MONTHLY PROGRESS REPORT JUNE – 2014
REHABILITATION, STRENGTHENING AND FOUR LANING OF QUAZIGUND TO BANIHAL SECTION OF NH‐1A FROM KM. 189.350 TO KM. 204.700, INCLUDING 2‐TUNNELS (2‐LANE) OF 0.69 KM AND 8.45 KM LENGTH ON DBFOR (ANNUITY) BASIS, IN THE STATE OF JAMMU AND KASHMIR
Client : National Highways Authority of India Agreement No. : NHAI/BOT/11019/1/2009/QB/58 30.04.2010
South Portal Cut & Cover Tube 1
NavayugaQuazigund Expressway Pvt. Ltd. Site office : Nowgam, Banihal, Dist. Ramban, Jammu & Kashmir – 182 146
Report No. NECMPR 0614
INDEX
DESCRIPTION PAGE NO.
1 DETAILS OF PROJECT 1
2 SCOPE OF THE PROJECT 2
3 PROJECT MAP 3
4 PROJECT DETAILS 4
5 STATUS OF STRUCTURES 6
6 TUNNEL CONSTRUCTION STATUS 8
7 CUMMULATIVE PLANNED V/S ACHIEVED STATUS OF TUNNEL 9
8 QUANTITY WISE PROGRESS ACHIVED FOR ROAD AND BRIDGES 10
9 EXISTING HIGHWAY MAINTENANCE 11
10 MILE STONE FOR THE COMPLETION OF THE PROJECT 13
11 HUMAN RESOURCE DEPLOYED FOR PROJECT 14
12 EQUIPMENT DEPLOYED FOR THE PROJECT 22
13 MAJOR CONSTRUCTION MATERIAL REPORT 26
14 PROGRESS AFFECTED 27
15 LAND AQUISATION STATUS 30
16 CORRESPONDENCE DURING THE MONTH 32
17 GEOLOGICAL REPORT 33
18 QUALITY REPORT 34
19 SAFTEY REPORT 35
20 PROJECT PROGRESS PHOTOGRAPHS 38
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 1
1. DETAILS OF PROJECT
NAME OF WORK:
Rehabilitation, Strengthening and Four Laning of Quazigund to Banihal Section of NH‐1A
from km.189.350 to km.204.700, including 2‐Tunnels (2‐lane) of 0.69 km & 8.45 km
length on DBFOT (Annuity) basis, in the state of Jammu & Kashmir (Package No: NHDP –
Phase II/BOT/II/J&K.)
AGREEMENT No. : NHAI/BOT/11019/1/2009/QB/58,
dated 30.04.2010.
EMPLOYER : NATIONAL HIGHWAY AUTHORITY OF INDIA.
INDEPENDENTCONSULTANT : SMEC INTERNATIONAL PTY. LTD. IN ASSOCIATED
WITH SMEC INDIA PVT. LTD & RODIC CONSULTANT
PVT.LTD.
CONTRACTOR : M/S NAVAYUGA ENGINEERING COMPANY LTD.
CONCESSIONAIRE : NAVAYUGA QUAZIGUND EXPRESSWAY PVT.LTD
PROJECT COST : Rs. 1987 Crores
PERFORMANCE SECURITY : Rs. 99.35 Crores
Date of Agreement : 13‐07‐2010
Appointed Date : 05‐06‐2011
Stipulated Date of completion : 04‐06‐2016
End of Concession : 04‐06‐2031
INTERNAL CONSULTANT
FOR TUNNEL : Geo Consults – Austria
FOR BRIDGE : ASC Infra Tech – Delhi
FOR ROADS & SURVEY : Aarvee Associates ‐ Hyderabad
Project Address : Village: Nowgam, Tehsil: Banihal, Dist. Ramban,
Jammu & Kashmir, 182146.
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 2
2. SCOPE OF THE PROJECT
The scope work is 4‐laning from km.189.350 (Banihal) to km 204.7OO (Srinagar) section and of
Nine bridges on Banihal bypass as per Concession Agreement.
The 8450 meter long tunnel T2 is located in the PirPanjal mountain ranges approximately 10 km
north of Banihal. The altitude of southern portal will be at Km 195.533 with formation level RL
1858.00 meter while altitude of northern portal formation level will be at 1790.298 meter at
Km 203.991 meter. The tunnel passes through rock cover zone as high as up to 1100 meter.
The proposed tunnel is Twin Tube Tunnel.
Total Project Length : 15.350 Km.
Tunnel Lengths : Tunnel T‐1: 696 meters.
: Twin Tube Tunnel T‐2: 8450 meters.
Major Bridges : 3 no’s
Minor Bridges : 6 no’s
Culverts : 9 no’s
Length of Roads : 4.928 Km
Truck Lay Bays : 2 no’s
Toll Plaza : 2 no’s
Construction Period : 5 Years.
Concession Period : 20 years including Construction Period.
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 3
3. PROJECT MAP
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 4
4. PROJECT DETAILS :
4.1. Major and Minor Structures:
Project Chainage in Km
Description
Nomenclature Crossing Structural Details Length Lanes
189.350 Start of the Project
189.440 Bridge No. 1 (Major)
Bichleri River Composite RCC abutment, piers
and steel girder.
110.950m 3 x 36.63 (43 Skew)
4 Lane
189.852 Bridge No. 2 (Minor)
Water Stream Composite RCC abutment, piers
and steel girder. 22.43 m 4 Lane
190.145 Bridge No. 3 (Minor)
Water Stream RCC Box Structure 9.94 m 4 Lane
190.305 Bridge No. 4 (Minor)
Water Stream Composite RCC abutment and
steel girder. 25.00 m 4 Lane
190.857 to
191.007
Retaining Wall
Along with Distributary for Bichleri
RCC Structure 150 m 4 Lane
191.066 Bridge No. 5 (Major)
Railway RUB RCC Box Structure 79.184 m 4 Lane
191.422 Bridge No. 6 (Minor)
Water Stream RCC wall type abutments. 10.82 m 4 Lane
193.354 Bridge No. 7 (Minor)
Water Stream RCC wall type abutments. 18.70 m 4 Lane
193.790 Bridge No. 8 (Minor)
Water Stream RCC Box Structure. 3.00 m 4 Lane
195.690 Bridge No. 9 (Major)
Hill Side along Bichleri River
RCC Viaduct, abutment, piers. 15.20 m 4 Lane
195.795 to
204.273
Twin Tube Tunnel‐2
Pir Panjal Mountain
RCC Twin Tube
195.834‐ West Tube South Portal
195.795‐ East Tube South Portal
204.273‐West Tube North Portal
204.249‐East Tube North Portal
8.42 Km 4 Lane
205.600 End of the Project
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 5
4.2. Others:
Project Chainage in
Km Structure Length in m Lanes
190.482 Pipe Culvert 1.44 4 Lane
190.658 Pipe Culvert 1.44 4 Lane
190.681 Box Culvert 4.00 4 Lane
191.574 Pipe Culvert 1.44 4 Lane
191.789 Box Culvert 2.00 4 Lane
191.914 Pipe Culvert 1.44 4 Lane
192.131 Box Culvert 2.00 4 Lane
192.925 Box Culvert 3.00 4 Lane
192.354 Box Culvert 4.00 4 Lane
204.386 Box Culvert 3.00 4 Lane
204.475 Box Culvert 3.00 4 Lane
204.597 Box Culvert 3.00 4 Lane
204.811 Box Culvert 3.00 4 Lane
205.131 Box Culvert 3.00 4 Lane
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 6
5. STATUS OF STRUCTURES AS ON 30.06.2014
Type of Structure Prj. Ch. Length Work Status
Major Bridge (Steel girder with RC deck composite) (Bridge no.1 (All drawings received for Super Structure)
189.440 109 .8m Sub Structure Completed Super Structure Fabrication Under Progress.
Framed Box Structure (Bridge no.2) (All drawings up to Super Structure received except return & wing wall) – Minor Bridge
189.852 22.654mMain Structure Completed Wing walls under progress.
Framed Box Structure (Bridge no.3)– Minor Bridge
190.140 9.94m Completed.
Steel girder with RC deck composite (Bridge no.4) (all drawings received) – Minor Bridge
190.318 25m Sub Structure Completed. Super Structure Fabrication Under Progress.
Box Type Structure RUB (Bridge no.5)
191.106 79.95m Completed
Framed Structure (Bridge No 6 )‐Minor Bridge
191.427 10.82m Main Structure Completed
Steel girder with RC deck composite (Bridge no.7)
193.363 28m Alignment to be approved.
Framed Structure (Bridge no.8) 193.791 15m Main Structure Completed Wings wall under progress.
Steel girder with RC deck composite (Bridge no.9)/viaduct
194.68 730m Approval is awaited.
Box Culvert 190.680 4X3 Completed
Box Culvert 191.789 2X3 Completed
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 7
Type of Structure Prj. Ch. Length Work Status
Box Culvert 192.131 2X3 Completed.
Box Culvert 192.354 4X3 Drawing received, land not acquired
Box Culvert 192.925 3X2 PCC Completed.
Box Culvert (Near North Portal) 204.811 2X3 RHS Walls under progress.
Pipe Culver (Near RUB) 191.020 2x1.2 PCC Completed
Truck Parking and Toll Plaza 192.680 to 193.680 Earthwork in progress
Road Work 191.789 to 192.131 Earthwork in progress
RCC Retaining wall along the water stream
190.857 to 191.007 150 m.
12 Nos. Panels excavation Completed out of 15 Nos.
12 Nos. Panels PCC Completed out of 15 Nos.
12 Nos. Panels RCC footing Completed out of 15 Nos.
11 Nos. Panels RCC counter forte and wall concrete in progress out of 15.
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 8
6. TUNNEL CONSTRUCTION STATUS as on 30.06.2014:
Description Unit Total Length
North Portal South Portal Upto
30.06.2014Balance Upto
31.05.2014 For June 2014
Upto 30.06.2014
Upto 31.05.2014
For June 2014
Upto 30.06.2014
Tube‐1 (Heading) Rm 8,442.51 2251.40 ‐ 2251.40 2097.50 ‐ 2097.50 4,348.90 4,093.61
Tube‐2 (Heading) Rm 8,457.45 2124.70 ‐ 2124.70 2079.00 ‐ 2079.00 4,203.70 4,253.75
Tube‐1 (Benching) Rm 8,442.51 2067.70 ‐ 2067.70 2023.00 ‐ 2023.00 4,090.70 4,351.81
Tube‐ 2 (Benching) Rm 8,457.45 2040.70 ‐ 2040.70 1855.30 ‐ 1855.30 3,896.00 4,561.45
Cross Passage Rm 900.00 244.30 ‐ 244.30 240.00 ‐ 240.00 484.30 415.70
Tube 1 Abutment Water Proofing Membrane
Rm 8,442.51 610.00 90.00 675.00 556.50 50.00 606.50 1,281.50 7,161.01
Tube 1 Abutment Concrete Rm 8,442.51 560.00 90.00
650.00 526.36 25.00 551.36 1,201.36 7,241.15
Tube 1 Overt Water Proofing Membrane
Rm 8,442.51 251.00 247.00 448.00 379.50 108.00 487.50 935.50 7,507.01
Tube 1 Overt Lining Concrete Rm 8,442.51 175.00
‐ 175.00 312.50 25.00 337.50 512.50 7,930.01
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 9
7. Cumulative PLANNED V/S ACHIVED UPTO June 2014 as per R2 Plan:
‐ 1,000.00 2,000.00 3,000.00 4,000.00 5,000.00 6,000.00 7,000.00 8,000.00 9,000.00
‐ 1,000.00 2,000.00 3,000.00 4,000.00 5,000.00 6,000.00 7,000.00 8,000.00 9,000.00 10,000.00
Length in Meter
South Portal T‐1 Heading
South Portal T‐2 Heading
South Portal T‐1 Benching
South Portal T‐2 Benching
North Portal T‐1 Heading
North Portal T‐2 Heading
North Portal T‐1 Benching
North Portal T‐2 Benching
Total Heading Total Benching
Planned 2,615.00 2,605.00 2,499.00 2,505.00 2,584.00 2,530.00 2,486.00 2,447.00 10,334.00 9,937.00
Achieved 2,097.00 2,079.00 2,023.00 1,855.50 2,251.00 2,124.00 2,067.70 2,040.70 8,551.00 7,986.90
SP T1 HEADING
SP T1 BENCHING
SP T2 BENCHING
NP T1 HEADING
NP T2 HEADING
NP T1 BENCHING
NP T2 BENCHINGTOTAL HEADING
TOTAL BENCHING
SP T2 HEADING
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 10
8. QUANTITY WISE PROGRESS ACHIEVED FOR ROADS AND BRIDGES JUNE 2014:
Bridge No.
Prj. Ch. Km
UOM Item Achieved
Qty Summery
Retaining wall
190.857 to 191.007 150 m.
Cum M35 66.00Counter fortes and walls under progress.
Bridge No. 2
189.852 Cum M40 310.00 RHS Top slab Completed.
Bridge No. 8
193.792 Cum M35 35.00RHS Top Slab Completed and Wing / Retaining Walls under progress.
Pipe Culvert
191.020 Cum M15 10.00 Bottom leveling completed.
Earth Work
Truck Parking Area
Cum Earth Work
Work In Progress
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 11
9. EXISTING HIGHWAY:
9.1. The existing highway maintenance is done by NECL for the scope stretch.
Concrete Pavement at Railway ROB
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 12
9.2. Quantities Utilized till 22.06.2014 for making existing highway traffic worthy :
Sl. No.
Description of Work UOM Quantity
1
Providing of Bitumen macadam with hot mixing of stone aggregates, filler and bitumen in computerized batch type hot mix plant, transporting the mixed material by tippers to site, using crushed aggregates of specified grading as per MORT&H Specifications Section 500,Clause 504,table 500‐4 premix with bituminous binder. a) Bitumen of grade 60/70 @ 3.5% (percentage by weight of total mix).
MT 583.450
2
Providing of of Bitumen Concrete with hot mixing of stone aggregates, filler and bitumen in computerized batch type hot mix plant, transporting the mixed material by tippers to site, using crushed aggregates of specified grading as per MORT&H Specifications Section 500,Clause 509,table‐500‐18 premix with bituminous binder. a) Bitumen of grade 60/70 @ 5%( percentage by weight of total mix) and lime filler @ 3% (percentage by weight of total mix).
MT 5458.250
3 Providing and spreading of Bitumen Tack coat layer as directed by Engineer In Charge
156 Kgs (One Barrel)
160
9.3. Equipment Resources Deployed:
1. Mechanical Paver – 2 Nos. 2. Vibratory Road Roller – 1 No. 3. Static Road Roller – 2 Nos. 4. Air Compressor – 2 Nos. 5. Hot Mix Plant – 1 No. 6. Tippers – 12 Nos. 7. Excavators (JCB) – 2 Nos. 8. Motor Grader – 1 No.
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 13
10. MILE STONE FOR THE COMPLETION OF THE PROJECT:
Mile stone No.
Time Allowed for Achieving the Mile Stone from Appointed
Date
Physical and Financial Progress to be achieved Remarks
1 180 days
Shall commence construction and expended not
less than 10 % of total capital cost set for in the
financial package.
Achieved
2 365 days
Shall have commenced construction of all bridges
and expended not less than 20 % of total capital
cost set for in the financial package.
Achieved,
Recommended by
IE
Approval from
NHAI awaited
3 550 days
Shall have commenced construction of all project
facilities and expended not less than 30 % of total
capital cost set for in the financial package.
Achieved,
122 days extension
Recommended by
IE,
Approval from
NHAI awaited
4 730 days
Shall have commenced construction of all project
facilities and expended not less than 40 % of total
capital cost set for in the financial package.
Achieved,
Recommendation
from IE awaited
5 925 days
Shall have commenced construction of all project
facilities and expended not less than 50 % of total
capital cost set for in the financial package.
‐‐‐‐‐‐‐‐
6 1105 days
Shall have commenced construction of all project
facilities and expended not less than 60 % of total
capital cost set for in the financial package.
‐‐‐‐‐‐‐‐
7 1285 days
Shall have commenced construction of all project
facilities and expended not less than 70 % of total
capital cost set for in the financial package.
‐‐‐‐‐‐‐‐
8 1465 days
Shall have commenced construction of all project
facilities and expended not less than 85 % of total
capital cost set for in the financial package.
‐‐‐‐‐‐‐‐
9 1645 days
Shall have commenced construction of all project
facilities and expended not less than 100 % of total
capital cost set for in the financial package.
‐‐‐‐‐‐‐‐
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 14
11. HUMAN RESOURCE DEPLOYED FOR PROJECT
a. MANAGEMENT
S.No. Name Designation Remarks
1 Mr. MdSirajuddin Regional Director From Kolkata
2 Mr. Pannagaraj M.K. Vice President (Projects) From CO
3 Mr. Deepak Surinder Kumar General Manager Tunnel Expert
4 Mr. P. Satyanarayana Deputy General Manager
5 Mr. Ch. BalaSubramanyam Project Manager
b. ADMINISTRATION
S.No. Name Designation Remarks
1 Mr. P. Rama Krishna Accounts Officer
2 Mr. A. SrinivasaRao Sr.HR Officer
3 Mr. Vinay Jain Chief Liaison Officer
4 Mr. Gh. Mustafa Khan P.R.O
5 Mr. GulamMohd Khan Jr. P.R.O
6 Mr. Narasayya HR Asst.
7 Mr. G Mahesh Kumar HR Asst
8 Mr. GovindaRao Accountant
9 Mr. Md. Kutbuddin Asst. Accountant
10 Mr. Ravi Kanth Asst. Accountant
11 Mr. C.H. SrinivasaRao Asst. Accountant
12 P. SuryaRamanjaneyaRaju Asst Engineer (Sims)
13 Mr. Prakash Chand Jat System Administrator
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 15
c. PLANNING AND MONITERING:
S.No. Name Designation Remarks
1 Mr. Sangamesh K Sr. Engineer
2 Mrs. Sandhya Sr. Engineer
D. SOUTH PORTAL TUNNEL:
S.No. Name Designation Remarks
1 Mr. Binay Kumar Singh Sr. Dy. Manager
2 Mr. Naveed Saif Wani Asst. Manager
3 Mr. V.M.V. Ramanchary Asst. Project Manager
4 Mr. SK Sunil Senior Site Engineer
6 Mr. Anil. bhardwaj Senior Site Engineer
7 Mr. Suresh Kumar Meena Site Engineer
8 Mr. Rajendra Singh Rawat Geologist
9 Mr. Madhuresh Kumar Singh Jr. Engineer (Electrical)
10 Mr. Pradeep Singh Jr. officer geologist
11 Mr. Laxmander Pal Sr.Foreman
12 Mr. Mujeeb Ur Rehman Foreman
13 Mr. Pawan Kumar Singh Foreman
14 Mr.Ajaykumar Foreman
15 Mr. Mir Babbar TR. Engineer
16 Mr. Om Prakash Foreman
17 Mr. Sehdev Rana Foreman
18 Mr. Irshad Ahmed Lone Foreman
19 Mr. Latchayya Foreman
20 Mr. Rambabu Sr. Supervisor
21 Mr. Bashir Ahmed Wani Supervisor (Electrical)
22 Mr. Irfan Amin Itoo Tr Supervisor
23 Mr. SukanthNayak Supervisor
24 Mr. Debasishlanka Supervisor
25 Mr. Bashir Ahmad Supervisor
26 Mr. Ishaq Supervisor
27 Mr. Asruf Supervisor
28 Mr. Safiq Ahmed Kaully Supervisor
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 16
E. NORTH PORTAL TUNNEL:
S.No. Name Designation Remarks
1 Mr. DebyenduHaldar Sr. Dy. Manager
2 Mr. Ram Prakash Garla Sr. Engineer
3 Mr. Jagtar Singh Sr. Engineer
4 Mr. BalaKoteswaraRao D Senior Site Engineer
5 Mr. Sree Ganesh Senior Site Engineer
6 Mr. SajadurRahmanGani Junior Engineer Civil
7 Mr. Mushtaq Ahmad Bhat Junior Engineer Civil
8 Mr. Davood Ahmed Rather DTE (Civil)
9 Mr. Laxman Singh Singwal Officer (Geologist)
10 Mr. Bhoopender Singh Geologist
11 Mr. PankajGulshan Jr. Geologist
12 Mr. Shoib Ahmed Khan DTE (Mech)
13 Mr. Sheikh Mumin Amin DTE (Civil)
14 Mr. ArifHussainBeigh DTE (Mech)
15 Mr. ZakirHussainNaik TR Engineer (Civil)
16 Mr. Y.S.Rathore Site Engineer (Electrical)
29 Mr. Sameer Ahmed Itoo Supervisor
30 Mr. Muzfara Ahmed Wani Supervisor
31 Mr. Dharma Biswal Supervisor
32 Mr. Javeed Ahmed Sheikh Supervisor
33 Mr. Irshad Ahmed Wani Supervisor
34 Mr. Iftikar Ahmed Supervisor
35 Mr. BaburamNayak Supervisor
36 Mr. Farooq Ahmed Wani Camp Supervisor
37 Mr. K Shibu Kumar Sr. Electrician
38 Mr. K. SuriBabu Sr. Mason
39 Mr. Ghani Khan Supervisor
40 Mr. Naval Singh Rajput Mechanic Chargand
41 Mr. Rajeev Kumar Singh Supervisor
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 17
17 Mr. Bilal Ahmed Khan TR Engineer (Mechanical)
18 Mr. Anup Kumar Pandey Jr. Foreman
19 Mr. Dilip Kumar Shah Sr. Foreman
20 Mr. Vijay Kumar Chargeman (Fitter)
21 Mr. Deepak Kumar Asst. Foremen (Electrical)
22 Mr. Ritu Raj Suman Sr.Supervisor
23 Mr. Abdul QuayyumParray Sr. Supervisor
24 Mr. K Kumar Electrician
25 Mr. Jakir Hussain Computer Operator
26 Mr. Amrit Pal Singh Supervisor
27 Mr. Kamalesh Borai Supervisor
28 Mr. Irshad Ahmed Wani Supervisor
29 Mr. Mohd. Ismail Wani Tr.Supervisor
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 18
F. ROADS AND BRIDGES:
S.No. Name Designation Remarks
1 Mr. V. Suneel Babu Sr. Dy. Manager
2 Mr.LoyaNani Site Engineer
3 Mr. L. Aditya Engineer
4 Mr. S. Hari Prasad GTE
5 Mr. B. Raja Reddy Foreman
6 Mr. Aamirmushtaq DTE(Mech)
7 Mr. P. Jagannadam Sr. Supervisor
8 Mr. Kharjur Singh HR Asst.
9 Mr. K. Mohan Rao Sr. Supervisor
10 Mr. Manoj Kumar Swain Sr. Supervisor
11 Mr. P.MalleswaraRao Sr. Supervisor
12 Mr. M. LaxmanaRao Supervisor
13 Mr. G. Suresh Supervisor
14 Mr. Mohd. Iqbal Dar Supervisor
15 Mr. Imtiyaz Ahmad Mir Supervisor
16 Mr. S. Kannababu Supervisor
17 Mr. Faiz Ahmed Gowhar Tr.Supervisor
18 Mr. K. KurmaRao Pump Operator
G. QUALITY ANALYSIS AND QUALITY CONTROL:
S.No. Name Designation Remarks
1 Mr. Kala Srinivasu Manager
2 Mr. Kranthi Kumar Site Engineer
3 Mr. Suraj Kumar Das G.T.E
4 Mr. Rithesh Kumar Tiwari Sr. Lab Technician
5 Mr. Gajendra Singh Operator (B/ Plant)
6 Mr. D. Damoder Operator (B/ Plant)
7 Mr. M.KoteswaraRao Lab Tech
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 19
8 Mr. K.ChinnaVenkanna Lab Asst.
9 Mr. D.Gangayya Lab Technician
10 Mr. P. TirupathiRao Batching Plant Operator
h. PLANT & MACHINERY
S.No. Name Designation Remarks
1 Mr. Mushtaq Ahmed Ganai Chief Manager (Electrical)
2 Mr. Muneeb Ahmad tak Sr. Manager (Electrical)
3 Mr. K. Gopal Krishnam Raju Manager (Mech)
4 Mr. Niranjan Reddy Asst. Manager
5 Mr. Irfan Elahi Lone Asst. Manager
6 Mr. Sunil Kumar Chauhan Senior Site Engineer (Fabrication)
7 Mr. HamsaRaju Asst. Project Manager (Electrical)
8 Mr. JaggaRao Site Engineer
9 Mr. Jaya Prakash Site Engineer (Fabrication)
10 Mr. Tinku Adak Site Engineer (Fabrication)
11 Mr. Rama Bangaru Naidu Site Engineer (Electrical)
12 Mr. Rajesh Chakraborthy Site Engineer
13 Mr. Kuldeep Singh Site Engineer
14 Mr. V.Ramanna Site Engineer (Mechanical)
15 Mr. G. VamsiKrishnam Naidu Site Engineer (Electrical)
16 Mr. MohitPlaha Site Engineer (Electrical)
17 Mr. G. Vinay Kumar GTE (Mechanical)
18 Mr. GLR Srinivasa Reddy Site Engineer (Electrical)
19 Mr. Sunil Chand Ramola Sr. Foreman (Electrical)
20 Mr. T. Ansari Electrician
21 Mr. Farooq Ahmed Tantry Record Keeper
22 Mr. Kurban Ansari Concrete Pump Operator
23 Mr. Ram KripalChoudhary Senior Mechanic
24 Mr. Satyendra Singh Foreman(Electrical)
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 20
i. STORE
S.No. Name Designation Remarks
1 Mr. P.S. Lobo Asst. Manager (In charge)
2 Mr. A. A. Naidu Sr. Store In Charge
3 Mr. SK. Mastan Ali Sr.Store in Charge Jammu
4 Mr. SPS Chauhan Sr. Store In Charge
5 Mr. L. Simhadri Naidu Sr. Store Assistant
6 Mr. Satyanarayana G Sr.Store Keeper
7 Mr. R. Ramana Sr.Store Assistant
8 Mr. Y. Appala Naidu Store Assistant
10 Mr. Suresh .B Store Assistant
11 M. Krishna Store Assistant
12 Mr. Mallesh Sr. Store Assistant
13 Mr. Meeraj Store Assistant
14 Mr. AB. Rashid Mir Store Assistant
15 Mr. Pankaj Kumar Sahu Store Assistant
16 Mr. K.V.Ramana Store Assistant
17 Mr. G. Murali Krishna Store Assistant
18 Mr. Baljit Singh Store Assistant
19 Mr. M Appalnaidu Store Assistant
20 Mr. Ch. Polidas Store Assistant
21 Mr. T Sravan Kumar Store Assistant
22 Mr. Anand Store Assistant
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 21
j. SURVEY:
S.No. Name Designation Remarks
1 Mr. Samim Ahmed Asst. Project Manager
2 Mr. Sumit Singh Senior Surveyor
3 Mr. Babun Roy Senior Surveyor
4 Mr. Pradeep Das Senior Surveyor
5 Mr. Ram BabruwanPinate Surveyor
6 Mr. SandeepSasmal Surveyor
7 Mr. Pradeep Rathi Surveyor
8 Mr. Sougata Jana Surveyor
9 Mr. R.Santoshnaidu Surveyor
10 Mr. Suvjit Gosh Jr. Surveyor
11 Mr. SajaySav Jr. Surveyor
12 Mr. ArghayadipSamanta Jr. Surveyor
13 Mr. ShanawazBhat Asst. Surveyor
14 Mr. Rakesh Kumar Sharma Asst. Surveyor
k. SAFETY:
S.No. Name Designation Remarks
1 Mr. B. Ramesh Rao Safety officer
2 Mr. Venkkatesha Safety officer
3 Mr. Sheikh BIlal Ahmed Safety Supervisor
4 Mr. Manawar Ali Sr. Safety Supervisor
5 Mr.Bilal Ahmed wasay Safety Supervisor
6 Mr. Irfan Amin Itoo Safety Supervisor
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 22
12. EQUIPMENT DEPLOYED FOR THE PROJECT
S.No. Equipment Description
Make Model Capacity Total No's
Location Remarks
1 DG Set Silent Old & Used
Leyland 62.5 Kva 5 1‐ work shop3‐Road& Bridges
1‐North Portal
Working
2 DG Set Silent Old & Used
Greaves GV125 SP 125 Kva 3 2‐ Colony1‐ North Portal
Working
3 DG Set Silent LiebherrCaterpillar
3306DITA‐GP‐4
250 Kva 4 1‐ Colony2‐ South Portal 1‐ North Portal
Working
4 DG Set Silent Caterpillar C‐18 600 Kva 2 1‐ South Portal1‐ North Portal
Working
5 DG Set Silent Caterpillar C‐18 500 Kva 2 2‐ North Portal Working
6 DG Set Silent Caterpillar C‐32 1010Kva 2 1‐ South Portal 1‐Crusher Plant
Working
7 DG Set Silent Mahindra 4375 25 kva 1 DGM Rest House Working
8 DG Set Silent Old & Used
Leyland 40 kva 1 North Portal Working
9 DG Set Silent Mahindra & Mahindra
2185 GM 15KVA 1 Dharsipura Working
10 DG Set Silent Portable
Honda EXK‐2000AC
1.6 Kva 1 Dharsipura Working
11 DG Set Silent Portable
Honda EXK‐2800 2 Kva 1 DGM Rest House Working
12 Dozer Caterpillar D6G 1 Batching Plant Working
13 Dozer BEML BD80
1 Working
13 Excavator Volvo Volvo EC290BLC 1.1cum 4 1‐Road&Bridges2‐ South Portal 1‐
North Portal
Working
14 Excavator Volvo Volvo EC210B 0.9 cum 2 1‐ South Portal 1‐ North Portal
Working
15 Tipper Volvo Volvo FM 400 8X4
18.7 cum 20 12‐ South Portal08‐ North Portal
Working
16 Motor Grader Volvo G930 1 01‐ North Portal Working
17 Tractor with Dozing Blade
Mahindra TR 605 CEU
60HP 2 01‐ North Portal1‐Road& Bridges
Working
18 JCB Back Hoe /Loader
JCB India Super 3DX 4WD
2 1‐ South Portal1‐North Portal
Working
19 Vibratory Compactor
Volvo SD110 2 1‐ Road 1‐North Portal
Working
20 Boomer Atlas Copco E2C 120 Kw 4 2‐ South Portal2‐North Portal
Working
21 Boomer Atlas Copco XE3C 175Kw 1 1‐North Portal
22 Camper Tata 207 Crew 6 Members
3 1‐South Portal2‐North Portal 3‐Road Works
Working
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 23
23 Explosive Vans Tata 207 Crew 2
South & North Portal
Working
24 Diamond Coring Tool
Hilti DD130 M 1 1‐Lab
Working
25 Rock Cutter Hydraulic
Sandvik ATH‐150 1 1‐Lab
Working
26 Concrete Spray Machine
SikaPutzmeister SPM 500 PC
30m3/hr 4 2‐ South Portal 2‐North Portal
Working
27 Shotcrete Pump Dry
CanstroEngg.Works 1 1‐North Portal Working
28 Grout Pump Atlas Copco MAI M400NT
5 3‐ South Portal2‐North Portal
Working
29 Grout Pump Atlas Copco E200‐55‐12H
1 1‐North Portal Working
30 Explosive Van Tata Motors SK 1616 9 ton 2 2‐work shop Working
31 Wheel Loader Volvo L120 2 1‐ South Portal 1‐North Portal
Working
32 Wheel Loader Volvo L220G 4 2‐ South Portal 2‐North Portal
Working
33 Hydraulic Rock Breaker
Atlas Copco MB1500 Star select
2 1‐ South Portal 1‐North Portal
Working
34 Truck Chassis/Scissor lift
Tata Motors LPT1613 2 1‐ South Portal1‐North Portal
Working
35 Air receiver Integrated engineers
3‐cum 4 2‐ South Portal 2‐North Portal
Working
36 Crawler Drill ROC
Atlas Copco ROC 203 PC XXXX 1 1‐North Portal Working
37 Air Compressor Atlas Copco XA280CUD 600cfm 2 2‐ South Portal Working
38 Air Compressor Electric
Atlas Copco GA160 2 2‐ South Portal Working
39 Crane Mobile Pick & Carry
ESCORTS F‐15 14 ton 2 1‐ road 1‐North Portal
Working
40 Re‐Bar Cutting Machine
Spartan SCM‐42 36 MM 5 1‐Fabrication Yard
4‐np
41 Re‐Bar Bending Machine
Spartan SBM‐42S 36 MM 5 1‐Fabrication Yard
Working
42 Concrete Mixer Old
Universal RM800 1.0 Cum 1 scrap
Working
43 Grinding Machine
Atlas Copco Secoroc BQ3
1 1‐ South Portal
Working
44 Lathe Machine Somnath Machine Tools
52mm 2 1‐ South Portal1‐North Portal Working
45 Lathe Machine Somnath Machine Tools
300mm 1 1‐ South Portal
Working
46 Batching Plant SchwingStetter CP‐30 30 Cum/hr 1 1‐north portal Working
47 Batching Plant SchwingStetter M1 60 Cum/hr 2 2‐south portal
Working
48 Concrete Pump Schwing SP1400 52cum/hr 4 1‐Work Shop 3‐Road&Bridges Working
49 Concrete Pump Schwing 350 EXT 46cum/hr 1 1‐Work Shop
Working
50 Transit‐Mixer SchwingStetter AM6 SHN‐ 6 Cum/hr 12 6‐South Portal Working
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 24
RH 6‐North Portal
51 Silo for Cement SchwingStetter NA 100 ton 4 3‐Batching Plant1‐North portal
Working
52 Crushing Plant Mobile
Metso Minerals LOCO TRACK
200TPH 1 1‐south portal Working
53 Tata Safari 4X4 Tata Motors Dicor 2179CC 1 1‐south portal Working
54 Scorpio Sle 2WD
Mahindra SLE 2WD 2600cc 1 1‐south portal Working
55 Scorpio VLX 4WD
Mahindra VLX4WD BS‐4
2179CC 2 1‐south portal Working
56 Utility Vehicle Mahindra Bolero Camper 4WD
5 4‐ South portal1‐North portal
Working
57 Ambulance Tata Motors Winger 1 1‐south portal Working
58 Ambulance Maruti Omni 1 1‐North portal
Working
59 Water Tanker Locally Made Trolley Mounted
2 2‐ Work Shop Working
60 Mini Truck Tata Motors SFC407EX 3 ton 2 1‐ South Portal Working
61 Weigh Bridge 18X3
EssaeDigitrinics TM‐960 100 ton 1 1‐ South Portal1‐North Portal Working
62 Motor Bike Bajaj Discover 150 cc 1 Jammu Working
63 Bus 24 Seater Tata Motors Tata Star Bus
1 1‐ South PortalWorking
64 Prime Mover for Trailer
Tata Motors LPS 3518 1 1‐ South PortalWorking
65 Diesel Tanker Chassis
Ashok Leyland 1012 E COMET
6KL 2 2‐ South PortalWorking
66 Excavator TATA ‐ Hitachi EX 200 LCH 1 1‐Crusher PlantWorking
67 Threading Machine
Industrial Machines Pvt. Ltd.
‐ ‐ 1 1‐Work shopWorking
68 Water Tanker Chassis
Ashok Leyland
‐ 12KL 2 2‐ South PortalWorking
69 Welding DG SET ESAB EDW 400 & 350 Amps
1 each
2‐Roads & Bridges
Working
70 Motor Cycles Hero Glamour 2 Seater 2 2‐ South Portal
Working
71 Dozer BEML BD80 180HP 1 South Portal Working
72 Tipper AMW AMW 2518TP 14Cum 4 2‐Crusher Plant2‐Roads & Bridges
Working
73 Batching Plant SchwingStetter M1 1 Working
74 Transit Mixer Tata Motors 4 Roads & Bridges,Tunnel
Working
75 High Pressure Jet Cleaner
Western Floor PW‐H25D1110
PM
Working
76 JCB Backhoe / Loader
JCB INDIA 3DX South Portal Working
77 Hydraulic Rock Breaker
DAEMO ALICON‐B210
North Portal Working
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 25
78 Wheel Loader Hindustan HM2021 1.7 Cum 1 South Portal Working
79 Crawler Crane P&H 320 20Ton 1 RUB Working
80 Crane Mobile Pick & Carry
Escorts Hydra14 14Ton 1 South PortalWorking
81 Concrete Spray Machine
SikaPutzmeister SPM4210 WETKRET
20m3/hr 2 1 North Portal1 South Portal
Working
82 Tata Tippers Tata Hyva 14 Cum 2 2 R&B Working
83 Tunnel Excavator
Liebherr Excavator 1 1 North Portal Working
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 26
13. MAJOR CONSTRUCTION MATERIAL REPORT FOR June 2014:
S. NO.
Item UnitOpening Balance
Procured Consumption BalanceAs on
30.06.14
1 Reinforcement Steel MT 385.08 ‐ 87.31 297.77
2 Cement OPC Bags 5952.00 22928.00 11688.00 17192.00
3 Coarse Aggregate(20 mm) Cum 18712.10 ‐ 522.37 18159.73
4 Coarse Aggregate(12 mm) Cum 2288.00 ‐ ‐ 2288.00
5 Coarse Aggregate(10 mm) Cum 7430.82 ‐ 516.09 6914.73
6 Crusher Dust Cum 8491.64 0.00 579.14 7912.50
7 Fine Aggregate Cum 2952.03 0.00 474.76 2477.27
9 Admixtures(APCON ADDPLAST FA)
Kgs 27750.00 0.00 6750.00 21000.00
10 Admixtures(APCOCRETE SHOT LAF)
Kgs 41000.00 0.00 12250.00 28750.00
11 Explosive(SUPER POWER 80/40MM)
Kgs 7175.78 0.00 275.78 6900.00
12 NED Nos. 9936.00 0.00 287.00 9649.00
13 ED Nos. 254.00 0.00 7.00 247.00
14 Detonating Fuse 10g/mtr Mtr 5625.00 0.00 375.00 5250.00
15 Detonating Fuse 80g/mtr Mtr 1300.00 0.00 0.00 1300.00
16 Connecting Wires Roll 234.00 0.00 6.00 228.00
17 MAI‐Anchor Rod ‐4Mtr No's 2.00 0.00 0.00 2.00
18 MAI‐Anchor Rod ‐3Mtr No's 10401.00 0.00 0.00 10401.00
19 MAI‐Nut No's 547.00 0.00 0.00 547.00
20 MAI‐Plate No's 416.00 0.00 0.00 416.00
21 Swellex Bolt ‐ 4Mtr Nos. 1947.00 0.00 0.00 1947.00
22 Swellex bolt ‐ 6Mtr Nos 742.00 0.00 0.00 742.00
23 Face Plate Nos 2009.00 0.00 0.00 2009.00
24 SN PLATE 150*150*8MM Nos 934.00 0.00 0.00 934.00
25 SN NUT Nos 949.00 0.00 100.00 849.00
26 Wire Mesh MT 23.41 0.00 3.66 19.75
27 Steel Fiber Kgs 97820.00 0.00 1100.00 96720.00
28 Ventilation Duct Pipe 2200mmØ
Mtr 610.00 0.00 0.00 610.00
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 27
14. PROGRESS AFFECTED DUE TO FOLLOWING:
a. MAJOR UTILITIES PRESENT IN THE PROPOSED ALIGNMENT:
1. At Ch. 189500, High Tension Line Crossing (132 KV) – Transmission Line Maintenance Division
– Udhampur.
2. At Ch.189540, newly constructed residential house.
3. At Ch.189660, School in the proposed alignment.
4. At Ch. 189670, Northern Railways compound wall falling in the proposed alignment (L.H.S)
5. At Ch.189710, newly constructed residential house.
6. At Ch. 189745, High Tension Line crossing (132 KV) & Pylon in the center of alignment –
Transmission line Maintenance Division – Udhampur.
7. At Ch. 189875, Residence of PHARWAGAN village both sides of project alignment ‐100 Kva
Substation and its HT/LT Network of village PHARWAGAN Feeder from old Nowgam.
8. At Ch.189875, Residence of PHARWAGAN Village both sides of proposed alignment.
9. At Ch.189955 Grave Yard – 02 Nos. & At Ch. 190060 ‐ 01 No.‐Pharwagan Village. [Alignment
is modified to accommodate graves]
10. At Ch.190660, Water pipeline crossing in proposed alignment. [Shifting under progress]
11. At Ch.190950, Electrical line (11Kv) crossing in the proposed alignment ‐11kv trunk line of Old
Nowgam feeder crossing in proposed alignment.
12. At Ch.191570, Water pipeline crossing in proposed alignment. [Shifting under progress]
13. At Ch. 192073, High Tension Line crossing (400 KV) –Transmission line Maintenance Division –
Udhampur. [This will be avoided after approval proposed alignment which includes viaduct]
14. At Ch. 193070, Ircon Explosive Store falling in the proposed alignment & Truck Parking Area.
15. At Ch. 193635, Electrical line (11 Kv) crossing in the proposed alignment –11Kv Tap of village
Lamber feeder from Chareel feeder.
16. At Ch. 193700, High Tension line crossing (400KV) crossing in the proposed alignment. [This
will be avoided after approval proposed alignment which includes viaduct]
17. At Ch. 193700, PANCHAYAT Building falling in the proposed alignment‐Chareel Lamber. [This
will be avoided after approval proposed alignment which includes viaduct]
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 28
b. Photographs:
HT LINE, Residential & SCHOOL BUILDING, ETC.,
CULTIVATED LAND & Grave YARDHT LINE, WATER BODIES, PUMP HOUSE,
Mobile tower, ETC.
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 29
c. CONTINUOUS SUPPORT REQUIRED FROM NHAI:
o CRPF Protection for South & North Portal.
o Getting the land for project Highway.
o Shifting of Utilities falling in the proposed alignment.
o Vacating Army camp from North Portal.
o Support from Local Administrative & Police to maintain Law and order.
o Vacating of 27 houses of Village Gund Tethar residing above the Tunnel at South Portal.
o Quick land acquisition for Viaduct.
o Support required preventing productivity loss due frequent local strikes.
o Land required for construction of way side amenities near North Portal.
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 30
15. LAND AQUISATION STATUS:
(A) Total Project Land Status including north & south portal as mentioned below:
Total land to be acquired for project : 1620 K Total Area of Land Under possession : 971 K (60%) Balance land to be acquired (Not in Possession) :647K(40%)
(B) Break up for South Portal :
Total Land to be acquired : 1255K Area of land under Possession : 858 K(68%) Area of land not in Possession : 396 K(32%)
(C) Break up for North Portal:
Total Land to be acquired : 364K Area of land under Possession : 113K(31%) Area of land not in Possession : 251K(69%)
(D) Break up as listed below village wise:
S. No.
Village Chainage ROW Acquired land
Possession Status
1. Devgol 189.35‐189.453
60 17K 16 M Under Possession
2.
Karawah B/W Br. No 1& 2
189.453‐189.835
30 21K 6M In Possession 5 K Rest Balance 16 K 6MAdditional 30 m papers under process with office of collector land acquisition.
60 19 K 0.5 M Not in possession
3.
Kaskoot B/W Br. No: 2,3& 4
189.835‐190.681
30 73K 1M Land under possession 80 K Balance 42 K 2 M, Compensation for fruit bearing, non fruit trees, houses pending with collector
60 49K 1 M
4. Zanihal 190.826‐191.057
30 33K 6M Land under possession 20 K , Balance 58 K, 30 m papers completed.Compensation paid except for shamylat land
60 44K 19M
5. Cheerel 191.09‐193.792
60 45 K 11M Under possession 20 K Balance 25 K payment not paid to land owners not in possession
6. Ashar (Truck Parking)
191.419‐191.783
30 282K 6M Land Under possession 270 K, Balance 58 K 5 M , Compensation pending with collector office 60 45K 19M
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 31
7. Lamber ‐ Toll plaza
242 K 6 M Completely under Possession
8. Tethar ‐ Haul road
9 K 12 M Not in Possession.
9. JahgirNamadr
193.738‐193.743
30 1K 4 M Land under possession 1 K 4 M(ROW 30), balance 3 K 18 M(ROW 60), Compensation not paid to land owners ;not in possession.
60 3 K18 M
10. GundTethar I
194.423‐195.545
Viaduct 153 K 14 M Amount deposited in court under sec 18, Land under possession 70 K 4 M, Balance 83 K 4 M, Not in possession.
11. GundTethar II
Way side Amenities
195 K 6 M Land under possession 115 K , balance 80 K 6 M, Compensation under process, Balance under not in possession
12. Nowgam ‐ Approach road
16 K 14 M Completely in possession
13 Ujroo 204.0‐204.3
248K Land under possession 93 K, Rest under army possession
14. Wangund 204.3‐204.7
116K 10M Under possession 20 K, rest under army possession.
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 32
16. CORESPONDENCE DURING THE MONTH :
16.1. SUBMISSIONS DURING THE MONTH TO INDEPENDENT ENGINEERS
Date Letter No. Description
NIL
16.2. SUBMISSIONS DURING THE MONTH TO INDEPENDENT ENGINEERS
Date Transmittal No. Description
07.06.2014 Tunnel/Dwg/T/018 Tunnel T2 Twin tube Niche, Manholes & Opening Along Main Tunnel
07.06.2014 Tunnel/Dwg/T/017 Traffic Control Center North Portal All Drawings
** All Transmittal are having prefix series NQEPL/1239/NHAI/SMEC/
16.3. SUBMISSIONS DURING THE MONTH TO PIU NHAI
Date Letter No. Description
14.06.14 14‐15/029 Concession Fee for the financial year 2014‐2015
14.06.14 14‐15/030 Escrow Account for May‐14
16.06.14 14‐15/031 Used Oil in highway macamadisation
25.06.14 14‐15/032 Financial expenditure upto 20.06.14
25.06.14 14‐15/033 Project Milestone
26.06.14 14‐15/034 Financial expenditure
** All the letters are having the prefix series NQEPL‐1239/JK/20
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 33
17. GEOTECHNICAL REPORT :
1. Geology of the Area
The twin tube tunnel falls in the area extending from Bichlari river valley in north of Banihal in south
to Wujru near Qazigund in the north. The tunnel crosses the PirPanjal mountain range which
separates the Kashmir valley from Jammu. Stratigraphically the area constitutes the Palaeozoic
succession of Kashmir. The main formations of this succession include Muth quartzite which lies
unconformable over Chamalwas Formation. The succession is then followed by Fenestella shale,
Agglomeratic slate, Punjal volcanic, Mammal and Zewan bed formations.
The main litho units of these formations are grey to dark grey and brownish lime stones, siltstones,
quartzites, pebbly sand stones, dark grey shale, Phyllites, basaltic and andesitic flows,tuffaceous
shale and conglomerates.
Geology along alignment
The twin tube tunnel cuts across the following geological formations;
(a) Fenestella shale with quartzite, pebbly sand stone beds, dark grely shale and phyllites as main
litho units.
(b) Panjal volcanic with basaltic and andesitic flows and tuffaceous shale as main litho units.
(c) Zewan beds with silt stones, sand stones, shale and lime stone as main lithounits
Geological Section of PirPanjal Mountain
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 34
18. QUALITY REPORT :
18.1. ABSTRACT FOR TESTS CUNDUCT DURING THE MONTH:
Sl.No. Items South Portal North Portal Total No.of tests
Remarks
Test Conducted at Lab & Field
1 Gradation(10MM) 3 24 27
2 Gradation(20MM) 0 0 0
3 Gradation(20MM:10MM) 23 20 43
4 Gradation(Sand:Dust) 22 23 45
5 Gradation(Sand) 4 4 8
6 Gradation(Dust) 2 4 6
7 Moisture Correction 23 23 46
8 Silt Content 22 23 45
9 Flakiness & Elongation Indices(20mm) 3 0 3
10 Flakiness & Elongation Indices(10mm) 3 3 6
11 Aggregate Impact value(20mm) 3 0 3
12 Aggregate Impact value(10mm) 3 3 6
13 Bulk Density(Coarse & Fine aggregates) 1 1
14 Specific gravity(Coarse & Fine aggregates)
1 1
15 Material Finer than75 Micron
a) N/Sand 3 1 4
b) C/Dust 3 1 4
16 Shotcrete
a) Penetrometer Needle 0 0 0
b) Panel Core Strength 0 0 0
c) In‐Situ Core Strength 0 0 0
d) Shotcrete Cube Strength 0 6 6
17 Grouting Cube Strength 0 0 0
18 Cement Test
a) Consistency 5 5
b) Fineness & Soundness 5 5
c) Compressive Strength 2 2
d) Setting Time 5 5
19 Concrete Cubes Strength
a) M30(Tunnel) 18 2 20
b) M30(Civil) 3 0 3
c) M45 0 0 0
d) M40 9 0 9
e) M35 13 0 13
f) M15 3 1 4
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 35
19. SAFETY REPORT :
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 36
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 37
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 38
20. PROJECT PROGRESS PHOTOGRAPHS:
North Portal Tube 1 Reinforcement Fixing in Overt
Installation of Lining Gantry at North Portal
NavayugaQuazigund Expressway Private Limited.
Four Laning of NH‐1A from Banihal to Quazigund to Banihal Section of Jammu & Kashmir, India
Monthly Progress Report – June 2014 39
Box Culvert at Km. Ch. 204.188
South Portal Cut and Cover Tube 1
‐‐END OF REPORT‐‐