Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Form-1, PreFeasibility Report, Mining Plan for Rough Stone S.F.No. 706 (Part)
Kuppam village, Aravakurichi Taluk, Karur District, Tamil Nadu of
Tmt.S.Tamilselvi,(Extent – 3.36.0 Ha).
PREFEASIBILITY REPORT
CHAPTER -1
EXECUTIVE SUMMARY
1.1. INTRODUCTION OF THE PROJECT /ACKGROUND INFORMATION:
Tmt.S.Tamilselvi, has applied for grant quarrying lease to quarry Rough Stone deposit over an
extent of 3.36.0 Ha. in S.F.No 706 (part) in Kuppam Village, Aravakurichi Taluk, Karur District, Tamil Nadu
for 5 years.
The District Collector, Karur vides their letter Rc.888/Mines/2016 Dated 05.01.2017 have conveyed
its decision to grant lease over an extent of 3.36.0 Ha. in S.F.No 706 (part) in Kuppam Village, Aravakurichi
Taluk, Karur District and requested Tmt.S.Tamilselvi, to submit the approved mining plan through the
Department of Geology and Mining, Karur and also obtain Environmental Clearance from SEIAA/DEIAA.
Department of Geology and Mining, Karur vides their letter RC. No 888Mines/2016 Dated 21.02.2017
have approved the Mining Plan over extent of 3.36.0 Ha. in S.F.No 706 (part) in Kuppam Village,
Aravakurichi Taluk, Karur District Tamil Nadu. (Copy of Mining plan approval letter enclosed)
Tmt.S.Tamilselvi, has proposed to quarry Rough Stone for 69941m3/year from this lease applied area
by open cast semi- mechanized mining technique. This Prefeasibility report is prepared towards obtaining the
Environmental Clearance.
As per MOEF O.M. No.L - 11011/47/2011 –A.II (M) dated 18th
May, 2012, leases of minor
minerals also require environmental clearance. For getting environmental clearance, depending on the nature
magnitude and capacity, the projects are categorized as “A” Category & “B” Category. “A”
Category projects have to be cleared by MOEF while “B” Category by the State/District
Environmental Impact Assessment Agency (SEIAA/DEIAA). This being a small quarry of
just 3.36.0 Ha (< 25 Ha) it can be treated as B-2 category.
1.2 DETAILS OF THE AREA:
It is Own Patta land in S.F.No 706 (Part).
2.1. PROJECT DETAILS:
2.1.1 SITE DESCRIPTION:
Salient details of the site &its environs are as follows:
SALIENT ASPECTS OF SITE AND ITS ENVIRONS
1. Name of the Project Rough Stone
2. Project Proponent Tmt.S.Tamilselvi,
3. ML area 3.36.0Ha
4. Land use
Sl.
No. Land Use
Present
Area (Hect)
Area in use during
the quarrying
period (Hect)
1. Area Under
Quarrying Pit
2.30.0 2.70.57
2 Infrastructure 0.01.0 0.02.0
3 Roads 0.01.0 0.02.0
4 Unutilized 1.04.0 0.61.43
Total = 3.36.0Ha 3.36.0Ha
5. Nearest Railway station Karur - 13kms
6. Nearest Airport Trichy -120 Kms
7. Nearest major water bodies Nil
8. Nearest Town / city K.Paramathi
9. Nearest Village
Direction Village Distance in
Kms
Population
North Salliyapalliyam 1.5km 300
East Kalipalayam 1km 50
South Velapa Goundanoor 1.5km 60
West Velayuthampalayam 1.5km 100
10. Notified Arachaeologically important places,
Monuments
Nil
11. Local Places of Historical and Tourism
interest
Nil
12. Environmental sensitive area , Protected area
(Tiger reserve, elephant reserve, Biospj
Heres, National parks, Wildlife sanctuaries,
Community reserves and conservation
reserves)
Nil
13. Reserved / Protected Forests Nil
14. Defence installations Nil
15. Seismic Zone Nil
16. Other Industries in the area Nil
2.1.2 PROJECT DESCIPTION
Salient of the project are as follows:
1. Production Capacity 69941m3 Year for Rough Stone
2. Geological reserves 681502m3for Rough stone
3. Total waste The overburden of the applied area Topsoil is Along
the lease boundary, so reject (Back filling) centre part of
the lease.
. Topsoil = 445m³
Dump = 7137
TOTAL = 7582m³
4. Method of Mining: Opencast Shallow mining with drilling & blasting.
5. Main mining equipment Hydraulic excavator, jack hammers, Tippers,
6. Bench height & Slope Bench height of 5m and bench width of 5m is proposed
for Rough Stone.
7. Life of mine 69941m3Year for Rough stone. Total Mineable reserves
are 349706m3.
Life of the Mine = 349706m3
/ 69941m3
= 5years.
8. Man power 18 including managerial staff
9. Water Requirement & source 2.5 KLD will be met from the bore well within the ML
area or through tankers.
Drinking & Domestic
Purposes (in KLD)
0.750 KLD
Dust Suppression (in KLD) 1.500 KLD
Green belt (in KLD) 0.250 KLD
Total 2.500 KLD
10. Infrastructure Mine office, store room, toilet, first-aid room and,
magazine will be provided on semi- permanent structures
with the lease area. Portable drinking water can be
transported to the work site in tippers or can be at from
bore well.
11. Use of Rough Stone and Gravel Rough Stone and Gravel are used mainly in construction
industries.
12. Environmental status
Being a small mine, impact of mining on environment
will be negligible.
The mining operation will provide more employment to
the rural people and environment friendly operations.
2.2 DISPOSAL OF WASTE:
The wastes (2%) are generated during the mining period is 7137m3
shall be proposed to dump in the
along lease boundary.
Year wise production Wastes generates are tabulated as under,
2.3 LAND USE PATTERN:
The area is a rural area. Rough Stone exposes in the lease area and it is strewn with boulders of various
sizes ranging from a few cm to one to half meter in diameter. The terrain is almost flat and it is cover with
Topsoil of 0 to 2 m. except some small bushes there are no other trees in the applied area.
Depth of mining is taken as 31m from the surface. Leaving the Gravel and weather rock, the thickness
of Rough Stone considered now for economical extraction is 48m. Since there is mineral occurrence below this
depth also, mining activity may continue in future below this depth. As such no backfilling of mined out void is
suggested now.
The post mining land use plan/ Conceptual plan along with cross section is shown as mining plan.
3.1. SITE ANALYSIS:
3.2. CONNECTIVITY:
K.Paramathi – Punnan 3 Km
Quarry site is located at Kuppam Village in West side distance of 2kms
3.3. PROJECT LATOUT IN RELATION TO PRIME NATURAL FEATURES:
There is no declared biosphere, wild life Sanctuaries, or tiger Sanctuary or migrating corridor or
Coastal Zone in the Zone and 10km buffer zone. As already mentioned, the entire mine lease area is Patta land
The applicant has obtained tender from the government. There is no habitation or other structures
like HT electric lines, water bodies in the lease area.
4.1. PLANNING CONCEPT:
Rough stone mined from this quarry will meet the domestic and export demands. The production and
method of mining is planned considering the geological factors, availability of proven technology, demand for
the material etc. Safety barriers as per State Government order is left in the planning stage itself.
4.2. GREENBELT:
Green belt will be developed in the safety zone area etc, and at all possible places. Local species will be
used for plantation.
5.1 REHABILITATION AND RESETTLEMENT (R&R) PLAN:
The entire quarry lease areas of 3.36.0 Ha are Patta land project proponent. The area is totally barren.
There are no human habitations also. As such no rehabilitation and resettlement plan is involve
6.1. PROJECT SCHEDULE AND COST ESTIMATES:
As soon as environmental clearance and other statutory clearance are obtained, the mining operations
will be commenced. The project cost would be around Rs. 26,00,000/- for deployment of machinery and
creation of infrastructural facilities like approach road, Mine Office / Workers Shed, first Aid Room etc.,
Including electrifications and water supply.
7.1 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION)
The proposed Rough Stone quarry of Tmt.S.Tamilselvi, will bring prosperity and improvements in
physical and social infrastructures in the area like
Direct employment to about 18 persons
Indirect employment to more than 100 persons
Financial gains for the state and central governments, through collection of various taxes like Royalty,
cess, etc.
Increase in General Awareness of the People
Improvement of the General Living Standard of the people in the vicinity
Overall Improvement in HDI (Human Development Index)
Growth of Allied Industries in the Area.
Reduction in migration of local people and at the same time increase in Inflow from outside.
Improvement in Per Capital Income.
Providing certain faculties’ for the local schools and Panchayat
In short, the working mining project will region in the fields of potential employment opportunities,
improved per capita for local people , improved social welfare facilities like infrastructural build – up ,
etc.
A meticulously well planned Environmental Management Plan, with various programme schedules and
timely execution objectives will ensure that the future environmental quality in the area will be maintained
within statutory limits.
With proper environmental management strategy, it is possible that industrial growth, if properly
planned with all environmental concerns and appropriate remedial measures can go a long way to improve life
pattern and living conditions of the local community around the project.
In view of above factors, the proposed project is worthy of approval for improving the social, physical
and financial status of the region, the state and the country as a whole.
CHAPTER-II
INTRODUCTION OF THE PROJECT / BACK GROUND INFORMATION
2.1. IDENTIFICATION OF PROJECT AND PROJECT PROPONENT:
Tmt.S.Tamilselvi, has applied for grant quarrying lease to quarry Rough Stone - Quarry deposit over
an extent of 3.36.0 hectares of Patta land in S.F.No. 706 (PART) of Kuppam Village, Aravakurichi Taluk,
Karur District, Tamil Nadu for 5 years.
The District Collector, Karur vide their letter Rc.888/Mines/2016 Dated 05.01.2017 have conveyed
its decision to grant lease over an extent of 3.36.0 hectares of Patta land in S.F.No. 706 (PART) of Kuppam
Village, Aravakurichi Taluk, Karur District Tamil Nadu and requested Tmt.S.Tamilselvi to submit the
approved mining plan through the Department of Geology and Mining, Karur and also obtain Environmental
Clearance from SEIAA/DEIAA.
Department of Geology and Mining, Karur vide their letter Rc. No. 888/Mines/2016 Dated 21.02.2017
have approved the Mining Plan over an extent of 3.36.0 hectares of Patta land in S.F.No. 706 (PART) of
Kuppam Village, Aravakurichi Taluk, Karur District Tamil Nadu (Copy of Mining plan approval letter
Enclosed)
Tmt.S.Tamilselvi, has proposed to quarry Rough Stone for 69941m3/year from this lease applied
area by open cast semi- mechanized mining technique. This feasibility report is prepared towards obtaining the
Environmental Clearance.
As per MOEF O.M. No.L - 11011/47/2011 –A.II (M) dated 18th
May, 2012, leases of minor
minerals also require environmental clearance. For getting environmental clearance, depending on the nature
magnitude and capacity, the projects are categorized as “A” Category & “B” Category. “A” Category projects
have to be cleared by MOEF while “B” Category by the State Environmental Impact Assessment Agency
(SEIAA)/(DEIAA). This being a small quarry of just 3.36.0 Ha (> 25 Ha) it can be treated as B-2 category.
1.2 DETAILS OF THE AREA:
Own Patta Land in S.F.No. 706 (PART) - Stands registered in the name of Tmt.S.Tamilselvi, The
applicant has obtained tender from the government.
2.1.2. PROJECT PROPONENT:
Name : Tmt.S.TAMILSELVI,
Address : Tmt.S.TAMILSELVI,
W/O.SABAPATHI,
16B, GANESHA NAGAR 1ST STREET
INAM KARUR,
KARUR TALUK,
KARUR DISTRICT.
2.2MINING LEASE:
State District Panchyat / Union Taluk Village S.F.Nos Extent in
hectares
Tamil Nadu Karur Kuppam/
K.Paramathi
Aravakurichi Kuppam 706 (PART) 3.36.0 Ha
Total = 3.36.0 Ha
The period of mining lease is 5 years. The Quarry lease area is shown in lease plan (Plate – II in the
Mining Plan).
2.3 NEED FOR THE PROJECT &ITS IMPORTANCE TO THE COUNTRY AND OR REGION:
Rough Stone is used in the constructions industries and road projects. The smaller domestic sales will
also bring good returns financially to state governmental in the form of taxes, cesses, duties, etc.,
As the Rough Stone mining operations in the proposed mine will employ about 18 persons directly and
about 100 persons on indirect basis through allied opportunities in logistics, trading, repining works etc good
employment potential will arise in this internal rural backward area, which will provide a great fillip for raising
income levels and standards of living in the area.
CHAPTER-III
PROJECT DESCRIPTION
3.1. TYPE OF PROJECT:
This will be an Open cast ,semi-mechanized mine to mine about 69941m3/year,out of which is about
349706m3 will be the recoverable reserves of Rough Stone .
3.2. LOCATION:
This project is for Quarrying of Rough Stone over an extent of 3.36.0Ha. In S.F.No 706 (Part)of
Kuppam Village, Aravakurichi Taluk, Karur District Tamil Nadu. The area Lies in the North Latitude
10°58'44.7872"N, 10°58'47.0098"NLongitude 77°55'56.2834"E, 77°55'56.1131"Efalls in the survey of India
Toposheet No. 58 F/13,
3.3. PROJECT DESCRIPTION:
3.3.1. GEOLOGY:
REGIONAL GEOLOGY:
Karur District is underlain by the wide range of metamorphic rocks of peninsular gneisses complex.
These rocks are extensively weathered and overlain by the recent valley fills and alluvium at places. The
geological formations found in the district are Archaean rocks like Gneisses, Granites, Charnockites basic
granulites and calc-gneisses. The younger formations are Quartz veins and pegmatite.
Description
Age Rock Formation
Recent to Sub recent Soil, Alluvium
Archaean Granites, basic granulites, Peninsular Gneiss, Calc
Gneiss and Charnockites
GEOLOGY OF THE AREA
1. The area is mainly composed of Archaean crystalline metamorphic complex.
2. The rock type noticed in the area for lease is Charnockite which contains mostly Quartz and Feldspar
with some ferromagnesian minerals.
3. The Charnockite is part of peninsular Gneisses, a high grade metamorphic rock.
4. The general geological succession of the area is given as under
Age Rock Formation
1. Recent to Sub recent Soil, Alluvium
2. Archaean Charnockites
3. Archaean Peninsular Gneiss, and Calc Gneiss
3.3.2. RESERVES:
3.3.2.1 EXPLORATION:
There is no exploration previously carried out in the lease applied area.
3.3.2.2 METHOD OF ESTIMATION OF RESERVES:
The geological and mineable reserves are estimated by cross-sectional method. Depth of mining is
taken as 31m from the surface
3.3.3 GEOLOGICAL RESERVES & MINEALE RESERVES:
The geological reserves are estimated for the area by the Cross-Sectional method is as 681502m3 upto
the estimated depth. The reserves details are as follows:
ESTIMATION OF GEOLOGICAL RESERVES FOR ROUGH STONE:
Geological Reserves:
The Geological reserve is estimated as 681502m3by area cross sectional method.
GEOLOGICAL RESERVES
Section Bench length
in (m)
Width
in (m)
Depth
in (m)
Volume
In M3
Geological
Reserves in m3 @
98%
Mine waste
in m3 @
2%
Top
Soil in
m3
XY-AB
I 18 45 1 810
810
II 18 45 5 4050 3969 81
III 18 45 5 4050 3969 81
IV 104 160 5 83200 81536 1664
V 104 160 5 83200 81536 1664
VI 104 160 5 83200 81536 1664
VII 104 160 5 83200 81536 1664
Total 340900 334082 6818 810
XY-CD
I 30 31 1 930 911 19 930
II 30 31 5 4650 4557 93
III 30 31 5 4650 4557 93
IV 144 151 5 86070 84349 1721
V 144 151 5 86070 84349 1721
VI 144 151 5 86070 84349 1721
VII 144 151 5 86070 84349 1721
TOTAL 354510 347420 7090 930
GRAND TOTAL 695410 681502 13908 1740
Recoverable Reserves
The mineable reserves and the recoverable reserves are 349706m3 respectively
MINEABLE RESERVES
Section Bench length
in (m)
Width
in (m)
Depth
in (m)
Volume
In M3
MINEABLE
Reserves in m3 @
98%
Mine waste
in m3 @
2%
Top
Soil in
m3
XY-AB
I 11 7 1 77 77
II 11 7 5 385 377 8
III 6 2 5 60 59 1
IV 87 112 5 48720 47746 974
V 82 102 5 41820 40984 836
VI 77 92 5 35420 34712 708
VII 72 82 5 29520 28930 590
TOTAL 156002 152807 3119 77
XY-CD
I 23 16 1 368 361 7 368
II 23 16 5 1840 1803 37
III 18 11 5 990 970 20
IV 96 126 5 60480 59270 1210
V 91 116 5 52780 51724 1056
VI 86 106 5 45580 44668 912
VII 81 96 5 38880 38102 778
TOTAL 200918 196900 4018 368
GRAND TOTAL 356920 349706 7137 445
3.3.4. SELECTION OF MINE BOUNDARY:
The mine boundary is demarcated in line with the following conditions / stipulations laid down by the
state government in their precise area letter on 05.01.2017
I. Mining plan shall be prepared by incorporating all the details as proposed in the draft
Tamilnadu Minor Mineral Conservation & Development Rules 2010.
II. Mining plan shall be prepared by incorporating all the details as proposed in State
Environment Impact Assessment Authority.
3.4. MINING METHOD:
Open cast method of semi –mechanized mining will be adopted to quarry the Rough stone.
3.4.1 BENCH DESIGN PARAMETERS:
Rough Stone benches will be formed to a height of 5m and width not less than 5m for movement of
machineries and slope shall not be more than 60º for waste bench and therefore the working face is designed to a
height of 5m and the width not less than 5 - 10m and the working slope will be vertical, however the final slope
will be 45º while abutting the ultimate pit limit. Construction of parapet as a fencing around such ultimate pit
limit on top of opencast workings will be arranged to safeguard the mine from inadvertent entry and hazards.
3.4.2 PRODUCTION RATE AND LIFE OF MINE:
The mineable reserves is estimated by cross-sectional method having considered the recovery factor,
depth of mining, safety barriers etc., The Rough stone mineable reserves is estimated as 349706m3 and the
recoverable reserves is 349706m3.
The Rough Stone life of the mine is computed as 5 years at a production rate of 69941m3 per annum.
The development involves only removal of small amount of rejects (i.e. 2%). The annual production is
proposed as 69941m3 for the proposed five years and generation of rejects are shown as under,
Year Wise Production for Rough Stone:
ROUGH STONES PRODUCTION DETAILS AS FOLLOWS:
The average proposed rate of production of Rough stone is about 69941m3 per year
YEARWISE PRODUCTION
YEAR Section Bench length
in (m)
Width
in (m)
Depth
in (m)
Volume
In M3
Mineable
Reserves in
m3 @ 98%
Mine
waste in
m3 @
2%
Top
Soil
in m3
I-YEAR XY-AB
I 11 7 1 77
77
II 11 7 5 385 377 8
III 6 2 5 60 59 1
IV 87 112 5 48720 47746 974
V 44 102 5 22440 21991 449
II-YEAR
V 38 102 5 19380 18992 388
VI 77 92 5 35420 34712 708
VII 40 82 5 16400 16072 328
III-YEAR
VII 32 82 5 13120 12858 262
XY-CD
I 23 16 1 368 361 7 368
II 23 16 5 1840 1803 37
III 18 11 5 990 970 20
IV 87 126 5 54810 53714 1096
IV-YEAR
IV 9 126 5 5670 5557 113
V 91 116 5 52780 51724 1056
VI 23 106 5 12190 11946 244
V-YEAR VI 63 106 5 33390 32722 668
VII 81 96 5 38880 38102 778
TOTAL 356920 349706 7137 445
Topsoil Development
There is topsoil development in this Along Lease applied area.
3.4.3 PROPOSED MECHINERIES:
The following machineries are proposed exclusively for the development for the development and
production works at this mine:
S.No Machineries Numbers Unit Size/Capacity Make
1
Jack hammer with 6
Mm
32Hand held
Atlas
Copco
2 Compressor
Hydraulic excavator
1 M3 1.7 Ex 300
3 Tipper 2 MT 10 Ashok
Leyland
The above machineries are adequate to meet out the simultaneous development and production
schedule.
3.4.4. BLASTING:
The massive formation shall be broken into pieces of portable size by drilling and blasting using jack
hammers and shot hole blasting. Powder factor of explosives for breaking such hard rock shall be in the order of
6 to 7 tonnes per K.g of explosives. Blasting parameters are as follows.
Diameter of the hole : 32-36 mm
Spacing : 60 Cms
Depth : 1 to 1.5m
Charge / Hole : D.Cord with water or 70 gms of gun powder or Gelatine.
Pattern of hole : Zig Zag
Inclination of hole : 700 from the horizontal.
Quantity of rock broken : 233MT x 2.6
= 1.17 MT
Blasting efficiency @ 95% : 1.17 x95% = 1.05MT / hole
Charge per hole : 140 gms of 25mm dia cartridge
Quantity of rock broken per day : 577 MT per day
3.4.5. DISPOSAL OF WASTE:
The wastes (2%) are generated during the mining period is 7137m3
shall be proposed to dump in the
along lease boundary.
3.4.6 USES OF PRODUCTS FROM QUARRY:
Rough Stone is mainly used in construction industries.
3.5 LAND USE PATTERN:
The area is a rural area. Rough Stone exposes in the lease area and it is strewn with boulders of various
sizes ranging from a few cm to one to half meter in diameter. The terrain is almost flat and it is cover with a
Gravel of 0 to 2 m. Except some small bushes there are no other trees in the applied area. Depth of mining is
taken as 32 m from the surface. Since there is mineral occurrence below this depth also, mining activity may
continue in future below this depth. As such no backfilling of mined out void is suggested now. The post
mining land use plan/ Conceptual plan along with cross section is shown as mining plan.
3.6 REQUIREMENTS:
3.6.1 Man Power:
Total manpower required will be 18 on direct basis. Indirectly more than 100 persons can derive
benefits in allied services like logistics, polishing, loading/ unloading repair works trading etc.
3.6.2 Water:
About 2.5 KLD water will be used for dust suppression, green belt and domestic sanitary needs.
Drinking & Domestic Purposes (in KLD) 0.750 KLD
Dust Suppression (in KLD) 1.500 KLD
Green belt (in KLD) 0.250 KLD
Total 2.500 KLD
3.6.3 Effluent System:
The only effluent arising from project consists of domestic water, to the tune of about 5 KLD which is
discharged into septic tanks with soak pits.
3.6.4 Electricity requirement:
No electricity is needed for quarry operations etc as only diesel operated mining machinery are used for
quarrying. The mining work is restricted to one general shift during daytime only. However, the power
requirement of the administrative buildings, roads etc are met from state grid. Besides, standby generators can
be used to meet the negligible power requirement of the mines.
3.7. SITE SERVICES:
The simple methods adopted and the limited scale of activities involved in Rough Stone dimensional
stone quarrying does not require huge worship facilities. Major Machinery repair works are attended at Karur-20
Kms and minor repairs are carried out by the company’s staff at the quarry site itself. Mine office, store room,
toilet, first – aid room and, magazine will be provided on semi- permanent structures within the lease area.
3.8 SCHEMATIC REPRESENTATION FOR MINING AND PROCESSING OF ROUGH STONE
LAND ITS FEASIBILITY:
The line diagram of Mining Operation is given below:
Drilling by Jack Hammers
Blasting
Segregation
Loading by tipper /trucks to the
crushing units
CHAPTER-IV
SITE ANALYSIS
4.1 CONNECTIVITY:
K.Paramathi- Punnam= 3kms
Quarry site is located at Kuppam village in west side at a distance of 2 kms
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP:
The area is a rural area. Rough Stone exposes in the lease area and it is strewn with boulders of various
sizes ranging from a few cm to one to half meter in diameter. The terrain is almost flat and it is cover with a
Topsoil of 0 to 2 m. except some small bushes there are no other trees in the applied area. Crops are only
seasonal cultivation with lift irrigation is practiced. The main crops are groundnut, maize, soybeans and cereals.
4.3 TOPOGRAPHY:
Rough Stone is located in the North southern side is elevated to a height of 1m from the regional level
as a exposure in few places. Topsoil is capping to a depth of 0 -2 m on the lower side of the area. There are no
HT Electric lines located in within a radius of 500m. Temperature of the region is reported to be 30 ºC to a
maximum of 43º C during summer. Rain fall of this area is about 700 mm during monsoons in a year. Regional
crops are ragi, paddy and maize. There are no monuments or area of public interest is found in the vicinity.
4.4 PROJECT LAYOUT IN RELATION TO IMPORTANT NATURALFEATURES:
There are No declared biosphere, wild life Sanctuaries, or tiger Sanctuary or migrating corridor or
Coastal Zone and 10km buffer Zone
As already mentioned, the entire mine lease area is Own Patta lands in lessees possession .There no
habitation or other structures like HT electric lines, Water bodies in the Patta land.
1 Nearest villages
Direction Village Distance in
Kms
Population
North Salliyapalliyam 1.5km 300
East Kalipalayam 1km 50
South Velapa Goundanoor 1.5km 60
West Velayuthampalayam 1.5km 100
2 Nearest Major Water bodies Nil
3 Notified Archaeologically important
places ,monuments
Nil
4 Local Places of Historical and
Tourism Interest
Nil
5 Environmental sensitive areas ,
Protected areas as per Wild life
Protection Act,1972
(Tiger reserve ,Elephant reserve ,
biospheres’ ,National Parks ,Wild life
Sanctuaries ,community reserves and
conservation reserves )
Nil
6 Reserved /Protected Forests Nil within 10 Km radius
7 Defence Installations Nil within 10km radius
8 Seismic Zone Zone –II (lease active)
9 Other Industries in the area No other industries in this area.
Index plan showing the features within 10km radius is given as Figure No.7
4.5 EXISTING INFRASTRUCTURE:
The area is well accessible by road .The mining work is restricted to one general shift during
daytime only .Major Machinery repair Works are attended at Karur town (20km) and minor repairs are carried
out by the company’s staff at the quarry site itself .Mine office ,store room ,toilet ,first –aid room and ,
magazine will e provided on semi –permanent structures within the lease area .
4.6 CLIMATIC SCENARIO:
The area receives rainfall about 700 mm/per annum and the rainy season is mainly from Oct –Dec.
The summer is hot with maximum temperature of 43°C and winter records a minimum temperature of
30°C.
4.7 SOIL STATUS:
The Gravel is in red colour and thickness of the soil is 0-2 m and followed weathered pediments. The
Rough Stone and Gravel is Overlain by Weathered Formation.
4.8 SOIL INFRASTRUCTURE:
The Project area and its immediate surroundings do not contain any human habitations,
1. Post Office K.Paramathi – 5kms
2. Police Station K.Paramathi – 5kms
3. Government Hospital K.Paramathi – 5kms
4. DSP Office Karur – 20kms
5. Nearest Railway Station Karur – 13kms
6. School K.Paramathi – 1kms
7. Nearest Airport Trichy – 120Kms
8. Nearest Seaport Chennai – 364kms
CHAPTER – V
PLANNING BRIEF
5.1 PLANNING CONCEPT:
Rough Stone mined from this quarry will meet the domestic demands. The production and method of
mining is planned considering the geological factors, availability of proven technology, demand for the material
etc. Safety barriers as per State Government order is left in the planning stage itself.
5.2 POPULATION PROJECTIONS:
The project will give employment opportunities to about 18 persons directly. Indirectly about 100
persons will find employment prospects in allied service sectors such as Rough Stone crushing units, logistics,
trading , etc.
While skilled persons for the project may have to be brought from outside initially, till local persons
attain proficiency in skilled operations, ultimately the nearby villagers may upgrade their operational skills for
finding good source of employment in the project late on.
5.3 LAND USE PLANNING:
The present land use of the entire mine lease area of 3.36.0 Ha is a Patta Land to project proponent.
The land use plans at the end of the mining period and in the ultimate stage of mining are described in para 3.5
chapters III earlier.
5.4 GREEN BELT PROPOSALS:
Green belt will be developed in the safety zone area etc, and at all possible places. Local trees like
Casuarinas, Eucalyptus, Neem, acacia, Tamarind etc will be planted along the western side lease boundary and
avenues as well as over Non- active dumps at a rate of 10 trees per annum with interval 5m in between. The rate
of survival expected to be 80% in this area. Land use and Afforestation plan is given Figure No.6
5.5 ASSESSMENT OF INFRASTRUCTURE DEMAND:
K.Paramathi- Punnam= 3kms
Quarry site is located at Kuppam village in west side at a distance of 2 kms
the logistics details of the product area as follows:
Rough Stone production : 69941 m3per annum
No of Working days per year : 300 days
No of Tipper loads per days : 25 Tipper loads
The existing roads are adequate to meet this negligible transport need.
5.6 AMENITIES AND FACILITIES:
Good site services will be set up in project area by establishing mine office, rest shelter, first aid room,
toilets etc.
Drinking water facilities will be on bore well supply basis to all operational personnel. Toilet facilities
will also be created through sewage pit and dispersion trench installations. Medical help on part time basis will
also be created to treat injured persons etc. Besides, occupational health problems will also be minimised
through proper pre-entry medical inspections and regular check – up thereafter during operational phase.
CHAPTER VI
PROPOSED INFRASTRUCTURE
6.1 INFRASTRUCTURAL LAYOUT IN MINING PROJECT AREA:
All necessary infrastructural facilities like mine office, rest shelter, first aid room, toilets etc will be
created for this project.
6.2 RESIDENTIAL AREA:
For the present limited scale of Mining operations, no residential areas are envisaged.
6.3 GREEN BELT:
As mentioned earlier in V- chapter, green belt will be raised along the inner boundary of ML area and
in all possible places
6.4 SOCIAL INFRASTRUCTURE:
The proposed project will give following employment prospects.
Direct basis - 18 persons
Indirect basis – More than 100 persons
The former category will be of skilled pattern and initially outside sources will be tapped. Later on,
through skill up-gradation, local community will also be benefitted.
The advent of the project will improve the social infrastructure through skills up-gradation, better
drinking water facilities, improvement in medical and educational services etc. As a result, the social
infrastructure in the area will improve considerably. Consequently the human development index of the area
will also go up.
6.5 CONNECTIVITY:
K.Paramathi- Punnam= 3kms
Quarry site is located at Kuppam village in west side at a distance of 2 kms
6.6 DRINKING WATER MANAGEMENT:
Drinking water facilities will be arranged from bore well within the lease or through tankers, as the
demand will be meagre at about 2.5 KLD.
Drinking & Domestic
Purposes (in KLD)
0.750 KLD
Dust Suppression (in
KLD)
1.500 KLD
Green belt (in KLD) 0.250 KLD
Total 2.500 KLD
6.7 SEWERAGE SYSTEM:
As there will be only about 18 persons during operational phase of project, the only effluent arising
from project consists of domestic waste, to the tune of about 2.5 KLD which is discharged into septic tanks with
soak pits.
6.8 INDUSTRIAL WASTE MANAGEMENT:
No industrial effluents or waste will arise from the project, except for solid waste, description of which
is given in para 3.3.8, Chapter – III. F.R
6.9 POWER REQUIREMENT, SUPPLY AND SOURCE:
As already mentioned the simple methods adopted and the limited scale of activities involved in Rough
Stone dimensional stone mining does not require high- tension electric power. The mining work is restricted to
one general shift during daytime only. No electricity is needed for quarry operations etc as mainly diesel
operated mining machinery are used for quarrying However, the power requirement of the administrative
buildings, roads etc can be met from state grid. Besides, standby generator will be available to meet the
emergency power requirement of the mines.
CHAPTER VII
REHABILITATION AND RESETTLEMENT (R&R) PLAN
7.1 The entire quarry lease area of 3.36.0Ha Patta land to project proponent. The quarry is totally barren.
There are no human habitations also. As such no rehabilitation and resettlement plan is involved.
CHAPTER VIII
PROJECT SCHEDULE AND COST ESTIMATES
8.1 TIME SCHEDULE FOR THE PROJECT:
As soon as environmental clearance and other statutory clearances are obtained the mining operations
will be commenced.
8.2 PROJECT COST AND ECONOMIC VIABILITY OF THE PROJECT
8.2.1 PROJECT COST:
The project cost would be around Rs. 26,00,000/- for deployment of machinery and creation of
infrastructural facilities like approach road, Mine office / Workers Shed, First Aid Room etc.., including
electrifications and water supply.
8.2.2 ECONOMIC VIABILITY:
Infact there will be a great demand for Rough Stone for construction industries. Hence, the economic
viability of the project will be greatly sustainable.
CHAPTER IX
ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION)
9.1 CONCLUSION:
The proposed Rough Stone quarry of Tmt.S.Tamilselvi, will bring prosperity and improvements in
physical and social infrastructures in the area like:
Direct employment to about 18 persons
Indirect employment to about 100 persons
Financial gains for the state and central governments, through collection of various taxes like royalty ,
cess, etc
Increase in General Awareness of the People.
Improvement of the General Living Standard of the People in the vicinity
Overall Improvement in HDI (Human Development Index)
Growth of Allied Industries in the Area.
Reduction in migration of local people and at the same time increase in Inflow from Outside.
Improvement in Per Capita Income.
Providing certain facilities for the local schools and panchayat.
In short, the working mining project will benefit this region in the fields of potential employment
opportunities, improved per capita income for local people, improved social welfare facilities like infrastructural
build – up, etc.
A meticulously well planned Environmental Management Plan, with various programme schedules and
timely execution objectives will ensure that the future environmental quality in the area will be maintained
within statutory limits.
With proper environmental management strategy, it is possible that industrial growth, if properly
planned with all environmental concerns and appropriate remedial measures can go a long way to improve life
pattern and living conditions of the local community around the project.
In view of above factors, the proposed project is worthy of approval for improving the social, physical
and financial status of the region, the state and the country as a whole.
Date: Signature of Project Proponent\Applicant
Place: Karur
Signature of Recognised qualified Person