Upload
khangminh22
View
2
Download
0
Embed Size (px)
Citation preview
Environmental Monitoring Report
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 43464-027February 2021
Period: July 2020 – December 2020
India: Himachal Pradesh Clean Energy Transmission Investment Program - Tranche 3
Submitted by Himachal Pradesh Power Transmission Corporation Limited (HPPTCL)
Environmental Monitoring Report
Project Number: 43464-026
Loan No. 3733-IND
Reporting Period: July to Dec, 2020
January, 2021
India: Himachal Pradesh Clean Energy Transmission Investment Program
Tranche–III
Prepared by H.P. Power Transmission Corporation Limited (HPPTCL)
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 2 of 110
Table of Contents
A. INTRODUCTION ............................................................................................................................. 4
B. PROJECT DESCRIPTION ............................................................................................................... 4
C. PROJECT PROGRESS STATUS ..................................................................................................... 8
D. COMPLIANCE STATUS WITH NATIONAL/STATE/LOCAL STATUTORY ENVIRONMENTAL REQUIREMENTS ......................................................................................... 9
E. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED IN THE LOAN AGREEMENT ...................................................................................................... 12
F. ENVIRONMENTAL MANAGEMENT PLAN (EMP) IMPLEMENTATION COMPLIANCE STATUS DURING THE REPORTING PERIOD .......................................................................... 15
G. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES .................................... 27
H. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURING IMPLEMENTATION, WHICH WERE NOT COVERED EARLIER DURING ENVIRONMENTAL ASSESSMENT OF THE PROJECT. .......................................................... 29
I. DETAILS OF GRIEVANCE REDRESSAL COMMITTEE AND COMPLAINTS RECEIVED FROM PUBLIC AND ACTIONS TAKEN THEREOF TO RESOLVE ........................................ 29
J. PUBLIC CONSULTATION PUBLIC CONSULTATION DURING PROJECT IMPLEMENTATION FOR THE REPORTING PERIOD ............................................................. 30
K. INSTITUTIONAL SET-UP FOR EMP IMPLEMENTATION ...................................................... 30
ANNEXURES ......................................................................................................... 32
Annexure-I: - Physical Progress Photographs of Sub-project Sites ............................................................ 33
Annexure-II: - Copy of Final Forest Clearance of Bagipul- Kotla Transmission Line .............................. 37
Annexure III-: - Copy of Forest Clearance Lahal Rajera (Chamera) Transmission Line ........................... 39
Annexure-IV: - Copy of Forest Clearance Bajoli Holi to Lahal Transmission Line .................................. 41
Annexure-V: - Copy of Forest Clearance Mazra Karian Transmission Line ............................................. 43
Annexure-VI: - Copy of Forest Clearance Mazra Substation ..................................................................... 46
Annexure-VII: - Copy of Land Transfer for Hatkoti Substation ................................................................ 48
Annexure-VIII: - Copy of Forest Clearance for 33/132kV GIS at Barshaini ............................................. 49
Annexure-IX: - Copy of Forest Clearance Barshaini-Charor Transmission Line ...................................... 51
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 3 of 110
Annexure-X: - Copy of Forest Clearance of 132kV LILO Kurtha- Bathri (132 kV) D/C Transmission Line to proposed 33/132/220 kV GIS substation Mazra at Pukhari ........................................................... 53
Annexure-XI: Sample Photographs of Health & Safety related awareness and other good practices in the sub-project sites .......................................................................................................................................... 55
Annexure-XII: Status of Muck Disposal .................................................................................................... 62
Annexure-XIII: Photographs showing status of labor camp facilities ........................................................ 64
Annexure-XIV: Sample copies of Advance Notices served to Community for temporary outage of electricity due to shut down operations ....................................................................................................... 67
Annexure-XV: HPPTCL’s Health and Safety Plan in response to Covid-19, pandemic ............................ 68
Annexure-XVI: - Results of Air, Noise, Water and Soil Quality Monitoring ............................................ 77
Annexure-XVII: - Grievance Redressal Committee ................................................................................. 109
Annexure-XVIII: - Environment & Social Monitoring Cell (ESC) of HPPTCL ..................................... 110
List of Abbreviations and Colloquial Terms Used
ADB Asian Development Bank AP’s Affected Persons C/o Construction of Distt. District Dept Department EHV Extra High Voltage ESSP Environment and Social Safeguards Policy of HPPTCL FCA Forest Conservation Act FRA Forest Right Act,2006 GIS Gas Insulated Switchgear GOI Government of India GRC Grievance Redress Committee Ha. Hectare (10,000 sq. m. land) NPV Net Present Value CA Compensatory Afforestation HPPTCL H.P. Power Transmission Corporation Ltd. IE Rule Indian Electricity Rule INR Indian Rupee NPV Net Present Value MPAF Main Project Affected Family MoEF&CC Ministry of Environment, Forest and Climate Change Pvt. Land Private Land PIU Project Implementing Unit RRRCP Resettlement, Relief, Rehabilitation and Compensation Policy of HPPTCL RoW Right of Way
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 4 of 110
A. INTRODUCTION
1. Himachal Pradesh is a mountainous State in Northern India with a population of slightly over 6 million, has abundant water resources in the five major rivers flowing through the state from the western Himalayas. The hydropower generation potential of Himachal Pradesh is about 27436 MW, which is about one-fourth of the total hydropower potential of India. In its Hydropower Policy (2007), the Government of Himachal Pradesh (GoHP) targets its comparative advantage in hydropower with the goal to become the "Hydropower State" of the Country.
2. For improvement/ strengthening of existing infrastructures and addition of new infrastructure for effective power evacuation, the Government of Himachal Pradesh (GoHP) through the Government of India (GoI), has requested the Asian Development Bank (ADB) for a Multi-Tranche Financing Facility (MFF) to provide financial assistance to the power sector investment program in the State. The investment program covers investments for transmission of clean energy to National Grid of India by construction of pooling substations and EHV transmission lines. To implement this activity, Himachal Pradesh Government has established HP Power Transmission Corporation Limited (HPPTCL) vide HP Government Notification No.: MPP-A (1)-4/2006-Loose dated 11th September 2008 as the State Transmission Utility (STU) and HPPTCL was declared as the State Transmission Utility (STU) vide notification no. MPP-A (3)-1/2001-IV dated 10th June 2010.
3. The Himachal Pradesh Clean Energy Transmission Investment Program (HPCETIP) is a $350 million multi tranche financing facility (MFF) from the Asian Development Bank (ADB), which will contribute to economic development in Himachal Pradesh through expanded power supplies from clean energy sources, and support a sustainable electricity sector in the state. HPCETIP will produce the following outcomes: (i) increase availability of clean energy downstream at pooling stations for effective power evacuation in a financially sustainable manner, (ii) improve state finances and power sector financial viability from sales revenue earned from power exports, (iii) improve sector governance, (iv) improve capacity in HP Power Transmission Corporation Limited (HPPTCL) for better planning, implementation and management of power evacuation infrastructure, and energy efficiency, and (v) improvement in implementation standards of environmental and social safeguards in the sector. With ADB support, the proposed program will sustain the energy sector reform agenda, and is expected to help attract other long-term financiers to the State.
B. PROJECT DESCRIPTION
4. The Tranche-III subprojects are located in Kullu, Chamba and Shimla districts of Himachal Pradesh. The Tranche-III components of the Himachal Pradesh Clean Energy Transmission Project include construction of Power Transmission Lines & Sub-stations. Details of sub-
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 5 of 110
projects including scope of the work under loan 3733-IND (Tranche-III) are provided in following Table-1.0. Figure-1.0 shows the indicative location of the transmission lines and the substations under Tranche-III sub-projects.
Table-1.0: Details of the Subprojects of Tranche-III
S. No.
Sub-Project Description Components of the Sub-Project
Name of the Contractor
Contract Signing Date
Contract Closing Date
1 66/22 kV GIS Substation station at Baghipul
22/66 kV Transformer, 250 kVA, 22 / 0.433 kV LT Transformer;
66kV GIS, 5 Bays, 3 Future
M/s Kanohar Electricals Ltd.
29-03-2019 23-04-2021
2 66 kV DC Line from Baghipul To kotla.
66kV D/C Transmission Line
Line Length-23 Km
Towers -74
M/s Man Structure limited
23-01-2019 20-02-2021
3 400 kV D/C (Twin MOOSE) from 400/220 kV,2x315 MVA Lahal GISS to 400 kV Chamera (Rajera) pooling station of PGCIL
400kV D/C Transmission Line
Line Length-35.31 Km
Towers-112
M/S
Apar Industries
21-05-2018 30-09-2021
4 220 kV D/c Line (Twin Moose) from Bhajoli Holi to HEP to 400/220 kV Lahal GISS
220kV D/C Transmission Line
Line Length- 18.340 Km
Towers-59
M/S
Apar Industries
26-12-2017 31-12-2020
5 220 kV D/C line from Mazra to Karian
220kV D/C Transmission Line
Line Length- 17.45 Km
Towers-52
M/S R.S. Infra Projects Ltd.
28-01-2019 25-02-2021
6 132/220 kV,2x80/100 MVA GISS at Mazra.
80/100 MV Transformers-2 No
M/s TBEA Energy (India) Pvt. Limited & TBEA Zonfa Shanghai, China
18-07-2019 15-08-2021
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 6 of 110
S. No.
Sub-Project Description Components of the Sub-Project
Name of the Contractor
Contract Signing Date
Contract Closing Date
7 220kV GIS Switching Station at Hatkoti.
220kV GIS Sub-Station
M/s GE T&D India Ltd.
04-12-2018 30-06-2021
8 33/132 kV Substation Barshaini
33/132kV GIS Sub-Station.
2x31.5 MVA, 3-Phase Transformer.
M/s GE T&D India Ltd.
04-12-2018 30-06-2021
9 132 kV D/c transmission Line from Barshaini to Charor
132kV D/C Transmission Line
Line Length- 37.230 Km
Towers-144
M/S Salasar Techno Engineering Ltd.
15-02-2018 06-07-2020
Additional scope of works
10 Augmentation of existing 220/132 kV Kangoo Sub Station and stringing of 2nd circuit of 220 kV S/C line (3.2 Km) on D/C Towers from Dehar Power House of BBMB to Kangoo sub-station in Mandi district
Augmentation of 220/132 kV Sub Station
A Circuit of 220 kV S/C line
M/s GE T&D India Limited
21-03-2020 30-08-2021
11 Construction of 2 No. AIS Bays in the existing 220/66kV Baddi substation and loop-in and loop-out (LILO) 2nd circuit of 220 kV Kunihar to Panchkula transmission line (2.5 Km) at Baddi sub-station in district Solan
2 No. AIS Bays M/s GE T&D India Limited
18-03-2020 30-03-2021
12 Construction of 66/220 kV, 80/100 MVA transformer in 400/220 kV Gumma sub-station in district Shimla
66/220kV, 80/100 MVA transformer
M/s GE T&D India Limited
21-03-2020 30-07-2021
13 LILO of 132 kV D/C Kurthala-Bathri line
132kV D/C Transmission Line
M/s RS Infra Projects
26-05-2020 22-09-2021
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 7 of 110
S. No.
Sub-Project Description Components of the Sub-Project
Name of the Contractor
Contract Signing Date
Contract Closing Date
(3.5 Km D/C) at Mazra sub-station in district Chamba
Line Length- 3.5 Km
Total Towers-31
14 Creation of a joint control and operations center for TL assets in district Solan and Sirmaur
Joint control and operations center
M/S GE T&D Ltd.
16-12-2020 15-10-2021
Figure-1.0; Indicative location of the transmission lines and the substations
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 8 of 110
C. PROJECT PROGRESS STATUS
5. Construction works of the Tranche-III (Loan No. 3733-IND) subprojects are on-going (refer Site Progress Photographs at Annexure-I). The status of overall progress and progress during the reporting period for the sub-projects under Tranche-III is provided in Table 2.0.
Table-2.0: Status of Physical Progress during the Reporting Period
S No Sub-Project Description Physical Progress Status
1 66 kV GIS Substation station at Baghipul 19 % of physical progress during the reporting period.
Total 36% up to the reporting period
2 66 kV DC Line from Baghipul to kotla 33% of physical progress during the reporting period.
Total 49% up to the reporting period
3 400 kV D/C (Twin MOOSE) from 400/220 kV,2x315 MVA Lahal GISS to 400 kV Chamera pooling station of PGCIL
17% Physical Progress during the Reporting Period.
Total 42% up to the reporting period
4 220 kV D/c Line (Twin Moose) from Bhajoli Holi to HEP to 400/220 kV Lahal GIS
39% of physical progress during the Reporting Period.
Total 79% up to the reporting period
5 220 kV D/C line from Mazra to Karian 41% Physical Progress during the Reporting Period.
Total 71% up to the reporting period
6 132/220 kV, 2x80/100 MVA GISS at Mazra
5% Physical Progress during the Reporting Period.
Total 10% up to the reporting period
7 220kV GIS Switching Station at Hatkoti. 29 % Physical Progress during the Reporting Period.
Total 49% up to the reporting period
8 33/132 kV Substation Barshaini 16% Physical Progress during the Reporting Period.
Total 51% up to the reporting period
9 132 kV D/c transmission Line from Barshaini to Charor
12% Physical Progress during the Reporting Period.
Total 44% up to the reporting period
10 Augmentation of existing 220/132 kV Kangoo Sub Station and stringing of 2nd circuit of 220 kV S/C line (3.2 Km) on D/C Towers from Dehar Power House of BBMB to Kangoo sub-station in Mandi district
Construction activities are yet to be commenced
11 Construction of 2 No. AIS Bays in the existing 220/66kV Baddi substation and
Construction activities are yet to be commenced
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 9 of 110
S No Sub-Project Description Physical Progress Status
loop-in and loop-out (LILO) 2nd circuit of 220 kV Kunihar to Panchkula TL (2.5 Km) at Baddi sub-station in district Solan
12 Construction of 66/220 kV, 80/100 MVA transformer in 400/220 kV Gumma sub-station in district Shimla
Construction activities are yet to be commenced
13 Creation of a joint control and operations center for TL assets in district Solan and Sirmaur
Construction activities are yet to be commenced
14 LILO of 132 kV D/C Kurthala Bathri line (3.5 Km D/C) at Mazra S/stn in district Chamba
Construction activities are yet to be commenced
D. COMPLIANCE STATUS WITH NATIONAL/STATE/LOCAL STATUTORY ENVIRONMENTAL REQUIREMENTS
6. Power Transmission projects have been exempted from Environmental Clearance as they are not listed in the schedule of MoEF&CC EIA Notification, 2006 and its subsequent amendments.
7. Wildlife clearance under Wildlife Protection Act, 1972 is required for the projects located within notified protected areas (Wildlife Sanctuary, National Park, etc.). As the subproject sites are not located within notified protected areas or its Eco-sensitive zone, Wildlife clearance is not required.
8. Since few subproject sites are in forest area, clearance under Forest Conservation Act, 1980 is required from MoEF&CC before starting construction activities in forest areas for sub projects located in the forest. Details of the sub-projects required forest clearance and status of clearance is provided in the Table-3.0.
Table-3.0: Status of Forest Clearance of the Sub-projects
S. No.
Sub-Project Description Forest Clearance Status Remarks, if any
1 66 kV GIS Substation station at Baghipul
Forest clearance is not required.
Private land
2 66 kV DC Line from Baghipul To kotla.
Forest Clearance has been obtained for Diversion of 36.4344 Ha.
Copy of FC Letter is enclosed as Annexure-II.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 10 of 110
S. No.
Sub-Project Description Forest Clearance Status Remarks, if any
3
400 kV D/C (Twin MOOSE) from 400/220 kV, 2x315 MVA Lahal GISS to 400 kV Rajera (Chamera) pooling station of PGCIL
Forest clearance has been obtained for Diversion of 78.8158 Ha.
Copy of FC Letter is enclosed as Annexure-III
4
220 kV D/c Line (Twin Moose) from Bhajoli Holi to HEP to 400/220 kV Lahal GIS.
Forest clearance has been obtained for Diversion of 30.6321 Ha.
Copy of FC Letter is enclosed as Annexure IV
5 220 kv D/C line from Mazra to Karian
Forest clearance has been obtained for Diversion of 43.023 Ha.
Copy of FC Letter is enclosed as Annexure V.
6 132/220 kV, 2x80/100 MVA GISS at Mazra.
Forest clearance has been obtained for Diversion of 0.8052 Ha.
Copy of FC Letter is enclosed as Annexure VI
7 220kV GIS Switching Station at Hatkoti.
The land was transferred by HPPCL to HPPTCL
Ref Annexure-VII for the transfer letter
8 33/132 kV Substation Barshaini Forest clearance has been obtained for Diversion of 0.6800 Ha.
Copy of FC Letter is enclosed as Annexure VIII.
9
132 kV D/c transmission Line from Barshaini to Charor132 kV D/c transmission Line from Barshaini to Charor
Forest clearance has been obtained for Diversion of 71.9788 Ha.
Copy of FC Letter is enclosed as Annexure-IX.
Additional Scope of the Works
10
Augmentation of existing 220/132 kV Kangoo Sub Station and stringing of 2nd circuit of 220 kV S/C line (3.2 Km) on D/C Towers from Dehar Power House of BBMB to Kangoo sub-station in Mandi district
Forest clearance is not required.
Private and HPSEBL land
11
Construction of 2 No. AIS Bays in the existing 220/66kV Baddi substation and loop-in and loop-out (LILO) 2nd circuit of 220 kV Kunihar to Panchkula transmission line (2.5 Km) at Baddi sub-station in district Solan
Forest clearance is not required.
Existing yard of HPSEBL Land
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 11 of 110
S. No.
Sub-Project Description Forest Clearance Status Remarks, if any
12
Construction of 66/220 kV, 80/100 MVA transformer in 400/220 kV Gumma sub-station in district Shimla
Forest clearance is not required.
HPPTCL Land
13
Creation of a joint control and operations center for transmission line assets in district Solan and Sirmaur
Forest clearance is not required. Existing building in
HPSEBL Land
14
LILO of 132 kV D/C Kurthala-Bathri line (3.5 Km D/C) at Mazra sub-station in district Chamba
Forest clearance has been obtained for Diversion of 16.2746 Ha.
Copy of FC Letter is enclosed as Annexure X.
9. The labor license and workman’s compensation insurance applicable for the sub-projects have been obtained by the concerned civil contractors. Details are provided in Table-4.0
Table-4.0: The Labor License and Workman’s Compensation Insurance Applicable for the Sub-Projects
S. No.
Sub-Project Description Name of the Contractor
License Validity
1 66 kV GIS Substation station at Baghipul
M/s Kanohar Ltd.
a.) Labour License- Labour License- valid till 02-09-2021.
b.) Workman’s compensation Insurance-valid till 27-05-2021.
2 66 kV DC Line from Baghipul To kotla.
M/s Man structure Ltd.
a.) Labour License- valid till 03-06-2021. b.) Workman’s compensation Insurance-
valid till 25-05-2021
3 400 kV D/C (Twin MOOSE) from 400/220 kV,2x315 MVA Lahal GISS to 400 kV Chamera (Rajera) pooling station of PGCIL
M/S Apar India Limited.
a.) Labour License- valid till 21-09-2021;
b.) Workman’s compensation Insurance-valid till 31-03-2021.
4 220 kV D/c Line (Twin Moose) from Bhajoli Holi to HEP to 400/220 kV Lahal GIS.
M/S Apar India Limited.
a.) Labour License- valid till 21-09-2021 b.) Workman’s compensation Insurance-
valid till 31-03-2021
5 220 kV D/C line from Mazra to Karian
R.S. Infra Projects Pvt. Ltd., Noida
a.) Labour License- valid till 07-07-2021 b.) Workman’s compensation Insurance-
valid till 02-07-2021
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 12 of 110
S. No.
Sub-Project Description Name of the Contractor
License Validity
6 132/220 kV, 2x80/100 MVA GISS at Mazra.
TBEA Energy (India) Pvt. Limited & TBEA Zonfa Shanghai
a.) Labour License- valid till 28-08-2021 b.) Workman’s compensation Insurance-
valid till 04-08-2021
7 220kV GIS Switching Station at Hatkoti.
M/S G.E India LTD.
a.) Labour License- 17-07-2021 b.) Workman’s compensation Insurance-
valid till 02-07-2021
8 33/132 kV Substation Barshaini
M/S G.E India LTD.
a.) Labour License- Valid till 06-05-2021.
b.) Workman’s compensation Insurance-valid till 02-07-2021
9. 132 kV D/c transmission Line from Barshaini to Charor
M/s Salasar Ltd. a.) Labour License- valid till 28-05-2021. b.) Workman’s compensation Insurance-
valid till 29-06-2021.
10. All the Civil Contractors are procuring the construction material from authorized & approved sources in compliance with Environmental regulation of the Country.
E. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED IN THE LOAN AGREEMENT
11. The compliance status during the reporting period with the environmental covenants as stipulated in the loan agreement is provided in Table 5.0.
Table-5.0: Compliance Status with the Environmental Covenants as Stipulated in the Loan Agreement
Reference As per ADB loan covenant Status
Para-8, schedule-5
The State and HPPTCL shall ensure that the preparation, design, construction, implementation, operation and decommissioning of each Subproject comply with (a) all applicable laws and regulations of the Borrower relating to environment, health, and safety; (b) the Environmental Safeguards; (c) the EARF; and (d) all measures and requirements set forth in the IEE and EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Being Complied
All applicable laws & regulations are complied with and the requisite permissions required for subprojects have been obtained.
Environment Safeguard measures as suggested in IEE report are being implemented.
EMP is a part of the Contract Document and mitigation measures suggested in EMP are being
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 13 of 110
Reference As per ADB loan covenant Status
implemented on site.
Para-13, schedule-5
The State and HPPTCL shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to:
(a) comply with the measures and requirements relevant to the contractor set forth in the IEE, the EMP, the RP and any IPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report;
(b) make available a budget for all such Environmental and Social measures;
(c) provide HPPTCL with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the project that were not considered in the IEE, the EMP, the RP or any IPP;
(d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and
(e) fully reinstate pathways, other local infrastructure, and agricultural land to at least
Being complied.
It has been ensured that Bidding/Contract documents have all the provisions that is required by the Contractor to mitigate measures as suggested in IEE and Environment Management Plan (EMP).
Budgetary provisions have been ensured for Environmental and Social measures.
Contract agreement have provisions to serve notice to HPPTCL for any unanticipated environmental, resettlement or indigenous peoples risks which have not been considered in the IEE, EMP, the RP or any IPP.
Bidding document also have provisions to reinstate any damages to local pathways, infrastructure and agricultural land.
Para 14, of schedule-5
Safeguards Monitoring and Reporting
The State and HPPTCL shall do the following:
(a) submit semi-annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;
(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, the RP or any IPP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and
As required semi-annual Safeguards Monitoring Reports are submitted to ADB in routine.
Spreading of pandemic; a highly pathogenic coronavirus disease (Covid-19) was an unanticipated health and safety risk that broke out during the last reporting period and continued its effects during this reporting period too.
HPPTCL have advised Contractor in writing to follow all guidelines issued by the Govt. and also, HPPTCL
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 14 of 110
Reference As per ADB loan covenant Status
(c) report any breach of compliance with the measures and requirements set forth in the EMP, the RP or any IPP promptly after becoming aware of the breach.
prepared a health and Safety plan in response to pandemic and was shared to the Contractors to follow up.
Para 15, of schedule-5
The Borrower, the State and HPPTCL shall ensure that no proceeds of the Loan are used to finance any activity included in the list of prohibited investment activities provided in Appendix 5 of the SPS
Being complied
Loan is not being used for any of the prohibited investment activities as provided in SPS and the same will be ensured in future too by HPPTCL.
Para 16, of schedule-5
The Borrower shall ensure or cause the State and HPPTCL to ensure that Works contracts follow all applicable labor laws of the Borrower and the State and that these further include provisions to the effect that contractors (i) carry out HIV/AIDS awareness programs for labor and disseminate information at worksites on risks of sexually transmitted diseases and HIV/AIDS as part of health and safety measures for those employed during construction; (ii) follow and implement all statutory provisions on labor (including not employing or using children as labor, equal pay for equal work), health, safety, welfare, sanitation, and working conditions; and (iii) maximize employment of women and local poor and disadvantaged persons for construction purposes, provided that the requirements for efficiency are adequately met. Such contracts shall also include clauses for termination in case of any breach of the stated provisions by the contractors.
Being complied
It has been ensured that all the applicable labor laws, statutory provisions and other requirements have been considered in Contract agreements and the same is being implemented by the Contractor on site.
HIV/AIDS awareness programs for labor have been included in the Contract agreements and are being implemented by the Contractor on site.
Labor licenses have been obtained.
No child labor has been employed & provisions of health, safety, welfare, sanitation and equal payments for equal works have been ensured.
Local poor and disadvantaged persons have been preferred for employment for construction purposes.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 15 of 110
F. ENVIRONMENTAL MANAGEMENT PLAN (EMP) IMPLEMENTATION COMPLIANCE STATUS DURING THE REPORTING PERIOD
12. The status of EMP implementation for the sub-projects under tranche-3 during the reporting period is provided in Table 6.0.
Table-6.0: Environmental Management Plan (EMP) Implementation Compliance Status during the Reporting Period
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
PRE-CONSTRUCTION PHASE
A. Physical Resources
Equipment specifications and design parameters
Release of chemicals and harmful gases in receptors (air, water, land)
PCBs, Chlorofluorocarbons (CFCs), including halons not used in transformers, or any other equipment.
Transformers and other equipment specifications compliant with GoI rules/regulations & (International Electro-technical Commission) IEC standards
Exclusion of PCBs, CFCs stated in tender documents - Once.
HPPTCL
Detailed Design
Complied
The specification of Transformer and other equipment comply to GoI rules/ regulations.
B. Environmental Resources
Location of land for substations/ transmission towers
Impact to the existing environment
Construction facilities should be placed at suitable distance from water bodies, natural flow paths, important ecological habitats and residential areas
Water and Air Quality
Air Quality Standards and Water Quality standards – Once
HPPTCL Detailed Design/ Planning Stage
Complied during transmission line route survey and identification of sites for the substation.
Baseline Air and water quality standards were also monitored.
Substation location and design
Noise generation Exposure to noise,
Nuisance to neighboring properties
Substation location/ designed to ensure noise will not be a nuisance to neighbouring properties.
Expected noise emissions based on substation design,
noise levels
Noise control regulations
Noise levels to be specified in tender documents-Once
HPPTCL Detailed Design/ Planning Stage
Complied during location identification survey process. Sites have been identified away from communities.
Location of transmission towers
Impact on water bodies / land/
Consideration of site location to avoid water
Site location, transmission line
Consultation with local
HPPTCL Part of detailed project siting, survey
Complied during transmission line route
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 16 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
and transmission line alignment and design
residences bodies or agricultural land/orchards as much as possible.
Careful site selection to avoid existing settlements
alignment selection (distance to dwelling, water and/or agricultural land)
authorities and land owners, water quality standards-Once
and design. survey.
Routes were finalised by avoiding water bodies and having minimum impacts to agricultural land/ orchards.
Interference with drainage patterns/Irrigation channels
Temporary flooding hazards/loss of agricultural production
Appropriate siting of towers to avoid channel interference
Site location and transmission line alignment selection
Consultation with local authorities and design engineers – Once
HPPTCL Detailed alignment survey and design
Complied during transmission line route survey. Tower locations have been selected so that it avoids any water channel interference.
C. Ecological Resources
Encroachment into precious ecological areas
Loss of precious ecological values/ damage to precious species
Avoid encroachment by careful site and alignment selection and reconnaissance before final siting of facilities.
Floral and faunal habitats loss
Enumeration of flora and fauna at the site - Once
ESC of HPPTCL
Detailed design/planning stage
Complied during planning stage. Line routes were selected away from ecological sensitive areas (National Parks, Wildlife or any other Eco sensitive areas).
Also, efforts were made to minimise acquisition of forest land. Whereas, some of the subprojects (6 transmission lines and 2 substations) are passing through forest and requisite forest clearances have been obtained for all these subprojects1.
1 Subprojects passing through or located in forest land are; 1) 66 kV double circuit (D/C) transmission line from 66 kV GIS Bagipul sub-station to Kotla substation, 2) Lahal-Rajera
transmission line, 3) Mazra-Karian transmission line details, 4) 220 kV double circuit (D/C) transmission line on D/C towers from Holi Bhajoli to Lahal substation, 5) 132 kV D/C transmission line from Barshaini to 132/220 kV substation at Charor, 6) 132/220 kV, 2x80/100 MVA substation at Mazra, 7) 33/132 kV 2x25/31.5 MVA GIS substation at Barshaini and 8) LILO of 132 kV D/C Kurthala-Bathri line at Mazra substation (Additional Scope of works).
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 17 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
D. Human Resource
Involuntary resettlement or land acquisition
Loss of lands and structures
Compensation paid for temporary/ permanent loss of productive land
Public complaints Rates paid as per the Resettlement plan/Frame work for the project – Once
ESC of HPPTCL
Prior to Construction phase/land acquisition
Complied
Resettlement frame work has been prepared and it includes compensation for loss of lands, and structures.
Encroachment into farmland
Loss of agricultural productivity
Avoid siting towers on farmland/orchards wherever possible
Farmers compensated for any permanent loss of productive fruit trees that need to be trimmed or removed along RoW.
Tower location and transmission line alignment selection
Statutory approvals for tree trimming /removal from Horticulture department
Implementation of crop and tree compensation (based on affected area)
Consultation with local authorities and design engineers - Once
ESC of HPPTCL
Part of detailed alignment, survey and design.
Complied during survey/design stage. Compensation for damages has been proposed for any losses of agricultural productivity by thorough loss evaluation process with concerned department.
Location and design of Substation
Disturbance to adjacent lands and the people due to cut and fill operations
Maintain adequate clearance, construction of retaining structures, minimise cut and fill operations adjoining the dwellings
Transformers and specifications and compliance with setback distances (“as-built” diagrams)
Technical specification- Once
Measure setback distances to nearest house structures – Once
HPPTCL Detailed design/planning stage
Complied during survey by maintaining adequate clearances and keeping provisions of retaining walls to stop flow of excess debris.
Location of transmission towers and transmission line alignment and design
Exposure to Electro-magnetic Frequency (EMF) and other safety related risks
Setback of dwellings to overhead line route designed in accordance with Indian Electricity Act (Rule 77 & 80) for each permitted level of power frequency and its proper
Tower location and transmission line alignment selection with respect to nearest dwellings – Once
Setback distances to nearest houses, clearance of conductor from ground –
HPPTCL Part of tower siting survey and detailed alignment survey and design
Complied during survey. Adequate clearances have been designed as per Indian Electricity Act.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 18 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
supervision at each tower site.
Once
Explosions/Fire Hazards to life Design of substations to include modern fire control systems/firewalls.
Provision of firefighting equipment to be located close to transformers, switchgear
Substation design compliance with fire prevention and control codes
Tender document to mention detailed specifications – Once
HPPTCL Part of detailed substation layout and design/drawings
Complied.
Provisions of Firefighting equipment are integral part of Substation design.
CONSTRUCTION PHASE
A. Physical Resources
Site clearance Soil erosion and surface runoff
Construction near seasonal rivers, erosion and flood-prone areas should be restricted to the non-rainy season.
Provision and maintenance of drains and retention ponds.
Treat clearing and filling areas against flow acceleration & const. work should be carefully designed to minimize obstruction or destruction to natural drainage.
Soil erosion Visual inspection
(Turbidity and sedimentation) – Once
Contractor through contract provisions under supervision of HPPTCL
Construction period Being Complied
Construction activities in erosion prone areas are taken during non-rainy season.
As designed, retaining walls have been provided, which accommodate excavated material.
Removal of disturbance to public utility services-Water supply, sanitation
Public inconvenience
Advance notice to the public about the time and the duration of the utility disruption.
Use of well trained and experienced machinery operators to reduce accidental damage to the public utilities - pipelines
Disruption to other commercial and public activities/public complaints
Technical specification – per public complaint – Once each time
Throughout the construction period
Being Complied
Advance notices are issued in case there is any utility disruption.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 19 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
Restore the utilities immediately to overcome public inconvenience
Equipment layout and installation
SF6 leakage during storage and erection of Switchgear
Record of all substation switchgear, cylinders located within secure casings
Switchgear casings and substation bounded area.
As per (International Electro-technical Commission) IEC standards - Once per year
throughout construction/erection
Being Complied
SF6 Gas cylinders are located/ kept vertical and tied together as shown in photographs at Annexure XI.
No incident related to SF6 gas handling was reported during the reporting period.
Surplus earthwork/soil
Runoff to cause water pollution, solid waste disposal
Excess fill from tower foundation excavation to be reused on site or disposed of next to roads or around houses, in agreement with the local community or landowners.
Location and amount (m3) of fill disposal
Soil disposal locations and volume (m3)
Appropriate fill disposal and dispersal locations - Quarterly
Construction Period Being Complied
Excavated material has been filled back in tower foundation, retaining wall and other developmental activities on site with provision of protection measures.
B. Environmental Resources
Equipment layout and installation
Noise and Vibrations
Selection of construction techniques and machinery to minimize ground disturbance.
Construction techniques and machinery
Minimal ground disturbance – Monthly
Construction Period Being Compiled
As designed, low noise producing machineries/ equipment are being used.
Substation Construction
Loss of soil Cutting and filling for the substation foundations obtained by creating or improving local drainage system.
Borrow area siting (area of site in m2 and estimated volume in m3)
CPCB norms - Quarterly
Contractor through contract provisions under the supervision of ESC, HPPTCL
Construction Period Being Complied
Debris has been used for filling and levelling of the substation sites.
Whereas, excess debris has been disposed of at pre identified designated location (ref Annexure
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 20 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
XII)
Water pollution Minimize construction activities involving significant ground disturbance (i.e. substation land forming) during the monsoon season. Provide drains and retention ponds if required.
Water Quality (pH, BOD/COD, suspended solids, other) during major earthworks
GoI water quality standards – Once prior to start of construction activities
Construction Period Water quality monitoring was carried during the reporting period and the results are within the prescribed limits of CPCB standards as given in Annexure XVI.
Provision of facilities for construction workers
Contamination of receptors (land, water, air)
Construction workforce facilities to include proper sanitation, water supply and waste disposal facilities.
Amenities for Workforce.
Presence of proper sanitation, water supply and waste disposal facilities -
Once
Construction Period Being Complied
There is a provision of kitchen, proper sanitation, washing and waste disposal facilities for workers as shown in sample photographs at Annexure XIII.
Mechanised construction
Noise, vibration and operator safety, efficient operation
Noise, vibration, equipment wear and tear
Construction equipment to be well maintained.
Construction techniques and Machinery selection to minimize ground disturbance.
Proper maintenance and turning off plants, not in use.
Construction techniques and equipment - estimated noise emissions and operating schedules
Technical specifications, safety regulations,
Noise control regulations -
Quarterly
Contractor through contract provisions under the supervision of HPPTCL
Construction Period Being Complied
Low noise producing machineries/ equipment are being used.
Construction of roads for accessibility to substations
Increase in airborne dust particles
Increased land requirement for temporary accessibility
Existing roads and tracks used for construction and maintenance access to the site wherever possible.
New access ways restricted to a minimum of single carriageway width.
Access roads, routes (length and width of access roads)
Use of established roads wherever possible
Access restricted to a minimum of single carriageway
Contractor through contract provisions under the supervision of HPPTCL
Construction Period Being Complied
Air quality monitoring was carried during the reporting period and the results are within the prescribed limits of CPCB standards as given in Annexure XVI.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 21 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
width-Once
C. Ecological Resources
Site clearance Vegetation Marking of vegetation to be removed prior to clearance, and strict control on clearing activities to ensure minimal clearance.
Vegetation marking and clearance control (area in m2)
Clearance strictly limited to target vegetation-Once
Contractor through contract provisions under supervision of HPPTCL
Construction Period Being complied
Tree cutting activity for “220kV double circuit (D/C) transmission line from Holi-Bhajoli” has been completed after taking requisite permission from the forest department.
Tree cutting has not been initiated and shall be started after getting requisite permission from the Forest department for remaining 6 more projects
Trimming/cutting of trees within RoW
Loss of vegetation and deforestation
Trees that can survive cutting should be pruned.
Felled trees and other cleared or pruned vegetation to be disposed of by authorised agents/forest department.
Species-specific tree retention as approved by statutory authorities (average and maximum tree height at maturity, in meters)
Disposal of cleared vegetation as approved by the statutory authorities (area cleared in m2)
Presence of target species in RoW following vegetation clearance – Once.
HPPTCL, Contractor through contract provisions under supervision of forest department
Construction Period Being complied
Tree cutting/disposal activity has been/will be done by HP Forest corporation, a subsidiary of HP Forest department.
Wood/ vegetation harvesting, cut and fill operations
Loss of vegetation and deforestation
Construction workers prohibited from harvesting wood in the project area during their employment.
Illegal wood/vegetation harvesting (area in m2, number of incidents reported)
Complaints by local people or other evidence of illegal harvesting – Once
HPPTCL, Contractor through contract provisions.
Construction Period Being complied
Workers are prohibited to harvest any wood or vegetation.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 22 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
Effect on fauna Prevent work force from disturbing the flora, fauna including hunting of animals and fishing in water bodies.
Proper awareness program regarding conservation of flora, fauna including ground vegetation to all workers.
Habitat loss Complaints by local people or other evidence of illegal hunting - Once
Construction Period Being complied
Workers are prohibited to hunt or disturb any animals and fishing in water bodies.
D. Human Environment
Construction schedules for substation
Noise nuisance to neighbouring properties
Minimize construction activities undertaken during the night and local communities informed of the construction schedule.
Timing of construction (noise emissions, dBA)
Construction as per Scheduled timings only
HPPTCL, Contractor through contract provisions
Construction Period Being complied
Substation sites are away from communities and construction activities are restricted in day time only.
Noise quality monitoring was carried during the reporting period and the results are within the prescribed limits of CPCB standards as given in Annexure XVI.
Acquisition of cultivable lands
Loss of agricultural productivity
Avoid faming/harvesting season for field crops wherever possible for the project activities.
Ensure existing irrigation facilities are maintained in working condition
Protect /preserve topsoil and reinstate after construction completed
Repair /reinstate damaged
Land area of agriculture loss
Usage of existing utilities
Status of facilities (earthwork in m3)
Implementation of crop compensation (amount paid, dates,
Loss of crops-work in post-harvest period but before next crop – Once per site
HPPTCL, Contractor through contract provisions
Throughout Construction Period
Being complied
Farming/harvesting seasons are avoided during project activities.
existing irrigation facilities are maintained in working condition.
Topsoil and damaged bunds are being reinstated after completion of construction activities.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 23 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
bunds etc. after construction completed
Compensation for temporary loss in agricultural production
etc.)
Temporary use of land
Losses to neighbouring land uses/ values
Contract clauses specifying careful construction practices.
As much as possible existing access ways will be used.
Productive land will be reinstated following completion of construction
Compensation will be paid for loss of production, if any.
Contract clauses
Design basis and layout.
Reinstatement of land status (area affected, m2).
Implementation of Tree/Crop compensation (amount paid).
Incorporating good construction management, design engineering practices - Once.
Consultation with affected parties immediately after completion of construction and after the first harvest – Once.
Contractor through contract provisions under the supervision of HPPTCL
Construction Period Being Complied
Existing access ways are being used. Any sites used temporarily and damaged are restored to its original state and also compensation is being paid, as per the HPPTCL’s policy for any damages.
Transportation and storage of materials
Nuisance to the general public
Transport loading and unloading of construction materials should no cause nuisance to the people by way of noise, vibration and dust
Avoid storage of construction materials beside the road, around water bodies, residential or public sensitive locations
Construction materials should be stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment
Water and Air Quality
CPCB Emission standards and Water Quality standards -
Quarterly
Contractor through contract provisions under supervision of HPPTCL
Throughout the construction Period
Being Complied
Transportation, loading and unloading is being carried without causing nuisance on site.
Material in every project has been stored at designated places in the office premises sample photographs of the material stockyard for different subprojects are shown in Annexure XI.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 24 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
friendly and nuisance free manner
Temporary outage of the electricity
Loss of power supply to the local community when distribution lines crossing the new transmission line are switched off
Advance notice to the public about the time and the duration of the utility disruption
Restore the utilities immediately to overcome public inconvenience
Disruption of power supply to houses and commercial premises.
Regular monitoring during the period of construction - At each public complaint.
Contractor through contract provisions under the supervision of HPPTCL,
Throughout the construction period
Being Complied
HPPTCL takes permission from Himachal Pradesh State Electricity Board limited (HPSEBL) for shutdown requirements. HPSEBL issues advance notice to local community for temporary outage of electricity through local Newspapers. Annexure XIV provides sample Newspaper cuttings of such advance notices.
Health and safety Injury and sickness of workers and members of the public
Contract provisions specifying minimum requirements for construction camps
Contractor to prepare and implement a health and safety plan and provide workers with required PPE.
Contractor to arrange for health and safety awareness programs including on AIDS and sexually transmitted diseases (STD).
Contract clauses (number of incidents and total lost-work days caused by injuries and sickness)
HPPTCL and ADB Health and safety standards -
Monthly
Contractor through contract provisions under the supervision of HPPTCL
Construction period Being Complied.
PPE discipline is being maintained on sub project sites.
No fatal accident was reported from any subproject sites during the reporting period. Though, there had been some minor injuries and these were treated on site by giving first aid2.
Photographs pertaining to health and safety awareness and other good practices at project sites are given in Annexure
2 During the reporting period, some minor injuries were reported from sub project sites i.e., C/o 220 kV D/C transmission line from 132/220 kV GIS substation Mazra to 33/220 kV Karian substation site (3 Nos) and C/o 66 kV double circuit (D/C) transmission line from 66 kV GIS Bagipul S substation to Kotla (5 nos). These injuries were treated by giving first aid on site.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 25 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
XI.
Capacity Building Improve standards of implementation and monitoring
Training of HPPTCL staff Training schedules Number of the training program - Yearly
HPPTCL- ESC Construction Period No trainings were provided to HPPTCL’s staff during the reporting period.
OPERATION AND MAINTENANCE PHASE
A. Physical Resources
Operation of Switchgear
Leakage of SF6 gas
Record of all substation switchgear located within secure casings.
Training on handling and management of SF6 gas.
Switchgear casings and substation boundary
Ozone Depleting substances – Monthly
HPPTCL Throughout the operation
Projects are still in Construction stage and compliance as required will be done during operation stage.
B. Environmental Resources
Soil Erosion at tower base of transmission line
Removal of top soil
Planting of buffer zone species suitable for hilly terrain
Turbidity of water
(Visual Inspection)
Visual inspection
(Turbidity and sedimentation)-Quarterly
HPPTCL Throughout the operation
Projects are still in Construction stage and compliance as required will be done during operation stage.
Oil spillage Contamination of land/nearby water bodies
Substation transformers located within secure and impervious bundled areas with a storage capacity of at least 100% of the capacity of oil in transformers and associated reserve tanks.
Substation bounding
(“as-built” diagrams)
Hazardous Waste (Management, handling, Trans-boundary Movement) Rules 2009 - Monthly
HPPTCL Throughout the operation
C. Ecological Resources
Soil Erosion at tower base of transmission line
Removal of top soil
Planting of buffer zone species suitable for hilly terrain
Turbidity of water
(Visual Inspection)
Visual inspection
(Turbidity and sedimentation)-Quarterly
HPPTCL Throughout the operation
Projects are still in Construction stage and compliance as required will be done during operation stage.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 26 of 110
Project Activity Potential Environmental Impact
Mitigation Action Parameters to be Monitored
Standards/ Measurement/ Frequency
Institutional Responsibility
Implementation Schedule
Status during the reporting period
Follow-up action, if any
Oil spillage Contamination of land/nearby water bodies
Substation transformers located within secure and impervious bundled areas with a storage capacity of at least 100% of the capacity of oil in transformers and associated reserve tanks.
Substation bounding
(“as-built” diagrams)
Hazardous Waste (Management, handling, Trans-boundary Movement) Rules 2009 - Monthly
HPPTCL Throughout the operation
D. Human Environment
Maintenance of Transmission line
Exposure to electromagnetic interference
Transmission line design to comply with the limits of electromagnetic interference from overhead power lines
Required ground clearance (meters).
Ground clearance, standards on EMF – Annual
HPPTCL Operation Period Projects are still in Construction stage and compliance as required will be ensured during operation stage.
Substation maintenance
Exposure to electromagnetic interference
Substation design to comply with the limits of electromagnetic interference within floor area
Required noise vibrations levels
Technical specifications – on public complaint
HPPTCL Throughout the operation
Noise generation Nuisance to the community around the site
Provision of noise barriers near substation sites
Noise level Noise level (dbA)- Once a year
HPPTCL Throughout the operation
Electric shock Death or injury to the workers and public
Security fences around substation. Establishment of warning signs
Careful design using appropriate technologies to minimise hazards
Proper maintenance of fences and sign boards
Usage of appropriate technologies (lost work days due to illness and injuries)
Periodic maintenance
Number of programs and percent of staff/ workers covered
HPPTCL Throughout the operation
Training for Electric safety
Raising awareness for electrical safety measures
Training of HPPTCL personnel.
Training schedules Number of training program - Yearly
HPPTCL-ESC Operations
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 27 of 110
G. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES
13. The ADB approved environmental monitoring plan is provided in Table 7.0.
Table 7.0: Environmental Monitoring Plan
Environmental component
Project stage Parameters to be monitored
Location Frequency Standards Implementation Supervision
1.Air Quality
A. Pre-construction stage (The project once assigned to contractor)
PM10, PM2.5, SO2, NOx, CO along with Meteorological data- temperature Humidity, wind speed, wind direction
Inside and outside (0.5 km) of the proposed substation
One time National Ambient Air Quality Standard, 2009
Contractor by CPCB approved laboratory
Contractor/ PMU
B. Construction Stage
PM10, PM2.5, SO2, NOx, CO along with Meteorological data- temperature Humidity, wind speed, wind direction
Inside and outside (0.5 km) of the proposed substation
Two times /year National
Ambient Air Quality Standard, 2009
Contractor by CPCB approved laboratory
Contractor/ PMU
C. Operation Stage
PM10, PM2.5, SO2, NOx, CO along with Meteorological data- temperature Humidity, wind speed, wind direction
Inside and outside (0.5 km) of the proposed substation
One time National Ambient Air Quality Standard, 2009
Contractor by CPCB approved laboratory
PMU
2.Water Quality
A. Pre-construction stage (The project once assigned to contractor)
EC, TSS, DO, BOD, PH Oil and grease, Pb,
Nearest downstream spring/handpump wells (2 wells) around the substation
One time IS: 10500 Drinking Water Quality Standard
Contractor by CPCB approved laboratory
Contractor/ PMU
B. Construction Stage
EC, TSS, DO, BOD, PH, Oil and grease, Pb
Nearest downstream spring/handpump wells (2 wells) around the substation
Two times /year
IS: 10500 Drinking Water Quality Standard
Contractor by CPCB approved laboratory
Contractor/ PMU
C. Operation Stage
EC, TSS, DO, BOD, PH Oil and grease, Pb
Nearest downstream spring/handpump wells (2 wells) around the substation
Yearly IS: 10500 Drinking Water Quality Standard
Contractor by CPCB approved laboratory
PMU
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 28 of 110
Environmental component
Project stage Parameters to be monitored
Location Frequency Standards Implementation Supervision
3.Noise/ Vibration
A. Pre-construction stage (The project once assigned to contractor)
Noise level in dB (A) Inside and outside (0.25 km) of the proposed substation
One time CPCB standards for Noise and vibrations
Contractor by CPCB approved laboratory
Contractor/ PMU
B. Construction Stage
Noise level in dB (A) Inside and outside (0.25 km) of the proposed substation
2 times/ year
CPCB standards for Noise and vibrations
Contractor by CPCB approved laboratory
Contractor/ PMU
C. Operation Stage
Noise level in dB (A) Inside and outside (0.25 km) of the proposed substation
Yearly CPCB standards for Noise and vibrations
Contractor by CPCB approved laboratory
PMU
4. Soil A. Pre-construction stage (The project after assign to contractor)
PH, Sulfate (SO3), Chloride, ORP, water Soluble salts EC, Organic Matter, Moisture Content
Inside and outside (just close to the proposed site, 2 locations) of the proposed substation
One time
Technical specifications
Contractor by CPCB approved laboratory
Contractor/ PMU
B. Construction Stage
PH, Sulfate (SO3), Chloride, ORP, water Soluble salts EC, Organic Matter, Moisture Content
Inside and outside (just close to the proposed site, 2 locations) of the proposed substation
Two times /year
Technical specifications
Contractor by CPCB approved laboratory
Contractor/ PMU
C. Operation Stage
PH, Sulfate (SO3), Chloride, ORP, water Soluble salts EC, Organic Matter, Moisture Content
Inside and outside (just close to the proposed site, 2 locations) of the proposed substation
A single time
Technical specifications
Contractor by CPCB approved laboratory
PMU
ESC –Environment & Social Cell of HPPTCL
Abbreviations:
SO2- -Sulphur Dioxide; NO2- - Nitrogen Dioxide; CO- Carbon Monoxide; Pb – Lead; PM2.5 - Particulate Matter <2.5; PM10 - Particulate Matter <10; EC - Electrical Conductivity; DO - Dissolved Oxygen; TSS - Total Suspended Solids; BOD - Biological Oxygen Demand; ORP – Oxidation Reduction Potential.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 29 of 110
14. During the reporting period Air, Noise, Water and soil quality monitoring was carried for the projects; 22/66 kV Gas Insulated Switchgear (GIS) Pooling station at Bagipul (Construction stage), 132/220 kV, 2x80/100 MVA GIS substation at Mazra (Construction stage), 220 kV GIS switching station at Hatkoti (Construction stage), 33/132 kV 2x25/31.5 MVA GIS substation at Barshaini (Construction stage), Construction of 66/220 kV and 80/100 MVA transformer in 400/220 kV Gumma substation (Pre-construction stage) as per ADB approved monitoring plan. The results of all the tested parameters were found well within the prescribed limits of CPCB standards and are given in Annexure XVI.
H. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURING IMPLEMENTATION, WHICH WERE NOT COVERED EARLIER DURING ENVIRONMENTAL ASSESSMENT OF THE PROJECT.
15. The effect of Pandemic due to novel Covid-19 continued during the reporting period too and the Contractor adhered to HPPTCL’s Health and Safety Plan (Ref Annexure XV) and the guidelines issued by Govt. of India or State Govt. to prevent the spread of the virus.
16. Some cases of Coronavirus infections were reported from different subprojects and all these were cured by following the guidelines in HPPTCL’s Health and Safety Plan and Govt’s guidelines. The cases reported were from subprojects i.e., C/o 66 kV double circuit (D/C) transmission line from 66 kV GIS Bagipul substation to Kotla (13 Nos) and C/o 220 kV D/C transmission line from Holi Bhajoli To Lahal (25 Nos). All these reported cases were isolated and quarantined at designated places by the Contractor and were provided with all required facilities (food and medicines). Infected workers were paid full wages during the isolation/quarantine period. All these workers rejoined the works after recovery.
I. DETAILS OF GRIEVANCE REDRESSAL COMMITTEE AND COMPLAINTS RECEIVED FROM PUBLIC AND ACTIONS TAKEN THEREOF TO RESOLVE
17. The Grievance Redressal Committee has been constituted by HPPTCL. The grievances, if any are generally addressed at PIU level efficiently. There are eight nos. of PIUs under HPPTCL. The initial Grievances are received at PIU levels in case the grievance could not be attended at PIU level; the grievance is redressed by the Head/Corporate office-level grievance redressal committee. Copy of the office order regarding the constitution of Grievance Redressal Committee (GRC) at Corporate Office level & PIU level is provided in Annexure-XVII. Copy of the same is also uploaded on HPPTCL’s website (http://www.hpptcl.com/page/Office-Orders.aspx). Contact details of GRC are also displayed at project sites & PIU offices. No Environment safeguard related grievances were received during the reporting period.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 30 of 110
J. PUBLIC CONSULTATION PUBLIC CONSULTATION DURING PROJECT IMPLEMENTATION FOR THE REPORTING PERIOD
18. Public Consultation is a continuous process and conducted throughout the project during design, pre-construction, construction and operation. One to one interaction with affected people/families or with very few people are being conducted frequently by PIU representatives at project sites. Organized consultations with the group of the people were avoided due to restrictions of maintaining social distancing to comply with Covid-19 guidelines. During the consultations, people showed their satisfaction with the project construction activities. Also, they were anticipating the development or other benefits (like jobs or business growth) to the locals during the operational stages of the project. Figure-2 below presents the sample photograph of consultation carried by PIU representatives at Bagipul Village with local people in the presence of Environmental Expert (HPPTCL) during the reporting period.
Figure-2.0; Consultation with Local people at Bagipul
K. INSTITUTIONAL SET-UP FOR EMP IMPLEMENTATION
19. Environment & Social Monitoring Cell (ESC) at the PMU level has been constituted, a copy of the same is provided in Annexure-XVIII. Copy of the same is also uploaded on HPPTCL’s website (http://www.hpptcl.com/page/Office-Orders.aspx). ESC is headed by GM, Projects and supported by other members consisting, Sr. Manager Projects, Dy. Manager Projects Environmental Expert (Consultant) and Social Safeguard Expert (Consultant).
20. The Environment and Social Cell (ESC) monitors the policy and implementation related to environmental impacts of all projects of HPPTCL. Environmental Expert (Consultant) was mobilized during the reporting period in the team of ESC, HPPTCL to assist PIUs in all
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 31 of 110
environmental aspects of the projects in compliance with HPPTCL’s Environment and Social Safeguards Policy, May 2011 and ADBs Safeguard Policy Statement, 2009.
21. Environmental Expert (HPPTCL) visited different subprojects i.e., C/o 22/66 kV Gas Insulated Switchgear (GIS) Pooling station at Bagipul, c/o 66 kV double circuit (D/C) transmission line from 66 kV GIS Bagipul S substation to Kotla, c/o 400 kV (D/C) transmission line from 220/400 kV Lahal substation upto Rajera (Chamera II), 132/220 kV, 2x80/100 MVA GIS substation at Mazra, c/o 220 kV D/C transmission line from 132/220 kV GIS substation Mazra to 33/220 kV Karian substation, c/o 220 kV GIS switching station at Hatkoti in the month of December, 2020 to monitor the compliance status of Environment Safeguard measures at the site. PIU and Contractor’s representatives were also oriented with compliance requirements ADB’s Safeguard Policy Statement, 2009 during the site visit by the Environmental Expert. Figure-3 below presents the discussions carried during the interactive session by the Environmental Expert and representatives of PIU and Contractor at Bagipul Substation site during the site visit of Expert.
Figure-3; Environment Expert orienting PIU and Contractor’s representatives about ADB’s Environmental Safeguard requirements at Baghipul Substation project site
22. Contractors have deployed their environmental and Safety Officer (ESO) on different subproject sites to ensure compliance of Environment, Health and Safety concerns at sites.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 32 of 110
ANNEXURES
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 33 of 110
Annexure-I: - Physical Progress Photographs of Sub-project Sites
Work under progress at Baghipul-Kotla transmission line project
Protection works under progress at Bagipul Substation site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 34 of 110
Tower erection in Holi-Bajholi transmission line Project
Stringing completed in Urni-Wangtoo transmission line project
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 35 of 110
Tower erection in Barshaini Charor line Project Tower erection and stringing in Hatkoti Sunda line
Work under progress at Hatkoti Substation site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 36 of 110
Tower erection in Lahal-Rajera line project Tower erection in Mazra-Karian line project
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 37 of 110
Annexure-II: - Copy of Final Forest Clearance of Bagipul- Kotla Transmission Line
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 38 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 39 of 110
Annexure III-: - Copy of Forest Clearance Lahal Rajera (Chamera) Transmission Line
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 40 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 41 of 110
Annexure-IV: - Copy of Forest Clearance Bajoli Holi to Lahal Transmission Line
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 42 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 43 of 110
Annexure-V: - Copy of Forest Clearance Mazra Karian Transmission Line
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 44 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 45 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 46 of 110
Annexure-VI: - Copy of Forest Clearance Mazra Substation
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 47 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 48 of 110
Annexure-VII: - Copy of Land Transfer for Hatkoti Substation
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 49 of 110
Annexure-VIII: - Copy of Forest Clearance for 33/132kV GIS at Barshaini
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 50 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 51 of 110
Annexure-IX: - Copy of Forest Clearance Barshaini-Charor Transmission Line
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 52 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 53 of 110
Annexure-X: - Copy of Forest Clearance of 132kV LILO Kurtha- Bathri (132 kV) D/C Transmission Line to proposed 33/132/220 kV GIS substation Mazra at Pukhari
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 54 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 55 of 110
Annexure-XI: Sample Photographs of Health & Safety related awareness and other good practices in the sub-project sites
Awareness programme on general Health and Safety at Hatkoti Substation project site
Training/Awareness programme on use of tools and tackles at Hatkoti Substation project site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 56 of 110
Training/Awareness programme on working at height at Hatkoti Substation project site
EHS Induction room at Hatkoti Substation project site
Motivational programme at Baghipul-Kotla line project
Awareness programme on general Health and Safety of the workers at Barshainin-charor line project
Awareness program on General Health and Safety of the workers at Mazra karian transmission line project
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 57 of 110
HIV/AIDS awareness program conducted at Mazra-Karian substation site
Awareness program on General Health and Safety of the workers at Mazra Substation project site
Material stacking by the Contractor at Baghipul Kotla transmission line project
Sand buckets for fire prevention at Baghipul Substation project site
Material stacking by the Contractor at Baghipul Substation project site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 58 of 110
Material stacking at designated place by the Contractor at Mazra-Karian line project
Material stacking by the Contractor at Hatkoti Substation project site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 59 of 110
First aid box availability in Holi Bajholi to Lahal transmission line project site
First aid box availability in Lahal Rajera transmission line project site
First aid box availability in Baghipul substation First aid box availability in Baghipul kotla substation
site
Spreading information to aware workers about Covid-19 related issues
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 60 of 110
Temperature scanning of the workers on sub project sites
Sample copy of the record keeping of temperature scanning at subproject sites
Drainage extension by installing pipe in newly constructed access by the Contractor near Mazra Substation site
Storing of SF6 Gas Cylinders at Barshaini Substation project site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 61 of 110
Storing of SF6 Gas Cylinders at Hatkoti Substation site
Designated area with fire safety for the storage of hazardous material (diesel) at Barshaini Substation site
Sample Waste management practices at sub project sites
Sanitation facilities at sub project sites
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 62 of 110
Annexure-XII: Status of Muck Disposal
As a result of construction-related activities, soil and debris is generated. Improper disposal of the debris will have an impact on the surrounding ecology, public health and scenic beauty. If not planned properly, dumped materials interfere with the drainage pattern of the area, any water bodies, agricultural lands, marshlands and down slope or any environmental sensitive areas. To avoid any impact on the environment, spoil materials (soil, sand, rock) generated from construction activities is being used for site leveling and back-filling (wherever possible). Wherever, there is excess muck, it has to be disposed at pre identified dumping site. Prior approval has to be obtained for such dumping grounds/land fill sites from relevant concerned authorities such as Forest, Roads, or Panchayats (local community) by the contractor as per contract provisions. Following is the status of muck disposal of the sub-projects.
1. 33/132kV GIS Substation Barshaini
Being the hilly area and steep site for construction of this substation, a huge volume of excavated soil (approx. 25,000 to 30,000 cum) needs to be dumped from the site of the substation. Excess muck approx. 14,000 to 15,000 cum needs to be disposed of at pre identified designated muck disposal location. For this private land has been acquired and an accord in the form of minutes of meeting held between negotiation committee and the land owner is attached over leaf. Provision of Protection works in the form of crate wall has been made by HPPTCL. The site is still in use and photograph of the site is shown below (LHS).
2. 66/22 kV GIS Baghipul Sub-Station
Site selection and development of layout design is such that the muck generated during the construction was minimum and was to be utilized in backfilling. If in future, there is an excess debris generation then it will be disposed of at pre identified approved sites.
3. 33/132/220 kV GIS Mazra Substation
As per design, the excavated material was to be utilized in backfilling. Though, a location in the land of HPPTCL land near to substation has been designated to dispose of excess muck. The site is in use and photograph of the site is shown below (RHS).
Designated place for muck disposal at Barshaini S/stn. Designated place for muck disposal at Mazra S/stn.
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 63 of 110
Minutes of meeting held for negotiation of private land acquisition for muck disposal at Barshaini substation
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 64 of 110
Annexure-XIII: Photographs showing status of labor camp facilities
Rented accommodation for labours at Baghipul-Kotla line project
Bedding and sanitation facilities for labours at Baghipul-Kotla line project
Bedding and sanitation facilities for labours at Baghipul substation project site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 65 of 110
Rented accommodation for labours at Barshaini Substation site
Accommodation provisions for labour at Barshaini Charor TL Project
Accommodation provisions for labour at Barshaini Substation Project
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 66 of 110
Labour accommodation facilities at Mazra substation site
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 67 of 110
Annexure-XIV: Sample copies of Advance Notices served to Community for temporary outage of electricity due to shut down operations
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 68 of 110
Annexure-XV: HPPTCL’s Health and Safety Plan in response to Covid-19, pandemic
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 69 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 70 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 71 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 72 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 73 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 74 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 75 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 76 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 77 of 110
Annexure-XVI: - Results of Air, Noise, Water and Soil Quality Monitoring a) 66 22/66 kV Gas Insulated Switchgear (GIS) Pooling station at Bagipul
- Results of Air Quality Sampling/monitoring:
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 78 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 79 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 80 of 110
- Results of Noise Quality Sampling/monitoring:
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 81 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 82 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 83 of 110
- Results of Water Quality Sampling/monitoring:
* not under NABL Scope - limits are in reference to IS 10500:2012 - N.D mean not detected
Sr. No.
Parameter Unit Acceptable limit
Permissible limit
Results G Water Surface Water 900 1800 2700 3600
1 pH ---- 6.5-8.5 No Relaxation 7.3 7.3 7.2 7.3 2 Electrical
Conductivity µS/cm 750 0-2000 466 441 450 447
3 Turbidity NTU 1 5 0 0 0 0 4 TDS mg/l 500 2000 298 282 288 286 5 Chloride as Cl mg/l 250 1000 19 19 18 22 6 Acidity mg/l 200 600 14 12 12 12 7 Alkalinity mg/l 200 600 33 33 31 27 8 Total hardness as
CaCO3
mg/l 200 600 130 130 132 127
9 Calcium as Ca mg/l 75 200 34 343 35 39 10 Magnesium as Mg2+ mg/l 30 100 11 11 11 7.3 11 COD mg/l No guidelines - 24 25 26 24 12 BOD mg/l - 2 <5 <5 <5 <5 13 DO mg/l - 6 5.8 5.4 5.6 5.6 14 Taste* ------- Agreeable Agreeable Agreeable 15 Odor ------- Agreeable Agreeable Agreeable 16 TSS mg/l <10 <10 <10 <10 <10 <10 17 O&G mg/l N. D. N. D. N. D. N. D. N. D. N. D. 18 Lead as Pb* mg/l 0.01 No Relaxation N. D. N. D. N. D. N. D. 19 Color Pt. Co.
Unit 5 15 0 0 0 0
20 Cyanide as (CN)* mg/l 0.05 No Relaxation N. D. N. D. N. D. N. D. 21 Fluoride as F mg/l 1.0 1.5 N. D. N. D. N. D. N. D. 22 Nitrate (NO3) mg/l 45 No Relaxation N. D. N. D. N. D. N. D. 23 Sulphate as SO4 mg/l 200 400 18 20 20 16 24 Phenolic Compound* mg/l 0.001 0.002 N. D. N. D. N. D. N. D. 25 Copper as (Cu)* mg/l 0.05 1.5 N. D. N. D. N. D. N. D. 26 Cadmium as (Cd)* mg/l 0.003 No Relaxation N. D. N. D. N. D. N. D. 27 Manganese as Mn* mg/l 0.1 0.3 N. D. N. D. N. D. N. D. 28 Zinc as (Zn)* mg/l 5 15 N. D. N. D. N. D. N. D. 29 Chromium as (Cr) mg/l 0.05 No Relaxation N. D. N. D. N. D. N. D. 30 Boron mg/l 0.5 1.0 N. D. N. D. N. D. N. D. 31 Iron mg/l 0.3 No Relaxation N. D. N. D. N. D. N. D. 32 Phosphate* mg/l 0.5 1 N. D. N. D. N. D. N. D. 33 Residual chlorine mg/l 0.2 1 Nil Nil Nil Nil 34 Silica mg/l 0.1 0.4-1 <0.01 <0.01 <0.01 <0.01 35 Sulphide mg/l 0.05 No Relaxation Nil Nil Nil Nil
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 84 of 110
- Results of Soil Quality Sampling/Monitoring:
* not under NABL Scope
Sr. No.
Parameter Unit Results
900 1800 2700 3600
1. pH (1:2) ---- 7.1 7.1 7.1 7
2. EC (1:2) µS/cm 314 302 310 318
3. Water Soluble Salts* mg/kg 1540 1479 1520 1560
4. Chloride as Cl mg/kg 122 105 106 142
5. Total Hardness* mg/kg 639 469 648 475
6. Organic Matter % 0.99 1.03 1.02 1.03
7. Sodium Oxide mg/kg 136 137 137 136
8. Potassium Oxide mg/kg 66 66 65 65
9. Calcium Oxide* mg/kg 48 48 73 97
10. MgO* mg/kg 224 155 210 122
11. Specific Gravity* g/ml 2.0 2.0 2.0 2.0
12. Water Holding Capacity % 36 36 37 36
13. Moisture % 14 12 12 11
14. ORP* mV 74 78 78 76
15. Total soluble Sulphate mg/kg 20 20 30 30
16. Available Nitrogen mg/kg 0.83 0.83 0.85 0.85
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 85 of 110
b) 132/220 kV, 2x80/100 MVA GIS substation at Mazra - Results of Air Quality Sampling/monitoring:
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 86 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 87 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 88 of 110
- Results of Noise Quality Sampling/monitoring
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 89 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 90 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 91 of 110
- Results of Water Quality Sampling/monitoring:
* not under NABL Scope - limits are in reference to IS 10500:2012 - N.D mean not detected
Sr. No.
Parameter Unit Acceptable limit
Permissible limit
Results Surface Water
900 1800 2700 3600 1 pH ---- 6.5-8.5 No Relaxation 7 7 7.1 7.1 2 Electrical
Conductivity µS/cm 750 0-2000 428 447 419 431
3 Turbidity NTU 1 5 0 0 0 0 4 TDS mg/l 500 2000 274 286 268 276 5 Chloride as Cl mg/l 250 1000 19 19 16 15 6 Acidity mg/l 200 600 12 12 10 10 7 Alkalinity mg/l 200 600 35 33 24 24 8 Total hardness as
CaCO3
mg/l 200 600 123 123 130 127
9 Calcium as Ca mg/l 75 200 35 36 37 38 10 Magnesium as Mg2+ mg/l 30 100 8 8 9 8 11 COD mg/l No guidelines - 30 30 26 27 12 BOD mg/l - 2 <5 <5 <5 <5 13 DO mg/l - 6 5.4 5.2 5.3 5.6 14 Taste* ------- Agreeable Agreeable Agreeable 15 Odor ------- Agreeable Agreeable Agreeable 16 TSS mg/l <10 <10 <10 <10 <10 <10 17 O&G mg/l N. D. N. D. N. D. N. D. N. D. N. D. 18 Lead as Pb* mg/l 0.01 No Relaxation N. D. N. D. N. D. N. D. 19 Color Pt. Co.
Unit 5 15 0 0 0 0
20 Cyanide as (CN)* mg/l 0.05 No Relaxation N. D. N. D. N. D. N. D. 21 Fluoride as F mg/l 1.0 1.5 N. D. N. D. N. D. N. D. 22 Nitrate (NO3) mg/l 45 No Relaxation N. D. N. D. N. D. N. D. 23 Sulphate as SO4 mg/l 200 400 14 15 12 11 24 Phenolic Compound* mg/l 0.001 0.002 N. D. N. D. N. D. N. D. 25 Copper as (Cu)* mg/l 0.05 1.5 N. D. N. D. N. D. N. D. 26 Cadmium as (Cd)* mg/l 0.003 No Relaxation N. D. N. D. N. D. N. D. 27 Manganese as Mn* mg/l 0.1 0.3 N. D. N. D. N. D. N. D. 28 Zinc as (Zn)* mg/l 5 15 N. D. N. D. N. D. N. D. 29 Chromium as (Cr) mg/l 0.05 No Relaxation N. D. N. D. N. D. N. D. 30 Boron mg/l 0.5 1.0 N. D. N. D. N. D. N. D. 31 Iron mg/l 0.3 No Relaxation N. D. N. D. N. D. N. D. 32 Phosphate* mg/l 0.5 1 N. D. N. D. N. D. N. D. 33 Residual chlorine mg/l 0.2 1 Nil Nil Nil Nil 34 Silica mg/l 0.1 0.4-1 <0.01 <0.01 <0.01 <0.01 35 Sulphide mg/l 0.05 No Relaxation Nil Nil Nil Nil
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 92 of 110
- Results of Soil Quality Sampling/Monitoring:
* not under NABL Scope
Sr. No.
Parameter Unit Results
900 1800 2700 3600
1. pH (1:2) ---- 6.8 7 6.9 6.9
2. EC (1:2) µS/cm 290 286 278 286
3. Water Soluble Salts* mg/kg 1420 1400 1360 1400
4. Chloride as Cl mg/kg 124 142 142 142
5. Total Hardness* mg/kg 1166 1210 1210 1166
6. Organic Matter % 0.90 0.81 0.78 0.78
7. Sodium Oxide mg/kg 120 123 123 121
8. Potassium Oxide mg/kg 52 57 57 55
9. Calcium Oxide* mg/kg 169 194 218 194
10. MgO* mg/kg 349 350 332 332
11. Specific Gravity* g/ml 2.0 2.0 2.0 2.0
12. Water Holding Capacity
% 37 36 35 35
13. Moisture % 13 12 12 13
14. ORP* mV 88 75 75 76
15. Total soluble Sulphate mg/kg 30 30 20 20
16. Available Nitrogen mg/kg 0.75 0.81 0.82 0.82
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 93 of 110
c) 33/132 kV 2x25/31.5 MVA GIS substation at Barshaini - Results of Air Quality Sampling/monitoring:
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 94 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 95 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 96 of 110
- Results of Noise Quality Sampling/monitoring:
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 97 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 98 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 99 of 110
- Results of Water Quality Sampling/monitoring:
* not under NABL Scope - limits are in reference to IS 10500:2012 - N.D mean not detected
Sr. No.
Parameter Unit Acceptable limit
Permissible limit
Result Surface water
1 pH ---- 6.5-8.5 No Relaxation 7.2 2 Electrical
Conductivity µS/cm 750 0-2000 419
3 Turbidity NTU 1 5 0 4 TDS mg/l 500 2000 268 5 Chloride as Cl mg/l 250 1000 18 6 Acidity mg/l 200 600 12 7 Alkalinity mg/l 200 600 26 8 Total hardness as
CaCO3
mg/l 200 600 127
9 Calcium as Ca mg/l 75 200 38 10 Magnesium as Mg2+ mg/l 30 100 8 11 COD mg/l No guidelines - 29 12 BOD mg/l - 2 <5 13 DO mg/l - 6 5.2 14 Taste* ------- Agreeable Agreeable Agreeable 15 Odor ------- Agreeable Agreeable Agreeable 16 TSS mg/l <10 <10 <10 17 O&G mg/l N. D. N. D. N. D. 18 Lead as Pb* mg/l 0.01 No Relaxation N. D. 19 Color Pt. Co.
Unit 5 15 0
20 Cyanide as (CN)* mg/l 0.05 No Relaxation N. D. 21 Fluoride as F mg/l 1.0 1.5 N. D. 22 Nitrate (NO3) mg/l 45 No Relaxation N. D. 23 Sulphate as SO4 mg/l 200 400 13 24 Phenolic Compound* mg/l 0.001 0.002 N. D. 25 Copper as (Cu)* mg/l 0.05 1.5 N. D. 26 Cadmium as (Cd)* mg/l 0.003 No Relaxation N. D. 27 Manganese as Mn* mg/l 0.1 0.3 N. D. 28 Zinc as (Zn)* mg/l 5 15 N. D. 29 Chromium as (Cr) mg/l 0.05 No Relaxation N. D. 30 Boron mg/l 0.5 1.0 N. D. 31 Iron mg/l 0.3 No Relaxation N. D. 32 Phosphate* mg/l 0.5 1 N. D. 33 Residual chlorine mg/l 0.2 1 Nil 34 Silica mg/l 0.1 0.4-1 <0.01 35 Sulphide mg/l 0.05 No Relaxation Nil
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 100 of 110
- Results of Soil Quality Sampling/Monitoring:
* not under NABL Scope
Sr. No.
Parameter Unit Results
900 1800 2700 3600
1. pH (1:2) ---- 6.8 6.8 6.9 6.9
2. EC (1:2) µS/cm 286 310 310 298
3. Water Soluble Salts* mg/kg 1399 1520 1519 1459
4. Chloride as Cl mg/kg 159 160 159 142
5. Total Hardness* mg/kg 389 432 691 475
6. Organic Matter % 1.06 1.06 1.09 1.09
7. Sodium Oxide mg/kg 139 140 143 141
8. Potassium Oxide mg/kg 59 59 58 58
9. Calcium Oxide* mg/kg 97 48 73 73
10. MgO* mg/kg 87 140 227 140
11. Specific Gravity* g/ml 2.0 2.0 2.0 2.0
12. Water Holding Capacity % 42 41 40 40
13. Moisture % 13 12 11 12
14. ORP* mV 80 82 84 80
15. Total soluble Sulphate mg/kg 40 40 30 30
16. Available Nitrogen mg/kg 0.85 0.86 0.87 0.86
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 101 of 110
d) C/o 66/220 kV, 80/100 MVA transformer in 400/220 kV Gumma substation - Results of Air Quality Sampling/monitoring:
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 102 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 103 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 104 of 110
- Results of Noise Quality Sampling/monitoring:
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 105 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 106 of 110
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 107 of 110
- Results of Water Quality Sampling/monitoring:
* not under NABL Scope - limits are in reference to IS 10500:2012 - N.D mean not detected
Sr. No.
Parameter Unit Acceptable limit
Permissible limit
Results Ground Water Soil Water 900 1800 2700 3600
1 pH ---- 6.5-8.5 No Relaxation 7.0 7.0 6.9 6.9 2 Electrical
Conductivity µS/cm 750 0-2000 491 469 478 481
3 Turbidity NTU 1 5 0 0 0 0 4 TDS mg/l 500 2000 314 300 306 308 5 Chloride as Cl mg/l 250 1000 19 20 21 19 6 Acidity mg/l 200 600 14 12 12 14 7 Alkalinity mg/l 200 600 39 37 35 35 8 Total hardness as
CaCO3
mg/l 200 600 136 136 138 138
9 Calcium as Ca mg/l 75 200 34 34 35 35 10 Magnesium as Mg2+ mg/l 30 100 13 13 13 13 11 COD mg/l No guidelines - 16 18 21 19 12 BOD mg/l - 2 <5 <5 <5 <5 13 DO mg/l - 6 5.8 5.6 5.5 5.4 14 Taste* ------- Agreeable Agreeable Agreeable 15 Odor ------- Agreeable Agreeable Agreeable 16 TSS mg/l <10 <10 <10 <10 <10 <10 17 O&G mg/l N. D. N. D. N. D. N. D. N. D. N. D. 18 Lead as Pb* mg/l 0.01 No Relaxation N. D. N. D. N. D. N. D. 19 Color Pt. Co.
Unit 5 15 0 0 0 0
20 Cyanide as (CN)* mg/l 0.05 No Relaxation N. D. N. D. N. D. N. D. 21 Fluoride as F mg/l 1.0 1.5 N. D. N. D. N. D. N. D. 22 Nitrate (NO3) mg/l 45 No Relaxation N. D. N. D. N. D. N. D. 23 Sulphate as SO4 mg/l 200 400 18 N. D. 20 18 24 Phenolic
Compound* mg/l 0.001 0.002 N. D. N. D. N. D. N. D.
25 Copper as (Cu)* mg/l 0.05 1.5 N. D. N. D. N. D. N. D. 26 Cadmium as (Cd)* mg/l 0.003 No Relaxation N. D. N. D. N. D. N. D. 27 Manganese as Mn* mg/l 0.1 0.3 N. D. N. D. N. D. N. D. 28 Zinc as (Zn)* mg/l 5 15 N. D. N. D. N. D. N. D. 29 Chromium as (Cr) mg/l 0.05 No Relaxation N. D. N. D. N. D. N. D. 30 Boron mg/l 0.5 1.0 N. D. N. D. N. D. N. D. 31 Iron mg/l 0.3 No Relaxation N. D. N. D. N. D. N. D. 32 Phosphate* mg/l 0.5 1 N. D. N. D. N. D. N. D. 33 Residual chlorine mg/l 0.2 1 Nil Nil Nil Nil 34 Silica mg/l 0.1 0.4-1 <0.01 <0.01 <0.01 <0.01 35 Sulphide mg/l 0.05 No Relaxation Nil Nil Nil Nil
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 108 of 110
- Results of Soil Quality Sampling/Monitoring:
* not under NABL Scope
Sr. No. Parameter Unit Results 900 1800 2700 3600
1. pH (1:2) ---- 7 7 7.1 7
2. EC (1:2) µS/cm 327 310 306 318
3. Water Soluble Salts* mg/kg 1599 1520 1500 1559
4. Chloride as Cl mg/kg 142 142 124 142
5. Total Hardness* mg/kg 475 562 561 475
6. Organic Matter % 0.84 0.81 0.81 0.81
7. Sodium Oxide mg/kg 129 128 128 127
8. Potassium Oxide mg/kg 61 63 63 63
9. Calcium Oxide* mg/kg 97 97 73 73
10. MgO* mg/kg 122 157 175 140
11. Specific Gravity* g/ml 2.0 2.0 2.0 2.0
12. Water Holding Capacity % 36 37 37 36
13. Moisture % 13 14 14 13
14. ORP* mV 82 84 85 88
15. Total soluble Sulphate mg/kg 40 30 40 40
16. Available Nitrogen mg/kg 0.98 0.98 0.99 0.99
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 109 of 110
Annexure-XVII: - Grievance Redressal Committee
Environmental Monitoring Report (EMR) Tranche-III
HP Power Transmission Corporation Ltd. Page 110 of 110
Annexure-XVIII: - Environment & Social Monitoring Cell (ESC) of HPPTCL Environment and Social monitoring Cell (ESC) of HPPTCL has been constituted at the corporate office of the HPPTCL as given below.