  • www.gov.uk/hs2

    HS2 – Britain’s new high speed railwaySusan Bridges, Engagement ManagerAlan Payne, Project ManagerAndy de Bell, BBV Community Engagement ManagerAlex Esslemont, Engagement Manager

    8 February 2018

  • Agenda items

    • Key Contacts

    • Programme update

    • MWCC Introduction

    • Traffic management

  • Area North Engagement Team & Partners

    3

    Jonathan LordSenior Engagement Manager – Area North

    Susan BridgesEngagement Manager –

    Joan GoodenEngagement Executive

    Tahir Ahmed Engagement Manager –

    Rachel JohnsonEngagement Manager -

    Rachna ShahEngagement Executive

    EWC

    Alex

    Esslemont

    Laing

    O’Rourke and

    Murphy &

    Sons (JV)

    MWCC

    Andy de Bell

    Balfour

    Beatty Vinci

    MWCC

    Geoff

    Durand

    Balfour

    Beatty Vinci

    EWC - Enabling Works Contractor• Surveys, environmental & habitat creation, highway works, compound set up

    MWCC - Main Works Contractor • Design and construction of main assets – embankments, cuttings, viaducts, bridges, tunnels

  • Programme

    2018 2019 2020 2021 2022 2023 2024 2025 2026

    1 Surveys and bat house

    2 A46 compound

    3 Outline Design

    4 Detailed design

    5 Main Works

    6 Env. works

    7 Retaining Wall

    8 Highway works – Ashow Rd

    9 Highway works – Stoneleigh Rd

    10 A46 bridge

    9 Rail Systems

    High Level Programme

  • Construction Work in the vicinity of Stoneleigh PC

    Bat house

    Woodland Planting

    Ashow Road BridgeB4115

    Signalisation of A46 junction if WCC new roundabout does not process

    Stoneleigh Road bridge & new entrance to Stoneleigh Park including new roundaboutB4113

    Environmental works to create new habitat

    New A46 bridge Temporary diversion of A46 to enable constructionTemporary new southbound access from compound

    HS2 site compound and stockpile areas

  • A46 Improvements – Warwickshire County Council

    We are working closely with Warwickshire County Council & Stoneleigh Park.

    Opportunities to use new roundabout to reduce construction traffic impact

  • www.gov.uk/hs2

    MWCC Key Dates/ Programme Update

  • 8

    MWCC - Overall programme

    ADVANCE WORKS

    Video on GI now or with HS2 piece?

  • Stage One Gateway Process

    9

    Now

  • 10

    MWCC - Indicative Design & Construction Start Dates

    Key Asset

    Detail

    Design

    Start

    Indicative Construction

    Start date & duration

    B4113 alignment, overbridge, roundabout and Park access

    Q4 2019 2022

    Stoneleigh Park retaining wall Q2 2019 Q1 2020 to Q4 2022

    Stoneleigh Park overbridgesQ2 2019 &

    Q2 2020

    Q3 2020 until Q2 2021 & Q3 2021 to Q4

    2022

    River Avon Viaduct Q2 2019 Q3 2021 to Q3 2022

    B4115 underbridge Q2 2020 Q4 2021 to Q3 2022

    A46 OverbridgeQ4 2020 Finalising programme

  • www.gov.uk/hs2

    Traffic Management Strategy

  • Route-wide Traffic Management Plan

    HS2’s overall objectives for managing transport, traffic and highways for the delivery of the Project are set out within the RTMP.

    Code of Construction Practice

    Environmental Statement

    HS2 Phase 1 Act provisions

    Undertakings and Assurances

    Route-wide TMP

    Rights

    Obligations

    Practice

  • Predicted HS2 Traffic Flows from the Environmental Statement

  • HS2 Traffic Liaison Groups and Interfacing Meetings

    Formal consultation with WCC Highways over highway works and transport routes

  • Lorry Routes Management• We have a route wide Undertaking to ensure highest standards for vehicles – engagement with haulage/industry

    suppliers• All lorries to be Euro6 standard by 2020 – highest environmental standards with lowest emissions and highest fuel

    efficiency• Lorry routes are set out in the Environmental Statement & agreed with the Highway Authority – with routes signed• A vehicle monitoring system will record vehicles entering sites in order to measure and assure that the sites do not

    breach flow limits.• HS2 Lorries will have indicators for ease of recognition• All lorries will have 360 degree or 4 way cameras recordable for four weeks• All drivers will be required to undertake urban rural driver safety training – new standards created • HS2 will monitor contractor performance

  • Thank you