Upload
khangminh22
View
1
Download
0
Embed Size (px)
Citation preview
TOTEM Status Report
E. Bossini1,2 ,on behalf of the TOTEM collaboration
145th LHCC open session03/03/2021
1 Università di Pisa, Italy2 INFN – Pisa Section, Italy
OUTLINE:
Publication update Tunnel services and Si-strip detectors New T2 detector status
E.Bossini 145th LHCC open session 4
Published on 17 December 2020
arXiv:2102.06945, CERN-EP-2020-229, submitted to PRD
E.Bossini 145th LHCC open session 5
pp cross-section @14 TeV
TOTEM pp cross-section measurements with the luminosity-independent method requires the simultaneous detection of the elastic and inelastic scattering events.
𝜎𝑡𝑜𝑡2 =
16𝜋
1 + 𝜌2ȁΤd𝑁𝑒𝑙 d𝑡 𝑡=0
𝑁𝑒𝑙 + 𝑁𝑖𝑛𝑒𝑙
LHC sector 45
ROMAN POTs(TOTEM/PPS)
LHC sector 56CMS central detector
nT2
Symmetric experimental setup w.r.t. the IP
Previous inelastic detectors T2 will be replaced by a new inelastic telescope based on scintillators (nT2) Elastic protons detected and
measured by the Si-strip detectors hosted in the TOTEM Roman Pots (RPOT)
E.Bossini 480th WGM, 10 December 2020 6
Main tunnel activities during LS2
Completed activities:
Detector Packages (DP) removed -> Si-strip ready for reinstallation in vertical RPOTs
RPOT “210 near” (qualified for high luminosity) successfully relocated @ “220 near”. New PPS timing detectors to be installed in “220 near” position – Sep 2019
Vertical realignment of the entire Long Straight Section LSS5 due to beam shift in Run3 – Sep 2019
Bake out sector 4-5 and 5-6 finished (sector valves closed) – Nov 2019
Upgrade of RPOT movement system – Nov 2019 Metrology for all RPOTs completed in joint
collaboration with BE-GM– Dec 2020.
RP station relocation
Q5
E.Bossini 145th LHCC open session 7
TOTEM Position Control System Upgrade
Main upgrade of the TOTEM Position Control System:
• Replacement of PXI crate with new PXIe-1084 • Replacement of Real Time Controller with new PXIe-8840• Upgrade of 7 old PXI-FPGA 7833R (no more supported by
NI) with newer 7856 R• New FPGA works with different voltage level w.r.t. the LVDT
interlock interface. Interface adapted by EP-DT-DI
Status:
• Overall RPOT movement system commissioned in manual mode after FPGA upgrade
• New recommissioning performed in summer 2020• Calibration campaign performed • EP-DT is ready to test communication CCC/FESA/PXI/TOTEM
E.Bossini 145th LHCC open session 8
Si-Strip status
Last used Si-Strips DPs uninstalled in Feb 2019 All 24 DPs stored in SX5 RP zone Permanently flushed by dry air from CMS line.
8 Si-Strips DPs are needed for installation on vertical RPOTs for Run3:
• In 2020 all 8 DPs passed the visual inspection and tests at IP5
• Few others DPs have been assigned as spares• Preparation of services (power distribution, DCS,
motor control) for the new DPs on schedule
• Migration of control software to CC7(8)/Qt5 completed and validated
Possible slot for reinstallation in the tunnel: week 42
E.Bossini 145th LHCC open session 9
Installation Overview
nT2electronics
Fibers toelectronics
Passive detector in the beam pipe area.
Mockup for mechanical test and installation training
E.Bossini 10
Detection and light transport
145th LHCC open session
Grooved sigma design:
• Green WLS fiber from Kuraray• Mechanical splicing with clear fiber to
reduce light loss from tile to photo-sensor (2m)
• Completed light-tight design for each individual tile
Easy to replace tiles or clear fiber in the mechanical frame
Robust design for tiles and grooved WLS
Production of the nT2 quarters started
E.Bossini 11
Photo sensor
145th LHCC open session
Light detection with Hamamatsu S13361-6050:
• 16 MPPCs in a 4x4 matrix, can readout one nT2 quarter• Each MPPC has area of 6 mm, easy to align with 1 mm fiber.• Detection efficiency @ green ~ 30%
• Bias provided through Hamamatsu C11204-01, remotely controlled and monitored
Fibers
Connection block between board, MPPCs and optical fiber (final design)
Board slot with alignment pin
Test board developed:• 16 amplification channels (20 db). • Mechanics and biasing as in final design
Characterization of MPPC array Test of electro-optical chain
E.Bossini 145th LHCC open session 12
Cosmic ray tests
3 scintillator tiles with final design dimension.
Final design from scintillator to MPPC :
• Scintillator size/mechanical support
• Internal fiber geometry• Fiber splicing/type/length• MPPC mechanical support• MPPC
All sources of light loss are included:
WLS collection, transport, detection.
E.Bossini 145th LHCC open session 13
Cosmic ray tests
Trigger on top scintillator.Bottom scintillator as offline coincidence.
Three different thresholds to check stability of the result
MiddleThr(mV)
Top & Bottom
Triple coincidences
Efficiency
15 16884 16767 0.993
20 16884 16750 0.992
25 16884 16686 0.988
Signal amplitude in central tile
preliminary
Preliminary checks with cosmic rays show an detection efficiency ~99%.
E.Bossini 14
Electronics
145th LHCC open session
MPPC, biasing and signal digitization (NINO chip) located on a mezzanine board mounted on the TOTEM/PPS “Digitizer board”. Firmware (control, readout & trigger) partially derived from the TOTEM timing system.
First complete version ready for hardware test in ~2 months. Control software very compatible with TOTEM/PPS timing detector. Development of DQM and reconstruction software (integrated in CMSSW) ongoing
Existing electronics
New electronics
On schedule to have the detector ready in early 2022
E.Bossini 145th LHCC open session 15
Conclusions
• TOTEM has recently published 2 new papers and 2 more have been submitted to journals. Related talks will be presented during the upcoming LHC Forward Physics meeting (link).
• Preparation for data taking @14TeV is ongoing:
RPOT infrastructure and services on schedule. Si-strip detector ready to be reinstalled.
nT2 is on schedule. Final design of the detector has been approved and production is ongoing. Electronics, firmware and software are well advanced.