 1 $ 500,00039Priority 5 $ 9,850,00040

Total $ 10,350,00041

JUDICIAL EXPENSES42

23/949 LOUISIANA JUDICIARY43

(1541) Land Acquisition, Planning, and Construction of New44Courthouse for the Louisiana Court of Appeal, Third 45Circuit 46(Calcasieu)47Payable from General Obligation Bonds48

Priority 1 $ 1,190,00049

ENROLLEDHB NO. 2

Page 75 of 202

LEGISLATIVE EXPENSES1

24/960 LEGISLATIVE BUDGETARY CONTROL COUNCIL2

(1542) State Capitol HVAC Replacement and Renovations3(East Baton Rouge)4Payable from General Obligation Bonds5

Priority 1 $ 11,000,0006

(1543) State Capitol Security Improvements, Planning and7Construction8(East Baton Rouge)9Payable from General Obligation Bonds10

Priority 1 $ 2,800,00011Priority 2 $ 655,00012

Total $ 3,455,00013

(2134) Legislative Office Building Located at Old 14Insurance Building Site, Design, Planning,15Construction and Demolition16(East Baton Rouge)17Payable from General Obligation Bonds18

Priority 2 $ 2,000,00019Priority 5 $ 30,000,00020

Total $ 32,000,00021

LEVEE DISTRICTS AND PORTS22

36/L08 LAKE BORGNE BASIN LEVEE DISTRICT23

(793) Drainage Improvements to LA 46 Roadway Drainage24Improvement Project Between Parish Road and Webster 25Road, Planning and Construction 26(St. Bernard)27Payable from General Obligation Bonds28

Priority 5 $ 1,510,00029

(795) Drainage Pump Stations and Channel Improvements,30Land Acquisitions, Planning and Construction31(St. Bernard)32Payable from General Obligation Bonds33

Priority 5 $ 15,00034

36/L10 ORLEANS LEVEE DISTRICT35

(1178) Southeast Louisiana Flood Protection Authority - East36for Bayou St. John, Maintenance and Improvements, 37Perimeter Elevation, Hydrology Study, Planning and 38Construction39(Orleans)40Payable from General Obligation Bonds41

Priority 1 $ 85,00042

36/L13 PONTCHARTRAIN LEVEE DISTRICT43

(1547) Lake Pontchartrain West Shore Hurricane Protection44Project45(Ascension, St. Charles, St. James, St. John the Baptist)46Payable from General Obligation Bonds47

Priority 1 $ 2,330,00048Priority 5 $ 8,500,00049

Total $ 10,830,00050

ENROLLEDHB NO. 2

Page 76 of 202

(1548) East St. Charles Urban Flood Control Project, Planning1and Construction2(St. Charles)3Payable from General Obligation Bonds4

Priority 1 $ 1,500,0005Priority 5 $ 500,0006

Total $ 2,000,0007

36/L16 SOUTH LAFOURCHE LEVEE DISTRICT8

(557) Larose to Golden Meadow Hurricane Protection9System, Planning and Construction10(Lafourche)11Payable from General Obligation Bonds12

Priority 1 $ 1,350,00013Priority 2 $ 1,500,00014Priority 5 $ 13,150,00015

Total $ 16,000,00016

36/L25 GRAND ISLE INDEPENDENT LEVEE DISTRICT17

(1306) Breakwater Protection, Planning and Construction 18(Jefferson)19Payable from General Obligation Bonds20

Priority 1 $ 445,00021Priority 5 $ 650,00022

Total $ 1,095,00023

36/L26 NATCHITOCHES LEVEE AND DRAINAGE DISTRICT24

(914) Lower Cane River Area Flood Gates Replacement25Program26(Natchitoches)27Payable from General Obligation Bonds28

Priority 1 $ 45,00029

36/L27 TERREBONNE LEVEE & CONSERVATION DISTRICT30

(2043) Barrier Plan for Terrebonne, Lafourche, 31Assumption and St. Mary, Planning 32and Construction Providing Flood 33Protection and Interior Drainage, 34Planning and Construction 35($280,000 Local Match)36(Assumption, Lafourche, St. Mary, Terrebonne)37Payable from General Obligation Bonds38

Priority 2 $ 1,385,50039

Provided, however, that $1,385,500 of the Priority 2 appropriation for this project is used to40replace general obligation bond proceeds reappropriated to Executive Department, Division41of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,42Gustav and Ike, Planning and Construction (Statewide) in this Act.43

36/L29 BOSSIER LEVEE DISTRICT44

(1656) Flat River Bank Stabilization, Planning and45Construction46(Bossier)47Payable from General Obligation Bonds48

Priority 5 $ 1,100,00049

ENROLLEDHB NO. 2

Page 77 of 202

36/L30 SOUTHEAST LOUISIANA FLOOD PROTECTION 1AUTHORITY-EAST2

(1214) Non-Federal Levee Certification New Orleans East3Polder-Maxent Lee4(Orleans)5Payable from General Obligation Bonds6

Priority 2 $ 510,0007Priority 5 $ 255,0008

Total $ 765,0009

36/L34 ORLEANS NON-FLOOD PROTECTION ASSET10MANAGEMENT AUTHORITY11

(1137) New Basin Canal Park Bicycle and Jogging Path,12Planning and Construction13(Orleans)14Payable from General Obligation Bonds15

Priority 2 $ 100,00016

(1138) Lakeshore Drive and Stars and Stripes Boulevard17Safety Striping and Pavement Markings,18Planning and Construction19(Orleans)20Payable from General Obligation Bonds21

Priority 5 $ 130,00022

(1140) Lakeshore Drive Levee Relocation of Utilities and23Repair of Lakeshore Drive Lighting24(Orleans)25Payable from General Obligation Bonds26

Priority 2 $ 60,00027

36/L35 ST MARY PARISH LEVEE DISTRICT28

(1480) Franklin Canal Levee and Floodgate Project, Planning29and Construction30(St. Mary)31Payable from General Obligation Bonds32

Priority 1 $ 630,00033

36/L37 IBERIA PARISH LEVEE HURRICANE AND 34CONSERVATION DISTRICT35

(750) Planning, Permitting, Engineering, and Right of36Way Acquisitions for the Iberia 37Hurricane Protection Master Plan 38(Iberia)39Payable from General Obligation Bonds40

Priority 1 $ 245,00041

36/P01 ABBEVILLE HARBOR AND TERMINAL DISTRICT42

(614) Bulkheading and Dredging at Port Vermilion43($1,000,000 Cash and/or In Kind Match)44(Vermilion)45Payable from General Obligation Bonds46

Priority 2 $ 750,00047Priority 5 $ 1,080,00048

Total $ 1,830,00049

ENROLLEDHB NO. 2

Page 78 of 202

36/P03 GREATER BATON ROUGE PORT COMMISSION1

(1657) Inland River Marine Terminal Dock and Access2Roadway Construction Project, Planning and Construction3(West Baton Rouge)4Payable from General Obligation Bonds5

Priority 1 $ 3,200,0006Priority 5 $ 20,000,0007

Total $ 23,200,0008

36/P05 WEST CALCASIEU PORT9

(585) New Bulkhead along Gulf Intracoastal Waterway -10West Calcasieu Port 11(Calcasieu)12Payable from General Obligation Bonds13

Priority 2 $ 200,00014Priority 5 $ 1,800,00015

Total $ 2,000,00016

(586) Land Acquisition and Rehabilitation of Existing17Bulkhead, Planning and Construction 18($1,305,000 Local Match)19(Calcasieu)20Payable from General Obligation Bonds21

Priority 1 $ 1,305,00022

36/P10 GREATER LAFOURCHE PORT COMMISSION23

(1459) Nolty J. Theriot Road Elevation Project, Planning and24Construction25(Lafourche)26Payable from General Obligation Bonds27

Priority 1 $ 1,400,00028

36/P12 LAKE PROVIDENCE PORT COMMISSION29

(949) Railroad Rehabilitation, Planning and Construction30(East Carroll)31Payable from General Obligation Bonds32

Priority 1 $ 1,500,00033

(1658) Coal Pad Repair34(East Carroll)35Payable from General Obligation Bonds36

Priority 1 $ 5,00037

(1659) Succinic Acid Biorefinery, Planning and Construction38(East Carroll)39Payable from General Obligation Bonds40

Priority 1 $ 10,00041

36/P14 MADISON PARISH PORT42

(1103) Improvements to Madison Parish Port former Northrop43Grumman Shipbuilding Expansion44(Madison)45Payable from General Obligation Bonds46

Priority 1 $ 15,00047

ENROLLEDHB NO. 2

Page 79 of 202

(1460) Railroad Rehabilitation/ Improvement and New Rail1Spur for Avondale Facility, and Improvements Required 2for Levee Raising Including Raise Rail, Road and Utilities 3($221,000 Local Match)4(Madison)5Payable from General Obligation Bonds6

Priority 1 $ 30,0007Priority 2 $ 100,0008

Total $ 130,0009

(1484) Complex Chemical Entrance Road, Planning and10Construction11(Madison)12Payable from General Obligation Bonds13

Priority 1 $ 50,00014

36/P15 MORGAN CITY HARBOR AND TERMINAL DISTRICT15

(292) Governmental Operations and Emergency Center,16Planning and Construction 17(St. Mary)18Payable from General Obligation Bonds19

Priority 1 $ 1,200,00020Priority 2 $ 5,900,00021Priority 5 $ 6,000,00022

Total $ 13,100,00023

(2041) Atchafalaya River, Bayou Chene, Bayou24Bouef, and Bayou Black Deepening 25Project Feasibility Study26(St. Mary)27Payable from General Obligation Bonds28

Priority 2 $ 128,90029

Provided, however, that $128,900 of the Priority 2 appropriation for this project is used to30replace general obligation bond proceeds reappropriated to Executive Department, Division31of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,32Gustav and Ike, Planning and Construction (Statewide) in this Act.33

36/P17 PORT OF NEW ORLEANS34

(882) Cruise Ship Terminal, Planning and Construction35(Orleans)36Payable from General Obligation Bonds37

Priority 1 $ 7,500,00038

(1551) Milan Upland Yard Improvements39(Orleans)40Payable from General Obligation Bonds41

Priority 1 $ 990,00042Priority 5 $ 9,165,00043

Total $ 10,155,00044

36/P20 ST. BERNARD PORT45

( ) Rehabilitation of Dock #1 Section A Seawall,46Planning and Construction (Supplemental Funding)47(St. Bernard)48Payable from General Obligation Bonds49

Priority 5 $ 1,000,00050

ENROLLEDHB NO. 2

Page 80 of 202

36/P21 PORT OF SOUTH LOUISIANA1

(354) Globalplex Building #76 Repairs Including 2Roof Replacement3(St. John the Baptist)4Payable from General Obligation Bonds5

Priority 2 $ 2,995,0006Payable from the Balance of State General Fund7(Direct) Non-Recurring Revenues previously8allocated under the authority of Act 23 of 2012 9to the Port of South Louisiana, Warehouse,10Planning and Construction 11(St. John the Baptist) $ 1,500,00012Total $ 4,495,00013

(497) Administration Building14(St. John the Baptist)15Payable from General Obligation Bonds16

Priority 2 $ 2,345,00017Priority 5 $ 6,765,00018

Total $ 9,110,00019

(518) Stabilization of Levee at Globalplex Finger Pier20(St. John the Baptist)21Payable from General Obligation Bonds22

Priority 2 $ 2,345,00023

(1552) Globalplex Rail Siding ($5,577,93224Local/Federal/Other Match)25(St. John the Baptist)26Payable from General Obligation Bonds27

Priority 1 $ 2,990,00028

(1553) Globalplex Terminal Building #71 and Other29Globalplex Terminal Building Upgrades, Planning and 30Construction31(St. John the Baptist)32Payable from General Obligation Bonds33

Priority 1 $ 2,840,00034

(1554) Warehouse and Property Acquisition and35Improvements, Planning and Construction36(St. John the Baptist)37Payable from General Obligation Bonds38

Priority 1 $ 90,00039

(1555) Dock, Planning and Construction40(St. John the Baptist)41Payable from General Obligation Bonds42

Priority 1 $ 90,00043

36/P23 TERREBONNE PORT COMMISSION44

(293) Slip Dredging and Improvements for Terrebonne Port45Commission Government Multi-Use Complex, Planning 46and Construction47(Terrebonne)48Payable from General Obligation Bonds49

Priority 1 $ 1,260,00050Priority 5 $ 3,000,00051

Total $ 4,260,00052

ENROLLEDHB NO. 2

Page 81 of 202

36/P26 PORT OF LAKE CHARLES1

(1070) Relocation of Railroad Tracks along Sallier Street,2Planning and Construction ($2,600,000 Local Match)3(Calcasieu)4Payable from General Obligation Bonds5

Priority 5 $ 2,000,0006

(1486) Dredging of Berth 8 at City Docks, Planning and7Construction ($1,000,000 Local Match)8(Calcasieu)9Payable from General Obligation Bonds10

Priority 1 $ 250,00011

(1487) New Administration Building, Planning and12Construction ($1,500,000 Local Match)13(Calcasieu)14Payable from General Obligation Bonds15

Priority 1 $ 500,00016

(1488) Industrial Canal Dockside Monopile Improvements17(LEEVAC), Planning and Construction18(Calcasieu)19Payable from General Obligation Bonds20

Priority 1 $ 190,00021

(1489) Command and Control Center at City Docks22($1,125,000 Federal and/or Local Match)23(Calcasieu)24Payable from General Obligation Bonds25

Priority 1 $ 35,00026

36/P33 SOUTH TANGIPAHOA PARISH PORT COMMISSION27

(900) Port Manchac Terminal Improvements, Planning and 28Construction29(Tangipahoa)30Payable from General Obligation Bonds31

Priority 1 $ 460,00032Priority 2 $ 300,00033

Total $ 760,00034

36/P35 MERMENTAU RIVER HARBOR AND 35TERMINAL DISTRICT36

(1490) Land Acquisition for New Slip Construction37(Mermentau River Harbor Terminal District), Planning 38and Construction39(Acadia)40Payable from General Obligation Bonds41

Priority 1 $ 225,00042

36/P40 GRAND ISLE PORT COMMISSION43

(1273) Port Access Road and New Commercial Boat Slip44Facility45(Jefferson)46Payable from General Obligation Bonds47

Priority 1 $ 1,030,00048

ENROLLEDHB NO. 2

Page 82 of 202

36/P41 JEFFERSON PARISH PORT DISTRICT1

(1557) Jefferson Parish Business Park: Science and2Technology Academy and Conference Center3(Jefferson)4Payable from General Obligation Bonds5

Priority 1 $ 23,250,0006Priority 5 $ 5,500,0007

Total $ 28,750,0008

36/P43 COLUMBIA PORT COMMISSION9

(1150) Railroad Spur, Planning and Construction10(Caldwell)11Payable from General Obligation Bonds12

Priority 1 $ 2,000,00013

36/P47 GREATER OUACHITA PORT COMMISSION14

(1558) Rail Extension, Planning and Construction15(Ouachita)16Payable from General Obligation Bonds17

Priority 1 $ 595,00018

36/P49 POINTE COUPEE PORT COMMISSION19

(1559) Pointe Coupee Parish Port Capital Improvements,20Planning and Construction21(Pointe Coupee)22Payable from General Obligation Bonds23

Priority 1 $ 790,00024

MISCELLANEOUS NON-STATE25

50/C03 OFFICE FACILITIES CORPORATION26

(1560) Capital Repairs and Improvements, Planning and27Construction28(Statewide)29Payable from General Obligation Bonds30

Priority 5 $ 15,000,00031

50/J03 ASCENSION PARISH32

(792) Lamar Dixon Expo Center Recreational Complex,33Planning and Construction34(Ascension)35Payable from General Obligation Bonds36

Priority 1 $ 300,00037Priority 2 $ 950,00038

Total $ 1,250,00039

(1172) St. Landry/Edenborne Connector Road40(Ascension)41Payable from General Obligation Bonds42

Priority 2 $ 2,500,00043Priority 5 $ 4,100,00044

Total $ 6,600,00045

ENROLLEDHB NO. 2

Page 83 of 202

(1561) Oak Grove Community and Recreational Center,1Planning and Construction 2(Ascension)3Payable from General Obligation Bonds4

Priority 1 $ 235,0005

(1562) Lamar Dixon Development, Purchase and Land6Acquisition7(Ascension)8Payable from General Obligation Bonds9

Priority 1 $ 95,00010

50/J04 ASSUMPTION PARISH11

(1491) Overlay of Bayou Drive, Planning and Construction12(Assumption)13Payable from General Obligation Bonds14

Priority 1 $ 120,00015Priority 5 $ 1,530,00016

Total $ 1,650,00017

(1491) Overlay of Bayou Drive, Planning and Construction18(Assumption)19Payable from General Obligation Bonds20

Priority 2 $ 275,00021

50/J05 AVOYELLES PARISH22

(1493) Avoyelles Parish Police Jury Cooperative Extension23Building, Acquisitions, Planning and Construction 24($50,000 Non-State Match)25(Avoyelles)26Payable from General Obligation Bonds27

Priority 1 $ 10,00028

50/J06 BEAUREGARD PARISH29

(1016) Crosby, Butler and Pleasant Hill Roads30(Beauregard)31Payable from General Obligation Bonds32

Priority 2 $ 825,00033

(1495) Lumas Road, Planning and Construction34(Beauregard)35Payable from General Obligation Bonds36

Priority 1 $ 390,00037Priority 5 $ 100,00038

Total $ 490,00039

(2144) Playground Equipment and Other Related Improvements40at Purple Heart Park, Planning and Construction41(Beauregard)42Payable from General Obligation Bonds43

Priority 2 $ 20,00044

Pending approval of a capital outlay budget request pursuant to the provisions of R.S.4539:112.46

ENROLLEDHB NO. 2

Page 84 of 202

50/J07 BIENVILLE PARISH1

(1496) Courthouse Improvements in Arcadia, Planning and2Construction ($115,000 Non-State Match)3(Bienville)4Payable from General Obligation Bonds5

Priority 1 $ 40,0006

(1981) Bienville Parish Jail ($5,034,000 Cash and/or In-Kind7Match)8(Bienville)9Payable from General Obligation Bonds10

Priority 5 $ 50,00011

(1982) Blue Ridge Water System12(Bienville)13Payable from General Obligation Bonds14

Priority 5 $ 490,00015

50/J08 BOSSIER PARISH16

(706) South Bossier Park Construction of17New Pavilions, Planning and Construction18(Bossier)19Payable from General Obligation Bonds20

Priority 2 $ 80,00021

(752) Sewerage District No. 1 of the Parish of Bossier, 22Planning and Construction ($28,000,000 Local Match)23(Bossier)24Payable from General Obligation Bonds25

Priority 1 $ 14,035,00026

(811) Cotton Valley Road Reconstruction, Planning and27Construction28(Bossier)29Payable from General Obligation Bonds30

Priority 1 $ 255,00031

(813) Acceleration Lane on US 71, Planning and32Construction 33(Bossier)34Payable from General Obligation Bonds35

Priority 2 $ 150,00036

(814) Extension of Crouch Road to Swan Lake37Road/Reconstruction of Swan Lake Road To I-220, 38Planning and Construction (Local Match Required)39(Bossier)40Payable from General Obligation Bonds41

Priority 1 $ 285,00042

(1564) Princeton Sports Complex - Fencing and Lighting at43New Ball Fields, Planning and Construction44(Bossier)45Payable from General Obligation Bonds46

Priority 1 $ 20,00047

ENROLLEDHB NO. 2

Page 85 of 202

50/J09 CADDO PARISH1

(1565) Caddo Parish Fire District No. 3, Station #4, 2Planning and Construction3(Caddo)4Payable from General Obligation Bonds5

Priority 1 $ 160,0006

50/J10 CALCASIEU PARISH7

(228) Gravity Sewer Trunk Mains and Pumping Stations8South Ward 3 and South Ward 4, Planning 9and Construction10(Calcasieu)11Payable from General Obligation Bonds12

Priority 1 $ 3,890,00013Priority 5 $ 9,300,00014

Total $ 13,190,00015

50/J11 CALDWELL PARISH16

(1110) Recreation Facilities Construction, Reconstruction,17Planning and Construction 18(Caldwell)19Payable from General Obligation Bonds20

Priority 2 $ 185,00021Priority 5 $ 1,465,00022

Total $ 1,650,00023

(1497) Wiles Road and Kountry Korner Road 24Reconstruction, Planning and Construction25(Caldwell)26Payable from General Obligation Bonds27

Priority 1 $ 505,00028

(1498) Parish Detention Facility, Planning and Construction29(Caldwell)30Payable from General Obligation Bonds31

Priority 1 $ 245,00032Priority 5 $ 1,370,00033

Total $ 1,615,00034

50/J12 CAMERON PARISH35

(1499) Holly Beach Sewer, Planning and Construction36(Cameron)37Payable from General Obligation Bonds38

Priority 1 $ 4,965,00039

50/J13 CATAHOULA PARISH40

(1111) Catahoula Parish Courthouse Roof, Planning and41Renovations42(Catahoula)43Payable from General Obligation Bonds44

Priority 1 $ 975,00045Priority 2 $ 80,00046

Total $ 1,055,00047

ENROLLEDHB NO. 2

Page 86 of 202

50/J15 CONCORDIA PARISH1

(762) Concordia Parish Courthouse District Courtroom2Security and Safety Renovations 3(Concordia)4Payable from General Obligation Bonds5

Priority 2 $ 315,0006

(1500) Concordia Parish Public Health Center Renovation,7Planning and Construction8(Concordia)9Payable from General Obligation Bonds10

Priority 1 $ 200,00011

50/J16 DE SOTO PARISH12

(719) DeSoto Parish Police Jury - Alumni Park Phase II,13Planning and Construction14(DeSoto)15Payable from General Obligation Bonds16

Priority 1 $ 50,00017

50/J18 EAST CARROLL PARISH18

(1180) East Carroll Parish Road Improvements 19(East Carroll)20Payable from General Obligation Bonds21

Priority 1 $ 15,00022

(1567) Industrial Site Development and Road Improvements23(For Economic Development Purposes, Including but not 24Limited to an Ethanol Plant), Planning and Construction25(East Carroll)26Payable from General Obligation Bonds27

Priority 1 $ 965,00028

(1568) Courthouse and Jail Renovations 29(East Carroll)30Payable from General Obligation Bonds31

Priority 1 $ 555,00032

50/J19 EAST FELICIANA PARISH33

(1569) Courthouse Improvements, Planning, Acquisitions,34Renovations and Construction ($1,000,000 Cash 35and/or In-Kind Match)36(East Feliciana)37Payable from General Obligation Bonds38

Priority 5 $ 2,700,00039

50/J21 FRANKLIN PARISH40

(593) Franklin Parish Activity Center, Planning and41Construction ($250,000 Local Match)42(Franklin)43Payable from General Obligation Bonds44

Priority 1 $ 1,325,00045Priority 5 $ 1,360,00046

Total $ 2,685,00047

ENROLLEDHB NO. 2

Page 87 of 202

(1173) Ernest Road at Deer Creek Bridge Replacement,1Planning and Construction 2(Franklin)3Payable from General Obligation Bonds4

Priority 2 $ 220,0005

(1502) Parish Road Improvements6(Franklin)7Payable from General Obligation Bonds8

Priority 1 $ 200,0009

(1503) Courthouse Renovations, Planning and Construction10(Franklin)11Payable from General Obligation Bonds12

Priority 1 $ 45,00013Priority 2 $ 360,00014

Total $ 405,00015

50/J22 GRANT PARISH16

(1162) Southern Grant Sewerage System17Construction, Planning and Construction18(Grant)19Payable from General Obligation Bonds20

Priority 5 $ 2,000,00021

(1504) Southern Grant Sewerage System Improvements, Study,22Design, Planning and Construction23(Grant)24Payable from General Obligation Bonds25

Priority 1 $ 1,415,00026

(1505) Regional Economic Development Building,27Rehabilitation, Planning and Construction28(Grant)29Payable from General Obligation Bonds30

Priority 1 $ 290,00031

50/J23 IBERIA PARISH32

(676) Road Extension from Sidney Blanchard Road to Ed33Broussard Road, Planning and Construction34(Iberia)35Payable from General Obligation Bonds36

Priority 1 $ 150,00037Priority 2 $ 50,00038

Total $ 200,00039

(746) LA 87 Improvements, Planning and Construction40(Iberia )41Payable from General Obligation Bonds42

Priority 2 $ 225,00043Priority 5 $ 2,480,00044

Total $ 2,705,00045

(1506) Robert B. Green Veterans Memorial Building46Renovation, Upgrade and Expansion Project for Robert B. 47Green American Legion Post 533 and Perry Thompson 48VFW Post 12065, Planning and Construction49(Iberia)50Payable from General Obligation Bonds51

Priority 1 $ 200,00052

ENROLLEDHB NO. 2

Page 88 of 202

(1507) Walking Track - Rynella Park, Planning and1Construction2(Iberia)3Payable from General Obligation Bonds4

Priority 1 $ 10,0005

(1508) Wastewater System Improvements for the Acadiana6Regional Airport ($667,000 Non-State Match)7(Iberia)8Payable from General Obligation Bonds9

Priority 1 $ 630,00010

(1509) Sugar Cane Festival Building Improvements, Planning11and Construction12(Iberia)13Payable from General Obligation Bonds14

Priority 1 $ 5,00015

(1510) Five Lane Road Extension from Highway 675 to16Highway 3212, Planning and Construction17(Iberia)18Payable from General Obligation Bonds19

Priority 1 $ 2,660,00020

(1511) Recreational Complex, Sports Including Baseball,21Planning and Construction (Supplemental Funding)22(Iberia)23Payable from General Obligation Bonds24

Priority 1 $ 100,00025Priority 2 $ 100,00026Priority 5 $ 150,00027

Total $ 350,00028

50/J24 IBERVILLE PARISH29

(1096) New Iberville Parish Hospital - Acquisition of Property,30Planning and Construction31(Iberville)32Payable from General Obligation Bonds33

Priority 1 $ 2,990,00034

50/J25 JACKSON PARISH35

(727) Jackson Parish Riding Arena and Livestock Pavilion,36Planning and Construction37(Jackson)38Payable from General Obligation Bonds39

Priority 2 $ 195,00040Priority 5 $ 1,405,00041

Total $ 1,600,00042

50/J26 JEFFERSON PARISH43

(52) 11th Street Roadway Replacement and Upgrade44of Subsurface Drainage System between Queens45and Manhattan Boulevard, Planning and Construction46(Jefferson)47Payable from General Obligation Bonds48

Priority 2 $ 100,00049

ENROLLEDHB NO. 2

Page 89 of 202

(54) 18th Street Drainage Improvements, Edenborn Avenue1Phase 2 (18th Street to West Esplanade Avenue Canal) 2(Jefferson)3Payable from General Obligation Bonds4

Priority 1 $ 95,0005

(58) Airline Drive (US 61) at 17th Street Canal Drainage6Crossing and Railroad Bridge Replacement, Planning 7and Construction8(Jefferson)9Payable from General Obligation Bonds10

Priority 1 $ 1,990,00011

(59) Ames Boulevard Widening from Two Lanes to Three12Lanes Between Barataria Boulevard and Bayou Boeuf 13Drive (2.0 miles) with Installation of Subsurface Drainage 14(Jefferson)15Payable from General Obligation Bonds16

Priority 1 $ 1,490,00017Priority 5 $ 3,340,00018

Total $ 4,830,00019

(63) Bike Path Along Leo Kerner Parkway (Barataria Blvd.20to Parc des Familles Entrance), Planning and Construction21(Jefferson)22Payable from General Obligation Bonds23

Priority 1 $ 60,00024

(65) Bonnabel Canal Rehabilitation and Bank Stabilization25(Veterans Boulevard to West Esplanade), Planning and 26Construction27(Jefferson)28Payable from General Obligation Bonds29

Priority 1 $ 4,340,00030

(66) Breaux Ditch Improvements (U-Channel Installation31from East Ames to Lafitte Larose Highway), Planning 32and Construction33(Jefferson)34Payable from General Obligation Bonds35

Priority 1 $ 120,00036Priority 5 $ 1,225,00037

Total $ 1,345,00038

(72) Canal 10 Concrete Lining and Box Culvert Installation39at Vintage Drive, Planning and Construction40(Jefferson)41Payable from General Obligation Bonds42

Priority 1 $ 95,00043Priority 2 $ 25,00044

Total $ 120,00045

(73) Canal 10 Concrete Lining Widening Between Canal 746and West Esplanade Avenue, Planning and Construction47(Jefferson)48Payable from General Obligation Bonds49

Priority 1 $ 45,00050Priority 2 $ 25,00051

Total $ 70,00052

ENROLLEDHB NO. 2

Page 90 of 202

(74) Canal Street Roadway Reconstruction and Installation1of Subsurface Drainage Between I-10 and Lake Avenue 2(Jefferson)3Payable from General Obligation Bonds4

Priority 1 $ 25,0005

(75) Carol Sue Avenue Drainage Improvements, Planning6and Construction7(Jefferson)8Payable from General Obligation Bonds9

Priority 1 $ 1,590,00010

(79) Codifier Boulevard, Homestead Avenue, and11Brockenbraugh Court Subsurface Drainage 12Improvements, Planning and Construction13(Jefferson)14Payable from General Obligation Bonds15

Priority 1 $ 195,00016

(86) East Jefferson Drainage Relief: Subsurface Drainage17Improvements to Garden Road, Tallulah, Sauve Road, and 18Midway Drive, and Replacement of the Citrus and Sauve 19Bridges over Soniat Canal20(Jefferson)21Payable from General Obligation Bonds22

Priority 1 $ 95,00023

(92) Jefferson Community Health Center Expansion to the24Existing River Ridge Facility In Order to Implement a 25Dental Program, Planning and Construction 26(Jefferson)27Payable from General Obligation Bonds28

Priority 1 $ 50,00029

(95) Jefferson Parish Housing Authority Street Lighting and30Security Upgrades (Between Betty and Julie Street in the 31East-West Direction and Acre and Lapalco in the 32North-South Direction), Planning and Construction33(Jefferson)34Payable from General Obligation Bonds35

Priority 5 $ 325,00036

(101) Latigue Street Roadway Improvements, Planning37and Construction38(Jefferson)39Payable from General Obligation Bonds40

Priority 2 $ 700,00041

(103) Livingston Place (Metairie Road to Loumor Avenue)42(Jefferson)43Payable from General Obligation Bonds44

Priority 1 $ 3,590,00045

(108) Martin Luther King Playground Improvements,46Planning and Construction47(Jefferson)48Payable from General Obligation Bonds49

Priority 1 $ 100,00050

ENROLLEDHB NO. 2

Page 91 of 202

(111) Multi-Purpose Recreational and Achievement Center 1(Jefferson)2Payable from General Obligation Bonds3

Priority 1 $ 4,985,0004

(116) Parc des Familles, Construction of Utilities, Restrooms,5Pavilions and Roadways in Raw Undeveloped Wooded 6Area in Order to Initiate Construction of Regional Park, 7Planning and Construction8(Jefferson)9Payable from General Obligation Bonds10

Priority 1 $ 3,525,00011

(117) Parish Line Drainage Pump Station Capacity12Increase, Planning and Construction13(Jefferson)14Payable from General Obligation Bonds15

Priority 2 $ 25,00016

(118) Performing Arts Center Modifications 17(Jefferson)18Payable from General Obligation Bonds19

Priority 1 $ 6,740,00020

(119) Performing Arts Center, Planning and Construction21($1,250,000 Local Match) 22(Jefferson)23Payable from General Obligation Bonds24

Priority 1 $ 3,855,00025

(127) South Kenner Road Rehabilitation from Live Oak26Boulevard to River Road, Planning and Construction27(Jefferson)28Payable from General Obligation Bonds29

Priority 1 $ 640,00030Priority 5 $ 5,140,00031

Total $ 5,780,00032

(129) Terry Parkway Drainage Between Carol Sue Drive and33Industry Canal ($500,000 Local Match) 34(Jefferson)35Payable from General Obligation Bonds36

Priority 1 $ 5,000,00037Priority 2 $ 1,137,00038Priority 5 $ 3,000,00039

Total $ 9,137,00040

Provided, however, that $1,137,000 of the Priority 2 appropriation for this project is used to41replace general obligation bond proceeds reappropriated to Executive Department, Division42of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,43Gustav and Ike, Planning and Construction (Statewide) in this Act.44

(131) Upper Kraak Ditch Drainage Pump Station Pump45Replacement and Generator Installation 46(Jefferson)47Payable from General Obligation Bonds48

Priority 1 $ 1,650,00049

ENROLLEDHB NO. 2

Page 92 of 202

(132) Upper Kraak Ditch Subsurface Drainage Improvement1(Upper Kraak Drainage Pump Station to Earhart 2Expressway), Planning and Construction3(Jefferson)4Payable from General Obligation Bonds5

Priority 1 $ 245,0006Priority 2 $ 50,0007

Total $ 295,0008

(134) Waggaman Subsurface Drainage Improvements,9Planning and Construction10(Jefferson)11Payable from General Obligation Bonds12

Priority 1 $ 730,00013

(135) Walkertown Bus Terminal, Planning and Construction14(Jefferson)15Payable from General Obligation Bonds16

Priority 1 $ 95,00017

(137) Sewer Lift Station Backup Generators - South, 18Planning and Construction 19(Jefferson)20Payable from General Obligation Bonds21

Priority 2 $ 100,00022

(138) Sewer Lift Station Backup Generators - North,23Planning and Construction24(Jefferson)25Payable from General Obligation Bonds26

Priority 2 $ 100,00027

(139) West Bank Code Enforcement Building, Planning and28Construction 29(Jefferson)30Payable from General Obligation Bonds31

Priority 2 $ 640,00032Priority 5 $ 2,940,00033

Total $ 3,580,00034

(143) Woodland West Drainage Improvements 35(Jefferson)36Payable from General Obligation Bonds37

Priority 1 $ 145,00038

(144) Woodmere Community Center, Real Estate39Acquisition, Planning, and Construction ($15,000 Match)40(Jefferson)41Payable from General Obligation Bonds42

Priority 1 $ 735,00043

(146) Avondale Booster Club and Playground Upgrades,44Planning and Construction45(Jefferson)46Payable from General Obligation Bonds47

Priority 1 $ 400,00048

ENROLLEDHB NO. 2

Page 93 of 202

(346) Lafreniere Park Marsh Island Restoration, Planning1and Construction2(Jefferson)3Payable from General Obligation Bonds4

Priority 2 $ 125,0005Priority 5 $ 1,000,0006

Total $ 1,125,0007

(435) Riverside Senior Center, Planning 8and Construction9(Jefferson)10Payable from General Obligation Bonds11

Priority 2 $ 825,00012Priority 5 $ 2,050,00013

Total $ 2,875,00014

(1074) Gretna Government Complex Parking Lot, Planning15and Construction16(Jefferson)17Payable from General Obligation Bonds18

Priority 2 $ 1,440,00019

( ) Fire Station Repairs and Maintenance, Planning20and Construction21(Jefferson)22Payable from State General Fund by Statutory23Dedications out of the Fire Marshal Fund $ 900,00024

Pending approval of a capital outlay budget request pursuant to the provisions of R.S.2539:112.26

50/J27 JEFFERSON DAVIS PARISH27

(1259) Regional Consolidated Jail Facility, Acquisition, Planning 28and Construction29(Jefferson Davis)30Payable from General Obligation Bonds31

Priority 1 $ 1,835,00032Priority 5 $ 8,165,00033

Total $ 10,000,00034

(1516) Third Street West Bridge Repair, Planning and35Construction36(Jefferson Davis)37Payable from General Obligation Bonds38

Priority 1 $ 45,00039

50/J28 LAFAYETTE PARISH40

(232) Kaliste Saloom Widening41(Lafayette)42Payable from General Obligation Bonds43

Priority 1 $ 3,945,00044Priority 2 $ 3,093,40045Priority 5 $ 8,890,00046

Total $ 15,928,40047

Provided, however, that $93,400 of the Priority 2 appropriation for this project is used to48replace general obligation bond proceeds reappropriated to Executive Department, Division49of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,50Gustav and Ike, Planning and Construction (Statewide) in this Act.51

ENROLLEDHB NO. 2

Page 94 of 202

(233) Governmental Complex, Jail Physical Plant Upgrade,1Planning and Construction ($4,980,000 Non-State Match)2(Lafayette)3Payable from General Obligation Bonds4

Priority 1 $ 500,0005Priority 5 $ 1,500,0006

Total $ 2,000,0007

(234) Parish Governmental Complex - Parish Courthouse,8Planning and Construction9(Lafayette)10Payable from General Obligation Bonds11

Priority 1 $ 240,00012Priority 2 $ 460,00013

Total $ 700,00014

(881) Lafayette Central Park Improvements 15(Lafayette)16Payable from General Obligation Bonds17

Priority 2 $ 750,00018Priority 5 $ 9,250,00019

Total $ 10,000,00020

50/J29 LAFOURCHE PARISH21

(927) South Lafourche Airport Corridor Project 22(Lafourche)23Payable from General Obligation Bonds24

Priority 5 $ 6,625,00025

(1527) Company Canal Pump Station, Planning and26Construction ($283,236 Cash and/or In-Kind Match)27(Lafourche)28Payable from General Obligation Bonds29

Priority 1 $ 930,00030

(1528) Fishing Pier at the Leeville Boat Launch, Planning and31Construction32(Lafourche)33Payable from General Obligation Bonds34

Priority 1 $ 500,00035

50/J30 LASALLE PARISH36

(844) LaSalle Parish Fair Grounds Barn Renovation, Planning37and Construction 38(LaSalle)39Payable from General Obligation Bonds40

Priority 2 $ 225,00041

(1530) Pine Hill Road Improvements, Planning and42Construction43(LaSalle)44Payable from General Obligation Bonds45

Priority 1 $ 665,00046

ENROLLEDHB NO. 2

Page 95 of 202

50/J32 LIVINGSTON PARISH1

(721) Cook Road Extension Economic Development Corridor2(Pete's Highway Frontage Road) 3(Livingston)4Payable from General Obligation Bonds5

Priority 1 $ 900,0006Priority 5 $ 4,000,0007

Total $ 4,900,0008

(722) Livingston Parish Regional Airport, Planning and9Construction ($900,000 Federal Funds)10(Livingston)11Payable from General Obligation Bonds12

Priority 1 $ 100,00013

(1581) Livingston Parish Animal Shelter14(Livingston)15Payable from General Obligation Bonds16

Priority 1 $ 70,00017

(1582) Livingston Parish Recreation District 2 Equipment18(Livingston)19Payable from General Obligation Bonds20

Priority 1 $ 20,00021

(1584) Twenty-First Judicial District Complex22(Livingston)23Payable from General Obligation Bonds24

Priority 1 $ 10,00025

(1586) District 9 Fire Station, Planning and Construction26(Livingston)27Payable from General Obligation Bonds28

Priority 1 $ 100,00029

50/J33 MADISON PARISH30

(1532) Charles Brown Road (Tendal Road) Repairs, Planning31and Construction32(Madison)33Payable from General Obligation Bonds34

Priority 1 $ 195,00035

(1533) Health Unit, Planning and Construction ($200,000 Cash36or In-Kind Match Required)37(Madison)38Payable from General Obligation Bonds39

Priority 1 $ 145,00040Priority 5 $ 405,00041

Total $ 550,00042

50/J34 MOREHOUSE PARISH43

(1583) Carl Road Improvements, Construction44(Morehouse)45Payable from General Obligation Bonds46

Priority 1 $ 500,00047Priority 2 $ 500,00048

Total $ 1,000,00049

ENROLLEDHB NO. 2

Page 96 of 202

50/J35 NATCHITOCHES PARISH1

(926) Natchitoches Parish Office of Community Services,2Addition and Renovation 3(Natchitoches)4Payable from General Obligation Bonds5

Priority 1 $ 45,0006

(937) Courthouse Security Improvements, Planning and7Construction8(Natchitoches)9Payable from General Obligation Bonds10

Priority 2 $ 100,00011Priority 5 $ 380,00012

Total $ 480,00013

(938) Hard Surfacing of Coco Bed Road, Phase 1, Planning 14and Construction15(Natchitoches)16Payable from General Obligation Bonds17

Priority 1 $ 100,00018Priority 2 $ 180,00019

Total $ 280,00020

(1539) Old River Bridge, Planning and Construction21(Natchitoches)22Payable from General Obligation Bonds23

Priority 1 $ 525,00024Priority 2 $ 980,00025

Total $ 1,505,00026

50/J37 OUACHITA PARISH27

(1540) Bayou DeSiard Ecosystem Restoration ($1,915,36828Federal Match)29(Ouachita)30Payable from General Obligation Bonds31

Priority 1 $ 880,00032

(1589) Extension of Interstate 20 Frontage Road East,33including a Bridge across Bennett Bayou, Acquisitions, 34Planning and Construction ($1,114,000 Cash and/or 35In-Kind Match, of which no more than $250,000 will 36be expended in Year 1)37(Ouachita)38Payable from General Obligation Bonds39

Priority 1 $ 70,00040

50/J38 PLAQUEMINES PARISH41

(265) Emergency Evacuation Complex, Planning and42Construction 43(Plaquemines)44Payable from General Obligation Bonds45

Priority 1 $ 490,00046Priority 5 $ 1,750,00047

Total $ 2,240,00048

ENROLLEDHB NO. 2

Page 97 of 202

(1590) Peters Road Bridge and Extension, Planning1and Construction2(Plaquemines)3Payable from General Obligation Bonds4

Priority 5 $ 51,800,0005

(1591) Belle Chasse Parks, Planning and Construction6(Plaquemines)7Payable from General Obligation Bonds8

Priority 1 $ 120,0009

(1594) Belle Chasse Water Tower, Planning and Construction10(Plaquemines)11Payable from General Obligation Bonds12

Priority 5 $ 20,00013

50/J39 POINTE COUPEE PARISH14

(1253) False River Ecosystem Restoration Project, Planning15and Construction16(Pointe Coupee)17Payable from General Obligation Bonds18

Priority 1 $ 2,690,00019

(1596) Regional Fence Line Monitoring, Planning and20Equipment21(Pointe Coupee)22Payable from General Obligation Bonds23

Priority 1 $ 200,00024

(2067) Emergency Communications Equipment25(Pointe Coupee)26Payable from General Obligation Bonds27

Priority 2 $ 200,00028

50/J40 RAPIDES PARISH29

(1544) Cotile Indian Creek and Kincaid Outflow Gate30Repair/Replacement (Cash and/or In-Kind Match 31Required)32(Rapides)33Payable from General Obligation Bonds34

Priority 1 $ 25,00035

50/J41 RED RIVER PARISH36

(525) Health Unit and Administrative Offices, Planning and37Construction38(Red River)39Payable from General Obligation Bonds40

Priority 2 $ 250,00041Priority 5 $ 50,00042

Total $ 300,00043

50/J42 RICHLAND PARISH44

(852) Sapa Drive Improvements, Planning and Construction45(Richland)46Payable from General Obligation Bonds47

Priority 1 $ 245,00048

ENROLLEDHB NO. 2

Page 98 of 202

(853) Richland Parish Courthouse Renovations 1(Richland)2Payable from General Obligation Bonds3

Priority 1 $ 30,0004

50/J43 SABINE PARISH5

(1545) Plainview Road Rehabilitation, Planning and6Construction7(Sabine)8Payable from General Obligation Bonds9

Priority 1 $ 2,630,00010Priority 2 $ 1,400,00011Priority 5 $ 3,000,00012

Total $ 7,030,00013

(1546) Water Treatment and Supply System Study14(Sabine)15Payable from General Obligation Bonds16

Priority 1 $ 300,00017

50/J44 ST. BERNARD PARISH18

(1597) St. Bernard Parish Tourist Commission, Planning and19Construction20(St. Bernard)21Payable from General Obligation Bonds22

Priority 1 $ 20,00023

(1598) New Hospital and Medical Office Building, Real Estate24Acquisition, Planning and Construction25(St. Bernard)26Payable from General Obligation Bonds27

Priority 1 $ 885,00028

(1980) Judicial Government Complex Renovation and29Expansion, Planning and Construction30(St. Bernard)31Payable from General Obligation Bonds32

Priority 5 $ 490,00033

50/J45 ST. CHARLES PARISH34

(1599) West Bank Hurricane Protection Levee35(St. Charles)36Payable from General Obligation Bonds37

Priority 1 $ 1,015,00038Payable from the balance of General Obligation39Bond proceeds previously allocated under the40authority of Act No. 24 of 2013 for St. Charles41Parish, West Bank Ground Storage Tank42(St. Charles); and Act No. 24 of 2013 for St.43Charles Parish, East Bank Clarifier, Planning44and Construction (St. Charles) $ 72,54545Total $ 1,087,54546

(1662) East Bank Clarifier, Planning and Construction47(St. Charles)48Payable from General Obligation Bonds49

Priority 1 $ 50,00050

ENROLLEDHB NO. 2

Page 99 of 202

(1663) St. Charles West Bank Ground Storage Tank1(St. Charles)2Payable from General Obligation Bonds3

Priority 1 $ 70,0004

(1666) St. Charles Emergency Operations Center5(St. Charles)6Payable from General Obligation Bonds7

Priority 1 $ 120,0008

(1978) Airline Drive (US 61) at the St. Charles/Jefferson9Parish Line Raising, Planning and Construction10(Jefferson, St. Charles)11Payable from General Obligation Bonds12

Priority 1 $ 90,00013

50/J46 ST. HELENA PARISH14

(825) St. Helena Parish Audubon Library 15(St. Helena)16Payable from General Obligation Bonds17

Priority 2 $ 100,00018Priority 5 $ 1,340,00019

Total $ 1,440,00020

(1053) Emergency ADA and Life Safety Renovations to the21Court House, Planning and Construction ($2,680,000 22Federal Funds)23(St. Helena)24Payable from General Obligation Bonds25

Priority 1 $ 400,00026

(1667) Eddy Road Improvements, Planning and Construction27(St. Helena)28Payable from General Obligation Bonds29

Priority 1 $ 10,00030

50/J47 ST. JAMES PARISH31

(294) St. James Parish Land Acquisition, Planning and32Construction 33(St. James)34Payable from General Obligation Bonds35

Priority 1 $ 15,100,00036Priority 5 $ 3,000,00037

Total $ 18,100,00038

(942) St. James Parish Eastbank Master Drainage Plan,39Planning and Construction40(St. James)41Payable from General Obligation Bonds42

Priority 5 $ 85,00043

(1189) Blind River Freshwater Diversion 44(St. James)45Payable from General Obligation Bonds46

Priority 2 $ 1,700,00047Priority 5 $ 19,200,00048

Total $ 20,900,00049

ENROLLEDHB NO. 2

Page 100 of 202

50/J48 ST. JOHN THE BAPTIST PARISH1

(695) River Forest Canal Extension Project, Planning2and Construction3(St. John the Baptist)4Payable from General Obligation Bonds5

Priority 2 $ 135,0006

(1257) Laplace Peavine Park Lights, Planning7and Construction8(St. John the Baptist)9Payable from General Obligation Bonds10

Priority 2 $ 10,00011

(1671) West Bank Courthouse Security System, Planning and12Construction13(St. John the Baptist)14Payable from General Obligation Bonds15

Priority 1 $ 45,00016Priority 5 $ 45,00017

Total $ 90,00018

(1673) East Bank Courthouse, Planning and Construction19(St. John the Baptist)20Payable from General Obligation Bonds21

Priority 1 $ 30,00022Priority 5 $ 30,00023

Total $ 60,00024

(1974) Woodland Road between Cambridge and Belle Terre,25LA Hwy 318826(St. John the Baptist)27Payable from General Obligation Bonds28

Priority 5 $ 100,00029

50/J49 ST. LANDRY PARISH30

(348) Airport Hangars, Planning and Construction31(St. Landry)32Payable from General Obligation Bonds33

Priority 2 $ 350,00034

(1347) Delta Grand Upgrade Lighting Project35(St. Landry)36Payable from General Obligation Bonds37

Priority 2 $ 75,00038

(1549) Hurricane Evacuations and Homeland Security39Coordination and Related Renovations, Planning 40and Construction41(St. Landry)42Payable from General Obligation Bonds43

Priority 1 $ 190,00044

50/J50 ST. MARTIN PARISH45

(906) General Improvements to Parks and Recreational46Facilities, Planning and Construction47(St. Martin)48Payable from General Obligation Bonds49

Priority 2 $ 50,00050

ENROLLEDHB NO. 2

Page 101 of 202

(907) I-10 Frontage Road, LA 328 to LA 347, Planning and1Construction2(St. Martin)3Payable from General Obligation Bonds4

Priority 2 $ 383,0005Priority 5 $ 4,550,0006

Total $ 4,933,0007

Provided, however, that $383,000 of the Priority 2 appropriation for this project is used to8replace general obligation bond proceeds reappropriated to Executive Department, Division9of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,10Gustav and Ike, Planning and Construction (Statewide) in this Act.11

(908) T-Bayou Drainage Improvements (Local Match12Required)13(St. Martin)14Payable from General Obligation Bonds15

Priority 5 $ 30,00016

(909) Road Improvements on Four-Mile Bayou Road 17(St. Martin)18Payable from General Obligation Bonds19

Priority 1 $ 295,00020

50/J51 ST. MARY PARISH21

(327) Reconstruction of Chitimacha Trail Road from LA 32822to LA 670 for St Mary Parish Government Within Existing 23Rights-of-Way24(St. Mary)25Payable from General Obligation Bonds26

Priority 2 $ 300,00027Priority 5 $ 760,00028

Total $ 1,060,00029

(328) Reconstruction of Flattown Road from Chitimacha30Trail to Ralph Darden Memorial Parkway for St Mary 31Parish Government Within existing Rights-of-Way32(St. Mary)33Payable from General Obligation Bonds34

Priority 2 $ 100,00035Priority 5 $ 450,00036

Total $ 550,00037

(331) Reconstruction of Charenton Beach Road from LA38Hwy. 87 to the West Atchafalaya Basin Protection Levee, 39Planning and Construction40(St. Mary)41Payable from General Obligation Bonds42

Priority 1 $ 300,00043Priority 5 $ 785,00044

Total $ 1,085,00045

(332) Installation of Culverts and Associated Infrastructure46in Middle Road Drainage Canal - Bayou Vista La.47for Sub-Gravity Drainage District #1 of 48St. Mary Parish Gravity Drainage District #2, 49Planning and Construction50(St. Mary)51Payable from General Obligation Bonds52

Priority 1 $ 450,00053Priority 2 $ 200,00054

Total $ 650,00055

ENROLLEDHB NO. 2

Page 102 of 202

(339) Recreation and Infrastructure Improvements at1Centerville Park, Planning and Construction2(St. Mary)3Payable from General Obligation Bonds4

Priority 1 $ 75,0005

(679) Capital Improvements and Construction for Recreation 6District #3, Planning and Construction7(St. Mary)8Payable from General Obligation Bonds9

Priority 2 $ 75,00010

(1570) Infrastructure Improvements at the Charenton Canal11Industrial Park12(St. Mary)13Payable from General Obligation Bonds14

Priority 1 $ 2,215,00015

(1572) Recreational Improvements at Kemper Williams Park,16Acquisitions, Installation, Planning and Construction 17($50,000 Local Match)18(St. Mary)19Payable from General Obligation Bonds20

Priority 1 $ 290,00021

(1573) St. Mary Parish Sewage District #5 Sewer Lift Station22Improvements23(St. Mary)24Payable from General Obligation Bonds25

Priority 1 $ 95,00026

(1574) DeGravelle Access Road to Duhon Bypass Road in27Amelia, Planning and Construction28(St. Mary)29Payable from General Obligation Bonds30

Priority 1 $ 180,00031

(1575) Plantation Pump Station Replacement for Sub-Gravity32Drainage District #1 of St. Mary Parish Gravity Drainage 33District #2, Planning and Construction34(St. Mary)35Payable from General Obligation Bonds36

Priority 1 $ 470,00037

(1576) Cajun Coast Welcome Center and Tower Overlook for38the Tourist Commission dba Cajun Coast Visitors and 39Convention Bureau, Planning and Construction 40($2,121,324 Local Funds)41(St. Mary)42Payable from General Obligation Bonds43

Priority 5 $ 1,000,00044

(1577) Access Road from Baker Hughes to Port Road in45Morgan City, Planning and Construction 46($200,000 Local Match)47(St. Mary)48Payable from General Obligation Bonds49

Priority 1 $ 810,00050

ENROLLEDHB NO. 2

Page 103 of 202

(2109) New Hospital in Franklin for Hospital 1Service District 1, Planning and Construction2($8,200,000 Local Match)3(St. Mary)4Payable from General Obligation Bonds5

Priority 2 $ 90,0006

Provided, however, that $90,000 of the Priority 2 appropriation for this project is used to7replace general obligation bond proceeds reappropriated to Executive Department, Division8of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,9Gustav and Ike, Planning and Construction (Statewide) in this Act.10

50/J52 ST. TAMMANY PARISH11

(598) South Slidell Levee Protection Rehabilitation 12(USACE 533d Report for Levees West and East 13of I-10 Planning and Construction14(St. Tammany)15Payable from General Obligation Bonds16

Priority 1 $ 1,545,00017Priority 5 $ 8,535,00018

Total $ 10,080,00019

(599) Camp Salmen Acquisition and Improvements, 20Planning and Construction ($449,000 Non-State 21Match) 22(St. Tammany)23Payable from General Obligation Bonds24

Priority 1 $ 80,00025

(600) St. Tammany Parish Fishing Pier, Planning and26Construction27(St. Tammany)28Payable from General Obligation Bonds29

Priority 1 $ 390,00030Priority 5 $ 1,470,00031

Total $ 1,860,00032

(601) University Square Learning Center Facilities, 33Planning and Construction34(St. Tammany)35Payable from General Obligation Bonds36

Priority 1 $ 1,420,00037Priority 5 $ 12,875,00038

Total $ 14,295,00039

(602) Bush Emergency Shelter and Community Center,40Acquisition, Planning and Construction41(St. Tammany)42Payable from General Obligation Bonds43

Priority 2 $ 250,00044Priority 5 $ 750,00045

Total $ 1,000,00046

(1019) St. Tammany Parish Cultural Arts District 47(St. Tammany)48Payable from General Obligation Bonds49

Priority 2 $ 11,000,00050

ENROLLEDHB NO. 2

Page 104 of 202

(1683) Covington Emergency Shelter, Community 1Health Center and Livestock Facility Addition, 2Planning and Construction3(St. Tammany)4Payable from General Obligation Bonds5

Priority 1 $ 970,0006Priority 5 $ 1,495,0007

Total $ 2,465,0008

50/J53 TANGIPAHOA PARISH9

(821) Juvenile Court Building Renovation -1021st District, Planning and Construction11(Tangipahoa)12Payable from General Obligation Bonds13

Priority 2 $ 120,00014Priority 5 $ 250,00015

Total $ 370,00016

(911) Wardline Road, Widening and Improvements17(Tangipahoa)18Payable from General Obligation Bonds19

Priority 2 $ 115,00020

(955) Courthouse and Courthouse Annex Renovations, 21and Expansions, planning and Construction 22($500,000 Local Match)23(Tangipahoa)24Payable from General Obligation Bonds25

Priority 1 $ 455,00026

(1269) South Airport Road - North Hoover Road27Improvements28(Tangipahoa)29Payable from General Obligation Bonds30

Priority 2 $ 190,00031Priority 5 $ 2,500,00032

Total $ 2,690,00033

(2003) Tangipahoa Parish Multipurpose Livestock and34Agricultural Facility, Planning and Construction, 35Supplemental Funding 36(Tangipahoa)37Payable from General Obligation Bonds38

Priority 1 $ 400,00039

50/J54 TENSAS PARISH40

(879) Tensas Parish Port/Port Priority Site Plan, Planning 41and Construction 42(Tensas)43Payable from General Obligation Bonds44

Priority 1 $ 225,00045

50/J55 TERREBONNE PARISH46

(229) Terrebonne Parish Emergency Operations Center,47Planning and Construction48(Terrebonne)49Payable from General Obligation Bonds50

Priority 1 $ 2,400,00051Priority 5 $ 1,950,00052

Total $ 4,350,00053

ENROLLEDHB NO. 2

Page 105 of 202

(325) Fireman's Skate and Bike Park, Planning and1Construction2(Terrebonne)3Payable from General Obligation Bonds4

Priority 1 $ 300,0005

(341) Renovate the Le Petit de Terrebonne Theater 6Building, Planning and Construction7(Terrebonne)8Payable from General Obligation Bonds9

Priority 2 $ 700,00010

(628) Bayou LaCarpe Watershed Project, Location C, 11Design and Construction12(Terrebonne)13Payable from General Obligation Bonds14

Priority 2 $ 440,00015Priority 5 $ 4,335,00016

Total $ 4,775,00017

(629) South Hollywood Road Widening, Planning and18Construction 19(Terrebonne)20Payable from General Obligation Bonds21

Priority 2 $ 105,00022Priority 5 $ 840,00023

Total $ 945,00024

(632) Bayou Terrebonne Boardwalk, Planning and25Construction ($1,000,000 Cash and/or In-Kind 26Match)27(Terrebonne)28Payable from General Obligation Bonds29

Priority 1 $ 325,00030

(633) Upper Bayou Dularge Pump Station, Planning and31Construction 32(Terrebonne)33Payable from General Obligation Bonds34

Priority 1 $ 195,00035

(744) Thompson Road Extension, Land Acquisition, 36Planning and Construction ($2,000,000 Local 37Match)38(Terrebonne)39Payable from General Obligation Bonds40

Priority 1 $ 3,210,00041Priority 5 $ 2,220,00042

Total $ 5,430,00043

(1021) Terrebonne Parish Consolidated Government -44Dredging of Bayou 45(Terrebonne)46Payable from General Obligation Bonds47

Priority 2 $ 870,00048Priority 5 $ 9,590,00049

Total $ 10,460,00050

ENROLLEDHB NO. 2

Page 106 of 202

(1109) Terrebonne Parish Animal Shelter Facility, 1Planning, Construction, and Equipment 2(Terrebonne)3Payable from General Obligation Bonds4

Priority 2 $ 780,0005Priority 5 $ 500,0006

Total $ 1,280,0007

(1159) South Louisiana Wetlands Discovery Center 8(Terrebonne)9Payable from General Obligation Bonds10

Priority 2 $ 300,00011Priority 5 $ 865,00012

Total $ 1,165,00013

50/J57 VERMILION PARISH14

(1588) Vermilion Parish Road Improvements15(Vermilion)16Payable from General Obligation Bonds17

Priority 5 $ 320,00018

50/J58 VERNON PARISH19

(578) Extension of Potable Water Line to Hutton, 20Planning and Construction21(Vernon)22Payable from General Obligation Bonds23

Priority 1 $ 745,00024Priority 2 $ 275,00025

Total $ 1,020,00026

(579) Visitor Center, Planning and Construction27(Vernon)28Payable from General Obligation Bonds29

Priority 1 $ 1,475,00030Priority 2 $ 280,00031

Total $ 1,755,00032

(581) Extension of Pavilion, Sidewalk Awning, 33Wastewater Line Extension, Storm Drainage 34Relocation, Foundations, and Other Associated 35Infrastructure at Rodeo Arena, Planning and 36Construction37(Vernon)38Payable from General Obligation Bonds39

Priority 1 $ 60,00040Priority 2 $ 420,00041

Total $ 480,00042

(582) Vernon/Fort Polk Thoroughfare Plan, Planning and43Construction44(Vernon)45Payable from General Obligation Bonds46

Priority 1 $ 9,365,00047

(583) Vernon/Fort Polk Thoroughfare Electrical Power48Extension 49(Vernon)50Payable from General Obligation Bonds51

Priority 2 $ 480,00052

ENROLLEDHB NO. 2

Page 107 of 202

(1135) Lift Station and Force Main for Vernon Parish Jail1(Vernon)2Payable from General Obligation Bonds3

Priority 2 $ 180,0004

(1593) Creation of Vernon Lake Cultural Center, Recreation5and Tourism Park, Planning and Construction6(Vernon)7Payable from General Obligation Bonds8

Priority 1 $ 200,0009Priority 2 $ 715,00010Priority 5 $ 300,00011

Total $ 1,215,00012

(1602) Plainview Road Improvements, Planning and13Construction14(Vernon)15Payable from General Obligation Bonds16

Priority 1 $ 1,850,00017

(2141) Catfish Hut Road and Bridge Repair and/or18Replacement, Planning and Construction19(Vernon)20Payable from General Obligation Bonds21

Priority 2 $ 325,00022

Pending submittal and approval of a capital outlay budget request pursuant to the provisions23of R.S. 39:112.24

(2146) 171 Walking Path, Planning and Construction25(Vernon)26Payable from General Obligation Bonds27

Priority 2 $ 40,00028

Pending approval of a capital outlay budget request pursuant to the provisions of R.S.2939:112.30

(2145) Rehabilitation of Various Streets Including Country31Club, Fullerton and Bellview Road and Bridge, 32Planning and Construction33(Vernon)34Payable from General Obligation Bonds35

Priority 2 $ 140,00036

Pending approval of a capital outlay budget request pursuant to the provisions of R.S.3739:112.38

50/J59 WASHINGTON PARISH39

(1313) Roadway Rehabilitation/Infrastructure Improvements,40Planning and Construction41(Washington)42Payable from General Obligation Bonds43

Priority 2 $ 250,00044

(1696) Emergency Operations, 911 and Multi-Agency45Communications Center, Real Estate, Planning 46and Construction ($125,000 Local Match)47(Washington)48Payable from General Obligation Bonds49

Priority 1 $ 55,00050

ENROLLEDHB NO. 2

Page 108 of 202

(1698) Animal Shelter, Planning and Construction1(Washington)2Payable from General Obligation Bonds3

Priority 1 $ 80,0004

50/J60 WEBSTER PARISH5

(465) Courthouse HVAC Renovations, Planning and6Construction7(Webster)8Payable from General Obligation Bonds9

Priority 2 $ 540,00010Priority 5 $ 725,00011

Total $ 1,265,00012

50/J61 WEST BATON ROUGE PARISH13

(1020) Sid Richardson Road Extension,14Planning and Construction15(West Baton Rouge)16Payable from General Obligation Bonds17

Priority 2 $ 150,00018

(1702) Regional Sewer System Located South of the 19Intra-Coastal Waterway and North of Brusly20(West Baton Rouge)21Payable from General Obligation Bonds22

Priority 1 $ 70,00023

(1709) LA 415 Bridge at Intracoastal Canal, Planning and24Construction25(West Baton Rouge)26Payable from General Obligation Bonds27

Priority 1 $ 570,00028Priority 5 $ 6,000,00029

Total $ 6,570,00030

50/J62 WEST CARROLL PARISH31

(851) Chip and Seal Road Repair32(West Carroll)33Payable from General Obligation Bonds34

Priority 1 $ 160,00035

50/J64 WINN PARISH36

(845) Beulah Road Reconstruction, Planning and37Construction 38(Winn)39Payable from General Obligation Bonds40

Priority 2 $ 1,000,00041

(1061) Parish-Wide Roadway Projects42(Winn)43Payable from General Obligation Bonds44

Priority 2 $ 385,00045

(1603) Country Club Road, Planning and Construction46(Winn)47Payable from General Obligation Bonds48

Priority 1 $ 850,00049

ENROLLEDHB NO. 2

Page 109 of 202

50/M01 ABBEVILLE1

(355) Chris Crusta Memorial Airport - Hangar2Rehabilitation, Planning and Construction3(Vermilion)4Payable from General Obligation Bonds5

Priority 2 $ 100,0006

50/M02 ABITA SPRINGS7

(1711) Water Lines and Sewer Lines, Extensions and8Upgrades, Planning and Construction (Cash and/or 9In-Kind Match Required)10(St. Tammany)11Payable from General Obligation Bonds12

Priority 1 $ 10,00013Priority 2 $ 460,00014Priority 5 $ 4,915,00015

Total $ 5,385,00016

50/M05 ALEXANDRIA17

(663) Sugarhouse Road/Eddie Williams Boulevard to 18LA Highway 1 Phase I and II, Planning and 19Construction ($5,000,000 Local Match)20(Rapides)21Payable from General Obligation Bonds22

Priority 1 $ 690,00023Priority 5 $ 6,930,00024

Total $ 7,620,00025

50/M06 AMITE26

(418) Town of Amite City Water Improvement Project,27Planning and Construction28(Tangipahoa)29Payable from General Obligation Bonds30

Priority 2 $ 100,00031Priority 5 $ 600,00032

Total $ 700,00033

50/M07 ANACOCO34

(2147) Anacoco Street Rehabilitation, Charles and Beaver35Streets, Planning and Construction36(Vernon)37Payable from General Obligation Bonds38

Priority 2 $ 20,00039

Pending approval of a capital outlay budget request pursuant to the provisions to R.S.4039:112.41

50/M09 ARCADIA42

(499) Multi-Purpose Community Center, Planning 43and Construction ($350,000 Local Match)44(Bienville)45Payable from General Obligation Bonds46

Priority 1 $ 1,910,00047

ENROLLEDHB NO. 2

Page 110 of 202

50/M10 ARNAUDVILLE1

(1604) Multipurpose Aquatic Recreational Facility2(St. Landry)3Payable from General Obligation Bonds4

Priority 1 $ 10,0005Priority 5 $ 260,0006

Total $ 270,0007

50/M14 BAKER8

(1712) Baker Fire Training Facility, Planning and 9Construction10(East Baton Rouge)11Payable from General Obligation Bonds12

Priority 1 $ 170,00013

50/M15 BALDWIN14

(1605) Fire Station and Public Service Center, 15Planning and Construction16(St. Mary)17Payable from General Obligation Bonds18

Priority 1 $ 75,00019

50/M16 BALL20

(1606) Sewer Extensions in the Springhill Road Area21(Rapides)22Payable from General Obligation Bonds23

Priority 1 $ 15,00024

50/M17 BASILE25

(841) Public Accommodation Facility Improvements26for Meeting/Recreation, Planning and27Construction28(Evangeline)29Payable from General Obligation Bonds30

Priority 2 $ 30,00031

The capital outlay budget request for this project was submitted after the November 1st32deadline, but it has been approved by the Joint Legislative Committee on Capital Outlay33pursuant to the provisions of R.S. 39:112.34

50/M19 BASTROP35

(1713) Bastrop City Hall - Roof Construction and 36Green Lighting, Planning and Construction37(Morehouse)38Payable from General Obligation Bonds39

Priority 1 $ 20,00040

(1714) Bastrop Central Fire Station, Replace Driveway 41City Hall, Roof Construction, Planning and 42Construction43(Morehouse)44Payable from General Obligation Bonds45

Priority 1 $ 200,00046Priority 5 $ 250,00047

Total $ 450,00048

ENROLLEDHB NO. 2

Page 111 of 202

50/M20 BATON ROUGE1

(621) Baton Rouge Fire Department Brookstown 2Fire Station #4, Planning and Construction 3(East Baton Rouge)4Payable from General Obligation Bonds5

Priority 1 $ 200,0006Priority 2 $ 100,0007

Total $ 300,0008

(623) Hooper Road Sewer Improvements 9($1,200,000 Local Match)10(East Baton Rouge)11Payable from General Obligation Bonds12

Priority 1 $ 1,190,00013

(627) Hooper Road Widening to Four Lanes 14(Blackwater Bayou to Sullivan Road), 15Planning, Engineering, Utilities and 16Construction 17(East Baton Rouge)18Payable from General Obligation Bonds19

Priority 1 $ 1,000,00020Priority 2 $ 500,00021Priority 5 $ 8,665,00022

Total $ 10,165,00023

(895) Chaneyville Fire District #7 Reames Road 24Fire Station 25(East Baton Rouge)26Payable from General Obligation Bonds27

Priority 2 $ 230,00028

(1731) Drainage Improvements in Old Goodwood 29Area, Planning and Construction30(East Baton Rouge)31Payable from General Obligation Bonds32

Priority 1 $ 65,00033

(1732) Jefferson Highway Signal Improvements, 34Government Street to Drusilla Lane, Planning 35and Construction ($150,000 Local Match)36(East Baton Rouge)37Payable from General Obligation Bonds38

Priority 1 $ 1,615,00039

(1733) Stanford Avenue Improvements, Sidewalk 40Widening, Planning and Construction41(East Baton Rouge)42Payable from General Obligation Bonds43

Priority 5 $ 70,00044

(1737) Baseball Stadium Improvements45(East Baton Rouge)46Payable from General Obligation Bonds47

Priority 1 $ 1,355,00048

(1740) Extension of Stumberg Lane from Jefferson 49Hwy. to Airline Hwy., Planning and Construction50(East Baton Rouge)51Payable from General Obligation Bonds52

Priority 1 $ 85,00053

ENROLLEDHB NO. 2

Page 112 of 202

(2110) Signage/Visitor's Amenities Program1($500,000 Federal Match and/or 2Non-State Match)3(East Baton Rouge)4Payable from General Obligation Bonds5

Priority 2 $ 198,4006

Provided, however, that $198,400 of the Priority 2 appropriation for this project is used to7replace general obligation bond proceeds reappropriated to Executive Department, Division8of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,9Gustav and Ike, Planning and Construction (Statewide) in this Act.10

50/M22 BENTON11

(950) Town of Benton Wastewater Collection System12Improvements, Planning and Construction13(Bossier)14Payable from General Obligation Bonds15

Priority 1 $ 475,00016

50/M24 BERWICK17

(538) Sewerage Collection System Along Old 18Spanish Trail and LA 182, Planning and 19Construction20(St. Mary)21Payable from General Obligation Bonds22

Priority 1 $ 1,350,00023Priority 5 $ 1,115,00024

Total $ 2,465,00025

(1607) Sewer Rehabilitation on Third and Fourth 26Streets and Sinclair Alley, Planning and 27Construction28(St. Mary)29Payable from General Obligation Bonds30

Priority 5 $ 45,00031

50/M25 BIENVILLE32

(1608) Village of Bienville, Water System 33Improvements34(Bienville)35Payable from General Obligation Bonds36

Priority 1 $ 100,00037Priority 5 $ 125,00038

Total $ 225,00039

50/M27 BOGALUSA40

(245) Drainage, Paving and Water System 41Improvements, Planning and Construction 42(Washington)43Payable from General Obligation Bonds44

Priority 1 $ 100,00045Priority 2 $ 200,00046

Total $ 300,00047

ENROLLEDHB NO. 2

Page 113 of 202

(246) Emergency Sewer Collection System 1Evaluation and Repairs, Planning and 2Construction3(Washington)4Payable from General Obligation Bonds5

Priority 1 $ 230,0006

(680) Industrial Park Road, Water, Natural Gas,7Sewer and Other Infrastructure, Planning8and Construction9(Washington)10Payable from General Obligation Bonds11

Priority 2 $ 75,00012Priority 5 $ 150,00013

Total $ 225,00014

(1746) City Hall Restoration and Renovations, 15Planning and Construction ($98,768 Federal 16Match)17(Washington)18Payable from General Obligation Bonds19

Priority 1 $ 290,00020

50/M29 BOSSIER CITY21

(370) Center for Creative Digital Media (CCDM)22(Bossier)23Payable from General Obligation Bonds24

Priority 1 $ 990,00025Priority 5 $ 25,500,00026

Total $ 26,490,00027

(1751) Hwy. 71 Street Lighting Project from 28LA 3032 (Westgate Drive) to LA 511 29(Jimmie Davis Hwy), Planning and 30Construction31(Bossier)32Payable from General Obligation Bonds33

Priority 1 $ 770,00034

50/M31 BREAUX BRIDGE35

( ) New Pavilion at Carl Williams Memorial36Park, Planning and Construction37(St. Martin)38Payable from General Obligation Bonds39

Priority 2 $ 25,00040

Pending submittal and approval of a capital outlay budget request pursuant to the provisions41of R.S. 39:112.42

( ) Renovations at Veterans' Park, Including the Installation43of Lighting, Planning and Construction44(St. Martin)45Payable from General Obligation Bonds46

Priority 2 $ 25,00047

Pending submittal and approval of a capital outlay budget request pursuant to the provisions48of R.S. 39:112.49

ENROLLEDHB NO. 2

Page 114 of 202

50/M32 BROUSSARD1

(645) South Bernard From Ambassador Caffery to 2LA Hwy 182 (Lafayette)3Payable from General Obligation Bonds4

Priority 2 $ 150,0005Priority 5 $ 1,830,0006

Total $ 1,980,0007

(1611) Three-Lane LA 182 in the City of Broussard, 8Planning and Construction ($750,000 Local 9Match)10(Lafayette)11Payable from General Obligation Bonds12

Priority 1 $ 1,640,00013Priority 5 $ 600,00014

Total $ 2,240,00015

(1612) Reconstruct South Bernard Road From 16LA Hwy 182 to US Hwy 90, Planning and 17Construction18(Lafayette)19Payable from General Obligation Bonds20

Priority 1 $ 645,00021Priority 2 $ 350,00022Priority 5 $ 4,000,00023

Total $ 4,995,00024

(1988) Rehabilitate LA Hwy 182 from US 90 to 25LA Hwy 89, Planning and Construction26(Lafayette)27Payable from General Obligation Bonds28

Priority 1 $ 245,00029

50/M33 BRUSLY30

(1752) New Police Department Headquarters, 31Maintenance, Material Storage and 32Annex Buildings33(West Baton Rouge)34Payable from General Obligation Bonds35

Priority 1 $ 2,435,00036

50/M37 CAMPTI37

(1318) Town of Campti Multi-Purpose Community 38Center, Planning and Construction39(Natchitoches)40Payable from General Obligation Bonds41

Priority 5 $ 50,00042

50/M39 CARENCRO43

(588) Wastewater and City Infrastructure Flood 44Damages, Planning and Construction45(Lafayette)46Payable from General Obligation Bonds47

Priority 1 $ 1,190,00048Priority 5 $ 4,770,00049

Total $ 5,960,00050

ENROLLEDHB NO. 2

Page 115 of 202

(589) Post Road Sewer Treatment Plant, Planning1and Construction2(Lafayette)3Payable from General Obligation Bonds4

Priority 2 $ 150,0005

(590) Water and Sewer Infrastructure Improvement Project6Planning and Construction7(Lafayette)8Payable from General Obligation Bonds9

Priority 2 $ 105,00010

(1613) City of Carencro City Hall Renovations 11to Include New Roof, Planning and 12Construction13(Lafayette)14Payable from General Obligation Bonds15

Priority 1 $ 65,00016

(1614) Arceneaux Road Drainage Improvements, 17Site Work and Culverting, Planning and 18Construction 19(50% Local Match)20(Lafayette)21Payable from General Obligation Bonds22

Priority 1 $ 205,00023

(1615) Gaston Coulee Cleaning, Planning and 24Improvements25(Lafayette)26Payable from General Obligation Bonds27

Priority 1 $ 190,00028

50/M40 CASTOR29

(1616) New Water Well and Related System 30Improvements, Planning and Construction31(Bienville)32Payable from General Obligation Bonds33

Priority 1 $ 310,00034

50/M43 CHENEYVILLE35

(636) After School Education Center, Planning36and Construction37(Rapides)38Payable from General Obligation Bonds39

Priority 2 $ 50,00040

50/M44 CHOUDRANT41

(1755) Village of Choudrant Town Hall42(Lincoln)43Payable from General Obligation Bonds44

Priority 1 $ 20,00045

ENROLLEDHB NO. 2

Page 116 of 202

50/M45 CHURCH POINT1

(1084) Town of Church Point Sewer System 2Rehabilitation, 3Planning and Construction4(Acadia)5Payable from General Obligation Bonds6

Priority 2 $ 60,0007

50/M46 CLARENCE8

(498) Clarence, Wastewater System Improvements, 9Planning and Construction10(Natchitoches)11Payable from General Obligation Bonds12

Priority 5 $ 50,00013

50/M48 CLAYTON14

(1617) Clayton School Gymnasium, Planning and15Construction16(Concordia)17Payable from General Obligation Bonds18

Priority 5 $ 100,00019

50/M52 COLUMBIA20

(787) Water Well, Planning and Construction 21(Caldwell)22Payable from General Obligation Bonds23

Priority 1 $ 85,00024Priority 2 $ 330,00025

Total $ 415,00026

50/M54 COTTON VALLEY27

(524) Cotton Valley Sewerage System Improvements,28Planning and Construction29(Webster)30Payable from General Obligation Bonds31

Priority 1 $ 400,00032Priority 5 $ 580,00033

Total $ 980,00034

50/M56 COUSHATTA35

(1129) Community Center, Planning and Construction36(Red River)37Payable from General Obligation Bonds38

Priority 2 $ 475,00039

(1619) Install New Streetlights and Sidewalks for the 40Town of Coushatta, Planning and Construction41(Red River)42Payable from General Obligation Bonds43

Priority 1 $ 50,00044

ENROLLEDHB NO. 2

Page 117 of 202

50/M57 COVINGTON1

(848) Extensions and Improvements to Water 2Distribution System3(St. Tammany)4Payable from General Obligation Bonds5

Priority 2 $ 560,0006

50/M58 CROWLEY7

(1208) North Avenue O Drainage Improvements, 8Planning and Construction 9(Acadia)10Payable from General Obligation Bonds11

Priority 2 $ 35,00012

(1240) Northern Avenue at Center Ditch Bridge 13Repair, Planning and Construction 14(Acadia)15Payable from General Obligation Bonds16

Priority 2 $ 420,00017

(1620) Wastewater Treatment Facility Improvements18($250,000 Local Match)19(Acadia)20Payable from General Obligation Bonds21

Priority 1 $ 45,00022

(1621) South Avenue H at Bayou Blanc, Bridge 23Replacement, Planning and Construction24(Acadia)25Payable from General Obligation Bonds26

Priority 1 $ 220,00027

50/M59 CULLEN28

(766) Potable Water and Distribution System 29Improvements, Planning and Construction30(Webster)31Payable from General Obligation Bonds32

Priority 1 $ 180,00033Priority 5 $ 250,00034

Total $ 430,00035

50/M60 DELCAMBRE36

(242) Water Distribution and Storage System37Improvements, Planning and Construction38(Vermilion)39Payable from General Obligation Bonds40

Priority 1 $ 440,00041

(1623) Delcambre Shrimp Festival Pavilion, Planning 42and Construction43(Iberia)44Payable from General Obligation Bonds45

Priority 1 $ 145,00046

ENROLLEDHB NO. 2

Page 118 of 202

50/M61 DELHI1

(689) Richland Parish Recreational and Learning 2Center, Planning and Construction 3(Richland)4Payable from General Obligation Bonds5

Priority 1 $ 950,0006Priority 2 $ 400,0007

Total $ 1,350,0008

50/M64 DEQUINCY9

(385) Drainage Improvements on Buxton Creek 10to Prevent Erosion at City Sewer Plant, 11Planning and Construction12(Calcasieu)13Payable from General Obligation Bonds14

Priority 2 $ 50,00015Priority 5 $ 700,00016

Total $ 750,00017

(940) Buxton Creek Improvements 18(Calcasieu)19Payable from General Obligation Bonds20

Priority 1 $ 465,00021Priority 2 $ 225,00022

Total $ 690,00023

(1624) New City Hall, Planning and Construction24(Calcasieu)25Payable from General Obligation Bonds26

Priority 1 $ 250,00027Priority 5 $ 800,00028

Total $ 1,050,00029

(1626) Sewer Rehabilitation of 8" Sewer on Holly 30and North Division Streets and 18" Sewer 31on William Still Road - City of Dequincy32(Calcasieu)33Payable from General Obligation Bonds34

Priority 1 $ 250,00035Priority 5 $ 300,00036

Total $ 550,00037

50/M65 DERIDDER38

(523) Education and Job Training Center, Planning 39and Construction40(Beauregard)41Payable from General Obligation Bonds42

Priority 2 $ 800,00043Priority 5 $ 1,600,00044

Total $ 2,400,00045

(1627) Community Recreational Building and Shelter,46Planning and Construction and/or Acquisition 47and Rehabilitation of the Existing Facility48($1,500,000 Local Match)49(Beauregard)50Payable from General Obligation Bonds51

Priority 1 $ 1,340,00052Priority 5 $ 1,975,00053

Total $ 3,315,00054

ENROLLEDHB NO. 2

Page 119 of 202

50/M68 DONALDSONVILLE1

(817) Regional Pump Station and Sewer System 2Improvements, Planning and Construction3(Ascension)4Payable from General Obligation Bonds5

Priority 5 $ 1,370,0006

(1059) Fire Station, Planning and Construction7(Ascension)8Payable from General Obligation Bonds9

Priority 5 $ 700,00010

(1756) Riverfront Development, Planning and 11Construction12(Ascension)13Payable from General Obligation Bonds14

Priority 1 $ 760,00015

50/M69 DOWNSVILLE16

(1760) Downsville Recreational Facility Improvements,17Planning and Construction18(Lincoln)19Payable from General Obligation Bonds20

Priority 1 $ 140,00021

50/M75 EAST HODGE22

(1970) Village Hall Improvements, Planning and 23Construction24(Jackson)25Payable from General Obligation Bonds26

Priority 5 $ 250,00027

50/M80 ERATH28

(775) Wastewater Treatment Plant Improvement, 29Planning and Construction30(Vermilion)31Payable from General Obligation Bonds32

Priority 1 $ 135,00033

(1628) Public Works Facility, Planning and Construction34(Vermilion)35Payable from General Obligation Bonds36

Priority 1 $ 410,00037

50/M83 EUNICE38

(612) City of Eunice Levee Site Work at Eunice City Lake,39Planning and Construction40(St. Landry)41Payable from General Obligation Bonds42

Priority 2 $ 180,00043

(1320) Cast Iron Gas Line Replacement,44Planning and Construction45(St. Landry)46Payable from General Obligation Bonds47

Priority 2 $ 70,00048

ENROLLEDHB NO. 2

Page 120 of 202

50/M87 FERRIDAY1

(1630) Downtown Revitalization, Planning and 2Construction ($253,750 In-Kind Local Match)3(Concordia)4Payable from General Obligation Bonds5

Priority 1 $ 525,0006

50/M90 FOLSOM7

(1763) Road and Street Repairs, Planning and 8Construction (Cash and/or In-Kind Match 9Required)10(St. Tammany)11Payable from General Obligation Bonds12

Priority 5 $ 50,00013

50/M91 FORDOCHE14

(2111) Potable Water Improvements Deep Water15Well and One Elevated Water Storage Tank,16Planning and Construction17(Pointe Coupee)18Payable from General Obligation Bonds19

Priority 2 $ 59,10020

Provided, however, that $59,100 of the Priority 2 appropriation for this project is used to21replace general obligation bond proceeds reappropriated to Executive Department, Division22of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,23Gustav and Ike, Planning and Construction (Statewide) in this Act.24

50/M92 FOREST25

(1250) Drainage Project26(West Carroll)27Payable from General Obligation Bonds28

Priority 2 $ 55,00029

50/M93 FOREST HILL30

(662) Renovation of Community Facilities, Planning and 31Construction ($375,000 Local Match)32(Rapides)33Payable from General Obligation Bonds34

Priority 1 $ 185,00035Priority 2 $ 75,00036Priority 5 $ 620,00037

Total $ 880,00038

50/M94 FRANKLIN39

(682) Caffery Park Renovation, Planning and Construction40(St. Mary)41Payable from General Obligation Bonds42

Priority 2 $ 120,00043

(1632) Renovation of Old Crowell Elementary Building,44Planning and Construction45(St. Mary)46Payable from General Obligation Bonds47

Priority 1 $ 1,825,00048

ENROLLEDHB NO. 2

Page 121 of 202

(2112) West St. Mary Civic & Convention Center,1Planning and Construction ($5,000,0002Local Match)3(St. Mary)4Payable from General Obligation Bonds5

Priority 2 $ 66,0006

Provided, however, that $66,000 of the Priority 2 appropriation for this project is used to7replace general obligation bond proceeds reappropriated to Executive Department, Division8of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,9Gustav and Ike, Planning and Construction (Statewide) in this Act.10

50/M95 FRANKLINTON11

(1764) Industrial Park Property and Acquisition and12Development13(Washington)14Payable from General Obligation Bonds15

Priority 1 $ 40,00016

(2113) Jones Creek Flood Control, Planning and 17Construction18(Washington)19Payable from General Obligation Bonds20

Priority 2 $ 196,00021

Provided, however, that $196,000 of the Priority 2 appropriation for this project is used to22replace general obligation bond proceeds reappropriated to Executive Department, Division23of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,24Gustav and Ike, Planning and Construction (Statewide) in this Act.25

50/MA3 GOLDEN MEADOW26

(1225) Median Turning Lane near Town Hall 27(Lafourche)28Payable from General Obligation Bonds29

Priority 2 $ 120,00030

(1633) Upgrade to North Sewerage Treatment Plant, 31Planning and Construction32(Lafourche)33Payable from General Obligation Bonds34

Priority 1 $ 175,00035

50/MA5 GONZALES36

(1191) City of Gonzales - GO Program LA Highway 3037Corridor, Planning and Construction38(Ascension)39Payable from General Obligation Bonds40

Priority 1 $ 55,00041Priority 2 $ 2,250,00042

Total $ 2,305,00043

(1969) Improvements on LA 3038, Including Patching,44Repairing and Overlaying of the Highway, 45Planning and Construction46(Ascension)47Payable from General Obligation Bonds48

Priority 1 $ 800,00049

ENROLLEDHB NO. 2

Page 122 of 202

50/MA6 GRAMBLING1

(846) City-Wide Drainage Improvements, Planning2and Construction3(Lincoln)4Payable from General Obligation Bonds5

Priority 2 $ 250,0006

(1768) Wastewater System Expansion7(Lincoln)8Payable from General Obligation Bonds9

Priority 1 $ 45,00010Priority 5 $ 195,00011

Total $ 240,00012

50/MA9 GRAND COTEAU13

(1634) Fire Truck and Fire Station Upgrades14(St. Landry)15Payable from General Obligation Bonds16

Priority 1 $ 10,00017

(1635) Police and Utility Departments Roof, 18Air Conditioning Unit for Town Hall, 19Handheld Meter Reader, Abandon 20and Plug Water Well21(St. Landry)22Payable from General Obligation Bonds23

Priority 1 $ 60,00024

50/MB1 GRAND ISLE25

(1304) Historic Recreation Center/Community 26Center, Planning and Construction27(Jefferson)28Payable from General Obligation Bonds29

Priority 1 $ 95,00030Priority 2 $ 150,00031Priority 5 $ 640,00032

Total $ 885,00033

50/MB2 GRAYSON34

(425) Wastewater Treatment Plant Facility, 35Planning and Construction 36(Caldwell)37Payable from General Obligation Bonds38

Priority 2 $ 540,00039

(603) Streets and Drainage Improvements40(Caldwell)41Payable from General Obligation Bonds42

Priority 2 $ 150,00043

(1636) Infrastructure Improvements, Planning and44Construction45(Caldwell)46Payable from General Obligation Bonds47

Priority 1 $ 5,00048

ENROLLEDHB NO. 2

Page 123 of 202

(1637) Children's Playground and Pavilion, 1Planning and Construction (Cash and/or 2In-Kind Match Required)3(Caldwell)4Payable from General Obligation Bonds5

Priority 1 $ 5,0006

50/MB4 GREENWOOD7

(454) Multipurpose Community Center, Planning 8and Construction ($200,000 Local Match)9(Caddo)10Payable from General Obligation Bonds11

Priority 5 $ 195,00012

50/MB5 GRETNA13

(615) Stumpf Boulevard Force Main, Planning and14Construction15(Jefferson)16Payable from General Obligation Bonds17

Priority 2 $ 640,00018

(765) Downtown Drainage Improvements, Planning 19and Construction20(Jefferson)21Payable from General Obligation Bonds22

Priority 2 $ 600,00023Priority 5 $ 1,650,00024

Total $ 2,250,00025

(770) Jefferson Parish Waterline Connection, Planning 26and Construction27(Jefferson)28Payable from General Obligation Bonds29

Priority 2 $ 115,00030

(1769) McDonoghville Fire Station, Planning and 31Construction32(Jefferson)33Payable from General Obligation Bonds34

Priority 1 $ 990,00035Priority 5 $ 175,00036

Total $ 1,165,00037

(1770) City Hall Exterior and Interior Renovation, 38Planning and Construction39(Jefferson)40Payable from General Obligation Bonds41

Priority 1 $ 400,00042

(1771) Lion's Club Conversion to Gretna Senior 43Center, Planning and Construction44(Jefferson)45Payable from General Obligation Bonds46

Priority 1 $ 300,00047Priority 2 $ 200,00048

Total $ 500,00049

ENROLLEDHB NO. 2

Page 124 of 202

(1772) Gretna Water Tower, Planning and Construction1(Jefferson)2Payable from General Obligation Bonds3

Priority 1 $ 45,0004

(1775) Cultural Center for the Arts, Planning and 5Construction ($300,000 Local Match, 6$500,000 Parish Match)7(Jefferson)8Payable from General Obligation Bonds9

Priority 1 $ 1,545,00010

(1777) New Garden Park Street Lighting, Planning and11Construction12(Jefferson)13Payable from General Obligation Bonds14

Priority 1 $ 60,00015

(1778) Mel Ott Multipurpose Center, Planning and16Construction ($150,000 Cash and/or In-Kind 17Local Match)18(Jefferson)19Payable from General Obligation Bonds20

Priority 1 $ 40,00021

(1780) Sewer Plant Primary Clarifier, Planning and22Construction23(Jefferson)24Payable from General Obligation Bonds25

Priority 1 $ 195,00026

(1781) Mel Ott Exterior Lighting and Improvements27(Jefferson)28Payable from General Obligation Bonds29

Priority 1 $ 220,00030

(1783) Hancock Street Canal Improvements 31(Kepler Street -Virgil Street), Planning 32and Construction33(Jefferson)34Payable from General Obligation Bonds35

Priority 1 $ 245,00036Priority 5 $ 1,700,00037

Total $ 1,945,00038

50/MB7 GUEYDAN39

(196) Street Improvements, Planning and Construction40($112,000 Local Match)41(Vermilion)42Payable from General Obligation Bonds43

Priority 1 $ 195,00044

50/MB9 HAMMOND45

(823) Sewer System Improvements, Oxidation Ditch46Conversion, Sequencing Batch Reactor and Pump 47Station, Planning and Construction48(Tangipahoa)49Payable from General Obligation Bonds50

Priority 1 $ 780,00051Priority 5 $ 120,00052

Total $ 900,00053

ENROLLEDHB NO. 2

Page 125 of 202

(1784) Pine Hill Sewer System Improvements and 1Municipal Tie-In, Planning and Construction2(Tangipahoa)3Payable from General Obligation Bonds4

Priority 1 $ 300,0005

(1786) Police Station, Acquisition and Renovation, 6Planning and Construction7(Tangipahoa)8Payable from General Obligation Bonds9

Priority 1 $ 275,00010

(1787) Air Traffic Control Tower, Planning and 11Construction ($450,000 Local Match)12(Tangipahoa)13Payable from General Obligation Bonds14

Priority 1 $ 740,00015

50/MC1 HARAHAN16

(1789) Magnolia Boulevard Drainage - West 17Magnolia to Jefferson Highway, Planning 18and Construction19(Jefferson)20Payable from General Obligation Bonds21

Priority 1 $ 40,00022

(1790) Penfold Place Drainage, Planning and 23Construction24(Jefferson)25Payable from General Obligation Bonds26

Priority 1 $ 50,00027

50/MC3 HAUGHTON28

(1792) Additional Water Supply Wells, Planning and29Construction30(Bossier)31Payable from General Obligation Bonds32

Priority 1 $ 10,00033

50/MC5 HEFLIN34

(1286) Conversion of Gym into Multipurpose Facility,35Planning and Construction36(Webster)37Payable from General Obligation Bonds38

Priority 1 $ 300,00039Priority 5 $ 185,00040

Total $ 485,00041

50/MC9 HOMER42

(1795) Town of Homer, Town Hall Renovations, 43Planning and Construction44(Claiborne)45Payable from General Obligation Bonds46

Priority 1 $ 370,00047

ENROLLEDHB NO. 2

Page 126 of 202

50/MD1 HORNBECK1

(388) Compressed Natural Gas Fueling Station, 2Planning and Construction3(Vernon)4Payable from General Obligation Bonds5

Priority 2 $ 700,0006Priority 5 $ 950,0007

Total $ 1,650,0008

(1638) Emergency Connection with Anacoco 9Water System, Planning and Construction10(Vernon)11Payable from General Obligation Bonds12

Priority 1 $ 490,00013

(1639) Emergency Connection with Sabine Parish 14Water Works District 1, Planning and 15Construction16(Sabine)17Payable from General Obligation Bonds18

Priority 1 $ 500,00019Priority 5 $ 450,00020

Total $ 950,00021

(1640) Rehabilitation of Elevated Water Tank, 22Planning and Construction23(Vernon)24Payable from General Obligation Bonds25

Priority 1 $ 180,00026

(1641) Emergency Connection with West Vernon 27Waterworks District and Inline Booster Station, 28Planning and Construction29(Vernon)30Payable from General Obligation Bonds31

Priority 1 $ 890,00032

50/MD5 INDEPENDENCE33

(956) Independence Area Community Pavilion, 34Planning and Construction35(Tangipahoa)36Payable from General Obligation Bonds37

Priority 1 $ 150,00038Priority 2 $ 335,00039

Total $ 485,00040

(1799) Sewerage Treatment and Sewer/Water Lines 41Repairs, Planning and Construction (Cash and/or 42In-Kind Match Required)43(Tangipahoa)44Payable from General Obligation Bonds45

Priority 1 $ 35,00046

50/MD6 IOTA47

(1076) Town of Iota Street Improvements, 48Planning and Construction49(Acadia)50Payable from General Obligation Bonds51

Priority 2 $ 30,00052

ENROLLEDHB NO. 2

Page 127 of 202

50/ME1 JEAN LAFITTE1

(1073) Lafitte Seafood Pavilion, Planning and 2Construction3(Jefferson)4Payable from General Obligation Bonds5

Priority 1 $ 1,325,0006

50/ME2 JEANERETTE7

(359) Sewer Treatment Facility Upgrade, Planning 8and Construction ($912,500 Federal and/or 9Local Match)10(Iberia)11Payable from General Obligation Bonds12

Priority 1 $ 190,00013

50/ME6 JONESVILLE14

(710) Renovations to National Guard Armory 15Building16(Catahoula)17Payable from General Obligation Bonds18

Priority 2 $ 320,00019

(1113) Drainage Improvements, Planning and 20Construction 21(Catahoula)22Payable from General Obligation Bonds23

Priority 1 $ 1,580,00024

(1643) Pumping Station Upgrade, Planning and 25Construction26(Catahoula)27Payable from General Obligation Bonds28

Priority 1 $ 55,00029

50/ME8 KAPLAN30

(1081) Street Improvements, Reconstruction and 8th Street31Bank Stabilization/Shoulder Mitigation, Planning32and Construction33(Vermilion)34Payable from General Obligation Bonds35

Priority 2 $ 100,00036

(1644) Public Safety Complex, Planning and 37Construction38(Vermilion)39Payable from General Obligation Bonds40

Priority 1 $ 230,00041

50/MF1 KENNER42

(560) Lake Trail Drainage Improvement, Planning 43and Construction44(Jefferson)45Payable from General Obligation Bonds46

Priority 1 $ 40,00047Priority 2 $ 1,000,00048

Total $ 1,040,00049

ENROLLEDHB NO. 2

Page 128 of 202

(562) Drainage Improvements Along Idaho Avenue, 126th Street to West Napoleon Canal, Planning 2and Construction3(Jefferson)4Payable from General Obligation Bonds5

Priority 1 $ 145,0006Priority 2 $ 100,0007

Total $ 245,0008

(570) Wastewater System Corrective Measures 9(Jefferson)10Payable from General Obligation Bonds11

Priority 1 $ 245,00012Priority 2 $ 125,00013

Total $ 370,00014

50/MF2 KENTWOOD15

(506) Recreational Facility Property Acquisition, 16Planning, Site Preparation, Master Recreation 17Plan and Construction18(Tangipahoa)19Payable from General Obligation Bonds20

Priority 1 $ 60,00021Priority 2 $ 50,00022

Total $ 110,00023

(507) Repairs to Water System, Planning and 24Construction25(Tangipahoa)26Payable from General Obligation Bonds27

Priority 2 $ 300,00028

50/MF8 LAKE ARTHUR29

(389) Street Rehabilitation, Planning and Construction30(Jefferson Davis)31Payable from General Obligation Bonds32

Priority 2 $ 250,00033

50/MF9 LAKE CHARLES34

(372) Expansion of Wastewater Treatment Plant D35(Calcasieu)36Payable from General Obligation Bonds37

Priority 5 $ 16,200,00038

(373) Expansion of Southwest Water Treatment Facility39(Calcasieu)40Payable from General Obligation Bonds41

Priority 5 $ 5,590,00042

(374) Wastewater Treatment Plant, Plant B/C Force 43Main Segment No. 2, Planning and Construction 44($4,195,000 Local Match)45(Calcasieu)46Payable from General Obligation Bonds47

Priority 1 $ 2,000,00048Priority 5 $ 7,530,00049

Total $ 9,530,00050

ENROLLEDHB NO. 2

Page 129 of 202

(375) Infrastructure Improvements for Economic1Development, Planning and Construction 2($2,000,000 Local Match)3(Calcasieu)4Payable from General Obligation Bonds5

Priority 1 $ 2,000,0006Priority 2 $ 1,000,0007Priority 5 $ 6,000,0008

Total $ 9,000,0009

(377) National Hurricane Museum and Science 10Center, Planning and Construction11(Calcasieu)12Payable from General Obligation Bonds13

Priority 1 $ 290,00014Priority 2 $ 710,00015Priority 5 $ 27,255,00016

Total $ 28,255,00017

(378) Riverside Park Improvements, Planning and18Construction19(Calcasieu)20Payable from General Obligation Bonds21

Priority 1 $ 100,00022Priority 5 $ 650,00023

Total $ 750,00024

(379) Lakefront Development 25(Calcasieu)26Payable from General Obligation Bonds27

Priority 2 $ 1,200,00028Priority 5 $ 13,700,00029

Total $ 14,900,00030

(1646) Relocation of Lakeshore Drive, to Include 31Eastbound and Westbound I-10 Ramps to 32Ryan Street, Planning and Construction33(Calcasieu)34Payable from General Obligation Bonds35

Priority 1 $ 10,00036

50/MG3 LEESVILLE37

(390) Acquisition of East Central Water System38(Vernon)39Payable from General Obligation Bonds40

Priority 2 $ 235,00041

(391) Rehabilitation and/or Replacement of Lift Stations 42and Equipment, Planning and Construction43(Vernon)44Payable from General Obligation Bonds45

Priority 1 $ 40,00046Priority 5 $ 560,00047

Total $ 600,00048

(776) Street Rehabilitation and Extension49(Vernon)50Payable from General Obligation Bonds51

Priority 2 $ 255,00052Priority 5 $ 1,180,00053

Total $ 1,435,00054

ENROLLEDHB NO. 2

Page 130 of 202

(1647) Highway 28 and 171 Sewer and Water Extension1(Vernon)2Payable from General Obligation Bonds3

Priority 1 $ 335,0004

(1649) University Parkway Sewer System and Wastewater5Treatment Facilities Enhancements, Planning 6and Construction7(Vernon)8Payable from General Obligation Bonds9

Priority 1 $ 3,020,00010

50/MG4 LEONVILLE11

(197) Leonville Boat Launch Facility Improvements - Phase II,12Planning and Construction13(St. Landry)14Payable from General Obligation Bonds15

Priority 2 $ 150,00016

50/MG8 LIVONIA17

(647) Sewer Infrastructure Improvements,18Planning and Construction19(Pointe Coupee)20Payable from General Obligation Bonds21

Priority 2 $ 50,00022

(1861) Purchase and Installation of Law Enforcement23Surveillance System, Planning and Construction24(Pointe Coupee)25Payable from General Obligation Bonds26

Priority 1 $ 120,00027

50/MG9 LOCKPORT28

(631) Lockport Sewer Collection System Rehabilitation,29Planning, Inspection and Repairs30(Lafourche)31Payable from General Obligation Bonds32

Priority 1 $ 110,00033

50/MH1 LOGANSPORT34

(596) Logansport Industrial Buildings, Planning and35Construction36(DeSoto)37Payable from General Obligation Bonds38

Priority 1 $ 50,00039

50/MH3 LOREAUVILLE40

(1650) Loreauville Water Tower Improvements, 41Planning and Construction42(Iberia)43Payable from General Obligation Bonds44

Priority 1 $ 120,00045

ENROLLEDHB NO. 2

Page 131 of 202

(1651) Loreauville Wastewater Treatment Plant 1Improvements and Demolition Project, 2Planning and Construction3(Iberia)4Payable from General Obligation Bonds5

Priority 1 $ 110,0006

50/MH6 MADISONVILLE7

(1862) Emergency Facilities, Renovations, 8Planning and Construction9(St. Tammany)10Payable from General Obligation Bonds11

Priority 1 $ 5,00012

(1863) Madisonville Bulkhead13(St. Tammany)14Payable from General Obligation Bonds15

Priority 1 $ 15,00016

50/MH8 MANDEVILLE17

(209) Mandeville Restrooms 18(St. Tammany)19Payable from General Obligation Bonds20

Priority 2 $ 150,00021

(437) Mandeville Police Classroom Addition22(St. Tammany)23Payable from General Obligation Bonds24

Priority 2 $ 340,00025

(1864) Mandeville Trailhead Property Acquisition, 26Planning and Construction27(St. Tammany)28Payable from General Obligation Bonds29

Priority 1 $ 390,00030

(1865) Water Tower, Construction31(St. Tammany)32Payable from General Obligation Bonds33

Priority 1 $ 2,190,00034

50/MH9 MANGHAM35

(880) Mangham Recreation Complex 36(Richland)37Payable from General Obligation Bonds38

Priority 2 $ 150,00039Priority 5 $ 1,530,00040

Total $ 1,680,00041

50/MI1 MANSFIELD42

(1652) Wastewater Collection System Improvements, 43Planning and Construction44(DeSoto)45Payable from General Obligation Bonds46

Priority 1 $ 50,00047

ENROLLEDHB NO. 2

Page 132 of 202

(1653) Turn Lane US Highway 84 (McArthur Drive) 1and Highway 175 (The Lake Road)2(DeSoto)3Payable from General Obligation Bonds4

Priority 1 $ 235,0005

50/MI4 MARINGOUIN6

(248) Governmental/Multi-Purpose Facility, 7Planning and Construction 8(Iberville)9Payable from General Obligation Bonds10

Priority 1 $ 120,00011Priority 2 $ 50,00012Priority 5 $ 250,00013

Total $ 420,00014

(249) Water Meter and Gas Meter Upgrade/Replacement,15 Planning and Construction16(Iberville)17Payable from General Obligation Bonds18

Priority 2 $ 200,00019

50/MI6 MARKSVILLE20

(1654) Mary Bethune Community Center, previously 21known as D.A. Jordan Community Center, 22for the City of Marksville, Planning and 23Construction24(Avoyelles)25Payable from General Obligation Bonds26

Priority 1 $ 450,00027Priority 5 $ 250,00028

Total $ 700,00029

50/MI8 MAURICE30

(1655) Civic Center - Post Hurricane Shelter 31($400,000 Local Match)32(Vermilion)33Payable from General Obligation Bonds34

Priority 1 $ 250,00035

50/MJ1 MELVILLE36

(251) Police Department Renovation, Planning37and Construction38(St. Landry)39Payable from General Obligation Bonds40

Priority 2 $ 70,00041Priority 5 $ 150,00042

Total $ 220,00043

(252) Multi-Purpose Community Center, 44Planning and Construction 45(St. Landry)46Payable from General Obligation Bonds47

Priority 1 $ 10,00048Priority 2 $ 5,00049

Total $ 15,00050

ENROLLEDHB NO. 2

Page 133 of 202

50/MJ3 MER ROUGE1

(1866) Boutz Lane Renovations2(Morehouse)3Payable from General Obligation Bonds4

Priority 1 $ 15,0005

50/MJ4 MERRYVILLE6

(395) Street Improvements7(Calcasieu)8Payable from General Obligation Bonds9

Priority 2 $ 170,00010

(1660) Sewerage Pump Station and Aeration System11Improvements, Planning and Construction12(Beauregard)13Payable from General Obligation Bonds14

Priority 1 $ 225,00015

50/MJ5 MINDEN16

(1161) Potable Water Ground Storage Tank, Planning 17and Construction18(Webster)19Payable from General Obligation Bonds20

Priority 1 $ 210,00021Priority 5 $ 650,00022

Total $ 860,00023

50/MJ6 MONROE24

(739) Monroe Regional Airport Terminal, Planning 25and Construction ($40,500,000 Federal and/or 26Local Match)27(Ouachita)28Payable from General Obligation Bonds29

Priority 1 $ 2,000,00030

(741) US Highway 165 South, US Highway 165 31Business Route Connector ($450,000 Local 32Match)33(Ouachita)34Payable from General Obligation Bonds35

Priority 1 $ 3,115,00036

(743) I-20 Interchange Improvement and Kansas 37Garrett Connector, Kansas Lane Connector, 38Planning and Construction ($1,000,000 Local 39and $6,000,000 Federal Match)40(Ouachita)41Payable from General Obligation Bonds42

Priority 1 $ 3,850,00043

(1661) Downtown Development District Facilities 44and Infrastructure for River Front, Design and 45Construction46(Ouachita)47Payable from General Obligation Bonds48

Priority 5 $ 250,00049

ENROLLEDHB NO. 2

Page 134 of 202

(2114) Northeast Louisiana Children's Museum 1Building Acquisition and Renovation, Planning 2and Construction ($160,000 Local Match)3(Ouachita)4Payable from General Obligation Bonds5

Priority 2 $ 240,0006

Provided, however, that $240,000 of the Priority 2 appropriation for this project is used to7replace general obligation bond proceeds reappropriated to Executive Department, Division8of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,9Gustav and Ike, Planning and Construction (Statewide) in this Act.10

50/MJ8 MONTPELIER11

(1867) Administration Building, Acquisition, 12Planning and Construction13(St. Helena)14Payable from General Obligation Bonds15

Priority 1 $ 185,00016

50/MK2 MORGAN CITY17

(1197) Lake End Parkway Cabins, Planning and 18Construction19(St. Mary)20Payable from General Obligation Bonds21

Priority 1 $ 990,00022

(1198) Water Plant Improvements, Planning and 23Constructions24(St. Mary)25Payable from General Obligation Bonds26

Priority 2 $ 50,00027Priority 5 $ 1,000,00028

Total $ 1,050,00029

(1200) LA Hwy. 70 Drainage Improvements, 30Planning and Construction31(St. Mary)32Payable from General Obligation Bonds33

Priority 1 $ 100,00034Priority 5 $ 1,370,00035

Total $ 1,470,00036

(1201) Brashear Avenue Drainage Canal Conversion 37to Subsurface Drainage, Planning and 38Construction39(St. Mary)40Payable from General Obligation Bonds41

Priority 1 $ 105,00042

(1668) Martin Luther King Jr. Boulevard Reconstruction 43(St. Mary)44Payable from General Obligation Bonds45

Priority 5 $ 500,00046

(1669) Docking Facility on Lake Palourde, Planning 47and Construction ($20,000 Cash and/or In-Kind 48Match)49(St. Mary)50Payable from General Obligation Bonds51

Priority 1 $ 5,00052

ENROLLEDHB NO. 2

Page 135 of 202

50/MK4 MORSE1

(2042) Installation of a Water Treatment Plant, 2Planning and Construction3(Acadia)4Payable from General Obligation Bonds5

Priority 2 $ 11,5006

Provided, however, that $11,500 of the Priority 2 appropriation for this project is used to7replace general obligation bond proceeds reappropriated to Executive Department, Division8of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,9Gustav and Ike, Planning and Construction (Statewide) in this Act.10

50/MK7 NAPOLEONVILLE11

(1268) Village of Napoleonville Catch Basin Project, 12Planning and Construction13(Assumption)14Payable from General Obligation Bonds15

Priority 5 $ 75,00016

(1670) Community Center Improvements17(Assumption)18Payable from General Obligation Bonds19

Priority 5 $ 25,00020

50/MK9 NATCHITOCHES21

(1116) Texas and Pacific Railway Natchitoches Depot22Redevelopment 23(Natchitoches)24Payable from General Obligation Bonds25

Priority 1 $ 195,00026

(1117) East Natchitoches By-Pass Project - Phase I 27(LA Hwy 6 East to LA Hwy 1226/Williams 28Avenue), Planning and Construction29(Natchitoches)30Payable from General Obligation Bonds31

Priority 1 $ 245,00032Priority 5 $ 5,750,00033

Total $ 5,995,00034

(1123) Blanchard Road Development, Planning and35Construction36(Natchitoches)37Payable from General Obligation Bonds38

Priority 2 $ 100,00039Priority 5 $ 1,600,00040

Total $ 1,700,00041

(1674) South Natchitoches Drainage Improvements, 42including Adjacent Roadwork, Planning and 43Construction44(Natchitoches)45Payable from General Obligation Bonds46

Priority 1 $ 45,00047Priority 5 $ 1,475,00048

Total $ 1,520,00049

ENROLLEDHB NO. 2

Page 136 of 202

50/ML1 NEW IBERIA1

(1675) Frontage Road Improvements, Real Estate, 2Planning and Construction3(Iberia)4Payable from General Obligation Bonds5

Priority 1 $ 145,0006

(1676) Sewer System Upgrade Area D Tributary, 7Planning and Construction ($360,000 Local 8Match)9(Iberia)10Payable from General Obligation Bonds11

Priority 1 $ 420,00012Priority 2 $ 100,00013Priority 5 $ 160,00014

Total $ 680,00015

(1677) Armenco Branch Canal Drainage 16Improvements (Non-State Match Required)17(Iberia)18Payable from General Obligation Bonds19

Priority 1 $ 2,195,00020

( ) Renovation of West End Park, including the Acquisition21of New Playground Equipment, Planning and Construction22(Iberia)23Payable from General Obligation Bonds24

Priority 2 $ 25,00025

Pending submittal and approval of a capital outlay budget request pursuant to the provisions26of R.S. 39:112.27

50/ML2 NEW LLANO28

(941) Raymond Street Rehabilitation 29(Vernon)30Payable from General Obligation Bonds31

Priority 2 $ 210,00032

(1679) Expansion of Wastewater System South to 33Fort Polk Entrance Road ($1,650,000 Local 34Match) Real Estate Acquisition, Planning and 35Construction36(Vernon)37Payable from General Obligation Bonds38

Priority 1 $ 1,650,00039

(1680) Water System Improvements, Construction 40($800,000 Local Match)41(Vernon)42Payable from General Obligation Bonds43

Priority 1 $ 1,490,00044

(1681) Street Improvements, Planning and 45Construction46(Vernon)47Payable from General Obligation Bonds48

Priority 1 $ 315,00049

ENROLLEDHB NO. 2

Page 137 of 202

50/ML3 NEW ORLEANS1

(656) Historic Algiers Courthouse Renovation, 2Planning and Construction 3(Orleans)4Payable from General Obligation Bonds5

Priority 1 $ 125,0006

(1348) New Consolidated Westbank Fire Station, 7Planning and Construction8(Orleans)9Payable from General Obligation Bonds10

Priority 2 $ 375,00011Priority 5 $ 1,625,00012

Payable from State General Fund By13Statutory Dedications out of the Fire14Marshal Fund $ 2,500,00015Total $ 4,500,00016

(1868) Behrman Park Improvements - New Soccer 17Facility, Planning and Construction, Master 18Planning19(Orleans)20Payable from General Obligation Bonds21

Priority 1 $ 9,245,00022

(1869) Eastern New Orleans Hospital Medical Office 23Buildings, Planning, Design, and Construction24(Orleans)25Payable from General Obligation Bonds26

Priority 1 $ 15,120,00027

(1870) George W. Carver Playground, Renovations and28Upgrades, Planning and Construction29(Orleans)30Payable from General Obligation Bonds31

Priority 1 $ 450,00032

(1871) Taylor Pool and Playground, Renovations and33Upgrades, Including Repair and Renovations 34of Basketball Courts and Pavilion, Replacing 35Perimeter Fencing, Installation of New Water 36Fountains, and Re-Grade Fields, Planning and 37Construction38(Orleans)39Payable from General Obligation Bonds40

Priority 1 $ 250,00041

(1872) Construction of Opelousas Street Extension 42from Behrman Avenue to Obannon Street and 43Construction of Patterson Drive Extension 44from Hendee Street to Obannon Street, 45Planning and Construction46(Orleans)47Payable from General Obligation Bonds48

Priority 1 $ 2,450,00049

ENROLLEDHB NO. 2

Page 138 of 202

(1873) Norman Playground Basketball Gym, and Park 1Enhancements, Planning and Construction2(Orleans)3Payable from General Obligation Bonds4

Priority 1 $ 1,970,0005Priority 5 $ 1,000,0006

Total $ 2,970,0007

(1874) Holiday Drive Roadway Construction 8(Gen. MacArthur to Behrman)9(Orleans)10Payable from General Obligation Bonds11

Priority 1 $ 265,00012

(1875) New Multi-Department Facility, Planning 13and Construction14(Orleans)15Payable from General Obligation Bonds16

Priority 1 $ 195,00017

(1876) Treme Center Improvements, Planning and18Construction19(Orleans)20Payable from General Obligation Bonds21

Priority 1 $ 25,00022

(1877) Rosenwald Community Center, Planning and23Construction24(Orleans)25Payable from General Obligation Bonds26

Priority 1 $ 390,00027Priority 2 $ 200,00028Priority 5 $ 1,400,00029

Total $ 1,990,00030

(1878) Fourth District Police Station, Planning and31Construction32(Orleans)33Payable from General Obligation Bonds34

Priority 1 $ 300,00035

(1879) Algiers Playgrounds and Parks, Renovation of36Restrooms, Lighting, Fencing, and Playground Equipment37(Orleans)38Payable from General Obligation Bonds39

Priority 1 $ 275,00040

(1880) Algiers Fire Station, Planning and Construction41(Orleans)42Payable from General Obligation Bonds43

Priority 1 $ 200,00044

(2115) Danzinger Bridge Ramps, Planning and Construction45(Orleans)46Payable from General Obligation Bonds47

Priority 2 $ 580,00048

Provided, however, that $580,000 of the Priority 2 appropriation for this project is used to49replace general obligation bond proceeds reappropriated to Executive Department, Division50of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,51Gustav and Ike, Planning and Construction (Statewide) in this Act.52

ENROLLEDHB NO. 2

Page 139 of 202

(2116) Gilbert Park/Carrollton Playground Boosters,1Inc., Improvements, Planning and Construction 2($300,000 Local Match)3(Orleans)4Payable from General Obligation Bonds5

Priority 2 $ 572,3006

Provided, however, that $572,300 of the Priority 2 appropriation for this project is used to7replace general obligation bond proceeds reappropriated to Executive Department, Division8of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,9Gustav and Ike, Planning and Construction (Statewide) in this Act.10

50/ML4 NEW ROADS11

(1232) Morrison Parkway Floating Dock Improvement12Project, Planning and Construction13(Pointe Coupee)14Payable from General Obligation Bonds15

Priority 2 $ 50,00016

(1882) Community Park Redevelopment, Planning and17Construction18(Pointe Coupee)19Payable from General Obligation Bonds20

Priority 1 $ 260,00021

50/MM4 OIL CITY22

(455) Water Treatment Plant Improvements, Planning 23and Construction24(Caddo)25Payable from General Obligation Bonds26

Priority 2 $ 110,00027Priority 5 $ 880,00028

Total $ 990,00029

(1884) Highway 538 Water Line Extension, Planning 30and Construction31(Caddo)32Payable from General Obligation Bonds33

Priority 1 $ 425,00034

50/MM5 OLLA35

(1060) Downtown Area Sidewalk, Ramps, Curbing, 36and Fencing Enhancements 37(LaSalle)38Payable from General Obligation Bonds39

Priority 2 $ 270,00040

50/MM6 OPELOUSAS41

(1293) Tourism Center and South Park Project42(St. Landry)43Payable from General Obligation Bonds44

Priority 5 $ 135,00045

ENROLLEDHB NO. 2

Page 140 of 202

(1294) Opelousas Infrastructure Renovation Program,1Planning and Construction2(St. Landry)3Payable from General Obligation Bonds4

Priority 1 $ 200,0005Priority 2 $ 80,0006Priority 5 $ 60,0007

Total $ 340,0008

50/MM8 PARKS9

(1682) Municipal Complex, Planning and Construction10(St. Martin)11Payable from General Obligation Bonds12

Priority 1 $ 115,00013Priority 2 $ 49,00014Priority 5 $ 250,00015

Total $ 414,00016

Provided, however, that $49,000 of the Priority 2 appropriation for this project is used to17replace general obligation bond proceeds reappropriated to Executive Department, Division18of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,19Gustav and Ike, Planning and Construction (Statewide) in this Act.20

50/MM9 PATTERSON21

(630) Replacement of Water and Gas Meters in Patterson,22Planning and Construction23(St. Mary)24Payable from General Obligation Bonds25

Priority 1 $ 200,00026Priority 2 $ 1,040,00027

Total $ 1,240,00028

(1684) Catherine Street Paving and Drainage, Engineering 29and Construction30(St. Mary)31Payable from General Obligation Bonds32

Priority 1 $ 95,00033

50/MN1 PEARL RIVER34

(1885) Sewer Treatment Plant Upgrade, Planning and 35Construction36(St. Tammany)37Payable from General Obligation Bonds38

Priority 1 $ 20,00039

(1886) River Dredging, Planning and Construction40(St. Tammany)41Payable from General Obligation Bonds42

Priority 1 $ 5,00043

50/MN3 PINEVILLE44

(1685) Pinecrest Roadway/Sidewalk Improvements, 45Planning and Construction46(Rapides)47Payable from General Obligation Bonds48

Priority 1 $ 90,00049

ENROLLEDHB NO. 2

Page 141 of 202

50/MN5 PLAIN DEALING1

(441) Wastewater Treatment Plant Improvement, 2Planning and Construction3(Bossier)4Payable from General Obligation Bonds5

Priority 1 $ 145,0006Priority 5 $ 160,0007

Total $ 305,0008

50/MN8 PLEASANT HILL9

(1686) Street Reconstruction and Overlay, Planning 10and Construction11(Sabine)12Payable from General Obligation Bonds13

Priority 1 $ 135,00014

(1687) Rehabilitate Two Elevated Water Tanks and15Rehabilitate Water Well, Planning and 16Construction17(Sabine)18Payable from General Obligation Bonds19

Priority 1 $ 150,00020

50/MO1 PONCHATOULA21

(1887) Consolidated Law Enforcement Complex, 22Acquisition, Planning and Construction23(Tangipahoa)24Payable from General Obligation Bonds25

Priority 5 $ 1,875,00026

(1888) Downtown Parking Lot, Acquisition, 27Planning and Construction28(Tangipahoa)29Payable from General Obligation Bonds30

Priority 1 $ 500,00031

50/MO7 QUITMAN32

(1688) Repair of Wastewater Treatment Facility33(Jackson)34Payable from General Obligation Bonds35

Priority 1 $ 115,00036

50/MO8 RAYNE37

(872) Martin Luther King Community Center Improvements38(City of Rayne), Planning and Construction39(Acadia)40Payable from General Obligation Bonds41

Priority 2 $ 65,00042Priority 5 $ 200,00043

Total $ 265,00044

ENROLLEDHB NO. 2

Page 142 of 202

50/MO9 RAYVILLE1

(870) Wastewater Transport and Treatment Facilities 2for Franklin Farms Mega Site 3(Richland)4Payable from General Obligation Bonds5

Priority 2 $ 330,0006Priority 5 $ 2,670,0007

Total $ 3,000,0008

(1244) Water Service Facilities for Franklin Farms Mega9Site, Planning and Construction10(Richland)11Payable from General Obligation Bonds12

Priority 2 $ 4,000,00013

(1690) Hangar, T-Hangar, Paved Areas and Utilities 14for Rayville Airport, Planning and 15Construction16(Richland)17Payable from General Obligation Bonds18

Priority 1 $ 290,00019

(1890) Railroad Spur, Planning and Construction20(Richland)21Payable from General Obligation Bonds22

Priority 1 $ 250,00023

50/MP3 RICHWOOD24

(1156) Richwood Municipal Complex, Planning, 25Construction, and Land Acquisition (Local 26Match Required)27(Ouachita)28Payable from General Obligation Bonds29

Priority 1 $ 155,00030

50/MP5 RINGGOLD31

(224) Town Hall/Civic Center Renovations, and 32Remodeling, Planning and Construction33(Bienville)34Payable from General Obligation Bonds35

Priority 1 $ 45,00036

50/MQ1 ROSEPINE37

(1013) Improvements to Sewer Collection System38(Vernon)39Payable from General Obligation Bonds40

Priority 2 $ 155,00041

(1692) Water System Improvements, Town of 42Rosepine, Planning and Construction43(Vernon)44Payable from General Obligation Bonds45

Priority 1 $ 195,00046

ENROLLEDHB NO. 2

Page 143 of 202

(1693) Rehabilitation of Elevated Water Tank, 1Planning and Construction2(Vernon)3Payable from General Obligation Bonds4

Priority 1 $ 245,0005

(1694) Rosepine Wastewater Treatment Plant 6Improvement, Planning and Construction7(Vernon)8Payable from General Obligation Bonds9

Priority 1 $ 1,610,00010

(1695) Rosepine Recreational Ball Park Acquisition, 11Planning and Construction12(Vernon)13Payable from General Obligation Bonds14

Priority 1 $ 70,00015

50/MQ2 RUSTON16

(1891) Goodwin Road Reconstruction, Planning and17Construction ($350,000 Local Match)18(Lincoln)19Payable from General Obligation Bonds20

Priority 1 $ 5,00021Priority 5 $ 20,00022

Total $ 25,00023

50/MQ3 ST. FRANCISVILLE24

(295) Burnet Road Bridge Replacement, Planning 25and Construction 26(West Feliciana)27Payable from General Obligation Bonds28

Priority 2 $ 535,00029

(1892) Natural Gas Distribution System Rehabilitation 30and Improvement, Planning and Construction31(West Feliciana)32Payable from General Obligation Bonds33

Priority 1 $ 305,00034

50/MQ4 ST. JOSEPH35

(604) Repairs and Upgrades to Water System, Planning 36and Construction37(Tensas)38Payable from General Obligation Bonds39

Priority 1 $ 600,00040Priority 5 $ 7,200,00041

Total $ 7,800,00042

(1697) Proposed City Hall/Convention Center, Planning 43and Construction44(Tensas)45Payable from General Obligation Bonds46

Priority 1 $ 235,00047

ENROLLEDHB NO. 2

Page 144 of 202

50/MQ5 ST. MARTINVILLE1

(1211) Sewer Lift Station Improvements 2(St. Martin)3Payable from General Obligation Bonds4

Priority 1 $ 90,0005

(1212) Recreation Improvements, Planning and Construction6(St. Martin)7Payable from General Obligation Bonds8

Priority 2 $ 50,0009

(1213) Recreation II, Planning and Construction10(St. Martin)11Payable from General Obligation Bonds12

Priority 2 $ 25,00013

(1699) Sewer Upgrade, Planning and Construction14(St. Martin)15Payable from General Obligation Bonds16

Priority 1 $ 350,00017

50/MQ6 SALINE18

(1968) Water Tower Repairs, Planning and Construction 19(Non-State Match Required)20(Bienville)21Payable from General Obligation Bonds22

Priority 5 $ 15,00023

50/MQ8 SCOTT24

(1703) Apollo Road Extension (Rue Du Belier and Dulles25Drive Intersection to Old Spanish Trail and Apollo 26Road Intersection), Planning, Construction and 27Land Acquisition28(Lafayette)29Payable from General Obligation Bonds30

Priority 1 $ 2,990,00031Priority 2 $ 10,000,00032Priority 5 $ 8,000,00033

Total $ 20,990,00034

(1704) Scott Events Center, Planning and Construction35(Lafayette)36Payable from General Obligation Bonds37

Priority 1 $ 55,00038

(1705) I-10 North Frontage Road, Planning and 39Construction40(Lafayette)41Payable from General Obligation Bonds42

Priority 1 $ 980,00043

(1706) Water and Sewer Line Installation along Apollo 44Road Extension, Planning and Construction45(Lafayette)46Payable from General Obligation Bonds47

Priority 1 $ 375,00048Priority 2 $ 1,500,00049

Total $ 1,875,00050

ENROLLEDHB NO. 2

Page 145 of 202

(1707) I-10 North Frontage Road Sewer and Water, 1Planning and Construction2(Lafayette)3Payable from General Obligation Bonds4

Priority 1 $ 375,0005

50/MR1 SHREVEPORT6

(791) Valencia Park Spray Park, Planning7and Construction8(Caddo)9Payable from General Obligation Bonds10

Priority 2 $ 100,00011

(800) C.C. Antoine Park, Planning and Construction12(Caddo)13Payable from General Obligation Bonds14

Priority 1 $ 75,00015Priority 2 $ 250,00016Priority 5 $ 325,00017

Total $ 650,00018

(804) Shreveport Arts Center Replacement, Planning,19Construction and Equipment 20(Caddo)21Payable from General Obligation Bonds22

Priority 1 $ 20,00023Priority 5 $ 255,00024

Total $ 275,00025

(807) Junior Golf Training Facilities (The First Tee) 26for Jerry Tim Brooks Lakeside Golf Course, 27Planning and Construction28(Caddo)29Payable from General Obligation Bonds30

Priority 1 $ 195,00031Priority 2 $ 250,00032

Total $ 445,00033

(809) ARTSPACE at the West Edge - Downtown 34Shreveport, Planning and Construction35(Caddo)36Payable from General Obligation Bonds37

Priority 1 $ 45,00038

(1836) C. C. Antoine Museum and Arts Center, Planning39and Construction ($64,000 Local Match)40(Caddo)41Payable from General Obligation Bonds42

Priority 1 $ 325,00043Priority 2 $ 5,00044

Total $ 330,00045

(1893) Convention Center Complex, Planning and46Construction ($85,000,000 Local Funds)47(Caddo)48Payable from General Obligation Bonds49

Priority 1 $ 12,000,00050

ENROLLEDHB NO. 2

Page 146 of 202

50/MR2 SIBLEY1

(670) Wastewater Collection Improvements, Planning 2and Construction3(Webster)4Payable from General Obligation Bonds5

Priority 1 $ 200,0006Priority 5 $ 265,0007

Total $ 465,0008

(671) Wastewater Treatment Facilities Improvements9(Webster)10Payable from General Obligation Bonds11

Priority 1 $ 305,00012

(674) Town of Sibley, Water Tank Rehabilitations, Planning 13and Construction14(Webster)15Payable from General Obligation Bonds16

Priority 2 $ 200,00017

(1894) Water Wells and Distribution System, Land18Acquisition, Planning and Construction19(Webster)20Payable from General Obligation Bonds21

Priority 1 $ 10,00022

50/MR4 SIKES23

(1715) Village of Sikes Water System Extensions and24Improvements, Planning and Construction25(Winn)26Payable from General Obligation Bonds27

Priority 1 $ 1,630,00028

50/MR5 SIMMESPORT29

(1967) Multipurpose Evacuation Shelter/Community 30Center in Simmesport, Acquisitions, Utilities, 31Planning and Construction32(Avoyelles)33Payable from General Obligation Bonds34

Priority 5 $ 390,00035

50/MR7 SIMSBORO36

(1895) Water Well and Water Main37(Lincoln)38Payable from General Obligation Bonds39

Priority 1 $ 30,00040Priority 5 $ 100,00041

Total $ 130,00042

(1896) Village of Simsboro, Extend Sewer Line/New43Subdivision44(Lincoln)45Payable from General Obligation Bonds46

Priority 5 $ 125,00047

ENROLLEDHB NO. 2

Page 147 of 202

(1897) Village of Simsboro Renovate "Old" Fire 1Station Into Town Hall, Planning and 2Construction3(Lincoln)4Payable from General Obligation Bonds5

Priority 1 $ 95,0006

50/MR9 SLIDELL7

(1898) W-14 Culverting Project8(St. Tammany)9Payable from General Obligation Bonds10

Priority 1 $ 2,000,00011

(1966) City Barn Flood Gates, Planning and Construction12(St. Tammany)13Payable from General Obligation Bonds14

Priority 5 $ 25,00015

50/MS4 SPRINGFIELD16

(357) Water System Planning and Construction 17(Livingston)18Payable from General Obligation Bonds19

Priority 1 $ 1,190,00020Priority 2 $ 595,00021

Total $ 1,785,00022

50/MS5 SPRINGHILL23

(923) Wastewater Collection System Improvements, 24Planning and Construction25(Webster)26Payable from General Obligation Bonds27

Priority 1 $ 70,00028

50/MS7 STERLINGTON29

(1132) Service Road, Planning and Construction30(Ouachita)31Payable from General Obligation Bonds32

Priority 1 $ 115,00033Priority 2 $ 255,00034

Total $ 370,00035

(1716) Wastewater Treatment Improvements - 36Headworks Structure, Planning and Construction37(Ouachita)38Payable from General Obligation Bonds39

Priority 1 $ 20,00040Priority 2 $ 140,00041

Total $ 160,00042

(1717) Sanitary Sewer Collection System Along US 16543Corridor, and Sewer Treatment Facility 44Upgrade/Improvements, Planning, Construction,45Land Acquisition ($1,000,000 Local Match)46(Ouachita)47Payable from General Obligation Bonds48

Priority 1 $ 5,00049

ENROLLEDHB NO. 2

Page 148 of 202

50/MS8 STONEWALL1

(526) Town Hall, Planning and Construction2(DeSoto)3Payable from General Obligation Bonds4

Priority 2 $ 200,0005

50/MS9 SULPHUR6

(398) Upgrade Regional Sewage Pumping Stations7(Arizona and Highway 108), Planning and8Construction9(Calcasieu)10Payable from General Obligation Bonds11

Priority 2 $ 2,700,00012Priority 5 $ 2,500,00013

Total $ 5,200,00014

(401) City of Sulphur - East Mimosa, West Mimosa,15 South Mimosa Streets, Planning and Construction16

(Calcasieu)17Payable from General Obligation Bonds18

Priority 2 $ 250,00019

(1718) Regional Wastewater Treatment Facility Sludge 20Belt Press and Conveyor System21(Calcasieu)22Payable from General Obligation Bonds23

Priority 1 $ 235,00024

(1719) Northside Industrial Park Rail Spur Extension,25Planning ($692,960 Cash and/or In-Kind Match)26(Calcasieu)27Payable from General Obligation Bonds28

Priority 1 $ 2,200,00029

50/MT1 SUN30

(1900) Town Hall Renovations, Planning and Construction31(St. Tammany)32Payable from General Obligation Bonds33

Priority 5 $ 120,00034

50/MT3 TALLULAH35

(1720) Improvements to Sewer System, Planning and36Construction37(Madison)38Payable from General Obligation Bonds39

Priority 1 $ 180,00040

(1721) Sewer Treatment Plant Improvements City of 41Tallulah42(Madison)43Payable from General Obligation Bonds44

Priority 1 $ 115,00045

(1722) Industrial Park Development, Planning and46Construction (Non-State Match Required)47(Madison)48Payable from General Obligation Bonds49

Priority 5 $ 500,00050

ENROLLEDHB NO. 2

Page 149 of 202

50/MT5 THIBODAUX1

(508) LA Hwy. 20 (N. Canal Blvd.) Widening, 2Planning and Construction3(Lafourche)4Payable from General Obligation Bonds5

Priority 1 $ 1,955,0006

50/MT6 TICKFAW7

(1901) Drainage Improvements on Highway 442 East 8and West, Planning and Construction9(Tangipahoa)10Payable from General Obligation Bonds11

Priority 1 $ 110,00012

50/MU2 VIDALIA13

(296) Development of a Slackwater Port on the 14Mississippi River, Planning and Construction15(Concordia)16Payable from General Obligation Bonds17

Priority 1 $ 9,990,00018

(1725) Vidalia Industrial Park Development, Planning 19and Construction ($16,710,800 Local, Federal, 20Other and In-Kind Match to be provided in phases 21as indicated in the capital outlay request)22(Concordia)23Payable from General Obligation Bonds24

Priority 1 $ 330,00025Priority 2 $ 366,00026

Total $ 696,00027

Provided, however, that $366,000 of the Priority 2 appropriation for this project is used to28replace general obligation bond proceeds reappropriated to Executive Department, Division29of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,30Gustav and Ike, Planning and Construction (Statewide) in this Act.31

(1726) Vidalia River Front Development, Design, 32Planning and Construction of Emergency Shelter33(Concordia)34Payable from General Obligation Bonds35

Priority 1 $ 210,00036

50/MU5 VINTON37

(402) Reconstruction of Big Woods Road, Planning 38and Construction39(Calcasieu)40Payable from General Obligation Bonds41

Priority 2 $ 250,00042

(1727) Town of Vinton, Vinton Street Improvements43(Calcasieu)44Payable from General Obligation Bonds45

Priority 1 $ 195,00046

ENROLLEDHB NO. 2

Page 150 of 202

(1728) Water Treatment Plant Improvements, Including1Rehabilitation of Elevated Water Storage Tank, 2Site and Electrical Improvements,3Planning and Construction4(Calcasieu)5Payable from General Obligation Bonds6

Priority 1 $ 215,0007

50/MU6 VIVIAN8

(501) Town of Vivian, Street Improvements, Planning 9and Construction10(Caddo)11Payable from General Obligation Bonds12

Priority 1 $ 390,00013

(502) Water and Wastewater System Improvements 14and Extension, Planning and Construction15(Caddo)16Payable from General Obligation Bonds17

Priority 1 $ 1,660,00018

50/MU7 WALKER19

(1902) Widening of Highway 447 and I-12 Overpass20Improvements, Environmental Phase 21Commencement, Planning and Construction22(Livingston)23Payable from General Obligation Bonds24

Priority 1 $ 290,00025

50/MV2 WEST MONROE26

(1152) Rehabilitation of Montgomery Street from 27LA 34 to I-20, Roadway, Water and Sewer28(Ouachita)29Payable from General Obligation Bonds30

Priority 2 $ 290,00031Priority 5 $ 1,800,00032

Total $ 2,090,00033

(1729) Creation of a Hurricane/Disaster Shelter by 34Expanding the West Ouachita Senior Center, 35Planning and Construction36(Ouachita)37Payable from General Obligation Bonds38

Priority 1 $ 330,00039Priority 5 $ 700,00040

Total $ 1,030,00041

(1730) West Ouachita Senior Center Facility - ADA, 42Federal Confidentiality Requirements, and 43Building Code Improvement Project, Planning 44and Construction45(Ouachita)46Payable from General Obligation Bonds47

Priority 1 $ 100,00048

ENROLLEDHB NO. 2

Page 151 of 202

50/MV3 WESTLAKE1

(1734) New Water Well, Planning and Construction2(Calcasieu)3Payable from General Obligation Bonds4

Priority 1 $ 425,0005

(1735) Ellis and Linda Drive Improvements, City of 6Westlake, Planning and Construction7(Calcasieu)8Payable from General Obligation Bonds9

Priority 1 $ 2,115,00010

(1736) Police and Emergency Response Facility, 11Planning and Construction12(Calcasieu)13Payable from General Obligation Bonds14

Priority 1 $ 1,000,00015

(1738) Golf Course Development, Planning and 16Development ($5,000,000 Local/Other Match 17Consisting of Cash and/or In-Kind, with First 18Year not to Exceed $200,000)19(Calcasieu)20Payable from General Obligation Bonds21

Priority 1 $ 1,610,00022

50/MV4 WESTWEGO23

(711) The WHARF, Planning and Construction24(Jefferson)25Payable from General Obligation Bonds26

Priority 2 $ 2,000,00027

(713) Park Land Improvements, Including 28Improvements to Existing Parks and Land 29Acquisition, Planning and Construction30(Jefferson)31Payable from General Obligation Bonds32

Priority 1 $ 800,00033Priority 2 $ 800,00034Priority 5 $ 500,00035

Total $ 2,100,00036

(716) Sala Avenue Street and Infrastructure 37Improvements 38(Jefferson)39Payable from General Obligation Bonds40

Priority 1 $ 400,00041

(724) Water Plant Improvements, Planning and 42Construction (50% Local Match)43(Jefferson)44Payable from General Obligation Bonds45

Priority 1 $ 990,00046Priority 2 $ 2,810,00047

Total $ 3,800,00048

(726) Drainage Improvements, Phase I49(Jefferson)50Payable from General Obligation Bonds51

Priority 1 $ 490,00052

ENROLLEDHB NO. 2

Page 152 of 202

(1222) Street Improvements, including the Placement of 1Fire Hydrants, Planning and Construction2(Jefferson)3Payable from General Obligation Bonds4

Priority 1 $ 1,000,0005

(1227) Fire Station, Planning and Construction6(Jefferson)7Payable from General Obligation Bonds8

Priority 1 $ 2,835,0009Priority 2 $ 1,265,00010

Total $ 4,100,00011

(1228) Performing Arts Center/Community Center 12Phase III, IV, and Equipment13(Jefferson)14Payable from General Obligation Bonds15

Priority 1 $ 555,00016Priority 2 $ 150,00017Priority 5 $ 250,00018

Total $ 955,00019

(1903) Emergency Preparedness Building, Planning 20and Construction21(Jefferson)22Payable from General Obligation Bonds23

Priority 1 $ 1,240,00024

(1904) Farmers/Fisheries Market, Planning and 25Construction26(Jefferson)27Payable from General Obligation Bonds28

Priority 1 $ 115,00029

(1907) Riverboat Landing Phase IV, Planning and30Construction ($200,000 Local Match)31(Jefferson)32Payable from General Obligation Bonds33

Priority 1 $ 150,00034

50/MV7 WINNFIELD35

(1025) Port DeLuce Reservoir, Planning and 36Construction37(Winn)38Payable from General Obligation Bonds39

Priority 2 $ 500,00040Priority 5 $ 15,000,00041

Total $ 15,500,00042

50/MV8 WINNSBORO43

(1741) Winnsboro Farmer's Market, Planning and 44Construction45(Franklin)46Payable from General Obligation Bonds47

Priority 1 $ 220,00048

ENROLLEDHB NO. 2

Page 153 of 202

(1742) Community Center, Renovations, Planning 1and Construction2(Franklin)3Payable from General Obligation Bonds4

Priority 1 $ 20,0005

50/MW2 YOUNGSVILLE6

(1036) Infrastructure Improvements for the Youngsville 7Sports Complex, Planning and Construction8(Lafayette)9Payable from General Obligation Bonds10

Priority 1 $ 3,165,00011Priority 2 $ 1,525,00012

Total $ 4,690,00013

(1748) Youngsville Parkway Road Project, Including14Waterline Improvements, Roadway Lighting,15and Other Infrastructure Improvements16Planning and Construction17(Lafayette)18Payable from General Obligation Bonds19

Priority 1 $ 1,625,00020

(1959) Highway 92 Realignment Near Youngsville,21Construction, Right of Way, and Utilities22(Lafayette)23Payable from General Obligation Bonds24

Priority 1 $ 295,00025

50/MW3 ZACHARY26

(297) Water System Improvements, Planning and27Construction 28(East Baton Rouge)29Payable from General Obligation Bonds30

Priority 1 $ 70,00031Priority 5 $ 230,00032

Total $ 300,00033

(298) Natural Gas Distribution System Improvements,34Planning and Construction 35(East Baton Rouge)36Payable from General Obligation Bonds37

Priority 1 $ 95,00038

(1910) Annison Plantation Renovation39(East Baton Rouge)40Payable from General Obligation Bonds41

Priority 1 $ 135,00042

(1912) Sewer Testing and Rehabilitation, Planning 43and Construction44(East Baton Rouge)45Payable from General Obligation Bonds46

Priority 1 $ 70,00047

ENROLLEDHB NO. 2

Page 154 of 202

50/MW4 ZWOLLE1

(1277) Installation of 6" Waterline and Water Well, 2Planning and Construction ($25,000 Local Match)3(Sabine)4Payable from General Obligation Bonds5

Priority 1 $ 350,0006

50/MW6 ST. GABRIEL7

(301) St. Gabriel Police Department - Land, Building 8Acquisition Project, Planning and Construction9(Iberville)10Payable from General Obligation Bonds11

Priority 1 $ 200,00012Priority 5 $ 300,00013

Total $ 500,00014

(2117) Civic Center, Planning and Construction 15(Local Match Required)16(Iberville)17Payable from General Obligation Bonds18

Priority 2 $ 5,00019

Provided, however, that $5,000 of the Priority 2 appropriation for this project is used to20replace general obligation bond proceeds reappropriated to Executive Department, Division21of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,22Gustav and Ike, Planning and Construction (Statewide) in this Act.23

50/MW8 CENTRAL24

(1914) Administration Building25(East Baton Rouge)26Payable from General Obligation Bonds27

Priority 1 $ 490,00028Priority 5 $ 1,415,00029

Total $ 1,905,00030

(1916) Expand, Repair, and Modify City of Central 31Drainage System, Planning and Construction32(East Baton Rouge)33Payable from General Obligation Bonds34

Priority 1 $ 375,00035Priority 2 $ 120,00036

Total $ 495,00037

50/N03 THE AUDUBON INSTITUTE, INC.38

(1107) Audubon 2020 Exhibits39(Orleans)40Payable from General Obligation Bonds41

Priority 1 $ 16,790,00042Priority 2 $ 6,200,00043Priority 5 $ 19,200,00044

Total $ 42,190,00045

ENROLLEDHB NO. 2

Page 155 of 202

50/N04 NEW ORLEANS MUSEUM OF ART1

(2118) Improvements and Acquisitions, 2Planning and Construction3($500,000 Local/Federal Match)4(Orleans)5Payable from General Obligation Bonds6

Priority 2 $ 139,2007

Provided, however, that $139,200 of the Priority 2 appropriation for this project is used to8replace general obligation bond proceeds reappropriated to Executive Department, Division9of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,10Gustav and Ike, Planning and Construction (Statewide) in this Act.11

50/N05 NEW ORLEANS EXHIBITION AUTHORITY12

(681) Property Development Project13(Orleans)14Payable from General Obligation Bonds15

Priority 2 $ 5,000,00016Priority 5 $ 20,000,00017

Total $ 25,000,00018

50/N06 STATE FAIR OF LOUISIANA19

(516) Hirsch Memorial Coliseum/Evacuation Shelter20Rehabilitation, Planning and Construction21(Caddo)22Payable from General Obligation Bonds23

Priority 5 $ 95,0002425

50/N07 ST BERNARD PARISH SHERIFF26

(1919) Arabi Sub-Station, Planning and Construction27(St. Bernard)28Payable from General Obligation Bonds29

Priority 1 $ 15,00030

50/N12 LOUISIANA CHILDREN'S MUSEUM31

(299) Early Learning Village, Planning, Design, 32Construction and Equipment ($18,750,000 33Local Match)34(Orleans)35Payable from General Obligation Bonds36

Priority 1 $ 2,765,00037Priority 2 $ 3,000,00038Priority 5 $ 14,115,00039

Total $ 19,880,00040

50/N13 CHENNAULT INDUSTRIAL AIRPARK AUTHORITY41

(922) Addition to Building #3101, Planning and 42Construction ($926,400 Local Match)43(Calcasieu)44Payable from General Obligation Bonds45

Priority 2 $ 310,00046Priority 5 $ 2,470,00047

Total $ 2,780,00048

ENROLLEDHB NO. 2

Page 156 of 202

(1757) New Air Cargo Facility, Planning and 1Construction ($1,100,000 Local Match)2(Calcasieu)3Payable from General Obligation Bonds4

Priority 1 $ 350,0005Priority 5 $ 2,750,0006

Total $ 3,100,0007

(1758) New Aviation Hangar and Ground Support 8Equipment Facility, Planning and Construction 9($1,000,000 Local Match)10(Calcasieu)11Payable from General Obligation Bonds12

Priority 1 $ 260,00013Priority 5 $ 1,825,00014

Total $ 2,085,00015

(1759) New Hangar, Planning and Construction16(Calcasieu)17Payable from General Obligation Bonds18

Priority 1 $ 2,300,00019

50/N21 BIOMEDICAL RESEARCH FOUNDATION20

(910) P.E.T. Clinical and Research Imaging Equipment21(Caddo)22Payable from General Obligation Bonds23

Priority 1 $ 4,800,00024

(1236) Micro-Imaging Equipment for the Molecular25Imaging Center at the Biomedical Research26Foundation in Shreveport: Equipment27(Caddo)28Payable from General Obligation Bonds29

Priority 2 $ 1,200,00030Priority 5 $ 2,500,00031

Total $ 3,700,00032

Pending approval of capital outlay budget request pursuant to the provisions of R.S. 39:112.33

(1331) Hospital HVAC Replacement, 34Planning and Construction35(Caddo)36Payable from General Obligation Bonds37

Priority 2 $ 1,000,00038Priority 5 $ 2,200,00039

Total $ 3,200,00040

Pending approval of capital outlay budget request pursuant to the provisions of R.S. 39:112.41

(1333) Essential Medical Equipment (BRF dba 42BRFHH, LLC for University Health Conway)43(Ouachita)44Payable from General Obligation Bonds45

Priority 2 $ 1,170,00046

Pending approval of capital outlay budget request pursuant to the provisions of R.S. 39:112.47

ENROLLEDHB NO. 2

Page 157 of 202

50/N25 WYES TV NEW ORLEANS1

(714) WYES Katrina Rebuilding/Equipment Project 2(Orleans)3Payable from General Obligation Bonds4

Priority 1 $ 990,0005Priority 2 $ 1,200,0006Priority 5 $ 2,000,0007

Total $ 4,190,0008

50/N31 ORLEANS PARISH LAW ENFORCEMENT 9DISTRICT10

(1954) Mental Health Facility, Planning and Construction11(Orleans)12Payable from General Obligation Bonds13

Priority 1 $ 100,00014Priority 5 $ 2,400,00015

Total $ 2,500,00016

50/N33 ENGLAND ECONOMIC AND INDUSTRIAL 17DEVELOPMENT DISTRICT18

(836) Warehouse/Distribution Complex, Planning19and Construction20(Rapides)21Payable from General Obligation Bonds22

Priority 2 $ 200,00023

50/N34 ODYSSEY HOUSE LOUISIANA, INC.24

(1157) Odyssey House Louisiana Renovation Project, 25Planning and Construction26(Orleans)27Payable from General Obligation Bonds28

Priority 5 $ 5,900,00029

50/N38 NEW ORLEANS REGIONAL BUSINESS PARK30

(1925) Multi-Purpose Athletic Complex, Planning and31Construction32(Orleans)33Payable from General Obligation Bonds34

Priority 1 $ 10,00035

50/N41 BATON ROUGE METRO AIRPORT36

(893) Airport Aviation Business Park, Planning and37Construction38(East Baton Rouge)39Payable from General Obligation Bonds40

Priority 1 $ 600,00041Priority 2 $ 100,00042Priority 5 $ 500,00043

Total $ 1,200,00044

ENROLLEDHB NO. 2

Page 158 of 202

50/N49 ST. HELENA PARISH SHERIFF1

(1933) Renovation of Sheriff's Office Administration Building2in Greensburg, Planning and Construction3(St. Helena)4Payable from General Obligation Bonds5

Priority 1 $ 190,0006Priority 5 $ 50,0007

Total $ 240,0008

50/N51 NEW ORLEANS JAZZ AND HERITAGE 9FOUNDATION10

(1762) The Jazz and Heritage Center Renovation and Addition111225 North Rampart, Planning and Construction12(Orleans)13Payable from General Obligation Bonds14

Priority 1 $ 70,00015Priority 2 $ 625,00016

Total $ 695,00017

50/N60 CALCASIEU PARISH WATERWORKS DISTRICT #218

(537) Mossville System Improvements, 19Planning and Construction20(Calcasieu)21Payable from General Obligation Bonds22

Priority 2 $ 100,00023Priority 5 $ 1,235,00024

Total $ 1,335,00025

50/N62 PLAQUEMINES PARISH LAW ENFORCEMENT 26DISTRICT27

(1934) Sheriff's Training Center, Planning and Construction28(Plaquemines)29Payable from General Obligation Bonds30

Priority 1 $ 1,865,00031

50/N70 REGIONAL TRANSIT AUTHORITY32

(1935) Airport to CBD Regional Rail Line ($5,000,000 Local33and $10,000,000 Federal Match)34(Orleans)35Payable from General Obligation Bonds36

Priority 5 $ 5,000,00037

50/N71 NORTH LAFOURCHE CONSERVATION 38LEVEE AND DRAINAGE DISTRICT39

(1143) Bayou Boeuf School Forced Drainage Area System40Improvements, Planning and Construction41(Lafourche)42Payable from General Obligation Bonds43

Priority 2 $ 105,00044

(1206) 80 Arpent Canal Dredging, Caldwell Plantation to45Laurel Valley, Planning and Construction46(Lafourche)47Payable from General Obligation Bonds48

Priority 1 $ 1,110,00049

ENROLLEDHB NO. 2

Page 159 of 202

50/N74 NATIONAL WORLD WAR II MUSEUM1

(616) Capital Expansion Project, including Parking Structure,2Skybridge, Andrew Higgins Plaza, Train Station 3Experience and Canopy, Planning and4Construction5(Orleans)6Payable from General Obligation Bonds7

Priority 1 $ 8,990,0008Priority 2 $ 6,000,0009Priority 5 $ 8,000,00010

Total $ 22,990,00011

50/N76 WEST CALCASIEU AIRPORT AUTHORITY12

(1014) T-Hangar and Fuel Farm Rehabilitation, 13Planning and Construction14(Calcasieu)15Payable from General Obligation Bonds16

Priority 2 $ 250,00017Priority 5 $ 200,00018

Total $ 450,00019

(1015) Entrance Roadway for Airport Industrial Park,20Planning and Construction21(Calcasieu)22Payable from General Obligation Bonds23

Priority 2 $ 50,00024Priority 5 $ 1,300,00025

Total $ 1,350,00026

50/N98 KINGSLEY HOUSE27

(788) Kingsley House Acquisition, Renovations, New28Construction and Major Repairs29(Orleans)30Payable from General Obligation Bonds31

Priority 1 $ 5,890,00032

50/NA2 LAFAYETTE AIRPORT COMMISSION33

(1767) Construction of Cargo Facilities, Planning and34Construction35(Lafayette)36Payable from General Obligation Bonds37

Priority 1 $ 4,990,00038

50/NAJ EFFORTS OF GRACE, INC.39

(1937) Ashe Too, Planning and Construction40(Orleans)41Payable from General Obligation Bonds42

Priority 1 $ 15,00043Priority 5 $ 360,00044

Total $ 375,00045

ENROLLEDHB NO. 2

Page 160 of 202

50/NAY OGDEN MUSEUM OF SOUTHERN ART1

(300) Ogden Museum/Taylor Library Renovation, 2Planning and Construction3(Orleans)4Payable from General Obligation Bonds5

Priority 1 $ 265,0006Priority 5 $ 1,000,0007

Total $ 1,265,0008

50/NB3 MCKINLEY HIGH SCHOOL ALUMNI9

(1938) Old McKinley High Community Center on 10Thomas Delpit Drive in the City of Baton 11Rouge, Planning and Construction12(East Baton Rouge)13Payable from General Obligation Bonds14

Priority 2 $ 589,60015

Provided, however, that $589,600 of the Priority 2 appropriation for this project is used to16replace general obligation bond proceeds reappropriated to Executive Department, Division17of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,18Gustav and Ike, Planning and Construction (Statewide) in this Act.19

50/NBB LIGHTHOUSE FOR BLIND20

(1285) Economic Development Project, Planning and21Construction22(Orleans)23Payable from General Obligation Bonds24

Priority 1 $ 2,850,00025Priority 5 $ 1,450,00026

Total $ 4,300,00027

50/NBC CAPITOL CITY FAMILY HEALTH CENTER28

(1939) New Federally Qualified Health Center, Acquisitions,29Planning and Construction ($71,000 Federal Match)30(Ascension, East Baton Rouge)31Payable from General Obligation Bonds32

Priority 1 $ 50,00033

50/NBG SOUTH LOUISIANA DEVELOPMENT COUNCIL34

(1089) Renovations to SLEC Offices Babington Hall35at NSU, Planning and Construction36(Assumption, Lafourche, St. Mary, 37Terrebonne)38Payable from General Obligation Bonds39

Priority 2 $ 195,00040

(1773) SLEC/Nicholls Field and Drainage Improvements,41Planning and Construction42(Lafourche)43Payable from General Obligation Bonds44

Priority 1 $ 1,000,00045

(1774) Center for Economic Growth and Technology46(Lafourche)47Payable from General Obligation Bonds48

Priority 1 $ 10,00049

ENROLLEDHB NO. 2

Page 161 of 202

50/NBM BLACK RIVER LAKE COMMISSION1

(1776) Black River Lake Drainage Structure Installation,2Studies, Permits, Planning and Construction3(Concordia)4Payable from General Obligation Bonds5

Priority 1 $ 255,0006Priority 5 $ 3,075,0007

Total $ 3,330,0008

50/NBT DISTRICT 2 ENHANCEMENT CORPORATION9

(1065) St. Claude Community Development and 10Beautification Project, Planning and Construction11(Orleans)12Payable from General Obligation Bonds13

Priority 1 $ 10,00014

(1066) New Orleans East Walking and Bike Trail, 15Planning and Construction16(Orleans)17Payable from General Obligation Bonds18

Priority 1 $ 25,00019

(2049) Health Clinics20(Orleans)21Payable from General Obligation Bonds22

Priority 2 $ 1,651,90023

Provided, however, that $1,651,900 of the Priority 2 appropriation for this project is used to24replace general obligation bond proceeds reappropriated to Executive Department, Division25of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,26Gustav and Ike, Planning and Construction (Statewide) in this Act.27

(2121) Eastern New Orleans Community Center, 28Planning and Construction29(Orleans)30Payable from General Obligation Bonds31

Priority 2 $ 1,850,70032

Provided, however, that $1,850,700 of the Priority 2 appropriation for this project is used to33replace general obligation bond proceeds reappropriated to Executive Department, Division34of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,35Gustav and Ike, Planning and Construction (Statewide) in this Act.36

50/NC2 BATON ROUGE RECREATION AND PARKS 37COMMISSION38

(781) Central Community Sports Park, Planning and39Construction40(East Baton Rouge)41Payable from General Obligation Bonds42

Priority 1 $ 1,140,00043Priority 2 $ 150,00044Priority 5 $ 555,00045

Total $ 1,845,00046

ENROLLEDHB NO. 2

Page 162 of 202

(782) Children's Museum, Planning and Construction1($5,000,000 Local Match)2(East Baton Rouge)3Payable from General Obligation Bonds4

Priority 1 $ 900,0005Priority 2 $ 150,0006

Total $ 1,050,0007

(783) Bluebonnet Swamp Nature Center Education8Building/Conference Center, Planning and 9Construction 10(East Baton Rouge)11Payable from General Obligation Bonds12

Priority 1 $ 260,00013Priority 5 $ 500,00014

Total $ 760,00015

(784) Anna T. Jordan Site and Facility Improvements 16(Non-State Match Required)17(East Baton Rouge)18Payable from General Obligation Bonds19

Priority 1 $ 1,405,00020Priority 2 $ 150,00021

Total $ 1,555,00022

(1941) Pete Goldsby Field Renovations (Non-State Cash23and/or In-Kind Match Required)24(East Baton Rouge)25Payable from General Obligation Bonds26

Priority 5 $ 45,00027

50/NCC ARCHDIOCESE OF NEW ORLEANS28

(1233) Preservation and Restoration of Historic Structures for29Hope Haven/Madonna Manor Campus, Planning and 30Construction31(Jefferson)32Payable from General Obligation Bonds33

Priority 2 $ 300,00034Priority 5 $ 2,800,00035

Total $ 3,100,00036

50/NCJ WATER WORKS DISTRICT 14 CALCASIEU37

(896) Replacement of Old Starks Water System Lines and38Plugging of Old Wells, Planning and Construction39(Calcasieu)40Payable from General Obligation Bonds41

Priority 2 $ 50,00042Priority 5 $ 250,00043

Total $ 300,00044

50/NCM FIFTH WARD RECREATION DISTRICT OF 45ST HELENA46

(1090) St. Helena Park District 47(St. Helena)48Payable from General Obligation Bonds49

Priority 2 $ 75,00050Priority 5 $ 915,00051

Total $ 990,00052

ENROLLEDHB NO. 2

Page 163 of 202

50/NCN SOUTH TOLEDO BEND WATERWORKS DISTRICT1

(1779) Water Distribution System Improvements2Including Water Meters3(Sabine)4Payable from General Obligation Bonds5

Priority 1 $ 630,0006

50/NCY RECONCILE NEW ORLEANS INC7

(1940) Reconcile New Orleans, Renovation and Expansion8Project, Central City New Orleans, Planning and 9Construction10(Orleans)11Payable from General Obligation Bonds12

Priority 1 $ 55,00013

50/NCZ LOUISIANA ASSOCIATION FOR THE BLIND14

(438) Louisiana Association for the Blind Manufacturing15Facility and Organization and Headquarters, Planning 16and Construction17(Caddo)18Payable from General Obligation Bonds19

Priority 1 $ 200,00020

(1942) Louisiana Association for the Blind Safety Walk21Manufacturing Facility, Planning and Construction22(Caddo)23Payable from General Obligation Bonds24

Priority 1 $ 10,00025

50/NDN OPPORTUNITIES INDUSTRIALIZATION CENTER26

(2135) New Education Building, Planning and Construction27(Ouachita)28Payable from General Obligation Bonds29

Priority 2 $ 1,000,00030Priority 5 $ 2,000,00031

Total $ 3,000,00032

50/NDX NEW ORLEANS COUNCIL ON AGING33

(1952) Office and Senior Community Center, Planning, Land34Acquisition, and Construction35(Orleans)36Payable from General Obligation Bonds37

Priority 1 $ 125,00038

50/NE7 WEST CALCASIEU COMMUNITY CENTER39

(1782) Community Center - Phase 2, Event Center, Planning40and Construction41(Calcasieu)42Payable from General Obligation Bonds43

Priority 1 $ 3,615,00044

ENROLLEDHB NO. 2

Page 164 of 202

50/NEB LIVINGSTON PARISH FAIRGROUND AUTHORITY1

(1965) Livingston Parish Fairgrounds, Livestock Exhibition2Building, Planning and Construction3(Livingston)4Payable from General Obligation Bonds5

Priority 5 $ 245,0006

50/NER ST HELENA HOSPITAL SERVICE DISTRICT #17

(1951) Drainage and Parking Improvements, Planning and8Construction9(St. Helena)10Payable from General Obligation Bonds11

Priority 1 $ 15,00012

50/NEZ LOUISIANA ALLIANCE OF BOYS AND GIRLS CLUB13

(1785) Louisiana Alliance of Boys and Girls Club, Inc.,14Planning, Acquisitions, and Construction15(Statewide)16Payable from General Obligation Bonds17

Priority 1 $ 35,00018Priority 5 $ 150,00019

Total $ 185,00020

50/NF8 CENTRAL LOUISIANA DETENTION CENTER 21AUTHORITY22

(613) Central Louisiana Juvenile Detention Center, Planning23and Construction24(Grant)25Payable from General Obligation Bonds26

Priority 1 $ 235,00027Priority 5 $ 500,00028

Total $ 735,00029

50/NFE CAJUNDOME30

(1788) Cajundome Improvements, Planning and Construction31(Lafayette)32Payable from General Obligation Bonds33

Priority 1 $ 220,00034

50/NFL BOGALUSA YMCA35

(1950) Bogalusa YMCA, Master Planning, Design,36Construction, Renovations and Equipment Acquisitions37(Washington)38Payable from General Obligation Bonds39

Priority 1 $ 80,00040

50/NFN DOC-DHL, INC.41

(1949) Cohn Senior High Renovation, Planning and42Construction43(West Baton Rouge)44Payable from General Obligation Bonds45

Priority 5 $ 400,00046

ENROLLEDHB NO. 2

Page 165 of 202

50/NFQ ALGIERS DEVELOPMENT DISTRICT1

(1948) New Westbank YMCA2(Orleans)3Payable from General Obligation Bonds4

Priority 1 $ 2,945,0005

50/NFS SHREVEPORT - RUSTON METHODIST CAMP6

(1947) Caney Conference Center Remodel Project, Planning7and Construction8(Webster)9Payable from General Obligation Bonds10

Priority 1 $ 645,00011

50/NG2 NORTHSHORE HARBOR CENTER12

(1325) Facility Renovations, Planning and Construction13(St. Tammany)14Payable from General Obligation Bonds15

Priority 2 $ 195,00016

(1946) Northshore Harbor Center Purchase of Additional17Equipment18(St. Tammany)19Payable from General Obligation Bonds20

Priority 1 $ 195,00021

50/NG6 LOUISIANA BLACK HISTORY HALL OF FAME22

(1945) Museum and Cultural Center, Land Acquisition,23Planning and Construction ($100,000 Cash and/or 24In-Kind Match)25(East Baton Rouge)26Payable from General Obligation Bonds27

Priority 5 $ 1,090,00028

50/NGA LINCOLN PARISH FIRE PROTECTION 29DISTRICT #130

(1944) Renovations to Existing Facility and Additional31Buildings, Acquisition, Planning and Construction32(Lincoln)33Payable from General Obligation Bonds34

Priority 1 $ 120,00035

50/NGE WEST VERNON WATERWORKS DISTRICT36

(1791) Expansion of Water Distribution System and Booster37Station West Vernon Waterworks District, Planning 38and Construction39(Vernon)40Payable from General Obligation Bonds41

Priority 1 $ 630,00042Priority 2 $ 300,00043

Total $ 930,00044

ENROLLEDHB NO. 2

Page 166 of 202

50/NGF FAMILY CENTER OF LIFE, INC.1

(1943) Family Center of Hope Community Center in New2Orleans, Planning and Construction ($600,000 3Local Match)4(Orleans)5Payable from General Obligation Bonds6

Priority 1 $ 90,0007

50/NGQ STRAND THEATRE OF SHREVEPORT8

(665) Repair and Renovation to the Strand Theatre of9Shreveport10(Caddo)11Payable from General Obligation Bonds12

Priority 5 $ 950,00013

50/NGS RURAL FRANKLINTON WATER CORPORATION14

(1932) Black Jack Road Water Well15(Washington)16Payable from General Obligation Bonds17

Priority 5 $ 20,00018

50/NGX CANE RIVER WATERWAY COMMISSION19

(217) Cane River Lake Pumping, Planning and Construction20(Natchitoches)21Payable from General Obligation Bonds22

Priority 2 $ 200,00023Priority 5 $ 1,000,00024

Total $ 1,200,00025

(218) Cane River Lake Drainage Study 26(Natchitoches)27Payable from General Obligation Bonds28

Priority 1 $ 70,00029

50/NGY LINCOLN PARISH SHERIFF OFFICE30

(1931) Public Safety Complex, Planning and Construction31(Lincoln)32Payable from General Obligation Bonds33

Priority 1 $ 2,865,00034

50/NHA WASHINGTON PARISH FAIR ASSOCIATION35

(1037) Replacement of and Repairs and Additions to 36Buildings on Fairgrounds and Renovations and 37Repairs to Historic Buildings at Mile Branch 38Settlement and Improvements at Fairgrounds, 39Planning and Construction 40(Washington)41Payable from General Obligation Bonds42

Priority 1 $ 80,00043

ENROLLEDHB NO. 2

Page 167 of 202

50/NHC ARC OF OUACHITA1

(1793) Emergency Shelter and Therapeutic Center for the2Developmentally Disabled, Acquisition, Planning, 3Construction and Renovation4(Ouachita)5Payable from General Obligation Bonds6

Priority 1 $ 95,0007Priority 5 $ 900,0008

Total $ 995,0009

50/NHF NEW ORLEANS NEIGHBORHOOD DEVELOPMENT10

(1929) NDF Homeownership Center, Planning and11Construction12(Orleans)13Payable from General Obligation Bonds14

Priority 5 $ 230,00015

50/NHL BOGALUSA COMMUNITY MEDICAL CENTER 16FOUNDATION17

(1928) Capital Improvements at Washington St. Tammany18Regional Medical Center19(St. Tammany, Washington)20Payable from General Obligation Bonds21

Priority 1 $ 6,090,00022

50/NHM TRINITY CHRISTIAN COMMUNITY23

(1927) Carrollton Community Center Renovations, Land24Acquisition, Site Work, Planning and Construction25(Orleans)26Payable from General Obligation Bonds27

Priority 1 $ 1,310,00028Priority 2 $ 235,00029

Total $ 1,545,00030

Provided, however, that $235,000 of the Priority 2 appropriation for this project is used to31replace general obligation bond proceeds reappropriated to Executive Department, Division32of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,33Gustav and Ike, Planning and Construction (Statewide) in this Act.34

50/NHN NEW ORLEANS MUSIC HALL OF FAME35

(1926) South Rampart Street Historic Development Project,36Planning and Construction, ($300,000 Non-State Match)37(Orleans)38Payable from General Obligation Bonds39

Priority 1 $ 40,00040Priority 5 $ 65,00041

Total $ 105,00042

50/NHS PLEASANT HILL-CROSSROADS WATER 43SYSTEM, INC.44

(1063) Pleasant Hill/Crossroads Water System-Repairs and45Extension, Planning and Construction46(Winn)47Payable from General Obligation Bonds48

Priority 1 $ 135,00049Priority 2 $ 230,00050

Total $ 365,00051

ENROLLEDHB NO. 2

Page 168 of 202

50/NI9 ASCENSION - ST JAMES AIRPORT AUTHORITY1

(1923) Automobile Parking Lot Improvements for the2Louisiana Regional Airport3(Ascension)4Payable from General Obligation Bonds5

Priority 1 $ 45,0006

50/NIJ TENSAS REUNION7

(1054) Tensas Reunion Museum and Heritage Culture8and Education Center9(Tensas)10Payable from General Obligation Bonds11

Priority 2 $ 250,00012Priority 5 $ 250,00013

Total $ 500,00014

50/NIK LOUISIANA 4-H FOUNDATION15

(1798) Louisiana 4-H Foundation Youth Educational16Development Center, Camp Windy Wood Property, 17Including Multipurpose Educational18Building, Planning, Construction and Acquisition19(Grant)20Payable from General Obligation Bonds21

Priority 1 $ 300,00022

50/NIX BELLWOOD WATER SYSTEM, INC.23

(1800) Bellwood Water System, Planning and Construction24(Natchitoches)25Payable from General Obligation Bonds26

Priority 1 $ 10,00027

(1801) Bellwood Water System Generator, Back-Up Power28Source, Planning and Construction29(Natchitoches)30Payable from General Obligation Bonds31

Priority 1 $ 15,00032

50/NJ2 CONTEMPORARY ARTS CENTER33

(1921) Contemporary Arts Center Renovation, Planning and34Construction ($6,131,272 Local Match)35(Orleans)36Payable from General Obligation Bonds37

Priority 1 $ 290,00038Priority 5 $ 300,00039

Total $ 590,00040

50/NJ5 REPUBLIC OF WEST FLORIDA MUSEUM41

(2122) Acquisition of Old McKowen High School,42Planning and Construction43(East Feliciana)44Payable from General Obligation Bonds45

Priority 2 $ 117,60046

Provided, however, that $117,600 of the Priority 2 appropriation for this project is used to47replace general obligation bond proceeds reappropriated to Executive Department, Division48of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,49Gustav and Ike, Planning and Construction (Statewide) in this Act.50

ENROLLEDHB NO. 2

Page 169 of 202

50/NJ7 LIFESHARE BLOOD CENTERS1

(1345) LifeShare Blood Centers' Lake Charles Facility Flood2Wall and Retractable Flood Gates Project 3(Calcasieu)4Payable from General Obligation Bonds5

Priority 2 $ 160,0006

50/NJ8 NORTH LOUISIANA CRIMINALISTICS LAB7

(1920) Replacement of Shreveport Facility, Planning and8Construction9(Caddo)10Payable from General Obligation Bonds11

Priority 1 $ 22,240,00012Priority 2 $ 1,400,00013Priority 5 $ 2,000,00014

Total $ 25,640,00015

50/NJ9 DRYADES YMCA16

(1913) Dryades YMCA Reconstruction, Planning and17Construction18(Orleans)19Payable from General Obligation Bonds20

Priority 1 $ 200,00021Priority 2 $ 50,00022

Total $ 250,00023

(1915) Technical Training Center, Planning and Construction24(Orleans)25Payable from General Obligation Bonds26

Priority 1 $ 1,030,00027Priority 5 $ 3,700,00028

Total $ 4,730,00029

50/NJP WATERWORKS DISTRICT #1 DESOTO PARISH30

(869) Water System Improvements and Extension, Planning31and Construction ($1,977,300 Local Match)32(DeSoto)33Payable from General Obligation Bonds34

Priority 1 $ 345,00035Priority 5 $ 715,00036

Total $ 1,060,00037

50/NJU RED HILL WATERWORKS38

(1803) Replacement Water Well, Connections and Equipment,39Planning and Construction40(Winn)41Payable from General Obligation Bonds42

Priority 1 $ 315,00043

50/NJV HARVEY - STEVENS MEMORIAL FOUNDATION44

(1804) Tutorial and Learning Resource Center Renovations,45Planning and Construction46(St. Landry)47Payable from General Obligation Bonds48

Priority 5 $ 65,00049

ENROLLEDHB NO. 2

Page 170 of 202

50/NJY EAST COLUMBIA WATER DISTRICT1

(1805) East Columbia Water System Improvements, Planning2and Construction3(Caldwell)4Payable from General Obligation Bonds5

Priority 1 $ 645,0006

50/NJZ GRAVITY DRAINAGE DISTRICT #87

(952) Belfield Ditch Drainage Improvement Project, Planning8and Construction9(Calcasieu)10Payable from General Obligation Bonds11

Priority 2 $ 910,00012Priority 5 $ 2,190,00013

Total $ 3,100,00014

50/NK2 COMMUNITY OUTREACH PROGRAMS15

(1960) Willow Glen River Road Senior Resource Center,16Planning, Construction and Equipment17(Rapides)18Payable from General Obligation Bonds19

Priority 5 $ 1,195,00020

50/NK8 FRANKLIN MEDICAL CENTER21

(1806) Franklin Medical Center Renovations, Planning and22Construction23(Franklin)24Payable from General Obligation Bonds25

Priority 1 $ 95,00026

50/NKC WEBSTER PARISH COUNCIL ON AGING27

(1911) New Building for Webster Parish Council on Aging,28Planning and Construction29(Webster)30Payable from General Obligation Bonds31

Priority 1 $ 475,00032

50/NKH ALLUME SOCIETY33

(1807) Frank's Theatre Restoration, Planning, Acquisition,34Renovation, and Construction ($100,000 Cash and/or 35In-Kind Match)36(Vermilion)37Payable from General Obligation Bonds38

Priority 1 $ 175,00039

50/NKY HOLUM WATER SYSTEM, INC.40

(1808) Holum Water System Improvements Including New41Water Well, Planning and Construction42(Caldwell)43Payable from General Obligation Bonds44

Priority 1 $ 5,00045

ENROLLEDHB NO. 2

Page 171 of 202

50/NL3 LOUISIANA YAMBILEE, INC.1

(2123) Louisiana Yambilee Building, Planning 2and Construction, Restoration and/or 3Remodeling to the Yamatorium and Facilities4(St. Landry)5Payable from General Obligation Bonds6

Priority 2 $ 33,7007

Provided, however, that $33,700 of the Priority 2 appropriation for this project is used to8replace general obligation bond proceeds reappropriated to Executive Department, Division9of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,10Gustav and Ike, Planning and Construction (Statewide) in this Act.11

50/NLA CENTENARY COLLEGE OF LOUISIANA12

(1909) Science Building, Planning and Construction13(Caddo)14Payable from General Obligation Bonds15

Priority 1 $ 845,00016

50/NLM FOUNDATION FOR SCIENCE AND 17MATH EDUCATION18

(1860) A Model for a 21st Century Workforce Development19Urban High School - New Orleans Science and 20Mathematics High School, Planning and21Construction and Land Acquisition22(Orleans)23Payable from General Obligation Bonds24

Priority 2 $ 2,335,50025Priority 5 $ 195,00026

Total $ 2,530,50027

Provided, however, that $2,335,500 of the Priority 2 appropriation for this project is used to28replace general obligation bond proceeds reappropriated to Executive Department, Division29of Administration, Repairs, Restoration and Replacement for Hurricanes Katrina, Rita,30Gustav and Ike, Planning and Construction (Statewide) in this Act.31

50/NLN MIDWAY WATERWORKS, INC.32

(1859) Midway Water System, Planning and Construction33(Webster)34Payable from General Obligation Bonds35

Priority 1 $ 95,00036Priority 5 $ 505,00037

Total $ 600,00038

50/NLQ SAREPTA WATER WORKS DISTRICT39

(1858) Sarepta Water Works40(Webster)41Payable from General Obligation Bonds42

Priority 5 $ 715,00043

50/NLR HORSESHOE ROAD WATER SYSTEM, INC.44

(1857) Horseshoe Water System, Planning and Construction45(Webster)46Payable from General Obligation Bonds47

Priority 1 $ 150,00048Priority 5 $ 80,00049

Total $ 230,00050

ENROLLEDHB NO. 2

Page 172 of 202

50/NM1 RAPIDES WATER WORKS DISTRICT NO. 31

(1141) Color Removal from Well No. 2 and Well 2No. 7 at LA Army National Guard, Camp 3Beauregard, Pineville, LA, Planning and 4Construction5(Rapides)6Payable from General Obligation Bonds7

Priority 1 $ 50,0008Priority 2 $ 75,0009

Total $ 125,00010

50/NM3 NATCHITOCHES COUNCIL ON AGING11

(842) Reconstruction and Renovations to Natchitoches Parish12Council on Aging Office and Activities Building, 13Planning and Construction14(Natchitoches)15Payable from General Obligation Bonds16

Priority 1 $ 50,00017

(1809) Reconstruct Natchitoches Parish Council on Aging18Activities Building, Planning and Construction19(Natchitoches)20Payable from General Obligation Bonds21

Priority 1 $ 845,00022

50/NMB WATERWORKS DISTRICT #1 OF WARD #1 23OF CALCASIEU24

(634) Topsy Road Waterline Improvements (Welcome Road25to Parish Road), Planning and Construction26(Calcasieu)27Payable from General Obligation Bonds28

Priority 2 $ 225,00029

50/NMD BELMONT WATERWORKS30

(1810) Water System Improvements, Planning and31Construction32(Sabine)33Payable from General Obligation Bonds34

Priority 1 $ 1,445,00035

50/NMG LIVINGSTON ASSOCIATION RETARDED 36CHILDREN, INC.37

(1158) New Facility for Livingston Association for Retarded38Children, Inc. Planning and Construction39(Livingston)40Payable from General Obligation Bonds41

Priority 1 $ 405,00042Priority 2 $ 125,00043

Total $ 530,00044

50/NMH SOUTHWEST OUACHITA WATERWORKS45

(1062) Water Distribution System Renovations, Planning and46Construction 47(Ouachita)48Payable from General Obligation Bonds49

Priority 2 $ 300,00050

ENROLLEDHB NO. 2

Page 173 of 202

50/NML CITY OF GRETNA POLICE DEPARTMENT1

(1341) Waterproof/Weatherize Vital Records Facility,2Planning and Construction 3(Jefferson)4Payable from General Obligation Bonds5

Priority 2 $ 250,0006

(1854) Gretna Police Department Critical Radio Infrastructure7Digital Bridging8(Jefferson)9Payable from General Obligation Bonds10

Priority 5 $ 25,00011

(1855) Gretna Police Department Crime Cameras12(Jefferson)13Payable from General Obligation Bonds14

Priority 1 $ 45,00015

(1856) Gretna Police Department, Construction of Armory,16Elevation/Flood Proofing/Wind Retrofit, Planning and 17Construction18(Jefferson)19Payable from General Obligation Bonds20

Priority 1 $ 1,280,00021Priority 2 $ 1,580,00022

Total $ 2,860,00023

50/NNB PROFESSIONAL SPECIALTIES24

(1853) USDA Veterinary Biologic Facility, Planning and25Construction26(East Baton Rouge)27Payable from General Obligation Bonds28

Priority 1 $ 200,00029Priority 2 $ 250,00030

Total $ 450,00031

50/NNL HUNGARIAN SETTLEMENT HISTORICAL 32SOCIETY33

(371) Hungarian Settlement Historical Museum, 34Planning and Construction35(Livingston)36Payable from General Obligation Bonds37

Priority 1 $ 110,00038Priority 2 $ 125,00039

Total $ 235,00040

50/NNO GRANT PARISH FIRE DISTRICT #741

(1811) New Fire Station in Verda42(Grant)43Payable from General Obligation Bonds44

Priority 1 $ 90,00045Priority 5 $ 480,00046

Total $ 570,00047

ENROLLEDHB NO. 2

Page 174 of 202

50/NNR WASHINGTON PARISH RECREATION 1DISTRICT #12

(1851) Multi-Purpose Recreation Facility, Land Acquisition,3Master Planning, Design and Construction4(Washington)5Payable from General Obligation Bonds6

Priority 1 $ 75,0007

50/NNW BEAUREGARD PARISH WATERWORKS 8DISTRICT #39

(912) Longacre Road Water Plant Improvements, Planning10and Construction11(Beauregard)12Payable from General Obligation Bonds13

Priority 2 $ 50,00014Priority 5 $ 250,00015

Total $ 300,00016

50/NP3 BAYOU LAFOURCHE FRESH WATER DISTRICT17

(2137) Donaldsonville Flood Control, Planning 18and Construction19(Ascension, Assumption, Lafourche, Terrebonne)20Payable from General Obligation Bonds21

Priority 2 $ 700,00022

Pending approval of a capital outlay budget request pursuant to the provisions of R.S.2339:112.24

50/NPD IBERIA ECONOMIC DEVELOPMENT AUTHORITY25

(1812) Progress Point Business Park and Airport Gateway,26Land Acquisition27(Iberia)28Payable from General Obligation Bonds29

Priority 1 $ 560,00030Priority 2 $ 50,00031

Total $ 610,00032

50/NPP ALLEN PARISH FIRE DISTRICT #333

(1813) Station Expansion, Planning and Construction34(Allen)35Payable from General Obligation Bonds36

Priority 1 $ 145,00037Priority 2 $ 100,00038

Total $ 245,00039

50/NPY WILEY PEVY POST #74 AMERICAN LEGION40

(324) American Legion, Wiley-Pevy Post #7441Roof Repairs/Replacement, Planning and42Construction43(Webster)44Payable from General Obligation Bonds45

Priority 2 $ 120,00046

ENROLLEDHB NO. 2

Page 175 of 202

50/NQ2 GRAVITY DRAINAGE DISTRICT #6 CALCASIEU 1PARISH2

(384) South Buxton Creek Drainage Improvements, 3Planning and Construction4(Calcasieu)5Payable from General Obligation Bonds6

Priority 2 $ 50,0007Priority 5 $ 650,0008

Total $ 700,0009

50/NQ3 NIBLETTS BLUFF PARK COMMISSION10

(1814) Bulkhead Along Sabine River, Planning and11Construction ($50,000 Non-State Match)12(Calcasieu)13Payable from General Obligation Bonds14

Priority 5 $ 95,00015

50/NQE FREED MEN, INC.16

(1815) Freed Men Housing Renovations, Planning 17and Construction18(Ouachita)19Payable from General Obligation Bonds20

Priority 1 $ 45,00021

50/NQF GENTILLY DEVELOPMENT DISTRICT22

(1816) Milne Boys Home, Planning and Construction23(Orleans)24Payable from General Obligation Bonds25

Priority 1 $ 365,00026

50/NQG LAFAYETTE METROPOLITAN EXPRESSWAY 27COMMISSION28

(1817) Lafayette Loop Project, Planning and Construction29(Lafayette)30Payable from General Obligation Bonds31

Priority 5 $ 1,000,00032

50/NQQ ACADIA PARISH TOURIST COMMISSION33

(1818) Acadia Parish Convention and Visitors Commission34Regional Conference Center, Planning and Construction35(Acadia)36Payable from General Obligation Bonds37

Priority 1 $ 150,00038Priority 5 $ 1,920,00039

Total $ 2,070,00040

50/NQV BEAUREGARD WATERWORKS DISTRICT #641

(381) Water System Improvements, Planning and42Construction43(Beauregard)44Payable from General Obligation Bonds45

Priority 1 $ 170,00046Priority 5 $ 1,700,00047

Total $ 1,870,00048

ENROLLEDHB NO. 2

Page 176 of 202

50/NQW CALCASIEU WATERWORKS DISTRICT #101

(382) New Water System, Planning and Construction2(Calcasieu)3Payable from General Obligation Bonds4

Priority 1 $ 750,0005Priority 5 $ 3,120,0006

Total $ 3,870,0007

50/NQY WESTON WATER SYSTEM, INC.8

(1819) Water Mains Extensions with Connections, 9Booster Station and Emergency Power 10Improvements, Planning and Construction11(Jackson)12Payable from General Obligation Bonds13

Priority 1 $ 735,00014

50/NR9 LONGUE VUE HOUSE AND GARDENS15

(1964) Restoration and Master Site Planning 16($498,760 Non-State Match)17(Orleans)18Payable from General Obligation Bonds19

Priority 5 $ 100,00020

50/NRD SOUTH BEAUREGARD PARISH RECREATION 21DISTRICT #222

(1106) Multi-Purpose Recreation Facility, Planning 23and Construction24(Beauregard)25Payable from General Obligation Bonds26

Priority 1 $ 710,00027

50/NRJ KINGWOOD HOMEOWNERS’ ASSOCIATION28

(1850) New Fence Kingwood Subdivision, Planning 29and Construction30(Orleans)31Payable from General Obligation Bonds32

Priority 1 $ 55,00033

50/NRO NATCHITOCHES COMMUNICATIONS DISTRICT34

(416) Natchitoches Parish Emergency Communications35District, Planning and Construction36(Natchitoches)37Payable from General Obligation Bonds38

Priority 1 $ 490,00039Priority 5 $ 2,400,00040

Total $ 2,890,00041

50/NRS NORTH DESOTO WATER SYSTEM, INC.42

(646) Expansion and Improvements to the Water System, 43Planning and Construction44(DeSoto)45Payable from General Obligation Bonds46

Priority 1 $ 100,00047

ENROLLEDHB NO. 2

Page 177 of 202

50/NRV MADISON VOLUNTARY COUNCIL ON AGING1

(667) Expansion and Improvements to Activities 2Building, Planning and Construction3(Madison)4Payable from General Obligation Bonds5

Priority 2 $ 200,0006

50/NSA CALCASIEU DRAINAGE DISTRICT 7 WARD 87

(383) L-14 Improvements, Gravity Drainage 8District 7, Ward 8 of Calcasieu Parish9(Calcasieu)10Payable from General Obligation Bonds11

Priority 2 $ 200,00012Priority 5 $ 1,000,00013

Total $ 1,200,00014

50/NSE SABINE PARISH WATER DISTRICT #115

(1176) New Production Water Well, Planning and 16Construction17(Sabine)18Payable from General Obligation Bonds19

Priority 2 $ 240,00020

50/NSI WALKER COMMUNITY WATER SYSTEM, INC.21

(1823) Water Distribution System Expansion, LA 81022Extension, Planning and Construction23(Jackson)24Payable from General Obligation Bonds25

Priority 1 $ 730,00026

50/NSL DAUGHTERS OF CHARITY SERVICES OF 27NEW ORLEANS28

(1104) Gentilly Health and Wellness Center, Planning29and Construction30(Orleans)31Payable from General Obligation Bonds32

Priority 2 $ 100,00033

50/NSM NATCHITOCHES VETERANS MEMORIAL 34PARK COMMISSION35

(1824) Natchitoches Veterans and Memorial Park, 36Planning and Construction37(Natchitoches)38Payable from General Obligation Bonds39

Priority 1 $ 45,00040

50/NSP EDEN HOUSE41

(1297) New Facility, Acquisition, Planning and 42Construction43(Orleans)44Payable from General Obligation Bonds45

Priority 2 $ 400,00046

ENROLLEDHB NO. 2

Page 178 of 202

50/NSR JUNIOR LEAGUE OF GREATER NEW ORLEANS1

(1846) Renovate Thrift Shop and Annex, Including Parking2Lot, Planning and Construction3(Orleans)4Payable from General Obligation Bonds5

Priority 1 $ 135,0006

(1847) Renovate Annex Building and Re-Purpose Space,7Including Installation of Handicap Accessibility Ramp 8and Bathroom Upgrades, Planning and Construction9(Orleans)10Payable from General Obligation Bonds11

Priority 1 $ 200,00012

(1848) Renovate Headquarters Building, Including HVAC13System, Planning and Construction14(Orleans)15Payable from General Obligation Bonds16

Priority 1 $ 65,00017

50/NSS LOUISIANA EMERGENCY MEDICAL UNIT18

(1825) Louisiana Emergency Medical Unit Medical 19Storage Facility, Planning and Construction20(Lafayette)21Payable from General Obligation Bonds22

Priority 1 $ 125,00023

50/NST DOWNTOWN DEVELOPMENTAL DISTRICT 24OF NEW ORLEANS25

(1845) Improvements to Girod Street, Planning and26Construction27(Orleans)28Payable from General Obligation Bonds29

Priority 1 $ 290,00030

50/NSU BAYOU CIVIC CLUB31

(1826) Facilities Upgrade/Roof and Kitchen, Planning and32Construction33(Lafourche)34Payable from General Obligation Bonds35

Priority 1 $ 135,00036

50/NSX MOREHOUSE PARISH SHERIFF37

(1844) Operations Center Relocation, Site Development,38Renovations and Improvements, Planning and 39Construction 40($130,000 Local Match)41(Morehouse)42Payable from General Obligation Bonds43

Priority 1 $ 375,00044

ENROLLEDHB NO. 2

Page 179 of 202

50/NT2 MERCY ENDEAVORS1

(1091) Irish Channel St. Andrew Street Elderly 2Resource Center, Planning and Construction3(Orleans)4Payable from General Obligation Bonds5

Priority 1 $ 475,0006Priority 2 $ 2,000,0007Priority 5 $ 1,445,0008

Total $ 3,920,0009

50/NTB CALCASIEU WATERWORKS DISTRICT 12 10WARD 311

(745) Waterworks District 12, Ward 3 - Water System12Improvements, Planning and Construction 13(Calcasieu)14Payable from General Obligation Bonds15

Priority 1 $ 1,980,00016Priority 2 $ 120,00017

Total $ 2,100,00018

50/NTG TERREBONNE PARISH RECREATION 19DISTRICTS 2 AND 320

(412) Terrebonne Sports Complex, Phase I, Infrastructure21Improvements, Acquisition, Planning and Construction22(Terrebonne)23Payable from General Obligation Bonds24

Priority 1 $ 1,330,00025Priority 5 $ 2,640,00026

Total $ 3,970,00027

50/NTI JACKSON TOURISM ENHANCEMENT28

(1842) Feliciana Veterans Memorial, Planning and29Construction30(East Feliciana)31Payable from General Obligation Bonds32

Priority 1 $ 30,00033

50/NTJ CADEVILLE WATER DISTRICT34

(1828) Site No. 4 Water System Renovations and35Improvements, Planning and Construction 36(50% Local Match)37(Ouachita)38Payable from General Obligation Bonds39

Priority 1 $ 200,00040

50/NTK UNION LINCOLN WATER SUPPLY INITIATIVE41

(405) Development of Alternative Water Supply from42Lake D'Arbonne for Lincoln and Union Parishes43(Lincoln, Union)44Payable from General Obligation Bonds45

Priority 2 $ 250,00046

ENROLLEDHB NO. 2

Page 180 of 202

50/NTQ EAST FELICIANA EMERGENCY 1COMMUNICATIONS DISTRICT2

(1841) Emergency Communications Center, Planning 3and Construction4(East Feliciana)5Payable from General Obligation Bonds6

Priority 1 $ 470,0007

50/NTT HOMER MEMORIAL HOSPITAL8

(1270) Hospital Roof Repair 9(Claiborne)10Payable from General Obligation Bonds11

Priority 2 $ 420,00012

(1838) Upper Parking Lot Expansion, Planning and13Construction14(Claiborne)15Payable from General Obligation Bonds16

Priority 1 $ 110,00017

(1839) Digital Mammography Machine, Acquisition 18and Installation19(Claiborne)20Payable from General Obligation Bonds21

Priority 1 $ 225,00022

(1840) Bone Density Machine, Acquisition and Installation23(Claiborne)24Payable from General Obligation Bonds25

Priority 1 $ 50,00026

50/NTU LAKE FOREST ELEMENTARY CHARTER SCHOOL27

(1223) Lake Forest Elementary Charter School,28Planning and Construction29(Orleans)30Payable from General Obligation Bonds31

Priority 2 $ 50,00032Priority 5 $ 260,00033

Total $ 310,00034

The capital outlay budget request for this project was submitted after the November 1st35deadline, but it has been approved by the Joint Legislative Committee on Capital Outlay36pursuant to the provisions of R.S. 39:112. 37

50/NTV SEEKER SPRINGS MINISTRY38

(1071) Seeker Springs Renovation, 39Planning and Construction40(Ouachita)41Payable from General Obligation Bonds42

Priority 2 $ 160,00043

ENROLLEDHB NO. 2

Page 181 of 202

50/NTY NEW ORLEANS JAZZ ORCHESTRA1

(1192) The New Orleans Jazz Market: A Home for the New2Orleans Jazz Orchestra at 1436 Oretha Castle Haley, 3Real Estate, Planning, Construction, Miscellaneous,4and Equipment5(Orleans)6Payable from General Obligation Bonds7

Priority 1 $ 1,110,0008Priority 2 $ 1,000,0009

Total $ 2,110,00010

50/NU4 RED RIVER REVEL ARTS FESTIVAL11

(1837) Covered Pavilion #2 for Shreveport Festival Plaza,12Planning and Construction13(Caddo)14Payable from General Obligation Bonds15

Priority 5 $ 50,00016

50/NUE EAST ST. TAMMANY CHAMBER OF COMMERCE17

(1298) East St. Tammany Chamber of Commerce 18Remodeling of Historic Building in Support 19of and Promotion of Economic Development20(St. Tammany)21Payable from General Obligation Bonds22

Priority 2 $ 150,00023

50/NUJ HAMMOND AREA RECREATION DISTRICT 124

(733) Parking Lot for Hammond Area Recreation 25District No. 1, Planning and Construction26(Tangipahoa)27Payable from General Obligation Bonds28

Priority 2 $ 250,00029Priority 5 $ 490,00030

Total $ 740,00031

50/NUL IBERIA WATERWORKS DISTRICT NO. 432

(779) Water System Improvements for Water Works33District No. 4, Planning and Construction34(Iberia)35Payable from General Obligation Bonds36

Priority 2 $ 50,00037

50/NUM UNIVERSITY HOSPITAL AND CLINICS38

(948) Renovations to University Hospital and Clinics,39Planning and Construction40(Lafayette)41Payable from General Obligation Bonds42

Priority 2 $ 605,00043Priority 5 $ 6,650,00044

Total $ 7,255,00045

ENROLLEDHB NO. 2

Page 182 of 202

(1128) Construction of Clinic and Medical Skills Lab 1Facilities at University Hospital and Clinics, 2Planning and Construction3(Lafayette)4Payable from General Obligation Bonds5

Priority 2 $ 605,0006Priority 5 $ 6,650,0007

Total $ 7,255,0008

50/NUN BELLE CHASSE YMCA9

(1134) Belle Chasse YMCA Phase II, Planning10and Construction11(Plaquemines)12Payable from General Obligation Bonds13

Priority 5 $ 700,00014

50/NUO HOUSTON RIVER WATER WORKS DISTRICT 1115

(638) Elevated Water Tank and Associated Piping, 16Planning and Construction17(Calcasieu)18Payable from General Obligation Bonds19

Priority 2 $ 600,00020Priority 5 $ 840,00021

Total $ 1,440,00022

50/NUR 9TH WARD FIELD OF DREAMS23

(609) 9th Ward Field of Dreams Football and 24Track Stadium Improvements, Planning 25and Construction26(Orleans)27Payable from General Obligation Bonds28

Priority 2 $ 200,00029Priority 5 $ 1,415,00030

Total $ 1,615,00031

50/NUV MONROE DOWNTOWN ECONOMIC 32DEVELOPMENT DISTRICT33

(1133) Monroe Riverwalk, Planning and Construction34(Ouachita)35Payable from General Obligation Bonds36

Priority 2 $ 475,00037

50/NUW TERREBONNE PARISH RECREATION 38DISTRICT #1139

(326) Mechanicville Gym - Multi-Purpose Building, 40Planning and Construction41(Terrebonne)42Payable from General Obligation Bonds43

Priority 2 $ 725,00044

50/NUY WEST STERLINGTON WATER SYSTEM45

(1193) Water Treatment System Renovation and46Improvements, Planning and Construction47(Union)48Payable from General Obligation Bonds49

Priority 2 $ 315,00050

ENROLLEDHB NO. 2

Page 183 of 202

50/NUZ COTTON COUNTRY PLAYERS, INC.1

(777) The Rose Theatre Upgrade Project, 2Planning and Construction3(Morehouse)4Payable from General Obligation Bonds5

Priority 2 $ 40,0006

50/NV5 SOUTHWEST LOUISIANA CENTER HEALTH 7SERVICES8

(1829) SWLA Center for Health Services - 9Healing Center, Planning and Construction10(Calcasieu)11Payable from General Obligation Bonds12

Priority 1 $ 335,00013

50/NV6 EAST CARROLL PARISH HOSPITAL14

(1835) East Carroll Parish Hospital Capital Improvement,15Emergency Repairs, Planning and Construction16(East Carroll)17Payable from General Obligation Bonds18

Priority 1 $ 625,00019

50/NV9 ALEXANDRIA CENTRAL ECONOMIC 20DEVELOPMENT DISTRICT21

(1963) Alexandria Riverfront Development, Phase 1,22Technical Planning and Construction ($250,000 23Local Match)24(Rapides)25Payable from General Obligation Bonds26

Priority 5 $ 170,00027

50/NVD DEVELOPMENT INSTITUTE FOR RURAL AND 28URBAN EXCELLENCE29

(1251) Renovation of Existing Building for Educational 30and Health Care Services31(Grant)32Payable from General Obligation Bonds33

Priority 2 $ 75,00034Priority 5 $ 825,00035

Total $ 900,00036

50/NVG DEEP WATER GULF TRANSFER TERMINAL 37AUTHORITY38

(1346) Deep Water Terminal Transfer Engineering Fees39(Plaquemines)40Payable from General Obligation Bonds41

Priority 2 $ 100,00042

50/NVL SOUTHEAST COMMUNITY HEALTH43

(2065) New Health Center in Baker, Planning and Construction44(East Baton Rouge)45Payable from General Obligation Bonds46

Priority 2 $ 100,00047

ENROLLEDHB NO. 2

Page 184 of 202

50/NVN UNION GROVE WATER SYSTEM, INC.1

(1971) Union Grove Water System2(Webster)3Payable from General Obligation Bonds4

Priority 5 $ 15,0005

50/NVO WIDOW'S SON LODGE #106

(2154) Widow's Son Lodge #10, Prince Hall Masonic 7Lodge Building Acquisition and Renovation8(Assumption)9Payable from General Obligation Bonds10

Priority 2 $ 100,00011

Pending approval of a capital outlay budget request pursuant to the provisions of R.S.1239:112.13

50/NVP MT. MORIAH MASONIC LODGE #1714

(2148) Restoration and Renovation of Historic Building15Damaged by Hurricane Gustav16(Iberville)17Payable from General Obligation Bonds18

Priority 2 $ 100,00019

Pending approval of a capital outlay budget request pursuant to the provisions of R.S. 39:11220

50/NW1 UNION PARISH LAW ENFORCEMENT DISTRICT21

(1834) New Law Enforcement/Services/Training/ Emergency22Shelter Complex, Planning and Construction ($500,00023Local In-Kind Match, $1,100,000 Federal Match)24(Union)25Payable from General Obligation Bonds26

Priority 1 $ 295,00027

50/NW9 RED RIVER FILM SOCIETY28

(1833) The Robinson Film Center (Formerly known as Red29River Art Film Theater), Planning and Construction30(Caddo)31Payable from General Obligation Bonds32

Priority 5 $ 510,00033

50/NX9 PROGRESS 63, INC.34

(1832) Progress 63 Center Providing Senior Center Services,35Veteran's Services, and Tutoring Services, Building 36Acquisition, Planning and Construction37(East Baton Rouge)38Payable from General Obligation Bonds39

Priority 5 $ 85,00040

50/N BLESSED TRINITY ROMAN CATHOLIC CHURCH41

(760) Community Art and Wellness Center in New Orleans,42Planning, Construction and Equipment43(Orleans)44Payable from General Obligation Bonds45

Priority 1 $ 380,00046Priority 2 $ 100,00047

Total $ 480,00048

ENROLLEDHB NO. 2

Page 185 of 202

50/S10 CALCASIEU PARISH SCHOOL BOARD1

(519) Renovations To Lake Charles Boston Stadium, 2Planning and Construction3(Calcasieu)4Payable from General Obligation Bonds5

Priority 1 $ 400,0006Priority 2 $ 400,0007

Total $ 800,0008

50/S18 EAST CARROLL SCHOOL BOARD9

(2068) Administration Building, Acquisition and 10Renovation, Planning and Construction11(East Carroll)12Payable from General Obligation Bonds13

Priority 2 $ 2,200,00014

50/S26 JEFFERSON PARISH SCHOOL BOARD15

(1831) Multipurpose Fine Arts Building Renovation16(Jefferson)17Payable from General Obligation Bonds18

Priority 1 $ 100,00019

50/S39 POINTE COUPEE PARISH SCHOOL BOARD20

(1830) Pointe Coupee Parish School Board Central Office21Relocation, Renovation and Rebuilding Due to 22Flooding Caused By Hurricane Gustav23(Pointe Coupee)24Payable from General Obligation Bonds25

Priority 1 $ 75,00026Priority 5 $ 3,225,00027

Total $ 3,300,00028

50/S42 RICHLAND PARISH SCHOOL BOARD29

(874) Archibald Alternative Center Improvements 30(Richland)31Payable from General Obligation Bonds32

Priority 5 $ 25,00033

50/S63 WEST FELICIANA PARISH SCHOOL BOARD34

(231) Julius Freyhan Cultural/Conference Center, 35Planning and Construction36(West Feliciana)37Payable from General Obligation Bonds38

Priority 1 $ 1,750,00039Priority 5 $ 1,500,00040

Total $ 3,250,00041

Section 2. The expenditure of funds appropriated in this Act, except appropriations42

made to non-profit economic development corporations, shall be in conformity to all existing43

statutes relative to public bidding, contractual review, and R.S. 39:101 through 128 and any44

other statutes affecting the capital outlay program for state government, state institutions,45

ENROLLEDHB NO. 2

Page 186 of 202

and political entities. No contract shall be awarded for any project prior to the granting of1

a line of credit or the sale of bonds by the State Bond Commission, determination by the2

State Treasurer that cash funding is available in the Comprehensive Capital Outlay Escrow3

Account for the project, or delivery of revenue bonds whose issuance is authorized in4

Section 1 of this Act. 5

Section 3. Payment for projects specified in this Act must be made by warrant6

submitted to the Division of Administration, Department of Transportation and7

Development, the State Treasurer or other administering agency as provided in Section 8,8

whichever is appropriate, only to the extent of funds required for immediate payment.9

Copies of invoices or other supporting documentation shall be submitted with warrants. In10

the event that any equipment included in this Act, is procured pursuant to the provisions of11

the State Lease-Purchase Act, R.S. 39:1761 et seq., the amounts included in this Act for each12

such piece of equipment shall not be appropriated. The provisions of R.S. 39:1771 which13

require equipment to be leased under the State Lease-Purchase Act to be included in the14

executive budget and approved by the Legislature through inclusion in the General15

Appropriation Act shall be considered waived upon the inclusion of such equipment in this16

Act. Projects contained in this Act may, at the direction of the Division of Administration17

and with the approval of the State Bond Commission, alternatively be funded through18

financing programs heretofore or hereafter provided by a public trust and public corporation19

duly organized pursuant to R.S. 9:2341 et seq., having for its beneficiary the State and the20

Louisiana Local Government Environmental Facilities and Community Development21

Authority, pursuant to R.S. 33:4548.1 et seq. 22

Section 4. If at any time during the Fiscal Year 2014-2015, the Governor should23

find, or the Joint Legislative Committee on the Budget or the Commissioner of24

Administration should report to the Governor, that the receipts of the treasury are falling25

short or appear likely to fall short of the revenue estimates for the fiscal year and that a cash26

deficit is likely to be incurred, the Governor shall take such steps as deemed necessary to27

prevent the occurrence of a cash deficit. In the event that a capital outlay project funded in28

this Act falls under an agency which is abolished or for which funds are not appropriated in29

the 2014-2015 General Appropriation Act, then the funds appropriated in this Act for such30

capital outlay projects shall not be expended unless deemed necessary by the Governor to31

ENROLLEDHB NO. 2

Page 187 of 202

protect life or property. In the event that legislation is enacted which transfers facilities or1

programs for which projects are funded in this Act, on behalf of one agency, institution,2

department, or management board to another agency, institution, department, or management3

board, then the projects in this Act shall be deemed transferred also.4

Section 5. All monies appropriated by this Act and any applicable funds of a prior5

capital outlay budget act adopted by the Legislature shall be deposited by the State Treasurer6

in the Comprehensive Capital Outlay Escrow Account, established by this Section, in the7

state treasury. In accordance with R.S. 36:764, no later than 60 days following the end of8

each quarter, the state treasurer shall report to the Joint Legislative Committee on the Budget9

and the Commissioner of Administration, all funds contained in the Miscellaneous Fund of10

the Comprehensive Capital Outlay Escrow Account. Notwithstanding any provisions11

contained herein or other law to the contrary, any original issue premium or accrued interest12

proceeds received pursuant to the sale of general obligation bonds shall remain on deposit13

to the credit of the Bond Security and Redemption Fund until such time as they may be14

utilized in accordance with U.S. Department of Treasury Regulations promulgated pursuant15

to the Internal Revenue Code of 1986. All such monies shall be administered according to16

the particular act pertaining to the fiscal year in which such monies were appropriated. If17

it is determined by the Director of the Office of Facility Planning and Control, Division of18

Administration, that the funds appropriated by this Act or any prior capital outlay budget act19

are not sufficient to complete the projects contained in any capital outlay budget act, through20

unavoidable deficiencies in appropriation, including administrative and legal requirements,21

the Commissioner of Administration, subject to approval of the Joint Legislative Committee22

on the Budget, may direct the use of interest earned from the investment of general23

obligation bond or note proceeds in the Comprehensive Capital Outlay Escrow Account, not24

to exceed an aggregate of five million dollars in any one fiscal year, for the purpose of25

completing the projects contained in any capital outlay budget act and such money shall be26

deemed appropriated in specific amounts necessary for such purpose. All appropriations in27

this Act which are made as additions to funds for previously authorized projects shall be28

included, for accounting purposes, in the account of said previously authorized projects. If29

it is determined by the Director of the Office of Facility Planning and Control, Division of30

Administration, that it is cost effective and practical to combine individual appropriations,31

ENROLLEDHB NO. 2

Page 188 of 202

the Commissioner of Administration, subject to the approval of the Joint Legislative1

Committee on the Budget, may direct that two or more appropriations or parts thereof may2

be combined into a single project for accounting and audit purposes. The Commissioner of3

Administration may direct that funding in the various statewide and/or multiple parish4

projects for improvements for state facilities may be transferred to any project, in this Act5

or any previous Capital Outlay Act, which require supplemental funding for improvements6

for state facilities which qualify for funding through the various statewide and/or multiple7

parish projects for improvements for state facilities. The Office of Facility Planning and8

Control, Division of Administration is authorized to receive settlements and vendor rebates9

not in excess of $50,000 unless approved by the Joint Legislative Committee on the Budget,10

and to add those receipts to the funding for projects in this Act or any previous Capital11

Outlay Act for which project funds are received. The Office of Facility Planning and12

Control, Division of Administration is authorized to receive insurance payments and are13

hereby authorized to immediately repair facilities that suffer insurance losses without those14

projects being included in the Act and shall report to the Joint Legislative Committee on the15

Budget any expenditures from insurance funds received pursuant to this section. A portion,16

as determined by the Commissioner of Administration and not to exceed one percent (1%),17

of the funding for projects which qualify for the Percent for Art Program, may be transferred18

from the qualifying project budgets, to the Department of Culture, Recreation and Tourism19

for costs of acquiring art and administering the program. For all Percent for Art Program20

projects in this or any previous capital outlay, up to ten percent (10%) of the aforementioned21

one percent (1%) may be used for the costs of administering the projects. 22

Section 6. Prior to March 1, 2015, the Commissioner of Administration shall submit23

to the Legislature a list of projects that are completed and the cash balances remaining in24

each project. 25

Section 7. The Commissioner of Administration, with the approval of the Joint26

Legislative Committee on the Budget, is authorized to supplement or substitute the27

appropriations specified in this or previous capital outlay acts with any federal or other funds28

which are or may become available and such funds shall be deemed appropriated in specific29

amounts necessary for the purposes of this Act. Any funds received by the State Bond30

Commission as a result of a prepayment of reimbursement contracts as authorized by law31

ENROLLEDHB NO. 2

Page 189 of 202

and the Policy and Procedure for Reimbursement Contracts of the Department of Treasury,1

Office of State Bond Commission, shall be deposited as set forth in such Policy and2

Procedure and shall be deemed available and appropriated in specific amounts necessary for3

the purposes of this Act pursuant to the procedure set forth in this section.4

Section 8. All of the funds herein appropriated, except for appropriations made to5

the Department of Military Affairs, the Legislature, the Louisiana Stadium and Exposition6

District, the Department of Economic Development, the Coastal Protection and Restoration7

Authority, the Board of Regents for the Library, Instructional and Scientific Equipment8

Acquisitions for Higher Education Institutions appropriation, the Division of Administration9

for Supplemental State Funds for Local Government Assistance Program, the Division of10

Administration for the Community Water Enrichment Program or the Department of11

Transportation and Development, shall be considered as having been appropriated directly12

to the Office of Facility Planning and Control, Division of Administration, and all projects13

herein authorized and funded shall be subject to the provisions of R.S. 39:101 through 128.14

All of the funds herein appropriated under the name of non-state entities shall be15

administered by the Office of Facility Planning and Control, Division of Administration,16

under cooperative endeavor agreements. All cooperative endeavor agreements for non-state17

entities shall be prepared by the Office of Facility Planning and Control and the18

Commissioner of Administration is hereby authorized and directed to effectuate any19

necessary transfer of funds from the Department of Justice to the Office of Facility Planning20

and Control in order to accomplish this purpose. However, all cooperative endeavor21

agreements between the Department of Transportation and Development and non-state22

entities entered into prior to the passage of this Act shall continue to be administered by the23

Department of Transportation and Development. Cooperative endeavor agreements entered24

into pursuant to this Act, and approved by the Commissioner of Administration or his25

designee, or the Secretary of the Department of Transportation and Development for projects26

appropriated to or administered by the Department of Transportation and Development, shall27

not be required to be submitted to the Division of Administration, Office of Contractual28

Review. For all projects in this or any previous Capital Outlay Act appropriated to the29

Office of Facility Planning and Control, Division of Administration, including those30

administered by cooperative endeavor agreements, up to six percent of each line-item may31

ENROLLEDHB NO. 2

Page 190 of 202

be used for costs of administering the projects. For all projects in this or any previous1

Capital Outlay Act appropriated to the Department of Transportation and Development, up2

to six percent of each line-item may be used for costs of administering the projects, or for3

field engineering/construction supervision. Line-item general obligation bond projects4

appropriated to the Department of Transportation and Development in this or any previous5

Capital Outlay Act shall be authorized to draw Transportation Trust Funds from the6

Highway Program appropriation, for supplemental funding on overruns in excess of the7

original estimated project cost as determined by the Department of Transportation and8

Development, provided however that said projects are in the state or federal highway system9

and in the priority program, and the overrun is less than $50,000. Any such overrun of10

$50,000 or more must be approved by the Joint Legislative Committee on the Budget.11

Furthermore, all ports, levee districts and other non-state entities must have a fully executed12

cooperative endeavor agreement, from the Office of Facility Planning and Control,13

Department of Transportation and Development, or the State Treasurer, whichever is14

appropriate, before entering into any contracts which obligate state funding and must follow15

all laws pertaining to public bidding. If a port, levee district or other non-state entity enters16

into a contract prior to receipt of funding, or prior to execution of a cooperative endeavor17

agreement, then payments under such contracts are prohibited from capital outlay18

appropriations, and are the sole responsibility of the port, levee district, or other non-state19

entity. Notwithstanding the provisions of this Section or any other capital outlay act,20

contracts may be entered into for the Atchafalaya Basin Protection and Enhancement21

Kemper Williams project in St. Mary Parish prior to a cooperative endeavor agreement being22

entered into with the state. Notwithstanding anything contained in this or any other capital23

outlay act, contracts may be entered into for the Natchitoches Industrial Park South project24

prior to receipt of funding and prior to execution of a cooperative endeavor agreement.25

Notwithstanding anything contained in this Act to the contrary or any other provision of law,26

contracts may be entered into for the Livingston Parish Twenty-First District Complex prior27

to receipt of funding and prior to execution of the cooperative endeavor agreement.28

Notwithstanding R.S. 39:112(A), subject to all other applicable statutes, the Department of29

Transportation and Development may execute a contractual instrument for the I-12 O’Neal30

Lane to Walker Widening project prior to receipt of a line of credit. Notwithstanding the31

ENROLLEDHB NO. 2

Page 191 of 202

provisions of R.S. 39:112(E)(2), the project for Independence, Independence Area1

Community Pavilion, Planning and Construction, shall be exempt from all local match2

requirements. Notwithstanding anything contained in this Act to the contrary or any other3

provision of law, the scope of the appropriations made in this or any other Capital Outlay4

Act for the St. Mary Parish Plantation Pump Station Replacement project shall be deemed5

to include repair, equipment, rehabilitation and infrastructure improvements at the existing6

Plantation Pump Station. Notwithstanding anything contained in this Act to the contrary or7

any other provision of law, the scope of the appropriations made in this or any other Capital8

Outlay Act for the Louisiana 4-H Foundation, Youth Education Development Camp Windy9

Wood project, shall be deemed to include planning, construction, and acquisition.10

Notwithstanding any other provision of this Act or any other provision of law to the11

contrary, the scope of the appropriation made for the Foundation for Science and Math12

Education shall be deemed to include land acquisition. Notwithstanding anything contained13

in this Act to the contrary or any other provision of law, the scope of the appropriations14

made in this or any other Capital Outlay Act for the Youngsville Parkway Road project shall15

be deemed to include waterline improvements and roadway lighting. Notwithstanding16

anything contained in this or any other Capital Outlay Act for the University Medical Center17

in New Orleans project, this appropriation and any other appropriation for this project in18

previous Acts of the Legislature shall be available for and used to pay and satisfy the19

judgments related to the expropriation of property related to said project in accordance with20

Article I, Section 4 of the Louisiana Constitution of 1974 in the suit entitled "Board of21

Supervisors of Louisiana State University and Agricultural and Mechanical College v. 173222

Canal Street, LLC, et al." bearing Number 10-10488, Section "8", Division "N", on the23

docket of Civil District Court, parish of Orleans, state of Louisiana and No. 2012-CA-137024

on the docket of the Fourth Circuit Court of Appeal, state of Louisiana. Notwithstanding25

anything contained in this Act to the contrary or any other provision of law, the scope of the26

appropriations made in this or any other Capital Outlay Act for the New Mental Health27

Clinic for New Orleans Behavior, Social, and Medical Support Detox Clinic project for the28

Metropolitan Human Service District shall be deemed to include the expansion and29

renovation of the existing facility. Notwithstanding anything contained in this Act to the30

contrary or any other provision of law, the scope of the appropriations made in this or any31

ENROLLEDHB NO. 2

Page 192 of 202

other Capital Outlay Act for the New Mental Health Center for Desire/Florida Mental Health1

Clinic project for the Metropolitan Human Service District shall be deemed to include the2

purchase, construction, or renovation of a new facility in New Orleans East.3

Notwithstanding anything contained in this Act to the contrary, or any other provision of4

law, the scope of the appropriations made in this or any other Capital Outlay Act for the City5

of New Orleans, Eastern New Orleans Hospital and Medical Office Building, Real Estate6

Acquisition, Planning, Design, Construction, Renovation and Equipment, project, the City7

of New Orleans may make such capital outlay funds available to the Parish Hospital Service8

District of the Parish of Orleans District "A" in furtherance of the District's planning, design,9

acquisition, development, renovation, construction, equipment and operation of a hospital10

and medical office building in Eastern New Orleans. Notwithstanding anything contained11

herein, or in any cooperative endeavor agreement between the Office of Facility Planning12

and Control and the City of New Orleans or the Hospital Service District to the contrary, the13

Hospital Service District may mortgage or otherwise encumber any and all land, real14

property, including buildings and equipment, and appurtenances acquired, in whole or part,15

with state capital outlay funds provided that bond counsel to the state opines that such16

mortgage shall not affect the tax-exempt status of the bonds to be issued by the state for the17

project. Notwithstanding anything in this Act to the contrary, contracts may be entered into18

for the City of New Orleans, Eastern New Orleans Hospital and Medical Office Building,19

Real Estate Acquisition, Planning, Design, Construction, Renovation and Equipment project20

prior to receipt of funding and prior to execution of the cooperative endeavor agreement.21

Notwithstanding anything contained in this Act to the contrary, or any other provision of22

law, or the cooperative endeavor agreement between the Ouachita Parish Police Jury and the23

Office of Facility Planning and Control, or the capital outlay request submitted for the24

Ouachita Parish, Extension of I-20 Frontage Road East, including a Bridge across Bennett25

Bayou, Acquisitions, Planning and Construction project, contracts may be entered into prior26

to a cooperative endeavor agreement being entered into with the Office of Facility Planning27

and Control, contracts may be entered into prior to approval of the plans, specifications or28

contracts by Facility Planning and Control, and funds for the appropriation made in this or29

any other Capital Outlay Act for this project may be made available to the Ouachita Parish30

Police Jury, the City of Monroe, or the City of Monroe's I-20 Economic Development31

ENROLLEDHB NO. 2

Page 193 of 202

Corporation in furtherance of the project. Notwithstanding anything contained in this Act1

to the contrary or any other provision of law, the scope of the appropriations made in this2

or any other Capital Outlay Act for the Vermilion Parish Pecan Island Waterworks District3

No. 3 Water System Improvements project shall be deemed to include automatic read meters4

for the entire system. Notwithstanding anything contained in this Act to the contrary or any5

other provision of law, the scope of the appropriations made in this or any other Capital6

Outlay Act for the Louisiana Technical College New Construction or Renovations to7

Morgan Smith Campus, Planning and Construction project shall be used for new8

construction or renovations to Morgan Smith Campus. Notwithstanding anything contained9

in this Act to the contrary or any other provision of law, the scope of the appropriations10

made in this or any other Capital Outlay Act for the Jefferson Parish Bonnabel Canal11

Rehabilitation and Bank Stabilization (Veterans Boulevard to West Esplanade), Planning12

and Construction project shall be deemed to include steel sheet pile bulkhead, and/or bank13

excavation and reshaping, bridge replacement, property acquisition, demolition and14

improvements needed to stabilize the canal bank along the Bonnabel Drainage Canal in15

order to address canal bank failures between Veterans Boulevard and West Esplanade16

Avenue. Notwithstanding anything contained in this Act to the contrary or any other17

provision of law, the scope of the appropriations made in this or any other Capital Outlay18

Act for the City of Broussard Rehabilitate LA Hwy 182 from US 90 to LA Hwy 89,19

Planning and Construction project shall be deemed to include deleting four thousand two20

hundred feet of two-lane rehabilitation in downtown Broussard and widening from two lanes21

to three lanes, the section of roadway from the western terminus of the City of Broussard22

Three-lane LA Hwy 182 in the city of Broussard, Planning and Construction ($750,00023

Local Match) project in downtown Broussard to South Broussard Road. Notwithstanding24

anything contained in this Act to the contrary or any other provision of law, the scope of the25

appropriations made in this or any other Capital Outlay Act for the St. Martin Parish I-1026

Frontage Road Project shall be deemed to include the planning, designing, and construction27

of public infrastructure improvements, including but not limited to roadways, water, sewer,28

lighting, and drainage improvements, adjacent to said frontage roads for the purposes of29

economic development and job creation as certified and audited by the St. Martin Economic30

Development Authority. Notwithstanding anything contained in this or any other capital31

ENROLLEDHB NO. 2

Page 194 of 202

outlay Act or the provisions of R.S. 39:112(E), the New Pavilion at Carl Williams Park,1

Planning and Construction and the Renovations at Veterans' Park, including the Installation2

of Lighting, Planning and Construction, projects for Breaux Bridge shall be exempt from all3

local match requirements. Notwithstanding anything contained in this or any other capital4

outlay Act or the provisions of R.S. 39:112(E), the Renovation of West End Park, including5

the Acquisition of New Playground Equipment, Planning and Construction, project for New6

Iberia shall be exempt from all local match requirements. Notwithstanding anything7

contained in this or any other capital outlay Act or the provisions of R.S. 39:112(E), the8

Recreation II, Planning and Construction, project for St. Martinville shall be exempt from9

all local match requirements. Notwithstanding anything contained in this Act to the contrary10

or any other provision of law, the scope of the appropriations made in this or any other11

Capital Outlay Act for the New Orleans Norman Playground Basketball Gym, Planning and12

Construction project shall be deemed to include park enhancements for a walking track,13

basketball, football and baseball fields and a concession stand. Notwithstanding anything14

contained in this Act to the contrary or any other provision of law, the Parish Road15

Improvements Project for Franklin Parish is exempt from the contract limit set forth in R.S.16

38:2212. Notwithstanding anything contained in this act to the contrary or any other Act or17

provision of law, the appropriations made for the Executive Department for facilities which18

promote economic development included in the Repair, Restoration, and Replacement for19

Hurricanes Katrina and Rita project, and the Department of Economic Development projects20

are for public purposes pursuant to the provisions of Article VII, Section 14 of the21

Constitution of Louisiana primarily for economic development, including the generation of22

tax revenues, creation of jobs, promotion of tourism, and creation of facilities for charitable,23

cultural, artistic, educational, social, civic, research, service, economic development24

activities, or provide facilities for professional golf events, pursuant to the terms of25

cooperative endeavor agreements, including leases and all expenditures of these26

appropriations and may be exempted, by the Commissioner of Administration, from all27

statutes relative to public bidding, contractual review and the provisions of R.S.28

33:9029.2(D) and in lieu thereof be allowed to use alternative competitive contracting29

arrangements where the appropriate administering entity submits documentation to the30

Commissioner of Administration substantiating that it is in the best interest of the citizens31

ENROLLEDHB NO. 2

Page 195 of 202

of the state, due to economic and/or operational benefits, and the necessity to complete the1

projects in a timely manner; and, the appropriate administering entity shall have the2

authority to directly appoint the design professional from a list of a minimum of three design3

firms or joint ventures with the appropriate specialized facility design experience submitted4

to and acceptable to the Commissioner of Administration and shall be exempt from other5

state requirements for selection of designers, and may include expenditures for computers,6

fixtures, furniture, and other equipment as such is deemed to be capital outlay in nature, and7

unless the Commissioner of Administration is advised by bond counsel to the State that such8

may violate federal tax law, may be used to reimburse any expenditure made prior to the9

granting of a line of credit or the sale of bonds by the State Bond Commission, determination10

by the State Treasurer that cash funding has been deposited in the Comprehensive Capital11

Outlay Escrow Account for the project or the execution of a cooperative agreement from the12

Office of Facility Planning and Control, and may be used to acquire land or real property,13

the title to which is held in the name of an entity exempt from taxation under the provisions14

of 26 U.S.C. 501(c)(3). Notwithstanding anything contained in this Act to the contrary or15

any other provision of law, all of the funds herein appropriated to the Department of16

Economic Development in connection with the Capital Improvements Project to Meet17

Economic Development Commitments for which the Department of Economic Development18

utilizes a cooperative endeavor agreement to further economic development as permitted19

under Article VII, Section 14 of the Louisiana Constitution, including the generation of tax20

revenues and creation of jobs, shall be considered as having been appropriated to the21

Department of Economic Development, may be used to reimburse any expenditure made22

prior to the granting of a line of credit and made prior to the execution of a cooperative23

endeavor agreement and shall be administered solely by the Department of Economic24

Development pursuant to, in compliance with, and on the terms contained in such25

cooperative endeavor agreements. Notwithstanding any provision of law to the contrary, the26

Commissioner of Administration is hereby authorized to take such actions as are necessary,27

including using such funds as may be available including those appropriated and available28

under this Act for professional sports facilities through the Louisiana Stadium and29

Exposition District and that are otherwise available, executing on behalf of the State such30

documents as are necessary in order to terminate the ground lease between the State and the31

ENROLLEDHB NO. 2

Page 196 of 202

PGA and thereby acquiring all leasehold improvements for the State, extending the1

management agreement between the State and the PGA, and extending the sponsorship and2

presence of the Zurich Classic in the Greater New Orleans area. Notwithstanding anything3

contained in this or any other capital outlay act, contracts may be entered into for the Tulane4

National Primate Research Center prior to receipt of funding and prior to execution of a5

cooperative endeavor agreement and the project is exempted from all statutes relative to6

public bidding and contractual review and in lieu thereof the appropriate administering entity7

shall have the authority to directly appoint design professionals and construction managers8

in accordance with National Institute of Health Design and Construction Guidelines.9

Notwithstanding anything contained in this or any other capital outlay act, contracts may be10

entered into for the Port of South Louisiana, Installation of New Dock/Building/Equipment11

and Land Acquisition; Dock, Planning and Construction; Globalplex Rail Siding; Globalplex12

Terminal Building #71 Upgrade, Planning and Construction; Globalplex Dock Access13

Bridge and Equipment Replacement/Repair; Warehouse Planning and Construction;14

Globalplex Intermodal Access Road and Railsiding prior to receipt of funding and prior to15

execution of a cooperative endeavor agreement. Notwithstanding anything in this Act, any16

previous capital outlay act, or other provision of law to the contrary, the scope of the17

appropriation for the Port of South Louisiana Globalplex Terminal Building #71 Upgrade18

project shall be deemed to also include similar upgrades for other Globalplex Terminal19

Buildings. Notwithstanding anything in this Act, any previous capital outlay act, or other20

provision of law to the contrary, monies appropriated herein for the Port of South Louisiana21

Globalplex Terminal Building #71 and Other Globalplex Terminal Building Upgrades,22

Planning and Construction may be expended for design fees related to the conveyor system23

and ancillary equipment that exceed the customary ten percent limitation on design fee costs.24

Notwithstanding anything in this Act to the contrary or any other provision of law, contracts25

may be entered into for the Jefferson Parish Performing Arts project prior to receipt of26

funding and prior to the execution of a cooperative endeavor agreement, and the State is27

authorized to financially participate in change orders approved by the Parish.28

Notwithstanding anything in this Act to the contrary or any other provision of law, contracts29

may be entered into for the Greater Baton Rouge Port Commission Inland River Marine30

Terminal Dock and Access Roadway Construction Project, Planning and Construction31

ENROLLEDHB NO. 2

Page 197 of 202

Project prior to receipt of funding and prior to the execution of a cooperative endeavor1

agreement. Notwithstanding anything contained in this act to the contrary or any other2

provision of law, the appropriations made for the Louisiana Stadium and Exposition District3

shall be appropriated directly to the Louisiana Stadium and Exposition District, and are4

public purposes pursuant to the provisions of Article VII, Section 14 of the Constitution of5

Louisiana primarily for economic development, including the generation of tax revenue,6

creation of jobs, and the generation of tourism, and may be used to reimburse any7

expenditure made prior to the granting of a line of credit or the sale of bonds by the State8

Bond Commission, determination by the State Treasurer that cash funding has been9

deposited in the Comprehensive Capital Outlay Escrow Account for the project. The10

Louisiana Stadium and Exposition District may apply up to $10,000,000 to reimburse the11

New Orleans Hornets NBA, LLC for costs incurred in constructing a new training facility12

as contemplated by the Amended and Restated Arena Use Agreement dated July, 1 2013;13

but, otherwise, contracts for projects funded through this appropriation shall be awarded14

utilizing the public bid and contractual review process set forth in Chapter 10 of Title 38 and15

Chapter 16 of Title 39 of the Louisiana Revised Statutes of 1950, except with respect to time16

requirements, or, in order to encourage competition for the projects funded through this17

appropriation and to complete the projects in a timely manner, the Louisiana Stadium and18

Exposition District shall have the authority to select a general contractor through an RFP19

process whereby general contractors will bid general conditions and contractor's fee based20

on the direct construction budget. The alternative time requirements shall be approved by21

the Commissioner of Administration before the awarding of any such contracts. The22

Louisiana Stadium and Exposition District shall have the authority to directly appoint the23

design professional from a list of a minimum of three architectural firms or joint ventures24

with professional sports facility design experience acceptable to the Commissioner of25

Administration and shall be exempt from other state requirements for selection of designers.26

The design professional fee shall be in accordance with state guidelines administered by the27

Office of Facility Planning and Control, Division of Administration. Eligible expenses for28

Economic Development Award Program funds may include documented project expenses29

beginning on the date of LEDC Board approval of the project and may be reimbursed upon30

execution of the cooperative endeavor agreement for the project. The new University31

ENROLLEDHB NO. 2

Page 198 of 202

Medical Center in New Orleans project in Orleans Parish shall be exempt from the state's1

requirements for selection of designers and the Commissioner of Administration shall have2

the authority to approve a design professional selection process. The design professional fee3

shall be in accordance with state guidelines administered by the Office of Facility Planning4

and Control, Division of Administration. The Division of Administration, Office of Facility5

Planning and Control, with approval of the Commissioner of Administration and the Joint6

Legislative Committee on the Budget, is authorized to use alternative delivery strategies in7

implementing the University Medical Center in New Orleans project, hurricane damage8

repairs to Southern University at New Orleans, Hazardous Material Abatement Projects, the9

City Park Golf Complex Improvements project, the Oakcrest Sprinkler System project, the10

Sprinkler Systems for Residences, Porches and Walkways project, the Health/Human11

Performance Education Complex, and the Patrick Taylor Hall Renovation and Expansion12

project. Due to the State's current investment in TPC Louisiana and the financial support13

it provides to the PGA TOUR event currently played at said facility, the funding of the City14

Park Golf Complex Improvements project described above is conditioned upon said PGA15

TOUR event not being played at New Orleans City Park Golf Complex without the prior16

agreement of the Commissioner of Administration and the Secretary of the Department of17

Economic Development. Notwithstanding the foregoing, the City Park Golf Complex may18

host any other golf tournament or event, including but not limited to any other19

PGA-affiliated or sponsored tournament or event. For all projects administered by the20

Office of Facility Planning and Control and payable from proceeds of self-generated21

revenues, funds shall be remitted to the Office of Facility Planning and Control for deposit22

in the state treasury at such time as may be deemed necessary by the Office of Facility23

Planning and Control in order to cover the amount of contracts or other project expenses.24

The State Treasurer shall refund to the appropriate source any surplus self-generated funds,25

advanced insurance funds received by the Office of Facility Planning and Control as26

Interagency Transfer from Office of Risk Management associated with hurricane damage27

recovery, and interest earned on these funds, provided the Treasurer's Office is notified,28

when these funds are deposited in the state treasury, that the user agency or Office of Risk29

Management intends to request a refund of this interest. Any revenue bonds appropriated30

in Section 1 of this Act shall not be secured by the full faith and credit of the state.31

ENROLLEDHB NO. 2

Page 199 of 202

Notwithstanding anything in this Act to the contrary or any other provision of law, contracts1

may be entered into for the Mississippi River Levee Raising, Arkansas to Old River project2

prior to receipt of funding, and the State is authorized to financially participate in obligations3

created by such contracts. Notwithstanding anything in this Act to the contrary or any other4

provisions of law, contracts may be entered into for the Ernest N. Morial New Orleans5

Exhibition Hall Authority, Hall A Renovation, Planning and Construction project prior to6

receipt of funding and prior to execution of the cooperative endeavor agreement.7

Notwithstanding anything in this Act to the contrary or any other provision of law, contracts8

may be entered into for the Outpatient Clinics in Rapides Parish, Planning and Construction9

project for the Division of Administration prior to the execution of a cooperative endeavor10

agreement. Notwithstanding anything in this Act to the contrary or any other provision of11

law, contracts may be entered into for the Natural Gas Distribution System Rehabilitation12

and Improvement project for the Town of St. Francisville prior to the execution of a13

cooperative endeavor agreement. Notwithstanding any other provision of this Act or any14

other provision of law to the contrary, funds appropriated for the Economic Development15

Award Program project for the Office of Business Development are to be used solely for16

capital and infrastructure improvements subject to verification by the Division of17

Administration, Office of Facility Planning and Control. Notwithstanding any other18

provision of this Act or any other provision of law to the contrary, all of the funds herein19

appropriated to the Department of Economic Development in connection with projects or20

programs for which the Department of Economic Development utilizes a cooperative21

endeavor agreement to further economic development as permitted under Article VII,22

Section 14 of the Louisiana Constitution, including the generation of tax revenues and23

creation of jobs, shall be considered as having been appropriated to the Department of24

Economic Development, may be used to reimburse any expenditure made prior to the25

granting of a line of credit and made prior to the execution of a cooperative endeavor26

agreement and shall be administered solely by the Department of Economic Development27

pursuant to, in compliance with, and on the terms contained in such cooperative endeavor28

agreements without compliance with any other law, including, but not limited to, the29

provisions of R.S. 39:101 through 128. Additionally, all expenditures of these appropriations30

ENROLLEDHB NO. 2

Page 200 of 202

may be exempted by the Commissioner of Administration, from all statutes relative to public1

bidding, contractual review and the provisions of R.S. 33:9029.2(D).2

Section 9. Notwithstanding any provisions contained herein or any other law to the3

contrary, the provisions of Chapter 16 of Subtitle III of Title 39 of the Louisiana Revised4

Statutes of 1950 as amended, shall not apply to architectural and engineering contracts,5

administered by the Office of Facility Planning and Control, Division of Administration6

pursuant to this or any other capital outlay act.7

Section 10. All funds appropriated herein to the Office of Facility Planning and8

Control, Division of Administration, on behalf of non-state entities, and administered by9

cooperative endeavor agreements pursuant to this Act shall be expended within two (2) years10

from the date of the issuance of the bonds. The Office of Facility Planning and Control,11

Division of Administration, agrees that it will notify the non-state entity of the date the12

bonds are issued within three (3) months from the issuance thereof. The non-state entity13

understands and agrees that if the funds appropriated herein and administered under14

cooperative endeavor agreements pursuant to this Act are not totally expended within two15

(2) years from the issuance of the bonds, the Office of Facility Planning and Control,16

Division of Administration, can close the project and recommend that the Legislature17

reallocate any unexpended proceeds to other projects.18

Section 11. Notwithstanding any provisions contained herein or law to the contrary,19

the proceeds of revenue bonds to be utilized to fund certain projects authorized in Section20

1 hereof may, in accordance with Article VII, Section 9 of the Louisiana Constitution of21

1974, be deposited in special accounts held outside the state treasury in accordance with the22

provisions of any bond resolution, indenture, reimbursement contract, or other bond or23

financing covenant which provides for the pledge of such funds in connection with the24

issuance of revenue bonds. For all projects administered by the Office of Facility Planning25

and Control, Division of Administration, authorized in Section 1 hereof which are payable26

from the proceeds of revenue bonds, only the Office of Facility Planning and Control,27

Division of Administration, will be authorized to requisition funds from the special accounts28

described immediately above, at such time or times as may be deemed necessary by the29

Office of Facility Planning and Control, Division of Administration, in order to cover30

contract amounts or other project expenses. 31

ENROLLEDHB NO. 2

Page 201 of 202

Section 12. The Governor shall have the power to veto any line-item in this Act. 1

Section 13. Except as otherwise provided herein, no funds shall be expended on any2

highway projects on highways within the state highway system as established in R.S. 48:1913

under the jurisdiction of the Department of Transportation and Development unless and until4

such project is in the Highway Program, R.S. 48:228 through 232, approved by the Joint5

Legislative Committee on Transportation, Highways and Public Works. Pursuant to R.S.6

49:214.6.2(B), no integrated coastal protection construction project shall be undertaken with7

funds included in this bill except those included in an annual plan finally approved by the8

legislature in accordance with the provisions of R.S. 49:214.5.3.9

Section 14. The word "statewide" used in place of the specific parish designation for10

projects contained in this Act indicates that the project or program is applicable to all sixty11

four parishes in the state. The description of any project in this Act shall be deemed to12

include planning, design, master planning, studies, permits, surveys, testing, construction,13

land and/or building/improvement acquisition, reconstruction, renovation, repair, right of14

way and utilities, site and other improvements, miscellaneous/contingencies, lease hold15

improvements ultimately owned by the State or a political subdivision of the State,16

equipment and other acquisitions, and any other component of the project if such are17

included or indicated in the capital outlay request for such projects required by R. S. 39:10118

subject to the provisions of Title 39 of the Louisiana Revised Statutes. For new construction19

or renovation projects, equipment or other acquisitions, which can reasonably be considered20

necessary for the facility to be functional, may be deemed to be included in the project, even21

if such equipment or other acquisitions are not included or indicated in the project name or22

the capital outlay request. When local or federal match is referenced in a project title, but23

only a portion of the state appropriation is granted a line of credit or otherwise funded, then24

the amount of local or federal match, required to be made available, may be prorated relative25

to the amount of state appropriation made available through lines of credit. 26

Section 15. The provisions, items, and projects contained in this Act are severable27

and if any provision, item, or project contained herein, or the application of any such28

provision, item, or project, is held invalid, such invalidity shall not affect other provisions,29

items, projects, or applications of the Act which can be given effect without the invalid30

provision, project, item, or application. 31

ENROLLEDHB NO. 2

Page 202 of 202

Section 16. Notwithstanding any other provisions of law to the contrary, the State1

shall not grant cash lines of credit, or authorize or issue general obligation bonds in a2

principal amount in excess of $1,605,035,000 for Fiscal Year 2014-2015. 3

Section 17. Notwithstanding any contrary provision of this Act or any contrary4

provision of law, no funds appropriated by this Act shall be released or provided to any5

recipient of an appropriation made in this Act if, when, and for as long as, the recipient fails6

or refuses to comply with the provisions of R.S. 24:513. No recipient shall be considered7

to fail or refuse to comply with the provisions of R.S. 24:513 pursuant to this Section during8

any extension of time granted by the Legislative Auditor to the recipient to comply. The9

Legislative Auditor is authorized to grant an extension of time to comply with the provisions10

of R.S. 24:513 for recipient entities of an appropriation contained in this Act.11

Section 18. This Act shall become effective upon signature by the Governor or, if12

not signed by the Governor, upon expiration of the time for bills to become law without13

signature by the Governor, as provided in Article III, Section 18 of the Constitution of14

Louisiana. If vetoed by the Governor and subsequently approved by the Legislature, this Act15

shall become effective on the day following such approval.16

SPEAKER OF THE HOUSE OF REPRESENTATIVES

PRESIDENT OF THE SENATE

GOVERNOR OF THE STATE OF LOUISIANA

APPROVED: