Minor Mineral Ordinary Sand Mine (Prposed Project) Village : Dethali, Taluka : Siddhpur, Dist. Patan (Gujarat) Production Capacity : 1,00,000 TPA Area : 06-03-41 Ha Proposal For Environmental Clearance (Category "B" Under item 1 (a), of EIA Notification dated 14.09.06 and its subsequent amentdments and as per Office Memorandum No. L-110011/47/2011-IA.II (M) dated 26.06.2012 Proponent Vedant Enterprise At : Dethali, Sr. No. 85, 116, 123 Ne lagu, Block No. 01 Saraswati Nadi Patt Paiky, Taluka : Siddhpur, Dist. Patan Mo :- +91 9824218590

Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Embed Size (px)

Citation preview

Page 1: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Minor Mineral Ordinary Sand Mine

(Prposed Project)

Village : Dethali, Taluka : Siddhpur, Dist. Patan (Gujarat)

Production Capacity : 1,00,000 TPA

Area : 06-03-41 Ha

Proposal

For

Environmental Clearance

(Category "B" Under item 1 (a), of EIA Notification dated 14.09.06and its subsequent amentdments and as per

Office Memorandum No. L-110011/47/2011-IA.II (M) dated 26.06.2012

Proponent

Vedant EnterpriseAt : Dethali, Sr. No. 85, 116, 123 Ne lagu, Block No. 01 Saraswati

Nadi Patt Paiky,

Taluka : Siddhpur, Dist. Patan

Mo :- +91 9824218590

Page 2: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Vedant Enterprise

Gundikhad, Barot Vas,

Visnagar,

Dist. : Mehsana.

Date :- 17-01-2016

To,

Assistant Geologist,

Geology and Mining Dept.,

Collector Offices,

Patan.

Sub :- Application for Environmental Clearance Certificate (Ec.)

Respected Sir,

As per the guideline of Hon'ble Supreme court of india, it is compulsory to getEc. to do mining activities. I the applicant Vedant Enterprise got a L.O.I. of mineralOrdinary Sand on Saraswati Nadi Patt Paiky, Sr. No. 85, 116, 123 Ne lagu,Block No. 01 of area 06-03-41 Ha. at Village : Dethali, Taluka : Siddhpur,Dist. Patan from collector Patan. I am submitting the application for EC. in prescribeform and format.

Your Thanking

(Vedant Enterprise)

Submissions :-

(1) Request letter to MS SEAC Gujarat.

(A) Form - 1

(B) Pre-feasibility Report

(C) Project Details-Minor Minerals (Ordinary Sand)

Page 3: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Vedant EnterpriseAt : Dethali, Ta: Patan, Dist : Patan (Gujarat)

_________________________________________________________

Date :- 17-01-2016

To,Respected,Member Secretary,S.E.A.C.,Paryavaran Bhavan,Sec., 10/A,Gandhingar.

Sub :- To issue the Environmental clearance Certificate for minor mineral

quarry lease of "Ordinary Sand" mining project as per the EIA

Notification of 14-Sep.-2006.

Sir,

I, the applicant Vedant Enterprise has been granted a L.O.I. of lease of

minor mineral “Ordinary Sand” by the Collector, Patan (Gujarat) on Sarasvati

Nadi Patt Paiky, Sr. No. 85, 116, 123 Ne laug, Block No. 01 of Vill : Dethali,

Ta : Patan, Dist. Patan, Gujarat for the lease area of 06-03-41 Ha.

According to the direction of Honourable Supreme Court of India,

MoEF’s OM dt. 18th May 2012 and latest amendment of the EIA Notification

on 9th September 2013, environmental clearance is required to be obtained for

our mining project.

You are well aware that the last term of the S.E.A.C. and S.E.I.A.A. for

Gujarat State is already expired in July, 2013 and presently there is no

S.E.A.C. and S.E.I.A.A. for Gujarat State. Kindly note that in absence of

S.E.A.C. and S.E.I.A.A. for the Gujarat State, previous secretariat of S.E.A.C.

Page 4: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

and S.E.I.A.A. located at Gujarat Pollution Control Board (GPCB) has stopped

accepting all kind of environmental clearance applications.

Para 4 (iii) of the EIA Notification, 2006, states that “In the absence ofa duly constituted SEIAA or SEAC, a Category ‘B’ project shall beconsidered at the Central Level as a Category ‘B’ project”. In view of this

provision, though our project falls under B category project, we are required to

submit our application at the central level Expert Appraisal Committee for

consideration. It may be noted that the District Collectorate is neither granting

new lease nor renewing the existing lease for want of environmental

clearance. Due to this, we are unable to continue mining operations and

losing our only source of income and livelihood.

In consideration of above, we humbly request you to accept our

application to accord environmental clearance at the earliest.

Annexures :-

(A) Form No. 1.

(B) Pre-feasibility Report.

(C) Project Details of river bed sand mining.

Your thanking

(Vedant Enterprise)

Page 5: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

(A)

FORM -1

Page 6: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

FROM 1 (Application for Environment Clearance Certificate)

Sr.No.

Item Details

1 Name of the Project River Sand Mining Project ofVedant EnterpriseAt Village : Dethali, Taluka : Patan,Dist : Patan (Gujarat)

2 S. No in schedule 1(a)

As per Gazette Notification dated 14thSeptember 2006 and as per the recentdirective of Hon'ble Supreme Court of Indiain the matter Deepak Kumar etc. Vs. State ofHaryana & Office Memorandum of Ministryof Environment & Forests dt. 18.05.2012 hasmade the Environmental Clearancemandatory for minor minerals having leasearea less than 5 ha. Further Ministry ofEnvironment & Forests has recommendedguidelines for consideration of the project bythe respective State Environment ImpactAssessment Authorities (SEIAA) foraccording Environmental Clearance. OfficeMemorandum is enclosed as Annexure-1

3 Proposedcapacity/area/length/tonnage tobe handled/commandarea/lease area/number of wellto be drilled

S.No. Proposed Capacity Area1. 1,00,000 (One

Lacs) TPA(Maximum)

06-03-41 Ha

4 New/expansion/modernization It is a Proposed Project , matter is pending incollector for grant order as Annexure-2

5 Existing capacity/area etc. The Production capacity of proposed projectwould be 1,00,000 (One Lacs)TPA(Maximum)Lease Area : 06-03-41 Ha.

6 Category of project i.e. “A” or“B”

"B" Category under S .No. 1(a)As per Gazette Notification dated 14thSeptember 2006 and as per the recentdirective of Hon'ble Supreme Court of Indiain the matter Deepak Kumar etc. Vs. State ofHaryana & Office Memorandum of Ministryof Environment & Forests dt. 18.05.2012 hasmade the Environmental Clearancemandatory for minor minerals having leasearea less than 5 ha. Further Ministry ofEnvironment & Forests has recommendedguidelines for consideration of the project bythe respective State Environment ImpactAssessment Authorities (SEIAA) for

Page 7: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

according Environmental Clearance.7 Does it attract the general

condition? If yes please specifyNo, it does not attract the general Condition.

8 Does it attract the specificcondition? If yes please specify

No, it does not attract the Specific Condition.

9 Location The lease area of Ordinary Sand situatednear village : Dethali, Ta.: Patan, Dist :Patan (Gujarat) The geographical location ofthe mine is as under :-

Latitude (N) Longitude (E)23°53'53.43"N 72°18'3.79"E

Plot/Survey/Khasra No Sarasvati Nadi Patt Paiky, Sr. No. 85, 116,123 Ne lagu, Block No. 01.

Village DethaliTehsil PatanDistrict PatanState Gujarat

10 Nearest railway station/airportalong with distance in Kms.

S.No.

Particulars Name Distance(FromLeaseboundary)

1 Nearestrailwaystation

Siddhpur 7.06 km.

2 NearestAirport

Mahesana 33.25km

11 Nearest town, city, districtheadquarter along withdistance in Kms.

S.No.

Particulars Name Distance(FromLeaseboundary)

1 NearestTown

Siddhpur 6.99 km

2 Nearest City Siddhpur 6.99 km3 Nearest

DistrictHeadquarter

Patan 18.61 km

12 Village Panchayat, ZilaParishad, MunicipalCorporation, local body(Complete postal address withtelephone nos to be given)

VillagePanchayat

Dethali GramPanchayat

1.91 km

ZillaPanchayat

Patan DistrictPanchayat

18.61 km

Nagarpalika Siddhpur 6.99 kmPostalAddresswithtelephoneNo.

Vedant EnterpriseGundikhad, Barot Vas,Visnagar,Dist : Mehsana.Tel :- 9824218590

Page 8: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

13 Name of the applicant Vedant Enterprise14 Registered address Vedant Enterprise

Gundikhad, Barot Vas,Visnagar,Dist : Mehsana.Tel :- 9824218590

15 Address for correspondence Vedant EnterpriseGundikhad, Barot Vas,Visnagar,Dist : Mehsana.Tel :- 9824218590

Name Vedant EnterpriseDesignation OwnerAddress Vedant Enterprise

Gundikhad, Barot Vas,Visnagar,Dist : Mehsana.Tel :- 9824218590

Pin codeE-mail [email protected] 09824218590Fax No --

16 Details of alternative sitesexamined, if any. Location ofthese sites should be shown ona topo sheet

No. Mineral river sand is naturally occurringresource and this is a site specific projectHence no alternative can be chosen.

17 Interlinked Project N.A.18 Whether separate application

for interlinked project has beensubmitted?

N.A.

19 If yes date of submission N.A.20 If no reason N.A.21 Whether the proposal involves

approval/ clearance under: ifyes, details of the same andtheir status to be given.

No

The Forest (Conservation) Act,1980?

There is no reserve orprotected forest within 10.00km periphery of lease area.

N.A.

The Wildlife (Protection) Act,1972?

There is no Wildlife sanctuarywithin 10.00 km periphery of

N.A.

Page 9: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

1. Construction, operation or decommissioning of the project involving actions, which willcause physical changes in the locality (topography, land use, changes in water bodies,etc)

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever possiblewith source of information of data

1.1 Permanent or temporarychange in land use, landcover or topographyincluding increase inintensity of land use (withrespect to local land useplan)

Yes Land USE :-The land use classification as perrevenue record is Govt. River Bedland. Due to mining activates therewill be slightly changes intopographical features becauseproposed mining confined to riverbed only, no other area disturbedexcept some mineral is stacked atearmarked site of surface. Area iscovered with water flow sand. Therewould be temporarily change intopography but river itselfreplenishes with sediment carriedduring monsoon season.

1.2 Clearance of existing land,vegetation and buildings?

Yes lease area is river bed area so thereis no clearance of vegetation andbuildings.

1.3 Creation of new land uses? Yes N.A.

lease area

Eco-Sensitivity zone within10.00 km periphery of leasearea

N.A.

The C.R.Z. Notification, 1991? There is no C.R.Z. within 10.00 km peripheryof lease area.

22 Whether there is anyGovernment order/policyrelevant/ relating to site

L.O.I. of collector Patan is issued on date 30-05-2014 and order no. is AGP/QL/Block/Dethali/334/I.P./2014/1443.

23 Forest Land involved? N.A.24 Whether there is any litigation

pending against the projectand / or land in which theproject is propose to be set upName of courtCase noOrder/directions of the court,if any and its relevance withthe proposed project.

Matter is pending for grant order in collectorand no other litigation is pending in the anycourt of law as per our best knowledge.

25 Expected cost of the project Rs. 3,00,000

Page 10: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever possiblewith source of information of data

1.4 Pre-constructioninvestigations e.g. boreholes, soil testing?

No N.A.

1.5 Construction works? No There will be not any significantconstruction activities.

1.6 Demolition works? No N.A.1.7 Temporary sites used for

construction works orhousing of constructionworkers?

No Local people will employed so onlytemporary rest shelter and toiletfacility is constructed at the mine siteon 0.0030 ha.

1.8 Above ground buildings,structures or earthworksincluding linear structures,cut and fill or excavations

Yes There will be not any significantconstruction activity except forworkers rest room and urinal facility.

1.9 Underground works includingmining or tunneling?

No There will be no undergroundworking since the proposal is foropencast mining activities only.

1.10 Reclamation works? No No reclamation measures will beadopted at site except leveling ofriver bed alter achieving UPL of 3mtrfrom river bed level. River itselfreplenishes with sediment carriedduring monsoon season.

1.11 Dredging? No Mining will not proposed inunderwater so no requirement ofdredging at all.

1.12 Offshore Structures? No Not applicable

1.13 Production andmanufacturingprocesses?

Yes @ 1,00,000 (One Lacs)TPA(Maximum)

1.14 Facilities for storage ofgoods or materials?

No N.A.

1.15 Facilities for treatment ordisposal of solid waste orliquid effluents?

Yes Nature of Waste : No wastegenerated at all except some amountof top soil in the from of alluvium willcome out. Disposal : Top soil isbeing stacked separately. A 8.0 mbuffer zone is left along riparianzone.

1.16 Facilities for long termhousing of operationalworkers?

No There will be not needed to providehousing within the lease area as thelocal persons will be givenemployment.

Page 11: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever possiblewith source of information of data

1.17 New road, rail or sea trafficduring construction oroperation?

No N.A.

1.18 New road, rail, airwaterborne or other transportinfrastructure including newor altered routes andstations, ports, airports etc?

No N.A.

1.19 Closure or diversion ofexisting transport routes orinfrastructure leading tochanges in trafficmovements?

No Not applicable

1.20 New or diverted transmissionlines or pipelines?

No Not applicable

1.21 Impoundment, damming,culverting, realignment orother changes to thehydrology of watercourses oraquifers?

No Not applicable

1.22 Stream crossings? No Not applicable1.23 Abstraction or transfers of

water form ground or surfacewaters?

Yes The daily water demand is only 3.0KLD. The domestic water demand ismet from the village panchayatDethali through tanker supply. Thelevel of ground water table is of thearea is about 40 m (in rainy season)to 60 m (in dry season). Thus,ground water table is notencountering during working in themine.

1.24 Changes in water bodies or No During mining no alteration or

Page 12: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever possiblewith source of information of data

the land surface affectingdrainage or run-off?

changes in the passage route ofriver.

1.25 Transport of personnel ormaterials for construction,operation ordecommissioning?

Yes Minerals River Sand will betransported in tractors & trucks byroad to consumers. Workers willcome from nearby villages on theirconvenience.

1.26 Long-term dismantling ordecommissioning orrestoration works?

Yes Whenever achieving 3mtr BGI, fromriver bed level, mining will not do atall. In restoration/reclamationprogramme, after 3 mt miningprovision of levelling or grading ofriver bed will be taken. River itselfcarried huge amount of sedimentduring every monsoon season sothere is no reclamation measuresproposed at mine site.

1.27 Ongoing activity duringdecommissioning whichcould have an impact on theenvironment?

Yes In 8 mtr buffer along riparian zone isbeing planted preferred local plantspecies. It is checking riparianerosion and creating aestheticenvironment of surrounding area. Bythis project of river sand mining inthe area. river is holding morevolume of water making to ensureavailability of water in nearby area.

1.28 Influx of people to an areaeither temporarily orpermanently?

No Impact is insignificant, as the localpeople are provided employment.About 10 local peoples are gettingemployment from this project.

1.29 Introduction of alien species? No Not applicable1.30 Loss of native species or

genetic diversity?No N.A.

1.31 Any other actions? No Not applicable2. Use of Natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short supply):

Sr.No

Information/Checklistconfirmation

Yes/No?

Details are there withapproximate quantity/rate ,wherever possible with sourceof information data

2.1 Land especially undeveloped oragricultural land (ha)

No The mining lease area is Govt.River bed area (Sarasvati NadiPatt Paiky).

2.2 Water (expected source &competing users) unit: KLD

Yes The daily water demand is only3.0 KLD. The domestic water

Page 13: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No

Information/Checklistconfirmation

Yes/No?

Details are there withapproximate quantity/rate ,wherever possible with sourceof information datademand is met from the villageDethali.

2.3 Minerals (MT) Yes River Sand @ 1,00,000 (OneLacs)TPA.

2.4 Construction material - stone,aggregates, sand / soil (expectedsource, MT)

No N.A.

2.5 Forests and timber (source, MT) No Not applicable2.6 Energy including electricity and

fuels (source, competing users) unit:fuel (MT), energy (MW)

Yes Presently there is no electricpower at mine. Diesel will beused on an average 10 LPD.Source Nearest Pump / Depot.

2.7 Any other natural resources (useappropriate standard units)

No Not applicable

3. Use, storage, transport, handling or production of substances or materials, which could beharmful to human health or the environment or raise concerns about actual or perceivedrisks to human health.

Sr.No.

Information / Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever possiblewith source of information of data

3.1 Use of substances or materials,which are hazardous (as perMSIHC rules) to human healthor the environment (flora,fauna, and water supplies)

No N.A.

3.2 Changes in occurrence ofdisease or affect diseasevectors (e.g. insect or waterborne diseases)

No The proposed mining project will notaffect in occurrence of disease due totransport, handing or production ofmineral / Ordinary Sand.

3.3 Affect the welfare of people e.g.by changing living conditions?

No The proposed project will provideOrdinary Sand for the end use in thelocal region and is not affecting thewelfare of people due to use, storage,transport, handling or production ofthe mineral.

3.4 Vulnerable groups of peoplewho could be affected by theproject e.g. hospital patients,children, the elderly etc.,

No The proposed project will not beharmful for the vulnerable groups ofthe people due to storage, transport,handling or production of the mineral.

3.5 Any other causes No None

Page 14: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

4. Production of solid wastes during construction or operation or decommissioning(MT/month)

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details there of with approximatequantity/rate wherever applicablewith source of information ofdata

4.1 Soil, overburden or mine wastes Yes Waste comprises of some amountof top soil occurring as alluvium.

4.2 Municipal waste (domestic andor commercial wastes)

No N.A.

4.3 Hazardous wastes (as perHazardous Waste ManagementRules)

No N.A.

4.4 Other industrial process wastes No Not applicable4.5 Surplus product No No surplus product will generate4.6 Sewage sludge or other sludge

from effluent treatmentNo N.A.

4.7 Construction or demolitionwastes

No Not Applicable

4.8 Redundant machinery orequipment

No There will be no redundantmachinery or equipment.

4.9 Contaminated soils or othermaterials

No Not Applicable

4.10 Agricultural wastes? No Not Applicable4.11 Other solid wastes? No N.A.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (kg/hr)

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details there of with approximatequantity/rate wherever applicable withsource of information of data

5.1 Emissions fromcombustion of fossil fuelsfrom stationary or mobilesources

Yes Mobile sources like diesel equipments usedin the process generate gaseous emission,however it is insignificant as the use of fuelis not be considerable. Proper maintenanceof vehicles, loading equipments andmachineries reduce the dieselconsumption and thereby emissions.Source Mitigation MeasuresMobilesourceslike dieselequipments

• Regular maintenance ofequipments• Proper calibration of fuelinjection pumps.• Proper air / fuel ratio• Timely changing of filters(fuel/oil)• Proper maintenance ofsilencers/mufflers

5.2 Emissions fromproduction processes

No N.A.

Page 15: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details there of with approximatequantity/rate wherever applicable withsource of information of data

5.3 Emissions from materialshandling includingstorage or transport

No There will be fugitive emissions generatingduring material handling transportation,loading and unloading etc.Transportation :-Movement of vehicles like dumper truckstankers etc. will generate dust particles.Regular water sprinkling on haul road willbe suppressing the dust particles andprevent them from getting air-borne.Loading :-Dust emission will be generating as thematerial will be loaded into dumpers byloader.

5.4 Emissions fromconstruction activitiesincluding plant andequipment

No There will not be any significantconstruction activities except for workersrest room and office.

5.5 Dust or odours fromhandling of materialsincluding constructionmaterials, sewage andwaste

No Only dust due to transportation and loadingof Ordinary Sand. The dust emission will becontrolled by adopting suitable measuresviz. Water sprinkling, plantation, makingenclosures & maintaining roads.

5.6 Emissions fromincineration of waste

No Not Applicable

5.7 Emissions from burningof waste in open air (e.g.slash materials,construction debris)

No Not Applicable

5.8 Emissions from any othersources

No Not Applicable

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever applicablewith source of information of data

Page 16: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

6.1 From operation ofequipment e.g. engines,ventilation plant, crushers

Yes Noise will be generated duringoperation of Diesel engine of vehicles.

Mitigation Measures :- The followingmeasures are adopted to control thenoise and vibration:» Proper and regular maintenance ofmachinery» Earmuffs and earplugs are provided» Periodical medical checkup is beingconducted. P.P.E. like earmuffs areprovided to the persons exposed tonoise levels.» Measures is being taken to containnoise levels up to 75 dB(A)

6.2 From industrial or similarprocesses

No Not Applicable

6.3 From construction ordemolition

No Not Applicable

6.4 From blasting or piling No N.A.6.5 From construction or

operational trafficNo There will be no construction proposed

at mine. Only mining of mineral will bebeing carried out.

6.6 From lighting or coolingsystems

No Proposed mining will be open castthus emission of light and heat will benegligible. All the mining operation isbeing done in day only. No coolingsystem will be required.

6.7 From any other sources No Not Applicable7. Risks of contamination of land or water from releases of pollutants into the

ground or into sewers, surface waters, groundwater, coastal waters or thesea

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever applicablewith source of information of data

7.1 From handling, storage, use orspillage of hazardous materials

No The proposed mine will not beinvolved handling, storage and useof hazardous materials.

7.2 From discharge of sewage orother effluents to water or theland (expected mode and placeof discharge)

No There will be no risk of contaminationof land and water due to discharge ofuntreated waste water. However, nountreated sewage will be to bedischarged in the open land causingthe contamination to ground water.The waste water generated is treatedin the septic tank followed by soakpit.

7.3 By deposition of pollutantsemitted to air into the land or

Yes During operation phase there will beemissions generate from loading and

Page 17: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No.

Information/Checklistconfirmation

Yes/No?

Details are there with approximatequantity/rate wherever applicablewith source of information of data

into water unloading and mineral handling,transportation and mobile sources.Dust generation will be controlled bywater sprinkling. Hence, no risk ofcontamination of air, water will beenvisaged.

7.4 From any other sources No There will not be any other sources,which will contaminate land andwater resources.

7.5 Is there a risk of long term buildup of pollutants in theenvironment from thesesources?

No Not Applicable.

8. Risk of accidents during construction or operation of the Project, whichcould affect human health or the environment

Sr.No.

Information/Checklistconfirmation

Yes/No? Details are there withapproximate quantity/ratewherever applicable withsource of information of data

8.1 From explosions, spillages,fires etc from storage,handling, use or production ofhazardous substances

No N.A.

8.2 From any other causes No N.A.8.3 Could the project be affected

by natural disasters causingenvironmental damage e.g.floods, earthquakes,landslides, cloudburst etc)?

No The project is located in seismiczone-IV. There is no flood.cloudburst and landslide reportedso far. Seismic zone map.

9. Factors which should be considered (such as consequential development)which could lead to environmental effects or the potential for cumulativeimpacts with other existing or planned activities in the locality

Sr.No.

Information/Checklistconfirmation

Yes/No? Details are there withapproximate quantity/ratewherever applicable withsource of information of data

Page 18: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No.

Information/Checklistconfirmation

Yes/No? Details are there withapproximate quantity/ratewherever applicable withsource of information of data

9.1 Lead to development ofsupporting. Facilities , ancillarydevelopment or developmentstimulated by the project whichcould have impact on theenvironment e.g.: supportinginfrastructure (roads, powersupply, waste or waste watertreatment, etc.) housingdevelopment extractiveindustries supply industries,(other)

Yes Roads and transport facility willimproved due to frequentlyavailable of mine vehicles.Project proponent will organiseregular medical checkup campsand recreational activities.Employment to local people will begenerated.Overall living standard of nearbypeople will have positive impact.

9.2 Lead to after-use of the site,which could have an impact onthe environment

Yes The mining activities will havepositive impact if environmentmeasures are effectivelyimplemented. Greenbelt alongriparian zone of 8.0 mtr. will havepositive impact on surroundingenvironment.

9.3 Set a precedent for laterdevelopments

Yes Mining of mineral is proposed withrated capacity of @ 1,00,000 (OneLacs) TPA and to obtain this,loading of mineral by manual.Proposed green belt developmentwill help in increasing theaesthetic beauty of the area.

9.4 Have cumulative effects due toproximity to other Existing orplanned projects with similareffects

No The area will be free from anydisturbances. There will not beany industries or developmentprojects in its close proximity.

10. Environmental SensitivitySr.No

Area Name /identity

Aerial distance (within 10 km)from proposed location boundary

1 Areas protected under

international conventions,

national or local legislation for

their ecological, landscape,

cultural or other related value

None Not Applicable

2 Areas which are important or

sensitive for ecological

reasons - Wetlands,

No Not Applicable

Page 19: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No

Area Name /identity

Aerial distance (within 10 km)from proposed location boundary

watercourses or other water

bodies, coastal zone,

biospheres, mountains, forests

3 Areas used by protected,

important or sensitive species

of flora or fauna for breeding,

nesting, foraging, resting, over

wintering, migration

No. Not Applicable

4 Inland, coastal, marine or

underground waters

No Not Applicable

5 State, National boundary No Not Applicable

6 Routes or facilities used by the

public for access to recreation

or other tourist, pilgrim areas

No Not Applicable

7 Defense installations No Not Applicable

8 Densely populated or built-up

area

Yes Nearest village Dethali (Population

1200) is about 1.91 km.

9 Areas occupied by sensitive

man-made land uses

(hospitals, schools, places of

worship, community facilities)

Yea All facilities are available at city

Siddhpur which is 6.99 km away

from lease area.

10 Areas containing important,high quality or scarceresources (ground waterresources, surface resources,forestry, agriculture, fisheries,tourism, minerals)

Yes

Mineral Resources : Ordinary Sandis abundantly available in this area.

Forest Resources : There is noreserve or protected forests in 10km radius area.Water Resources :Mostly Surface water bodies(Seasonal) & ground water is themajor source of water in this region.Water table is 15 m to 20 m duringpre monsoon and post monsoonperiod respectively. Ultimateworking level is above the water

Page 20: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Sr.No

Area Name /identity

Aerial distance (within 10 km)from proposed location boundarytable hence will not intersect.

Agricultural Resources :Major occupation is agriculture inthis region.

11 Areas already subjected topollution or environmentaldamage. (those where existinglegal environmental standardsare exceeded)

No None

12 Areas susceptible to naturalhazard which could cause theproject to presentenvironmental problems(earthquakes, subsidence,landslides, erosion, flooding orextreme or adverse climaticconditions)

Yes The water level in river mayfluctuate depending on the rainfallintensity.According to BMTPC VulnerabilityAtlas (earthquake), the study areafalls in a Zone-IV.There is no incidence of landslidebut in 2001 a major incidence ofearth quake was there.There is no date available floodingof the area.

(IV).Proposed Terms of Reference for EIA studies

We commit to undertake only controlled blasting for minimizing noise and vibration from

blasting operation. We request you to consider our project as B2 category project looking to

tiny scale of our project and negligible potential of environmental impacts.

“I hereby given undertake that the data and information given in the application and

enclosures are true to the best of my knowledge and belief and I am aware that if any part of

the data and information submitted is found to be false or misleading at any stage, the

project will be rejected and clearance given, if any project will be revoked at our risk and

cost.”

Date :- 17-01-2016

Place :- Patan

Signature of the applicant

(Vedant Enterprise)

Page 21: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

At Village : Dethali,

Ta : Siddhpur,

Dist : Patan.

(Project Proponent/Authorised Signatory)

Page 22: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

NOTE :

1. The projects involving clearance under Coastal Regulation Zone Notification.

1991 shall submit with the application a C.R.Z. map duly demarcated by one

of the authorized agencies. showing the project activates, w.r.t. C.R.Z. (at the

stage of TOR) and the recommendations of the State Coastal Zone

Management Authority (at the stage of EC). Simultaneous action shall also be

taken to obtain the requisite clearance under the provisions of the C.R.Z.

Notification, 1991 for the activites to be located in the CRZ.

2. The projects to be located within 10 km of national Parks. Sanctuaries.

Biosphere Reserves, Migratory Corridors of Wild Animals, the project

proponent shall submit the map duly authenticated by Chief Wildlife Warden

showing these features vis-à-vis the project location and the

recommendations or comments of the Chief Wildlife Warden thereon (at the

stage of EC)".

3. All correspondence with the Ministry of Environment & Forests including

submission of application for TOR/Environmental Clearance, subsequent

clarification, as may be required from time to time, participation in the EAC

Meeting on behalf of the project proponent shall be made by the authorized

signatory only. The authorized signatory should also submit a document in

support of his claim of being an authorized signatory for the specific project".

Page 23: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Annexure-1

Page 24: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got
Page 25: Vedant Enterprise - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/EC/FORM_1/17012016...Ec. to do mining activities. I the applicant Vedant Enterprise got

Annexure-2